Appendix II – Composite Capital Programme - Summary of Capital Resources and Expenditure 2024/25 to 2029/30
Perth and Kinross Council · 5 February 2025
Back to Finance and Resources Committee — 5 February 2025 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30 APPENDIX II Approved Proposed Revised Actuals Projected Revised Revised Revised Revised Revised Revised Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget 20-Nov-24 Adjustment 30-Nov-24 Report 2 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 2024/25 2024/25 2024/25 2024/25 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) ENVIRONMENT & INFRASTRUCTURE 37,187 (6,377) 30,810 15,666 30,810 46,773 36,167 22,639 17,896 16,103 170,388 HOUSING & COMMUNITIES 1,829 0 1,829 577 1,829 4,009 1,493 1,558 1,500 1,500 11,889 ECONOMY, DEVELOPMENT & PLANNING 51,840 (972) 50,868 22,825 50,868 12,457 32,843 (5,862) (2,150) (2,636) 85,520 PROPERTY SERVICES 68,197 615 68,812 40,834 68,812 55,876 52,803 48,867 35,000 22,500 283,858 CUSTOMER & DIGITAL SERVICES 8,418 (71) 8,347 2,614 8,347 5,995 5,219 10,222 8,502 5,911 44,196 HEALTH & SOCIAL CARE 962 100 1,062 573 1,062 1,649 1,390 1,306 1,320 170 6,897 UNALLOCATED CAPITAL RESOURCES 0 52 52 0 52 0 0 0 0 0 52 TOTAL NET EXPENDITURE 168,433 (6,653) 161,780 83,089 161,780 126,759 129,915 78,730 62,068 43,548 602,800 (NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS) GENERAL CAPITAL GRANT (27,103) 175 (26,928) (20,284) (26,928) (13,414) (19,255) (12,750) (12,750) (12,750) (97,847) DEVELOPER CONTRIBUTIONS (3,707) 0 (3,707) 0 (3,707) (2,367) (2,600) (2,600) (2,500) (2,500) (16,274) CAPITAL RECEIPTS (1,126) 0 (1,126) (378) (1,126) (937) 0 (1,088) 0 0 (3,151) ANNUAL BORROWING REQUIREMENT 136,497 (6,478) 130,019 62,427 130,019 110,041 108,060 62,292 46,818 28,298 485,528 CAPITAL RECEIPTS BROUGHT FORWARD (2,102) 0 (2,102) (2,102) (2,102) (1,120) (1,550) (1,550) (2,638) (2,638) (2,102) CAPITAL RECEIPTS CARRIED FORWARD 1,120 0 1,120 239 1,120 1,550 1,550 2,638 2,638 2,638 2,638 TOTAL NET BORROWING REQUIREMENT 135,515 (6,478) 129,037 60,564 129,037 110,471 108,060 63,380 46,818 28,298 486,064
Page 2
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30 APPENDIX II Revised Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Adjustment 30-Nov-24 Report 2 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 2024/25 2024/25 2024/25 2024/25 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) ENVIRONMENT & INFRASTRUCTURE Traffic & Road Safety Road Safety Initiatives (20mph Zones etc..) 335 383 718 15 718 362 362 361 400 400 2,603 Scottish Government Grant 0 (383) (383) (383) 0 0 0 0 0 (383) Road Safety Initiatives - A94 Safety Improvements 84 84 84 0 0 0 0 0 84 Active Travel Grant -Traffic & Road Safety Schemes 739 77 816 251 816 600 600 600 600 600 3,816 Third Party Contribution 0 (77) (77) (77) 0 0 0 0 0 (77) Additional Road Safety - Pedestrian Crossings 60 60 60 246 153 0 0 0 459 Schools Road Safety Measures 122 122 185 122 0 0 0 0 0 122 20mph Signage Programme - Schools 128 128 3 128 0 0 0 0 0 128 20mph Signage Programme 39 39 25 39 0 0 0 0 0 39 Car Parking Investment - Pitlochry 205 205 94 205 0 0 0 0 0 205 Revenue Contribution (55) (55) (55) 0 0 0 0 0 (55) Sub-Total 1,657 0 1,657 573 1,657 1,208 1,115 961 1,000 1,000 6,941 Asset Management - Roads & Lighting Structural Maintenance 10,911 2,436 13,347 9,422 13,347 8,963 8,963 8,964 8,320 8,320 56,877 Third Party Contribution 0 (262) (262) (114) (262) 0 0 0 0 0 (262) Revenue Contribution 0 0 (16) 0 0 0 0 0 0 0 Traffic Signal Renewals - Upgrading 173 173 77 173 100 100 100 100 100 673 Footways 415 207 622 500 622 368 368 368 341 341 2,408 Street Lighting 0 0 0 0 0 0 600 600 1,200 Investment in Local Footpaths 0 0 0 20 100 0 0 0 120 Road Safety Barriers 22 22 24 22 0 0 0 0 0 22 Sub-Total 11,521 2,381 13,902 9,893 13,902 9,451 9,531 9,432 9,361 9,361 61,038 Asset Management - Bridges Bridge Refurbishment Programme 1,233 50 1,283 575 1,283 2,723 2,520 3,201 2,000 2,000 13,727 Vehicular Bridge Parapets Programme - Assess & Upgrade 1 1 1 33 0 0 0 0 34 Old Perth Bridge - Strengthening 155 155 25 155 2,380 0 0 0 0 2,535 Perth Queens Bridge - Strengthening 59 59 44 59 