Democracy Spraffa

Agenda Document Pack - Finance and Resources Committee - 04/02/2026

Perth and Kinross Council · 4 February 2026
Back to Finance and Resources Committee — 4 February 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Ambition | Compassion | Integrity
Our vision is for
a Perth and Kinross where everyone can live life
well, free from poverty and inequality
Council Building
2 High Street
Perth
PH1 5PH
29/01/2026
A hybrid meeting of the Finance and Resources Committee will be held in the
Council Chamber on Wednesday, 04 February 2026 at 13:00.
If you have any queries please contact Democratic Services on (01738) 475000 or
email Committee@pkc.gov.uk.
THOMAS GLEN
Chief Executive
Those attending the meeting are requested to ensure that all notifications are silent
on their device and other devices are in silent mode.
Please note that the meeting will be broadcast online and recorded.  The recording
will be publicly available on the Council’s website following the meeting.
Members:
Councillor Stewart Donaldson  (Convener)
Councillor Eric Drysdale  (Vice-Convener)
Bailie Chris Ahern
Councillor Keith Allan
Councillor Dave Cuthbert
Councillor John Duff
Councillor David Illingworth
Councillor Ian Massie
Provost Xander McDade
Councillor Tom McEwan
Bailie Claire McLaren
Depute Provost Andrew Parrott
Councillor John Rebbeck
Councillor Caroline Shiers
Councillor Colin Stewart
Councillor Alan Watt
Page 1 of 86

Page 2

Page 2 of 86

Page 3

Finance and Resources Committee
Wednesday, 04 February 2026
Agenda
Members are reminded of their obligation to declare any financial or non-
financial interest which they may have in any item on this agenda in
accordance with the councillors’ code of conduct.
1 WELCOME AND APOLOGIES/SUBSTITUTES
2 DECLARATIONS OF INTEREST
3 MINUTES
3(i) MINUTE OF MEETING OF THE FINANCE AND RESOURCES
COMMITTEE OF 26 NOVEMBER 2025 FOR APPROVAL
(copy herewith)
5 - 8
3(ii) MINUTE OF MEETING OF THE EXECUTIVE SUB-COMMITTEE
OF THE FINANCE AND RESOURCES COMMITTEE OF 16
DECEMBER 2025 FOR APPROVAL
(copy herewith)
9 - 10
3(iii) MINUTE OF MEETING OF THE EMPLOYEES JOINT
CONSULTATIVE COMMITTEE OF 17 SEPTEMBER 2025 FOR
NOTING
(copy herewith)
11 - 16
4 OUTSTANDING BUSINESS STATEMENT
(copy herewith 26/35)
17 - 18
5 2025/26 REVENUE BUDGET - UPDATE NO. 3
Report by Chief Finance Officer (copy herewith 26/36)
19 - 52
6 COMPOSITE CAPITAL BUDGET 2025/31 AND HOUSING
INVESTMENT PROGRAMME 2025/30 - MONITORING REPORT
NO. 3
Report by Chief Finance Officer (copy herewith 26/37)
53 - 86
Page 3 of 86

Page 4

Page 4 of 86

Page 5

DRAFT
Finance and Resources Committee
Minute of hybrid meeting of the Finance and Resources Committee held in the
Council Chamber, 2 Hight Street, Perth on Wednesday 26 November 2025 at
1.30pm.
Present: Councillors S Donaldson and E Drysdale, Provost X McDade, Bailie
C McLaren, Councillors K Allan, P Barrett, D Cuthbert, E Drysdale, J Duff, A Forbes
(substituting for Bailie C Ahern), D Illingworth, I Massie, T McEwan, J Rebbeck,
C Shiers, C Stewart and R Watters (substituting for Depute Provost A Parrott).
In Attendance: T Glen, Chief Executive; C Mailer, Dute Chief Executive; S Walker,
Strategic Lead - Finance and Business Support; A O’Brien, S Coyle, C France,
J Jennings and C Robertson (Finance and Business Support), J Beveridge, Strategic
Lead – Property Services; N Lennon (Property Services); S Merone, Strategic Lead
– Economy, Development and Planning  D Macluskey, Strategic Lead – Education
and Learning; E Ritchie, Strategic Lead - Housing and Communities; K Campbell, 
A Clegg, D Stokoe, H Hope, J McColl and K Steven (Housing and Communities)
D Davidson and P Leonard (Environment and Infrastructure), L Brady, K Fraser,
N Sutherland and P Taylor (Customer and Digital Services); C Guild, Strategic Lead
– Projects and Programmes; S Hendry, K Molley, A Brown and M Pasternak (all
Legal and Governance).
Apologies: Bailie C Ahern and Depute Provost A Parrott
Councillor S Donaldson, Convener, Presiding.
The Convener Led on items 1-5 and 7-9. The Vice-Convener led on item 6.
1. Welcome and Apologies
The Convener welcomed all those present to the meeting and apologies were
noted as above.
2. Declarations of Interest
There were no declarations made in terms of the Councillors’ Code of
Conduct.
3. Minute of Meeting of the Finance and Resources Committee of 1 October
2025
The minute of meeting of the Finance and Resources Committee of 1 October
2025 was submitted and approved as a correct record.
4. Outstanding Business Statement
Resolved:
The status of action in the Outstanding Business Statement (25/325) be noted
and completed actions removed accordingly.
3(i)
Page 5 of 86

Page 6

DRAFT
5. Appointments to Committee
Resolved:
The Committee agreed to appoint Councillor Ian Massie to the vacant position
on the Executive Sub-Committee of the Finance and Resources Committee.
6. 2025/26 Revenue Budget - Update No. 2
There was submitted a report by the Chief Finance Officer (25/326) providing
an update on progress with the 2025/26 General Fund Revenue Budget based upon
the August 2025 ledger, updated for any subsequent known material movements,
and the projected financial position of the Housing Revenue Account.
Resolved:
(i) The contents of Report 25/326, be noted.
(ii) The projected outturn for the General Fund, as set out in Section 4 of Report
25/326 and Appendices 1 and 2, be noted.
(iii) The adjustments to the 2025/26 General Fund budgets, as detailed in Section
5 of Report 25/326 and Appendices 1, 2, 4, 5, 6 and 7, be approved.
(iv) The financial risks, as set out in Section 6 of Report 25/326 and Appendix 8,
be noted.
7. Composite Capital Budget 2025/31 and Housing Investment Programme
2025/30 – Monitoring Report No.2
There was submitted a report by the Chief Finance Officer (25/327) (1)
providing a summary position to date for the 6-year Composite Capital Budget for
2025/26 to 2030/31 and the 5-year Housing Investment Programme for 2025/26 to
2029/30; and (2) seeking approval for adjustments to the programmes.
Resolved:
(i) The contents of Report 25/327, be noted.
(ii) The proposed adjustments to the six-year Composite Capital Budget 2025/26
to 2030/31, as set out in Sections 4 and 5 of Report 25/327 and summarised
in Appendices I and II, be approved.
(iii) The proposed adjustments to the Housing Investment Programme Budget
2025/26 to 2029/30, as set out in Section 6 of Report 25/327 and summarised
in Appendix III, be approved.
(iv) Progress with the delivery of major Capital projects, as summarised in
Appendix IV to Report 25/327, be noted.
(There followed a 10-minute recess and the Committee reconvened at 3.15pm)
(The Committee agreed to vary the order of business)
8. Missing Shares Service – Update on Progress and Next Steps
There was submitted a report by the Principal Officer – Environmental Health
(25/323) (1) providing an update on the progress made through the Missing Shares
Service; and (2) seeking support to continue using the second homes budget to
underwrite the value of predicted missing shares.
Page 6 of 86

Page 7

DRAFT
Resolved:
(i) The ongoing use of the second homes budget to underwrite the expected
future Missing Shares until the applications approved within the pilot period
are concluded, be approved.
(ii) An increase to the current maximum per share from £10,000 to £30,000, with
Strategic Lead approval beyond this amount, be approved.
(iii) The proposal to make the Missing Shares officer post permanent, be
approved.
(vi) The continued success of the pilot, and the increasing service demand, be
acknowledged.
(v) The existing, effective financial mechanisms in place to secure missing share
recovery, be recognised.
9. Treasury Activity and Compliance Report 2025/26 – 6 months to
30 September 2025
There was submitted a report by the Chief Finance Officer (25/328) (1)
updating on Treasury Activity for the period 1 April to 30 September 2025; and (2)
reporting on compliance with the Council’s Treasury Management Policy Statement
(TMPs), Investment Strategy and Prudential Indicators.
Resolved:
The contents of Report 25/326, be noted.
Page 7 of 86

Page 8

Page 8 of 86

Page 9

DRAFT
Executive Sub-Committee of Finance and Resources
Committee
Minute of hybrid meeting of the Executive Sub-Committee of the Finance and
Resources Committee held in MR410, 2 Hight Street, Perth on Tuesday
16 December at 3.00pm.
Present: Councillors S Donaldson, E Drysdale, P Barrett, D Cuthbert, J Duff,
I Massie and C Shiers.
In Attendance: T Glen, Chief Executive; S Walker, Chief Finance Officer; F Crofts,
Strategic Lead – Environment and Infrastructure; P Leonard (Environment and
Infrastructure); L Simpson, Strategic Lead – Legal and Governance; K Molley (Legal
and Governance); and L Potter (Strategic Planning, People and Performance).
Councillor S Donaldson, Convener, Presiding.
1. Welcome and Apologies
The Convener welcomed all those present to the meeting.
2. Declarations of Interest
There were no declarations made in terms of the Councillors’ Code of
Conduct.
(It is recommended that the public and press should be excluded during
consideration of the following item(s) in order to avoid the disclosure of information
which is exempt in terms of Schedule 7A to the Local Government (Scotland) Act
1973)
P1. Residual Waste Contract 
There was submitted a report by Strategic Lead – Environment and
Infrastructure (25/358) advising Members of significant risks that have arisen with
regard to the Council’s residual waste contract and to set out recommended actions
required to mitigate these risks insofar as is possible. 
Resolved:
(i) A mutual termination of the current contract, with effect from 1 February 2026,
subject to a compensation payment to the Council as outlined in Report
25/358, be agreed. 
(ii) As an interim measure, a direct award for residual waste disposal services is
made to an alternative provider on an emergency basis, for a period of 18
months, with an option to extend by a further year if required, be approved.
(iii) It be noted that the additional costs for the 18-month period would be covered
by a compensation payment and that should a further 12 months’ extension
be required, additional costs outlined in Report 25/358 would be incurred. This
will be reflected in forthcoming budget process.
3(ii)
Page 9 of 86

Page 10

DRAFT
(iv) It be noted that the options for the provision of longer-term waste disposal
arrangements will be explored and will be the subject of a further paper to
Members in 6 months’ time. 
Page 10 of 86

Page 11

Perth and Kinross Council
Finance and Resources Committee
Employees Joint Consultative Committee
Minute of hybrid meeting of the Employees Joint Consultative Committee held
Meeting Room 410, 2 High Street, Perth on Wednesday 17 September 2025 at
1.30pm.
Present: Representing Perth and Kinross Council:
Councillors K Allan, S McCole and J Rebbeck.
Present: Representing Trade Unions:
S Topen-Cooper (NASUWT)
C Weston (EIS)
S Hope (UNISON)
M Mackie (SSTA)
In Attendance: L Hamilton, P Johnstone, E Bayne, L McGeorge, F MacKay,
D Black, S Stephen, A McConnachie.
Apologies: D MacLuskey and N Ferry.
S Hope in the Chair.
1. Welcome and Apologies
S Hope welcomed all present to the meeting and apologies were noted as
above.
2. Declarations of Interest
There were no declarations of interest made in terms of the Councillors’ Code
of Conduct.
3. Minute of Meeting of Employees Joint Consultative Committee of
16 June 2025
The minute of meeting of the Employees Joint Consultative Committee of
16 June 2025 was submitted and approved as a correct record.
4. Matters Arising
(i) End Violence at Work Charter
P Johnstone advised information on this has been provided to Unison.
3(iii)
Page 11 of 86

Page 12

5. Health and Safety Performance Report Quarter 1 2025/26 – April – June
2025
There was a report submitted by the Health and Safety Team Leader
(G/25/127) informing and assisting the Employees Joint Consultative
Committee in monitoring health and safety compliance and performance
across Perth and Kinross Council and providing an overview of health and
safety activities undertaken.
In response to a question from Councillor McCole regarding medication
errors, L Hamilton advised prevention actions with managers in the relevant
teams and discussions have taken place with the Health and Safety Team to
look at ways to reduce the number of incidents. L Hamilton agreed to bring an
update to the next meeting of the Committee.  Councillor McCole added she
will also raise with the Health and Social Care Partnership.
In response to a question from S Topen-Cooper regarding differing fire
regulations and doors in schools, L Hamilton advised that differences may not
be a fire safety issue but contractual and the most appropriate adjustment will
depend on individual circumstances.
Resolved:
(i) L Hamilton to speak to colleagues in the Health and Social Care
Partnership about Medication Errors and report update at the next
meeting of the Committee.
(ii) The contents of Report G/25/127, be noted.
6. Fire Safety Performance Report – Quarter 1 2025/26 – April – June 2025
There was a report submitted by the Health and Safety Team Leader
(G/25/128) informing and assisting the Employees Joint Consultative
Committee in monitoring fire safety performance across Perth and Kinross
Council and providing an overview of fire safety activities undertaken.
In response to a request from Councillor McCole regarding updates on
outstanding items, L McGeorge advised projects are ongoing and agreed to
bring an update to the next meeting.  L Hamilton added that managers have
been reminded of reporting requirements.
In response to a question from Councillor McCole regarding fire service
attendance, L McGeorge advised attendance is only when a fire is confirmed,
with exceptions for linked systems in Council sleeping accommodation.
Resolved:
(i) L McGeorge to provide update on outstanding fire safety actions at
next meeting.
(ii) The contents of Report G/25/128, be noted.
Page 12 of 86

Page 13

7. Health and Wellbeing Update
There was a report submitted by the People and Culture Manager (G/25/129)
providing an update on current Health and Wellbeing data and current Health
and Wellbeing activities.
E Bayne highlighted the downturn in staff absences and added while not
mentioned in the report details of the flu vaccine program that will be
published shortly.
In response to a question from Councillor McCole regarding the possibility of
“drop-ins” for staff for Winter vaccines in Pullar House, E Bayne advised the
Health and Social Care Partnership have their own arrangements around
vaccines and did not think there was any scope for this.
In response to a question from Councillor McCole regarding the recent
procurement of the Occupational Health service and whether the unions were
involved, P Johnstone advised the unions were involved in the previous
tender process and the same terms were used for this tender. However, the
most recent procurement had been undertaken nationally, and it is not known
if unions were engaged. Locally, we still have to negotiate with the agreed
provider, People Asset Management about our local service requirements.
Councillor McCole encouraged engagement on local service requirements
with the unions and S Hope said he would want to input.
In response to a question from M Mackie about the effect of staff absences on
staff ratios to pupils with ASN and class size maximums, F MacKay advised
staffing standards are part of the DSM policy which sets out agreed staffing
ratios. It is an area that is regularly reviewed to ensure ratios remain
appropriate.
In response to a question from Councillor McCole about how an aging
workforce might cope with physically demanding work, P Johnstone advised
as part of future workforce planning the Council are looking at what services
they will be expected to deliver in the future along with the workforce needed
to deliver the Council’s priorities.
S Topen-Cooper asked if the difference between short- and long-term
absences could be separated in the next report and E Bayne said he will
speak to systems colleagues.
In response to a question from S Hope about who decides when something is
classed as an industrial injury and what benefits arise from the absence being
classed as an industrial injury, L Hamilton advised that there is a section on
the fitness for work note that asks if the absence is “work-related.” This would
be considered, along with whether an incident has been reported as a work-
related injury and E Bayne advised that depending how an absence is
recorded could affect staff’s entitlement to sickness allowance.
Page 13 of 86

Page 14

S Hope did not think this approach to recording absences as industrial injuries
is being applied council wide. E Bayne and P Johnstone said they would
review guidance and share with unions.
Resolved:
The contents of Report G/25/129, be noted.
8. Staff Reporting: Incidents of Violence/Aggression and incidents of
Distressed/Challenging Behaviour in Education Settings – Term 4
2024/25
There was a report submitted by the Quality Improvement Manager, Inclusion
and Additional Support, and Inclusion Quality Improvement Officer (G/25/130)
on Education and Learning’s performance in managing and reducing staff
reports of incidents of distressed, challenging, violent, or aggressive
behaviour that have impacted staff in the workplace.
It also provides a summary of the information gathered in Term 4 of academic
year 2024/25 in relation to staff reports of incidents in schools and other
educational settings and information on the activity of an established
Reducing Challenging Behaviour Working Group to prevent and reduce the
number of incidents.
In response to C Weston, S Hope and S Topen-Cooper feeling the decrease
in the number of reported incidents was not reflective of what is happening but
is instead apathy from school staff when it comes to filling in the form as they
feel nothing changes following a report, F MacKay advised that it is
recognised that it can be challenging working in schools and that staff are
encouraged to report incidents. This was reinforced in a recent
communications bulletin that went out to headteachers in all schools.
In response to discussion about consequences for pupils involved in incidents
with staff with views shared by S Hope, Councillor Allan, S Topen-Cooper and
C Weston; F MacKay advised there is ongoing work on behaviour and that the
primary focus is to reduce dysregulation or distress that can lead to an
incident. At times situations can lead to discussions with headteachers about
exclusions where time is needed to review planning for the child involved and
that in these situations headteachers are supported to think through the
legality of exclusion, as equalities legislation needs to be considered where a
child with ASN is involved.
S Hope raised the difficulties there are recruiting PSAs, Councillor Rebbeck
acknowledged the role has become more challenging in the last few years.
They are being provided with better training opportunities and work is ongoing
to establish some career progression.
In response to S Topen-Cooper asking about getting ‘zero tolerance’ posters
in PKC schools, F Mackay said that it is easy to say there should be zero
tolerance but implementation of a zero-tolerance approach within education
would often be unworkable. It is important to remember that the majority of
Page 14 of 86

