Appendix II – Composite Capital Programme - Summary of Capital Resources and Expenditure 2023/24 to 2027/28
Perth and Kinross Council · 24 April 2024
Back to Finance and Resources Committee — 24 April 2024 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2023/24 to 2027/28 APPENDIX II Approved Approved Proposed Revised Actuals Projected Revised Revised Revised Revised Revised Budget Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Adjustment Adjustment 29-Feb-24 Report 3 28-Feb-24 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 2023/24 2023/24 2023/24 2023/24 2023/24 2023/24 2024/25 2025/26 2026/27 2027/28 (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) EDUCATION AND CHILDREN'S SERVICES 56,744 0 (3,301) 53,443 39,656 53,443 66,456 26,894 21,904 22,223 190,920 COMMUNITIES 102,371 (6,351) (22,582) 73,438 68,953 73,438 112,513 52,793 71,752 79,436 389,932 HEALTH AND SOCIAL CARE 1,303 0 (250) 1,053 557 1,053 2,186 1,391 1,390 1,306 7,326 CORPORATE AND DEMOCRATIC SERVICES 9,382 0 (759) 8,623 5,438 8,623 17,029 8,608 7,628 12,256 54,144 TOTAL NET EXPENDITURE 169,800 (6,351) (26,892) 136,557 114,604 136,557 198,184 89,686 102,674 115,221 642,322 (NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS) GENERAL CAPITAL GRANT (22,699) 0 0 (22,699) (20,179) (22,699) (24,078) (12,639) (18,008) (12,150) (89,574) DEVELOPER CONTRIBUTIONS (2,847) 0 0 (2,847) 0 (2,847) (2,300) (2,367) (2,600) (2,600) (12,714) CAPITAL RECEIPTS (504) (400) 103 (801) (291) (801) (1,131) (1,086) (250) (1,338) (4,606) ANNUAL BORROWING REQUIREMENT 143,750 (6,751) (26,789) 110,210 94,134 110,210 170,675 73,594 81,816 99,133 535,428 CAPITAL RECEIPTS BROUGHT FORWARD (2,245) 0 0 (2,245) (2,245) (2,245) (1,872) (1,120) (1,550) (1,550) (2,245) CAPITAL RECEIPTS CARRIED FORWARD 616 0 1,256 1,872 1,494 1,872 1,120 1,550 1,550 2,638 2,638 TOTAL NET BORROWING REQUIREMENT 142,121 (6,751) (25,533) 109,837 93,383 109,837 169,923 74,024 81,816 100,221 535,821
Page 2
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2023/24 to 2027/28 APPENDIX II Revised Approved Proposed Revised Actual Projected Revised Revised Revised Revised Revised Budget Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Adjustment Adjustment 29-Feb-24 Report 3 28-Feb-24 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 2023/24 2023/24 2023/24 2023/24 2023/24 2023/24 2024/25 2025/26 2026/27 2027/28 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) EDUCATION AND CHILDREN'S SERVICES MIS - SEEMIS Licensing 745 745 147 745 0 0 0 0 745 Blairgowrie Recreation Centre - Replacement 16,374 16,374 12,180 16,374 13,150 4,003 0 0 33,527 Schools Modernisation Programme Investment in the Learning Estate 1,491 243 1,734 1,345 1,734 10,145 8,550 8,650 6,823 35,902 Scottish Govt. Grant (Inspiring School Age Childcare Spaces) (105) (105) (105) 0 0 0 0 (105) Free School Meal Expansion Programme 1,348 1,348 1,348 2,000 0 0 0 3,348 Methven Primary School Refurbishment 124 119 243 45 243 21 0 0 0 264 Breadalbane Academy, Aberfeldy - 3G Pitch 29 29 18 29 0 0 0 0 29 Third Party Contribution (The Scottish Football Association) (29) (29) (14) (29) 0 0 0 0 (29) Kirkmichael Primary School Upgrades 0 0 6 0 32 0 0 0 32 Capital Receipt (ring-fenced) (128) (128) (127) (128) 0 0 0 0 (128) Early Learning & Childcare 0 0 0 0 0 0 0 0 - Oakbank Primary School Upgrade Project 12 12 12 12 0 0 0 0 12 - Rattray Primary School Upgrade Project 155 155 91 155 0 0 0 0 155 New Primary School at Bertha Park Site 559 159 718 473 718 0 341 7,500 15,400 23,959 Riverside Primary New School 3,410 3,410 2,767 3,410 0 0 0 0 3,410 Technology Upgrades 128 128 23 128 1,016 250 0 0 1,394 Perth Academy - Refurbishment 2,311 755 3,066 2,525 3,066 1,745 1,650 1,650 0 8,111 Perth Grammar School - Upgrade Programme Phase 3 849 263 1,112 603 1,112 1,857 1,500 504 0 4,973 Perth High School - Internal Services & Refurbishment 16 16 4 16 0 0 0 0 16 Perth High School - New School Investment 25,244 (4,840) 20,404 15,788 20,404 36,340 10,600 3,600 0 70,944 Harris Academy/Invergowrie - Extension 4,211 4,211 3,770 4,211 150 0 0 0 4,361 TOTAL: EDUCATION AND CHILDREN'S SERVICES 56,744 0 (3,301) 53,443 39,656 53,443 66,456 26,894 21,904 22,223 190,920 COMMUNITIES Traffic & Road Safety Road Safety Initiatives (20mph Zones etc..) 0 34 34 1 34 328 362 362 361 1,447 Road Safety Initiatives - A94 Safety Improvements 0 0 0 84 0 0 0 84 Additional Road Safety - Pedestrian Crossings 0 0 0 153 153 