Page 1

PERTH & KINROSS COUNCIL 
Finance & Resources Committee 
24 April 2024 
COMPOSITE CAPITAL BUDGET 2023/28 & HOUSING INVESTMENT
PROGRAMME 2023/28 – MONITORING REPORT No.4 
Report by Strategic Lead – Finance & Business Support
(Report No. 24/131) 
1. PURPOSE 
1.1 This report provides a summary position to date for the 5-year Composite
Capital Budget and the 5-year Housing Investment Programme for 2023/24 to
2027/28 and seeks approval for adjustments to the programmes. 
2. RECOMMENDATIONS 
2.1 It is recommended that the Committee: 
(i) notes the contents of the report.
(ii) approves the proposed adjustments to the five-year Composite Capital
Budget 2023/24 to 2027/28 set out in Sections 5 and 6 of the report
and summarised in Appendices I and II.
(iii) approves the proposed adjustments to the Housing Investment
Programme Budget 2023/24 to 2027/28 set out in Section 7 of the
report and summarised in Appendix III.
(iv) notes progress with the delivery of major Capital projects as
summarised in Appendix IV. 
3. STRUCTURE 
3.1 The report is structured over the following sections: 
• Section 4: Background / Main Issues
• Section 5: Composite Capital Programme – Gross Capital Resources
• Section 6: Composite Capital Programme – Expenditure
• Section 7: Housing Investment Programme
• Section 8: Summary 
4. BACKGROUND / MAIN ISSUES 
4.1 The Finance & Resources Committee approved an updated five-year gross
Composite Capital Budget for 2023/24 to 2027/28 totalling £623.916 million
and a five-year gross Housing Investment Programme for 2023/24 to 2027/28
totalling £92.205 million at its meeting on 31 January 2024 (Report 24/41
refers).

Page 2

4.2 At its meeting on 28 February 2024, the Council approved a revised
Composite Capital Budget for the 6 years 2024/25 to 2029/30 (Report 24/64
refers). In line with the previous reports for 2023/24, this report only refers to
years 2023/24 to 2027/28 with the total gross budget approved for the 5
years, including 2023/24, totalling £673.453 million. This includes the
adjustments approved by the Council for these years on 28 February 2024,
whilst the budgets for 2028/29 and 2029/30 will be included in the monitoring
reports for 2024/25. 
4.2 This report advises on expenditure to 29 February 2024, and the latest
estimate of the projected outturn for each of the years to 2027/28 for the
Composite Programme and for the Housing Investment Programme. 
5. COMPOSITE CAPITAL PROGRAMME – GROSS CAPITAL RESOURCES 
5.1 On 28 February 2024 the Council approved a revised Composite Capital
Budget totalling £673.453 million for the years 2023/24 to 2027/28, which
reflected an increase in resources of £49.537 million from the Budget
approved on 31 January 2024. All approved movements in resources and
expenditure have been included in Appendices I and II of this report and are
summarised in the table below: 
Increase in Gross Expenditure: £m
Bertha Park Link Road 13.200
Comrie Flood Scheme 11.577
South Kinross Flood Scheme 11.314
Milnathort Flood Scheme (1.306)
Flood Mitigation – Dunkeld and Craigie Burn 1.000
IT Licensing & Infrastructure 6.330
Friarton Depot Waste Transfer Station 3.000
Economic Development 2.000
Other (Mosaic, Traffic Signals, CWSR, Community Planning) 2.422  
Total Increase in Gross Expenditure 49.537  
Funded By: 
Increase in General Capital Grant (Flood Schemes, CWSR,
General Allocation)
(16.553)
Capital Receipt (0.400)  
Increase in Borrowing 32.584 
5.2 As a result of ongoing monitoring of the programme, further adjustments to
the budget are proposed. The current estimated total gross capital resources
(which includes movements in Capital Receipts, Capital Grants, Contributions
and borrowing) available over the five years 2023/24 to 2027/28 amount to
£678.939 million.

