Composite Capital Budget 2025/31 and Housing Investment Programme 2025/30 - Monitoring Report No. 3

Perth and Kinross Council · 4 February 2026
Back to Finance and Resources Committee — 4 February 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Our vision is a Perth and Kinross where everyone can live life
well, free from poverty and inequality
___________________________________________________________________
Committee: Finance and Resources Committee
Date of Meeting: 4 February 2026
Report Title: Composite Capital Budget 2025/31 and Housing
Investment Programme 2025/30 – Monitoring Report
No.3
Report Number: 26/37
Report Author: John Jennings, Senior Accountant
James Salisbury, Senior Accountant
Organisational Lead: Scott Walker, Chief Finance Officer
___________________________________________________________________
1. Purpose
1.1 This report provides a summary position to date for the 6-year Composite
Capital Budget for 2025/26 to 2030/31 and the 5-year Housing Investment
Programme for 2025/26 to 2029/30 and seeks approval for adjustments to the
programmes.
1.2 Sections
1. Purpose
2. Recommendations
3. Background
4. Composite Capital Programme – Gross Capital Resources
5. Composite Capital Programme – Expenditure
6. Housing Investment Programme
7. Budget Overview
8. Financial Risks
9. Impact and Value Assessment
10. Appendices
2. Recommendations
It is recommended that the Committee:
2.1 notes the contents of the report.
2.2 approves the proposed adjustments to the six-year Composite Capital Budget
2025/26 to 2030/31 set out in Sections 4 and 5 of the report and summarised
in Appendices I and II.

Page 2

2.3 approves the proposed adjustments to the Housing Investment Programme
Budget 2025/26 to 2029/30 set out in Section 6 of the report and summarised
in Appendix III.
2.4 notes progress with the delivery of major Capital projects as summarised in
Appendix IV.
3. Background
3.1 The Finance and Resources Committee approved an updated six-year gross
Composite Capital Budget for 2025/26 to 2030/31 totalling £560.047 million
and a five-year gross Housing Investment Programme for 2025/26 to 2029/30
totalling £89.027 million at its meeting on 26 November 2025 (report 25/327
refers).
3.2 This monitoring report advises on current year expenditure to 31 December
2025, and the latest estimate of the projected outturn for each of the years to
2030/31 for the Composite Programme and 2029/30 for the Housing
Investment Programme.
4. Composite Capital Programme – Gross Capital Resources
4.1 The current estimated total gross capital resources (which includes
movements in Capital Receipts, Capital Grants, Contributions and borrowing)
available over the six years 2025/26 to 2030/31 amount to £561.986 million.
Movements from the revised Composite Capital Budget approved on 26
November 2025 for these six years are summarised in the table below, and
the constituent elements for each year are shown in Appendix I.
Total Gross Composite Capital Resources
Approved
26 Nov 2025
Current
Estimate
Movement
£M £M £M
2025/26 137.062 118.327 (18.735)
2026/27 112.742 133.279 20.537
2027/28 88.212 88.795 0.583
2028/29 71.157 71.470 0.313
2029/30 70.245 68.533 (1.712)
2030/31 80.629 81.582 0.953
Total 560.047 561.986 1.939
4.2 The movement in the total Gross Resources for the 6 years 2025/26 to
2030/31 shown at Section 4.1 above can be summarised as follows:
£’000
Increase in Scottish Government Capital Grants (Section 4.3) 1.593
Reduction in Ring Fenced Capital Receipts (Section 4.4) (0.221)
Increase in Third Party and Revenue Contributions (Section 4.5 and 4.6) 1.132
Reduction in Borrowing (Section 4.7 and 4.8) (0.565)
Total Increase in Gross Capital Resources (Section 4.1) 1.939
4.3 On the 26 November 2025 the Scottish Government announced £1 million of
Capital Grant towards the Scott Street fire. As the work associated with the