153 0 459 Schools Road Safety Measures 488 488 433 488 0 0 0 0 488 Scottish Government Grant - CWSS (66) 66 0 0 0 0 0 0 0 20mph Signage Programme - Schools 10 10 1 10 119 0 0 0 129 20mph Signage Programme 76 76 35 76 0 0 0 0 76 Cycling Walking & Safer Routes (CWSR) 1,396 66 1,462 811 1,462 664 200 200 200 2,726 Scottish Government Grant - CWSR (1,246) (66) (1,312) (646) (1,312) (664) (200) (200) (200) (2,576) Third Party Contribution (TACTRAN) (150) (150) (150) 0 0 0 0 (150) Car Parking Investment 356 40 396 255 396 0 0 0 0 396 Revenue Contribution (65) (40) (105) (65) (105) 0 0 0 0 (105) Car Parking Investment - Pitlochry 0 0 0 150 0 0 0 150 Sub-Total 799 0 100 899 825 899 834 515 515 361 0 3,124 Asset Management - Roads & Lighting Structural Maintenance 12,114 (746) 11,368 10,100 11,368 10,420 9,498 9,706 7,500 48,492 Third Party Contribution (Forestry Commission Timber Routes) (299) (91) (390) (299) (390) 0 0 0 0 (390) Third Party Contribution (14) (85) (99) (14) (99) 0 0 0 0 (99) Traffic Signal Renewals - Upgrading 73 (69) 4 4 169 100 100 100 473 Footways 578 77 655 602 655 390 390 390 393 2,218 Investment in Local Footpaths 0 0 0 0 60 100 0 160 Road Safety Barriers 22 (22) 0 0 22 0 0 0 22 Sub-Total 12,474 0 (936) 11,538 10,389 11,538 11,001 10,048 10,296 7,993 50,876
Page 3
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2023/24 to 2027/28 APPENDIX II Revised Approved Proposed Revised Actual Projected Revised Revised Revised Revised Revised Budget Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Adjustment Adjustment 29-Feb-24 Report 3 28-Feb-24 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 2023/24 2023/24 2023/24 2023/24 2023/24 2023/24 2024/25 2025/26 2026/27 2027/28 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) Asset Management - Bridges Bridge Refurbishment Programme 1,536 (264) 1,272 758 1,272 1,736 2,221 2,520 3,201 10,950 Vehicular Bridge Parapets Programme - Assess & Upgrade 0 0 1 0 35 0 0 0 35 Old Perth Bridge - Strengthening 190 (140) 50 50 50 2,469 0 0 2,569 Perth Queens Bridge - Strengthening 335 (83) 252 4 252 143 70 2,153 0 2,618 Garry Viaduct 110 (72) 38 38 372 300 1,900 1,790 4,400 Culteuchar Culvert 391 42 433 293 433 20 0 0 0 453 Sub-Total 2,562 0 (517) 2,045 1,056 2,045 2,356 5,060 6,573 4,991 21,025 Improvement Schemes A9/A85 Road Junction Improvements 270 (213) 57 52 57 213 0 0 0 270 Cross Tay Link Road (CTLR) 72,842 (15,057) 57,785 46,970 57,785 41,270 0 0 0 99,055 Scottish Government Grant (15,000) (15,000) (15,000) 0 0 0 0 (15,000) Bertha Park Link Road 0 324 324 324 668 400 10,000 1,808 13,200 A977 Upgrades 350 17 367 323 367 173 0 0 0 540 Brioch Road, Crieff - Road Realignment & Safety Measures 31 31 13 31 0 0 0 0 31 Sub-Total 58,493 0 (14,929) 43,564 47,358 43,564 42,324 400 10,000 1,808 98,096 Public Transport Community Transport Iniaitives 199 (199) 0 0 199 0 0 0 199 Sub-Total 199 0 (199) 0 0 0 199 0 0 0 0 199 Rural Flood Protection Schemes Almondbank Flood Protection Scheme 17 17 16 17 0 0 0 0 17 Perth Flood Protection Scheme (South Inch Culvert Reinstatement 354 (262) 92 84 92 262 0 0 0 354 Comrie Flood Protection Scheme 7,385 (6,233) 121 1,273 480 1,273 10,310 15,420 8,800 0 35,803 Milnathort Flood Protection Scheme 79 (28) 51 9 51 229 83 0 0 363 South Kinross Flood Protection Scheme 225 26 251 189 251 412 1,783 8,823 3,225 14,494 Scone Flood Protection Scheme 90 (90) 0 0 50 69 68 580 767 Flood Mitigation Measures - Dunkeld and Craigie Burn 0 0 0 1,000 0 0 0 1,000 Coastal Change Adaptation 100 (100) 0 0 100 0 0 0 100 Sub-Total 8,250 (6,351) (215) 1,684 778 1,684 12,363 17,355 17,691 3,805 52,898 Perth & Kinross Place-making Mill Street Environmental Improvements 127 (78) 49 50 49 0 0 0 0 49 Perth, Place, People 3,598 (3,598) 0 0 3,598 0 0 0 3,598 Perth City Centre Golden Route (Rail Station) 11 40 51 13 51 38 0 0 0 89 City Greening 31 (31) 0 0 31 0 0 0 31 Perth & Kinross Lighting Action Plan 1,071 (433) 638 322 638 1,110 0 0 0 1,748 Sub-Total 4,838 0 (4,100) 738 385 738 4,777 0 0 0 5,515 Other Planning Projects Creative Exchange (former St. John's Primary School) 53 53 53 0 0 0 0 53 Local Full Fibre Network 22 4 26 5 26 0 0 0 0 26 Third Party Contribution - Tay Cities Deal 0 (4) (4) (58) (4) 0 0 0 0 (4) Low Carbon Transport & Active Travel Hub - Broxden EV Chargers 429 429 436 429 0 0 0 0 429 Third Party Contribution - ERDF (162) (162) (160) (162) 0 0 0 0 (162) Third Party Contribution - Tay Cities Deal (267) (267) (253) (267) 0 0 0 0 (267) Perth Eco-Innovation Park at Perth West 0 0 0 23,800 9,017 0 0 32,817 Third Party Contributions - Tay Cities Deal 0 0 0 (999) (550) (505) (2,946) (5,000) Other Third Party Contributions 0 0 0 0 0 (2,000) (3,000) (5,000) Capital Receipts - Ring Fenced Land Disposals 0 0 0 0 0 (550) (725) (1,275) Economic Development Investment - Land & Serviced Units 0 0 0 1,000 1,000 0 0 2,000 Nature Restoration 386 386 49 386 0 0 0 0 386 Sub-Total 461 0 0 461 19 461 23,801 9,467 (3,055) (6,671) 24,003
