SIGNIFICANT CAPITAL PROJECTS
PROGRESS UPDATE
APPENDIX IV
Project Title Total
Gross
Budget
Third Party
Funding
(£'000)
Total Net
Budget
(£'000)
Projected
Outturn
(£'000)
Completion Date Contract
Awarded
On
Site
Status Change Since
Last Report
Additional Commentary
Blairgowrie Recreation
Centre - Replacement 36,000 0 36,000 36,000
Opening August 2025
Phase 2 Completion
Date TBC
Yes Yes On track No Practical completion of Phase 1 achieved on 11/08/25. Phase 2 works delayed completion date
tbc.
North/West Perth New
Primary School* 24,000 0 24,000 24,000 Summer 2028 No No On track No Project restarted, design to meet in November to review scope and Stage 1 report issued prior
to the projetc being paused.
Perth High School - New
School Investment 80,200 0 80,200 80,200 School opening as
planned August 2025 Yes Yes On track No School opened August 2025, phase 2 underway.
Bertha Park Link Road 16,322 1,064 15,258 15,258 December 2026 Yes Yes On track Yes - on site
Construction work continues and is progressing well. Pavement works have now commenced.
The works remain ahead of programme and it is hoped that they will be substantially completed
by the end of the summer in 2026.
Comrie Flood Protection
Scheme 40,353 32,657 7,696 7,696 Autumn 2026 Yes Yes On track No Main construction works commenced in March 2025. Project on budget and programmed for
completion in October 2026.
Perth Eco Innovation Park* 32,817 17,711 15,106 15,106 Not currently
programmed No No
Design package
awarded - design
programme on track
Yes
[See previous reports in relation to funding.]
Outline Design works generally progressing on programme with a completion date of July 2026.
Ground investigation works are currently on site and nearing completion.  S42 application to
vary conditions being prepared. Marketing brochure for business park finalised. Liaison
continues with JDLT. High level programme updated for inclusion in upcoming report for Council
meeting on 4 March 2026.
PH2O 73,847 0 73,847 73,847 Not currently
programmed No No
Thimblerow approved
as new site for PH2O
project, including
leisure water, at
Council on 18 June
2025.
Yes
Programme under development, procurement of main contractor and design team has
commenced via hubco, - design will then commence based on June 2025 approved brief. As
instructed by Council on 18 June 2025 a PKC contract strategy has now been approved with
Hub East Central Scotland the preferred procurement route. A main contractor selection
process has been completed and Robertson Construction have been selected as the main
contractor to deliver the design and build phase of the PH20 project at Thimblerow.
Bells Sport Centre 10,000 0 10,000 10,000 Not currently
programmed No No Approved 18 June
2025 Yes Early stages of development, Contractor appointed for intrusive surveys , removal of RAAC and
asbestos, feasibility of Counil vision will be informed by surveys and strip out.
Kinross Community
Campus Sports Facilities 6,900 0 6,900 6,900 Not currently
programmed No No Approved 18 June
2025 Yes Early stages of development, will be updated in future reports
Crieff Community Campus
Sports Facilities 6,300 0 6,300 6,300 Not currently
programmed No No Approved 18 June
2025 Yes Early stages of development, will be updated in future reports
Crieff Drummond Arms -
Regenertaion 3,000 0 3,000 3,000
DBN Works due to be
completed October
2025; LBC still to be
achieved  Yes Yes
DBN Works due to be
completed October
2025; LBC still to be
achieved - demolition
of the remainder of the
building outstanding
yes 20/01/2025 Demolition split into two parts. 1st part are all works listed within the Dangerous
Building Notice (DBN) was completed November 2025. The site has been made secure and
remains in the possession of Beatties demolition who are carrying out weekly inspections. For
remainder of the demolition listed building consent (LBC) is required. The Design Team are in
the process of responding to HES Objection letter which asks PKC to investigate facade
retension options. 
Multi Storey Flats - Energy
Efficiency Works (HRA) 7,060 548 6,512 6,512
Phase 1 - Pomarium
Blocks 7-51 & 52-95
Completion July 2026.
Phase 2a - Market,
Milne and Lickley Court
Lifts December 2026,
Phase 2b Market, Milne
and Lickley Court EWI
works May 2027 and 1-
48 Potterhill Flats June
2028.
Yes Yes Pomarium blocks on
site currently.
n/a
Phase 1 Pomarium Contract Works to two blocks on site until July 2026. £5.7m Contract Sum.
Works commenced on 14th July 2025. Block 1 is 7-51 includes, 45 flats (8 storey tower block).
Block 52-95 includes 44 flats (11 storey tower block). Scottish Government HEEPS ABS
funding awarded July 2025 for Private Owners (applied for in May) and Private Owners are
share of cost are included in the Third Party Funding. Phase 2a MML Lift replacements
Contract is £1.1m is signed/approved, Lifts in Manufacture on site February 2026. Income is
£340k from Private Owners in blocks. Phase 2b for EWI/Roofing works (105 flats) is planned for
commencement on site July 2026 (grant funding application is to be made in May 2026 as per
Pomarium). Potterhill Flats (48 flats) planned for July 2027 commencement. Budget shown for
all six blocks.
* Third Party Funding excludes Developer Contributions and receipts to be received in future years beyond the current 6-year programme.