APPENDIX 2
PERTH AND KINROSS COUNCIL - GENERAL FUND 2025/26 FINAL OUTTURN  - SERVICE ANALYSIS
Variance Variance
£'000 £'000
EDUCATION AND LEARNING
Total (1,942)
NON DEVOLVED
Education and Learning Core
(19) Underspend on clothing grants and parent council funding offset by not meeting slippage target
26 Overspend on free school meals over the holiday period due to exceptional closures and seven
week Summer 
Nursery Sector
(1,106) Underspend due to additional slippage over target due to turnover of staff; lower than anticipated
staffing required for deferred places and lower partner providers payments than budgeted.
Primary Sector
797 Slippage target projected not to be met within primary sector due to the requirement to have a
teacher in front of class at all times.
Secondary Sector
(848) Underspend due to slippage in excess of target as a result of part year allocation of fte required for
new Intensive Support Provisions and reduction in supplies and services spend.
Special Sector
(710) Underspend due to slippage in excess of target due to turnover of staff and challenges in
recruitment of posts- in particular pupil support assistants.
333 Overspend on independent school placements due to increased number of placements.
Home to School Transport
(415) Underspend due to lower number of school days in financial year 2025/26.  
DEVOLVED SCHOOL MANAGEMENT SCHEME (DSM)
542 Underspend of less than 1% of total budget.
(542) To be carried forward
PUPIL EQUITY FUND
103 Underspend to be utilised in advance of June 2026.
(103) To be carried forward
CHILDREN, FAMILIES AND JUSTICE
Total 123
Children and Families
(210) Overspend due to not meeting slippage target offset by reduction in demand for some services over
1st Quarter.
(603) Underspend on foster, kinship and adoption in part due to reduction in overall placements in foster
carers. This reduction in demand is linked to the new working practices which include a greater
focus on early intervention some of which is funded from the WFWF temporary funding. 
901 Overspend on residential placements due to additional placements in excess of budget and higher
inflation uplifts than budgeted.
Justice Service
35 Overspend In part due to unrecoverable employability sickness costs.
SERVICE Summary of Service Variances

Page 2

APPENDIX 2
PERTH AND KINROSS COUNCIL - GENERAL FUND 2025/26 FINAL OUTTURN  - SERVICE ANALYSIS
Variance Variance
£'000 £'000SERVICE Summary of Service Variances
ECONOMY, DEVELOPMENT AND PLANNING
Total (602)
Service Wide
(356) Slippage across Economy, Development & Planning in excess of target
20 Shortfall in sales ledger bad debt provision
20 Overspend for contribution towards Tay Cities Deal project management costs
(14) Other net underspends across Economy, Development & Planning budgets
Tourism, Culture and Place
126 Perth Harbour - increase in operating costs /shortfall in income.
89 Net overspend relating to events 
150 Savings delayed due to the ongoing review of our cultural and leisure ALEOs.
64 Net overspend in the Electric Vehicle Charging Points, trading account, mainly due to a shortfall in
income.
(77) Underspends across other Tourism, Culture & Place budgets - including Invest In Perth,  Market
Development Grants,  Business Projects, Green Capital Recovery Fund , offset by an overspend on
Enterprise & Investment projects.
(128) Increased income in the Commercial Property Investment Portfolio and underspends in Estates
consultants, licences and energy costs.
Development Management & Building Standards
(802) Additional Planning Application and Building Warrant  income
Roads Infrastructure
306 Expenditure on Cross Tay Link Road landscaping works
ENVIRONMENT AND INFRASTRUCTURE
Total (203)
Service Wide
149 Non-achievement of slippage target across Environment & Infrastructure
124 Shortfall in recharge to capital due to staff dealing with more severe weather and emergency events
34 Shortfall in sales ledger bad debt provision
35 Other net overspends across Environment and Infrastructure budgets
Direct Services - Waste Disposal
(389) Additional income from sale of recyclates as a result of the new twin-streaming collection and
favourable market prices.
(162) Net additional savings on the waste disposal contract as a result of increased residual waste
tonnage and gate fee price
(170) Saving on fuel
Direct Services - Refuse Collection
186 Net shortfall in commercial waste income
Direct Services - Fleet
196 Additional cost of vehicle materials and repairs.
(14) Net reduction in transport costs
Traffic and Network
(183) Additional income from statutory road network works.
(52) Underspend on Traffic TRO's
Roads Maintenance Partnership
97 Additional expenditure on routine and cyclic roads maintenance including emptying of gullies.
124 Overspend on flood maintenance
50 Additional expenditure on Council's severe weather response
Street Lighting Partnership
(35) Saving on repairs and maintenance
(136) Saving on energy due to positive impact of LED replacement programme
Climate Change & Zero Waste
(57) Underspend on Climate Change projects

