Appendix IV – Significant Capital Projects Progress Update
Perth and Kinross Council · 20 November 2024
Back to Finance and Resources Committee — 20 November 2024 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
SIGNIFICANT CAPITAL PROJECTS PROGRESS UPDATE APPENDIX IV Project Title Total Gross Budget (£'000) Third Party Funding (£'000) Total Net Budget (£'000) Projected Outturn (£'000) Completion Date Contract Awarded On Site Status Change Since Last Report Additional Commentary Blairgowrie Recreation Centre - Replacement 36,000 0 36,000 36,000 Easter 2025 - new centre currently scheduled to open late 2024 Yes Yes On track No Work on programme for phase 1 completion December 2024. North/West Perth New Primary School* 24,000 0 24,000 24,000 Summer 2026 No No On track No Project has been put on hold for 2 years due to slow build out rates at Bertha Park. Riverside Primary New School 19,899 0 19,899 19,899 Early summer 2023 Yes Yes Complete No Project complete. Perth High School - New School Investment 80,200 0 80,200 80,200 Summer 2026 - school building curently scheduled to open summer 2025 Yes Yes On track No Works are on programme. Harris Academy/Invergowrie Extension 5,200 0 5,200 5,200 Late 2023 Yes Yes On track No Main extension complete. Cross Tay Link Road (CTLR) 150,500 40,000 110,500 110,500 Spring 2025 Yes Yes On programme No Works continue to progress well with traveller system on R Tay Crossing now dismantled. Demarkfield portal structure constructed. Works continue on old A9 - surfacing, paths, parking area. Finishing and snagging works continue on Link Road. No change to completion which is 31 March 2025. Risks signficantly reduced in period, with weather as well as railway possessions being the key current risks. Comrie Flood Protection Scheme 40,821 32,657 8,164 8,164 Autumn 2026 Yes Yes Contract awarded Yes Balfour Beatty commenced site setup in October 2024. The initial phase of construction will involve site setup, site clearance works, and construction of access routes and are programmed from October 2024 to February 2025. The main construction works are programmed from February 2025 to October 2026. Perth Eco Innovation Park* 32,817 11,275 21,542 21,542 Not currently programmed No No Design package awarded - design programme on track Yes Following the application for LUF grant of £10m being unsuccessful, the Council approved a net increased of £10m on 1 March 2023. Balance of £20m remains unfunded. Further contributions and receipts are anticipated in years beyond the current programme to 2027/28. Approval to spend £1.55m on the inital design works (including planning application) was given in June 2024. Design work package issued to Amey in August 2024, with start-up complete. Project progressing as per design programme. Key risks include liaison with Transport Scotland and determine innovation scope.Positive discussions continue with JDLT in terms of s75, planning and design. Perth Museum 27,232 10,300 16,932 16,932 Spring 2024 Yes Yes Complete No Project complete and opened in March 2024. PH2O 90,000 0 90,000 90,000 Not currently programmed No No Thimblerow approved as new site for Ph2O project at Council on 4 September 2024. Yes Project Board established, programme under development, project no longer on hold. * Third Party Funding excludes Developer Contributions and receipts to be received in future years beyond the current 5-year programme.