154 2,143 0 0 0 2,356 Garry Viaduct 372 (326) 46 15 46 321 515 1,790 1,690 0 4,362 Culteuchar Culvert 8 5 13 14 13 0 0 0 0 0 13 Sub-Total 1,828 (271) 1,557 673 1,557 5,611 5,178 4,991 3,690 2,000 23,027 Improvement Schemes A977 Upgrades 1 4 5 5 173 0 0 0 0 178 Broich Road, Crieff - Road Realignment & Safety Measures 0 0 0 18 0 0 0 0 18 Sub-Total 1 4 5 0 5 191 0 0 0 0 196 Rural Flood Protection Schemes Perth Flood Protection Scheme (South Inch Culvert Reinstatement) 259 259 49 259 0 0 0 0 0 259 Comrie Flood Protection Scheme 10,475 (4,282) 6,193 456 6,193 21,481 7,830 0 0 0 35,504 Milnathort Flood Protection Scheme 256 (184) 72 2 72 267 0 0 0 0 339 South Kinross Flood Protection Scheme 418 (179) 239 58 239 1,962 8,823 3,150 75 0 14,249 Scone Flood Protection Scheme 50 50 2 50 69 68 535 45 0 767 Flood Mitigation Measures - Dunkeld and Craigie Burn 8 8 7 8 72 48 180 375 317 1,000 Coastal Change Adaptation 100 (52) 48 1 48 52 0 0 0 0 100 Sub-Total 11,566 (4,697) 6,869 575 6,869 23,903 16,769 3,865 495 317 52,218 Climate Change Nature Restoration 232 232 22 232 0 0 0 0 0 232 Sub-Total 232 0 232 22 232 0 0 0 0 0 232 Waste Strategy Recycling Improvement Fund 202 (104) 98 98 98 0 0 0 0 0 98 Scottish Government Grant (98) (98) (98) (98) 0 0 0 0 0 (98) Sub-Total 104 (104) 0 0 0 0 0 0 0 0 0 Prudential Borrowing Projects Wheeled Bin Replacement Programme - Domestic Bins 267 267 132 267 200 200 200 220 220 1,307 Wheeled Bin Replacement Programme - Commercial Bins 57 104 161 104 161 20 20 20 25 25 271 Recycling Containers, Oil Banks & Battery Banks Replacement Progr 209 209 131 209 105 105 105 70 70 664 Capital Receipts - Disposals (2) (2) (5) (2) 0 0 0 0 0 (2)
Page 3
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30 APPENDIX II Revised Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Adjustment 30-Nov-24 Report 2 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 2024/25 2024/25 2024/25 2024/25 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) Litter Bins 50 50 8 50 50 50 50 55 55 310 Vehicle Replacement Programme 9,271 (3,776) 5,495 3,288 5,495 5,777 2,942 2,692 3,311 3,394 23,611 Capital Receipts - Vehicle Disposals (587) 37 (550) (222) (550) (578) (294) (269) (331) (339) (2,361) Street Lighting Renewal - LED & Column Replacement 1,013 (55) 958 494 958 835 551 592 0 0 2,936 Sub Total 10,278 (3,690) 6,588 3,930 6,588 6,409 3,574 3,390 3,350 3,425 26,736 TOTAL - ENVIRONMENT & INFRASTRUCTURE 37,187 (6,377) 30,810 15,666 30,810 46,773 36,167 22,639 17,896 16,103 170,388 HOUSING & COMMUNITIES Community Greenspace Play Areas - Improvements Implementation Strategy 641 641 150 641 872 150 150 500 500 2,813 Third Party Contribution (4) (4) (4) 0 0 0 0 0 (4) 3G Pitch, Blairgowrie 117 117 75 117 0 0 0 0 0 117 Settlement/Neighbourhood Parks 250 250 109 250 300 0 0 0 0 550 Third Party Contribution (84) (84) (84) 0 0 0 0 0 (84) Countryside Sites 0 0 0 0 0 139 0 0 139 Community Greenspace Sites 0 0 0 654 898 894 700 700 3,846 Community Greenspace Bridges 197 197 94 197 0 0 0 0 0 197 Third Party Contribution (13) (13) (13) 0 0 0 0 0 (13) Revenue Contribution 0 0 0 0 0 0 0 0 0 Core Path Implementation 110 110 110 0 0 0 0 0 110 Third Party Contribution (110) (110) (110) 0 0 0 0 0 (110) Premier Parks 46 46 21 46 0 0 0 0 0 46 Third Party Contribution (14) (14) (10) (14) 0 0 0 0 0 (14) Kinnoull Hill 8 8 8 0 0 0 0 0 8 Cemetery Extensions 13 13 13 13 60 445 375 300 300 1,493 Sub-Total 1,157 0 1,157 452 1,157 1,886 1,493 1,558 1,500 1,500 9,094 Housing Projects Gypsy Travellers Site Improvement Works 185 185 2 185 0 0 0 0 0 185 Additional Gypsy Traveller Site Improvement Works 225 225 18 225 0 0 0 0 0 225 New Gypsy Traveller Site 6 6 6 1,990 0 0 0 0 1,996 Sub Total 416 0 416 20 416 1,990 0 0 0 0 2,406 Public Transport Community Transport Iniatives 181 181 105 181 18 0 0 0 0 199 Sub-Total 181 0 181 105 181 18 0 0 0 0 199 Prudential Borrowing Projects Community Transport Vehicles 0 0 0 115 0 0 0 0 115 Sub Total 0 0 0 0 0 115 0 0 0 0 115 Community Planning Community-Led Asset Transfers 75 75 75 0 0 0 0 0 75 Sub-Total 75 0 75 0 75 0 0 0 0 0 75 TOTAL - HOUSING & COMMUNITIES 1,829 0 1,829 577 1,829 4,009 1,493 1,558 1,500 1,500 