Page 15

children involved have additional support needs and are in the early stages of
primary school. She suggested taking further discussion on this to the
Reducing Challenging Behaviour Working Group which the union reps who sit
on this committee are part of.  Councillor McCole said she would take zero
tolerance posters as an action to follow up which Councillor Allan said he was
happy to support.
Councillor Rebbeck said any positive message we can give staff that we care
is welcome, but a poster and a policy are different things.
Both C Weston and S Topen-Cooper said they have been asking for posters
for years. C Weston wanted her disappointment at the lack of action noted
and S Topen-Cooper wanted it noted that other Councils have them and that
he felt the Councillors at committee are in favour of them.
Resolved:
The contents of Report G/25/130, be noted.
9. Modern Apprentice Programme – Update
There was a report submitted by the Corporate People and Culture Manager
(G/25/131) providing an update on the achievements of the Councils’ Modern
Apprentice Programme over the past year.
P Johnstone added in terms of promoting the Modern Apprentice scheme
they have good links with colleges, and the Economic Development Team
look at employability and graduate opportunities which are not just Modern
Apprentices at PKC.
In response to Councillor Allan asking if PKC had a graduate scheme
P Johnstone advised they currently did not.
Councillor McCole said the report was fantastic and great news. She asked if
the young people offered work experience when Perth High School was being
built were part of the Modern Apprentice programme and P Johnstone
advised they were not part of the PKC offer but may have been part of the
community benefit package as part of procurement.
Resolved:
The contents of Report G/25/131, be noted.
10. Smarter Working
P Johnstone gave a verbal update:
 PKC took ownership of Pullar House and Kinnoull Street car park on
11 September.
 Office moves are taking place within 2 High Street and Pullar House.
 Parking space arrangements have changed, and they are now linked to
roles and not specific people.
Page 15 of 86

Page 16

 Travel hierarchy is being reinforced.
 Those allocated a parking space are expected to have to use their own
car for work while additional pool cars are sourced.
 In future it is hoped there will be no need for staff to use their own cars.
Councillor McCole asked about the staff who had transferred to PKC from
Horizon Parking following the purchase of the car park and P Johnstone
advised a total of 6 staff transferred from different employers and no issues so
far.
Resolved:
The update was noted.
11. Disclosure Scotland
P Johnstone gave a verbal update:
 Continuing to implement changes following new legislation in April.
 There are a number of people who have still not completed disclosure
checks including those on maternity leave or sick and there will be a
requirement they do that when they are returning to work.
 Lifetime membership of the scheme has been replaced by 5 year
renewals where PKC will be asked if a person is still of interest to them
and if they are still doing regulated work. They will not have to pay for
this.
Councillor Rebbeck said he had been asked by a couple of schools if the
legislation has changed for volunteers doing trips, discos etc and was directed
to guidance on Disclosure Scotland’s website and PKC’s People & Culture
documentation on the website.
Resolved:
The update was noted.
12. Any Other Competent Business
S Hope wanted to thank Fiona Thomson who put a lot into this committee and
is leaving the Council.
13. Date of Next Meeting
3 December 2025
Page 16 of 86

Page 17

Finance and Resources Committee
Outstanding Business Statement (OBS)
(Report No. 26/35)
Please note that this statement sets out outstanding decisions of this committee along with an update and estimated completion date.  Actions
which are overdue are shaded for ease of reference.  Where an update reflects that an action is complete then the Committee’s agreement will be
sought to its removal from the OBS.
No Minute
Reference
Subject Title Outstanding Action Update Lead Officer/
Service
Action
Due
Action
Expected
40. 26 November
2025
Item 6.
2025/26 Revenue
Budget – Update
No. 2
An update on when the
cost and expenses of the
Short Term Lets scheme
would be provided to
members.
Response was circulated
to members on 27
January via email.
Scott Walker /
Lisa Simpson
Complete 4 February
2026
4
Page 17 of 86

Page 18

Page 18 of 86

Page 19

Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality
___________________________________________________________________
Committee: Finance and Resources Committee
Date of Meeting: 4 February 2026
Report Title: 2025/26 Revenue Budget – Update No. 3
Report Number: 26/36
Report Author: Scott Walker, Chief Finance Officer
Organisational Lead: Scott Walker, Chief Finance Officer
___________________________________________________________________
1. Purpose
1.1 The purpose of this report is to provide an update on progress with the
2025/26 General Fund Revenue Budget based upon the November 2025
ledger, updated for any subsequent known material movements, and the
projected financial position of the Housing Revenue Account.
1.2 The total net projected underspend on the 2025/26 General Fund
Management Budget, is £2.234 million (or 0.4% of the 2025/26 Revised
Management Budget) which represents a positive movement of £2.573 million
(see Appendix 1).
1.3 Sections
1. Purpose
2. Recommendations
3. Background
4. 2025/26 Revenue Monitoring
Service Budgets
Corporate Budgets
Funding
Other Updates
5. 2025/26 Revenue Budget Adjustments
Additional Funding
Virements
Movements In Reserves
6. Financial Risks
7. Conclusion
8. Impact and Value Assessment
9. Appendices
5
Page 19 of 86

Page 20

2. Recommendations
It is recommended that the Committee:
2.1 Note the contents of the report,
2.2 Note the projected outturn for the General Fund set out in Section 4 and
Appendix 1 and 2,
2.3 Approve the adjustments to 2025/26 General Fund budgets set out in Section
5 and Appendices 1,2,4,5,6 and 7,
2.4 Note the financial risks set out in Section 6 and Appendix 8.
3. Background
3.1 This report updates the Committee on progress with the 2025/26 Revenue
Budget.  Appendix 1 to this report summarises the current projected year end
(outturn) position for each Service based upon the November 2025 ledger,
updated for any subsequent known material movements.
3.2 The budget reflected in Column 1 of Appendix 1 to this report is that
approved by the Council in setting the final 2025/26 Revenue Budget on 26
February 2025 (Report No. 25/36 refers).  In addition, adjustments approved
by the Finance and Resources Committee on 30 April, 25 June, 1 October
and 26 November 2025 (Report No’s 25/99, 25/172, 25/248 and 25/326 refer)
are reflected in Appendix 1 (Column 2).  In addition, approval to apply
additional resources to Perth and Kinross Health and Social Care Partnership
on 29 October 2025 is also reflected ( Report No 25/278 refers).
4. 2025/26 Revenue Monitoring
Service Budgets
4.1 The total net projected underspend on Service budgets, which is
summarised in Section 1 of Appendix 1 to this report, is £2.260 million
which represents 0.6% of total net Service expenditure.
4.2 Details of variances against individual Service budgets are shown in
Appendix 2 to this report with the most significant variances summarised
below.
4.3 The management of Service over and underspends are considered
throughout the financial year and may also form part of the Revenue Budget
strategy for future years.
4.4 There remains a risk that the Council continues to experience increases in
costs over the short to medium term that are higher than budgeted.  Going
forward, this may continue to have an impact on projected outturns and future
years’ budgets.
Page 20 of 86

Page 21

Education and Learning
4.5 There is currently a projected underspend for Education and Learning
excluding Devolved School Management (DSM) and the Pupil Equity Fund
(PEF) of £835,000 or 0.5% of the budget which represents a positive
movement of £784,000.  The individual elements contributing to this position
are summarised in the following table with commentary on the significant
variances below.
Projected Outturn MovementFunction
£’000 % £’000
Education and Learning Core Overspend 8 0.5 2
Nursery Sector Underspend (588) (2.0) (227)
Primary Sector Overspend 908 1.7 (206)
Secondary Sector Underspend (567) (9.1) (78)
Special Sector Underspend (316) (1.8) (275)
Home to School Transport Underspend (280) (2.5) -
TOTAL Underspend (835) (0.5) (784)
4.6 In the Nursery Sector, there is an increase in the projected underspend of
£227,000 due to updated staff cost projections, including deferred places and
lower partner provider payments.
4.7 In the Primary Sector, there is a reduction in the projected overspend of
£206,000 due to updated staff cost projections.  This is a result of a reduction
in the projected costs associated with sickness absence.
4.8 Within the Secondary Sector, there is an increase in the projected
underspend of £78,000 due to updated staff cost projections.
4.9 In the Special Sector there is an increase in the projected net underspend
of £275,000 due to updated staff cost projections, partially offset by increases
in the cost of independent school placements.
4.10 In the Devolved School Management Scheme there is a projected
underspend of £100,000.  However, some schools are experiencing
challenges in delivering approved staff slippage targets and facing inflationary
pressures against budgets that have been reduced over previous years.  The
budgets for the Devolved School Management scheme are allocated by
financial year (April – March), whereas expenditure is incurred by academic
year (August – June).
4.11 At this stage of the academic year, expenditure met from the Pupil Equity
Fund (PEF) is projected to be £100,000 less than budget.  It is anticipated
this this expenditure will be incurred prior to the conclusion of the 2025/26
academic year.
Page 21 of 86

Page 22

Children, Families and Justice
4.12 There is currently a projected underspend for Children, Families and Justice
of £155,000 or 0.6% of the budget, which represents an adverse movement
of £115,000.  The individual elements contributing to this position are
summarised in the following table with narrative on the significant variances
below.
Projected Outturn MovementFunction
£’000 % £’000
Children & Families Underspend (155) (0.7) 115
Justice Service On Target - - -
TOTAL Underspend (155) (0.6) 115
4.13 In Children and Families, there is a reduction in the projected underspend
of £115,000.  This is due to an increase in the number and costs of residential
placements, partially offset by projected savings on staff costs and foster,
kinship and adoption services linked to new working practices.
Economy, Development and Planning
4.14 There is currently a projected underspend for Economy, Development and
Planning of £260,000 or 1.6% of the approved budget which represents a
positive movement of £207,000.  The individual elements contributing to this
position are summarised in the following table with narrative on the significant
variances below.
Projected Outturn MovementFunction
£’000 % £’000
Service Wide Underspend (73) (1.2) (120)
Tourism, Culture and Place Overspend 113 2.4 13
Development Management and
Building Standards
Underspend (300) - (100)
TOTAL Underspend (260) (1.6) (207)
4.15 Service Wide there is an increase in the projected underspend of £120,000
based on the latest staff cost projections.
4.16 4In Development Management and Building Standards, there is an
increase in the projected underspend of £100,000 due to additional income
from planning applications.
Environment and Infrastructure
4.17 There is currently a projected overspend for Environment and Infrastructure
of £275,000 or 0.8%, which represents a positive movement of £250,000. 
The individual elements contributing to this position are summarised in the
following table with narrative on the significant variances below.
Projected Outturn MovementFunction
Page 22 of 86

Page 23

£’000 % £’000
Service Wide Overspend 100 0.8 (400)
Traffic and Network Underspend (150) (12.0) (50)
Waste Disposal Underspend (150) (1.7) 100
Refuse Collection Overspend 175 3.4 -
Fleet Overspend 200 - -
Roads Maintenance
Partnership
Overspend 100 4.1 100
TOTAL Overspend 275 0.8 (250)
4.18 Service wide there is a reduction in the projected overspend of £400,000
due to updated staff cost projections.
4.19 In Traffic and Network there is an increase in the projected underspend of
£50,000 due to additional income from statutory road network charges.
4.20 In Waste Disposal, there is an increase in the projected overspend of
£100,000 due to increases in both the volume of waste and gate fees.
4.21 Across the Roads Maintenance Partnership there is a net increase in the
projected overspend of £100,000.  This is derived from a projected
overspend on routine and cyclic works and flood maintenance partially offset
by savings on street lighting.
4.22 Since the start of 2026 there has been significant activity reacting to severe
weather events including snow, ice and rain.  Currently, there is no reported
variance.  However, there is a risk that if there are further weather events that
this will result in an overspend which will impact on the level of unearmarked
Reserves.
Housing and Communities
4.23 The projected outturn for Housing and Communities is currently anticipated
to be £250,000 or 1.3% more than budget, a positive movement of £7,000. 
The individual elements contributing to this movement are summarised in the
following table with commentary on the significant variances below.
Projected Outturn MovementFunction
£’000 % £’000
Service Wide Underspend (7) - (7)
Bereavement Services Overspend 14 1.7 -
Public Transport Unit Overspend 75 (0.5) -
Parking and Civil
Contingencies
Overspend 94 - -
Specialist Services Overspend 74 1.2 -
TOTAL Overspend 250 1.3 (7)
Page 23 of 86

Page 24

Property Services
4.24 The projected outturn for Property Services is currently anticipated to be
£212,000 or 0.3% less than budget which represents a positive movement of
£366,000.  The individual elements contributing to this movement are
summarised in the following table with commentary on the significant
variances below.
Projected Outturn MovementFunction
£’000 % £’000
Service Wide Overspend 593 1.5 (69)
Energy Underspend (996) (12.8) (216)
Facilities Management Overspend 446 5.63 28
Catering Underspend (255) (3.1) (109)
TOTAL Underspend (212) (0.3) (366)
4.25 On a Service Wide basis, there is a reduction in the projected overspend of
£69,000 due to updated staff cost projections.
4.26 On Energy, there is an increase in the projected underspend of £216,000
based on the latest consumption information.
4.27 In Catering there is an increase in the projected underspend of £109,000
based on the latest data on school meal uptake.
Legal and Governance
4.28 Within Legal and Governance there is a projected underspend of £126,000
or 3.1%, which represents a positive movement of £18,000.
Customer and Digital Services
4.29 The projected outturn for Customer and Digital Services is currently
anticipated to be £581,000 or 4.3% less than budget, which represents a
favourable movement of £568,000.  The individual elements contributing to
this movement are summarised in the following table with commentary on the
significant variances below.
Projected Outturn MovementFunction
£’000 % £’000
IT and Customer Services Underspend (661) (7.2) (574)
Revenues and Benefits Overspend 80 1.35 6
TOTAL Underspend (581) (4.3) (568)
4.30 In IT and Customer Services there is an increase in the projected
underspend of £574,000 due to updated staff cost projections which have
been impacted by delays in recruitment.
Page 24 of 86

Page 25

Strategic Planning, People and Performance
4.31 The projected outturn for Strategic Planning and Performance is £476,000
or 7.8% less than budget which represents a favourable movement of
£350,000. The majority of this projected underspend relates to the Community
Mental Health and Fairer Futures Locality funds which have not been utilised
to date and additional income from the salary sacrifice scheme.
Finance and Business Support
4.32 The projected outturn for Finance and Business Support is currently
anticipated to be £140,000 or 1.3% less than budget which represents a
favourable movement of £115,000 due to updated staff cost projections.
Scott Street Fire
4.33 At this time, there are no costs included within the Service monitoring
information in relation to the fire that took place at Scott Street, Perth in June
2025.
4.34 To date the Council has incurred costs of around £1.3 million, with the latest
projection reducing to £2.6 million.
4.35 Work continues with insurance companies to recover costs, and the Council
has appointed its own loss adjuster to represent it in the complex discussions.
4.36 Furthermore, the Council has received a contribution of £1 million from the
Scottish Government towards the cost of responding to the incident.
4.37 Further updates will be provided to future meetings of the Finance and
Resources Committee.
Corporate Budgets
4.38 Included within Section 2 of Appendix 1 is an update on the Council’s
Corporate budgets.  More information on variances against individual budget
headings is set out below.
Health and Social care
4.39 On 17 December 2025, Perth and Kinross Integration Joint Board considered
a report on the 2025/26 Financial Position, based on financial information to
month seven (October 2025) (Report No. G/25/198 refers).
4.40 The financial recovery plan identified measures that could be delivered in the
current financial year (part A) which are reflected in the projected outturn
below, as well as other measures (part B) which will require further
consideration and may be deliverable over the longer term, and this was
included in an update to Council on 14 January 2026 (Report No. 26/13
refers).
Page 25 of 86

Page 26

4.41 The latest financial update included an updated projected net overspend
across the Health and Social Care Partnership of £4.414 million which is
summarised in the following table and in detail in Appendix 3.  This position
remains consistent with the financial challenges facing health and social care
across Scotland.
Social
Care
£m
Health
£m
Health and Social
Care Partnership
£m
Gross Projected Overspend 4.581 0.947 5.528
Application of Remaining
General Reserves
(0.164) - (0.164)
Financial Recovery Actions
- (Part A)
(0.250) (0.700) (0.950)
Net Projected Overspend 4.167 0.247 4.414
4.42 On 29 October 2025, the Council agreed to provide up to £4.180 million of
additional financial support in 2025/26 (Report No. 25/278 refers).  This
funding will meet the costs associated with high service demand and provide
time to complete the work outlined in part A and B of the Financial Recovery
Plan.
4.43 The Finance and Resources Committee will receive further updates as
information becomes available.
Funding
4.44 Further information on the Council’s funding is set out within Section 3 of
Appendix 1.  More information on variances against individual budget
headings are set out below.
Council Tax Income
4.45 The amount of income the Council will generate from Council Tax is
dependent on two main factors, firstly the collection levels and secondly, the
number of Band D properties on the Valuation Roll.
4.46 Monitoring of Council Tax collection levels is carried out monthly.  The
following graph sets out collection performance to 31 December 2025
together with prior year comparative figures for the previous five financial
years.
Page 26 of 86

Page 27

4.47 Between 2020/21 and 2024/25, the average collection figure to 31 December
was 81.41%.  The actual collection figure to 31 December 2025 was 81.14%
which is 0.27% less than the five-year average and 0.03% more than the
comparable position in 2024.
4.48 Secondly, in setting the Council’s Revenue Budget, assumptions are made on
increases in the number of Band D equivalent properties.  The graph set out
below suggests that actual growth levels are in line with budget assumptions.
Page 27 of 86

Page 28

4.49 Currently, the level of Council Tax income is projected to be on target against
the budget assumptions which is reflected in Appendix 1.
Non-Domestic Rates
4.50 The actual collection rate to 31 December 2025 was 83.13%, compared to
81.38% for the same period in 2024/25.
Other Updates
Housing Revenue Account
4.51 In terms of recurring activity across the Housing Revenue Account, there is
a projected underspend of £200,000 for the current financial year.  All things
being equal, this will result in an increase in the level of unearmarked HRA
reserves and ensure that the level of unearmarked reserves is maintained at
between 2 and 4%.  The main elements of the movements are summarised
below and set out in Appendix 4.
4.52 The significant factors contributing to the increase in the level of
unearmarked HRA Reserves of £200,000 are as follows.  Additional staff
slippage across the HRA (£101,000), a reduction in the projected overspends
in Repairs and Trades (£158,000) and additional income (£134,000).  These
projected underspends are partially offset by projected overspends on Internet
of Things sensors (£70,000), recharges (£50,000) and an increase in the level
of capital funded from revenue (£73,000).
Page 28 of 86