Page 3

fire is in the Revenue Budget, it is proposed to reflect the funding in the
Revenue Budget by adjusting the General Fund Contribution to the Capital
Fund, as outlined in the Revenue Monitoring report being considered by this
Committee at today’s meeting. The Council has also been allocated £530,000
from the Road Safety Improvement Fund in 2025/26 (Section 5.2.2), less an
adjustment of a £1,000 reduction in the Road Safety Initiative Grant on
completion of the previous programme of works. In addition, the Scottish
Government announced the allocation of Housing First Capital Grant funding
for 2025/26, with this Council being allocated £63,742. This has been added
to Unallocated Capital Resources in 2025/26 pending proposals being
brought forward.
4.4 The only movement in Capital Receipts is a reduction of £226,000 in
estimated Ring-Fenced Receipts in relation to the Vehicle Replacement
Programme, offset by an increase of £5,000 in Waste Recycling disposals
(Section 5.2.6).
4.5 There is an increase of £1.120 million in Third Party Contributions relating to
the following programmes:
 Active Travel - £1.050 million (Section 5.2.2)
 Core Paths - £73,000 (Section 5.3.2)
 Kinnoull Hill - £16,000 (Section 5.3.2)
 Less £19,000 (Section 5.2.3) reduction for Structural Maintenance
4.6 There is also an increase of £12,000 in Revenue Contributions for Energy
Efficiency works from the Salix Reserve (Section 5.5.3).
4.7 The projected borrowing requirement in 2025/26, which is effectively the
balancing item for resources, is £97.631 million. This is £20.689 million
lower than the amount approved by this Committee on 26 November 2025
(£118.320 million).
4.8 The total borrowing requirement in the subsequent years 2026/27 to 2030/31
has increased by £20.124 million to £330.801 million, resulting in an overall
reduction in the level of borrowing across the whole 6-year programme of
£0.565 million. This movements in borrowing is summarised as follows:
2025/26 2026/27 2027/28 Later
Years
Total
£m £m £m £m £m
(Increase) in Scottish Government
Grant (Section 4.3).
(1.000) 0.000 0 0 (1.000)
Increase/(Reduction) in Environment
& Infrastructure Prudential
Borrowing (Section 5.2.6)
(0.525) 0.960 0 0 0.435
Movements arising from re-phasing
of expenditure and receipts
(Appendix II)
(19.164) 19.027 0.583 (0.446) 0
Increase/(Reduction) in
Borrowing Requirement
(20.689) 19.987 0.583 (0.446) (0.565)

Page 4

4.9 The chart below shows the Capital Resources required to fund the 2025/26
Composite Capital Programme following the proposed budget adjustments
detailed in this report.
83%
10%
0%5% 2%0%Projected Capital Resources 2025/26
(February 2026)
Borrowing (£97.631M)
Grants (£12.968M)
Tay City Deal (£0.000M)
Developer Contributions (£5.344M)
Third Party & Revenue Contributions (£1.920M)
Receipts (£0.464M)
£Million
5. Composite Capital Programme – Expenditure
5.1 Total Expenditure and Proposed Budget Adjustments to the Current
Programme
5.1.1 Total expenditure (net of grants and contributions) to 31 December 2025 on
the Composite Capital Programme is detailed in Appendix II and summarised
as follows:
Projected
Outturn
(£m)
Net
Expenditure to
31 Dec 2025
(£m)
% of
Projected
Outturn
Environment and Infrastructure 41.504 25.681 62%
Housing and Communities 5.958 1.533 26%
Economy, Development and Planning 24.054 10.755 45%
Property Services 33.923 20.459 60%
Customer and Digital Services 4.185 1.754 42%
Health and Social Care 0.953 0.752 79%
Unallocated 4.743 0.000 0%
Total Net Capital Expenditure 115.320 60.934 53%
5.1.2 Appendix IV includes updates on the progress of delivering the Council’s
major Capital projects.