Page 3

5.3 Movements from the revised Composite Capital Budget approved on 28
February 2024 for the five years are summarised in the table below, and the
constituent elements for each year are shown in Appendix I. 
Total Gross Composite Capital Resources 
Approved 
28 February 2024
Current
Estimate
Movement 
£m £m £m
2023/24 184.831 158.138 (26.693)
2024/25 207.568 201.068 (6.500)
2025/26 119.305 90.913 (28.392)
2026/27 90.371 106.406 16.035
2027/28 71.378 122.414 51.036
Total 673.453 678.939 5.486  
5.4 The overall movement in total Gross Resources for the 5 years 2023/24 to
2027/28 since 28 February 2024 shown at Section 5.2 above can be
summarised as follows: 
£’m
Increase in Ring-Fenced Receipts (Section 5.5) 0.078
Decrease in Revenue Contributions (Section 5.6) (0.023)
Increase in Third Party Contributions (Section 5.7)  0.231
Increase in Borrowing Requirement (Section 5.8 and 5.9) 5.200
Increase in Gross Capital Resources (Section 5.3) 5.486 
5.5 There has been some rephasing of General Fund and Commercial Property
receipts across the 5-year programme but with no change to the overall totals
under each category. However, there is an increase in Ring-Fenced receipts
of £78,000 in the current year (disposal of vehicles). 
5.6 Revenue Contributions have reduced by a total of £23,000 over 2023/24 and
2024/25, relating to Mosaic (reduction of £74,000, Section 6.4.5 refers), Traffic
and Road Safety (increase of £40,000, Section 6.3.2 refers) and Community
Greenspace (increase of £11,000. Section 6.3.10 refers). 
5.7 Third Party Contributions have increased by £218,000 in 2023/24 and
£13,000 in 2024/25, relating to Structural Maintenance (£176,000, Section
6.3.3 refers), Community Greenspace (£51,000, Section 6.3.10 refers) and
Other Planning Projects (£4,000). 
5.8 The projected borrowing requirement in 2023/24, which is effectively the
balancing item for resources, is £109.837 million. This is £25.533 million
lower than the borrowing requirement approved by Council on 28 February
2024. 
5.9 The total borrowing requirement in the subsequent years 2024/25 to 2027/28
has increased by £30.733 million to £425.984 million, resulting in an overall
increase of £5.2 million in the total level of borrowing across the whole 5-year
programme. The movement in borrowing is summarised as follows:

Page 4

No embedded text on this page.

Page 5

2023/24 2024/25 2025/26 Later
Years
Total 
£m £m £m £m £m
Increase in Prudential Borrowing –
Communities (net of receipts)
(Section 6.3.12)
(0.168) 5.228 0.050 0.090 5.200
Movements arising from re-
phasing of expenditure and
receipts (Appendix II)
(25.365) (13.212) (28.404) 66.981 0.000
Increase/(Decrease) in
Borrowing Requirement
(25.533) (7.984) (28.354) 67.071 5.200 
5.10 The chart below shows the Capital Resources required to fund the 2023/24
Composite Capital Programme following the proposed budget adjustments
detailed in this report. 
6. COMPOSITE CAPITAL PROGRAMME – EXPENDITURE 
6.1 Total Expenditure and Proposed Budget Adjustments to the Current
Programme 
6.1.1 Total expenditure (net of grants and contributions) to 29 February 2024 on the
Composite Capital Programme is detailed in Appendix II and summarised as
follows: 
Projected
Outturn
(£m)
Net Expenditure
to 29 February
2024 (£m)
% of
Projected
Outturn    
Education & Children’s Services  53.443 39.656 74%
Communities 73.438 68.953 94%
Health & Social Care 1.053    0.557 53%
Corporate & Democratic Services 8.623 5.438 63%
Total Net Capital Expenditure 136.557 114.604 84%
69.5%
26.2%
0.2%
1.8%
1.3%
1.0%
4.3%
Projected Capital Resources 2023/24
(March 2024)
Borrowing (£109.837M)
Grants (£41.479M)
Tay City Deal (£0.271M)
Developer Contributions (£2.847M)
Third Party & Revenue Contributions (£2.087M)
Receipts (£1.617M)
£Million