Page 29

4.53 There is also a reduction in the funding required from earmarked HRA
Reserves of £139,000.  This is made up of slippage in housing repairs
(£70,000), housing improvements and localities.
4.54 The net result of this latest monitoring on Housing Revenue Account Balances
is as follows –
 HRA unearmarked Reserves - £1.2 million
 HRA earmarked Reserves - £968,000
5. 2025/26 Revenue Budget Adjustments
Additional Funding
5.1 Since elected members were provided with the 2025/26 Revenue Budget
update on 26 November 2025 (Report No. 25/326 refers), notification has
been received of additional resources in the current financial year from
several sources as set out below.  To ensure that the 2025/26 Management
Budget continues to reflect the operational requirements of the Council,
several adjustments are required, which are summarised below and included
either in Appendix 1 or Appendix 5.
Scottish Government – Revenue Support Grant:
 Teacher Induction Scheme - £64,000 (Education and Learning)
 Discretionary Housing Payment – Tranche 2 (for bedroom tax mitigation
and benefit cap mitigation) and Housing Emergency Action Plan - £24,000
(Customer and Digital Services)
 Scottish Welfare Fund - £101,000 (Customer and Digital)
 Invest to Save - £529,000 (Directorate Core Costs)
 Rapid Rehousing Transition Plan - £20,000 (Housing and Communities)
 Single Use Vapes - £5,000 (Housing and Communities)
 Nature Restoration Fund £94,000 (Environment and Infrastructure)
 Prisoner Early Release £34,000 (Housing and Communities)
 Pay Deal Single Status £481,000 (Reserves)
5.2 The Scottish Government has advised that the increase in Revenue Support
Grant identified above of £1,352,000 will be made through a redetermination
of the Council’s funding.  It is therefore necessary to adjust budgets for
Education & Learning, Customer & Digital Services, Directorate Core Costs,
Housing & Communities, Environment & Infrastructure and Revenue Support
Grant.
Other Funding
5.3 Other funding amounting to £1.687million has been paid outside the
Revenue Support Grant mechanism as Other Grant income and is, therefore,
cost neutral in terms of the budget summary.  Details of this funding is set out
in Appendix 5.
Page 29 of 86

Page 30

5.4 ACTION: The Committee is asked to note the receipt of £1.687 million of
additional resources, with this funding being reflected within Housing and
Communities, Economy, Development and Planning, Strategic Planning,
People and Performance, Education and Learning, Children, Families and
Justice and Customer and Digital Services as additional grant income.  The
current projected outturn assumes that all these additional resources will be
fully expended in 2025/26 or will be carried forward under the terms of the
grant award.
5.5 In addition, the receipt of £1 million from the Scottish Government towards
the cost of responding to the Scott Street fire is now reflected in Appendix 1
with an increase in the budgets for Capital Grant and Property.
Virements
Contribution to/from Capital Fund
5.6 In line with the strategy for managing the Council’s Capital Programme over
the medium term, it is recommended that the eventual over or underspend on
Capital Financing Costs and Interest on Revenue Balances be transferred
from or to the Capital Fund.
5.7 The latest monitoring indicates a projected reduction in capital financing costs
(loan charges) of £1.416 million based on the latest treasury management
activity and an increase of £487,000 in income from interest on revenue
balances due to updated cashflow projections.  This will result in an increased
Contribution to the Capital Fund of £1.903 million in the current financial
year.  This is consistent with the planned use of the Capital Fund to manage
the revenue cost of supporting the Capital budget over the short term.
5.8 ACTION: The Committee is requested to approve the virement of £1.416
million to the Capital Financing Costs (Loan Charges) Budget and £487,000
to Interest on Revenue Balances with a corresponding increase in the
projected Contribution to the Capital Fund.  These adjustments have been
reflected in Appendix 1 (Column 4) to this report.
Service Virements
5.9 To ensure that the 2025/26 Management Revenue Budget continues to reflect
current Service needs and operational requirements there are several
virements that are reflected in Appendix 1 (column 4) that have been
processed in line with the Scheme of Administration.
Movements In Reserves
5.10 Included at Appendix 6 is an update on the Council’s General Fund Reserves
which includes the following:
 Earmarked and unearmarked Reserves at 31 March 2025 (per audited
Annual Accounts).
Page 30 of 86

Page 31

 previously approved contributions to and from earmarked Reserves in
2025/26, 2026/27 and 2027/28.
 The impact of proposals within this report on earmarked Reserves.
 The impact of the latest revenue monitoring on the level of
unearmarked Reserves.
5.11 The earmarked Reserves are presented under three headings as follows:
i. Balances held under statute / regulation – these earmarked Reserves
are prescribed under legislation, and the Council has limited discretion in
how they are applied.
ii. Balances held for specific (previously approved) purposes – the purpose
of these earmarked Reserves has been previously approved by Council
in either the Reserves Strategy or Annual Accounts
iii. Balances held for other purposes – the creation of these earmarked
Reserves has been approved by Council, but not specific proposals.
5.12 Going forward proposals involving earmarked Reserves under i. and ii. above
will be advised to Committee in summary as Council either has limited
discretion or previously approved their application.  Proposals to apply
earmarked Reserves under iii. above will include more detail for elected
member consideration.
Balances Held Under Statute / Regulation
5.13 The following are adjustments to the earmarked Reserves held under statute
or regulation.
 £740,000 from Revenue Grants to Housing and Communities to
support eligible expenditure including costs associated with Ukraine
resettlement costs and the Rapid Rehousing Transition Plan.
Balances Held for Specific (Previously Approved) Purposes
5.14 These earmarked Reserves have previously been approved by elected
members in their consideration of the Reserves Strategy or Annual Accounts.
5.15 Specifically, authority is sought to adjust the following earmarked Reserves
identified below:
 £58,000 from the School Estate earmarked Reserve to support IT costs at
Bertha Park (Education and Learning)
 £49,000 from Climate Change to take forward approved projects
(Environment and Infrastructure)
 £70,000 returned to works maintenance due to a rephasing of the
expenditure (to be drawn down in 2026/27) (Housing and Communities)
 £24,000 returned to Community Investment Fund (to be now drawn down
in 2026/27) (Housing and Communities)
 £6,000 from the Local Area Partnerships reserve for scheme applications
(Housing and Communities)
Page 31 of 86

Page 32

 £35,000 from the Feasibility reserve towards the cost of taking forward the
strategic energy partnership (and a further £65,000 in 2026/27) (Economy
Development and Planning)
 £400,000 returned to the Extended Producer Packaging reserve due to
slippage on waste projects (to now be drawn down in 2026/27)
(Environment and Infrastructure)
 £694,000 to Council Approved Revenue Budget Flexibility to reflect the
timing of expenditure towards approved projects.
5.16 ACTION: The Committee is asked to approve the transfers to or from
earmarked Reserves set out in paragraph 5.15 above.  These adjustments
are reflected in Appendix 1 (Column 5) to the report.
Balances Held for Other Purposes
5.17 Approval is sought for an adjustment relating to the earmarked Reserve for
Transformation and Workforce Management of £110,000 for workforce
management in order to deliver recurring savings to the Revenue Budget.
5.18 Approval is also sought to adjust the budgets for Projects and Programmes
(£181,000) and Strategic Planning People and Performance (£150,000) to
reflect a rephasing of transformation and change activity.
5.19 ACTION: The Committee is asked to approve the transfer of £110,000 from
the Transformation and Workforce Management earmarked Reserve to
Property Services for workforce management and £331,000 from Projects and
Programmes and Strategic Planning, People and Performance.  These
adjustments are reflected in Appendix 1 (Column 5) to the report.
5.20 The Health and Social Care Partnership has completed the trialling and
evaluation of a digital enabled transcription tool, designed to streamline
notetaking and documentation. The evaluation has evidenced significant
efficiencies, an increase in productivity, quality of data and staff well-being. 
Approval is now sought to scale up this project for a further year with a
contribution from the Transformation and Workforce Management earmarked
Reserve of £88,000.
5.21 This proposal would be subject to agreed governance requirements where a
limited extension to the pilot would be agreed for a 12 month period.  During
this time the Service will work with IT and governance colleagues to produce
an options appraisal for a range of transcription solutions to identify a cost
effective long term solution.
5.22 ACTION: The Committee is asked to approve the transfer of £88,000 from the
Health and Social Care earmarked Reserve to the Health and Social Care
Partnership.  This adjustment is reflected in Appendix 1 (Column 5) to the
report.
5.23 Approval is sought to draw down funding of £60,000 from the Anti-Poverty
earmarked Reserve to support the Council’s Summer Work Placements
Programme.  For Summer 2026, the proposal is to introduce four-week paid
Page 32 of 86

Page 33

placements for school leavers with roles aligned to workforce needs and
apprenticeship routes, strengthening the Council’s ability to attract and
develop new talent in a sustainable way.  Each placements costs
approximately £2,000 for a 4-week placement (paid at the real living wage)
and it is proposed to offer 30 placements in 2026.  Approval is required at this
stage to commence the recruitment to the programme.
5.24 ACTION: The Committee is asked to approve the transfer of £60,000 from the
Anti-Poverty earmarked Reserve to the Strategic Planning, People and
Performance in 2026/27.
Unearmarked Reserves
5.25 Following an increase in longer term interest rates in November 2025, the
opportunity was taken to prematurely repay £28 million of Public Works Loan
Board loans which had between 30 and 35 years left until maturity. As the
interest rates on these loans were lower than the comparative PWLB rates at
that time, a discount of £2.268 million was received from the PWLB, of which
£1.6 million accrues to the General Fund through reduced Loan Charges.
5.26 It is therefore proposed to reduce the General Fund Contribution to the
Capital Fund by £1.6 million which results in an increase in the level of
unearmarked Reserves.
5.27 Based on the latest information, the level of unearmarked Reserves at 31
March 2026 is projected to be £16.786 million or 3.3%.  This position will
change throughout the financial year as more information becomes available.
5.28 The level of unearmarked Reserves has increased by £4.634 million since
the last update in November for three main reasons.  Firstly, the treasury
activity set out in paragraph 5.21 contributed £1.6 million, secondly the
movement from a projected overspend to a projected underspend contributed
a further £2.573 million (see paragraph 1.2) and the additional contribution to
Reserves included in paragraph 5.1.
5.29 The Reserves Strategy sets out a range of between 2% and 4%.
6. Financial Risks
6.1 In preparing the Council's revenue monitoring, officers have considered the
key strategic, operational and financial risks facing the Council over this
period.  Whilst the risks may be managed in the current financial year, there is
the potential for there to be an impact in the future.
6.2 To alleviate the impact these risks may have if they occur, a number of
general risk mitigation factors are utilised by the Council which include
detailed budget monitoring carried out by Services and having general fund
balances available to meet unforeseen expenditure.
6.3 Risks are captured within the body of the report with a summary being
maintained in Appendix 8.
Page 33 of 86

Page 34

6.4 As set out above, following a prolonged period of severe weather there is
now a risk that the budget for responding to this is insufficient in the current
year.  The actual impact of this on the level of unearmarked Reserves will be
included in the final revenue monitoring report in April 2026.
6.5 Going forward, risks to the 2025/26 Revenue Budget and beyond will be
captured with mitigating actions identified.
7. Conclusion
7.1 This report provides an update on the financial performance of Perth and
Kinross Council for 2025/26. The report highlights a projected net underspend
of £2.234 million.
7.2 The report also outlines several adjustments to the 2025/26 Revenue Budget,
including additional funding from the Scottish Government and various
virements to ensure the budget aligns with current service needs.
7.3 Financial risks are identified and mitigated through detailed budget monitoring
and the availability of general fund balances.
7.4 The latest monitoring indicates that the Council will have unearmarked
General Fund balances of £16.786 million or 3.3% on 31 March 2026.
7.5 The report recommends approval of the proposed budget adjustments and
notes the importance of continued vigilance in managing financial risks.
8. Impact and Value Assessment
8.1 This is an operational report, and as such, an impact and value assessment is
not required.
9. Appendices
Appendix 1 – 2025/26 Management Budget
Appendix 2 – General Fund 2025/26 Projected Outturn – Service Analysis
Appendix 3 – Perth and Kinross Health and Social Care Partnership - 2025/26
Projected Outturns
Appendix 4 – Housing Revenue Account 2025/26 Projected Outturns
Appendix 5 - Other Grant Funding
Appendix 6 - General Fund Reserves Update
Appendix 7 - Council Approved Revenue Budget Flexibility
Appendix 8 - Financial Risks
Page 34 of 86

Page 35

Appendix 1
(1) (2) (3) (4) (5) (6) (7) (8) (9)
2025/26 Previously Movements Virements Movements 2025/26 Projected Variance Variance
Council Approved in in Revised Outturn to to
Approved Adjustments Funding Reserves Mgt Revised Revised
Budget (Net) Budget Mgt Mgt
Budget Budget
£'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 %
SECTION 1
Service Budgets
Education and Learning 178,397 2,105 64 58 180,624 179,789 (835) (0.5%)
Children, Families and Justice 24,415 2,432 26,847 26,692 (155) (0.6%)
Economy, Development and Planning 14,857 1,034 (74) 15,817 15,557 (260) (1.6%)
Environment and Infrastructure 31,049 2,441 94 (1) (403) 33,180 33,455 275 0.8%
Housing and Communities 18,772 265 59 (132) 587 19,551 19,801 250 1.3%
Property Services 65,316 673 1,000 (71) 110 67,028 66,816 (212) (0.3%)
Legal and Governance 4,898 (664) 36 (170) 4,100 3,974 (126) (3.1%)
Customer and Digital Services 12,466 728 125 79 13,398 12,817 (581) (4.3%)
Strategic Planning, People and Performance 6,159 375 (395) 6,139 5,663 (476) (7.8%)
Projects and Programmes 527 90 (30) (234) 353 353 0 0.0%
Finance and Business Support 8,521 1,990 7 10,518 10,378 (140) (1.3%)
Directorate Core Costs 570 (6) 529 1,093 1,093 0 0.0%
Sub - Total: Service Budgets 365,947 11,463 1,871 (112) (521) 378,648 376,388 (2,260) (0.6%)
SECTION 2
Corporate Budgets
Health and Social Care 106,313 4,663 112 88 111,176 111,163 (13) (0%)
Contribution to Valuation Joint Board 1,421 1,421 1,421 0 0.0%
Capital Financing Costs 18,914 4,170 (1,416) 21,668 21,668 0 0.0%
Interest on Revenue Balances (3,936) (139) (487) (4,562) (4,562) 0 0.0%
Net Contribution to/(from) Capital Fund 5,331 (4,031) (1,000) 1,903 (1,600) 603 603 0 0.0%
Contribution to/(from) Insurance Fund 4,000 4,000 4,000 0 0.0%
Trading Operations Surplus (550) (550) (550) 0 0.0%
Support Service External Income (2,323) (2,323) (2,323) 0 0.0%
Tayside Pension Fund 1,711 1,711 1,695 (16) (0.9%)
Apprenticeship Levy 956 956 1,011 55 5.8%
Pay Award (2,800) 2,800 0 0 0 0.0%
Leadership and Procurement (305) 305 0 0 0 0.0%
Council Tax Reduction Scheme 7,400 7,400 7,400 0 0.0%
Discretionary Relief 1,104 1,104 1,104 0 0.0%
Net Expenditure (General Fund) 503,183 19,231 871 0 (2,033) 521,252 519,018 (2,234) (0.4%)
PERTH
&
KINROSS
COUNCIL GENERAL FUND
2025/26 REVENUE
BUDGET - SUMMARY
5
Page 35 of 86

Page 36

Appendix 1
(1) (2) (3) (4) (5) (6) (7) (8) (9)
2025/26 Previously Movements Virements Movements 2025/26 Projected Variance Variance
Council Approved in in Revised Outturn to to
Approved Adjustments Funding Reserves Mgt Revised Revised
Budget (Net) Budget Mgt Mgt
Budget Budget
£'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 %
PERTH
&
KINROSS
COUNCIL GENERAL FUND
2025/26 REVENUE
BUDGET - SUMMARY
SECTION 3
Funding
Revenue Support Grant (304,896) (6,841) (1,352) (313,089) (313,089) 0 0.0%
Ring Fenced Grant (1,967) (1,922) (3,889) (3,889) 0 0.0%
Non Domestic Rate Income (63,537) (63,537) (63,537) 0 0.0%
Council Tax Income (119,157) (119,157) (119,157) 0 0.0%
Capital Grant (1,600) (1,600) (1,600) 0 0.0%
Total Financing (491,157) (8,763) (1,352) 0 0 (501,272) (501,272) 0 0.0%
Financed from/(returned to) Reserves 12,026 10,468 (481) 0 (2,033) 19,980 17,746 (2,234)
APPENDIX
1
Page 36 of 86

Page 37

APPENDIX 2
PERTH AND KINROSS COUNCIL - GENERAL FUND 2025/26 PROJECTED OUTTURN  - SERVICE ANALYSIS
(Based on Expenditure to 30 November 2025)
Variance Variance
£'000 £'000
EDUCATION AND LEARNING
Total (835)
NON DEVOLVED
Education and Learning Core
8 Not yet meeting slippage target.
Nursery Sector
(588) Projected additional slippage over target due to turnover of staff, lower than anticipated staffing
required for deferred places and lower Partner Providers payments than budgeted.
Primary Sector
908 Slippage target projected not to be met within primary sector due to the requirement to have a
teacher in front of class at all times. Movement due to lower projected absence cover costs.
Secondary Sector
(567) Projected slippage in excess of target due to part year allocation of fte required for new Intensive
Support Provisions.
Special Sector
(607) Projected slippage in excess of target due to turnover of staff and challenges in recruitment of posts
in particular Pupil Support Assistant and part year allocation of Scottish Government funding.
291 Projected overspend on independent school placements due to increased number of placements.
Home to School Transport
(280) Projected underspend due to increased costs being offset by lower number of school days in
financial year 25/26.  
DEVOLVED SCHOOL MANAGEMENT SCHEME (DSM)
100 Projected underspend of less than 1% of total budget.
(100) DSM carry forward
PUPIL EQUITY FUND
100 Projected underspend to cover costs until June 2026.
(100) PEF carry forward
CHILDREN, FAMILIES AND JUSTICE
Total (155)
Children and Families
(179) Projected overspend due to not meeting slippage target offset by reduction in demand for some
services over 1st Quarter.
(715) Projected under spend on foster, kinship and adoption in part due to reduction in overall placements
in foster carers. This decrease in demand is linked to the new working practices which include a
greater focus on early intervention some of which is funded from the WFWF temporary funding.
739 Projected over spend on residential placements due to additional placements in excess of budget
and higher inflation uplifts than budgeted. Movement due to extension in a number of placements,
ECONOMY, DEVELOPMENT AND PLANNING
Total (260)
Service Wide
(150) Projected slippage across Economy, Development & Planning in excess of slippage target
57 Projected shortfall in sales ledger bad debt provision
20 Projected overspend for contribution towards Tay Cities Deal project management costs
Tourism, Culture and Place
113 Perth Harbour - projected increase in operating costs /shortfall in income.
(24) Underspend relating to events due to under recovery of income
24 Events, projected under recovery of income
Development Management & Building Standards
(300) Projected additional Planning Application income
SERVICE Summary of Service Variances
5
Page 37 of 86