Page 5

5.2 Environment and Infrastructure
5.2.1 The Strategic Lead has reviewed the programme for Environment and
Infrastructure and proposes various budget adjustments, the most significant
of which are described below.
5.2.2 Within Traffic and Road Network, £530,000 has been received from the Road
Safety Improvement Fund which has resulted in a corresponding increase in
the expenditure budget for Road Safety Initiatives. This funding has to be
used by 31 March and has therefore taken priority, with a consequential
movement of £186,000 from the current year to next on the core programme.
Similarly, within Active Travel Grant, £1.050 million has been received with
an expenditure deadline of 31 March, with a consequential movement of
£210,000 into 2026/27.
5.2.3 Within the Roads Maintenance Partnership, there has been a reduction in
Third-Party Contributions of £19,000 relating to the Scottish Water works at
Tay Street within Structural Maintenance, with a resulting reduction in the
expenditure budget. Works at the South Inch Culvert have completed, and it is
proposed the remaining budget of £195,000 is returned to Structural
Maintenance.  Lastly, in line with the estimated works due for completion
within Structural Maintenance for the remainder of the financial year, it is
proposed £904,000 is moved into 2026/27.
5.2.4 Within Structures, the following budget adjustments are proposed:
Project 25/26
£m
26/27
£m
Future
Years
£m
Virement
£m
Description
Bridge
Refurbishment
Programme
(0.105) 0.165 - (0.052) The budget required for the
remainder of the year has been
reviewed and it is proposed
£165,000 is slipped to 2026/27. Of
this £52,000 relates to the Corb
Bridge virement from below, and
£8,000 of other smaller
movements.
Corb Bridge
Culvert,
Kinross
(0.052) - - 0.052 Works completed, virement to
return underspend to Bridge
Refurbishment Programme.
Garry Viaduct - (0.127) 0.127 - Rephasing in line with the
programme of works received from
the contractor with initial works
continuing in 2026/27 and main
works commencing in 2027/28.
Bridge of Tilt (0.965) 0.965 - - River levels are currently high, and
with a SEPA restriction on
construction work in rivers during
winter months, scour works cannot
progress within the previously
anticipated timescales with the
budget slipped accordingly.

Page 6

5.2.5 Within Flooding, the following budget adjustments are proposed:
2025/26
£m
2026/27
£m
Description
Comrie Flood Protection Scheme (5.263) 5.263 There is slight slippage on the
overall programme of
approximately three weeks
resulting in a requirement to slip
some of the construction cost
into 2026/27. Additionally, the
remainder of the contingency
budget in the current year is not
anticipated to be spent this year
and this too requires rephasing
into 2026/27.
South Kinross Flood Protection
Scheme
(0.221) 0.221 Expenditure incurred during the
current year is limited to survey
work. Following two valid
objections to the scheme an
initial Local Authority Hearing
took place in October 2025. The
hearing will reconvene in
February 2026. It is proposed an
additional £221,000 is rephased
to 2026/27 due to this delay.
Coastal Change Adaptation (0.059) 0.059 Works are not due to take place
in the current financial year and
are planned for 2026/27. It is
proposed this budget is therefore
rephased into 2026/27.
5.2.6 Within the Prudential Borrowing programme, the following budget adjustments
are proposed:
Project 25/26
£m
26/27
£m
Description
Recycling in Schools
– Waste Bin
Purchases
(0.036) 0.036 The budget for Recycling in Schools was
previously split equally between 2025/26 and
2026/27. The timeframe for delivery has been
reviewed and revised, and it is proposed
£36,000 is rephased to reflect this. 
Recycling
Containers, Oil
Banks & Battery
Banks Replacement
Programme
Capital Receipts –
Disposals
(0.055)
(0.003)
0.058
-
There is a slight increase in the receipts
expected for Recycling Containers and this is
combined with a reduction in the number of
replacements in the current year. It is proposed
£58,000 is rephased into 2026/27 accordingly.
Litter Bins (0.057) 0.057 An assessment of need for the replacement of
Litter Bins is currently underway to inform the
planning for the roll out next year. The
replacements to take place in 2025/26 are
therefore limited and it is proposed £57,000 of
the budget is rephased.

