Composite Capital Budget 2025-31 and Housing Investment Programme 2025-30 – Monitoring Report No1

Perth and Kinross Council · 1 October 2025
Back to Finance and Resources Committee — 1 October 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Our vision is a Perth and Kinross where everyone can live life
well, free from poverty and inequality 
__________________________________________________________________ 
Committee or Board: Finance and Resources Committee 
Date of Meeting: 1 October 2025 
Report Title: Composite Capital Budget 2025/31 and Housing
Investment Programme 2025/30 – Monitoring Report
No.1 
Report Number: 25/249 
Report Author: John Jennings, Senior Accountant
James Salisbury, Senior Accountant 
Organisational Lead: Scott Walker, Chief Finance Officer 
__________________________________________________________________ 
1. Purpose 
1.1 This report provides a summary position to date for the 6-year Composite
Capital Budget for 2025/26 to 2030/31 and the 5-year Housing Investment
Programme for 2025/26 to 2029/30 and seeks approval for adjustments to the
programmes. 
1.2  Sections 
1. Purpose
2. Recommendations
3. Background
4. Composite Capital Programme – Gross Capital Resources
5. Composite Capital Programme – Expenditure
6. Housing Investment Programme
7. Budget Overview
8. Financial Risks
9. Impact and Value Assessment
10. Appendices 
2. Recommendations 
2.1 It is recommended that the Committee: 
(i) notes the contents of the report.

Page 2

(ii) approves the proposed adjustments to the six-year Composite Capital
Budget 2025/26 to 2030/31 set out in Sections 4 and 5 of the report
and summarised in Appendices I and II.
(iii) approves the proposed adjustments to the Housing Investment
Programme Budget 2025/26 to 2029/30 set out in Section 6 of the
report and summarised in Appendix III.
(iv) notes progress with the delivery of major Capital projects as
summarised in Appendix IV.
(v) notes the financial risks set out in Section 8 and Appendix V 
3. Background 
3.1 The Finance and Resources Committee approved an updated six-year gross
Composite Capital Budget for 2024/25 to 2029/30 totalling £635.464 million
and a five-year gross Housing Investment Programme for 2024/25 to 2028/29
totalling £96.917 million at its meeting on 30 April 2025 (report 25/100
refers). 
3.2 This monitoring report now incorporates the approved Composite Capital
Budgets for 2030/31 and the Housing Investment Programme for 2029/30.
The report also advises on the final outturns for 2024/25 for both
programmes, current year expenditure to 31 July 2025, and the latest
estimate of the projected outturn for each of the years to 2030/31 for the
Composite Programme and 2029/30 for the Housing Investment Programme. 
4. Composite Capital Programme – Gross Capital Resources 
4.1 The current estimated total gross capital resources (which includes
movements in Capital Receipts, Capital Grants, Contributions and borrowing)
available over the six years 2025/26 to 2030/31 amount to £559.588 million.
Movements from the revised Composite Capital Budget approved on 30 April
2025 for these six years are summarised in the table below, and the
constituent elements for each year are shown in Appendix I. 
Total Gross Composite Capital Resources 
Approved 
30 April 2025
Current
Estimate
Movement 
£M £M £M
2025/26 147.463 140.101 (7.362)
2026/27 131.218 113.258 (17.960)
2027/28 90.468 86.264 (4.204)
2028/29 65.909 69.249 3.340
2029/30 48.527 70.187 21.660
2030/31 44.716 80.529 35.813
Total 528.301 559.588 31.287  
4.2 The monitoring position has been updated for amounts carried forward from
2024/25 as reflected within the unaudited accounts. The overall movement in
the total Gross Resources for the 6 years 2025/26 to 2030/31 shown at
Section 4.1 above can be summarised as follows:

