Composite Capital Budget 2022/28 & Housing Investment Programme 2022/27 - Monitoring Report No. 1

Perth and Kinross Council · 7 September 2022
Back to Finance and Resources Committee — 7 September 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Some pages contain no extractable text. They may be blank, graphics or scanned pages. OCR has not been applied.

Page 1

PERTH & KINROSS COUNCIL 
Finance & Resources Committee 
7 September 2022 
COMPOSITE CAPITAL BUDGET 2022/28 & HOUSING INVESTMENT
PROGRAMME 2022/27 – MONITORING REPORT No.1 
Report by Head of Finance
(Report 22/209) 
1. PURPOSE 
1.1 This report provides a summary position to date for the 6-year Composite
Capital Budget for 2022/23 to 2027/28 and the 5-year Housing Investment
Programme 2022/23 to 2026/27 and seeks approval for adjustments to the
programmes. 
2. BACKGROUND 
2.1 The Strategic Policy & Resources Committee approved an updated six-year
gross Composite Capital Budget for 2022/23 to 2027/28 totalling
£646,040,000 and a five-year gross Housing Investment Programme for
2022/23 to 2027/28 totalling £83,856,000 at its meeting on 20 April 2022
(report 22/88 refers). 
2.2 This report advises on the impact of the final outturn expenditure in 2021/22
on the programmes; expenditure to 31 July 2022, and the latest estimate of
the projected outturn for each of the years to 2027/28 for the Composite
Programme and to 2026/27 for the Housing Investment Programme. 
3. RECOMMENDATIONS 
3.1 It is recommended that the Committee: 
(i) notes the contents of this report.
(ii) approves the proposed adjustments to the six-year Composite Capital
Budget 2022/23 to 2027/28 set out in Sections 5 and 6 of this report
and summarised in Appendices I and II.
(iii) notes the implications for the Council’s approved Capital funding
strategy as set out in section 5.2.8 and 5.2.9 of the report.
(iv) approves the proposed adjustments to the Housing Investment
Programme Budget 2022/23 to 2026/27 set out in Section 6 of this
report and summarised in Appendix IV. 
4. COMPOSITE CAPITAL PROGRAMME – GROSS CAPITAL RESOURCES 
4.1 The current estimated total gross capital resources (which includes
movements in Capital Receipts, Capital Grants, Contributions and borrowing)
available over the six years 2022/23 to 2027/28 amount to £683,102,000.
Movements from the revised Composite Capital Budget approved on 20 April

Page 2

2022 are summarised in the table below, and the constituent elements for
each year are shown in Appendix I. 
Total Gross Composite Capital Resources 
Approved 
20 April 2022
Current
Estimate
Movement 
£’000 £’000 £’000
2022/23 162,452 176,488 14,036
2023/24 187,177 176,322 (10,855)
2024/25 137,954 148,027 10,073
2025/26 61,769 81,489 19,720
2026/27 52,830 56,639 3,809
2027/28 43,858 44,137 279
Total 646,040 683,102 37,062 
4.2 The report on 20 April 2022 did not include estimates for amounts carried
forward from 2021/22. To determine the carry-forward adjustment required for
each project in 2022/23, the 2021/22 actual position (subject to audit) has
been compared to the projected outturn. These adjustments, are, however,
cost neutral over the 2 financial years as they simply reflect changes in the
timing of expenditure or the application of income. It is, therefore, proposed to
adjust the budget in 2022/23 by the carry forward amounts detailed within
Appendix II. 
4.3 The overall movement in the total Gross Resources for the 6 years 2022/23 to
2027/28 shown at Section 4.1 above can be summarised as follows: 
£’000
Increase in General Fund Property, Commercial Property and
Ring-Fenced Receipts (Section 4.4)
107
Increase in Capital Grants (Section 4.5) 802
Increase in Third Party, Revenue and Developer Contributions
(Section 4.6) 
1,356
Reduction in Receipts c/f to future years (Section 4.4) 213
Increase in new Borrowing Requirement (Section 4.8) 34,584
Increase in Gross Capital Resources (Section 4.1) 37,062 
4.4 Estimated receipts have increased by £107,000, however £103,000 of this
relates to timing differences between 2021/22 and 2022/23, with a £4,000
increase in Ring-Fenced receipts relating to Waste Operations in 2022/23
(Section 5.3.12). Similarly, the reduction in Receipts Carried-Forward to future
years includes a £68,000 adjustment from last year together with £145,000
relating to the proposed increased expenditure on the Commercial Investment
Programme (Section 5.3.11). 
4.5 There is an adjustment of £318,000 in capital grants carried forward from last
year. In addition, the Scottish Government has made additional grant
allocations in 2022/23 for the programmes listed below. These have been
reflected in the proposed expenditure budgets for these programmes, and are
included in Appendix II, as follows: 
• £308,000 additional allocation for Cycling Walking & Safer Streets
• £176,000 Nature Restoration Fund

