Democracy Spraffa

Composite Capital Budget 2024/30 and Housing Investment Programme 2024/29 – Monitoring Report No.3

Perth and Kinross Council · 5 February 2025
Back to Finance and Resources Committee — 5 February 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Perth and Kinross Council 
Finance and Resources Committee 
5 February 2025 
Composite Capital Budget 2024/30 and Housing Investment Programme
2024/29 – Monitoring Report No.3 
Report by Chief Finance Officer
(Report No. 25/25) 
1. Purpose 
1.1 This report provides a summary position to date for the 6-year Composite
Capital Budget for 2024/25 to 2029/30 and the 5-year Housing Investment
Programme for 2024/25 to 2028/29 and seeks approval for adjustments to the
programmes. 
2. Recommendations 
2.1 It is recommended that the Committee: 
(i) notes the contents of the report.
(ii) approves the proposed adjustments to the six-year Composite Capital
Budget 2024/25 to 2029/30 set out in Sections 5 and 6 of the report
and summarised in Appendices I and II.
(iii) approves the proposed adjustments to the Housing Investment
Programme Budget 2024/25 to 2028/29 set out in Section 7 of the
report and summarised in Appendix III.
(iv) notes progress with the delivery of major Capital projects as
summarised in Appendix IV. 
3. Structure 
3.1 The report is structured over the following sections: 
• Section 4: Background / Main Issues
• Section 5: Composite Capital Programme – Gross Capital Resources
• Section 6: Composite Capital Programme – Expenditure
• Section 7: Housing Investment Programme
• Section 8: Summary 
4. Background / Main Issues 
4.1 The Finance and Resources Committee approved an updated six-year gross
Composite Capital Budget for 2024/25 to 2029/30 totalling £619.672 million
and a five-year gross Housing Investment Programme for 2024/25 to 2028/29
totalling £96.917 million at its meeting on 20 November 2024 (report 24/319
refers). A separate report at that meeting (report 24/321) approved a further
£3 million in 2025/26 in respect of the demolition and regeneration of the

Page 2

Drummond Arms in Crieff, which has now been included in the budget at
Appendix II. This therefore took the Composite Capital Programme to a
revised total of £622.672 million. 
4.2 This report advises on expenditure to 30 November 2024, and the latest
estimate of the projected outturn for each of the years to 2029/30 for the
Composite Programme and 2028/29 for the Housing Investment Programme. 
5. Composite Capital Programme – Gross Capital Resources 
5.1 As a result of the latest monitoring exercise, further adjustments to the budget
are proposed. The current estimated total gross capital resources (which
includes movements in Capital Receipts, Capital Grants, Contributions and
borrowing) available over the six years 2024/25 to 2029/30 amount to
£623.577 million. 
5.2 Movements from the revised Composite Capital Budget approved on 20
November 2024 for the six years are summarised in the table below, and the
constituent elements for each year are shown in Appendix I. 
Total Gross Composite Capital Resources 
Approved 
20 Nov 2024
Current
Estimate
Movement 
£m £m £m
2024/25 170.283 164.313 (5.970)
2025/26 117.177 128.011 10.834
2026/27 136.685 133.388 (3.297)
2027/28 84.962 86.793 1.831
2028/29 65.787 64.549 (1.238)
2029/30 47.778 46.523 (1.255)
Total 622.672 623.577 0.905  
5.3 The above movements can be summarised as follows: 
Total 
£m
Increase in Scottish Government Grant (Section 5.4) 0.383
Increase in Ring Fenced Capital Receipts (Section 5.5) 0.148
Increase in Third Party Contributions (Section 5.6)  0.301
Increase in Revenue Contributions (Section 5.6)  0.036
Increase in Borrowing Requirement (Section 5.7 and 5.8) 0.037
Increase in Gross Capital Resources (Section 5.2) 0.905 
5.4 The Scottish Government allocated a Capital Grant of £383,000 in 2024/25
under the Road Safety Fund Initiative (Section 6.2.2). The only other
movement in Capital Grants across the 6-year programme is the deferral of
the Nature Restoration Fund grant of £175,000 in 2024/25 to 2025/26, as part
of the Scottish Government’s support for the 2024/25 pay award.