Page 6

6.1.2 The Service Budget projections included within this section and Appendix II
to Appendix IV have been prepared based on the Council’s previous
structure.  Going forward, future reports will reflect the new structure. A
comprehensive monitoring exercise has been carried out, which is detailed in
Appendix II. The most significant features are discussed below. 
6.1.3 In common with all Scottish local authorities and public and private sector
bodies, the Council has experienced significant inflationary pressures on the
delivery of its Capital investment programme over the past few years. 
6.1.4 The Building Cost Information Service (BCIS) publish well established cost
indices for the construction industry. The BCIS All-in Tender Price Index,
which shows the general movement on construction pricing, currently
forecasts a 2.9% increase in construction costs in the current year compared
to 8.6% for the same period last year, indicating a continuing slowdown in
construction inflation. BCIS expects annual growth in tender prices to continue
to fall, reaching 1.6% by the end of 2024, however, global issues may
significantly impact both haulage costs for raw materials and fuel costs and
the situation will be kept under review. 
6.2 Education & Children’s Services 
6.2.1 The Executive Director (Education & Children’s Services) reviewed the
programme for their Service and proposed the following budget adjustments
which reflect the rephasing of existing budgets: 
Project 2023/24
£m
2024/25
£m
Later
Years
£m
Description
Investment in
Learning Estate
0.243 (0.243) 0.000 Acceleration of budget to align with
works completed in 2023/24. 
Methven Primary
School
Refurbishment
0.119 (0.119) 0.000 Acceleration to cover fees that
were incurred earlier than
previously anticipated.
New Primary
School at Bertha
Park site
0.159 0.000 (0.159) Programme previously revised in
line with current/anticipated
housebuilding in the catchment
area. Rephasing of some funding
to cover the fees incurred in
2023/24. 
Perth Academy
Refurbishment
0.755 (0.755) 0.000 Rephasing of budget to align with
latest estimated cashflow and year
end projection from the contractor.
Perth Grammar
School
0.263 (0.263) 0.000 Planned works were previously
rephased by one year to reflect
diversion of resources towards
replacement of Reinforced
Autoclaved Aerated Concrete
(RAAC) roof during 2023.
Acceleration reflects cost of works
that were actioned during 2023/24.

Page 7

Perth High School
– New School
(4.840) 4.840 0.000 Rephasing of budget to align with
latest estimated cashflow from the
contractor. There is no change to
the planned completion date. 
6.2.2 All of the above proposed adjustments have been reflected in Appendix II. 
6.3 Communities 
6.3.1 The Executive Director (Communities) reviewed the programme for their
Service and proposed various budget adjustments, the most significant of
which are described below. 
6.3.2 Within Traffic & Road Safety, it is proposed to transfer £66,000 from
Pedestrian Crossings in future years to Cycling, Walking and Safer Streets
(CWSS) in the current year. Consequently, it is also proposed to reallocate
£66,000 of CWSS grant to this programme. In addition, due to increased
costs on the extension of car parking within Auchterarder, an additional
Revenue Contribution from the Car Parking Reserve of £40,000 is proposed. 
6.3.3 Within the Structural Maintenance budget, it is proposed to move £922,000 to
2024/25 due to the team focussing on works as part of the Bellwin Scheme.
This movement encompasses an underspend of £746,000 in the current year,
combined with additional Third-Party Contributions of £91,000 from Scottish
Forestry, £80,000 from Scottish Gas towards reinstatement works and £5,000
for Road Adoptions. In addition, within Roads and Lighting the following
smaller adjustments are proposed:  
Project 2023/24
£m
2024/25
£m
Later
Years
£m
Description
Traffic Signal
Renewals 
(0.069) 0.069 0.000 During 2023/24 some works
to traffic signals were
funded in Revenue with an
impact on capital signal
works. These are now
scheduled for 2024/25.
Footways 0.077 (0.020) (0.057) Funding to be accelerated
from future years towards
additional works on Tay
Street. 
6.3.4 Within Asset Management – Bridges, it is proposed to draw down £42,000
from the Bridge Refurbishment Programme to Culteuchar Culvert in 2023/24,
with a further amount of £20,000 in 2024/25. In addition, the following
rephasings are proposed:

