Appendix II - Composite Capital Programme - Summary of Capital Resources and Expenditure 2025/26 to 2030/31
Perth and Kinross Council · 22 April 2026
Back to Finance and Resources Committee — 22 April 2026 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30 APPENDIX II Approved Approved Proposed Revised Actuals Projected Revised Revised Revised Revised Revised Revised Budget Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Report 3 Adjustment Adjustment 28-Feb-26 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 2025/26 2024/25 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) ENVIRONMENT & INFRASTRUCTURE 41,504 0 (5,875) 35,629 29,706 35,629 52,743 28,184 25,783 20,919 17,167 180,425 HOUSING & COMMUNITIES 5,958 0 (3,187) 2,771 2,223 2,771 4,780 2,099 1,558 1,558 1,050 13,816 ECONOMY, DEVELOPMENT & PLANNING 24,054 0 (1,096) 22,958 12,840 22,958 13,246 12,680 10,250 (2,436) 1,186 57,884 PROPERTY SERVICES 33,923 0 (5,912) 28,011 23,158 28,011 40,790 49,120 36,056 42,350 43,027 239,354 CUSTOMER & DIGITAL SERVICES 4,185 (58) 2 4,129 2,057 4,129 4,848 11,104 6,214 6,030 12,256 44,581 HEALTH & SOCIAL CARE 953 0 0 953 893 953 1,353 1,369 1,370 1,354 1,326 7,725 UNALLOCATED CAPITAL RESOURCES 4,743 (4,743) 0 0 0 0 5,258 0 0 0 0 5,258 TOTAL NET EXPENDITURE 115,320 (4,801) (16,068) 94,451 70,877 94,451 123,018 104,556 81,231 69,775 76,012 549,043 (NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS) GENERAL CAPITAL GRANT (12,438) 0 0 (12,438) (12,988) (12,438) (12,481) (21,752) (12,750) (12,750) (12,750) (84,921) DEVELOPER CONTRIBUTIONS (5,344) 3,844 0 (1,500) 0 (1,500) (1,800) (2,000) (2,000) (2,000) (2,000) (11,300) CAPITAL RECEIPTS (1,189) 0 497 (692) (253) (692) (732) (2,398) (2,530) (645) (800) (7,797) ANNUAL BORROWING REQUIREMENT 96,349 (957) (15,571) 79,821 57,636 79,821 108,005 78,406 63,951 54,380 60,462 445,025 CAPITAL RECEIPTS BROUGHT FORWARD (1,332) 0 0 (1,332) (1,332) (1,332) (2,614) (2,449) (3,947) (4,577) (5,022) (1,332) CAPITAL RECEIPTS CARRIED FORWARD 2,614 0 0 2,614 384 2,614 2,449 3,947 4,577 5,022 1,922 1,922 TOTAL NET BORROWING REQUIREMENT 97,631 (957) (15,571) 81,103 56,688 81,103 107,840 79,904 64,581 54,825 57,362 445,615
Page 2
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30 APPENDIX II Revised Approved Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised Budget Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Adjustment Adjustment 28-Feb-26 Report 3 04-Mar-26 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 2025/26 2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) ENVIRONMENT & INFRASTRUCTURE Traffic & Road Network Road Safety Initiatives (20mph Zones etc..) 732 732 212 732 453 453 417 418 418 2,891 Scottish Government Grant (Transport Scotland) (530) (530) (530) 0 0 0 0 0 (530) Road Safety Initiatives - A94 Safety Improvements 84 84 84 0 0 0 0 0 84 Active Travel Grant -Traffic & Road Safety Schemes 1,823 (418) 1,405 716 1,405 1,138 600 600 600 600 4,943 Third Party Contribution (1,050) 90 (960) (960) 0 0 0 0 0 (960) 20mph Signage Programme 0 0 0 120 0 0 0 0 120 Additional Road Safety - Pedestrian Crossings 246 (124) 122 112 122 277 0 0 0 0 399 Traffic Signal Renewals - Upgrading 200 (70) 130 55 130 270 300 300 100 95 1,195 Investment in Local Footpaths 0 0 0 120 0 0 0 0 120 Car Parking Investment - Pitlochry 7 7 7 7 0 0 0 0 0 7 Revenue Contribution (1) (1) (1) 0 0 0 0 0 (1) A977 Upgrades 0 0 0 177 0 0 0 0 177 Broich Road, Crieff - Road Realignment & Safety