Page 3

£’000
Resources Brought-forward from 2024/25 to 2025/26: 
- Property Receipts, including carried forward to future years 264
Capital Grants 6
- Tay City, Developer, Other Third Party and Revenue Contributions 2,791
Borrowing Requirement 12,425
Total Resources Brought-forward from 2024/25 15,486  
Increase in Resources from current monitoring: 
Increase in Capital Grants (Section 4.4) 369
Increase in Capital Receipts (Section 4.5) 6,579
Increase in Third Party, Revenue and Developer Contributions
(Section 4.6) 
1,391     
Increase in Borrowing (Section 4.7 and 4.8) 7,462
Total Increase in Gross Capital Resources (Section 4.1) 31,287 
4.3 The resources brought forward from 2024/25 to 2025/26 represent
adjustments between the final estimate in 2024/25 and the final outturn.
Therefore, these merely represent timing differences and are neutral over the
two years. Adjustments arising from the current year monitoring are described
in the sections below. 
4.4 The Scottish Government has allocated a Capital Grant of £374,000 to the
Council in 2025/26 under the Bus Infrastructure Fund (see Section 5.3.2).
There is also a reduction of £5,000 in the Road Safety Initiative Grant
originally allocated in 2024/25 and carried forward to the current year. These
amounts have therefore now been incorporated into the programme at
Appendix I and II. 
4.5 Commercial Property Receipts have been reviewed which results in an
increase of £6.572 million comprising new receipts of £5.087 million and use
of brought forward receipts of £1.485 million. Additionally, Ring-Fenced
Capital Receipts for the disposal of waste containers within the Environment
and Infrastructure Prudential Borrowing programme have increased by
£7,000. It is therefore proposed to increase the expenditure budgets by these
amounts. 
4.6 There is an increase of £1.391 million in Third Party Contributions, with
additional contributions towards Structural Maintenance (£155,000, Section
5.2.3), the Bertha Park Link Road (£1.064 million, Section 5.4.3), and Energy
Conservation and Carbon Reduction (£41,000, Section 5.5.7); less carry
forward adjustments for Active Travel (£2,000) and the Low Carbon Transport
Hub (£3,000). There has also been an increase in Revenue Contributions
totalling £30,000 in relation to Car Parking – Pitlochry (£11,000), Almondbank
Flood Protection Scheme (£11,000) and the Low Carbon Transport Hub
(£8,000). In addition, there are adjustments on the Tay City Deal Contribution
(£74,000) and Scottish Water Contribution towards Broxden Drainage
(£32,000) in 2025/26 to remove the carry forward amounts as a result actual
receipts in 2024/25 being higher than estimated by this amount.

Page 4

4.7 The projected borrowing requirement in 2025/26, which is effectively the
balancing item for resources, is £121.818 million. This is £10.398 million
lower than the amount approved by this Committee on 30 April 2025
(£132.216 million). This total can be broken down between borrowing carried
forward from 2024/25 (increase of £12.425 million as set out in the table
above at Section 4.2) less proposed budget adjustments from the current
monitoring (reduction of £22.823 million as set out in Appendix II). 
4.8 The total borrowing requirement in the subsequent years 2026/27 to 2030/31
has increased by £30.285 million to £307.179 million, resulting in an overall
increase of £7.462 million in the total level of borrowing across the whole 6-
year programme. This increase in borrowing is summarised as follows: 
2025/26 2026/27 2027/28 Later
Years
Total 
£m £m £m £m £m
Property Services – Leisure Asset
Review (PH2O, Bells etc.) (Section
5.5.5)
0.000 0.000 0.000 7.200 7.200
Environment and Infrastructure
Prudential Borrowing – Recycling in
Schools Programme and Vehicle
Replacement Programme (Section
5.2.7)
0.262 0.000 0.000 0.000 0.262
Movements arising from re-phasing
of expenditure and receipts
(Appendix II)
(23.085) (18.360) (5.104) 46.549 0.000
Increase/(Reduction) in
Borrowing Requirement
(22.823) (18.360) (5.104) 53.749 7.462 
4.9 The chart below shows the Capital Resources required to fund the 2025/26
Composite Capital Programme following the proposed budget adjustments
detailed in this report. 
86.5%
8.1%
0.4%
3.8%
0.2%
1.0%
5.4%
Projected Capital Resources 2025/26
(August 2025)
Borrowing (£121.818M)
Grants (£11.375M)
Tay City Deal (£0.550M)
Developer Contributions (£5.344M)
Third Party & Revenue Contributions (£0.257M)
Receipts (£1.412M)
£Million