11,889 ECONOMY, DEVELOPMENT & PLANNING Improvement Schemes A9/A85 Road Junction Improvements 212 212 212 0 0 0 0 0 212 Cross Tay Link Road (CTLR) 44,745 44,745 20,102 44,745 0 0 0 0 0 44,745 Bertha Park Link Road 686 686 594 686 400 10,000 1,808 0 0 12,894 Sub-Total 45,643 0 45,643 20,696 45,643 400 10,000 1,808 0 0 57,851 Perth & Kinross Place-making Perth, Place, People 0 0 0 0 3,598 0 0 0 3,598 Perth City Centre Golden Route (Rail Station) 68 (45) 23 24 23 45 0 0 0 0 68 City Greening 31 (31) 0 0 31 0 0 0 0 31 Perth & Kinross Lighting Action Plan 1,320 (844) 476 77 476 844 0 0 0 0 1,320 Sub-Total 1,419 (920) 499 101 499 920 3,598 0 0 0 5,017 Other Planning Projects Creative Exchange (former St. John's Primary School) 52 (52) 0 0 0 0 0 0 0 0
Page 4
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30 APPENDIX II Revised Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Adjustment 30-Nov-24 Report 2 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 2024/25 2024/25 2024/25 2024/25 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) Local Full Fibre Network 0 0 0 0 0 0 0 0 0 Third Party Contribution - Tay Cities Deal 0 0 (53) 0 0 0 0 0 0 0 Low Carbon Transport & Active Travel Hub - Broxden EV Chargers (74) (74) 5 (74) 0 0 0 0 0 (74) Third Party Contribution - ERDF (2) (2) (2) 0 0 0 0 0 (2) Third Party Contribution - Tay Cities Deal 69 69 69 0 0 0 0 0 69 Revenue Contribution 7 7 7 0 0 0 0 0 7 Perth Eco-Innovation Park at Perth West 780 780 135 780 9,737 22,300 0 0 0 32,817 Third Party Contributions - Tay Cities Deal 0 0 0 (550) (505) (3,945) (500) (956) (6,456) Other Third Party Contributions 0 0 0 0 (2,000) (3,000) (1,000) (1,000) (7,000) Capital Receipts - Ring Fenced Land Disposals 0 0 0 0 (550) (725) (650) (680) (2,605) Economic Development Investment - Land & Serviced Units 1,000 1,000 1,000 1,000 0 0 0 0 2,000 Adapt Your Property - Vacant Town & City Centre Space 300 300 9 300 0 0 0 0 0 300 Sub-Total 2,132 (52) 2,080 96 2,080 10,187 19,245 (7,670) (2,150) (2,636) 19,056 Commercial Property Investment Programme North Muirton Industrial Estate - Site Servicing & Provision of Units 43 43 43 0 0 0 0 0 43 Broxden Business Park - Additional Infrastructure 6 6 6 0 0 0 0 0 6 Western Edge, Kinross - Site Servicing (17) (17) 17 (17) 0 0 0 0 0 (17) Broxden Drainage Mitigation Works 1,225 1,225 1,915 1,225 0 0 0 0 0 1,225 Third Party Contribution (Scottish Water) (919) (919) (919) 0 0 0 0 0 (919) Ruthvenfield Business Centre 1,356 1,356 1,356 0 0 0 0 0 1,356 North Muirton Drainage 2 2 2 0 0 0 0 0 2 Sub-Total 1,696 0 1,696 1,932 1,696 0 0 0 0 0 1,696 Prudential Borrowing Projects Land Purchase & Development (Hotel Development) 950 950 950 950 0 0 0 0 1,900 Sub Total 950 0 950 0 950 950 0 0 0 0 1,900 TOTAL - ECONOMY, DEVLOPMENT & PLANNING 51,840 (972) 50,868 22,825 50,868 12,457 32,843 (5,862) (2,150) (2,636) 85,520 PROPERTY SERVICES Project Support Investment in the Learning Estate 1,591 1,591 1,081 1,591 13,050 8,650 6,823 0 0 30,114 Methven Primary School Refurbishment 206 206 42 206 3,500 300 0 0 0 4,006 Kirkmichael Primary School Upgrades 25 25 25 25 0 0 0 0 0 25 North/West Perth - New Primary School 0 0 0 341 7,672 15,400 0 0 23,413 Riverside Primary New School 483 483 324 483 0 0 0 0 0 483 Perth Academy - Refurbishment 1,699 1,351 3,050 2,291 3,050 1,650 299 0 0 0 4,999 Perth Grammar School - Upgrade Programme Phase 3 1,000 1,000 538 1,000 1,500 1,488 0 0 0 3,988 Perth High School - Internal Services & Refurbishment 12 12 12 0 0 0 0 0 12 Perth High School - New School Investment 40,899 40,899 21,831 40,899 6,600 3,600 0 0 0 51,099 Harris Academy/Invergowrie - Extension 591 591 21 591 0 0 0 0 0 591 Blairgowrie Recreation Centre - Replacement 15,327 15,327 11,744 15,327 1,303 0 0 0 0 16,630 Technology Upgrades 76 39 115 82 115 771 483 0 0 0 1,369 Sub-Total 61,909 1,390 63,299 37,979 63,299 28,715 22,492 22,223 0 0 136,729 Project & Contracts Free School Meal Expansion Programme 0 0 0 1,000 2,511 0 0 0 3,511 Community Campus Access Adaptations 15 (15) 0 0 25 0 0 0 0 25 Sub-Total 15 (15) 0 0 0 1,025 2,511 0 0 0 3,536 Property Service Manager DDA Adaptation & Alteration Works Programme 230 (100) 130 28 130 300 