Page 38

APPENDIX 2
PERTH AND KINROSS COUNCIL - GENERAL FUND 2025/26 PROJECTED OUTTURN  - SERVICE ANALYSIS
(Based on Expenditure to 30 November 2025)
Variance Variance
£'000 £'000SERVICE Summary of Service Variances
ENVIRONMENT AND INFRASTRUCTURE
Total 275
Service Wide
100 Projected non-achievement of slippage target across Environment & Infrastructure
Direct Services - Waste Disposal
(250) Projected additional income from sale of recyclates as a result of the new twin-streaming collection
and favourable market prices.
100 Projected net additional cost on the waste disposal contract as a result of increased residual waste
tonnage and gate fee price
Direct Services - Refuse Collection
175 Projected net shortfall in commercial waste income
Direct Services - Fleet
200 Projected additional cost of vehicle materials and repairs.
Traffic and Network
(150) Projected additional income from statutory road network works.
Roads Maintenance Partnership
100 Projected additional expenditure on routine and cyclic roads maintenance including emptying of
gullies.
150 Projected overspend on flood maintenance
Street Lighting Partnership
(50) Projected saving on repairs and maintenance
(100) Projected saving on energy due to positive impact of LED replacement programme
HOUSING AND COMMUNITIES
Total 250
Service Wide
(35) Projected slippage across Housing & Communities in excess of slippage target
28 Projected shortfall in recharge to capital
Bereavement Services
14 Projected over spend on loan charges.
Public Transport Unit
(45) Projected additional income from park and ride departure charges
46 Projected overspend in relation to park & ride expenditure
29 Projected overspend due to health & safety works and a shortfall in income at Perth Bus Station.
45 Projected overspend on tendered service
Parking, PTU & Civil Contingencies
94 Projected overspend on Visitor Rangers
Specialist Services
74 Projected overspend in property set-up costs for temporary accommodation
PROPERTY SERVICES
Total (212)
Service Wide
356 Projected overspend as not yet meeting slippage target, increased costs for loan charges and
required works for tree surveys and emergency works across the portfolio.
230 Projected overspend on unitary charge due to increased interest rates and historic lifecycle costs
and low income from Campus RHI.
7 Increased costs for grass pitch lets in LAL settings
Energy
(996) Projected reduction in energy costs due to reduced rates and consumption. Movement due to 
milder temperatures.
Facilities Management
196 Overspend due to delay in implementing new cleaning schedule required to achieve £406,000
Tayside Contract approved saving and associated redundancy costs. New cleaning schedule for
offices in place from 1st July 2025.
250 Projected overspend due to shortfall in income target for Pullar House lets in the current year due to
delays from public sector partners.
Catering
(255) Projected underspend due to lower meals than budgeted.
Page 38 of 86

Page 39

APPENDIX 2
PERTH AND KINROSS COUNCIL - GENERAL FUND 2025/26 PROJECTED OUTTURN  - SERVICE ANALYSIS
(Based on Expenditure to 30 November 2025)
Variance Variance
£'000 £'000SERVICE Summary of Service Variances
LEGAL AND GOVERNANCE
Total (126)
36 Projected non-achievement of slippage target across Legal & Governance
8 Projected overspend on supplies and services
(170) Projected additional income across Legal and Governance (Short Term Lets £84,000,  Licences
£35k, external recharges to Dundee City Council & Angus Council £40,000, rebates income on
contracts £25,000 offset against a reduction in internal recharges £14k due to transferring budgets).
CUSTOMER AND DIGITAL SERVICES
Total (581)
IT
(661) Projected under spend on staff costs in excess of slippage target caused by delay in recruiting and
£145k in year underspend on AI due to issues in recruiting.
Revenues and Benefits
0 Projected on budget. Excess staff slippage due to early delivery of savings offset by  additional costs
in Local taxes.
80 Projected shortfall due to increased service charges from Social Housing Providers that are not
covered by Housing Benefit Subsidy.
STRATEGIC PLANNING, PEOPLE AND PERFORMANCE
Total (476)
(141) Projected staff slippage across Strategic Planning, People and Performance in excess of slippage
target
8 Projected overspend on supplies and services
(218) Projected net underspend on Community Mental Health Futures and Locality budget to reflect
known commitments.
(125) Projected additional income from the salary sacrifice scheme
PROJECTS AND PROGRAMMES
Total 0 0 No material variances at present
FINANCE AND BUSINESS SUPPORT
Total (140)
(140) Projected underspend due to slippage in excess of  target due to turnover and early delivery of
savings.
CHIEF EXECUTIVE
Total 0
0 No material variances at present
TOTAL (2,260)
Page 39 of 86

Page 40

Page 40 of 86

Page 41

APPENDIX 3
Perth and Kinross Health and Social Care Partnership
Projected outturn based on Revenue Monitoring to 31 October 2025
Social Care Health
Health &
Social Care
Partnership
£'000 £'000 £'000
DEVOLVED FUNCTIONS
Older People Services 2,085 1,745 3,830
Adult Services 2,148 (581) 1,567
Other Community Services (79) 0 (79)
Management/Commissioned/Other 312 (60) 252
Undelivered Savings 115 110 225
Sub Total - Hospital & Community Health 4,581 1,214 5,795
P&K IJB Lead Partner 0 (1,565) (1,565)
Dundee & Angus Hosted Services Recharges In/Out 0 1,950 1,950
Sub Total - Lead Partner Arrangement 0 385 385
Acute / Whole System Pressures 0 (653) (653)
Total Lead Partner Arrangements 0 (268) (268)
GP Prescribing / Other Family Health Services 0 (305) (305)
General Medical Services / Family Health Services 0 306 306
Sub Total - PKHSCP 4,581 947 5,528
Approved Use of General Reserves in 2025/26 (164) 0 (164)
Financial Recovery Actions - Part A (250) (700) (950)
Total Projected Outturn Perth & Kinross HSCP 4,167 247 4,414
NON - DEVOLVED FUNCTIONS 0 0 0
TOTAL HEALTH AND SOCIAL CARE 4,167 247 4,414
Projected Out-turn Over /
(Under) Spend
5
Page 41 of 86

Page 42

Page 42 of 86

Page 43

APPENDIX 4
PERTH AND KINROSS COUNCIL - HOUSING REVENUE ACCOUNT 2025/26 PROJECTED OUTTURN
(Based on expenditure to 30 November 2025)
£'000
Service Wide
100 Projected additional pay award costs across the Housing Revenue Account
(101) Projected slippage across HRA in excess of slippage target
Repairs & Trades
490 Projected overspend on external voids due to use of external contractors.
152 Projected overspend on external repairs & maintenance due to use of external contractors and increased stock levels.
(600) Projected underspend within stores as a result of increased usage of external contractors.
(200) Projected underspend within Electrical Inspection Condition Report (EICR) contract as a result of less remedial works required.
102 Purchase of additional Internet Of Things Sensors for installing in tenant's homes
89 Housing Repairs - additional staff and fire assessments remedial work to be funded from earmarked reserves.
Improvements
(126) Projected additional Ofgem income for Renewable Heat Incentives
(11) Recharge to HEEPS ABS programme for Project Manager costs
87 Projected overspend in relation to cost of RAAC surveys and architects fees
50 Projected overspend in relation to cost of Energy performance Certificate works
49 Housing Improvements - additional staff to be funded from earmarked reserves.
Housing Localities
152 Localities - additional staff to be funded from earmarked reserves..
Specialist Services
0 Localities - additional staff and costs for downsizing scheme to be funded from earmarked reserves.
General Administration
139 Projected overspend on Void Council Tax based on 24/25 outturn.
550 Projected overspend on loan charges due to acceleration of capital programme including buy backs.
119 Projected overspend on corporate recharges based on 24/25 plus 3% due to increasing Council wide costs.
(494) Projected underspend on rent bad debt provision based on estimated rent arrears position.
157 Projected increase in insurance costs
Income
(100) Projected additional Interest on Revenue Balances income.
(750) Projected additional income based on stock levels.
CFCR
236 As a result of the projected net under spends highlighted above, this is the additional amount available to support the HRA capital
programme from the Revenue Budget.
(290) Contribution from HRA Earmarked Reserve
(200) Net Projected Underspend to be transferred to Unearmarked Reserves
HRA Reserve Information
1,258 Opening HRA Earmarked Reserve
(290) Total contribution from HRA Earmarked Reserve.
968 Projected Closing HRA Earmarked Reserve
1,000 Opening HRA Unearmarked Reserve
200 Total contribution to HRA Unearmarked Reserve
1,200 HRA Unearmarked Reserve - 3.1%
Summary of Service Variances
5
Page 43 of 86

Page 44

Page 44 of 86

Page 45

APPENDIX 5
Other Grant Funding
Housing and Communities
NHS Tayside Charitable Foundation – Used as part of Fairer Communities for All £100,000
Homes for Ukraine – Q1 Tariff Funding and Thank You Payments £85,600
Economy, Development and Planning
Transport Scotland – EV Infrastructure Fund 25/26 Grant £83,503
Strategic Planning, People and Performance
Scottish Government – Fairer Futures Partnership £247,000
Education and Learning
Scottish Government - Strategic Equity Funding £996,583
Children, Families and Justice
Scottish Government - Care Experienced Children and  Young People Fund £135,553
Customer and Digital Services
Scottish Government - Discretionary Housing Payment  £39,091
TOTAL £1,687,330
5
Page 45 of 86

Page 46

Page 46 of 86

Page 47

APPENDIX 6
General Fund Reserves Update
Proposals
Included
in Report
Proposals
Included
in Report
Commit-
ments Balance
31/3/25 25/26 26/27 27/28 25/26 Future
£m £m £m £m £m £m £m £m
General Fund Balance 68.284
Balances Held Under Statute / Regulation
- Revenue Grants 13.355 (1.814) (0.740) (10.801) 0.000
- Service Concessions 13.262 (9.000) (2.000) (1.000) (1.262) 0.000
- Council Tax Income for affordable housing 4.796 (0.042) 0.283 0.283 (5.320) 0.000
- Developers Contributions: Affordable Housing 4.627 (4.627) 0.000
- Developers Contributions: Commuted Sums 1.202 (1.202) 0.000
- Car Parking 0.977 (0.168) (0.809) 0.000
- Devolved School Management 0.527 (0.527) 0.000
Sub total 38.746 (11.551) (1.717) (0.717) (0.740) 0.000 (24.021) 0.000
Balances Held for Specific (Previously Approved) Purposes
- Council Approved Revenue Budget Flexibility 1.483 (1.252) 0.694 (0.694) 0.231
- Culture 0.499 (0.105) (0.216) 0.178
- School Estate 0.311 0.791 0.347 (0.058) 1.391
- Climate Change 0.295 (0.049) 0.246
- Works Maintenance 0.200 (0.090) 0.070 (0.070) 0.110
- Modern Apprentice Scheme 0.186 0.186
- School Counsellors 0.151 (0.151) 0.000
- Local Government Elections 0.106 0.053 0.053 (0.212) 0.000
- Events 0.097 (0.097) 0.000
- Cemetery Walls 0.080 (0.076) 0.004
- Salix 0.075 0.075
- Community Investment Fund 0.061 (0.047) 0.024 (0.024) 0.014
- Historic Child Abuse Scheme 0.050 0.050
- Financial Assistance (Mod) 0.040 0.020 0.020 0.020 0.100
- Local Area Partnerships 0.036 (0.006) 0.030
- Feasibility 0.100 0.062 0.100 (0.035) (0.065) 0.162
- Health and Social Care 0.000 0.397 0.500 (0.088) 0.809
Approved
Contributions (from) / to
Reserves
5
Page 47 of 86

Page 48

APPENDIX 6
General Fund Reserves Update
Proposals
Included
in Report
Proposals
Included
in Report
Commit-
ments Balance
31/3/25 25/26 26/27 27/28 25/26 Future
£m £m £m £m £m £m £m £m
Approved
Contributions (from) / to
Reserves
- pEPR Funding 0.000 0.000 (0.475) (0.356) 0.400 (0.400) 0.831 0.000
- Community Resilience 0.000 0.800 0.800
Sub total 3.770 (0.486) 0.773 (0.201) 0.952 (1.253) 0.831 4.386
Balances Held for Other Purposes 0.000
- Transformation & Workforce Management 4.837 (1.052) (0.550) 0.221 (0.150) (0.923) 2.383
- Anti - Poverty 1.213 (0.165) (0.318) (0.050) (0.060) 0.620
- Communities 1.003 (0.285) (0.055) (0.055) 0.608
Sub total 7.053 (1.502) (0.923) (0.105) 0.221 (0.210) (0.923) 3.611
Earmarked Reserves 49.569 (13.539) (1.867) (1.023) 0.433 (1.463) (24.113) 7.997
Uncommitted General Fund Balance 18.715
Use of unearmarked Reserves in setting Budgets (1.989)
Impact of Current Year Decisions (4.255)
Impact of Current Year Projected Outturn 2.234
Impact of proposals within this report 2.081
Updated Unearmarked General Fund Balance 16.786
Percentage of Net Revenue Budget 3.3%
Page 48 of 86

Page 49

APPENDIX 7
Council Approved Revenue Budget Flexibility
Economy Development & Planning
Civic Events £55,000
Rural Employment - Rural Skills Academy (carry forward from 2025/26 £54,000
to 2026/27 £16,000 and 2027/28 £38,000) £54,000
Environment and Infrastructure
Green Living Fund £52,000
Housing and Communities
Community Resilience Fund £36,000
Buses 2030 £29,000
Strategic Planning, People and Performance
Communication capacity £156,000
Health & Safety capacity £37,000
Pay and Grading Review £52,000
Programmes & Projects
Transformation Capacity £53,000
Legal and Governance
Local Area Committees £170,000
Total £694,000
5
Page 49 of 86

Page 50

Page 50 of 86

Page 51

Appendix 8
FINANCIAL RISKS
Risk to Revenue Budget Mitigation
1 Achievement of staff slippage targets, particularly
relating to teacher numbers and impact on pupil /
teacher ratio
- Proactive workforce
management
- Revenue monitoring
- Future budget submissions
2 Funding to Health & Social Care - Proactive management
- Financial Recovery Plan
- Revenue monitoring
- Future budget submissions
3 Inflation in excess of budgeted levels - Revenue monitoring
- Future budget submissions
4 Council Tax income - Revenue monitoring
- Future budget submissions
5 Extended Producer Responsibility for Packaging
income
- Revenue monitoring
- Future budget submissions
6 Cost of responding to Severe Weather - Revenue monitoring
5
Page 51 of 86

Page 52

Page 52 of 86

Page 53

Our vision is a Perth and Kinross where everyone can live life
well, free from poverty and inequality
___________________________________________________________________
Committee: Finance and Resources Committee
Date of Meeting: 4 February 2026
Report Title: Composite Capital Budget 2025/31 and Housing
Investment Programme 2025/30 – Monitoring Report
No.3
Report Number: 26/37
Report Author: John Jennings, Senior Accountant
James Salisbury, Senior Accountant
Organisational Lead: Scott Walker, Chief Finance Officer
___________________________________________________________________
1. Purpose
1.1 This report provides a summary position to date for the 6-year Composite
Capital Budget for 2025/26 to 2030/31 and the 5-year Housing Investment
Programme for 2025/26 to 2029/30 and seeks approval for adjustments to the
programmes.
1.2 Sections
1. Purpose
2. Recommendations
3. Background
4. Composite Capital Programme – Gross Capital Resources
5. Composite Capital Programme – Expenditure
6. Housing Investment Programme
7. Budget Overview
8. Financial Risks
9. Impact and Value Assessment
10. Appendices
2. Recommendations
It is recommended that the Committee:
2.1 notes the contents of the report.
2.2 approves the proposed adjustments to the six-year Composite Capital Budget
2025/26 to 2030/31 set out in Sections 4 and 5 of the report and summarised
in Appendices I and II.
6
Page 53 of 86

Page 54

2.3 approves the proposed adjustments to the Housing Investment Programme
Budget 2025/26 to 2029/30 set out in Section 6 of the report and summarised
in Appendix III.
2.4 notes progress with the delivery of major Capital projects as summarised in
Appendix IV.
3. Background
3.1 The Finance and Resources Committee approved an updated six-year gross
Composite Capital Budget for 2025/26 to 2030/31 totalling £560.047 million
and a five-year gross Housing Investment Programme for 2025/26 to 2029/30
totalling £89.027 million at its meeting on 26 November 2025 (report 25/327
refers).
3.2 This monitoring report advises on current year expenditure to 31 December
2025, and the latest estimate of the projected outturn for each of the years to
2030/31 for the Composite Programme and 2029/30 for the Housing
Investment Programme.
4. Composite Capital Programme – Gross Capital Resources
4.1 The current estimated total gross capital resources (which includes
movements in Capital Receipts, Capital Grants, Contributions and borrowing)
available over the six years 2025/26 to 2030/31 amount to £561.986 million.
Movements from the revised Composite Capital Budget approved on 26
November 2025 for these six years are summarised in the table below, and
the constituent elements for each year are shown in Appendix I.
Total Gross Composite Capital Resources
Approved
26 Nov 2025
Current
Estimate
Movement
£M £M £M
2025/26 137.062 118.327 (18.735)
2026/27 112.742 133.279 20.537
2027/28 88.212 88.795 0.583
2028/29 71.157 71.470 0.313
2029/30 70.245 68.533 (1.712)
2030/31 80.629 81.582 0.953
Total 560.047 561.986 1.939
4.2 The movement in the total Gross Resources for the 6 years 2025/26 to
2030/31 shown at Section 4.1 above can be summarised as follows:
£’000
Increase in Scottish Government Capital Grants (Section 4.3) 1.593
Reduction in Ring Fenced Capital Receipts (Section 4.4) (0.221)
Increase in Third Party and Revenue Contributions (Section 4.5 and 4.6) 1.132
Reduction in Borrowing (Section 4.7 and 4.8) (0.565)
Total Increase in Gross Capital Resources (Section 4.1) 1.939
4.3 On the 26 November 2025 the Scottish Government announced £1 million of
Capital Grant towards the Scott Street fire. As the work associated with the
Page 54 of 86