Page 5

5. Composite Capital Programme – Expenditure 
5.1 Total Expenditure and Proposed Budget Adjustments to the Current
Programme 
5.1.1 Total expenditure (net of grants and contributions) to 31 July 2025 on the
Composite Capital Programme is detailed in Appendix II and summarised as
follows: 
Projected
Outturn 
(£m)
Net
Expenditure to
31 July 2025
(£m) 
% of
Projected
Outturn
Environment and Infrastructure  50.464 9.095 18%
Housing and Communities 6.122 0.227 4%
Economy, Development and Planning 31.111 3.451 11%
Property Services 40.613 8.849 22%
Customer and Digital Services 5.023 0.696 14%
Health and Social Care 0.953 0.275 29%
Unallocated 4.885 0.000 0%
Total Net Capital Expenditure 139.171 22.593 16%
5.1.12 Appendix IV includes updates on the progress of delivering the Council’s
major Capital projects. 
5.2 Environment and Infrastructure 
5.2.1 The Strategic Lead has reviewed the programme for Environment and
Infrastructure and proposes various budget adjustments, the most significant
of which are described below. 
5.2.2 Within Traffic and Road Network, a revenue budget grant has been received
towards the 20mph Signage Programme with a focus on utilising this grant
first. The capital budget is therefore not required in the current year and it is
proposed £119,000 is moved to next year. In addition, with the current closure
of the South Street/Scott Street junction in Perth, work to replace the traffic
signals originally scheduled for 2026/27 has been brought forward to the
current year, and it is proposed £125,000 is accelerated accordingly.   
5.2.3 Within the Roads Maintenance Partnership, there has been a net movement
in the contributions, with a subsequent increase in the expenditure budget for
Structural Maintenance. Included within the movement is a contribution of
£249,000 from Scottish Water towards works at Tay Street and Shore Road in
Perth. 
5.2.4 Within Structures, it is proposed to drawdown amounts from the Bridge
Refurbishment Programme for works in 2025/26, for Bolfrack River Retaining
Wall (£85,000), Bridge of Tilt (£630,000) and Corb Bridge Culvert (£97,000). It
is also proposed to drawdown a further £1.375 million for works on
Blairgowrie Bridge between 2025/26 and 2027/28. The drawdowns have been
allocated across all future years in line with anticipated spend on the Bridge

Page 6

Refurbishment Programme. In addition, the following rephasings are
proposed: 
Project 25/26
£m
26/27
£m
Future
Years
£m
Description
Perth Queens
Bridge 
(0.078)  0.028  0.050  Limited works are scheduled to
take place on Perth Queens Bridge
in the current year, with works
scheduled to commence in
2026/27. 
Garry Viaduct 0.051 (0.205) 0.154 Phasing of project has been
reviewed with various movements
mainly relating to future years in
line with expected completion in
2029/30. 
5.2.5 Within Flooding, objections have been received on the design for the South
Kinross Flood Protection Scheme which needed addressing prior to
proceeding (Report 25/25 refers). Advanced utility works are also unable to
proceed due to the objections, and it is proposed £1.422 million is moved
from the current year to 2026/27. Additionally, within Flooding, the works on
Dunkeld and Craigie Burns now has a design contract in place which is
progressing the design in the current year and it is therefore proposed
£194,000 of the budget is accelerated from future years. 
5.2.6 Within Climate Change and Zero Waste, £1.274 million Climate Change
Grant from Scottish Government was initially added to Unallocated Resources
pending the development of projects for its use. It is now proposed £945,000
of the budget is drawn down from Unallocated Resources for use on various
Climate Change projects between 2025/26 and 2027/28, with the remaining
£329,000 remaining unallocated within the Climate Change programme in
2025/26 whilst further project options are explored. Also, within Climate
Change and Net Zero, additional Scottish Government Capital Grant of
£49,000 for Nature Restoration has been added to the expenditure
programme in 2025/26. The additional grant monies had also previously been
included in the Unallocated Resources pending confirmation of the final
allocation. 
5.2.7 Within the Prudential Borrowing programme, the Recycling in Schools project
has commenced for the purchase of waste bins aimed at improving the
recycling rate with additional borrowing of £102,000 included. Further, it is
proposed that an additional £160,000 of borrowing is undertaken on the
Vehicle Replacement Programme for the purchase of an additional 10 hybrid
electric pool vehicles. 
5.2.8 The above proposed adjustments, together with other small movements, have
been reflected in Appendices I and II. 
5.3 Housing and Communities