200 200 0 0 830 Property Compliance Works Programme 1,017 1,017 657 1,017 650 650 400 0 0 2,717 Capital Improvement Projects Programme 2,265 2,265 1,285 2,265 1,800 1,800 894 10,000 10,000 26,759 Pitlochry High School - Upgrade Programme 164 (60) 104 97 104 60 0 0 0 0 164 Friarton Depot - Waste Transfer Station 250 250 143 250 2,531 0 0 0 0 2,781 Energy Efficiency Works - Various Properties 0 36 36 36 0 0 0 0 0 36 Revenue Contribution (Salix Reserve) 0 (36) (36) (36) 0 0 0 0 0 (36) Letham Community Wellbeing Hub 133 (38) 95 95 0 0 0 0 0 95 Third Party Contribution (Letham4All) (38) 38 0 0 0 0 0 0 0 0 PH2O 500 500 500 2,000 25,000 25,000 25,000 12,500 90,000 Crieff Drummond Arms - Regeneration 0 0 0 3,000 0 0 0 0 3,000
Page 5
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30 APPENDIX II Revised Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Adjustment 30-Nov-24 Report 2 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 Report 3 2024/25 2024/25 2024/25 2024/25 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) Perth Museum 167 167 167 0 0 0 0 0 167 Perth Art Gallery 100 100 100 2,795 0 0 0 0 2,895 Sub-Total 4,788 (160) 4,628 2,210 4,628 13,136 27,650 26,494 35,000 22,500 129,408 Prudential Borrowing Projects Decarbonisation 1,339 (600) 739 558 739 600 0 0 0 0 1,339 Energy Conservation & Carbon Reduction Programme 146 146 87 146 150 150 150 0 0 596 Pullar House - Purchase & Re-Purposing 0 0 0 10,000 0 0 0 0 10,000 Kinnoull Street Car Park - Purchase 0 0 0 2,250 0 0 0 0 2,250 Sub-Total 1,485 (600) 885 645 885 13,000 150 150 0 0 14,185 TOTAL - PROPERTY SERVICES 68,197 615 68,812 40,834 68,812 55,876 52,803 48,867 35,000 22,500 283,858 CUSTOMER & DIGITAL SERVICES ICT Infrastructure Replacement and Upgrade Programme 4,927 4,927 1,308 4,927 3,112 3,273 7,698 6,472 3,687 29,169 Data & Analytics 600 600 28 600 1,206 720 708 716 733 4,683 Supporting Digital 750 750 161 750 1,175 928 1,185 914 920 5,872 Software Licences (Revenues & Benefits) 51 51 52 51 51 51 49 0 0 202 School Audio-Visual (AV) Equipment Replacement Programme 196 (71) 125 231 125 35 106 35 300 471 1,072 Mosaic - Swift Social Work System Replacement 1,712 1,712 828 1,712 430 180 586 0 0 2,908 Revenue Contribution 0 0 0 (124) (124) (124) 0 0 (372) Hardware 22 22 6 22 15 14 14 25 25 115 Licenses 80 80 80 95 71 71 75 75 467 Case Management System 80 80 80 0 0 0 0 0 80 TOTAL - CUSTOMER & DIGITAL SERVICES 8,418 (71) 8,347 2,614 8,347 5,995 5,219 10,222 8,502 5,911 44,196 HEALTH & SOCIAL CARE Occupational Therapy Equipment 300 350 650 226 650 250 250 150 250 100 1,650 Technology Enabled Telecare 610 (250) 360 333 360 1,088 1,087 1,087 1,000 0 4,622 Moving & Handling Office Refurbishment 0 0 0 29 0 0 0 0 29 Software Licences 52 52 14 52 53 53 69 70 70 367 Developing Supported Tenancies 0 0 0 229 0 0 0 0 229 TOTAL - HEALTH & SOCIAL CARE 962 100 1,062 573 1,062 1,649 1,390 1,306 1,320 170 6,897 Unallocated Capital Resources 0 52 52 52 0 0 0 0 0 52 TOTAL COMPOSITE NET EXPENDITURE 168,433 (6,653) 161,780 83,089 161,780 126,759 129,915 78,730 62,068 43,548 602,800 (NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS) CAPITAL INCOME & RECEIPTS General Capital Grant - Scottish Government (27,103) 175 (26,928) (20,284) (26,928) (13,414) (19,255) (12,750) (12,750) (12,750) (97,847) Developer Contributions (3,707) (3,707) (3,707) (2,367) (2,600) (2,600) (2,500) (2,500) (16,274) General Fund - Capital Receipts/Disposal (413) 0 (413) (309) (413) (507) 0 0 0 0 (920) Commercial Property - Capital Receipts/Disposal (713) 0 (713) (69) (713) (430) 0 (1,088) 0 0 (2,231) Total: Capital Receipts (31,936) 175 (31,761) (20,662) (31,761) (16,718) (21,855) (16,438) (15,250) (15,250) (117,272) Annual Composite Borrowing Requirement 136,497 (6,478) 130,019 62,427 130,019 110,041 108,060 62,292 46,818 28,298 485,528 CAPITAL RECEIPTS BROUGHT FORWARD (2,102) 0 (2,102) (2,102) (2,102) (1,120) (1,550) (1,550) (2,638) (2,638) (2,102) CAPITAL RECEIPTS CARRIED FORWARD 1,120 0 1,120 239 1,120 1,550 1,550 2,638 2,638 2,638 2,638 TOTAL NET COMPOSITE BORROWING REQUIREMENT 135,515 (6,478) 129,037 60,564 129,037 110,471 108,060 63,380 46,818 28,298 486,064
Page 6