Page 4
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2023/24 to 2027/28 APPENDIX II Revised Approved Proposed Revised Actual Projected Revised Revised Revised Revised Revised Budget Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Adjustment Adjustment 29-Feb-24 Report 3 28-Feb-24 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 2023/24 2023/24 2023/24 2023/24 2023/24 2023/24 2024/25 2025/26 2026/27 2027/28 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) City Centre Developments - Cultural Attractions Perth Museum 2,368 2,368 1,456 2,368 0 0 0 0 2,368 Perth Art Gallery 3,272 3,272 245 3,272 0 0 0 0 3,272 PH2O 0 0 0 500 2,000 25,000 62,500 90,000 Sub-Total 5,640 0 0 5,640 1,701 5,640 500 2,000 25,000 62,500 95,640 Community Planning Letham Community Wellbeing Hub 1,571 1,571 1,158 1,571 0 0 0 0 1,571 Third Party Contribution (Letham4All) (519) (519) (482) (519) 0 0 0 0 (519) Adapt Your Property - Vacant Town & City Centre Space 0 0 0 300 0 0 0 300 Community-Led Asset Transfers 0 0 0 75 0 0 0 75 Sub-Total 1,052 0 0 1,052 676 1,052 375 0 0 0 1,427 Community Greenspace Play Areas - Improvements Implementation Strategy 383 40 423 77 423 973 561 150 150 2,257 Third Party Contribution (10) (10) (6) (10) 0 0 0 0 (10) 3G Pitch, Blairgowrie 3 3 3 3 117 0 0 0 120 Settlement/Neighbourhood Parks 25 1 26 26 429 0 0 0 455 Countryside Sites 0 0 0 139 0 0 0 139 Community Greenspace Sites 0 0 1 0 306 450 898 894 2,548 Community Greenspace Bridges 27 11 38 9 38 100 0 0 0 138 Third Party Contribution 0 0 0 (13) 0 0 0 (13) Revenue Contribution 0 (11) (11) (11) 0 0 0 0 (11) Core Path Implementation 9 36 45 3 45 0 0 0 0 45 Third Party Contribution (21) (24) (45) (45) 0 0 0 0 (45) Premier Parks 8 20 28 28 0 0 0 0 28 Third Party Contribution 0 (14) (14) (14) 0 0 0 0 (14) Auchterarder Public Park 30 (4) 26 19 26 0 0 0 0 26 The Knock 0 0 0 0 0 0 0 0 Third Party Contribution (3) (3) (3) 0 0 0 0 (3) Kinnoull Hill 8 (8) 0 0 8 0 0 0 8 Third Party Contribution (4) (4) (7) (4) 0 0 0 0 (4) Cemetery Extensions 20 20 16 20 60 229 225 375 909 Sub-Total 475 0 47 522 115 522 2,119 1,240 1,273 1,419 6,573 Waste Strategy Recycling Improvement Fund 2,363 2,363 2,104 2,363 0 0 0 0 2,363 Scottish Government Grant (2,363) (2,363) 0 (2,363) 0 0 0 0 (2,363) Sub-Total 0 0 0 0 2,104 0 0 0 0 0 0 Support Services PC Replacement & IT Upgrades Hardware 16 16 7 16 15 15 14 14 74 Licenses 152 152 83 152 112 95 71 71 501 Sub-Total 168 0 0 168 90 168 127 110 85 85 575 Commercial Property Investment Programme North Muirton Industrial Estate - Site Servicing & Provision of Units 57 57 57 0 0 0 0 57 Broxden Business Park - Additional Infrastructure 10 10 10 0 0 0 0 10 Western Edge, Kinross - Site Servicing 5 5 5 0 0 0 0 5 Broxden Drainage Mitigation Works 638 638 742 638 866 0 0 0 1,504 Third Party Contribution (Scottish Water) (470) (470) (470) (658) 0 0 0 (1,128) Ruthvenfield Business Centre 1,372 (1,256) 116 9 116 1,256 0 0 0 1,372 North Muirton Drainage 17 17 17 0 0 0 0 17 Sub-Total 1,629 0 (1,256) 373 751 373 1,464 0 0 0 1,837
Page 5
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2023/24 to 2027/28 APPENDIX II Revised Approved Proposed Revised Actual Projected Revised Revised Revised Revised Revised Budget Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Adjustment Adjustment 29-Feb-24 Report 3 28-Feb-24 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 2023/24 2023/24 2023/24 2023/24 2023/24 2023/24 2024/25 2025/26 2026/27 2027/28 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) Prudential Borrowing Projects Wheeled Bin Replacement Programme - Domestic Bins 203 (58) 145 125 145 258 200 200 200 1,003 Wheeled Bin Replacement Programme - Commercial Bins 208 (37) 171 171 57 20 20 20 288 Recycling Containers, Oil Banks & Battery Banks Replacement Pro 205 205 102 205 120 105 105 105 640 Capital Receipts - Disposals (9) (9) (7) (9) 0 0 0 0 (9) Litter Bins 25 25 25 25 50 50 