Page 7

5.3.1 The Strategic Lead has reviewed the programme for Housing and
Communities and proposes the following budget adjustment. 
5.3.2 Within Parking, Public Transport and Civil Contingencies, a Scottish
Government grant of £374,000 from the Bus Infrastructure Fund has been
confirmed and added to the Council’s General Capital Grant. This amount has
also been added to the expenditure programme in 2025/26, for the purpose of
design, development and delivery of bus infrastructure measures. 
5.3.3 The above adjustment has been reflected in Appendices I and II. 
5.4 Economy, Development and Planning 
5.4.1 The Strategic Lead has reviewed the programme for Economy,
Development and Planning and proposed various budget adjustments, the
most significant of which are described below. 
5.4.2 Within Roads Infrastructure, the Destiny Bridge and New Kingsway, as part of
Perth Transport Futures Phase 2, are complete. There are still costs
outstanding and it is therefore proposed to move £0.314 million to 2026/27.
However, a revised estimate of the overall cost has resulted in an underspend
on the project of £6.703 million and it is proposed this is transferred to
Unallocated Resources. 
5.4.3 Also within Roads Infrastructure, the Bertha Park Link Road costs are
anticipated to be higher than currently budgeted with an additional £249,000
required in the current year and £2.873 million in 2026/27. In addition, a
contribution from the Developer of £1.064 million is anticipated to be received
in 2030/31. It is proposed to meet the increased estimate by transferring the
net amount of £2.058 million from Unallocated Resources. Further, for the
A9/A85 Road Junction Improvements it is proposed that £145,000 is
transferred from Unallocated Resources to meet increased costs from
2024/25 for land compensation. 
5.4.4 The Commercial Property Investment Programme for the remainder of the
Capital Programme has been comprehensively reviewed, with distribution of
the Economic Development Investment budget to specific projects throughout
the region. Appendix II provides the proposed allocation and phasing for the
various projects. 
5.4.5 The above proposed adjustments, together with other small movements,
including small carry forward adjustments, have been reflected in
Appendices I and II. 
5.1 Property Services 
5.5.1 The Strategic Lead has reviewed the programme for Property Services and
proposed various budget adjustments, the most significant of which are
described below.

Page 8

5.5.2 Within Project Support, budgets for Braco Primary School Upgrade (£8.5
million) and Pitlochry High School Extension (£8.7 million) have been
allocated with the phasing set out in the table below. It is proposed these are
funded through a virement from Investment in the Learning Estate with
£11.062 million transferred from the current year and £6.138 million in
2026/27. 
2025/26
£m
2026/27
£m
2027/28
£m
2028/29
£m
Braco Primary School Upgrade 0.150 0.350 3.000 5.000
Pitlochry High School Extension 0.200 0.750 5.000 2.750 
5.5.3 Additionally, within Project Support it is proposed £400,000 is vired from
Capital Improvement Projects in 2029/30 to the School Toilet Upgrade
Programme in 2025/26 to enable the commencement of works in the current
year. The following rephasings are also proposed:
Project 25/26
£m
26/27
£m
Future
Years
£m
Description
Methven
Primary School
Refurbishment
(0.670) 0.670 - Works at the school have commenced and this
rephasing aligns with the timeline of spend.
Technology
Upgrades
(0.519) - 0.519 The works to be completed in the current year have
been reviewed and the budget exceeds that
required. The budget for next year is sufficient for
planned works and it is therefore proposed
£519,000 of the budget is moved to 2027/28. 
5.5.4 Finally, within Project Support, works to upgrade the kitchen at the
Community School of Auchterarder for free school meals have been delayed
due to redirection of resources. It is therefore now anticipated that the majority
of works will take place between 2027/28 and 2028/29 and it is proposed that
the 2025/26 budget is moved to align with this as follows: 
2025/26
£m
2026/27
£m
2027/28
£m
2028/29
£m
Community School of
Auchterarder (FSM) (1.000) (2.261) 0.750 2.511 
5.5.5 At its meeting on 18 June 2025 (report 25/162 refers), the Council approved
the allocation of the PH2O budget to the revised PH2O project (£74 million),
Bells Sports Centre (£10 million) and the Community Campuses in Kinross
and Crieff (£13.2 million). The Council also approved that the overall
increase in costs of £7.2 million is to be funded by increased borrowing.
These projects are now incorporated within the Capital programme with
budget movements proposed to reflect the following phasing: 
2025/26
£m
2026/27
£m
2027/28
£m
2028/29
£m
2029/30 2030/31