Page 3

APPENDIX 2
PERTH AND KINROSS COUNCIL - GENERAL FUND 2025/26 FINAL OUTTURN  - SERVICE ANALYSIS
Variance Variance
£'000 £'000SERVICE Summary of Service Variances
HOUSING AND COMMUNITIES
Total 27
Service Wide
(94) Slippage across Housing & Communities in excess of slippage target
36 Shortfall in recharge to capital
(60) Underspend across non-staff budgets
39 Shortfall in sales ledger bad debt provision
Bereavement Services
10 Overspend on loan charges.
131 Shortfall in bereavement income
(58) Underspend across non-staff budgets
Community Learning & Development
(42) Various underspends across non-staff budgets
Public Transport Unit
(78) Additional income from park and ride departure charges
78 Overspend in relation to park & ride expenditure
37 Overspend due to health & safety works and a shortfall in income at Perth Bus Station.
54 Overspend on tendered service
(19) Underspend on loan for community transport
(42) Various underspends across non-staff budgets
Parking & Civil Contingencies
110 Overspend on Visitor Rangers
(26) Various underspends across non-staff budgets in Civil Contingencies and Safer Communities
230 Under-recovery of parking income
(499) Underspend on parking expenditure budgets
269 Return net underspend to parking reserve
Specialist Services
46 Overspend in property set-up costs for temporary accommodation
18 Overspend within Care & Repair
(46) Additional fee income from PKC Lets within the Private Sector Access Team
10 Overspend with Bed & Breakfast accommodation
(25) Underspend within Housing Support
(39) Additional Income from Missing Shares
(13) Various underspends across non-staff budgets in Specialist Services
PROPERTY SERVICES
Total (845)
Service Wide
225 Overspend due to not meeting slippage target, increased costs for loan charges and required works
for tree surveys and emergency works across the portfolio offset by lower water costs due to
completion of a detailed audit and proactive water saving measures and lower spend on external
contractors.
230 Projected overspend on unitary charge due to increased interest rates and historic lifecycle costs
and low income from Campus RHI.
7 Increased costs for grass pitch lets in LAL settings
Energy
(1,246) Projected reduction in energy costs due to reduced rates and consumption. Movement due to less
consumption, proactive energy management and milder weather between December to March.
Maintenance
(10) Small underspend.
Facilities Management
185
Overspend due to delay in implementing new cleaning schedule required to achieve £406,000
Tayside Contract approved saving and associated redundancy costs. New cleaning schedule for
offices in place from 1st July 2025. Reduction due to less than expected charges for new building.
308 Overspend in part due to shortfall in income target for Pullar House lets in the current year due to
delays from public sector partners and timing of building purchase.
Catering
(544) Underspend due to lower meals than budgeted. Movement due to reduced Q4 food costs than
projected by TC and additional Income.

Page 4

APPENDIX 2
PERTH AND KINROSS COUNCIL - GENERAL FUND 2025/26 FINAL OUTTURN  - SERVICE ANALYSIS
Variance Variance
£'000 £'000SERVICE Summary of Service Variances
LEGAL AND GOVERNANCE
Total (155)
27 Non-achievement of slippage target across Legal & Governance
(22) Additional income in staff recharge to capital
60 Overspend on supplies and services
(220) Additional income across Legal and Governance (Short Term Lets £124,000,  Licences £37,000,
Rebates On Contracts £19,000, External work including Council house buy backs £24,000 and
Private Landlord Registrations £16,000.
CUSTOMER AND DIGITAL SERVICES
Total (1,062)
IT & Customer Services
(910) Projected under spend on staff costs in excess of slippage target caused by delays in recruiting and
difficulties in sourcing suitably experience / skilled staff for technical IT roles including AI following
one off restructure. All posts are now filled. 
Revenues and Benefits
(37) Projected underspend due to excess staff slippage due to early delivery of savings.
(145) Additional statutory additions income and small underspend on supplies and services
30 Projected shortfall due to increased service charges from Social Housing Providers that are not
covered by Housing Benefit Subsidy. Movement due to increased debt recovery.
STRATEGIC PLANNING, PEOPLE AND PERFORMANCE
Total (555)
(241) Staff slippage across Strategic Planning, People and Performance in excess of slippage target
112 Overspend on supplies and services
(154) Net underspend on the Locality budget to reflect known commitments.
(272) Additional income from the salary sacrifice scheme
PROJECTS AND PROGRAMMES
Total 0 0 No material variances
FINANCE AND BUSINESS SUPPORT
Total (659)
(659) Underspend due to excess slippage in excess of  target due to turnover, early delivery of approved
savings and additional income.
CHIEF EXECUTIVE -
Total 0 No material variances