Project Project Description ENVIRONMENT & INFRASTRUCTURE Traffic & Road Safety Road Safety Initiatives (20mph Zones etc.) A programme of works to improve road safety Road Safety Initiatives - A94 Safety Improvements A programme of works to improve road safety Active Travel Grant - Traffic & Road Safety Schemes A programme of works to improve active travel Additional Road Safety - Pedestrian Crossings A programme of works to provide pedestrian crossing facilities Schools Road Safety Measures A programme of works to improve road safety in the vicinity of schools 20mph Signage Programme - Schools A programme of works to improve road safety in the vicinity of schools 20mph Signage Programme A programme of works to introduce 20mph speed limits. Car Parking Investment - Pitlochry Purchase of land and construction of a public car park Roads & Lighting Structural Maintenance Road maintenance to extend the life of roads, including predominately road resurfacing, surface dressings, installing new drainage infrastructure and repairs to and replacement of defective embankments and retaining walls Traffic Signal Renewals - Upgrading A programme of works to upgrade existing traffic signal infrastructure Footways Replacement of existing deteriorated footway surfaces Street Lighting Replacement of existing street lighting lanterns, columns and cable network. Investment in Local Footpaths A programme of works to improve and provide local footpaths Road Safety Barriers Renewal of existing barriers where unrecoverable damage has occurred and renewal of barriers where timber posts have been used in construction Bridges Bridge Refurbishment Programme Used to appoint specialist external inspection teams and consultants to carry out specialist access bridge inspections and assessments Vehicular Bridge Parapets Programme - Assess & Upgrade Assessment and Upgrading of Vehicle Parapets Programme Old Perth Bridge - Strengthening Carry out works recommended by the 2018 Bridge Assessment study, including a range of assessment, investigation, strengthening and improvement works Perth Queens Bridge - Strengthening Carry out works recommended by the 2018 Bridge Assessment study, including a range of assessment, investigation, strengthening and improvement works Garry Viaduct Replacement of Bearings and Parapets; including strengthening of deck for bearing replacement jacking up, and to cater for increased parapet vehicular deterrent capacity Culteuchar Culvert Replace existing temporary steel bridge (on hire) with culvert Improvement Schemes A977 Upgrades A programme of works to improve road safety along the A977. Broich Road, Crieff - Road Realignment & Safety Measures Complete Rural Flood Protection Schemes Perth Flood Protection Scheme (South Inch Culvert Reinstatement) Ground investigation and monitoring then design project to refurbish existing culvert Comrie Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in Comrie Milnathort Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in Milnathort South Kinross Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in South Kinross Scone Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in Scone Flood Mitigation Measures - Dunkeld and Craigie Burn Design and construction of schemes to reduce the risk of flooding in Dunkeld and Craigie Burn Coastal Change Adaptation Design and construct projects to deal with incidents of coastal erosion Climate Change Nature Restoration Protection and restoration of biodiversity focusing on over-exploitation of the natural environment and addressing its consequences; habitat loss and fragmentation; and invasive non-native species. Waste Strategy Recycling Improvement Fund Complete Prudential Borrowing Projects Wheeled Bin Replacement Programme - Domestic Bins Replacement of damaged and end of life wheeled bins for households. Also suppling bins for new properties Wheeled Bin Replacement Programme - Commercial Bins Replacement of damaged and end of life wheeled bins for commercial customers. Also suppling bins for new customers and changes to collection contracts Recycling Containers, Oil Banks & Battery Banks Replacement Programme Replacement of damaged and end of life oil and battery banks Litter Bins Replacement of damaged and end of life litter bins and/or for general supply of litter bins where required. Vehicle Replacement Programme Fleet vehicle replacement programme
