SIGNIFICANT CAPITAL PROJECTS
PROGRESS UPDATE
APPENDIX IV
Project Title Total
Gross
Budget
Third Party
Funding
(£'000)
Total Net
Budget
(£'000)
Projected
Outturn
(£'000)
Completion Date Contract
Awarded
On Site Status Change Since
Last Report
Additional Commentary
Blairgowrie Recreation
Centre - Replacement
36,000 0 36,000 36,000 Summer 2025 - new
centre currently
scheduled to open early
2025
Yes Yes On track Yes Work on programme for phase 1 completion early 2025.
North/West Perth New
Primary School*
24,000 0 24,000 24,000 Summer 2026 No No On track No Project has been put on hold for 2 years due to slow
build out rates at Bertha Park.
Riverside Primary New
School
19,899 0 19,899 19,899 Early summer 2023 Yes Yes Complete No Project complete.
Perth High School - New
School Investment
80,200 0 80,200 80,200 Summer 2026 - school
building curently
scheduled to open
summer 2025
Yes Yes On track No Works are on programme.
Harris
Academy/Invergowrie
Extension
5,200 0 5,200 5,200 Late 2023 Yes Yes On track No Main extension complete.
Cross Tay Link Road
(CTLR) 150,500 40,000 110,500 110,500 Spring 2025 Yes Yes On programme No
Main superstructure works on Destiny Bridge are
complete with finishing works being undertaken and
progressing on programme.  Primarily finishing,
snagging and testing works are being undertaken
elsewhere.No change to completion date.  Risks
signficantly reduced in period, with weather being the
main risk, particuarly in relation to the bridge surfacing.
Comrie Flood Protection
Scheme 40,353 32,657 7,696 7,696 Autumn 2026 Yes Yes Contract awarded Yes
Works are on programme.
Site setup, site clearance and formation of construction
access routes are ongoing.
Main civils construction works are on target to
commence from February 2025.
Perth Eco Innovation Park* 32,817 16,061 16,756 16,756
Not currently
programmed No No
Design package
awarded - design
programme on track Yes
[See previous reports in relation to funding.] Amey
continue with the design works package, with innovation
workshops held along with regular design meetings
involving JDLT's representative. Key risks include
liaison with Transport Scotland and determination of
innovation scope.Positive discussions continue with
JDLT in terms of s75, planning and design with last
meeting held on 17 Dec 2025.
PH2O 90,000 0 90,000 90,000
Not currently
programmed No No
Thimblerow approved
as new site for Ph2O
project at Council on 4
September 2024. Yes
Project Board established, programme under
development, project no longer on hold.
* Third Party Funding excludes Developer Contributions and receipts to be received in future years beyond the current 6-year programme.