Measures 18 18 18 0 0 0 0 0 18 Sub-Total 1,529 0 (522) 1,007 1,102 1,007 2,555 1,353 1,317 1,118 1,113 8,463 Street Lighting Partnership Street Lighting 0 0 0 0 0 600 600 600 1,800 Sub-Total 0 0 0 0 0 0 0 0 600 600 600 1,800 Roads Maintenance Partnership Structural Maintenance 10,257 10,257 8,721 10,257 11,000 11,500 11,851 8,320 9,500 62,428 Third Party Contribution (513) (513) (197) (513) 0 0 0 0 0 (513) Footways 359 359 313 359 768 768 741 341 400 3,377 Third Party Contribution (2) (2) (2) (2) 0 0 0 0 0 (2) Perth Flood Protection Scheme (South Inch Culvert Reinstatement) 9 9 9 9 0 0 0 0 0 9 Sub-Total 10,110 0 0 10,110 8,844 10,110 11,768 12,268 12,592 8,661 9,900 65,299 Structures Bridge Refurbishment Programme 1,682 (349) 1,333 996 1,333 2,552 2,424 2,651 6,200 1,999 17,159 Old Perth Bridge - Strengthening 38 38 24 38 235 2,216 0 0 0 2,489 Perth Queens Bridge - Strengthening 81 81 8 81 179 192 1,850 0 0 2,302 Culteuchar Culvert 5 5 5 5 0 0 0 0 0 5 Garry Viaduct 393 393 266 393 183 1,195 1,755 786 25 4,337 Bolfrack River Retaining Wall 521 521 484 521 0 0 0 0 0 521 Bridge of Tilt 285 285 264 285 965 0 0 0 0 1,250 Corb Bridge Culvert, Kinross 398 398 387 398 0 0 0 0 0 398 Blairgowrie Bridge 200 (175) 25 2 25 150 1,200 0 0 0 1,375 Aldour 0 0 0 250 250 1,000 0 0 1,500 Vehicular Bridge Parapets Programme - Assess & Upgrade 10 10 10 24 0 0 0 0 34 Sub-Total 3,613 0 (524) 3,089 2,436 3,089 4,538 7,477 7,256 6,986 2,024 31,370 Flooding Comrie Flood Protection Scheme 17,730 (3,990) 13,740 11,362 13,740 17,083 0 0 0 0 30,823 Milnathort Flood Protection Scheme 331 (308) 23 2 23 308 0 0 0 0 331 South Kinross Flood Protection Scheme 480 480 373 480 10,517 3,099 75 0 0 14,171 Flood Mitigation Measures - Dunkeld and Craigie Burn 282 282 186 282 88 153 338 129 0 990 Investment in Surface Water Management Schemes - Leaky Dam, Rattray Burn3 3 3 48 44 255 0 0 350 Coastal Change Adaptation 0 0 0 59 0 0 0 0 59 Almondbank Flood Protection Scheme 0 0 153 0 0 0 0 0 0 0 Sub-Total 18,826 0 (4,298) 14,528 12,076 14,528 28,103 3,296 668 129 0 46,724 Climate Change and Zero Waste Climate Change Programme 215 (53) 162 42 162 580 200 0 0 0 942 Climate Change Unallocated 329 (329) 0 0 332 0 0 0 0 332 Nature Restoration 199 199 10 199 0 0 0 0 0 199 Sub-Total 743 0 (382) 361 52 361 912 200 0 0 0 1,473 Prudential Borrowing Projects Climate Change and Zero Waste Wheeled Bin Replacement Programme - Domestic Bins 279 (109) 170 158 170 309 200 220 220 225 1,344 Wheeled Bin Replacement Programme - Commercial Bins 71 71 48 71 20 20 25 25 25 186 Capital Receipts - Disposals (3) (3) (2) (3) 0 0 0 0 0 (3) Recycling in Schools - Waste Bin Purchases 18 (5) 13 7 13 25 30 0 0 0 68 Recycling Containers, Oil Banks & Battery Banks Replacement Programme99 99 53 99 163 105 70 70 75 582 Capital Receipts - Disposals (7) (7) (1) (7) 0 0 0 0 0 (7)
Page 3
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30 APPENDIX II Revised Approved Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised Budget Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Adjustment Adjustment 28-Feb-26 Report 3 04-Mar-26 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 2025/26 2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) Litter Bins 8 8 2 8 107 50 55 55 55 330 Direct Services Vehicle Replacement Programme 5,800 5,800 4,484 5,800 3,751 2,692 3,311 3,394 3,500 22,448 Capital Receipts - Vehicle Disposals (547) (547) (309) (547) (294) (269) (331) (339) (350) (2,130) Additional