Page 3

4.6 Third Party Contributions have increased by £1,356,000, of which £221,000
relates to the adjustments to the programme and amounts carried forward
from last year, and £1,135,000 are new Contributions to the programme in
2022/23. These relate to £75,000 from TACTRAN for the Cycling Walking &
Safer Streets programme (Section 5.3.2), £945,000 from the Forestry
Commission for Timber Routes (Section 5.3.4) and £115,000 on the
Commercial Property Investment Programme (Section 5.3.11). All movements
in Developer Contributions and Revenue Contributions relate to carry forward
adjustments between 2021/22 and 2022/23. 
4.7 The projected borrowing requirement in 2022/23, which is effectively the
balancing item for resources, is £136,959,000. This is £11,315,000 higher
than the borrowing requirement approved on 20 April 2022. 
4.8 The total borrowing requirement in the subsequent years 2023/24 to 2027/28
has increased by £23,269,000 to £399,628,000, resulting in an overall
increase of £34,584,000 across the whole 6-year programme. After allowing
for the amount brought forward from 2021/22 of £1,384,000, this leaves an
increase of £33,200,000 relating to new borrowing. The movement in
borrowing is summarised as follows: 
2022/23 2023/24 2024/25 Later
Years
Total 
£’000 £’000 £’000 £’000 £’000
Increased Borrowing Requirement
brought forward from 2021/22
(Appendix II)
1,384 0 0 0 1,384
Increase in Borrowing due to
inflationary pressures (Section 5.1)
16,597 5,045 11,558 0 33,200
Movements arising from re-
phasing of other expenditure and
receipts (Appendix II)
(6,666) (15,657) (1,485) 23,808 0
Increase/(Decrease) in
Borrowing Requirement
11,315 (10,612) 10,073 23,808 34,584 
4.9 The chart below shows the Capital Resources required to fund the 2022/23
Composite Capital Programme following the proposed budget adjustments
detailed in this report. 
78.0%
18.2%
0.9%
1.9%
1.0%
3.8%
Projected Capital Resources 2022/23
(August 2022)
Borrowing (£136.959M)
Grants (£31.995M)
Developer Contributions (£1.549M)
Third Party & Revenue Contributions (£3.345M)
Receipts (£1.827M)
£Million

Page 4

5. COMPOSITE CAPITAL PROGRAMME – EXPENDITURE 
5.1 Total Expenditure and Proposed Budget Adjustments to the Current
Programme 
5.1.1 Total expenditure (net of grants and contributions) to 31 July 2022 on the
Composite Capital Programme amounts to £20,846,000, which is detailed in
Appendix II and summarised as follows: 
Net Expenditure
to 31 July 2022 
£’000
Education & Children’s Services  4,016
Communities 15,047
Health and Social Care    43
Corporate & Democratic Services 1,740
Total 20,846 
5.1.2 A comprehensive monitoring exercise has been carried out, which is detailed
in Appendix II. The most significant features are discussed below under the
respective service headings . 
5.1.3 In setting the 6-year Capital Budget in February 2022 (report 22/36 refers),
the Council approved a Capital funding strategy based upon a £450,000
annual increase in the Council’s debt servicing or “loan charges” budget each
and every year. This funding strategy provided for the estimated cost of
delivering the Capital programme at that time, together with some further
capacity for future investment needs. There were no specific commitments
against this capacity but, as examples, it was recognised that the Council
would likely require future Capital investment to support the delivery of the
Climate Change Strategy and Economic Wellbeing Plan amongst others. 
5.14 Since the Capital Budget was set, the cost uncertainty caused by construction
inflation and supply chain difficulties has been exacerbated by the impact of
the conflict in Ukraine on global energy prices and the consequential impact
on the supply and cost of construction materials. As a consequence project
costs have escalated beyond anything reasonably anticipated back in
February. 
5.2 Communities 
5.2.1 The Executive Director (Communities) has reviewed the programme for their
Service and proposes various budget adjustments, which are described
below. The two most significant are CTLR and Perth City Hall. 
5.2.2 The estimated cost of delivering these has been revised upwards as follows: 
• Cross Tay Link Road (CTLR) - up to £32,500,000 
• Perth City Hall - £700,000 
Both projects are on site with considerable expenditure already incurred in
their delivery to date.