Page 8

Project 2023/24
£m
2024/25
£m
Later
Years
£m
Description
Bridge
Refurbishment
Programme 
(0.222)  (0.696) 0.918 Ongoing assessment of the
works to be completed during
2023/24 and 2024/25 has
concluded there will be
underspend in both years. It
is proposed this underspend
is rephased equally into
future years. 
Old Perth Bridge 
Perth Queen’s
Bridge
(0.140) 
(0.083)
0.040 
0.083
0.100 
0.000
All works that can be
completed prior to major
works in 2025/26 have
concluded. The remaining
budget is rephased in line
with planned works on Old
Perth Bridge and Queen’s
Bridge following the opening
of Destiny Bridge.   
Garry Viaduct (0.072) 0.072 0.000 There are delays on
consultancy work for Garry
Viaduct and it is proposed
£72,000 is moved by one
year to 2024/25. 
6.3.5 Within Improvement Schemes, £213,000 of the contingency budget within the
A9/A85 Road Junction Improvements budget is not required in 2023/24, and it
is therefore proposed that this is moved to 2024/25. The Cross Tay Link Road
(Destiny Bridge) project is progressing as planned and is currently on
schedule, however it is proposed that £15.057 million is rephased from
2023/24 to 2024/24 following a review of the value of works completed by the
31 March 2024. In addition, design and consultancy works have progressed in
2023/24 for the Bertha Park Link Road, with ground investigations and further
consultancy due to take place in 2024/25. Accordingly, it is proposed
£324,000 and £368,000 are accelerated from 2027/28 to cover these
respectively. 
6.3.6 Within Public Transport it is proposed the budget of £199,000 for Community
Transport Initiatives is moved to 2024/25 as a result of the 26 week lead time
to purchase vehicles. 
6.3.7 Within Flood Schemes, works at Comrie are expected to commence in August
2024 by the works contractor. The works on the scheme were previously
expected to last for 18 months but has been revised to 24 months. The flood
scheme at South Kinross is facing potential land acquisition difficulties and as
such is also likely to be delayed, whilst the flood scheme at Scone has been
paused by the Scottish Government with major works unlikely to take place
prior to 2027/28. It has therefore been necessary to revise the spend profile of
these schemes as outlined below:

Page 9

2023/24
£m
2024/25
£m
2025/26
£m
2026/27
£m
2027/28
£m
Comrie 0.000 0.121 (7.298) (1.623) 8.800
South Kinross 0.026 (1.496) (3.719) 1.964 3.225
Scone 0.000 0.004 (0.188) (0.348) 0.532 
In addition to the above, within Flood Protection Measures the following
rephasing’s are also proposed: 
Project 2023/24
£m
2024/25
£m
Later
Years
£m
Description
South Inch Culvert
Reinstatement 
(0.262)  0.262 0.000 Further engineering
assessment is necessary
resulting in a delay to work
in 2023/24.
Coastal Change
Adaptation
(0.100) 0.100 0.000 Flood team focussing on
severe weather in latter part
of 2023/24, this project has
therefore not progressed as
planned. 
6.3.8 Within Place-making, the Mill Street Environmental Improvements have been
completed and it is proposed that the remaining budget in 2023/24 of £78,000
is transferred to Perth City Centre Golden Route with £40,000 allocated to
2023/24 and the remaining £38,000 to 2024/25. In addition to this the
following rephasing’s are proposed: 
Project 2023/24
£m
2024/25
£m
Later
Years
£m
Description
Perth, Place,
People 
(3.598)  3.598 0.000 Discussions are ongoing
around potential schemes
and the possibility of match
funding. No scheme to
progress in 2023/24. 
Perth & Kinross
Lighting Action
Plan
(0.433) 0.433 0.000 The level of works to be
completed in 2023/24 is
lower than previously
anticipated. It is proposed
that £433,000 of the budget
is moved into 2024/25. 
6.3.9 In line with the Council decision on 28 February 2024, the budget for PH2O is
to be reviewed as part of the Review of Leisure Assets. In the meantime, it is
proposed that the existing budgets of the project in 2024/25 to 2027/28 be
rephased over this period, as reflected in Appendix II. This will be reviewed
further in light of the findings of the Review of Leisure Assets. 
6.3.10 Within Community Greenspace, a Revenue Contribution of £11,000 and
Third-Party Contribution of £13,000 have been provided towards Community