Page 55

fire is in the Revenue Budget, it is proposed to reflect the funding in the
Revenue Budget by adjusting the General Fund Contribution to the Capital
Fund, as outlined in the Revenue Monitoring report being considered by this
Committee at today’s meeting. The Council has also been allocated £530,000
from the Road Safety Improvement Fund in 2025/26 (Section 5.2.2), less an
adjustment of a £1,000 reduction in the Road Safety Initiative Grant on
completion of the previous programme of works. In addition, the Scottish
Government announced the allocation of Housing First Capital Grant funding
for 2025/26, with this Council being allocated £63,742. This has been added
to Unallocated Capital Resources in 2025/26 pending proposals being
brought forward.
4.4 The only movement in Capital Receipts is a reduction of £226,000 in
estimated Ring-Fenced Receipts in relation to the Vehicle Replacement
Programme, offset by an increase of £5,000 in Waste Recycling disposals
(Section 5.2.6).
4.5 There is an increase of £1.120 million in Third Party Contributions relating to
the following programmes:
 Active Travel - £1.050 million (Section 5.2.2)
 Core Paths - £73,000 (Section 5.3.2)
 Kinnoull Hill - £16,000 (Section 5.3.2)
 Less £19,000 (Section 5.2.3) reduction for Structural Maintenance
4.6 There is also an increase of £12,000 in Revenue Contributions for Energy
Efficiency works from the Salix Reserve (Section 5.5.3).
4.7 The projected borrowing requirement in 2025/26, which is effectively the
balancing item for resources, is £97.631 million. This is £20.689 million
lower than the amount approved by this Committee on 26 November 2025
(£118.320 million).
4.8 The total borrowing requirement in the subsequent years 2026/27 to 2030/31
has increased by £20.124 million to £330.801 million, resulting in an overall
reduction in the level of borrowing across the whole 6-year programme of
£0.565 million. This movements in borrowing is summarised as follows:
2025/26 2026/27 2027/28 Later
Years
Total
£m £m £m £m £m
(Increase) in Scottish Government
Grant (Section 4.3).
(1.000) 0.000 0 0 (1.000)
Increase/(Reduction) in Environment
& Infrastructure Prudential
Borrowing (Section 5.2.6)
(0.525) 0.960 0 0 0.435
Movements arising from re-phasing
of expenditure and receipts
(Appendix II)
(19.164) 19.027 0.583 (0.446) 0
Increase/(Reduction) in
Borrowing Requirement
(20.689) 19.987 0.583 (0.446) (0.565)
Page 55 of 86

Page 56

4.9 The chart below shows the Capital Resources required to fund the 2025/26
Composite Capital Programme following the proposed budget adjustments
detailed in this report.
83%
10%
0%5% 2%0%Projected Capital Resources 2025/26
(February 2026)
Borrowing (£97.631M)
Grants (£12.968M)
Tay City Deal (£0.000M)
Developer Contributions (£5.344M)
Third Party & Revenue Contributions (£1.920M)
Receipts (£0.464M)
£Million
5. Composite Capital Programme – Expenditure
5.1 Total Expenditure and Proposed Budget Adjustments to the Current
Programme
5.1.1 Total expenditure (net of grants and contributions) to 31 December 2025 on
the Composite Capital Programme is detailed in Appendix II and summarised
as follows:
Projected
Outturn
(£m)
Net
Expenditure to
31 Dec 2025
(£m)
% of
Projected
Outturn
Environment and Infrastructure 41.504 25.681 62%
Housing and Communities 5.958 1.533 26%
Economy, Development and Planning 24.054 10.755 45%
Property Services 33.923 20.459 60%
Customer and Digital Services 4.185 1.754 42%
Health and Social Care 0.953 0.752 79%
Unallocated 4.743 0.000 0%
Total Net Capital Expenditure 115.320 60.934 53%
5.1.2 Appendix IV includes updates on the progress of delivering the Council’s
major Capital projects.
Page 56 of 86

Page 57

5.2 Environment and Infrastructure
5.2.1 The Strategic Lead has reviewed the programme for Environment and
Infrastructure and proposes various budget adjustments, the most significant
of which are described below.
5.2.2 Within Traffic and Road Network, £530,000 has been received from the Road
Safety Improvement Fund which has resulted in a corresponding increase in
the expenditure budget for Road Safety Initiatives. This funding has to be
used by 31 March and has therefore taken priority, with a consequential
movement of £186,000 from the current year to next on the core programme.
Similarly, within Active Travel Grant, £1.050 million has been received with
an expenditure deadline of 31 March, with a consequential movement of
£210,000 into 2026/27.
5.2.3 Within the Roads Maintenance Partnership, there has been a reduction in
Third-Party Contributions of £19,000 relating to the Scottish Water works at
Tay Street within Structural Maintenance, with a resulting reduction in the
expenditure budget. Works at the South Inch Culvert have completed, and it is
proposed the remaining budget of £195,000 is returned to Structural
Maintenance.  Lastly, in line with the estimated works due for completion
within Structural Maintenance for the remainder of the financial year, it is
proposed £904,000 is moved into 2026/27.
5.2.4 Within Structures, the following budget adjustments are proposed:
Project 25/26
£m
26/27
£m
Future
Years
£m
Virement
£m
Description
Bridge
Refurbishment
Programme
(0.105) 0.165 - (0.052) The budget required for the
remainder of the year has been
reviewed and it is proposed
£165,000 is slipped to 2026/27. Of
this £52,000 relates to the Corb
Bridge virement from below, and
£8,000 of other smaller
movements.
Corb Bridge
Culvert,
Kinross
(0.052) - - 0.052 Works completed, virement to
return underspend to Bridge
Refurbishment Programme.
Garry Viaduct - (0.127) 0.127 - Rephasing in line with the
programme of works received from
the contractor with initial works
continuing in 2026/27 and main
works commencing in 2027/28.
Bridge of Tilt (0.965) 0.965 - - River levels are currently high, and
with a SEPA restriction on
construction work in rivers during
winter months, scour works cannot
progress within the previously
anticipated timescales with the
budget slipped accordingly.
Page 57 of 86

Page 58

5.2.5 Within Flooding, the following budget adjustments are proposed:
2025/26
£m
2026/27
£m
Description
Comrie Flood Protection Scheme (5.263) 5.263 There is slight slippage on the
overall programme of
approximately three weeks
resulting in a requirement to slip
some of the construction cost
into 2026/27. Additionally, the
remainder of the contingency
budget in the current year is not
anticipated to be spent this year
and this too requires rephasing
into 2026/27.
South Kinross Flood Protection
Scheme
(0.221) 0.221 Expenditure incurred during the
current year is limited to survey
work. Following two valid
objections to the scheme an
initial Local Authority Hearing
took place in October 2025. The
hearing will reconvene in
February 2026. It is proposed an
additional £221,000 is rephased
to 2026/27 due to this delay.
Coastal Change Adaptation (0.059) 0.059 Works are not due to take place
in the current financial year and
are planned for 2026/27. It is
proposed this budget is therefore
rephased into 2026/27.
5.2.6 Within the Prudential Borrowing programme, the following budget adjustments
are proposed:
Project 25/26
£m
26/27
£m
Description
Recycling in Schools
– Waste Bin
Purchases
(0.036) 0.036 The budget for Recycling in Schools was
previously split equally between 2025/26 and
2026/27. The timeframe for delivery has been
reviewed and revised, and it is proposed
£36,000 is rephased to reflect this. 
Recycling
Containers, Oil
Banks & Battery
Banks Replacement
Programme
Capital Receipts –
Disposals
(0.055)
(0.003)
0.058
-
There is a slight increase in the receipts
expected for Recycling Containers and this is
combined with a reduction in the number of
replacements in the current year. It is proposed
£58,000 is rephased into 2026/27 accordingly.
Litter Bins (0.057) 0.057 An assessment of need for the replacement of
Litter Bins is currently underway to inform the
planning for the roll out next year. The
replacements to take place in 2025/26 are
therefore limited and it is proposed £57,000 of
the budget is rephased.
Page 58 of 86

Page 59

Vehicle
Replacement
Programme
Capital Receipts –
Disposals
(0.600)
0.226
0.809
-
The majority of vehicles to be delivered in the
current year are on track. There has been a
delay in procuring a library vehicle whilst the
specification is finalised. In addition, the
contingency budget is not required for the
remainder of the year. It is therefore proposed a
total of £600,000 is rephased into 2026/27.
Further is it proposed borrowing is increased in
2026/27 by £209,000 due to the rising cost of
replacement vehicles.
Additionally, capital receipt budgets for the
disposal of old vehicles have been rolled into
future years over time. These amounts have not
always been achieved, and it is now expected
that £226,000 of the income budget will not be
realised. This results in a need to increase
borrowing to pay for replacement vehicles.
This results in a total increase in borrowing of
£435,000.
5.2.7 The above proposed adjustments, together with other small movements, have
been reflected in Appendices I and II.
5.3 Housing and Communities
5.3.1 The Strategic Lead has reviewed the programme for Housing and
Communities and proposes the following budget adjustments.
5.3.2 Within Community Greenspace, it is proposed £50,000 is drawn down from
Community Greenspace Sites in 2026/27 for the Crematorium Access Road
in the current year. Additionally, Third Party Contributions have been received
as follows which increase the expenditure budgets:
 £92,000 from Walk Wheel Cycle Trust (formerly Sustrans) towards the
Crieff to Comrie path within Core Path Implementation. However this is
offset by an underspend of £19,000 in expenditure and grant on the
previous programme from last year, giving an overall increase in
£73,000 in the current year.
 £16,000 from Kinnoull Hill Woodland Park User Group towards
landscaping to supplement work already being undertaken at Kinnoull
Hill.
5.3.3 The above adjustments, together with other small movements, have been
reflected in Appendices I and II.
5.4 Economy, Development and Planning
5.4.1 The Strategic Lead has reviewed the programme for Economy,
Development and Planning and proposed the following budget adjustments.
5.4.2 Within Roads Infrastructure, the contract for the design work for the Perth
Eco-Innovation Park was awarded toward the end of 2025. The expenditure
for the remainder of this financial year will be limited to this design work, and it
Page 59 of 86

Page 60

is therefore proposed the remainder of the budget of £7.931 million is moved
into 2026/27. There is also a corresponding movement of the £550,000 Tay
Cities Deal Funding into 2026/27. These adjustments are pending a full
review of the project to be considered by the Council as part of the budget
report to be submitted to its meeting on 4 March 2026.
5.4.3 The above proposed adjustments have been reflected in Appendices I and
II.
5.5 Property Services
5.5.1 The Strategic Lead has reviewed the programme for Property Services and
proposed various budget adjustments, the most significant of which are
described below.
5.5.2 Within Project Support, the following budget adjustments are proposed:
Project 25/26
£m
26/27
£m
27/28
£m
Virement
£m
Description
School Toilet
Upgrade
Programme
0.200 0.600 0.600 1.400 Proposed phasing allocation and
budget virement from Capital
Improvement Projects Programme
in 2029/30 to provide for a
continuous programme of works for
the School Toilet Upgrades. 
Methven
Primary School
Refurbishment
(1.000) 1.000 - - The tender received for the
proposed design of the gym / dining
hall was significantly over budget.
Market testing is being undertaken
to inform the next steps.
Perth Academy
Refurbishment
0.145 (0.145) - - Wi-Fi works are underway and
progressing well and the proposed
budget acceleration reflects this.
Perth High
School – New
School
Investment
(1.300) 1.300 - - Phase 2 for the demolition of the
old building has been delayed due
to additional surveys requiring to be
undertaken prior to commencement
of the works.
Harris
Academy
(0.026) - - (0.026) Project has been confirmed as
completed with an underspend of
£26,000 which has been vired to
the Unallocated Resources.
Roof Upgrade
Programme
0.500 - - 0.500 Proposed budget virement from
Capital Improvement Projects
Programme in 2029/30 to provide
for the Roof Upgrade Programme.
Page 60 of 86

Page 61

5.5.3 Within Property Service Management, the following budget adjustments are
proposed:
2025/26
£m
2026/27
£m
Future Years
£m
Description
DDA Adaptation &
Alteration Works
Programme
(0.103) 0.103 -
Rephasing in line with works
anticipated to now take place
in 2026/27.
Energy Efficiency
Works
Revenue Contribution
(Salix Reserve)
0.012
(0.012)
-
-
-
-
Works on building a
management system at
Logiealmond Primary School,
funded from the Salix
Reserve.
Crieff Drummond Arms
Regeneration
(0.750) 0.750 - Works to address the
Dangerous Building Notice
have been completed. The
site is effectively closed until
Listed Building Consent is
obtained from Historic
Environment Scotland.
Perth Concert Hall (0.195) - 0.195 Rephasing in line with the
level of works to be
completed in the current
year.
5.5.4 Within the Property Service Management Prudential Borrowing programme,
the office moves associated with Pullar House are now complete and the
project has moved towards the construction phase. It is proposed £200,000 is
moved into 2026/27 in line with the updated expenditure projections.
5.5.5 All the above proposed adjustments have been reflected in Appendices I and
II.
5.6 Customer and Digital Services
5.6.1 The Strategic Lead has reviewed the programme for Customer and Digital
Services and it is proposed to move some of the budget for ICT Infrastructure
Replacement (£0.582 million) and Supporting Digital (£0.256 million) from
2025/26 to 2030/31. These adjustments reflect updated estimated
requirements for the current year.
5.6.2 It is also proposed to increase and extend the budget for Software Licences
(Revenues and Benefits) from 2026/27 to 2030/31. The budget for this annual
requirement has not increased previously and the 2026/27 and 2027/28
budgeted amount is not sufficient to meet the current estimated costs.
Further, there is currently no budget provision for the years from 2028/29. It is
therefore proposed to increase the budgets for this programme across all
these years by £0.324 million by applying this amount from Unallocated
Resources in 2025/26.
Page 61 of 86

Page 62

5.7 Unallocated Resources
5.7.1 The proposals outlined in this report in relation to the Unallocated Capital
Resources are summarised in the following table:
2025/26
£m
Later
Years
£m
TOTAL
£m
Description
Opening
Resources
4.977 6.246 11.223
Transfers In:
Housing First
Grant
0.064 0 0.064 Section 4.3
Harris Academy 0.026 0 0.026 Section 5.5.2
Transfers Out:
Software
Licences
(Revenues and
Benefits)
(0.324) 0 (0.324) Section 5.6.2
Closing Resources 4.743 6.246 10.989
5.7.2 After the above proposed movements, the balance of Unallocated Resources
is £10.989 million over the 6-year programme.
6. Housing Investment Programme
6.1 The total current estimated expenditure, net of contributions, for the Housing
Investment Programme over the 5 years 2025/26 to 2029/30 has remained
unchanged to £89.027 million. Movements across years from the previous
estimates are summarised in the table below and detailed in Appendix III.
Approved
26 Nov 2025
Current
Estimate
Movement
£m £m £m
2025/26 42.138 46.695 4.557
2026/27      17.000      17.321 0.321
2027/28 13.776 12.280 (1.496)
2028/29 8.015 7.003 (1.012)
2029/30 8.098 5.728 (2.370)
Total 89.027 89.027 0.000
Total Expenditure to 31 December 2025 (Housing Investment
Programme)
6.2 Net expenditure for 2025/26 to 31 December 2025 amounts to £24.832
million, with £18,000 of receipts. Therefore, the borrowing requirement for the
year to date is £24.814 million.
Page 62 of 86

Page 63

6.3 The Strategic Leads for Housing and Communities and Property Services
have reviewed the Housing Investment Programme and proposed the budget
adjustments outlined below.
6.4 It is proposed to drawdown £100,000 from the New Build Future
Developments budget in 2025/26 for site preparation works for the proposed
schemes at Beechgrove (£62,000) and Balhousie (£38,000) sites. There are
no proposed budget movements on the Council House Buy Back programme.
To date, 102 properties have been purchased, with a further 13 properties
under offer, exceeded the annual target of 40 buybacks.
6.5 It is also proposed to draw down various amounts from the SHQS Future
Developments budgets over various years for the Multi-Storey Flats project as
follows:
2025/26
£m
2026/27
£m
2027/28
£m
2028/29
£m
2029/30
£m
TOTAL
£m
Multi-Storey Flats 2.544 2.273 0 0 0 4.817
Scottish Government
Grant (0.067) 0 0 0 0 (0.067)
Third Party
Contribution 0 (0.481) 0 0 0 (0.481)
SHQS Future
Developments 0 (1.459) (1.131) (1.012) (0.667) (4.269)
Total 2.477 0.333 (1.131) (1.012) (0.667) 0
6.6 Due to factors such as delays with utilities, chalet manufacturing timelines,
additional drainage works and incomplete design costings following changes
to the original Quantity Surveyor (now in administration), the projected costs
for the Double Dyles Chalet Replacement programme have increased by
£1.684 million. There is also an adjustment of £19,000 to the Scottish
Government Grant budget. This results in an overall increase of £1.703
million in 2025/26, and it is proposed that this funded by transferring £1.591
million from the New Build Future Developments budget and £112,000 from
the SHQS Future Developments budget in 2029/30.
6.7 There are other smaller proposed adjustments which have been included in
Appendix III. These include £33,000 of Scottish Government Grant for Energy
Efficiency in 2025/26 which enhances the expenditure on this programme.
6.8 There are no movements in Capital Receipts or Capital Financed from
Current Revenue (CFCR) across the 6-year programme. Consequently, the
total borrowing remains unchanged at £79.786 million. The proposed
adjustments in this report have increased the borrowing for the current year to
56% of the whole 6-year programme Borrowing Requirement.
6.9 All the proposed movements outlined above have been included in Appendix
III.
Page 63 of 86

Page 64

7. Budget Overview
7.1 The projected net expenditure outturn in 2025/26 for the Composite Capital
Budget is £115.320 million and represents 79% of the original 2025/26
budget approved on 30 April 2025 (£146.146 million). The revised budget is
based on the latest projections of expenditure and all budget adjustments
outlined within this report.
7.2 Net expenditure to 31 December 2025 on the Composite Capital Budget is
£60.934 million and represents 53% of the proposed revised budget for
2025/26 of £115.320 million.
7.3 The projected net expenditure outturn in 2025/26 for the Housing Investment
Programme is £46.695 million and represents 166% of the original 2025/26
budget approved on 30 April 2025 (£28.098 million). This increase reflects the
allocation of future years block budgets to specific projects in 2025/26 and the
increase in the Council House Buy-Back programme.
7.4 Net expenditure to 31 December 2025 on the Housing Investment
Programme is £24.832 million which represents 53% of the proposed revised
budget for 2025/26 of £46.695 million.
7.5 The Council’s total Borrowing Requirement to 31 December 2025, based on
the Composite and Housing Investment Programmes, is £73.952 million.
7.6 The estimated overall Council Borrowing Requirement for 2025/26 as a whole
has reduced by £16.132 million to £142.642 million as a result of the
monitoring adjustments reflected within this report. This reflects a reduction in
estimated borrowing in the current year on the Composite Programme of
£20.689 million and an increase on the Housing Investment Programme of
£4.557 million.
7.7 In the context of the Capital Budget, the borrowing above refers specifically to
the funding of capital expenditure and therefore the need to borrow. The
actual amounts and timing of the borrowing is undertaken as part of the
Council’s Treasury Management operations and reported within the Treasury
Activity and Compliance reports throughout the year.
8. Financial Risks
8.1 In preparing the Council's capital monitoring, officers have considered the key
strategic, operational and financial risks facing the Council over this period.
Whilst the risks may be managed in the current financial year, given the
nature of capital projects these risks are also likely to impact future years
plans.
8.2 To alleviate the impact these risks may have if they occur, a number of
general risk mitigation factors are utilised by the Council which include
detailed budget monitoring carried out by Services and having general
unallocated funds available to meet unforeseen expenditure.
Page 64 of 86