Page 5

5.2.2 With regard to the Cross Tay Link Road (CTLR) project, Appendix III to the
report provides the committee with background to the development of the
project; its role in the delivery of the approved Local Development Plan 2 and
the factors giving rise to a potential increase in forecast cost of up to £32.5
million. 
5.2.3 The contractor has provided a range of forecast cost estimates for the
construction element of the contract. Separately, the Council has engaged
Turner & Townsend to review the adequacy of the contingency provision
through an assessment of potential risks to the project using industry standard
methodology. The table below summarises the main elements of the forecast
increase in cost:   
Approved 
Budget
£ million
Revised
Estimate
£ million
Variance 
£ million
Construction 94.5 108.9 to
111.7
14.4 to 17.2
Risk Assessment
(contingency)
2.4 16.9  14.5
Land and compensation 5.6 5.6 0
Professional Fees 6.8 6.6 (0.2)
Licenses and Public Utilities 3.6 4.0 0.4
Insurance 2.0 2.2 0.2
Consultancy, Surveys &
Investigations
1.9 1.9 0
Engineering Administration 1.2 1.6 0.4    
Total 118 147.7 to
150.5
29.7 to 32.5
Transport Scotland Funding (40) (40) 0    
Revised Net Cost 78 107.7 to
110.5
29.7 to 32.5 
5.2.4 The range of potential cost estimates for the CTLR reflect the scale and
complexity of the project which is the largest civil engineering works ever
undertaken by the Council. The revised forecast for construction costs
includes £5 million of cost mitigation measures achieved though value
engineering in relation to the design. The risk assessment, in particular, has
been revised to reflect the impact of a range of scenarios as outlined in
Appendix III and the estimated costs of contingency works are, by definition,
uncertain. Given the uncertainties and challenges being experienced across a
range of Capital projects, it is , therefore, proposed that the committee make
provision for the current  “worst-case” scenario with the potential that the
eventual cost of the project may not be as high as this forecast. 
5.2.5 There are a number of significant legal, financial and reputational risks in
relation to the CTLR should the Council not progress with the project. These
are detailed in Appendix III and include significant risk around the strategic

Page 6

housing land allocations set out within the Local Development Plan 2 which
cannot be delivered without the CTLR 
5.2.6 In terms of the financial risks, these are significant and are outlined below: 
• The Council has incurred a total of  £23.5 million to 31 July 2022 on the
delivery of the project since its inception, including expenditure in prior
financial years.
• In the current financial year, the Council has spent £6.7 million on the
delivery of the project up to the end of July with a further £3.8m million
forecast to be spent in August, bringing total expenditure in year on the
project to £10.5 million.  Should the project not be progressed, any
expenditure in year would require to be accounted for as Revenue
pressure rather than Capital expenditure as there is no resultant
Capital asset. As this expenditure has not been budgeted for, it would
add to  the  Council’s existing structural deficit.
• The Council would forfeit the £40 million of Transport Scotland funding
for the CTLR and be required to pay back the £5 million received to
date as the conditions of the grant funding will  not have been met.
• In addition, the cost of reinstating the site  would require to be met
together with any resultant costs from the early termination of contracts
or through any successful claims against the Council. 
5.2.7 The Perth City Hall project is on track to open in early 2024 and the majority of
the works are contained within the budget. However, unanticipated additional
works surrounding archaeology and repairs to the building fabric mean that
the contingency provision is now fully committed. It is anticipated that further
expenditure will be required on internal repairs and some aspects of the
exhibition fit-out. It is proposed that a further £700,000 is allocated in 2023/24
to replenish the contingency fund, with Culture Perth and Kinross committing
to fundraise a further £300,000 to support the project’s exhibition and display
requirements. 
5.2.8 In respect of these two key committed  projects, based on the latest
assessment under the approved funding Strategy which was approved in
February 2022, there is approximately £70 million of forecast uncommitted
capacity available to support the delivery of the approved Capital Budget . The
Committee is therefore requested to approve the application of £33,200,000 of
that uncommitted capacity to support the delivery of these projects as
reflected in Appendix II to the report.  
5.2.9 Subject to the approval of these adjustments, the remaining forecast capacity
available to  absorb  the anticipated  construction inflation and increasing
costs in relation to other approved projects and programmes  or indeed, for
any for new investment will be approximately £37 million. 
5.2.10 Given the challenging financial position, officers will continue to monitor and
review the capital programme in line with the Financial Strategy and
Investment Blueprint .