50 50 225 Smart Cities - Smart Waste 45 45 46 45 0 0 0 0 45 Third Party Contribution (ERDF) (24) (24) (24) 0 0 0 0 (24) Vehicle Replacement Programme 3,813 (113) 3,700 2,084 3,700 8,031 2,800 2,800 2,500 19,831 Capital Receipts - Vehicle Disposals (376) 70 (306) (188) (306) (500) (352) (352) (322) (1,832) Street Lighting Renewal - LED & Column Replacement 804 (30) 774 505 774 898 835 551 592 3,650 LED Traffic Signal Replacement 4 4 4 4 0 0 0 0 4 Almondbank Flood Protection Scheme 3 3 3 0 0 0 0 3 Land Purchase & Development (Hotel Development) 0 0 0 950 950 0 0 1,900 Sub Total 4,901 0 (168) 4,733 2,696 4,733 9,864 4,608 3,374 3,145 25,724 Housing Projects Gypsy Travellers Site Improvement Works 195 (184) 11 10 11 184 0 0 0 195 Additional Gypsy Traveller Site Improvement Works 225 (225) 0 0 225 0 0 0 225 New Gypsy Traveller Site 10 10 10 0 1,990 0 0 2,000 Sub Total 430 0 (409) 21 10 21 409 1,990 0 0 2,420 TOTAL: COMMUNITIES 102,371 (6,351) (22,582) 73,438 68,953 73,438 112,513 52,793 71,752 79,436 0 389,932 Health & Social Care Occupational Therapy Equipment 250 100 350 350 250 250 250 150 1,250 Technology Enabled Telecare 1,000 (350) 650 503 650 1,625 1,088 1,087 1,087 5,537 Moving & Handling Office Refurbishment 0 0 0 29 0 0 0 29 Software Licences 53 53 54 53 53 53 53 69 281 Developing Supported Tenancies 0 0 0 229 0 0 0 229 TOTAL: HEALTH & SOCIAL CARE 1,303 0 (250) 1,053 557 1,053 2,186 1,391 1,390 1,306 7,326 CORPORATE AND DEMOCRATIC SERVICES Property Services DDA Adaptation & Alteration Works Programme 410 (10) 400 278 400 210 200 200 200 1,210 Property Compliance Works Programme 902 (327) 575 398 575 727 650 650 650 3,252 Third Party Contribution (LAL) (25) (25) (25) (25) 0 0 0 0 (25) Capital Improvement Projects Programme 2,275 (238) 2,037 1,342 2,037 2,038 1,800 1,800 894 8,569 Pitlochry High School - Upgrade Programme 316 (136) 180 119 180 136 0 0 0 316 Friarton Depot - Waste Transfer Station 0 0 0 2,250 750 0 0 3,000 Community Campus Access Adaptations 0 0 0 25 0 0 0 25 Energy Efficiency Works - Various Properties 27 27 27 27 0 0 0 0 27 Revenue Contribution (Salix Reserve) (27) (27) (27) 0 0 0 0 (27) Decarbonisation - Prudential Borrowing Programme (PB) 700 (150) 550 281 550 1,450 0 0 0 2,000 Energy Conservation & Carbon Reduction Programme (PB) 138 138 67 138 150 150 150 150 738 Information Systems & Technology ICT Infrastructure Replacement and Upgrade Programme 2,416 2,416 1,879 2,416 6,745 3,077 3,076 7,757 23,071 Data & Analytics 600 600 205 600 806 946 720 708 3,780 Supporting Digital 750 (50) 700 99 700 963 927 928 1,185 4,703 Software Licences (Revenues & Benefits) 50 2 52 52 52 51 51 51 49 254 School Audio-Visual (AV) Equipment Replacement Programme 50 50 26 50 173 35 35 35 328 Mosaic - Swift Social Work System Replacement 800 150 950 690 950 1,355 147 143 628 3,223 Revenue Contribution 0 0 0 (50) (125) (125) 0 (300) TOTAL: CORPORATE AND DEMOCRATIC SERVICES 9,382 0 (759) 8,623 5,438 8,623 17,029 8,608 7,628 12,256 54,144
Page 6
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2023/24 to 2027/28 APPENDIX II Revised Approved Proposed Revised Actual Projected Revised Revised Revised Revised Revised Budget Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Adjustment Adjustment 29-Feb-24 Report 3 28-Feb-24 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 2023/24 2023/24 2023/24 2023/24 2023/24 2023/24 2024/25 2025/26 2026/27 2027/28 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) TOTAL COMPOSITE NET EXPENDITURE 169,800 (6,351) (26,892) 136,557 114,604 136,557 198,184 89,686 102,674 115,221 642,322 (NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS) CAPITAL RECEIPTS General Capital Grant - Scottish Government (22,699) (22,699) (20,179) (22,699) (24,078) (12,639) (18,008) (12,150) (89,574) Developer Contributions (2,847) (2,847) (2,847) (2,300) (2,367) (2,600) (2,600) (12,714) General Fund - Capital Receipts/Disposal (504) (400) 103 (801) (291) (801) (419) (656) (250) (250) (2,376) Commercial Property - Capital Receipts/Disposal 0 0 0 0 0 (712) (430) 0 (1,088) (2,230) Total: Capital Receipts (26,050) (400) 103 (26,347) (20,470) (26,347) (27,509) (16,092) (20,858) (16,088) (106,894) Annual Composite Borrowing Requirement 143,750 (6,751) (26,789) 110,210 94,134 110,210 170,675 73,594 81,816 99,133 535,428 CAPITAL RECEIPTS BROUGHT FORWARD (2,245) 0 (2,245) (2,245) (2,245) (1,872) (1,120) (1,550) (1,550) (2,245) CAPITAL RECEIPTS CARRIED FORWARD 616 1,256 1,872 1,494 1,872 1,120 1,550 1,550 2,638 2,638 TOTAL NET COMPOSITE BORROWING REQUIREMENT142,121 (6,751) (25,533) 109,837 93,383 109,837 169,923 74,024 81,816 100,221 535,821