Page 9

PH2O 0.300 1.700 2.000 10.000 30.000 29.847
Bells Sports Centre 0.500 1.500 1.500 3.500 3.000 -
Kinross Community
Campus Sports
Facilities
- 0.900 5.000 1.000 - -
Crieff Community
Campus Sports
Facilities
- - 1.000 4.000 1.300 - 
5.5.6 Additionally, within Property Service Management, following arbitration in
relation to a contract dispute, the costs of the Letham Community Wellbeing
Hub have increased by £326,000. It is proposed to fund this additional cost
from the Unallocated Resources. The following rephasings are also proposed:

Page 10

Project 25/26
£m
26/27
£m
Future
Years
£m
Description
Friarton Depot –
Waste Transfer
Station
(0.221) 0.221 - The spend projection for the current year has been
revised with some costs now anticipated in 2026/27
and it is proposed £221,000 is moved accordingly. 
Crieff
Drummond
Arms
Regeneration
(1.442) 1.442 - Demolition works are progressing per the
dangerous buildings notice with demolition expected
to take significant time due to the condition and
location of the building. It is proposed £1.442 million
is moved from the current year to 2026/27 in line
with anticipated spend profile. 
Prudential
Borrowing:
Pullar House –
Purchase and
Re-purposing
(2.799) 1.600 1.199  The purchase of Pullar House will proceed in the
current year, whilst the budget also includes
amounts for re-purposing of the office space. The
re-configuration works will take place over the next
few years as the building occupancy increases. It is
proposed the budget is revised to align with this
timeframe. 
5.5.7 Within Prudential Borrowing – Energy Saving and Carbon Reduction
Programme, a grant of £41,000 has been received from Salix towards the
energy works at Arngask Primary School and the expenditure budget has
been increased to reflect this. 
5.5.8 All the above proposed adjustments, together with other small movements,
have been reflected in Appendices I and II. 
5.6 Customer and Digital Services 
5.6.1 The Strategic Lead has reviewed the programme for Customer and Digital
Services and proposed various budget adjustments, the most significant of
which are described below. 
5.6.2 Within Customer and Digital Services, the budgets for Hardware and Licences
have been transferred to the main ICT Infrastructure Replacement and
Upgrade Programme. The following rephasings are also proposed within
Customer and Digital Services to align budgets to the revised programme
planned by IT: 
2025/26
£m
2026/27
£m
2027/28
£m
2028/29
£m
2029/30
£m
2030/31
£m
ICT Infrastructure
Replacement and
Upgrade Programme
(0.781) 0.760 0.822 (2.462) (0.240) 1,901
Data and Analytics (0.532) 0.125 0.141 0.138 0.157 (0.029)
Supporting Digital (0.090) 0.109 (0.196) 0.208 0.233 (0.264)

Page 11

School AV Equipment
Replacement Programme  (0.016) (0.080) (0.008) (0.074) (0.126) 0.304
5.6.3 In addition to above, the Mosaic system anticipated spend in the current year
has been revised upwards slightly and it is proposed that £54,000 of the
budget is accelerated from 2027/28. 
5.6.4 All the above proposed adjustments, together will smaller movements, have
been reflected in Appendices I and II. 
5.7 Health and Social Care 
5.7.1 Within Technology Enabled Telecare, in line with the number of installs and
replacements units due to be completed by the end of 2025/26, it is proposed
£355,000 of the budget is moved to future years towards the end of the
programme. This reflects savings resulting by moving from a 3 year to a 5
year replacement programme, lower supplier costs and lower demand from
that originally anticipated. 
5.7.2 The budgets for Moving and Handling Office Refurbishment (£29,000) and
Developing Support Tenancies (£229,000) have not progressed and it is
proposed the budgets are transferred to Unallocated Resources. 
5.7.3 The proposed adjustments, together with smaller movements, have been
reflected in Appendices I and II. 
5.8 Unallocated Resources 
5.8.1 The proposals to and from the Unallocated Resources are set out in the
following table: 
2025/26
£m
Later
Years
£m
TOTAL
£m
Description
Opening Resources 1.869 6.246 8.115 
Transfers In:     
Destiny Bridge 6.703 0 6.703 Section 5.4.2 
Developing
Supported Tenancies
0.229 0 0.229 Section 5.7.2 
Moving and Handling
Office
0.029 0 0.029 Section 5.7.2
Transfers Out:     
Bertha Park Link
Road
(2.058) 0 (2.058) Section 5.4.3 
Climate Change
Grant
(1.274) 0 (1.274) Section 5.2.6 
Nature Restoration
Fund
(0.049) 0 (0.049) Section 5.2.6 
Letham Community
Wellbeing Hub
(0.326) 0 (0.326) Section 5.5.6 
A9/A85 Road
Junction
(0.145) 0 (0.145) Section 5.4.3 
Miscellaneous  (0.001) 0 (0.001) Carry Forward Adjustments
Closing Resources  4.977 6.246 11.223

