Appendix IV – Significant Capital Projects Progress Update
Perth and Kinross Council · 24 April 2024
Back to Finance and Resources Committee — 24 April 2024 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
SIGNIFICANT CAPITAL PROJECTS PROGRESS UPDATE APPENDIX IV Project Title Total Gross Budget Third Party Funding (£'000) Total Net Budget (£'000) Projected Outturn (£'000) Completion Date Contract Awarded On Site Status Change Since Last Report Additional Commentary Blairgowrie Recreation Centre - Replacement 36,000 0 36,000 36,000 Phase 1 completion date December 2024, phase 2 Easter 2025. Yes Yes On track No Works are progressing well on-site. New Primary School at Bertha Park Site 24,000 0 24,000 24,000 Summer 2028 No No Rephased pending review No Rephasing of the project to take account of the projections for the number of catchment pupils. Riverside Primary New School 19,899 0 19,899 19,899 June 2023 Yes Yes Complete Yes. Complete. Official opening 26 March 2024. Perth High School - New School Investment 80,200 0 80,200 80,200 Summer 2026 - school building curently scheduled to open summer 2025 Yes Yes On track No Works are progressing on-site. Harris Academy/Invergowrie Extension 5,200 0 5,200 5,200 Late 2023 Yes Yes On track No Main extension complete, reconfiguration works still to be undertaken. Cross Tay Link Road (CTLR) 150,500 40,000 110,500 110,500 Spring 2025 Yes Yes On programme No Works progessing and remain on target for completion in Spring 2025 as per the current programme. Bridge deck works commenced in March 2024 with the first deck segment concrete pours. Now that this is underway, progress will be closely monitored to inform a detailed analysis of available contingency and compensation events which will give more certainty over the cost forecasts (which are currently within budget). Comrie Flood Protection Scheme 39,544 0 39,544 39,544 Summer 2026 No No Advance works complete; Main works to be re-tendered April 2024 Yes Main works tender received in June 2023 but cost significantly higher than anticipated; Finance have since received confirmation from Scottish Government that the capital grant will be increased to match the revised value (equal to 80% of the project cost at tender stage) and the Council's capital plan (for the remaining 20%) was approved at Council Committee on 28/2/24. However, the June 2023 tender has timed out. Therefore, the main works will be re-tendered in April 2024 with a tentative start date of August 2024, subject to tender value remaining within budget. The works programme is currently being reviewed with a duration of up to 2 years (August 2026).Perth Eco Innovation Park* 32,817 11,275 21,542 21,542 Not currently programmed No No Preliminary design works completed Yes Procurement of the design consultant has progressed as far as possible, but is put on hold pending full funding package being in place. Discussions between PKC and the developers on the required private sector contribution levels are on-going to secure an indicative £13m. An Outline Business Case has been submitted to secure £5m from the Tay Cities Deal which would then be subject to approval of Full Business Case. Further evidence is being gathered to ensure that the identified £5m from sale receipts are in line with market trends. The above £23m contributions would complement the £10m approved by the Council to meet the project total estimated costs of £33m. Perth Museum 27,232 10,300 16,932 16,932 Spring 2024 Yes Yes On track No Project complete and opened to public 30 March PH2O 90,000 0 90,000 90,000 Not currently programmed No No Outline Business Case reported to Council 23 February 2023, and project on hold pending review. Yes Leisure assets review recommendations considered by Council 22 Jan 2024 with instruction to re-scope PH20 and revert to Council Aug '24 with re-costed option. * Third Party Funding excludes Developer Contributions and receipts to be received in future years beyond the current 5-year programme.