Page 3

5.5 Ring Fenced Capital Receipts for vehicle disposals have been revised as part
of the review of the Fleet Replacement programme, with an overall increase of
£148,000 across the 6-year programme (Section 6.2.8). 
5.6 There is an increase of £301,000 in Third Party Contributions, with additional
contributions towards Active Travel (£77,000, Section 6.2.2) and Structural
Maintenance (£262,000, Section 6.2.3), offset by a reduction on the Letham
Community Wellbeing Hub (£38,000, Section 6.4.5), in line with estimated
expenditure remaining on the project. There is also an increase in Revenue
Contributions on the Property Energy Efficiency programme, with a proposed
drawdown of £36,000 from the Salix Reserve (Section 6.4.4). 
5.7 The projected borrowing requirement in 2024/25, which is effectively the
balancing item for resources, is £129.037 million. This is £6.478 million
lower than the borrowing requirement approved by this Committee on 20
November 2024. 
5.8 The total borrowing requirement in the subsequent years 2025/26 to 2029/30
has increased by £6.515 million to £357.027 million, resulting in an overall
increase of £0.037 million in the total level of borrowing across the whole 6-
year programme. This increase in borrowing is summarised as follows: 
2024/25 2025/26 2026/27 Later
Years
Total 
£m £m £m £m £m
Increase in Vehicle Replacement
Programme Prudential Borrowing
(net of receipts) – Environment
and Infrastructure (Section 6.2.8)
(3.739) 2.751 0.200 0.880 0.092
Reduction in Street Lighting
Renewals Prudential Borrowing –
Environment and Infrastructure
(Section 6.2.8)
(0.055) 0.000 0.000 0.000 (0.055)
Movements arising from re-
phasing of expenditure and
receipts (Appendix II)
(2.684) 7.682 (3.439) (1.559) 0.000
Increase/(Reduction) in
Borrowing Requirement
(6.478) 10.433 (3.239) (0.679) 0.037 
5.9 The chart below shows the Capital Resources required to fund the 2024/25
Composite Capital Programme following the proposed budget adjustments
detailed in this report.

Page 4

6. Composite Capital Programme – Expenditure 
6.1 Total Expenditure and Proposed Budget Adjustments to the Current
Programme 
6.1.1 Total expenditure (net of grants and contributions) to 30 November 2024 on
the Composite Capital Programme is detailed in Appendix II and summarised
as follows: 
Projected
Outturn 
(£m)
Net
Expenditure
to 30 Nov
2024 
(£m)
% of
Projected
Outturn
Environment and Infrastructure  30.810 15.666 51%
Housing and Communities 1.829 0.577 32%
Economy, Development and
Planning
50.868    22.825 45%
Property Services 68.812 40.834 59%
Customer and Digital Services 8.347 2.614 31%
Health and Social Care 1.062 0.573 54%
Unallocated 0.052 0.000 0%
Total Net Capital Expenditure 161.780 83.089 51% 
6.1.2 Appendix IV includes updates on the progress of delivering the Council’s
major Capital projects. 
6.1.3 At present the accepted practice is that any budget savings identified on
specific projects are generally reallocated by the Service to other budgets
within their own programme. However, it is proposed that any such savings
arising are now “returned” to the programme and held as “Unallocated”
pending future consideration of how these savings should be applied. This
78.5%
16.4%
0.0%
2.3%
1.2%
1.6%
5.1%
Projected Capital Resources 2024/25
(December 2024)
Borrowing (£129.037M)
Grants (£27.026M)
Tay City Deal (-£0.069M)
Developer Contributions (£3.707M)
Third Party & Revenue Contributions (£1.952M)
Receipts (£2.660M)
£Million

Page 5

approach would ensure any savings identified through budget monitoring are
redirected to the highest priorities. Savings identified within rolling
programmes will be subject to further consideration, given the nature of the
work undertaken. 
6.2 Environment and Infrastructure 
6.2.1 The Strategic Lead has reviewed the programme for Environment and
Infrastructure and proposed various budget adjustments, the most significant
of which are described below. 
6.2.2 Within Traffic and Road Safety, a Capital Grant of £383,000 has been
allocated from the Scottish Government Road Safety Initiative Fund towards
crash barriers near Meikleour with the Road Safety Initiative budget being
increased accordingly.  Also within Traffic and Road Safety, a Third-party
Contribution of £77,000 has been provided by Perth and Kinross Countryside
Trust towards works on Jeanfield Swift Footpath with a corresponding
increase in the Active Travel Grant expenditure budget. 
6.2.3 Within Asset Management – Roads and Lighting, Third Party Contributions of
£262,000 have been received towards Structural Maintenance in the current
year, with £181,000 received from Scottish Water and £81,000 from various
other sources. In addition, within Roads and Lighting the following rephasings
are proposed: 
Project 2024/25
£m
2025/26
£m
Later
Years
£m
Description
Structural
Maintenance
2.174 (0.335) (1.839) There is an acceleration of
funding proposed into the current
year to undertake emergency
works. Budgets in later years
have been broadly equalised as
part of this acceleration.
Footways 0.207 (0.022) (0.185) There is an acceleration of
funding proposed into the current
year to undertake rephased works
on Tay Street. Budgets in later
years have been broadly
equalised as part of this
acceleration. 
6.2.4 Within Asset Management – Bridges, Bridge Refurbishment Programme, in
line with the works ongoing over the remainder of the year it is proposed
£50,000 is accelerated to the current year from 2025/26. In addition, it is
proposed £5,000 is vired to Culteuchar Culvert for the final expenditure.
Finally within Asset Management – Bridges, it was reported to the previous
Committee in November that the Garry Viaduct project required rephasing
with adjustments to later year budgets. In line with the staff resources
available for this project in the current year, it is further proposed that
£326,000 of the budget this year is moved to 2025/26 (£66,000) and 2026/27
(£260,000).