Page 10

Greenspace Bridges in 2023/24 and 2024/25 respectively, with a proposed
subsequent increase in the expenditure budget. Additional Third-Party
Contributions have also been received towards Core Path Implementation
(£24,000) and Premier Parks (£14,000) with the expenditure budgets for each
programme increased accordingly. On Community Greenspace Sites it is
proposed that the budget in 2024/25 is reduced by £321,000 with a further
reduction of £232,000 in 2025/26. Of this £432,000 is rephased to future
years with the remaining £121,000 vired between other Community
Greenspace projects as follows: 
Project 2023/24
£m
2024/25
£m
Settlement / Neighbourhood Parks  0.001 0.050
Community Greenspace Bridges 0.000 0.056
Core Path Implementation 0.012 0.000
Premier Parks 0.006 0.000
Auchterarder Public Park (0.004) 0.000 
0.015 0.106 
6.3.11 Within Commercial Property Investment Programme, works on the
Ruthvenfield Business Centre have been paused while other potential uses
for the site are identified. It is therefore proposed that £1.256 million of the
budget is moved into 2024/25. 
6.3.12 Within the Prudential Borrowing Projects, on Recycling Containers, it is
proposed to borrow an additional £160,000 over the next 4 years to cover
increased costs of replacement. Additionally, on the Vehicle Replacement
Programme, Fleet are continuing the catch-up exercise of vehicle purchases
following worldwide supply issues which has also resulted in the significant
increase in cost of new vehicles over the past couple of years. Deliveries are
expected in 2024/25 for vehicles purchased in 2023/24 and it is therefore
proposed to reduce the budget in 2023/24 by £113,000 and increase the
budget in 2024/25 by £5.231 million. There are corresponding adjustments to
capital receipts for vehicle disposals resulting in a net increase in borrowing of
£5.040 million for vehicles. The total increase in Prudential Borrowing
Projects is £5.2 million. 
6.3.13 Within Housing Projects, following a vacancy on the team and with a focus on
the chalet replacement project at Double Dykes, Gypsy Traveller Site
Improvement works have not been progressed in 2023/24 and it is proposed
that a total of £409,000 is moved into 2024/25.   
6.3.14 All the above proposed adjustments, together with other small movements,
have been reflected in Appendices I & II. 
6.4 Corporate & Democratic Services 
6.4.1 The Chief Operating Officer reviewed the programme for their Service and
proposed the budget adjustments described below.

Page 11

Property Services 
6.4.2 Within the Property Compliance Works Programme the preliminary work on
the Friarton Depot Transfer Shed structural remedials are to take place
following the 2023/24 year-end, and as such it is proposed that £327,000 is
moved into 2024/25. Similarly, on the Capital Improvement Projects
Programme with work scheduled to take place in 2024/25, it is also proposed
that £238,000 of this budget is moved into 2024/25. 
6.4.3 The Upgrade Programme at Pitlochry High School requires further
infrastructure works which are likely to be disruptive. With the need to protect
the learning environment these works could not take place in 2023/24 and will
instead be undertaken during the summer holidays and require the moving of
£136,000 to 2024/25.   
6.4.4 Within Decarbonisation there is a delay to delivery of Phase II following delays
in the completion of contract documentation with works now due to take place
in 2024/25, with £150,000 of the budget moved accordingly. 
6.4.5 Implementation of the Mosaic Social Work system is progressing and is
anticipated to “go-live” in the summer 2024. Accordingly, an increased amount
has been spent for Consultancy and Data Migration in 2023/24 with a
corresponding reduction in 2024/25. It is therefore proposed to rephase the
budget as shown in Appendix II. 
6.4.6 All the above proposed adjustments, together with other small movements,
have been reflected in Appendix II. 
6.5 Health & Social Care 
6.5.1 Within Occupational Therapy Equipment, the service is seeing an increase in
demand from the growing elderly population combined with an increase in the
number of items of equipment individuals require, as well as inflationary cost
increases for the equipment. It is therefore proposed that £100,000 is
accelerated from 2027/28 to 2023/24. 
6.5.2 The Technology Enabled Telecare project to upgrade the community alarm
system has faced supply difficulties during the year and issues with some
equipment requiring further testing prior to installation. These issues have now
been resolved and it is expected the project will now continue as planned. It is
therefore proposed that £350,000 of the budget in 2023/24 is rephased
equally across future years. 
7. HOUSING INVESTMENT PROGRAMME 
7.1  The total current estimated expenditure, net of contributions, for the Housing
Investment Programme over the 5 years 2023/24 to 2027/28 amounts to
£96.205 million. This has increased by £4 million following the approval of
the revised Housing Investment Programme by the Housing & Social
Wellbeing Committee on 24 January 2024 (Report 24/24 refers) which
allocated further resources to the Council House Buy-Back Programme from

