SIGNIFICANT CAPITAL PROJECTS
PROGRESS UPDATE
APPENDIX IV
Project Title Total Gross
Budget
(£'000)
Third Party
Funding
(£'000)
Total Net
Budget
(£'000)
Projected
Outturn
(£'000)
Completion Date Contract
Awarded
On Site Status Change Since
Last Report
Additional Commentary
Blairgowrie Recreation
Centre - Replacement
36,000 0 36,000 36,000 Easter 2025 - new
centre currently
scheduled to open late
2024
Yes Yes On track Yes - on-site. The project has been delayed due to leaks in the pool.
Commissioning work continues, the opening date is to be
confirmed.
North/West Perth New
Primary School*
24,000 0 24,000 24,000 Summer 2028 No No On track Yes. Project has been put on hold for 2 years due to slow
build out rates at Bertha Park.
Perth High School - New
School Investment
80,200 0 80,200 80,200 Summer 2026 - school
building curently
scheduled to open
summer 2025
Yes Yes On track Yes - on-site. Works are on programme for the school to open in
Augus 2025.
Harris
Academy/Invergowrie
Extension
5,200 0 5,200 5,200 Late 2023 Yes Yes On track Yes. Main extension complete, reconfiguration works still to be
undertaken.
Cross Tay Link Road
(CTLR) 150,500 40,000 110,500 110,500 Spring 2025 Yes Yes On programme No
Completion of project imminent with official opening
taking place on 31 March 2025. Site will remain
operational in light of works associated with completion
and defects e.g. as-built drawings, H&S file, minor
snagging, final landscaping and associated
maintenance.
Bertha Park Link Road 13,200 0 13,200 13,200 December 2026
Letter of
Intent Yes On programme N/a
Detailed design currently being undertaken by Sweco.
Letter of Intent issued to BAM UK & Ireland for advance
works with a view to awarding the Stage 1 contract in
June 2025 and Notice to Proceed to Stage 2 (main
construction) in August 2025. Site clearance has been
undertaken.
Comrie Flood Protection
Scheme 40,353 32,657 7,696 7,696 Autumn 2026 Yes Yes Contract awarded Yes
Works are on programme.
Site setup, site clearance and formation of construction
access routes are now largely complete.  Main civils
construction works commenced March 2025.
Perth Eco Innovation Park* 32,817 16,061 16,756 16,756
Not currently
programmed No No
Design package
awarded - design
programme on track Yes
[See previous reports in relation to funding.] Amey's
performance on the project deteriotated signficantly from
earlyl January 2025 - insufficiently resourced, changes in
personnel, programme delay, poor communications and
quality issues.  IN liaison with Legal, Default Notice was
issued in February, followed by a Termination Notice in
March. All outputs issued to PKC. JDLT advised.
Strategy and Scope being prepared to engage Trekelion
through Scape who have the ability to engage quickly
minimising programme risk. 
PH2O 90,000 0 90,000 90,000
Not currently
programmed No No
Thimblerow approved
as new site for Ph2O
project at Council on 4
September 2024. Yes
Project Board established, programme under
development, project no longer on hold.
* Third Party Funding excludes Developer Contributions and receipts to be received in future years beyond the current 6-year programme.