Page 7
EDUCATION AND CHILDREN'S SERVICES Project Project Description MIS - SEEMIS Licensing Licencing of Schools Management Information System Blairgowrie Recreation Centre - Replacement Replacement of the Recreation Centre in Blairgowrie Investment in the Learning Estate Investment to upgrade the infrastructure and environment of our existing school estate Free School Meal Expansion Programme Upgrading kitchen and dining facilities to provide the enhanced Free School Meals programme Methven Primary School Refurbishment Upgrade of Methven Primary School facilities Breadalbane Academy, Aberfeldy - 3G Pitch Additional investment required to upgrade 2G to 3G Kirkmichael Primary School Upgrades Upgrade of Kirkmichael Primary School facilities Early Learning & Childcare - Letham Primary School Upgrade Project 1140 hrs project plus upgrade of primary school infrastructure - Completed - Oakbank Primary School Upgrade Project 1140 hrs project - Completed - Rattray Primary School Upgrade Project 1140 hrs project plus upgrade of primary school infrastructure - Completed New Primary School at Bertha Park Site New primary school located at Bertha Park Riverside Primary New School Replacement of North Muirton and Balhousie primary schools Technology Upgrades Upgrade to practical teaching environment within the existing school estate Perth Academy - Refurbishment Investment to upgrade the infrastructure and environment of the Perth Academy including structural work to sports block, lighting upgrades, classroom upgrades and science block cladding Perth Grammar School - Upgrade Programme Phase 3 Investment to upgrade the infrastructure and environment of the Perth Grammar School including structural work to assembly hall, AV and WiFi upgrades, classroom refurbishment and door upgrades Perth High School - Internal Services & Refurbishment Necessary works to the infrastructure and environment of the current Perth High School Perth High School - New School Investment Replacement of the existing Perth High School Harris Academy/Invergowrie - Extension Extension and reconfiguration of existing space at Harris Academy in Dundee for continuation of access for pupils based in Invergowrie COMMUNITIES Project Project Description Traffic & Road Safety Road Safety Initiatives (20mph Zones etc.) A programme of works to improve road safety Additional Road Safety - Pedestrian Crossings A programme of works to provide pedestrian crossing facilities Road Safety Improvement Fund works Provision of safety barriers on routes where motor cycling is common Schools Road Safety Measures A programme of works to improve road safety in the vicinity of schools 20mph Signage Programme - Schools A programme of works to improve road safety in the vicinity of schools 20mph Signage Programme A programme of works to introduce 20mph speed limits. Cycling Walking & Safer Routes (CWSR) A programme of works providing infrastructure for cycling, walking and safer routes Car Parking Investment Construction of new car park in Auchterarder Car Parking Investment - Pitlochry Purchase of land and construction of a public car park Strathmore Cycle Network Contribution towards a shared use path between Coupar Angus and Blairgowrie Asset Management - Roads & Lighting
Page 8
Structural Maintenance Road maintenance to extend the life of roads, including predominately road resurfacing, surface dressings, installing new drainage infrastructure and repairs to and replacement of defective embankments and retaining walls Traffic Signal Renewals - Upgrading A programme of works to upgrade existing traffic signal infrastructure Footways Replacement of existing deteriorated footway surfaces Investment in Local Footpaths A programme of works to improve and provide local footpaths Road Safety Barriers Renewal of existing barriers where unrecoverable damage has occurred and renewal of barriers where timber posts have been used in construction Bridge Refurbishment Programme Used to appoint specialist external inspection teams and consultants to carry out specialist access bridge inspections and assessments Dalhenzean Culvert Culvert replacement project (later years) Dunkeld Golf Course Culvert replacement project (later years) Vehicular Bridge Parapets