Page 12

2024/25 to 2027/28. Movements from the previous estimates approved by this
Committee on 31 January 2024 are summarised in the table below and
detailed in Appendix III. 
Approved 
31 January 2024
Current
Estimate
Movement 
£m £m £m
2023/24 18.738 19.249 0.511
2024/25        18.831       21.536 2.705
2025/26 17.248 19.942 2.694
2026/27 16.283 15.633 (0.650)
2027/28 21.105  19.845  (1.260)
Total 92.205 96.205 4.000 
Total Expenditure to 29 February 2024 (Housing Investment Programme) 
7.2 Net expenditure for 2023/24 to 29 February 2024 amounts to £18.863 million
and receipts amount to £11,000. Therefore, the borrowing requirement for the
year to date is £18.852 million. 
7.3 The Executive Director (Communities) reviewed the Housing Investment
Programme and proposed the budget adjustments outlined below.
7.4 Phase 2 of the Council House New Build Programme at Lynedoch Road,
Methven has commenced with £1.243 million provided by the Scottish
Government in 2023/24 and an allocation from Council Tax Second Home
income of £240,000 in 2024/25. These amounts are complemented by
proposed transfers of £91,000 into 2023/24 and £932,000 into 2024/25 from
Future Developments budget in 2027/28.
7.5 It is proposed to transfer a further £1.237 million from the New Build Future
Developments Budget in 2027/28 to the Council House Buy-Back programme
in 2023/24. This is supplemented by additional grant of £630,000 from the
Scottish Government and reflects the additional properties being purchased in
the current year. A total of 48 properties have been purchased this year,
which exceeds the target of 30 properties. 
7.6 On the Triple Glazing Programme, additional addresses have been identified
that require an upgrade to their windows. It is proposed that £1.5 million is
transferred from SHQS Future Developments in 2026/27 with £1.2 million
allocated to 2023/24 and £300,000 in 2024/25. These movements also take
account of some properties which were previously identified for triple glazing
but not actioned due to access difficulties. Following considerable work by
tenant liaison officers, access has now been achieved and the installations
have commenced.

Page 13

7.7 The following rephasings/virements are also proposed: 
Project 2023/24
£m
2024/25
£m
Later
Years
£m
Description
Heating Upgrade
Contract Works
0.215 (0.215) 0.000 Accelerate due to improved
access rates and addresses
now certified that were
previously missing
completion certificates.
Rewiring,
Infrastructure &
Property
Refurbishment
(0.850) 0.000 0.850 Based on current level of
work completed in year.
Environmental
Improvements
0.150 0.000 0.000 Fund anticipated costs at
Pullar Terrace and
additional works to drainage
work at Firbank Road.
SHQS Future
Developments 
0.000 0.000 (0.150)
Fire Precaution
Measures
(0.224) 0.224 0.000 Delay to completing contract
due to access issues
requiring forced access and
delays to additional smoke
detector fittings.
Sound insulation (0.289) 0.289 0.000 No works were identified in
2023/24.
Structural (0.463) 0.000 0.463 Minimal works undertaken in
2023/24, moved to future
years.
Anchor House,
Rannoch Road
(0.060) 0.060 0.000 No further works to be
carried out in 2023/24.
Shops & Offices (0.239) 0.000 0.239 No works identified for
2023/24.
Upgrade and
Replacement to Lift
Programme
(0.116) 0.116 0.000 No works identified for
2023/24.
ICT Expenditure (0.110) 0.000 0.110 Moved to 2025/26 based on
latest projections. 
7.8 Third party contributions of £35,000 have been received towards External
Fabric works in 2023/24 and the expenditure budget has therefore been
increased accordingly. Similarly, the Scottish Government have provided a
grant of £71,000 towards Double Dykes Chalet Replacement resulting in an
increase to the expenditure budget by the same amount in 2023/24. 
7.9 The above proposed adjustments, together with other smaller adjustments
within Appendix III, do not impact the borrowing requirement over the 5-year
programme. However, there is an increase in Capital Funded from Current
Revenue (CFCR) of £0.28 million in 2023/24, as reported in the Revenue
Monitoring Report at this Committee meeting.