Page 7

In addition; 
5.2.11 Within Traffic & Road Safety, further funding has been allocated to Cycling
Walking and Safer Streets (CWSS) by the Scottish Government and
TACTRAN of £308,000 and £75,000 respectively. Resources have been
prioritised towards these grant funded schemes and this has impacted upon
the staff resources available for other projects within this programme with
proposed adjustments as follows: 
- Road Safety Initiatives – £298,000 from the current year with £237,000
rephased to next year and £61,000 in 2024/25;
- Pedestrian Crossings - £175,000 from the current year to 2025/26; and
-  Schools Road Safety Measures - £106,000 from the current year to
next year. 
5.2.12 Also, within Traffic & Road Safety it is proposed to rephase £177,000 for Car
Parking Investment from the current year to next year due to unexpected
delays surrounding drainage issues and to minimise disruption to parking over
the festive period.  In addition, Car Parking Investment at Pitlochry is currently
being reviewed whilst a suitable site is identified and so it is proposed that the
budget of £150,000 is moved to next year.   
5.2.13 Within Asset Management – Roads & Lighting, it is proposed to increase the
budget for Structural Maintenance by a net £1,358,000. This follows allocation
of third-party funding totalling £945,000, combined with a proposed
acceleration of £433,000 from 2023/24 to the current year. These budget
adjustments in the current year are offset by a proposed transfer of £20,000
from the Welton Road Retaining Wall underspend within Structural
Maintenance to the Bridge Refurbishment Programme.  Also, within Roads &
Lighting, due to staff resources being focused on grant funded projects, it is
proposed that £100,000 for Investment in Local Footpaths is moved to
2024/25 from the current year. 
5.2.14 Within Asset Management – Bridges, works within the Bridge Refurbishment
Programme are currently at the planning stage and as such, anticipated
spend in the current year is less than previously budgeted. It is therefore
proposed that £1,080,000 is rephased with £125,000 next year and £955,000
in 2024/25. In addition, there is expected to be an £80,000 underspend on
Glendevon Bridge and it is proposed that this is combined with the
underspend of £20,000 from section 5.3.4 above, and that the £100,000 total
is allocated to the Bridge Refurbishment Programme in 2026/27.  Due to
current engineering staff resource constraints, reduced works on Perth
Queens Bridge and Culteuchar Culvert are expected to take place in the
current year and therefore it is proposed that their budgets of £70,000 and
£278,000 respectively, be moved from the current year to next year. 
5.2.15 Within the Perth & Kinross Place-making programme it is proposed that the
budgets for Perth City Centre Golden Route, Green Network Routes, Tay
Street, Mill Street and South Street be consolidated into one budget heading
for Perth, Place, People where funding can be drawn down towards various
projects as they commence.