Electrical Vehicles (EVs) 0 0 0 200 200 0 0 0 400 Street Lighting Partnership Street Lighting Renewal - LED & Column Replacement 965 (35) 930 756 930 586 562 0 0 0 2,078 Sub Total 6,683 0 (149) 6,534 5,196 6,534 4,867 3,590 3,350 3,425 3,530 25,296 TOTAL - ENVIRONMENT & INFRASTRUCTURE 41,504 0 (5,875) 35,629 29,706 35,629 52,743 28,184 25,783 20,919 17,167 180,425 HOUSING & COMMUNITIES Community Greenspace Community Greenspace Sites 0 0 0 25 894 700 700 250 2,569 Play Areas and Parks 1,039 (241) 798 333 798 1,636 582 500 500 500 4,516 Third Party Contribution (19) 15 (4) (4) 0 (15) 0 0 0 (19) Revenue Contribution (50) (50) (50) 0 0 0 0 0 (50) 3G Pitch, Blairgowrie 34 (24) 10 10 24 0 0 0 0 34 Countryside Sites 0 0 0 0 139 0 0 0 139 Community Greenspace Bridges 106 106 81 106 0 0 0 0 0 106 Core Path Implementation 92 (26) 66 66 0 0 0 0 0 66 Third Party Contribution (92) 26 (66) (66) 0 0 0 0 0 (66) Kinnoull Hill 24 24 14 24 0 0 0 0 0 24 Third Party Contribution (16) (16) (16) (16) 0 0 0 0 0 (16) Crematorium Access Road 50 (45) 5 5 45 0 0 0 0 50 Cemetery Extensions 7 15 22 7 22 143 499 358 358 300 1,680 Sub-Total 1,175 0 (280) 895 419 895 1,873 2,099 1,558 1,558 1,050 9,033 Improvements New Gypsy Traveller Site 1,942 (1,914) 28 7 28 1,914 0 0 0 0 1,942 Sub Total 1,942 0 (1,914) 28 7 28 1,914 0 0 0 0 1,942 Parking, Public Transport Unit and Civil Contingencies Community Transport Initiatives 27 27 26 27 0 0 0 0 0 27 Bus Infrastructure Fund Expenditure 374 (374) 0 5 0 374 0 0 0 0 374 Sub-Total 401 0 (374) 27 31 27 374 0 0 0 0 401 Community Learning and Development and Equalities Community-Led Asset Transfers 75 (68) 7 5 7 68 0 0 0 0 75 Sub-Total 75 0 (68) 7 5 7 68 0 0 0 0 75 Prudential Borrowing Projects Parking, Public Transport Unit and Civil Contingencies Community Transport Vehicles 115 115 115 115 0 0 0 0 0 115 Kinnoull Street Car Park - Purchase & Upgrade 2,250 (551) 1,699 1,646 1,699 551 0 0 0 0 2,250 Sub Total 2,365 0 (551) 1,814 1,761 1,814 551 0 0 0 0 2,365 TOTAL - HOUSING & COMMUNITIES 5,958 0 (3,187) 2,771 2,223 2,771 4,780 2,099 1,558 1,558 1,050 13,816 ECONOMY, DEVELOPMENT & PLANNING Roads Infrastructure A9/A85 Road Junction Improvements (PTF Phase 1) 14 14 105 14 0 0 0 0 0 14 Destiny Bridge and New Kingsway (PTF Phase 2) 5,785 5,785 2,135 5,785 314 0 0 0 0 6,099 Bertha Park Link Road (PTF Phase 3) 10,598 10,598 8,836 10,598 4,462 0 0 0 0 15,060 Third Party Contribution 0 0 0 0 0 0 0 (1,064) (1,064) Perth Eco-Innovation Park at Perth West 1,724 1,724 450 1,724 3,921 16,000 10,500 0 0 32,145 Third Party Contributions - Tay Cities Deal 0 0 0 (1,055) (3,945) (500) (956) 0 (6,456) Other Third Party Contributions 0 0 0 (2,000) (3,000) (1,000) (1,000) (1,000) (8,000) Capital Receipts - Ring Fenced Land Disposals 0 0 0 (550) (725) (650) (680) (650) (3,255) Sub-Total 18,121 0 0 18,121 11,526 18,121 0 5,092 8,330 8,350 (2,636) (2,714) 34,543
Page 4
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30 APPENDIX II Revised Approved Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised Budget Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Adjustment Adjustment 28-Feb-26 Report 3 04-Mar-26 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 2025/26 2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) Tourism, Culture and Place Perth City Improvements (PTF Phase 4) 0 0 0 3,642 0 0 0 0 3,642 City Greening 31 (31) 0 0 31 0 0 0 0 31 Perth & Kinross Lighting Action Plan 1,175 (1,065) 110 107 110 281 0 0 0 0 391 Low