SIGNIFICANT CAPITAL PROJECTS
PROGRESS UPDATE
APPENDIX IV
Project Title Total
Gross
Budget
Third Party
Funding
(£'000)
Total Net
Budget
(£'000)
Projected
Outturn
(£'000)
Completion Date Contract
Awarded
On
Site
Status Change Since
Last Report
Additional Commentary
Blairgowrie Recreation
Centre - Replacement 36,000 0 36,000 36,000
Opening August 2025
Phase 2 Completion
Date TBC
Yes Yes On track Yes - phase 1
completed
Practical completion of Phase 1 achieved on 11/08/25. Phase 2 works
delayed completion date tbc.
North/West Perth New
Primary School* 24,000 0 24,000 24,000 Summer 2028 No No On track No Project has been put on hold for 2 years due to slow build out rates at
Bertha Park.
Perth High School - New
School Investment 80,200 0 80,200 80,200 School opening as
planned August 2025 Yes Yes On track Yes - phase 1
completed School opened August 2025, phase 2 underway.
Destiny Bridge and New
Kingsway (PTF Phase 2) 150,668 40,168 110,500 103,797 March-25 Yes Yes Project Complete No
Project was completed as per programme and the official opening took
place on 31 March 2025.  Some areas of the site are still operational as
work continues to undertake land reinstatement  (on temporary plots)
and minor finishing. Landscape maintenance will continue for 3 and 5
years. Final paperwork requirements (e.g. final certifications, as-built
drawings etc) nearly complete.
Bertha Park Link Road 13,200 0 13,200 15,258 December 2026 Yes Yes On track Yes - on site
Detailed design by Sweco complete. Following letter of intent, Stage 1
was awarded to BAM UK & Ireland in mid July 2025, and notice to
proceed to Stage 2 given in late August 2025. Construction work is
progressing well and on programme with all advance works complete,
earthworks nearing completion and drainage works now commenced.
Comrie Flood Protection
Scheme 40,353 32,657 7,696 7,696 Autumn 2026 Yes Yes On track No Main construction works commenced in March 2025. Project on budget
and programmed for completion in October 2026.
Perth Eco Innovation Park* 32,817 17,711 15,106 15,106 Not currently
programmed No No
Design package
awarded - design
programme on track
Yes
[See previous reports in relation to funding.]  Contract Strategy and
Scope prepared and approved for engaging Triskelion through SCAPE.
Mobilisation contract only awarded at this time to progress works
including gap analysis. Ground investigation works currently being
procured with programme start late Sept. Awaiting feedback from JDLT
on housebuilders interest before issuing instruction for GI and entering
into main contract with Triskelion.
PH2O 73,847 0 73,847 73,847 Not currently
programmed No No
Thimblerow approved
as new site for PH2O
project, including
leisure water, at
Council on 18 June
2025.
Yes Project Board established, programme under development, project no
longer on hold.
Bells Sport Centre 10,000 0 10,000 10,000 Not currently
programmed No No Approved 18 June
2025 Yes Early stages of development, will be updated in future reports
Kinross Community
Campus Sports Facilities 6,900 0 6,900 6,900 Not currently
programmed No No Approved 18 June
2025 Yes Early stages of development, will be updated in future reports
Crieff Community Campus
Sports Facilities 6,300 0 6,300 6,300 Not currently
programmed No No Approved 18 June
2025 Yes Early stages of development, will be updated in future reports
Crieff Drummond Arms -
Regenertaion 3,000 0 3,000 3,000
DBN Works due to be
completed October
2025; LBC applied for,
outstanding result for
the remainder of the
demolition
Yes Yes
DBN Works due to be
completed October
2025; LBC applied for,
outstanding result for
the remainder of the
demolition
n/a Demolition split into two parts. 1st part are all works listed within the
Dangerous Building Notice (DBN) are due to be completed in October
2025. For remainder of the demolition listed building conscent (LBC) is
required. If LBC is not granted within good time the building will have to
be made safe until LBC is achiveved, then the demolition will
recommence with the same contractor. 
* Third Party Funding excludes Developer Contributions and receipts to be received in future years beyond the current 6-year programme.