Page 8

5.2.16 Within Other Planning Projects, following a reduction of £120,000 funding
from the Department of Digital, Culture, Media & Sport, the budget for Local
Full Fibre Network has been adjusted accordingly. The Council has been
allocated £176,000 in 2022/23 from the Nature Restoration Fund by the
Scottish Government, and this has been included in the budget. 
5.2.17 The community in Auchterarder have raised £140,000 towards Auchterarder
Public Park, and the budget for the works has been increased to reflect the
additional funding towards this project.Within the Commercial Property
Investment Programme, it is proposed that the budget of £1,398,000 for the
Eco-Hub Manufacturing Facility is removed from the current programme of
works, and that industrial units be created with a budget of £1,655,000 over
this year and next year. These units are part funded by a £115,000 third party
contribution. These proposed adjustments, together with a £3,000 adjustment
carried forward from last year, result in a net increase in expenditure of
£145,000. 
5.2.18 Within the Prudential Borrowing programme the Street Lighting Renewal for
the current year has been reviewed. As a result of additional works completed
last year it is proposed that the budget for the programme in relation to
column replacements is rephased over the remaining years of the project. In
addition, following the disposal of skips and containers as part of the
replacement programme, it is proposed to increase the budget for new skips
by the £4,000 net proceeds received to date. 
5.2.19 All the above proposed adjustments have been reflected in Appendices I & II. 
5.3 Education and Children’s Services 
5.3.1 The Executive Director (Education & Children’s Services) has reviewed the
programme for their Service and proposes the following budget adjustments. 
5.3.2 Works on the new Riverside Primary School are progressing well and it is
proposed to accelerate £3,008,000 from next year into the current year to
reflect the level of work due for completion this year. 
5.3.3 The following adjustments reflect the movement in the overall programme
following the effects of Covid-19 on the timescales across the projects. 
5.3.4 There have been several small adjustments to various Education & Children’s
Services projects relating to amounts carried forward from 2021/22 which are
included in Appendix II. These mostly relate to projects that have been
completed. 
5.3.5 Within the Investment in the Learning Estate, it is proposed to move
£2,000,000 from the current year, and £5,000,000 from next year, with
£4,000,000 being allocated to 2024/25 and £1,000,000 into each of the
subsequent three years of the programme.  Further details for the use of this
funding will be provided following a review of the programme. 
5.3.6 In line with a proposed opening date of August 2026, the budget for a new
primary school at Bertha Park requires rephasing. It is proposed to transfer

Page 9

£7,500,000 from both 2023/24 and 2024/25 into 2025/26; and to reduce the
current year by £400,000 with a corresponding increase in 2026/27. 
5.3.7 Within the budget for Technology Upgrades, planned works indicate that
£400,000 of the budget will not be utilised in the current year and it is
proposed that this budget be moved to 2023/24. 
5.3.8 The expected payment profile for the extension of Harris Academy has also
been updated, and it is proposed that £1,100,000 of the budget is moved from
2022/23 to 2023/24. In addition, works are continuing on-site upgrading
facilities at Perth Grammar and Perth Academy. Following an update to the
actual value of the current phases, it is proposed that both budgets be
rephased as follows: 
- A reduction at Perth Academy of £1,300,000 in the current year and
£3,000,000 next year with a budget of £2,150,000 being allocated to
both 2025/26 and 2026/27;  
- A reduction at Perth Grammar of £2,000,000 in the current year and
£815,000 next year, with £811,000 allocated to 2024/25, £1,500,000 to
2025/26 and the remainder of £504,000 to 2026/27. 
5.3.9 All of the above proposed adjustments have been reflected in Appendices I &
II.
5.4 Corporate & Democratic Services 
5.4.1 The Chief Operating Officer has reviewed the programme for their Service
and proposes the budget adjustments described below. 
Property Services 
5.4.2 Within Capital Improvement Projects it is proposed that £600,000 is
accelerated from 2027/28 to the current year to fund energy efficiency
measures. 
Information Systems & Technology 
5.4.3 The works within Data & Analytics for the year have been assessed and it is
proposed to rephase £135,000 from the current year to next year in line with
planned activity. 
5.4.4 Within Information Systems and Technology there are separate budgets for
Supporting Digital, Online/Mobile Working and Customer Service Blueprint. As
there are strong links and crossovers between these areas of IT work it is
proposed that the budgets for these areas are consolidated into one budget
under the overarching Supporting Digital programme. This will enable a
streamlined approach to prioritising works and for testing and deploying digital
improvements.  In addition, it is proposed that within the Supporting Digital
programme £477,000 is moved from the current year to next year to reflect
the level of anticipated spend.