Page 65

8.3 Given the latest monitoring position outlined in this report, the risks to 2025/26
have been removed or reduced. Going forward, risks to future years Capital
Expenditure plans will be monitored with mitigating actions identified. The
main risks impacting the Capital Budget are maintained in Appendix V.
8.4 These risks are monitored continuously by officers, and any implications on
the Capital Budget will be reported to the Committee at the appropriate time.
9. Impact and Value Assessment
9.1 This is an operational report, and as such, an impact and value assessment in
not required.
10. Appendices
Appendix I - Composite Capital Programme - Estimated Capital Resources
2025/26 to 2030/31
Appendix II – Composite Capital Programme - Summary of Capital Resources
and Expenditure 2025/26 to 2030/31       
Appendix III – HRA Capital Investment Programme – Summary of Capital
Resources and Expenditure 2025/26 to 2029/30
Appendix IV – Significant Capital Projects Progress Update
Appendix V – Capital Budget Financial Risks
Page 65 of 86

Page 66

Page 66 of 86

Page 67

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
Estimated Capital Resources 2024/25 to 2029/30
APPENDIX I
Capital Capital Capital Capital Capital Capital Capital
Resources Resources Resources Resources Resources Resources Resources
2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Revised Revised Revised Revised Revised Revised Revised
Budget Budget Budget Budget Budget Budget Budget
Capital Grants
Road Safety Initiaive Fund 530 0 0 0 0 0 530
General Capital Grant 12,438 21,752 12,750 12,750 12,750 12,750 85,190
Total Capital Grants 12,968 21,752 12,750 12,750 12,750 12,750 85,720
General Capital Receipts
General Fund - Capital Receipts 570 0 0 0 0 0 570
General Fund - Ring Fenced Receipts 557 844 994 981 1,019 1,000 5,395
Total General Capital Receipts 1,127 844 994 981 1,019 1,000 5,965
Commercial Property Receipts
Capital Receipts brought-forward 1,332 2,614 2,449 3,947 4,577 5,022 1,332
Commercial Property Capital Receipts 619 235 2,398 2,530 645 800 7,227
Capital Receipts carried-forward (2,614) (2,449) (3,947) (4,577) (5,022) (1,922) (1,922)
Total Commercial Property Receipts Applied (663) 400 900 1,900 200 3,900 6,637
Contributions
Tay Cities Deal 0 1,055 3,945 500 956 0 6,456
Developer Contributions 5,344 2,600 2,600 2,500 2,500 2,000 17,544
Other Third Party Contributions 1,733 2,000 3,000 1,000 1,000 2,064 10,797
Revenue Budget Contributions 187 124 124 0 0 0 435
Total Contributions 7,264 5,779 9,669 4,000 4,456 4,064 35,232
Capital Borrowing Requirement 97,631 104,504 64,482 51,839 50,108 59,868 428,432
TOTAL CAPITAL RESOURCES/
GROSS BUDGET EXPENDITURE 118,327 133,279 88,795 71,470 68,533 81,582 561,986
Movements in Resources from Approved Budget - 26 November 2025
Revised Revised Revised Revised Revised Revised Revised
Budget Budget Budget Budget Budget Budget Budget
2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 TOTAL
£'000 £'000 £'000 £'000 £'000 £'000 £'000
Increase/(Decrease) in:
Capital Receipts - General Fund 0 0 0 0 0 0 0
Capital Receipts - Commercial Property 0 0 0 0 0 0 0
Capital Receipts - Ring Fenced (221) 0 0 0 0 0 (221)
Capital Grants:
Road Safety Initiaive Fund 529 0 0 0 0 0 529
General Capital Grant 1,064 0 0 0 0 0 1,064
Tay Cities Deal (550) 550 0 0 0 0 0
Third Party Contributions 1,120 0 0 0 0 0 1,120
Revenue Contributions 12 0 0 0 0 0 12
Developer Contributions 0 0 0 0 0 0 0
Resources b/f 0 0 0 0 0 0 0
Resources c/f to future years 0 0 0 0 0 0 0
Borrowing Requirement (20,689) 19,987 583 313 (1,712) 953 (565)
Total Increase/(Decrease) in Resources (18,735) 20,537 583 313 (1,712) 953 1,939
Approved Resources 26 November 2025 137,062 112,742 88,212 71,157 70,245 80,629 560,047
Revised Resources 118,327 133,279 88,795 71,470 68,533 81,582 561,986
6
Page 67 of 86

Page 68

Page 68 of 86

Page 69

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30
APPENDIX II
Approved Proposed Revised Actuals Projected Revised Revised Revised Revised Revised Revised
Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget
Report 2 Adjustment 31-Dec-25
Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3
2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
ENVIRONMENT & INFRASTRUCTURE 50,004 (8,500) 41,504 25,681 41,504 44,861 23,688 20,243 16,960 17,803 165,059
HOUSING & COMMUNITIES 5,901 57 5,958 1,533 5,958 1,563 2,129 1,558 1,558 1,050 13,816
ECONOMY, DEVELOPMENT & PLANNING 31,435 (7,381) 24,054 10,755 24,054 38,884 (3,520) (250) (2,436) 1,186 57,918
PROPERTY SERVICES 36,652 (2,729) 33,923 20,459 33,923 36,424 46,254 39,606 42,150 40,997 239,354
CUSTOMER & DIGITAL SERVICES 5,023 (838) 4,185 1,754 4,185 6,179 10,925 6,397 6,036 9,790 43,512
HEALTH & SOCIAL CARE 953 0 953 752 953 1,345 1,256 1,435 1,290 1,446 7,725
UNALLOCATED CAPITAL RESOURCES 4,977 (234) 4,743 0 4,743 0 0 0 0 6,246 10,989
TOTAL NET EXPENDITURE 134,945 (19,625) 115,320 60,934 115,320 129,256 80,732 68,989 65,558 78,518 538,373
(NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS)
GENERAL CAPITAL GRANT (11,374) (1,064) (12,438) (10,888) (12,438) (21,752) (12,750) (12,750) (12,750) (12,750) (85,190)
DEVELOPER CONTRIBUTIONS (5,344) 0 (5,344) 0 (5,344) (2,600) (2,600) (2,500) (2,500) (2,000) (17,544)
CAPITAL RECEIPTS (1,189) 0 (1,189) (253) (1,189) (235) (2,398) (2,530) (645) (800) (7,797)
ANNUAL BORROWING REQUIREMENT 117,038 (20,689) 96,349 49,793 96,349 104,669 62,984 51,209 49,663 62,968 427,842
CAPITAL RECEIPTS BROUGHT FORWARD (1,332) 0 (1,332) (1,332) (1,332) (2,614) (2,449) (3,947) (4,577) (5,022) (1,332)
CAPITAL RECEIPTS CARRIED FORWARD 2,614 0 2,614 677 2,614 2,449 3,947 4,577 5,022 1,922 1,922
TOTAL NET BORROWING REQUIREMENT 118,320 (20,689) 97,631 49,138 97,631 104,504 64,482 51,839 50,108 59,868 428,432
6
Page 69 of 86

Page 70

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30
APPENDIX II
Revised Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised
Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget
Adjustment 31-Dec-25
Report 2 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3
2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
ENVIRONMENT & INFRASTRUCTURE
Traffic & Road Network
Road Safety Initiatives (20mph Zones etc..) 389 343 732 283 732 548 361 400 400 450 2,891
Scottish Government Grant (Transport Scotland) 0 (530) (530) (530) 0 0 0 0 0 (530)
Scottish Government Grant (Transport Scotland) (1) 1 0 0 0 0 0 0 0 0
Road Safety Initiatives - A94 Safety Improvements 84 84 84 0 0 0 0 0 84
Active Travel Grant -Traffic & Road Safety Schemes 983 840 1,823 285 1,823 810 600 600 600 600 5,033
Third Party Contribution 0 (1,050) (1,050) (1,050) 0 0 0 0 0 (1,050)
20mph Signage Programme 0 0 0 120 0 0 0 0 120
Additional Road Safety - Pedestrian Crossings 246 246 94 246 153 0 0 0 0 399
Traffic Signal Renewals - Upgrading 200 200 15 200 0 100 100 100 95 595
Investment in Local Footpaths 20 (20) 0 0 120 0 0 0 0 120
Car Parking Investment - Pitlochry 7 7 7 7 0 0 0 0 0 7
Revenue Contribution (1) (1) (1) 0 0 0 0 0 (1)
A977 Upgrades 0 0 0 177 0 0 0 0 177
Broich Road, Crieff - Road Realignment & Safety Measures 18 18 18 0 0 0 0 0 18
Sub-Total 1,945 (416) 1,529 684 1,529 1,928 1,061 1,100 1,100 1,145 7,863
Street Lighting Partnership
Street Lighting 0 0 0 0 0 600 600 600 1,800
Sub-Total 0 0 0 0 0 0 0 600 600 600 1,800
Roads Maintenance Partnership
Structural Maintenance 10,985 (728) 10,257 7,560 10,257 9,867 8,964 8,320 8,320 9,500 55,228
Third Party Contribution (532) 19 (513) (513) 0 0 0 0 0 (513)
Footways 359 359 297 359 368 368 341 341 400 2,177
Third Party Contribution (2) (2) (2) (2) 0 0 0 0 0 (2)
Perth Flood Protection Scheme (South Inch Culvert Reinstatement) 204 (195) 9 9 9 0 0 0 0 0 9
Sub-Total 11,014 (904) 10,110 7,864 10,110 10,235 9,332 8,661 8,661 9,900 56,899
Structures
Bridge Refurbishment Programme 1,787 (105) 1,682 828 1,682 2,020 1,836 2,259 2,259 2,603 12,659
Old Perth Bridge - Strengthening 38 38 14 38 235 2,216 0 0 0 2,489
Perth Queens Bridge - Strengthening 81 81 4 81 179 192 1,850 0 0 2,302
Culteuchar Culvert 0 5 5 5 5 0 0 0 0 0 5
Garry Viaduct 393 393 181 393 183 1,195 1,755 786 25 4,337
Bolfrack River Retaining Wall 534 (13) 521 478 521 0 0 0 0 0 521
Bridge of Tilt 1,250 (965) 285 256 285 965 0 0 0 0 1,250
Corb Bridge Culvert, Kinross 450 (52) 398 387 398 0 0 0 0 0 398
Blairgowrie Bridge 200 200 1 200 175 1,000 0 0 0 1,375
Vehicular Bridge Parapets Programme - Assess & Upgrade 10 10 10 24 0 0 0 0 34
Sub-Total 4,743 (1,130) 3,613 2,154 3,613 3,781 6,439 5,864 3,045 2,628 25,370
Page 70 of 86

Page 71

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30
APPENDIX II
Revised Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised
Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget
Adjustment 31-Dec-25
Report 2 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3
2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Flooding
Comrie Flood Protection Scheme 22,993 (5,263) 17,730 9,733 17,730 13,093 0 0 0 0 30,823
Milnathort Flood Protection Scheme 331 331 1 331 0 0 0 0 0 331
South Kinross Flood Protection Scheme 701 (221) 480 361 480 10,517 3,099 75 0 0 14,171
Flood Mitigation Measures - Dunkeld and Craigie Burn 264 18 282 150 282 88 153 338 129 0 990
Investment in Surface Water Management Schemes - Leaky Dam, Rattray Burn3 3 3 48 44 255 0 0 350
Coastal Change Adaptation 59 (59) 0 0 59 0 0 0 0 59
Almondbank Flood Protection Scheme 0 0 132 0 0 0 0 0 0 0
Sub-Total 24,351 (5,525) 18,826 10,377 18,826 23,805 3,296 668 129 0 46,724
Climate Change and Zero Waste
Climate Change Programme 215 215 215 530 200 0 0 0 945
Climate Change Unallocated 329 329 329 0 0 0 0 0 329
Nature Restoration 199 199 199 0 0 0 0 0 199
Sub-Total 743 0 743 0 743 530 200 0 0 0 1,473
Prudential Borrowing Projects
Climate Change and Zero Waste
Wheeled Bin Replacement Programme - Domestic Bins 277 2 279 148 279 200 200 220 220 225 1,344
Wheeled Bin Replacement Programme - Commercial Bins 71 71 48 71 20 20 25 25 25 186
Capital Receipts - Disposals (1) (2) (3) (1) (3) 0 0 0 0 0 (3)
Recycling in Schools - Waste Bin Purchases 54 (36) 18 6 18 84 0 0 0 0 102
Recycling Containers, Oil Banks & Battery Banks Replacement Programme154 (55) 99 53 99 163 105 70 70 75 582
Capital Receipts - Disposals (4) (3) (7) (1) (7) 0 0 0 0 0 (7)
Litter Bins 65 (57) 8 2 8 107 50 55 55 55 330
Direct Services
Vehicle Replacement Programme 6,400 (600) 5,800 3,907 5,800 3,751 2,692 3,311 3,394 3,500 22,448
Capital Receipts - Vehicle Disposals (773) 226 (547) (233) (547) (294) (269) (331) (339) (350) (2,130)
Street Lighting Partnership
Street Lighting Renewal - LED & Column Replacement 965 965 673 965 551 562 0 0 0 2,078
Sub Total 7,208 (525) 6,683 4,602 6,683 4,582 3,360 3,350 3,425 3,530 24,930
TOTAL - ENVIRONMENT & INFRASTRUCTURE 50,004 (8,500) 41,504 25,681 41,504 44,861 23,688 20,243 16,960 17,803 165,059
HOUSING & COMMUNITIES
Community Greenspace
Community Greenspace Sites 0 0 0 25 894 700 700 250 2,569
Play Areas and Parks 1,039 1,039 148 1,039 1,395 582 500 500 500 4,516
Third Party Contribution (19) (19) (19) 0 0 0 0 0 (19)
Revenue Contribution (50) (50) (50) 0 0 0 0 0 (50)
3G Pitch, Blairgowrie 34 34 34 0 0 0 0 0 34
Countryside Sites 0 0 0 0 139 0 0 0 139
Community Greenspace Bridges 106 106 81 106 0 0 0 0 0 106
Page 71 of 86

Page 72

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30
APPENDIX II
Revised Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised
Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget
Adjustment 31-Dec-25
Report 2 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3
2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Core Path Implementation 19 73 92 92 0 0 0 0 0 92
Third Party Contribution (19) (73) (92) (92) 0 0 0 0 0 (92)
Kinnoull Hill 8 16 24 14 24 0 0 0 0 0 24
Third Party Contribution 0 (16) (16) (16) 0 0 0 0 0 (16)
Crematorium Access Road 0 50 50 50 0 0 0 0 0 50
Cemetery Extensions 0 7 7 7 7 143 514 358 358 300 1,680
Sub-Total 1,118 57 1,175 250 1,175 1,563 2,129 1,558 1,558 1,050 9,033
Improvements
New Gypsy Traveller Site 1,942 1,942 1 1,942 0 0 0 0 0 1,942
Sub Total 1,942 0 1,942 1 1,942 0 0 0 0 0 1,942
Parking, Public Transport Unit and Civil Contingencies
Community Transport Iniatives 27 27 27 0 0 0 0 0 27
Bus Infrastructure Fund Expenditure 374 374 26 374 0 0 0 0 0 374
Sub-Total 401 0 401 26 401 0 0 0 0 0 401
Community Learning and Development and Equalities
Community-Led Asset Transfers 75 75 5 75 0 0 0 0 0 75
Sub-Total 75 0 75 5 75 0 0 0 0 0 75
Prudential Borrowing Projects
Parking, Public Transport Unit and Civil Contingencies
Community Transport Vehicles 115 115 115 115 0 0 0 0 0 115
Kinnoull Street Car Park - Purchase & Upgrade 2,250 2,250 1,136 2,250 0 0 0 0 0 2,250
Sub Total 2,365 0 2,365 1,251 2,365 0 0 0 0 0 2,365
TOTAL - HOUSING & COMMUNITIES 5,901 57 5,958 1,533 5,958 1,563 2,129 1,558 1,558 1,050 13,816
ECONOMY, DEVELOPMENT & PLANNING
Roads Infrastructure
A9/A85 Road Junction Improvements (PTF Phase 1) 14 14 100 14 0 0 0 0 0 14
Destiny Bridge and New Kingsway (PTF Phase 2) 5,785 5,785 2,068 5,785 314 0 0 0 0 6,099
Bertha Park Link Road (PTF Phase 3) 10,598 10,598 7,287 10,598 4,462 0 0 0 0 15,060
Third Party Contribution 0 0 0 0 0 0 0 (1,064) (1,064)
Perth Eco-Innovation Park at Perth West 9,655 (7,931) 1,724 261 1,724 30,421 0 0 0 0 32,145
Third Party Contributions - Tay Cities Deal (550) 550 0 0 (1,055) (3,945) (500) (956) 0 (6,456)
Other Third Party Contributions 0 0 0 (2,000) (3,000) (1,000) (1,000) (1,000) (8,000)
Capital Receipts - Ring Fenced Land Disposals 0 0 0 (550) (725) (650) (680) (650) (3,255)
Sub-Total 25,502 (7,381) 18,121 9,716 18,121 0 31,592 (7,670) (2,150) (2,636) (2,714) 34,543
Page 72 of 86

Page 73

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30
APPENDIX II
Revised Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised
Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget
Adjustment 31-Dec-25
Report 2 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3
2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Tourism, Culture and Place
Perth City Improvements (PTF Phase 4) 0 0 0 3,642 0 0 0 0 3,642
City Greening 31 31 31 0 0 0 0 0 31
Perth & Kinross Lighting Action Plan 1,175 1,175 93 1,175 0 0 0 0 0 1,175
Low Carbon Transport & Active Travel Hub - Broxden EV Chargers 0 0 65 0 0 0 0 0 0 0
Adapt Your Property - Vacant Town & City Centre Space 390 390 390 300 300 0 0 0 990
Sub-Total 1,596 0 1,596 158 1,596 3,942 300 0 0 0 5,838
Commercial Property Investment Programme
Tourism, Culture and Place
Broxden Drainage Mitigation Works 17 17 21 17 0 0 0 0 0 17
Mercian Buildings, Shore Road, Perth 451 451 650 451 0 0 0 0 0 451
Crioch Business Centre, Crieff 316 316 77 316 0 0 0 0 0 316
Northfield Business Park 2,027 2,027 83 2,027 0 0 0 0 0 2,027
Northfield Business Park (Phase 2) 0 0 0 0 0 800 0 0 800
Northfield Business Park - Site 6 0 0 0 0 1,500 0 0 0 1,500
Plot 4 Kinross West 1,526 1,526 50 1,526 0 0 0 0 0 1,526
Welton Road SBU's, Blairgowrie 0 0 0 200 1,400 0 0 0 1,600
Burnside Street SBU's, Pitlochry 0 0 0 600 0 0 0 0 600
Depot SBU's, Blackford 0 0 0 0 0 0 200 1,400 1,600
SBU's, Inveralmond Road, Perth 0 0 0 900 0 0 0 0 900
Land at South Turfhills Depot, Kinross 0 0 0 0 0 1,100 0 0 1,100
Aldour Business Centre, Pitlochry 0 0 0 0 0 0 0 900 900
Borlich Business Centre, Aberfeldy 0 0 0 0 0 0 0 1,600 1,600
Aberfeldy SBU's 0 0 0 700 0 0 0 0 700
4,337 0 4,337 881 4,337 2,400 2,900 1,900 200 3,900 15,637
Prudential Borrowing Projects
Tourism, Culture and Place
Land Purchase & Development (Hotel Development) 0 0 0 950 950 0 0 0 1,900
Sub Total 0 0 0 0 0 950 950 0 0 0 1,900
TOTAL - ECONOMY, DEVLOPMENT & PLANNING 31,435 (7,381) 24,054 10,755 24,054 38,884 (3,520) (250) (2,436) 1,186 57,918
PROPERTY SERVICES
Project Support
Investment in the Learning Estate 1,900 1,900 1,060 1,900 2,506 6,823 0 0 0 11,229
Braco Primary School Upgrade 150 150 17 150 350 3,000 5,000 0 0 8,500
School Toilet Upgrade Programme 400 200 600 370 600 600 600 0 0 0 1,800
Methven Primary School Refurbishment 1,700 (1,000) 700 507 700 2,970 0 0 0 0 3,670
North/West Perth - New Primary School 341 341 341 7,672 15,400 0 0 0 23,413
Page 73 of 86

