APPENDIX 2
PERTH & KINROSS COUNCIL - GENERAL FUND 2022/23 PROJECTED OUTTURN  - SERVICE ANALYSIS
(Based on Expenditure to 30 June 2022)
Variance Variance
£'000 £'000
Education & Children's Services
Total 0
DEVOLVED SCHOOL MANAGEMENT SCHEME (DSM)
There are 66 primary schools, 7 secondary schools, 4 all through schools, 46 nurseries and early learning
centres and 1 special school within the Council's DSM scheme.  Each school has an individual budget,
primarily based on pupil numbers.  Headteachers are responsible for the annual budgets devolved to them in
April each year. The total DSM budget for 2022/23 is £113.876 million including carry forwards. 
Within the scheme there is a facility allowing for DSM balances, whether surplus or deficit, to be brought
forward from the previous financial year. In addition to the resources devolved, balances may also be available
to headteachers of schools that have a carry forward. In 2021/22, £1.191 million of DSM balances were
brought forward.
(449) Staff Costs
Additional slippage due to staff turnover
449 There is currently a projected net under spend of £449,000 based on current spending plans from schools for
the current academic year that runs to June 2023.  The maximum carry forward under the DSM scheme is
2.5%,  the current projection is 0.4%.
Pupil Equity Fund
(300) The majority of schools within Perth & Kinross Council have been allocated a share of £1.874 million of Pupil
Equity Funding from the Scottish Government as a ring fenced grant.  Schools are being instructed to use this
year’s PEF Grant by 31 March 2023 as per the revised Scottish Government guidance. At this time £300,000
is projected to be carried forward into 2023/24 for teacher and support staff costs to the end of the current
academic year.
300 Projected carry forward of Pupil Equity Funding.
NON DEVOLVED
Education Services
Nursery Sector
(184) Additional slippage due to turnover of staff.
(31) Savings from non-domestic rates as early learning centres are exempt from the charge.
Secondary Sector
(181) Projected under spend on investment in learning unitary charge due to  an insurance rebate.
Special Sector
(130) Projected under spend on home to school transport after allowing for non-recurring increase of £250,000.
(211) There is a projected under spend on the  budget for young people with additional support needs (ASN) who
are educated out with the Council's mainstream school provision.
Services for Children, Young People & Families
188 Projected costs of additional social work capacity to meet increasing need.
(188) Contribution from Covid-19 earmarked Reserve
86 Projected over spend on legal fees and translation / interpreter services
734 The budget for young people with complex behavioural issues, which includes a number of pupils placed
within residential schools, is projected to overspend due to additional demand.
286 A projected over spend on Kinship Care (£555,000) due to demand partially offset by a projected under spend
in Foster Care (£229,000).
309 There is a projected over spend in relation to supporting care experienced young people (continuing care,
supported accommodation,) due to increasing demand.
85 There is a projected over spend on self directed support (children & disability team - respite provision) due to
the level of demand and an increase to the hourly rate paid to clients.
(124) Additional grant funding for Unaccompanied Asylum Seeking Children (£86,000); Wellbank Rental Income
(£23,000) and Alcohol & Drug Partnership (£15,000)
Business and Resources Services
(44) Additional slippage due to turnover of staff.
(27) Projected underspend due to Area Office recharge no longer required.
SERVICE Summary of Service Variances

Page 2

APPENDIX 2
PERTH & KINROSS COUNCIL - GENERAL FUND 2022/23 PROJECTED OUTTURN  - SERVICE ANALYSIS
(Based on Expenditure to 30 June 2022)
Variance Variance
£'000 £'000SERVICE Summary of Service Variances
Catering Services
(76) Additional staff slippage.
(600) Projected under spend (£600,000) within the Early Learning & Childcare 1140 grant, for nursery meals.
(255) Projected under spend of school meals due to uptake (£255,000) partially offset below by reduced income.
363 Projected shortfall in income from breakfast clubs (£120,000) and school meals (£243,000).
Communities
Total 248
BUSINESS AND RESOURCES
Public Transport Unit / Corporate Property Asset Management
40 Perth Bus Station - increased costs
(80) Corporate Asset Management - accelerated savings
355 Car Park Trading Account - projected reduction in income and increased provision for bad debts
(355) Drawdown from Car Park Trading Account earmarked Reserve
ENVIRONMENTAL AND CONSUMER SERVICES
Roads
(150) Projected additional income from statutory road network works
Regulation
25 Projected shortfall in Corporate Health and Safety income
Operations
270 Projected shortfall in commercial waste income
(150) Projected additional income from sale of recyclates due to favourable market prices
400 Projected additional cost of fuel across Operations due to increase in price
Fleet Management
(280) Saving on loan charges due to slippage on planned vehicle replacement programme
PLANNING AND DEVELOPMENT
98 Perth Harbour - projected increase in operating costs /shortfall in income
HOUSING
35 Greyfriars - projected increased in void rent loss and provision for bad debts
10 Greyfriars - projected increase in energy costs
30 Cost of Local House Condition Survey to inform the Local Housing Strategy

Page 3

APPENDIX 2
PERTH & KINROSS COUNCIL - GENERAL FUND 2022/23 PROJECTED OUTTURN  - SERVICE ANALYSIS
(Based on Expenditure to 30 June 2022)
Variance Variance
£'000 £'000SERVICE Summary of Service Variances
Corporate & Democratic Services
Total 1,340
Legal & Governance Services
(130) Projected additional income from licensing and recharges
(94) Rephasing of expenditure relating to Council approved projects (Kinross Area Committee & Events Support)
36 Projected over spend in relation to elected members
38 Net projected overspend across function (including non-achievement of slippage target)
Human Resources
(113) Additional projected income from salary sacrifice scheme and other recharges
(26) Additional staff slippage
(9) Net projected under spend on other budgets
Information Technology and Revenues & Benefits
(20) Miscellaneous other projected net under spends.
Property
959 Projected over spend on energy costs due to inflationary pressures.
740 Projected over spend on maintenance relating to compliance remedial works.
(41) Miscellaneous other projected net under spends.
Chief Executive's Service
Total (20) Core Costs
(20) Staff slippage
TOTAL 1,568