Page 10

5.4.5 The roll out of School Audio Visual Equipment Replacement is progressing
well and it is proposed that the budget is accelerated in the current year with
an increase of £848,000 to be funded from future year budgets within the
programme. 
5.4.6 Following the appointment of the preferred supplier for the Swift Social Work
System Replacement last year, it is proposed to adjust the budget in line with
the terms of the agreed contract. In particular, the licence costs are due in
2023/24 when the system goes lives, with only staff costs for the ongoing
development and implementation being incurred in the current year. It is also
proposed to move the unallocated budget of £292,000 to 2024/25 to allow for
further development works to be undertaken post-implementation. The
proposed budget adjustments have been included in Appendix II. 
5.4.7 All the above proposed adjustments, together with other small movements,
have been reflected in Appendix II. 
5.5 Health & Social Care 
5.5.1 The Developing Supported Tenancies project is a contribution towards works
within the Housing Revenue Account. It has been confirmed that the budget of
£229,000 will not be drawn down in the current year and it is proposed that
the budget is moved to next year will options continue to be evaluated. 
5.5.2 The above proposed adjustment has been reflected in Appendix II. 
6. HOUSING INVESTMENT PROGRAMME 
Final Outturn 2021-22 
6.1 The final position for 2021/22 on the Housing Investment Programme (subject
to audit) was as follows: 
2021/22
Budget 
Actual to 31
March 2022
Variance to
Budget 
£’000 £’000 £000
Total Net Expenditure 12,018 11,856 (162)
Total Receipts & CFCR (2,259) (2,328) (69)
Borrowing Requirement 9,759 9,528 (231) 
6.2 In order to determine the carry-forward adjustments required for each project
in 2022/23, the 2021/22 actual outturns have been compared to the previous
projections. The difference between the actuals and previous projections are
then adjusted against the 2022/23 budgets, which are shown in Appendix IV.
These adjustments are neutral over the 2 years and has resulted in a
movement of £231,000 of borrowing from 2021/22 to 2022/23.   
Current Programme: 2022/23 to 2026/27 
6.3 The current estimated expenditure, net of contributions, for the Housing
Investment Programme over the 5 years 2022/23 to 2026/27 amounts to

Page 11

£84,018,000. Movements from the previous estimates approved by the
Strategic Policy & Resources Committee on 20 April 2022 are summarised in
the table below and detailed in Appendix IV. The overall increase of £162,000
represents the amount of expenditure carried forward from last year. 
Approved 
20 April 2021
Current
Estimate
Movement 
£’000 £’000 £’000
2022/23 17,963 18,131 168
2023/24 15,983          17,022 1,039
2024/25 13,871 13,867 (4)
2025/26 19,995 18,954 (1,041)
2026/27 16,044 16,044  0
Total 83,856 84,018 162 
6.4 Total Expenditure to 31 July 2022 (Housing Investment Programme) 
Net expenditure for 2022/23 to 31 July 2022 amounts to £3,186,000 and
receipts amount to £4,000. This therefore means that the borrowing
requirement for the year to date is £3,182,000. 
6.5 After making adjustments relating to small carry-forward amounts from last
year, the Executive Director (Communities) has reviewed the Housing
Investment Programme and proposes the budget adjustments outlined below
and which are included in Appendix IV. 
6.6 It is proposed to transfer a net total of £1,746,000 from the New Build Future
Development budget in 2022/23 for the scheme at Lynedoch Road, Methven
in 2022/23 (£707,000) and 2023/24 (£1,039,000). These amounts are after
applying £480,000 from the Council Tax Reserve and £1,643,000 of Scottish
Government Grant. It is also proposed to transfer a further £90,000 from the
Glebe, Scone budget which is now effectively completed. 
6.7 The New Build scheme at Newburgh Road, Abernethy is also nearing
completion. It is proposed to adjust the expenditure budget by £1,200,000 in
2022/23 in relation to the share equity properties, of which £492,000 is being
funded from Scottish Government grant and £708,000 from sales to the
shared equity owners. 
6.8 In order to support the Council House Buy-Back programme, Scottish
Government Grant of £1,050,000 has been sought in 2022/23, based on
£35,000 per property (30 properties). It is, therefore, proposed to increase the
expenditure budget in 2022/23 by this amount. 
6.9 With various work programmes ongoing, it is also proposed to allocate funding
from the Scottish Housing Quality Standard Future Developments budget in
2025/26 to various schemes in the current year, and these are summarised as
follows:- 
• Central Heating & Rewiring - £938,000, with a reduction of £98,000 in
Third party Contributions from last year.
• Triple Glazing - £60,000.