Page 7
Project Project Description Street Lighting Renewal - LED & Column Replacement Street Lighting LED conversion and column replacement programme HOUSING & COMMUNITIES Community Greenspace Play Areas - Improvements Implementation Strategy Regular refurbishment of 146 play areas based on approx. 6-8 per year. Involves community engagement and often co-funding and design of the sites 3G Pitch, Blairgowrie Two phase community led project to provide a new full sized 3G football pitch and pavilion Settlement/Neighbourhood Parks Refurbishment of neighbourhood parks working in partnership with communities to improve, update and renew worn out or obsolete infrastructure Countryside Sites Refurbishment of more natural parks and open spaces Community Greenspace Sites Main fund for all Community Greenspace Sites which is drawn down to support the overall capital programme of refurbishments and upgrades Community Greenspace Bridges Refurbishment programme for all bridges on Community Greenspace sites Core Path Implementation Holding budget for Crieff Comrie Core path development mainly funded through Sustrans Premier Parks Small budget to facilitate refurbishment of former Premier Park upgrades Kinnoull Hill Complete Cemetery Extensions Funding to allow the extension of existing or development of new cemeteries to address the pressure for burial space Housing Projects Gypsy Travellers Site Improvement Works Programme of works for improvements on Gypsy Traveller sites at Bobbin Mill and Double Dykes Additional Gypsy Traveller Site Improvement Works Additional funding to support improvements works programme on Gypsy Traveller sites New Gypsy Traveller Site Feasibility Study for Gypsy Traveller Transient Site Public Transport Community Transport Iniatives Purchase of vehicles and charging infrastructure for community transport/resilience groups to use to deliver on unmet need in the local area. Community Planning Community-Led Asset Transfers Financial assistance for community groups wishing to take on PKC assets using the community asset transfer process ECONOMY, DEVELOPMENT & PLANNING Improvement schemes A9/A85 Road Junction Improvements New infrastructure including a new A9 overbridge, a bridge over the River Almond and road linking the A85 to Inveralmond and Bertha Park (Phase 1 of Perth Transport Futures Project) - Complete Cross Tay Link Road (CTLR) New road and major structure over the River Tay, linking the A9 north of Inveralmond and the A94 north of Scone (Phase 2 of Perth Transport Futures Project). Bertha Park Link Road Phase 3 of Perth Transport Futures Project which is a new link road (1.4km) running through Bertha Park, connecting Phases 1 and 2. Status - specimen design underway. Perth & Kinross Place-making Perth, Place, People Design and development of sustainable transport corridors to improve access to and from Perth and enable additional development and improvement within Perth city centre Perth City Centre Golden Route (Rail Station) Design and development of improvements to access, signage and animation from rail and bus station to Perth city centre to complement improvements to integration of transport City Greening Improvements to support enhancement of retail trading environment and residential areas and enhanced use of space for markets, events and alfresco use Perth & Kinross Lighting Action Plan Architectural and creative lighting to enhance city and towns appearance, reduce energy cost and increase safety at nighttime to increase dwell time, support the hospitality sector, events and grow the evening economy Other Planning Projects Creative Exchange (former St. John's Primary School) Repurposing old school to offer space to creative industry businesses and create the Famous Grouse Idea Centre, a space to support business innovation. Complete Local Full Fibre Network Provision of gigabit fibre connectivity to Council's buildings to unlock gigabit connectivity for surrounding communities. Complete Low Carbon Transport & Active Travel Hub - Broxden EV Chargers Provision of fast EV chargers combined with solar power generation and battery storage at Broxden Park & Ride - Near completion