Programme - Assess & Upgrade Assessment and Upgrading of Vehicle Parapets Programme Old Perth Bridge - Strengthening Carry out works recommended by the 2018 Bridge Assessment study, including a range of assessment, investigation, strengthening and improvement works Perth Queens Bridge - Strengthening Carry out works recommended by the 2018 Bridge Assessment study, including a range of assessment, investigation, strengthening and improvement works Garry Viaduct Replacement of Bearings and Parapets; including strengthening of deck for bearing replacement jacking up, and to cater for increased parapet vehicular deterrent capacity Culteuchar Culvert Replace existing temporary steel bridge (on hire) with culvert Glendevon Bridge Major bridge repair works required due to severe river scour damage (now complete) Tullyfergus Bridge Installation of scour protection to protect existing bridge abutments (later years) A9/A85 Road Junction Improvements New infrastructure including a new A9 overbridge, a bridge over the River Almond and road linking the A85 to Inveralmond and Bertha Park (Phase 1 of Perth Transport Futures Project) - complete Cross Tay Link Road (CTLR) New road and major structure over the River Tay, linking the A9 north of Inveralmond and the A94 north of Scone (Phase 2 of Perth Transport Futures Project). A977 Upgrades A programme of works to improve road safety along the A977. Broich Road, Crieff - Road Realignment & Safety Measures Complete Community Transport Iniaitives Funded by the Community Bus Fund - expenditure to improve connectivity and integrate transport modes,or to support innovative transport solutions in areas of rural deprivation Almondbank Flood Protection Scheme Substantially complete Perth Flood Protection Scheme (Pump Replacement) Complete Perth Flood Protection Scheme (South Inch Culvert Reinstatement) Ground investigation and monitoring then design project to refurbish existing culvert Comrie Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in Comrie Milnathort Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in Milnathort Asset Management - Bridges Improvement Schemes Rural Flood Protection Schemes Public Transport
Page 9
South Kinross Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in South Kinross Scone Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in Scone Coastal Change Adaptation Design and construct projects to deal with incidents of coastal erosion Mill Street Environmental Improvements Potential compensation payments associated with claims against compulsory land acquisition to enable delivery of environmental improvements to stimulate and support development and investment Perth, Place, People Design and development of sustainable transport corridors to improve access to and from Perth and enable additional development and improvement within Perth city centre Perth City Centre Golden Route (Rail Station) Design and development of improvements to access, signage and animation from rail and bus station to Perth city centre to complement improvements to integration of transport City Greening Improvements to support enhancement of retail trading environment and residential areas and enhanced use of space for markets, events and alfresco use Perth & Kinross Lighting Action Plan Architectural and creative lighting to enhance city and towns appearance, reduce energy cost and increase safety at nighttime to increase dwell time, support the hospitality sector, events and grow the evening economy Creative Exchange (former St. John's Primary School) Repurposing old school to offer space to creative industry businesses and create the Famous Grouse Idea Centre, a space to support business innovation. Complete Town Centre - Regeneration & Economic Improvements Complete Local Full Fibre Network Provision of gigabit fibre connectivity to Council's buildings to unlock gigabit connectivity for surrounding communities. Completed Low Carbon Transport & Active Travel Hub - Broxden EV Chargers Provision of fast EV chargers combined with solar power generation and battery storage at Broxden Park & Ride - Near completion Perth Eco-Innovation Park at Perth West Provision of enabling infrastructure (access road, A9 underpass and unit platforms) to develop 25ha of employment land supporting clean growth, business innovation and jobs - Phase 1 (11ha) - In development Coupar Angus - Strathmore Community Hub Complete Nature Restoration Protection