Page 74

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30
APPENDIX II
Revised Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised
Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget
Adjustment 31-Dec-25
Report 2 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3
2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Perth Academy - Refurbishment 1,476 145 1,621 1,097 1,621 49 0 0 0 0 1,670
Perth Grammar School - Upgrade Programme Phase 3 600 600 480 600 1,628 819 0 0 0 3,047
Perth High School - New School Investment 13,018 (1,300) 11,718 9,680 11,718 4,900 0 0 0 0 16,618
Pitlochry High School Extension (Pitlochry Leisure Review) 200 200 66 200 750 5,000 2,750 0 0 8,700
Harris Academy/Invergowrie 26 (26) 0 0 0 0 0 0 0 0
Blairgowrie Recreation Centre - Replacement 832 832 531 832 1,700 0 0 0 0 2,532
Technology Upgrades 250 250 4 250 483 519 0 0 0 1,252
Community School of Auchterarder (FSM) 0 0 0 250 750 2,511 0 0 3,511
Community Campus Access Adaptations 25 25 16 25 0 0 0 0 0 25
Roof Upgrade Programme 0 500 500 3 500 0 0 0 0 0 500
Sub-Total 20,918 (1,481) 19,437 13,831 19,437 23,858 32,911 10,261 0 0 86,467
Property Service Management
DDA Adaptation & Alteration Works Programme 353 (103) 250 112 250 303 200 0 0 0 753
Property Compliance Works Programme 609 609 405 609 650 400 0 0 0 1,659
Capital Improvement Projects Programme 1,866 1,866 846 1,866 1,800 894 10,000 7,700 11,000 33,260
Pitlochry High School - Upgrade Programme 20 20 7 20 0 0 0 0 0 20
Friarton Depot - Waste Transfer Station 2,300 2,300 51 2,300 221 0 0 0 0 2,521
Energy Efficiency Works - Various Properties 0 12 12 12 12 0 0 0 0 0 12
Revenue Contribution (Salix Reserve) 0 (12) (12) (12) 0 0 0 0 0 (12)
Letham Community Wellbeing Hub 338 338 323 338 0 0 0 0 0 338
PH2O 300 300 32 300 1,700 2,000 10,000 30,000 29,847 73,847
Bells Sport Centre 414 414 59 414 1,500 1,500 3,500 3,000 0 9,914
Kinross Community Campus Sports Facilities 0 0 0 900 5,000 1,000 0 0 6,900
Crieff Community Campus Sports Facilities 0 0 0 0 1,000 4,000 1,300 0 6,300
Crieff Drummond Arms - Regeneration 1,500 (750) 750 621 750 2,192 0 0 0 0 2,942
Perth Concert Hall 395 (195) 200 115 200 1,000 1,000 695 0 0 2,895
Perth Museum 113 113 15 113 0 0 0 0 0 113
Sub-Total 8,208 (1,048) 7,160 2,598 7,160 10,266 11,994 29,195 42,000 40,847 141,462
Prudential Borrowing Projects
Decarbonisation 178 178 31 178 350 0 0 0 0 528
Energy Conservation & Carbon Reduction Programme 189 189 147 189 150 150 150 150 150 939
Third Party Contribution (41) (41) (41) 0 0 0 0 0 (41)
Pullar House - Purchase & Re-Purposing 7,200 (200) 7,000 3,852 7,000 1,800 1,199 0 0 0 9,999
Sub-Total 7,526 (200) 7,326 4,030 7,326 2,300 1,349 150 150 150 11,425
TOTAL - PROPERTY SERVICES 36,652 (2,729) 33,923 20,459 33,923 36,424 46,254 39,606 42,150 40,997 239,354
CUSTOMER & DIGITAL SERVICES
ICT Infrastructure Replacement and Upgrade Programme 2,661 (582) 2,079 1,329 2,079 4,118 8,605 4,110 3,547 7,583 30,042
Data & Analytics 733 733 44 733 845 849 854 890 621 4,792
Page 74 of 86

Page 75

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30
APPENDIX II
Revised Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised
Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget
Adjustment 31-Dec-25
Report 2 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3
2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Third Party Contribution 0 0 0 0 0 0 0 0 0
Supporting Digital 937 (256) 681 54 681 1,037 989 1,122 1,153 992 5,974
Software Licences (Revenues & Benefits) 50 50 52 50 80 82 85 87 90 474
School Audio-Visual (AV) Equipment Replacement Programme 27 27 26 27 26 27 226 359 504 1,169
Mosaic - Swift Social Work System Replacement 659 659 169 659 197 497 0 0 0 1,353
Revenue Contribution (124) (124) (124) (124) (124) 0 0 0 (372)
Case Management System 80 80 80 80 0 0 0 0 0 80
TOTAL - CUSTOMER & DIGITAL SERVICES 5,023 (838) 4,185 1,754 4,185 6,179 10,925 6,397 6,036 9,790 43,512
HEALTH & SOCIAL CARE
Occupational Therapy Equipment 250 250 250 250 250 150 250 100 256 1,256
Technology Enabled Telecare 650 650 502 650 1,042 1,037 1,115 1,120 1,120 6,084
Software Licences 53 53 53 53 69 70 70 70 385
TOTAL - HEALTH & SOCIAL CARE 953 0 953 752 953 1,345 1,256 1,435 1,290 1,446 7,725
Unallocated Capital Resources 4,977 (234) 4,743 4,743 0 0 0 0 6,246 10,989
TOTAL COMPOSITE NET EXPENDITURE 134,945 (19,625) 115,320 60,934 115,320 129,256 80,732 68,989 65,558 78,518 538,373
(NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS)
CAPITAL INCOME & RECEIPTS
General Capital Grant - Scottish Government (11,374) (1,064) (12,438) (10,888) (12,438) (21,752) (12,750) (12,750) (12,750) (12,750) (85,190)
Developer Contributions (5,344) (5,344) (5,344) (2,600) (2,600) (2,500) (2,500) (2,000) (17,544)
General Fund - Capital Receipts/Disposal (570) 0 (570) (27) (570) 0 0 0 0 0 (570)
Commercial Property - Capital Receipts/Disposal (619) 0 (619) (226) (619) (235) (2,398) (2,530) (645) (800) (7,227)
Total: Capital Receipts (17,907) (1,064) (18,971) (11,141) (18,971) (24,587) (17,748) (17,780) (15,895) (15,550) (110,531)
Annual Composite Borrowing Requirement 117,038 (20,689) 96,349 49,793 96,349 104,669 62,984 51,209 49,663 62,968 427,842
CAPITAL RECEIPTS BROUGHT FORWARD (1,332) 0 (1,332) (1,332) (1,332) (2,614) (2,449) (3,947) (4,577) (5,022) (1,332)
CAPITAL RECEIPTS CARRIED FORWARD 2,614 0 2,614 677 2,614 2,449 3,947 4,577 5,022 1,922 1,922
TOTAL NET COMPOSITE BORROWING REQUIREMENT 118,320 (20,689) 97,631 49,138 97,631 104,504 64,482 51,839 50,108 59,868 428,432
Page 75 of 86

Page 76

Project Project Description
Traffic & Road Network
Road Safety Initiatives (20mph Zones etc.) A programme of works to improve road safety
Road Safety Initiatives - A94 Safety Improvements A programme of works to improve road safety on the A94
Active Travel Grant - Traffic & Road Safety Schemes A programme of works to improve active travel
20mph Signage Programme A programme of works to introduce 20mph speed limits.
Schools Road Safety Measures A programme of works to improve road safety in the vicinity of schools
Additional Road Safety - Pedestrian Crossings A programme of works to provide pedestrian crossing facilities
Traffic Signal Renewals - Upgrading A programme of works to upgrade existing traffic signal infrastructure
Investment in Local Footpaths A programme of works to improve and provide local footpaths
Car Parking Investment - Pitlochry Purchase of land and construction of a public car park
A977 Upgrades A programme of works to improve road safety along the A977.
Broich Road, Crieff - Road Realignment & Safety
Measures
Realignment of Broich Road, Burrell Street and Gallowhill Junction
Street Lighting Partnership
Street Lighting Replacement of existing street lighting lanterns, columns and cable network.
Roads Maintenance Partnership
Structural Maintenance Road maintenance to extend the life of roads, including predominately road
resurfacing, surface dressings, installing new drainage infrastructure and repairs
to and replacement of defective embankments and retaining walls
Footways Replacement of existing  deteriorated footway surfaces
Perth Flood Protection Scheme (South Inch Culvert
Reinstatement)
Ground investigation and monitoring then design project to refurbish existing
culvert
Road Safety Barriers Renewal of existing barriers where unrecoverable damage has occurred and
renewal of barriers where timber posts have been used in construction
Bridges
Bridge Refurbishment Programme Used to appoint specialist external inspection teams and consultants to carry out
specialist access bridge inspections and assessments
Old Perth Bridge - Strengthening Carry out works recommended by the 2018 Bridge Assessment study, including a
range of assessment, investigation, strengthening and improvement works
Perth Queens Bridge - Strengthening Carry out works recommended by the 2018 Bridge Assessment study, including a
range of assessment, investigation, strengthening and improvement works
Culteuchar Culvert Replace existing temporary steel bridge (on hire) with culvert
Garry Viaduct Replacement of Bearings and Parapets; including strengthening of deck for
bearing replacement jacking up, and to cater for increased parapet vehicular
deterrent capacity
Bolfrack River Retaining Wall Replacement of failed section of retaining wall supporting A827 adjacent to River
Tay
Bridge of Tilt Repairs to masonry bridge and installation of major scour mitigation measures
Corb Bridge Culvert, Kinross Installation of structural lining to dilapidated culvert
Blairgowrie Bridge Major scour mitigation scheme
Vehicular Bridge Parapets Programme - Assess &
Upgrade
Assessment and Upgrading of Vehicle Parapets Programme
Flooding
Comrie Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in Comrie
Milnathort Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in Milnathort
South Kinross Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in South
Kinross
Flood Mitigation Measures - Dunkeld and Craigie Burn Design and construction of schemes to reduce the risk of flooding in Dunkeld and
Craigie Burn
Investment in Surface Water Management Schemes -
Leaky Dam, Rattray Burn
Design and construction of a natural flood management measure (Leaky Dam) to
reduce the risk of flooding in Rattray
Coastal Change Adaptation Design and construct projects to deal with incidents of coastal erosion
Climate Change and Zero Waste
Climate Change Programme A programme of projects to meet the priorities to deliver the Top and High Priority
Projects in the Council's Climate Change Strategy and Action Plan. Proposed
projects will be scrutinised by the Council's Climate Change and Sustainabliltiy
Group
Nature Restoration Protection and restoration of biodiversity focusing on over-exploitation of the
natural environment and addressing its consequences; habitat loss and
fragmentation; and invasive non-native species.
ENVIRONMENT & INFRASTRUCTURE
Page 76 of 86

Page 77

Project Project Description
Prudential Borrowing Projects
Wheeled Bin Replacement Programme - Domestic Bins Replacement of damaged and end of life wheeled bins for households. Also
suppling bins for new properties
Wheeled Bin Replacement Programme - Commercial
Bins
Replacement of damaged and end of life wheeled bins for commercial customers.
Also suppling bins for new customers and changes to collection contracts
Recycling in Schools - Waste Bin Purchases This project will improve the recycling infrastrucuture in PKC learning
establishments and will improve positive behaviours with staff and pupils.
Recycling Containers, Oil Banks & Battery Banks
Replacement Programme
Replacement of damaged and end of life oil and battery banks
Litter Bins Replacement of damaged and end of life litter bins and/or for general supply of
litter bins where required.
Vehicle Replacement Programme Fleet vehicle replacement programme
Street Lighting Renewal - LED & Column Replacement Street Lighting LED conversion and column replacement programme
Community Greenspace
Community Greenspace Sites Main fund for all Community Greenspace Sites which is drawn down to support
the overall capital programme of refurbishments and upgrades
Play Areas and Parks Refurbishment of 'Settlement and Neighbourhood' classification parks working in
partnership with communities to improve, update and renew worn out or obsolete
infrastructure.  Small budget to facilitate refurbishment of former Premier Park
upgrades
3G Pitch, Blairgowrie Two phase community led project to provide a new full sized 3G football pitch and
pavilion
Countryside Sites Refurbishment of more natural parks and open spaces
Community Greenspace Bridges Refurbishment programme for all bridges on Community Greenspace sites
Core Path Implementation Holding budget for Crieff Comrie Core path development mainly funded through
Sustrans
Kinnoull Hill Complete
Cemetery Extensions Funding to allow the extension of existing or development of new cemeteries to
address the pressure for burial space
Improvements
New Gypsy Traveller Site Feasibility Study for Gypsy Traveller Transient Site
Parking, Public Transport Unit and Civil Contingencies
Community Transport Iniatives Purchase of vehicles and charging infrastructure for community
transport/resilience groups to use to deliver on unmet need in the local area.
Bus Infrastructure Fund Improving the infrastructure needed to operate buses
Community Learning and Development and Equalities
Community-Led Asset Transfers Financial assistance for community groups wishing to take on PKC assets using
the community asset transfer process
Prudential Borrowing Projects
Community Transport Vehicles Providing vehicles to community transport groups
Kinnoull Street Car Park - Purchase Purchase of Kinnoull Street Multi-Storey Car Park to increase Perth and Kinross
Council car parking capacity to support delivery of the Perth City Integrated
Investment Proposal
Roads Infrastructure
A9/A85 Road Junction Improvements (PTF Phase 1) New infrastructure including a new A9 overbridge, a bridge over the River Almond
and road linking the A85 to Inveralmond and Bertha Park (Phase 1 of Perth
Transport Futures Project)
Destiny Bridge and New Kingsway (PTF Phase 2) New road and major structure over the River Tay, linking the A9 north of
Inveralmond and the A94 north of Scone (Phase 2 of Perth Transport Futures
Project)
Bertha Park Link Road (PTF Phase 3) Phase 3 of Perth Transport Futures Project which is a new link road (1.4km)
running through Bertha Park, connecting Phases 1 and 2.
Perth Eco-Innovation Park at Perth West Provision of enabling infrastructure (access road, A9 underpass and unit
platforms) to develop 25ha of employment land supporting clean growth, business
innovation and jobs - Phase 1 (11ha).
Tourism, Culture and Place
Perth City Improvements (PTF Phase 4) Design and development of sustainable transport corridors to improve access to
and from Perth and enable additional development and improvement within Perth
city centre
HOUSING & COMMUNITIES
ECONOMY, DEVELOPMENT & PLANNING
Page 77 of 86

Page 78

Project Project Description
Perth City Centre Golden Route (Rail Station) Design and development of improvements to access, signage and animation from
rail and bus station to Perth city centre to complement improvements to
integration of transport
City Greening Improvements to support enhancement of retail trading environment and
residential areas and enhanced use of space for markets, events and alfresco use
Perth & Kinross Lighting Action Plan Architectural and creative lighting to enhance city and towns appearance, reduce
energy cost and increase safety at nighttime to increase dwell time, support the
hospitality sector, events and grow the evening economy
Low Carbon Transport & Active Travel Hub - Broxden EV
Chargers
Provision of fast EV chargers combined with solar power generation and battery
storage at Broxden Park & Ride - Near completion
Adapt Your Property - Vacant Town & City Centre Space Adapt Your Property supports capital adaptation works to empty and underused
commercial property in city & town centres, looking at adaptation to attract new
commercial, community or residential use.
Other Planning Projects
Local Full Fibre Network Provision of gigabit fibre connectivity to Council's buildings to unlock gigabit
connectivity for surrounding communities. Complete
Commercial Property Investment Programme Capital investment in economic development in serviced units and land
Prudential Borrowing Project
Land Purchase & Development (Hotel Development) This scheme involves the redevelopment of 1-5 High Street as serviced
apartments courtesy of a heritage grant funding award that includes disposal to a
developer subject to conclusion of a development agreement
Project Support
Investment in the Learning Estate Investment to upgrade the infrastructure and environment of our existing school
estate
Braco Primary School Upgrade Replacement school on adjacent land
School Toilet Upgrade Programme Major toilet upgrades in various schools
Methven Primary School Refurbishment Upgrade of Methven Primary School facilities including new dining and gym hall
North/West Perth - New Primary School New primary school located at Bertha Park
Riverside Primary New School Replacement of North Muirton and Balhousie primary schools
Perth Academy - Refurbishment Investment to upgrade the infrastructure and environment of the Perth Academy
including structural work to sports block, lighting upgrades, classroom upgrades
and science block cladding
Perth Grammar School - Upgrade Programme Phase 3 Investment to upgrade the infrastructure and environment of the Perth Grammar
School including structural work to assembly hall, AV and WiFi upgrades,
classroom refurbishment and door upgrades
Perth High School - New School Investment Replacement of the existing Perth High School
Pitlochry High School Extension (Pitlochry Leisure
Review)
Creation of community campus including sports facilities including 4 court sports
hall and associated works
Harris Academy/Invergowrie - Extension Extension and reconfiguration of existing space at Harris Academy in Dundee for
continuation of access for pupils based in Invergowrie
Blairgowrie Recreation Centre - Replacement Replacement of the Recreation Centre in Blairgowrie
Technology Upgrades Upgrade to practical teaching environment within the existing school estate
Community School of Auchterarder (FSM) Upgrading kitchen and dining facilities to provide the enhanced Free School
Meals programme
Community Campus Access Adaptations To support adaptations in schools and community campuses to help facilitate
increased community access
Property Service Management
DDA Adaptation & Alteration Works Programme To provide unhindered accessibility to all Council Buildings - e.g.
Ramps/Lifts/Door Access/Accessible Toilets and Changing Areas
Property Compliance Works Programme To ensure compliance with current and changing legislation including - New Fire
Alarms; Lighting; Wiring; Fire Protection Works; Gas pipework within buildings
and Roof Restraint safety systems
Capital Improvement Projects Programme Roof Upgrades; Full internal refurbishment works; New Heating Systems; Boilers
and pipework; Structural Upgrades; Small extensions; New Windows/Doors; New
Fencing; New Cladding
Pitlochry High School - Upgrade Programme Upgrades to Mechanical and Electrical Infrastructure, including rewiring, heating
and controls systems, replacement lighting and consequential building works such
as new ceilings, painting and flooring
Friarton Depot - Waste Transfer Station This project aims to refurbish the main waste transfer station building to provide a
safe environment for workers. The project will involve a complete re-cladding of
the existing structure, new doors and new services installation. Some initial
enabling work are being carried out currently.
PROPERTY SERVICES
Page 78 of 86