Page 8
Project Project Description Perth Eco-Innovation Park at Perth West Provision of enabling infrastructure (access road, A9 underpass and unit platforms) to develop 25ha of employment land supporting clean growth, business innovation and jobs - Phase 1 (11ha). Economic Development Investment - Land & Serviced Units Provision of serviced lands and business units - Additional business units (eg Northfields Business Park and Kinross Business Park) - procurement for design in progress followed by construction. Adapt Your Property - Vacant Town & City Centre Space Adapt Your Property supports capital adaptation works to empty and underused commercial property in city & town centres, looking at adaptation to attract new commercial, community or residential use. Commercial Property Investment Programme North Muirton Industrial Estate - Site Servicing & Provision of Units Only road adoption works remaining Broxden Business Park - Additional Infrastructure Only road adoption works remaining Western Edge, Kinross - Site Servicing Only road adoption works remaining Broxden Drainage Mitigation Works Drainage/pumping station works underway and subject to agreement/contribution from Scottish Water Ruthvenfield Business Centre Works on redevelopment in progress North Muirton Drainage Drainage/pumping station underway Prudential Borrowing Project Land Purchase & Development (Hotel Development) Development agreement secured and release of grant for heritage subject to progression through planning and cost evidence STRATEGY, PEOPLE & RESOURCES Property Services - Project Support Investment in the Learning Estate Investment to upgrade the infrastructure and environment of our existing school estate Methven Primary School Refurbishment Upgrade of Methven Primary School facilities Kirkmichael Primary School Upgrades Upgrade of Kirkmichael Primary School facilities North/West Perth - New Primary School New primary school located at Bertha Park Riverside Primary New School Replacement of North Muirton and Balhousie primary schools Perth Academy - Refurbishment Investment to upgrade the infrastructure and environment of the Perth Academy including structural work to sports block, lighting upgrades, classroom upgrades and science block cladding Perth Grammar School - Upgrade Programme Phase 3 Investment to upgrade the infrastructure and environment of the Perth Grammar School including structural work to assembly hall, AV and WiFi upgrades, classroom refurbishment and door upgrades Perth High School - Internal Services & Refurbishment Necessary works to the infrastructure and environment of the current Perth High School Perth High School - New School Investment Replacement of the existing Perth High School Harris Academy/Invergowrie - Extension Extension and reconfiguration of existing space at Harris Academy in Dundee for continuation of access for pupils based in Invergowrie Blairgowrie Recreation Centre - Replacement Replacement of the Recreation Centre in Blairgowrie Technology Upgrades Upgrade to practical teaching environment within the existing school estate Property Services - Projects & Contracts Free School Meal Expansion Programme Upgrading kitchen and dining facilities to provide the enhanced Free School Meals programme Community Campus Access Adaptations To support adaptations in schools and community campuses to help facilitate increased community access Property Services - Property Service Manager DDA Adaptation & Alteration Works Programme To provide unhindered accessibility to all Council Buildings - e.g. Ramps/Lifts/Door Access/Accessible Toilets and Changing Areas Property Compliance Works Programme To ensure compliance with current and changing legislation including - New Fire Alarms; Lighting; Wiring; Fire Protection Works; Gas pipework within buildings and Roof Restraint safety systems Capital Improvement Projects Programme Roof Upgrades; Full internal refurbishment works; New Heating Systems; Boilers and