and restoration of biodiversity focusing on over- exploitation of the natural environment and addressing its consequences; habitat loss and fragmentation; and invasive non- native species - 22/23 completed - 23/24 started Perth Museum Refurbishment of Perth City Hall to create new museum spaces and cafe. Main construction phase complete and install/fit out on schedule for planned opening spring 2024 Perth Art Gallery Refurbishment of temporary galleries - scheduled for completion November 2023 Collections Centre Project removed from programme PH2O Replacement of Perth Leisure Pool and Dewars Ice Rink. On hold pending outcome of Leisure and Culture Assets Review Letham Community Wellbeing Hub Refurbishment of Letham Wellbeing Hub to offer a range of services to the local community managed by Letham4All - scheduled for completion end 2023 City Centre Developments - Cultural Attractions Community Planning Other Planning Projects Perth & Kinross Place-making
Page 10
Play Areas - Improvements Implementation Strategy Regular refurbishment of 146 play areas based on approx. 6-8 per year. Involves community engagement and often co-funding and design of the sites 3G Pitch, Blairgowrie Two phase community led project to provide a new full sized 3G football pitch and pavilion Settlement/Neighbourhood Parks Refurbishment of neighbourhood parks working in partnership with communities to improve, update and renew worn out or obsolete infrastructure Countryside Sites Refurbishment of more natural parks and open spaces Community Greenspace Sites Main fund for all Community Greenspace Sites which is drawn down to support the overall capital programme of refurbishments and upgrades Community Greenspace Bridges Refurbishment programme for all bridges on Community Greenspace sites Core Path Implementation Holding budget for Crieff Comrie Core path development mainly funded through Sustrans Alyth Environmental Improvements Town centre upgrade including community led refurbishment of the burnside - complete Premier Parks Small budget to facilitate refurbishment of former Premier Park upgrades Auchterarder Public Park Major play area upgrade co-funded and designed with the community The Knock Complete Kinnoull Hill Complete Cemetery Extensions Funding to allow the extension of existing or development of new cemeteries to address the pressure for burial space Recycling Improvement Fund External Scottish Government funding (Recycling Improvement Fund) to roll out 4th bin to householders for recycling Hardware Funding of additional or bespoke IT Hardware for Communities Staff Licenses Funding of software contracts North Muirton Industrial Estate - Site Servicing & Provision of Units Only road adoption works remaining Broxden Business Park - Additional Infrastructure Only road adoption works remaining Western Edge, Kinross - Site Servicing Only road adoption works remaining Additional Infrastructure Investment - Broxden Complete Broxden Drainage Mitigation Works Drainage/pumping station works underway and subject to agreement/contribution from Scottish Water Ruthvenfield Business Centre Works on redevelopment in progress North Muirton Drainage Drainage/pumping station underway North Muirton Industrial Estate Expansion Land - Servicing Complete Wheeled Bin Replacement Programme - Domestic Bins Replacement of damaged and end of life wheeled bins for households. Also suppling bins for new properties Wheeled Bin Replacement Programme - Commercial Bins Replacement of damaged and end of life wheeled bins for commercial customers. Also suppling bins for new customers and changes to collection contracts Recycling Containers, Oil Banks & Battery Banks Replacement Programme Replacement of damaged and end of life oil and battery banks Litter Bins Replacement of damaged and end of life litter bins and/or for general supply of litter bins where required. Prudential Borrowing Projects Community Greenspace Waste Strategy Support Services - PC Replacement & IT Upgrades Commercial Property Investment Programme
Page 11