Page 12

5.8.2 After the application of the above proposed adjustments, the balance of
Unallocated Resources is £11.223 million over the 6-year programme. 
6. Housing Investment Programme 
6.1 The total current estimated expenditure, net of contributions, for the Housing
Investment Programme over the 5 years 2025/26 to 2029/30 is £89.027
million. Movements across years from the previous estimates are
summarised in the table below and detailed in Appendix III. 
Approved 
30 April 2025
Current
Estimate
Movement 
£m £m £m
2025/26 28.098 41.478 13.380
2026/27       14.411       16.923 2.512
2027/28 14.265 13.633 (0.632)
2028/29 12.076 8.515 (3.561)
2029/30 20.044  8.478  (11.566)
Total 88.894 89.027 0.133 
6.2 The increase in net expenditure of £133,000 relates to the amount of
resources carried forward from 2024/25 to 2025/26. 
Total Expenditure to 31 July 2025 (Housing Investment Programme) 
6.3 Net expenditure for 2025/26 to 31 July 2025 amounts to £11.171 million with
no receipts to date. Therefore, the borrowing requirement for the year to date
is also £11.171 million. 
6.4 The Strategic Leads for Housing and Communities and Property Services
have reviewed the Housing Investment Programme and proposed the budget
adjustments outlined below. 
6.5 It is proposed to draw down various amounts from the New Build Future
Developments budgets from future years to 2025/26 as follows: 
• Brioch Road, Crieff - £1.234 million to cover construction costs (£2.716
million) for the development of the site, less Scottish Government Grant
(£1.242 million) and a Council Tax Second Home Reserve contribution
(£240,000).
• Kinloch Brae, Blairgowrie - £299,000 to cover construction costs
(£783,000) for the development of the site, less Scottish Government
Grant (£404,000) and a Council Tax Second Home Reserve contribution
(£80,000).
• Former Balhousie Primary School, Perth - £263,000 to cover ongoing
professional fees for the development of the site.
• Beechgrove, Perth - £52,000 to cover ongoing professional fees for the
development of the site.

Page 13

• Various – a total of £2,000, to cover small carry forward adjustments from
2024/25 required for Huntingtower, Fairfield, Kinloch Gardens, Lynedoch
Road Phases 1 and 2 and Weavers Gait. 
6.6 The Council House Buy Back Programme has progressed at an increased
level in the current year, with 65 purchases completed this year to date. With
the multi-storey major refurbishment programme anticipated to commence
later this year there has been a significant increase in private owners wishing
to sell their property back to the Council. Therefore, it is proposed to increase
the Buy Backs budget in the current year by £10.775 million by accelerating
this amount spread equally from the subsequent four years of the programme.
The current year budget is further enhanced by £1.4 million of Scottish
Government grant allocated this year. 
6.7 In addition, a further property has been purchased under the Mortgage-to-
Rent scheme in the current year. It is therefore proposed to increase the
budget in the current year by £75,000, together with £75,000 of Scottish
Government Grant awarded for the purchase. Further, third party recharges of
£69,000 are estimated on the External Fabric programme in 2025/26, and it is
therefore proposed to increase the expenditure budget by this amount. 
6.8 It is also proposed to allocate some of the SHQS Future Developments
Budget across all years to various schemes, as summarised in the table
below. This table also highlights the need to bring forward most of the SHQS
Future Developments Budgets from later years: 
Project 25/26
£m
26/27
£m
27/28
£m
28/29
£m
29/30
£m
Total
£m
Triple Glazing 4.024 4.025 0 0 0 8.049
OT Adaptations 0.500 0 0 0 0 0.500
External Fabric 1.811 1.744 1.228 0 0 4.783
Environmental Improvements 0.978 0.973 0.973 0.973 0 3.897
Bathroom Upgrades 1.178 0 0 0 0 1.178
Energy Efficiency 0.579 0 0 0 0 0.579
Fire Alarm Replacements 0.084 0.166 0 0 0 0.250
Major Adaptations 0.120 0 0 0 0 0.120
Rannoch Road Refurbishment 0.041 0 0 0 0 0.041
149-151 Dunkeld Road 0.029 0 0 0 0 0.029
Fire Precautions 0.002 0 0 0 0 0.002
TOTAL 9.346 6.908 2.201 0.973 0 19.428
SHQS Future Developments (4.066) (1.706) (2.946) (1.839) (8.871) (19.428)
Increase/(Reduction) in
Borrowing 5.280 5.202 (0.745) (0.866) (8.871) 0 
6.9 The remaining proposed budget movement is to move £2.808 million of the
budgeted works at St. Catherines Square from 2025/26 to 2027/28, with only
professional fees to be incurred this year. 
6.10 Due to additional Capital Receipts received in 2024/25 there is a carry forward
adjustment in 2025/26 of £97,000. Further, the Revenue Budget monitoring