pipework; Structural Upgrades; Small extensions; New Windows/Doors; New Fencing; New Cladding Pitlochry High School - Upgrade Programme Upgrades to Mechanical and Electrical Infrastructure, including rewiring, heating and controls systems, replacement lighting and consequential building works such as new ceilings, painting and flooring Friarton Depot - Waste Transfer Station This project aims to refurbish the main waste transfer station building to provide a safe environment for workers. The project will involve a complete re-cladding of the existing structure, new doors and new services installation. Some initial enabling work are being carried out currently. Energy Efficiency Works - Various Properties Focusing on a spend to save with projects aiming to reduce energy cost across the property estate Letham Community Wellbeing Hub Complete
Page 9
Project Project Description PH2O Replacement of Perth Leisure Pool and Dewars Ice Rink. On hold pending outcome of Leisure and Culture Assets Review Crieff Drummond Arms - Regeneration Demolition of former hotel, regeneration of site for housing use Perth Museum Complete Perth Art Gallery Refurbishment of temporary galleries - scheduled for completion November 2023 Prudential Borrowing Projects Decarbonisation This budget will support PKCs path to NetZero and focus primarily on the de- carbonisation of heat and replacing inefficient direct emissions heat sources Energy Conservation & Carbon Reduction Programme This budget is focused on works to reduce PKC energy consumption and help achieve annual KPI energy reduction of 3% Pullar House - Purchase & Re-Purposing Purchase and development of Pullar House to create a shared Public Sector Hub Kinnoull Street Car Park - Purchase Purchase of Kinnoull Street Multi-Storey Car Park to increase Perth and Kinross Council car parking capacity to support delivery of the Perth City Integrated Investment Proposal Customer & Digital Services ICT Infrastructure & Replacement and Upgrade Programme This Programme delivers the IT / digital environment, digital resources and systems required by staff and young people. The programme maintains, supports and develops computers; networks; telephony; Microsoft systems; connectivity and equipment; datacentres; servers; file storage and back up; security systems and video conferencing Data & Analytics Delivers the governance, tools, technologies and organisation-wide skills required for optimising value from Council data, driving informed decision making around resources, priorities and service delivery targets Supporting Digital Develops the capabilities we need to be an innovative digital organisation. Including developing the Council’s corporate employee (mobile working) and customer (online services) platforms, to create new digital products and services; investment in tools such as Microsoft; resourcing innovation and building digital skills, insight and expertise Software Licences (Revenues & Benefits) NAC Live system licensing for Revenues & Benefits team School Audio-Visual (AV) Equipment Replacement Programme Ensures all Perth and Kinross classrooms have equitable access to audio visual panels and the digital skills to exploit these resources for learning and teaching Mosaic - Swift Social Work System Replacement Purchase and Development of a new Social Work system to replace SWIFT Hardware Funding of additional or bespoke IT Hardware for Communities Staff Licenses Funding of software contracts Case Management System New system for management of client cases HEALTH & SOCIAL CARE Occupational Therapy Equipment Supply and install of occupational therapy equipment following referral from heakth and social care professionals. Technology Enabled Telecare Replacement of existing analogue Community Alarm devices to digital alarm units prior to UK switch-off of analogue network, as well as ongoing rolling replacement programme. Moving & Handling Office Refurbishment Relocate staff base, currently under review Software Licences Various licences for essential social care systems Developing Supported Tenancies Contribution towards flagship core and cluster facility for adults with learning disabilities’