Smart Cities - Smart Waste Programme now complete - included introduction of In Cab system for refuse vehicles, fill level sensors on city centre litter bins Vehicle Replacement Programme Fleet vehicle replacement programme Crematorium - Abatement Works Complete Street Lighting Renewal - LED & Column Replacement Street Lighting LED conversion and column replacement programme Smart Cities - Intelligent Street Lighting Complete LED Traffic Signal Replacement Complete Almondbank Flood Protection Scheme Under Rural Flood Land Purchase & Development (Hotel Development) Development agreement secured and release of grant for heritage subject to progression through planning and cost evidence Technology & Innovation Incubator Units Complete Gypsy Travellers Site Improvement Works Programme of works for improvements on Gypsy Traveller sites at Bobbin Mill and Double Dykes Additional Gypsy Traveller Site Improvement Works Additional funding to support improvements works programme on Gypsy Traveller sites Gypsy Traveller Site Community Improvement Works Funding from Gypsy Traveller Scottish Government Funding Bid for replacement of chalets at Double Dykes New Gypsy Traveller Site Feasibility Study for Gypsy Traveller Transient Site HEALTH & SOCIAL CARE Project Project Description Occupational Therapy Equipment Supply and install of occupational therapy equipment Technology Enabled Telecare Replacement of existing Community Alarm devices from analogue to digital units prior to UK switch-off of analogue, as well as ongoing rolling replacment programme. Moving & Handling Office Refurbishment Refurbishment of space following relocation of the moving and handling office Software Licences Licences for various social care systems Developing Supported Tenancies Cntribution towards health resettlemetn of Community Care clients to be supported in the community CORPORATE AND DEMOCRATIC SERVICES Project Project Description DDA Adaptation & Alteration Works Programme To provide unhindered accessibility to all Council Buildings - e.g. Ramps/Lifts/Door Access/Accessible Toilets and Changing Areas Property Compliance Works Programme To ensure compliance with current and changing legislation including - New Fire Alarms; Lighting; Wiring; Fire Protection Works; Gas pipework within buildings and Roof Restraint safety systems Capital Improvement Projects Programme Roof Upgrades; Full internal refurbishment works; New Heating Systems; Boilers and pipework; Structural Upgrades; Small extensions; New Windows/Doors; New Fencing; New Cladding Pitlochry High School - Upgrade Programme Upgrades to Mechanical and Electrical Infrastructure, including rewiring, heating and controls systems, replacement lighting and consequential building works such as new ceilings, painting and flooring Friarton Depot - Waste Transfer Station Energy Efficiency Works - Various Properties Focusing on a spend to save with projects aiming to reduce energy cost across the property estate Housing Projects Property Services
Page 12
Decarbonisation - Prudential Borrowing Programme (PB) This budget will support PKCs path to NetZero and focus primarily on the de-carbonisation of heat and replacing inefficient direct emissions heat sources Energy Conservation & Carbon Reduction Programme (PB) This budget is focused on works to reduce PKC energy consumption and help achieve annual KPI energy reduction of 3% ICT Infrastructure & Replacement and Upgrade Programme This Programme delivers the IT / digital environment, digital resources and systems required by staff and young people. The programme maintains, supports and develops computers; networks; telephony; Microsoft systems; connectivity and equipment; datacentres; servers; file storage and back up; security systems and video conferencing Data & Analytics Delivers the governance, tools, technologies and organisation- wide skills required for optimising value from Council data, driving informed decision making around resources, priorities and service delivery targets Supporting Digital Develops the capabilities we need to be an innovative digital organisation. Including developing the Council’s corporate employee (mobile working) and customer (online services) platforms, to create new digital products and services; investment in tools such as Microsoft; resourcing innovation and building digital skills, insight and expertise Software Licences (Revenues & Benefits) NAC Live system licensing for Revenues & Benefits team School Audio-Visual (AV) Equipment Replacement Programme Ensures all Perth and Kinross classrooms have equitable access to audio visual panels and the digital skills to exploit these resources for learning and teaching Mosaic - Swift Social Work System Replacement Purchase and Development of a new Social Work system to replace SWIFT Information Systems & Technology