Page 7

Vehicle
Replacement
Programme
Capital Receipts –
Disposals
(0.600)
0.226
0.809
-
The majority of vehicles to be delivered in the
current year are on track. There has been a
delay in procuring a library vehicle whilst the
specification is finalised. In addition, the
contingency budget is not required for the
remainder of the year. It is therefore proposed a
total of £600,000 is rephased into 2026/27.
Further is it proposed borrowing is increased in
2026/27 by £209,000 due to the rising cost of
replacement vehicles.
Additionally, capital receipt budgets for the
disposal of old vehicles have been rolled into
future years over time. These amounts have not
always been achieved, and it is now expected
that £226,000 of the income budget will not be
realised. This results in a need to increase
borrowing to pay for replacement vehicles.
This results in a total increase in borrowing of
£435,000.
5.2.7 The above proposed adjustments, together with other small movements, have
been reflected in Appendices I and II.
5.3 Housing and Communities
5.3.1 The Strategic Lead has reviewed the programme for Housing and
Communities and proposes the following budget adjustments.
5.3.2 Within Community Greenspace, it is proposed £50,000 is drawn down from
Community Greenspace Sites in 2026/27 for the Crematorium Access Road
in the current year. Additionally, Third Party Contributions have been received
as follows which increase the expenditure budgets:
 £92,000 from Walk Wheel Cycle Trust (formerly Sustrans) towards the
Crieff to Comrie path within Core Path Implementation. However this is
offset by an underspend of £19,000 in expenditure and grant on the
previous programme from last year, giving an overall increase in
£73,000 in the current year.
 £16,000 from Kinnoull Hill Woodland Park User Group towards
landscaping to supplement work already being undertaken at Kinnoull
Hill.
5.3.3 The above adjustments, together with other small movements, have been
reflected in Appendices I and II.
5.4 Economy, Development and Planning
5.4.1 The Strategic Lead has reviewed the programme for Economy,
Development and Planning and proposed the following budget adjustments.
5.4.2 Within Roads Infrastructure, the contract for the design work for the Perth
Eco-Innovation Park was awarded toward the end of 2025. The expenditure
for the remainder of this financial year will be limited to this design work, and it

Page 8

is therefore proposed the remainder of the budget of £7.931 million is moved
into 2026/27. There is also a corresponding movement of the £550,000 Tay
Cities Deal Funding into 2026/27. These adjustments are pending a full
review of the project to be considered by the Council as part of the budget
report to be submitted to its meeting on 4 March 2026.
5.4.3 The above proposed adjustments have been reflected in Appendices I and
II.
5.5 Property Services
5.5.1 The Strategic Lead has reviewed the programme for Property Services and
proposed various budget adjustments, the most significant of which are
described below.
5.5.2 Within Project Support, the following budget adjustments are proposed:
Project 25/26
£m
26/27
£m
27/28
£m
Virement
£m
Description
School Toilet
Upgrade
Programme
0.200 0.600 0.600 1.400 Proposed phasing allocation and
budget virement from Capital
Improvement Projects Programme
in 2029/30 to provide for a
continuous programme of works for
the School Toilet Upgrades. 
Methven
Primary School
Refurbishment
(1.000) 1.000 - - The tender received for the
proposed design of the gym / dining
hall was significantly over budget.
Market testing is being undertaken
to inform the next steps.
Perth Academy
Refurbishment
0.145 (0.145) - - Wi-Fi works are underway and
progressing well and the proposed
budget acceleration reflects this.
Perth High
School – New
School
Investment
(1.300) 1.300 - - Phase 2 for the demolition of the
old building has been delayed due
to additional surveys requiring to be
undertaken prior to commencement
of the works.
Harris
Academy
(0.026) - - (0.026) Project has been confirmed as
completed with an underspend of
£26,000 which has been vired to
the Unallocated Resources.
Roof Upgrade
Programme
0.500 - - 0.500 Proposed budget virement from
Capital Improvement Projects
Programme in 2029/30 to provide
for the Roof Upgrade Programme.