Page 12

• Fire Precaution Measures - £250,000.
• 111 Rannoch Road, Perth (Conversion) - £211,000. 
6.10 With no works currently planned within the Structural Programme, it is
proposed to move £418,000 from 2022/23 to 2025/26, in order to maintain a
rolling programme of works in future years. 
6.11 The estimate for Capital Financed by Current Revenue (CFCR) in 2022/23
has reduced by £156,000 to £2,458,000, which is offset by an adjustment of
£73,000 relating to Receipts. These result in an overall increase in borrowing
of £83,000 in the current year. After including the reduction in borrowing
brought forward from last year of £231,000, the overall increase in the
Borrowing Requirement for the current 5 years to 2026/27 is £320,000. 
7. BUDGET OVERVIEW 
7.1 The projected net expenditure outturn in 2022/23 for the Composite Capital
Budget is £150,335,000 and represents 109% of the 2022/23 budget as
approved on 20 April 2022 (£138,276,000). The revised budget is based on
the latest projection of expenditure and all budget adjustments outlined within
this report. 
7.2 Net expenditure to 31 July 2022 on the Composite Capital Budget is
£20,846,000 and represents 14% of the proposed revised budget for 2022/23
of £150,335,000. 
7.3 The projected net expenditure outturn in 2022/23 for the Housing Investment
Programme is £18,131,000 and represents 101% of the 2022/23 budget
approved on 20 April 2022 (£17,963,000). 
7.4 Net expenditure to 31 July 2021 on the Housing Investment Programme is
£3,186,000 which represents 18% of the proposed revised budget for 2022/23
of £18,131,000. 
7.5 While the projections have been based on a comprehensive monitoring
exercise, they continue to remain subject to uncertainty as a result of ongoing
inflationary pressures, particularly in the construction industry, in the current
economic environment. 
Author(s)
Name  Designation Contact Details
John Jennings Senior Accountant CHXFinance@pkc.gov.uk 
Approved 
Name Designation Date
Karen Donaldson 
Stewart MacKenzie
Chief Operating Officer 
Head of Finance
24 August 2022 
24 August 2022

Page 13

No embedded text on this page.

Page 14

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications 
Corporate Plan 
1.1 The Council’s Corporate Plan 2018 – 2023 lays out five outcome focussed
strategic objectives which provide clear strategic direction, inform decisions at
a corporate and service level and shape resources allocation.  They are as
follows: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
1.2 This report relates to all of these objectives. 
2. Resource Implications 
Financial 
2.1 There are no direct financial implications arising from this report other than
those reported within the body of the main report. 
Workforce 
2.2 There are no direct workforce implications arising from this report other than
those reported within the body of the main report.

Page 15

Asset Management (land, property, IT)   
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the
Corporate Equalities Impact Assessment process (EqIA) and has been
assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. In terms of the Climate Change Act,
the Council has a general duty to demonstrate its commitment to sustainability
and the community, environmental and economic impacts of its actions.   
3.6 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
4. Consultation 
Internal 
4.1 The Chief Executive and the Executive Directors have been consulted in the
preparation of this report.   
2. BACKGROUND PAPERS 
No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (other than any containing confidential or exempt

Page 16

information) were relied on to any material extent in preparing the above
report. 
3. APPENDICES 
• Appendix I – Composite Capital Programme - Estimated Capital
Resources 2022/23 to 2027/28
• Appendix II – Composite Capital Programme - Summary of Capital
Resources and Expenditure 2022/23 to 2027/28 
• Appendix III – Cross Tay Link Road – Revised Cost Analysis Report
July 2022       
• Appendix IV – HRA Capital Investment Programme – Summary of
Capital Resources and Expenditure 2022/23 to 2026/27