Page 6

6.2.5 Within Flood Protection Schemes, the works on the Comrie Flood Protection
Scheme have commenced on the ground with site clearance undertaken to
create a works compound for the duration of the project as well as clearance
of the construction areas. The majority of construction for the scheme will take
place during 2025/26 and a revised expenditure profile has been received
from the contractor. It is therefore proposed that £4.282 million of the budget
from the current year, and £1.779 million of the budget in 2026/27 are moved
to 2025/26, totalling £6.061 million. 
6.2.6 In addition, within Flood Protection Schemes the following rephasings are
proposed: 
Project 2024/25
£m
2025/26
£m
Later
Years
£m
Description
Milnathort Flood
Protection Scheme
(0.184) 0.184 - Re-engagement is required for the
design of the scheme to be
progressed with this work now
due to take place next year.
South Kinross Flood
Protection Scheme
(0.179) 0.179 - The scheme design received
objections which need to be
addressed prior to proceeding.
The rephasing allows for time to
rectify these design concerns.
Coastal Change
Adaptation
(0.052) 0.052 - Rephasing to align with the work
to be completed on this project for
the remainder of the year. 
6.2.7 Within Waste Strategy, following completion of the Recycling Improvement
Fund project and in order to align the budget with the final spend, it is
proposed £104,000 is transferred to Prudential Borrowing Wheeled Bin
Replacement Programme. 
6.2.8 In addition within the Prudential Borrowing programme, the Vehicle
Replacement Programme has been reviewed. To better reflect the deliveries
planned in advance of the financial year end, and with a corresponding
adjustment to vehicles due to be disposed of, the adjustments in the below
table are proposed. Further to this, there is an underspend on the Street
Lighting Renewal – LED and Column Replacement works in the current year
of £55,000 which results in a reduction in Prudential Borrowing. Together, the
above movements result in a net increase in Prudential Borrowing over the 6-
year programme of £37,000. 
2024/25
£m
2025/26
£m
Future Years 
£m
Movement 
£m
Vehicle Replacement
Programme
(3.776) 2.977 1.039 0.240
Capital Receipts –
Vehicle Disposals
0.037 (0.226) 0.041 (0.148) 
6.2.9 All the above proposed adjustments, together with other small movements,
have been reflected in Appendices I and II.

Page 7

6.3 Economy, Development and Planning 
6.3.1 The Strategic Lead has reviewed the programme for Economy,
Development and Planning and proposed various budget adjustments, the
most significant of which are described below. 
6.3.2 Within the Perth and Kinross Lighting Action Plan, it is proposed that
£844,000 is moved from the current year to next year following a review of the
works which are anticipated to be completed prior to the financial year end.  
6.3.3 Within Other Planning Projects, the project to develop the Creative Exchange
has formally been completed with a remaining budget of £52,000. In line with
the proposal outlined at Section 6.1.3 above, it is proposed this is transferred
to Unallocated Resources for future consideration.  
6.3.4 All the above proposed adjustments, together with other small movements,
have been reflected in Appendices I and II. 
6.4 Property Services 
6.4.1 Within Project Support, the programme of works at Perth Academy are
progressing at an increased pace with the fourth phase of works on the
science block underway. It is therefore proposed that £1.351 million is
accelerated from 2026/27 into the current year. 
6.4.2 Within Property Service Management, the scope of works on projects due for
completion in the current year within the DDA and Alteration Works
Programme has been reduced slightly resulting in lower costs. It is therefore
proposed that £100,000 is moved from the current year to 2025/26. 
6.4.3 Following the cessation of trading of the contractor on the Pitlochry High
School Upgrade Programme, works on site has been halted and only ongoing
design works are anticipated for the remainder of the year. On site works will
recommence when a replacement contractor has been appointed and it is
anticipated this will occur around Easter 2025. It is therefore proposed that
£60,000 of the budget is moved to next year. 
6.4.4 Energy Efficiency Works within various properties are ongoing for the
remainder of the financial year. It is proposed that £36,000 is allocated for
these works in the current year and funded from the Salix Earmarked
Reserve. 
6.4.5  Lastly within Property Service Management, the Letham Community
Wellbeing Hub project has been completed. The contribution of £38,000 from
Letham4All is therefore no longer required and both the income and
expenditure budgets are reduced by this amount. 
6.4.6 Within Prudential Borrowing Projects, Decarbonisation Works at various
properties have not commenced as early as previously anticipated. Works are
currently still in the design phase and therefore unlikely to be commenced in