Page 9

5.5.3 Within Property Service Management, the following budget adjustments are
proposed:
2025/26
£m
2026/27
£m
Future Years
£m
Description
DDA Adaptation &
Alteration Works
Programme
(0.103) 0.103 -
Rephasing in line with works
anticipated to now take place
in 2026/27.
Energy Efficiency
Works
Revenue Contribution
(Salix Reserve)
0.012
(0.012)
-
-
-
-
Works on building a
management system at
Logiealmond Primary School,
funded from the Salix
Reserve.
Crieff Drummond Arms
Regeneration
(0.750) 0.750 - Works to address the
Dangerous Building Notice
have been completed. The
site is effectively closed until
Listed Building Consent is
obtained from Historic
Environment Scotland.
Perth Concert Hall (0.195) - 0.195 Rephasing in line with the
level of works to be
completed in the current
year.
5.5.4 Within the Property Service Management Prudential Borrowing programme,
the office moves associated with Pullar House are now complete and the
project has moved towards the construction phase. It is proposed £200,000 is
moved into 2026/27 in line with the updated expenditure projections.
5.5.5 All the above proposed adjustments have been reflected in Appendices I and
II.
5.6 Customer and Digital Services
5.6.1 The Strategic Lead has reviewed the programme for Customer and Digital
Services and it is proposed to move some of the budget for ICT Infrastructure
Replacement (£0.582 million) and Supporting Digital (£0.256 million) from
2025/26 to 2030/31. These adjustments reflect updated estimated
requirements for the current year.
5.6.2 It is also proposed to increase and extend the budget for Software Licences
(Revenues and Benefits) from 2026/27 to 2030/31. The budget for this annual
requirement has not increased previously and the 2026/27 and 2027/28
budgeted amount is not sufficient to meet the current estimated costs.
Further, there is currently no budget provision for the years from 2028/29. It is
therefore proposed to increase the budgets for this programme across all
these years by £0.324 million by applying this amount from Unallocated
Resources in 2025/26.

Page 10

5.7 Unallocated Resources
5.7.1 The proposals outlined in this report in relation to the Unallocated Capital
Resources are summarised in the following table:
2025/26
£m
Later
Years
£m
TOTAL
£m
Description
Opening
Resources
4.977 6.246 11.223
Transfers In:
Housing First
Grant
0.064 0 0.064 Section 4.3
Harris Academy 0.026 0 0.026 Section 5.5.2
Transfers Out:
Software
Licences
(Revenues and
Benefits)
(0.324) 0 (0.324) Section 5.6.2
Closing Resources 4.743 6.246 10.989
5.7.2 After the above proposed movements, the balance of Unallocated Resources
is £10.989 million over the 6-year programme.
6. Housing Investment Programme
6.1 The total current estimated expenditure, net of contributions, for the Housing
Investment Programme over the 5 years 2025/26 to 2029/30 has remained
unchanged to £89.027 million. Movements across years from the previous
estimates are summarised in the table below and detailed in Appendix III.
Approved
26 Nov 2025
Current
Estimate
Movement
£m £m £m
2025/26 42.138 46.695 4.557
2026/27      17.000      17.321 0.321
2027/28 13.776 12.280 (1.496)
2028/29 8.015 7.003 (1.012)
2029/30 8.098 5.728 (2.370)
Total 89.027 89.027 0.000
Total Expenditure to 31 December 2025 (Housing Investment
Programme)
6.2 Net expenditure for 2025/26 to 31 December 2025 amounts to £24.832
million, with £18,000 of receipts. Therefore, the borrowing requirement for the
year to date is £24.814 million.

Page 11

6.3 The Strategic Leads for Housing and Communities and Property Services
have reviewed the Housing Investment Programme and proposed the budget
adjustments outlined below.
6.4 It is proposed to drawdown £100,000 from the New Build Future
Developments budget in 2025/26 for site preparation works for the proposed
schemes at Beechgrove (£62,000) and Balhousie (£38,000) sites. There are
no proposed budget movements on the Council House Buy Back programme.
To date, 102 properties have been purchased, with a further 13 properties
under offer, exceeded the annual target of 40 buybacks.
6.5 It is also proposed to draw down various amounts from the SHQS Future
Developments budgets over various years for the Multi-Storey Flats project as
follows:
2025/26
£m
2026/27
£m
2027/28
£m
2028/29
£m
2029/30
£m
TOTAL
£m
Multi-Storey Flats 2.544 2.273 0 0 0 4.817
Scottish Government
Grant (0.067) 0 0 0 0 (0.067)
Third Party
Contribution 0 (0.481) 0 0 0 (0.481)
SHQS Future
Developments 0 (1.459) (1.131) (1.012) (0.667) (4.269)
Total 2.477 0.333 (1.131) (1.012) (0.667) 0
6.6 Due to factors such as delays with utilities, chalet manufacturing timelines,
additional drainage works and incomplete design costings following changes
to the original Quantity Surveyor (now in administration), the projected costs
for the Double Dyles Chalet Replacement programme have increased by
£1.684 million. There is also an adjustment of £19,000 to the Scottish
Government Grant budget. This results in an overall increase of £1.703
million in 2025/26, and it is proposed that this funded by transferring £1.591
million from the New Build Future Developments budget and £112,000 from
the SHQS Future Developments budget in 2029/30.
6.7 There are other smaller proposed adjustments which have been included in
Appendix III. These include £33,000 of Scottish Government Grant for Energy
Efficiency in 2025/26 which enhances the expenditure on this programme.
6.8 There are no movements in Capital Receipts or Capital Financed from
Current Revenue (CFCR) across the 6-year programme. Consequently, the
total borrowing remains unchanged at £79.786 million. The proposed
adjustments in this report have increased the borrowing for the current year to
56% of the whole 6-year programme Borrowing Requirement.
6.9 All the proposed movements outlined above have been included in Appendix
III.

