DRAFT
Executive Sub-Committee of Finance and Resources
Committee
Minute of hybrid meeting of the Executive Sub-Committee of the Finance and
Resources Committee held in MR410, 2 Hight Street, Perth on Tuesday
16 December at 3.00pm.
Present: Councillors S Donaldson, E Drysdale, P Barrett, D Cuthbert, J Duff,
I Massie and C Shiers.
In Attendance: T Glen, Chief Executive; S Walker, Chief Finance Officer; F Crofts,
Strategic Lead – Environment and Infrastructure; P Leonard (Environment and
Infrastructure); L Simpson, Strategic Lead – Legal and Governance; K Molley (Legal
and Governance); and L Potter (Strategic Planning, People and Performance).
Councillor S Donaldson, Convener, Presiding.
1. Welcome and Apologies
The Convener welcomed all those present to the meeting.
2. Declarations of Interest
There were no declarations made in terms of the Councillors’ Code of
Conduct.
(It is recommended that the public and press should be excluded during
consideration of the following item(s) in order to avoid the disclosure of information
which is exempt in terms of Schedule 7A to the Local Government (Scotland) Act
1973)
P1. Residual Waste Contract 
There was submitted a report by Strategic Lead – Environment and
Infrastructure (25/358) advising Members of significant risks that have arisen with
regard to the Council’s residual waste contract and to set out recommended actions
required to mitigate these risks insofar as is possible. 
Resolved:
(i) A mutual termination of the current contract, with effect from 1 February 2026,
subject to a compensation payment to the Council as outlined in Report
25/358, be agreed. 
(ii) As an interim measure, a direct award for residual waste disposal services is
made to an alternative provider on an emergency basis, for a period of 18
months, with an option to extend by a further year if required, be approved.
(iii) It be noted that the additional costs for the 18-month period would be covered
by a compensation payment and that should a further 12 months’ extension
be required, additional costs outlined in Report 25/358 would be incurred. This
will be reflected in forthcoming budget process.

Page 2

DRAFT
(iv) It be noted that the options for the provision of longer-term waste disposal
arrangements will be explored and will be the subject of a further paper to
Members in 6 months’ time.