Page 8

the current financial year. It is therefore proposed that £600,000 is moved to
next year in line with updated expenditure estimates. 
6.4.7 All the above proposed adjustments, together with other small movements,
have been reflected in Appendices I and II. 
6.5 Health and Social Care 
6.5.1 Within Occupational Therapy Equipment, with an aging population there is
increased demand for equipment, combined with an increased cost , resulting
in higher than previously budgeted costs in the current year. It is therefore
proposed that £100,000 is accelerated to the current year from 2029/30. In
addition, the rollout of the digital replacement for Technology Enabled
Telecare has concluded for the current phase this year, and with a lower than
anticipated refresh of the Digital Equipment installed. Consequently, it is
proposed that the underspend of £250,000 is transferred to Occupational
Therapy Equipment to supplement the increased demand and costs on the
budget. 
6.5.2 These proposed adjustments have been reflected in Appendices I and II. 
7. Housing Investment Programme 
7.1  The total current estimated expenditure, net of contributions, for the Housing
Investment Programme over the 5 years 2024/25 to 2028/29 remains
unchanged at £96.917 million. Movements across years from the previous
estimates are summarised in the table below and detailed in Appendix III. 
Approved 
20 Nov 2024
Current
Estimate
Movement 
£m £m £m
2024/25 28.161 31.513 3.352
2025/26       20.256       22.826 2.570
2026/27 15.633 15.633 0.000
2027/28 19.502 14.869 (4.633)
2028/29 13.365  12.076  (1.289)
Total 96.917 96.917 0.000 
Total Expenditure to 30 November 2024 (Housing Investment Programme) 
7.2 Net expenditure for 2024/25 to 30 November 2024 amounts to £15.975
million and receipts amount to £112,000. Therefore, the borrowing
requirement for the year to date is £15.863 million. 
7.3 The Strategic Leads for Housing and Communities and Property Services
have reviewed the Housing Investment Programme and proposed the budget
adjustments outlined below.
7.4 It is proposed to draw down various amounts from the Future Developments
New Build Programme in 2024/25, 2027/28 and 2028/29 to be applied as
follows:

Page 9

• Kinloch Gardens, Rattray. Estimated expenditure for new house building
for this project is £3.633 million, with Scottish Government grant of £1.944
million and £400,000 to be applied form the Second Home Council Tax
Reserve, thus leaving £1.289 million to be funded from the Future
Developments budget.
• National Trust Scotland, Dunkeld. Total estimated expenditure for the new
purchase of 20 properties in 2024/25 and 2025/26 is £5.448 million, with
Scottish Government grant of £1.947 million and £700,000 from the
Second Home Council Tax Reserve, thus leaving £2.801 million to be
funded from the Future Developments budget.
• Weavers Gait, Kinross. Estimated expenditure for new house building for
this project is £1.348 million, with £120,000 to be applied form the Second
Home Council Tax Reserve and £0.55 million of Commuted Sums, thus
leaving £0.678 million to be funded from the Future Developments budget
• Council House Buy-Backs. It is proposed to increase the budget by £3.890
million in 2024/25 to meet the ongoing purchase programme. It is
anticipated that further increases in the Buy-Back budget will be required
as the year progresses, with 90 property purchases completed by the
end of December 2024 and further purchases currently being progressed.
• Balhousie, Perth. It is proposed to transfer £37,000 in relation to fees in
the current year to further develop proposals for this site. 
7.5 It is also proposed to allocate part of the SHQS Future Developments Budget
in 2027/28 to current schemes in 2024/25, as follows: 
• Adaptations (OT) - £500,000 in 2024/25 for works approved under the
new OT Adaptations Referrals Policy approved by the Strategic Lead for
Housing and Communities in September 2024.
• Environmental Improvements - £41,000 for the removal of lead pipe work
at various locations. 
7.6   It is also proposed to move £500,000 for Rewiring, Infrastructure and Property
Refurbishments and £1.531 million for Multi-Storey Flats from the current
year to 2025/26. These movements reflect the level of anticipated works to be
completed in the current year. 
7.7 There has been an increase in Capital Receipts in the current year of
£28,000. Therefore, the borrowing requirement over the five-year programme
has reduced by this amount. 
8. BUDGET OVERVIEW 
8.1 The projected net expenditure outturn in 2024/25 for the Composite Capital
Budget is £161.728 million and represents 82% of the original 2024/25
budget approved on 24 April 2024 (£198.184 million). The revised budget is
based on the latest projections of expenditure and all budget adjustments
outlined within this report. 
8.2 Net expenditure to 30 November 2024 on the Composite Capital Budget is
£83.089 million and represents 51% of the proposed revised budget for
2024/25 of £161.728 million.