Page 12

7. Budget Overview
7.1 The projected net expenditure outturn in 2025/26 for the Composite Capital
Budget is £115.320 million and represents 79% of the original 2025/26
budget approved on 30 April 2025 (£146.146 million). The revised budget is
based on the latest projections of expenditure and all budget adjustments
outlined within this report.
7.2 Net expenditure to 31 December 2025 on the Composite Capital Budget is
£60.934 million and represents 53% of the proposed revised budget for
2025/26 of £115.320 million.
7.3 The projected net expenditure outturn in 2025/26 for the Housing Investment
Programme is £46.695 million and represents 166% of the original 2025/26
budget approved on 30 April 2025 (£28.098 million). This increase reflects the
allocation of future years block budgets to specific projects in 2025/26 and the
increase in the Council House Buy-Back programme.
7.4 Net expenditure to 31 December 2025 on the Housing Investment
Programme is £24.832 million which represents 53% of the proposed revised
budget for 2025/26 of £46.695 million.
7.5 The Council’s total Borrowing Requirement to 31 December 2025, based on
the Composite and Housing Investment Programmes, is £73.952 million.
7.6 The estimated overall Council Borrowing Requirement for 2025/26 as a whole
has reduced by £16.132 million to £142.642 million as a result of the
monitoring adjustments reflected within this report. This reflects a reduction in
estimated borrowing in the current year on the Composite Programme of
£20.689 million and an increase on the Housing Investment Programme of
£4.557 million.
7.7 In the context of the Capital Budget, the borrowing above refers specifically to
the funding of capital expenditure and therefore the need to borrow. The
actual amounts and timing of the borrowing is undertaken as part of the
Council’s Treasury Management operations and reported within the Treasury
Activity and Compliance reports throughout the year.
8. Financial Risks
8.1 In preparing the Council's capital monitoring, officers have considered the key
strategic, operational and financial risks facing the Council over this period.
Whilst the risks may be managed in the current financial year, given the
nature of capital projects these risks are also likely to impact future years
plans.
8.2 To alleviate the impact these risks may have if they occur, a number of
general risk mitigation factors are utilised by the Council which include
detailed budget monitoring carried out by Services and having general
unallocated funds available to meet unforeseen expenditure.

Page 13

8.3 Given the latest monitoring position outlined in this report, the risks to 2025/26
have been removed or reduced. Going forward, risks to future years Capital
Expenditure plans will be monitored with mitigating actions identified. The
main risks impacting the Capital Budget are maintained in Appendix V.
8.4 These risks are monitored continuously by officers, and any implications on
the Capital Budget will be reported to the Committee at the appropriate time.
9. Impact and Value Assessment
9.1 This is an operational report, and as such, an impact and value assessment in
not required.
10. Appendices
Appendix I - Composite Capital Programme - Estimated Capital Resources
2025/26 to 2030/31
Appendix II – Composite Capital Programme - Summary of Capital Resources
and Expenditure 2025/26 to 2030/31       
Appendix III – HRA Capital Investment Programme – Summary of Capital
Resources and Expenditure 2025/26 to 2029/30
Appendix IV – Significant Capital Projects Progress Update
Appendix V – Capital Budget Financial Risks