Page 14

for the Housing Revenue Account has identified an increase in Capital
Financed from Current Revenue (CFCR) of £201,000 in the current year.
These adjustments reduce the Borrowing Requirement by £298,000 for the
overall programme, however it should be noted that the level of borrowing in
the current year has increased by £11.949 million as a result of the proposed
acceleration of the various budgets outlined above. 
6.11 All the proposed movement outlined above have been included in Appendix
III. 
7. Budget Overview 
7.1 The projected net expenditure outturn in 2025/26 for the Composite Capital
Budget is £139.171 million and represents 95% of the original 2025/26
budget approved on 30 April 2025 (£146.146 million). The revised budget is
based on the latest projections of expenditure and all budget adjustments
outlined within this report. 
7.2 Net expenditure to 31 July 2025 on the Composite Capital Budget is £22.592
million and represents 16% of the proposed revised budget for 2025/26 of
£139.171 million. 
7.3 The projected net expenditure outturn in 2025/26 for the Housing Investment
Programme is £40.478 million and represents 144% of the original 2025/26
budget approved on 30 April 2025 (£28.098 million). This increase reflects the
allocation of future years block budgets to specific projects in 2025/26 and the
increase in the Council House Buy-Back programme. 
7.4 Net expenditure to 31 July 2025 on the Housing Investment Programme is
£11.171 million which represents 28% of the proposed revised budget for
2025/26 of £40.478 million. 
7.5 The Council’s total Borrowing Requirement to 31 July 2025, based on the
Composite and Housing Investment Programmes, is £29.538 million. The
estimated overall Council Borrowing Requirement for 2025/26 as a whole has
reduced by £10.874 million to £160.612 million as a result of the monitoring
adjustments reflected within this report. This reflects a reduction in estimated
borrowing in the current year on the Composite Programme of £22.823
million and an increase on the Housing Investment Programme of £11.949
million. 
7.6 In the context of the Capital Budget, the borrowing above refers specifically to
the funding of capital expenditure and therefore the need to borrow. The
actual amounts and timing of the borrowing is undertaken as part of the
Council’s Treasury Management operations and reported within the Treasury
Activity and Compliance reports throughout the year. 
8. Financial Risks

Page 15

8.1 In preparing the Council's capital monitoring, officers have considered the key
strategic, operational and financial risks facing the Council over this period.
Whilst the risks may be managed in the current financial year, given the
nature of capital projects these risks are also likely to impact future years
plans. 
8.2 To alleviate the impact these risks may have if they occur, a number of
general risk mitigation factors are utilised by the Council which include
detailed budget monitoring carried out by Services and having general
unallocated funds available to meet unforeseen expenditure. 
8.3 Given the latest monitoring position outlined in this report, the risks to 2025/26
have been removed or reduced. Going forward, risks to future years Capital
Expenditure plans will be monitored with mitigating actions identified. The
main risks impacting the Capital Budget are maintained in Appendix V. 
8.4 These risks are monitored continuously by officers, and any implications on
the Capital Budget will be reported to the Committee at the appropriate time. 
9. Impact and Value Assessment 
9.1 This is an operational report, and as such, an impact and value assessment in
not required. 
10. Appendices 
Appendix I - Composite Capital Programme - Estimated Capital Resources
2025/26 to 2030/31
Appendix II – Composite Capital Programme - Summary of Capital Resources
and Expenditure 2025/26 to 2030/31        
Appendix III – HRA Capital Investment Programme – Summary of Capital
Resources and Expenditure 2025/26 to 2029/30 
Appendix IV – Significant Capital Projects Progress Update
Appendix V – Capital Budget Financial Risks