Appendix IV – Significant Capital Projects Progress Update
Perth and Kinross Council · 18 September 2024
Back to Finance and Resources Committee — 18 September 2024 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
SIGNIFICANT CAPITAL PROJECTS PROGRESS UPDATE APPENDIX IV Project Title Total Gross Budget (£'000) Third Party Funding (£'000) Total Net Budget (£'000) Projected Outturn (£'000) Completion Date Contract Awarded On Site Status Change Since Last Report Additional Commentary Blairgowrie Recreation Centre - Replacement 36,000 0 36,000 36,000 Easter 2025 - new centre currently scheduled to open late 2024 Yes Yes On track Yes - on-site. Works are progressing well on-site. North/West Perth New Primary School* 24,000 0 24,000 24,000 Summer 2026 No No On track Yes. Project has been put on hold for 2 years due to slow build out rates at Bertha Park. Riverside Primary New School 19,899 0 19,899 19,899 Early summer 2023 Yes Yes Phase 2 On Track Yes - School operational. Project complete. Perth High School - New School Investment 80,200 0 80,200 80,200 Summer 2026 - school building curently scheduled to open summer 2025 Yes Yes On track Yes - on-site. Works are on programme. Harris Academy/Invergowrie Extension 5,200 0 5,200 5,200 Late 2023 Yes Yes On track Yes. Main extension complete, reconfiguration works still to be undertaken. Cross Tay Link Road (CTLR) 150,500 40,000 110,500 110,500 Spring 2025 Yes Yes On programme No Works progressing well and project remains on programme for completion in Spring 2025. No significant movements in projected spend. Construction of the Destiny Bridge segments is near completion thus the main structural elements of the bridge will shortly be complete. Works elsewhere continue. Monthly risk meetings continue with T&T. Detailed analysis of costs and risks due to take place with Finance in coming months given the significant risks relating to the structure have reduced. Comrie Flood Protection Scheme 40,821 32,657 8,164 8,164 Autumn 2026 Yes No Contract awarded Yes Detailed design completed April 2023. Preliminary advance works completed in July 2023. The main works were originally tendered in June 2023 but timed-out. The main works were re-tendered and returned in June 2024. Tender price higher than anticipated; Scottish Government updated prior to contract award on 21 August 2024. Works to commence from September 2024 for approximately 2 years. Perth Eco Innovation Park* 32,817 11,275 21,542 21,542 Not currently programmed No No Preliminary design works completed Yes Following the application for Levelling Up Fund Grant funding of £10m being unsuccessful, the Council approved a net increased of £10m on 1 March 2023 however the balance of £20m remains unfunded. Further contributions and receipts are anticipated in years beyond the current programme to 2027/28. Approval to spend £1.55m on the inital design works (including planning application) was given in June 2024. Associated work package due to be awarded to consultant in August 2024. Discussions continue with JDLT. * Third Party Funding excludes Developer Contributions and receipts to be received in future years beyond the current 5-year programme.