Page 10

8.3 The projected net expenditure outturn in 2024/25 for the Housing Investment
Programme is £31.513 million and represents 146% of the original 2024/25
budget approved on 26 April 2024 (£21.536 million). This increase reflects the
allocation of future years block budgets to specific projects in 2024/25 and the
increase in the Council House Buy-Back programme. 
8.4 Net expenditure to 30 November 2024 on the Housing Investment Programme
is £15.975 million which represents 51% of the proposed revised budget for
2024/25 of £31.513 million. 
8.5 The Council’s total Borrowing Requirement to 30 November 2024, based on
the Composite and Housing Investment Programmes, is £76.427 million. The
estimated overall Council Borrowing Requirement for 2024/25 as a whole has
reduced by £3.154 million to £158.605 million as a result of the monitoring
adjustments reflected within this report. This reflects a reduction in estimated
borrowing in the current year on the Composite Programme of £6.478 million,
and an increase on the Housing Investment Programme of £3.324 million. 
8.6 In the context of the Capital Budget, the borrowing above refers specifically to
the funding of capital expenditure and therefore the need to borrow. The
actual amounts and timing of the borrowing is undertaken as part of the
Council’s Treasury Management operations and reported within the Treasury
Activity and Compliance reports throughout the year. 
Author(s)
Name  Designation Contact Details
John Jennings Senior Accountant CHXFinance@pkc.gov.uk 
Approved 
Name Designation Date
Scott Walker Chief Finance Officer 21 January 2025

Page 11

ANNEX 
1. Implications, Assessments, Consultation and Communication 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications 
Corporate Plan 
1.1 The Council’s Corporate Plan 2022 – 2027 lays out seven outcome focussed
strategic objectives which provide clear strategic direction, inform decisions at
a corporate and service level and shape resources allocation.  They are as
follows: 
• Tackling Poverty 
• Tackling climate change and supporting sustainable places 
• Growing a sustainable and inclusive local economy 
• Enabling our children and young people to achieve their full potential 
• Protecting and caring for our most vulnerable people   
• Supporting and promoting physical and mental wellbeing
• Placing communities at the heart of how we work 
1.2 This report relates to all of these objectives. 
2. Resource Implications 
Financial 
2.1 There are no direct financial implications arising from this report other than
those reported within the body of the main report.

Page 12

Workforce 
2.2 There are no direct workforce implications arising from this report other than
those reported within the body of the main report. 
Asset Management (land, property, IT)   
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the
Corporate Equalities Impact Assessment process (EqIA) and has been
assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. In terms of the Climate Change Act,
the Council has a general duty to demonstrate its commitment to sustainability
and the community, environmental and economic impacts of its actions.   
3.6 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
4. Consultation 
Internal 
4.1 The Executive Leadership Team and the Strategic Leadership Team have
been consulted in the preparation of this report.

Page 13

2. Background Papers 
No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (other than any containing confidential or exempt
information) were relied on to any material extent in preparing the above
report. 
3. Appendices 
Appendix I – Composite Capital Programme - Estimated Capital Resources
2024/25 to 2029/30
Appendix II – Composite Capital Programme - Summary of Capital Resources
and Expenditure 2024/25 to 2029/30        
Appendix III – HRA Capital Investment Programme – Summary of Capital
Resources and Expenditure 2024/25 to 2028/29 
Appendix IV – Significant Capital Projects Progress Update