Page 79

Project Project Description
Energy Efficiency Works - Various Properties Focusing on a spend to save with projects aiming to reduce energy cost across
the property estate
Letham Community Wellbeing Hub Complete
PH2O Replacement of Perth Leisure Pool and Dewars Ice Rink.
Bells Sport Centre Development of Bells' as an unheated, covered sports pitch and events space
Kinross Community Campus Sports Facilities Improvements to the building fabric and energy efficiency of Live Active Loch
Leven
Crieff Community Campus Sports Facilities Improvements to the building fabric and energy efficiency of Strathearn
Community Campus Leisure Facilities
Crieff Drummond Arms - Regeneration Demolition of former hotel, regeneration of site for housing use
Perth Museum Redevelopment of former Perth City Hall to New Perth Museum
Prudential Borrowing Projects
Decarbonisation This budget will support PKCs path to NetZero and focus primarily on the de-
carbonisation of heat and replacing inefficient direct emissions heat sources
Energy Conservation & Carbon Reduction Programme This budget is focused on works to reduce PKC energy consumption and help
achieve annual KPI energy reduction of 3%
Pullar House - Purchase & Re-Purposing Purchase and development of Pullar House to create a shared Public Sector Hub
Customer & Digital Services
ICT Infrastructure & Replacement and Upgrade
Programme
This Programme delivers the IT / digital environment, digital resources and
systems required by staff and young people. The programme maintains, supports
and develops computers; networks; telephony; Microsoft systems; connectivity
and equipment; datacentres; servers; file storage and back up; security systems
and video conferencing
Data & Analytics Delivers the governance, tools, technologies and organisation-wide skills required
for optimising value from Council data, driving informed decision making around
resources, priorities and service delivery targets
Supporting Digital Develops the capabilities we need to be an innovative digital organisation. 
Including developing the Council’s corporate employee (mobile working) and
customer (online services) platforms, to create new digital products and services;
investment in tools such as Microsoft; resourcing innovation and building digital
skills, insight and expertise
Software Licences (Revenues & Benefits) NAC Live system licensing for Revenues & Benefits team
School Audio-Visual (AV) Equipment Replacement
Programme
Ensures all Perth and Kinross classrooms have equitable access to audio visual
panels and the digital skills to exploit these resources for learning and teaching
Mosaic - Swift Social Work System Replacement Purchase and Development of a new Social Work system to replace SWIFT
Hardware Funding of additional or bespoke IT Hardware for Communities Staff
Licenses Funding of software contracts
Case Management System New system for management of client cases
Occupational Therapy Equipment Supply and install of occupational therapy equipment following referral from
heakth and social care professionals.
Technology Enabled Telecare Replacement of existing analogue Community Alarm devices to digital alarm units
prior to UK switch-off of analogue network, as well as ongoing rolling replacement
programme.
Moving & Handling Office Refurbishment Relocate staff base, currently under review
Software Licences Various licences for essential social care systems
Developing Supported Tenancies Contribution towards flagship core and cluster facility for adults with learning
disabilities’
HEALTH & SOCIAL CARE
Page 79 of 86

Page 80

Page 80 of 86

Page 81

APPENDIX III
Approved Proposed Revised Actual Projected Revised Revised Revised Revised Revised
Budget Budget Budget to Outturn Budget Budget Budget Budget Budget
Report 2 Adjustment 31-Dec-25
Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3
2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 TOTAL
£'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000
Council House New Build Programme
Beechgrove, Perth 49 62 111 239 111 0 0 0 0 111   
Council Tax (Second Income) 0 0 0 0 0 0 0 0   
Scottish Government Subsidy 0 0 0 0 0 0 0 0
49 62 111 239 111 0 0 0 0 111
Balhousie, Perth 150 38 188 205 188 0 0 0 0 188   
Council Tax (Second Income) 0 0 0 0 0 0 0 0   
Scottish Government Subsidy 0 0 0 0 0 0 0 0
150 38 188 205 188 0 0 0 0 188
Kinloch Gardens, Rattray (20 units) 1,417 1,417 1,417 1,417 0 0 0 0 1,417   
Council Tax (Second Income) (400) (400) (400) (400) 0 0 0 0 (400)
Scottish Government Subsidy 0 0 0 0 0 0 0 0
1,017 0 1,017 1,017 1,017 0 0 0 0 1,017
Kinloch Brae, Blairgowrie (4 units) 783 783 783 0 0 0 0 783   
Council Tax (Second Income) (80) (80) (80) 0 0 0 0 (80)
Scottish Government Subsidy (404) (404) (404) 0 0 0 0 (404)
Communted sums 0 0 0 0 0 0 0 0
299 0 299 0 299 0 0 0 0 299
Broich Road, Crieff (12 units) 2,716 2,716 2,716 0 0 0 0 2,716   
Council Tax (Second Income) (240) (240) (240) 0 0 0 0 (240)
Scottish Government Subsidy (1,242) (1,242) (1,242) 0 0 0 0 (1,242)
1,234 0 1,234 0 1,234 0 0 0 0 1,234
Future Developments 3,650 (100) 3,550 3,550 5,500 5,596 4,725 4,423 23,794   
Council Tax (Second Income) 0 0 0 0 0 0 0 0   
Scottish Government Subsidy 0 0 0 0 0 0 0 0
3,650 (100) 3,550 0 3,550 5,500 5,596 4,725 4,423 23,794
Total Council House New Build 6,399 0 6,399 1,461 6,399 5,500 5,596 4,725 4,423 26,643
Increase in Council House Stock
Council House Buy-Backs 15,810 15,810 11,994 15,810 1,310 1,305 1,305 1,305 21,035   
Scottish Government Subsidy (2,450) (2,450) (2,450) (2,450) 0 0 0 0 (2,450)
13,360 0 13,360 9,544 13,360 1,310 1,305 1,305 1,305 18,585
National Trust Scotland (NTS), Dunkeld
Purchase of properties (20 units) 966 966 434 966 0 0 0 0 966   
Council Tax (Second Income) 0 0 0 0 0 0 0 0   
Scottish Government Subsidy 0 0 0 0 0 0 0 0
966 0 966 434 966 0 0 0 0 966
Total Increase in Council House stock 14,326 0 14,326 9,978 14,326 1,310 1,305 1,305 1,305 19,551
Standard Delivery Plan
Heating Upgrade Contract Works 1,492 1,492 701 1,492 811 0 0 0 2,303
Rewiring, Infrastructure & Property Refurbishment 1,339 1,339 1,165 1,339 0 0 0 0 1,339
Triple Glazing 4,025 4,025 1,644 4,025 4,025 0 0 0 8,050
Controlled Door Entry 56 56 44 56 0 0 0 0 56 
- less Third Party Contribution (7) (7) (7) 0 0 0 0 (7)
Kitchen Modernisation Programme 2,242 2,242 1,181 2,242 0 0 0 0 2,242
Bathroom Modernisation Programme 1,000 1,000 846 1,000 0 0 0 0 1,000
Adaptations (OT) 637 637 283 637 0 0 0 0 637
External Fabric 1,735 365 2,100 1,557 2,100 1,744 863 0 0 4,707 
- less Third Party Contribution (69) (69) (20) (69) 0 0 0 0 (69)
HRA CAPITAL INVESTMENT PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2025/26 to 2029/30
PERTH AND KINROSS COUNCIL
6
Page 81 of 86

Page 82

APPENDIX III
Approved Proposed Revised Actual Projected Revised Revised Revised Revised Revised
Budget Budget Budget to Outturn Budget Budget Budget Budget Budget
Report 2 Adjustment 31-Dec-25
Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3
2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 TOTAL
£'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000
Energy Efficiency 691 33 724 599 724 0 0 0 0 724 
- less Scottish Government Grant 0 (33) (33) (33) 0 0 0 0 (33)
Multi Storey Flats 1,754 2,544 4,298 2,045 4,298 2,273 0 0 0 6,571 
- less Third Party Contribution 0 0 0 (481) 0 0 0 (481)
- less Scottish Government Grant 0 (67) (67) (67) 0 0 0 0 (67)
Environmental Improvements 959 959 720 959 973 973 973 0 3,878
Fire Precaution Measures 388 388 18 388 1,000 735 0 0 2,123
Fire Alarm Replacement Programme 84 84 84 166 0 0 0 250
Sound Insulation 408 408 10 408 0 0 0 0 408
Structural Improvements 1,233 1,233 1,233 0 0 0 0 1,233
Retrofit Works 162 162 152 162 0 0 0 0 162
SHQS Future Developments 0 0 0 0 0 0 0 0
Total Standard Delivery Plan 18,129 2,842 20,971 10,945 20,971 10,511 2,571 973 0 35,026
Other Investment in Council House Stock
Total Major Adaptations to Council House Stock 270 270 168 270 0 0 0 0 270
Rannoch Road, Perth - Housing Regeneration 85 85 76 85 0 0 0 0 85
149-151 Dunkeld Road, Perth 2 2 1 2 0 0 0 0 2
St.Catherine's Square Redevelopment 500 500 36 500 0 2,808 0 0 3,308
Lock-ups and Garage Sites 50 50 50 0 0 0 0 50
Shops & Offices 289 (20) 269 269 0 0 0 0 269
Greyfriars and Satellite Sites 73 73 73 0 0 0 0 73
Double Dykes Chalet Replacement 3,131 1,684 4,815 3,643 4,815 0 0 0 0 4,815 
- Scottish Government Grant (1,709) 19 (1,690) (1,690) (1,690) 0 0 0 0 (1,690)
General Capital Works 56 56 48 56 0 0 0 0 56
Upgrade and Replacements to Lifts Programme 201 32 233 6 233 0 0 0 0 233
ICT Expenditure 162 162 114 162 0 0 0 0 162
Mortgage to Rent 249 249 121 249 0 0 0 0 249 
- less Government Grant (75) (75) (75) (75) 0 0 0 0 (75)
Total Other Investment in Council House Stock 3,284 1,715 4,999 2,448 4,999 0 2,808 0 0 7,807
Total Net Expenditure 42,138 4,557 46,695 24,832 46,695 17,321 12,280 7,003 5,728 89,027
Income
CAPITAL RECEIPTS 0 0 (18) 0 0 0 0 0 0
CFCR (1,684) (1,684) (1,684) (1,546) (1,613) (2,013) (2,385) (9,241)
TOTAL BORROWING REQUIREMENT 40,454 4,557 45,011 24,814 45,011 15,775 10,667 4,990 3,343 79,786
Page 82 of 86

Page 83

SIGNIFICANT CAPITAL PROJECTS
PROGRESS UPDATE
APPENDIX IV
Project Title Total
Gross
Budget
Third Party
Funding
(£'000)
Total Net
Budget
(£'000)
Projected
Outturn
(£'000)
Completion Date Contract
Awarded
On
Site
Status Change Since
Last Report
Additional Commentary
Blairgowrie Recreation
Centre - Replacement 36,000 0 36,000 36,000
Opening August 2025
Phase 2 Completion
Date TBC
Yes Yes On track No Practical completion of Phase 1 achieved on 11/08/25. Phase 2 works delayed completion date
tbc.
North/West Perth New
Primary School* 24,000 0 24,000 24,000 Summer 2028 No No On track No Project restarted, design to meet in November to review scope and Stage 1 report issued prior
to the projetc being paused.
Perth High School - New
School Investment 80,200 0 80,200 80,200 School opening as
planned August 2025 Yes Yes On track No School opened August 2025, phase 2 underway.
Bertha Park Link Road 16,322 1,064 15,258 15,258 December 2026 Yes Yes On track Yes - on site
Construction work continues and is progressing well. Pavement works have now commenced.
The works remain ahead of programme and it is hoped that they will be substantially completed
by the end of the summer in 2026.
Comrie Flood Protection
Scheme 40,353 32,657 7,696 7,696 Autumn 2026 Yes Yes On track No Main construction works commenced in March 2025. Project on budget and programmed for
completion in October 2026.
Perth Eco Innovation Park* 32,817 17,711 15,106 15,106 Not currently
programmed No No
Design package
awarded - design
programme on track
Yes
[See previous reports in relation to funding.]
Outline Design works generally progressing on programme with a completion date of July 2026.
Ground investigation works are currently on site and nearing completion.  S42 application to
vary conditions being prepared. Marketing brochure for business park finalised. Liaison
continues with JDLT. High level programme updated for inclusion in upcoming report for Council
meeting on 4 March 2026.
PH2O 73,847 0 73,847 73,847 Not currently
programmed No No
Thimblerow approved
as new site for PH2O
project, including
leisure water, at
Council on 18 June
2025.
Yes
Programme under development, procurement of main contractor and design team has
commenced via hubco, - design will then commence based on June 2025 approved brief. As
instructed by Council on 18 June 2025 a PKC contract strategy has now been approved with
Hub East Central Scotland the preferred procurement route. A main contractor selection
process has been completed and Robertson Construction have been selected as the main
contractor to deliver the design and build phase of the PH20 project at Thimblerow.
Bells Sport Centre 10,000 0 10,000 10,000 Not currently
programmed No No Approved 18 June
2025 Yes Early stages of development, Contractor appointed for intrusive surveys , removal of RAAC and
asbestos, feasibility of Counil vision will be informed by surveys and strip out.
Kinross Community
Campus Sports Facilities 6,900 0 6,900 6,900 Not currently
programmed No No Approved 18 June
2025 Yes Early stages of development, will be updated in future reports
Crieff Community Campus
Sports Facilities 6,300 0 6,300 6,300 Not currently
programmed No No Approved 18 June
2025 Yes Early stages of development, will be updated in future reports
Crieff Drummond Arms -
Regenertaion 3,000 0 3,000 3,000
DBN Works due to be
completed October
2025; LBC still to be
achieved  Yes Yes
DBN Works due to be
completed October
2025; LBC still to be
achieved - demolition
of the remainder of the
building outstanding
yes 20/01/2025 Demolition split into two parts. 1st part are all works listed within the Dangerous
Building Notice (DBN) was completed November 2025. The site has been made secure and
remains in the possession of Beatties demolition who are carrying out weekly inspections. For
remainder of the demolition listed building consent (LBC) is required. The Design Team are in
the process of responding to HES Objection letter which asks PKC to investigate facade
retension options. 
Multi Storey Flats - Energy
Efficiency Works (HRA) 7,060 548 6,512 6,512
Phase 1 - Pomarium
Blocks 7-51 & 52-95
Completion July 2026.
Phase 2a - Market,
Milne and Lickley Court
Lifts December 2026,
Phase 2b Market, Milne
and Lickley Court EWI
works May 2027 and 1-
48 Potterhill Flats June
2028.
Yes Yes Pomarium blocks on
site currently.
n/a
Phase 1 Pomarium Contract Works to two blocks on site until July 2026. £5.7m Contract Sum.
Works commenced on 14th July 2025. Block 1 is 7-51 includes, 45 flats (8 storey tower block).
Block 52-95 includes 44 flats (11 storey tower block). Scottish Government HEEPS ABS
funding awarded July 2025 for Private Owners (applied for in May) and Private Owners are
share of cost are included in the Third Party Funding. Phase 2a MML Lift replacements
Contract is £1.1m is signed/approved, Lifts in Manufacture on site February 2026. Income is
£340k from Private Owners in blocks. Phase 2b for EWI/Roofing works (105 flats) is planned for
commencement on site July 2026 (grant funding application is to be made in May 2026 as per
Pomarium). Potterhill Flats (48 flats) planned for July 2027 commencement. Budget shown for
all six blocks.
* Third Party Funding excludes Developer Contributions and receipts to be received in future years beyond the current 6-year programme.
6
Page 83 of 86

Page 84

Page 84 of 86

Page 85

CAPITAL BUDGET FINANCIAL RISKS APPENDIX V
1 Inflation Whilst inflation has reduced from the previous highs, there is evidence that
inflation may be starting to increase again. Many projects are also subject to
construction inflation affecting labour rates and materials costs, which may differ
from general retail inflation.
2 Interest Rates Higher interest rates mean that borrowing is more expensive, and therefore the
Council can afford to borrow less. If interest rates are higher than the
budgeted/estimated rates over the period of the budget, this means some capital
expenditure funded by borrowing may need to be reviewed.
3 Staff Capacity The ability of Services to deliver the Council’s approved plans may be limited to
the availability of appropriately qualified and experienced staff and their capacity
to deliver the projects in the budgeted timescales. Staff turnover and delays in
recruitment may lead to delays in delivering projects.
4 Changing priorities /
regulations
Changing regulations can affect projects, for example building regulations and
new climate change requirements may require construction projects to be
reviewed and modified to meet the new regulations. This may lead to delays and
increased costs. Also, changes to the local demographics may mean the
Council’s priorities change over time, particularly when considering the Capital
Budget over several years into the future.
5 Capital Grant The Scottish Government Capital Grant allocations are made on an annual basis,
and therefore subsequent years estimates cannot be guaranteed.
6 Developer
Contributions
Developer Contributions are payable into future years, usually in line with house
building rates, and act as a contribution towards infrastructure already delivered
and expensed. These contributions therefore reduce the need for borrowing in
future, with completed infrastructure costs already incurred. There is a risk that
developer plans do not progress as anticipated and this can result in contributions
not materialising. The Developer Contributions income budget is currently
£18.608 million.
7 Compensation
Claims
The cost of completed capital projects can increase in future if claims for
compensation are received from contractors or other persons if land is purchased
or disturbed for projects. Whilst large capital projects include a degree of
contingency, the amounts potentially awarded for compensation can far exceed
this contingency and are not budgeted for.