Page 14

7.10 The Housing & Social Wellbeing Committee also approved a reduction in
CFCR of £1.398 million over the years 2024/25 to 2027/28 in January 2024,
together with the additional £4 million allocated to Council House Buy-Backs.
This increased the borrowing requirement for the overall programme by
£5.398 million, which is offset by the increased CFCR above and an increase
in capital receipts of £3,000 in the current year, resulting in a net total
borrowing requirement of £85.819 million over the 5-year programme. 
8. BUDGET OVERVIEW 
8.1 The projected net expenditure outturn in 2023/24 for the Composite Capital
Budget is £136.557 million and represents 77% of the original 2023/24
budget approved on 26 April 2023 (£178.033 million). The revised budget is
based on the latest projections of expenditure and all budget adjustments
outlined within this report. 
8.2 Net expenditure to 29 February 2024 on the Composite Capital Budget is
£114.604 million and represents 84% of the proposed revised budget for
2023/24 of £136.557 million. The actual expenditure does not include
accrued expenditure or provision for works certified as completed. All such
expenditure is accounted for when preparing the final outturn as at 31 March
2024. 
8.3 The projected net expenditure outturn in 2023/24 for the Housing Investment
Programme is £19.249 million and represents 94% of the original 2023/24
budget approved on 26 April 2023 (£20.422 million). 
8.4 Net expenditure to 29 February 2024 on the Housing Investment Programme
is £18.863 million which represents 98% of the proposed revised budget for
2023/24 of £19.249 million. 
8.5 The Council’s total Borrowing Requirement to 29 February 2024, based on the
Composite and Housing Investment Programmes, is £112.235 million. The
estimated overall Council Borrowing Requirement for 2023/24 as a whole has
reduced by £32.056 million to £126.74 million as a result of the monitoring
adjustments reflected within this report. This mostly reflects updated cashflow
estimates on larger contracts as the year-end approaches. Over the whole 5-
year programme, there is an increase of £5.2 million in the overall level of
borrowing on the Composite Programme relating to Communities Prudential
Borrowing projects, and an increase in borrowing of £5.115 million on the
Housing Investment Programme relating to Council House Buy-Backs and
adjustments to CFCR. 
8.6 While the projections have been based on a comprehensive monitoring
exercise, they continue to remain subject to uncertainty due to ongoing
inflationary pressures in the current economic environment. 
Author(s)
Name  Designation Contact Details
John Jennings Senior Accountant  CHXFinance@pkc.gov.uk

Page 15

Approved 
Name Designation Date 
Scott Walker 
Clare Mailer 
Strategic Lead – Finance
& Business Support 
Director (Strategy, People
& Resources) 
17 April 2024

Page 16

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications 
Corporate Plan 
1.1 The Council’s Corporate Plan 2022 – 2027 lays out seven outcome focussed
strategic objectives which provide clear strategic direction, inform decisions at
a corporate and service level and shape resources allocation.  They are as
follows: 
• Tackling Poverty 
• Tackling climate change and supporting sustainable places 
• Growing a sustainable and inclusive local economy 
• Enabling our children and young people to achieve their full potential 
• Protecting and caring for our most vulnerable people   
• Supporting and promoting physical and mental wellbeing
• Placing communities at the heart of how we work 
1.2 This report relates to all of these objectives. 
2. Resource Implications 
Financial 
2.1 There are no direct financial implications arising from this report other than
those reported within the body of the main report.

Page 17

Workforce 
2.2 There are no direct workforce implications arising from this report other than
those reported within the body of the main report. 
Asset Management (land, property, IT)   
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the
Corporate Equalities Impact Assessment process (EqIA) and has been
assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. In terms of the Climate Change Act,
the Council has a general duty to demonstrate its commitment to sustainability
and the community, environmental and economic impacts of its actions.   
3.6 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
4. Consultation 
Internal 
4.1 The Chief Executive and the Executive Directors have been consulted in the
preparation of this report.

Page 18

2. BACKGROUND PAPERS 
No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (other than any containing confidential or exempt
information) were relied on to any material extent in preparing the above
report. 
3. APPENDICES 
Appendix I – Composite Capital Programme - Estimated Capital Resources
2023/24 to 2027/28
Appendix II – Composite Capital Programme - Summary of Capital Resources
and Expenditure 2023/24 to 2027/28        
Appendix III – HRA Capital Investment Programme – Summary of Capital
Resources and Expenditure 2023/24 to 2027/28 
Appendix IV – Significant Capital Projects Progress Update