Carbon Transport & Active Travel Hub - Broxden EV Chargers 0 0 78 0 0 0 0 0 0 0 Third Party Contribution - Tay Cities Deal 0 0 (45) 0 0 0 0 0 0 0 Adapt Your Property - Vacant Town & City Centre Space 390 390 390 500 500 0 0 0 1,390 Adapt Your Property - Royal Bank Building, South Street, Perth 0 0 0 350 0 0 0 0 350 Glover Street, Perth Masterplan 0 0 0 750 0 0 0 0 750 Less Capital Receipt 0 0 0 (750) 0 0 0 0 (750) Sub-Total 1,596 0 (1,096) 500 140 500 4,804 500 0 0 0 5,804 Commercial Property Investment Programme Tourism, Culture and Place Broxden Drainage Mitigation Works 17 17 21 17 0 0 0 0 0 17 Mercian Buildings, Shore Road, Perth 451 451 713 451 0 0 0 0 0 451 Crioch Business Centre, Crieff 316 316 243 316 0 0 0 0 0 316 Northfield Business Park 2,027 2,027 117 2,027 0 0 0 0 0 2,027 Northfield Business Park (Phase 2) 0 0 0 0 0 800 0 0 800 Northfield Business Park - Site 6 0 0 0 0 1,500 0 0 0 1,500 Plot 4 Kinross West 1,526 1,526 80 1,526 0 0 0 0 0 1,526 Welton Road SBU's, Blairgowrie 0 0 0 200 1,400 0 0 0 1,600 Burnside Street SBU's, Pitlochry 0 0 0 600 0 0 0 0 600 Depot SBU's, Blackford 0 0 0 0 0 0 200 1,400 1,600 SBU's, Inveralmond Road, Perth 0 0 0 900 0 0 0 0 900 Land at South Turfhills Depot, Kinross 0 0 0 0 0 1,100 0 0 1,100 Aldour Business Centre, Pitlochry 0 0 0 0 0 0 0 900 900 Borlich Business Centre, Aberfeldy 0 0 0 0 0 0 0 1,600 1,600 Aberfeldy SBU's 0 0 0 700 0 0 0 0 700 4,337 0 0 4,337 1,174 4,337 2,400 2,900 1,900 200 3,900 15,637 Prudential Borrowing Projects Tourism, Culture and Place Land Purchase & Development (Hotel Development) 0 0 0 950 950 0 0 0 1,900 Sub Total 0 0 0 0 0 0 950 950 0 0 0 1,900 TOTAL - ECONOMY, DEVLOPMENT & PLANNING 24,054 0 (1,096) 22,958 12,840 22,958 13,246 12,680 10,250 (2,436) 1,186 57,884 PROPERTY SERVICES Project Support Investment in the Learning Estate 1,900 (570) 1,330 1,068 1,330 3,076 6,823 0 0 0 11,229 Braco Primary School Upgrade 150 150 17 150 350 3,000 5,000 0 0 8,500 School Toilet Upgrade Programme 600 85 685 465 685 515 600 500 500 500 3,300 Methven Primary School Refurbishment 700 700 514 700 2,970 0 0 0 0 3,670 North/West Perth - New Primary School 341 (306) 35 35 7,672 15,400 306 0 0 23,413 Perth Academy - Refurbishment 1,621 (247) 1,374 1,149 1,374 296 0 0 0 0 1,670 Perth Grammar School - Upgrade Programme Phase 3 600 103 703 599 703 1,525 819 0 0 0 3,047 Perth High School - New School Investment 11,718 (699) 11,019 9,984 11,019 5,599 0 0 0 0 16,618 Pitlochry High School Extension (Pitlochry Leisure Review) 200 46 246 133 246 704 5,000 2,750 0 0 8,700 Blairgowrie Recreation Centre - Replacement 832 (218) 614 590 614 1,918 0 0 0 0 2,532 Technology Upgrades 250 (240) 10 5 10 723 519 0 0 0 1,252 Community School of Auchterarder (FSM) 0 0 0 250 750 2,511 0 0 3,511 Community Campus Access Adaptations 25 25 16 25 0 0 0 0 0 25 Roof Upgrade Programme 500 (125) 375 170 375 625 610 500 500 500 3,110 Third Party Contribution 0 (110) (110) (110) 0 0 0 0 0 (110) Sub-Total 19,437 0 (2,281) 17,156 14,710 17,156 26,223 33,521 11,567 1,000 1,000 90,467 Property Service Management DDA Adaptation & Alteration Works Programme 250 250 149 250 303 200 200 200 200 1,353 Property Compliance Works Programme 609 609 477 609 650 650 650 650 650 3,859 Capital Improvement Projects Programme 1,866 1,866 883 1,866 1,800 2,000 4,294 5,500 11,000 26,460 Pitlochry High School - Upgrade Programme 20 20 7 20 0 0 0 0 0 20 Friarton Depot - Waste Transfer Station 2,300 (2,150) 150 78 150 2,371 0 0 0 0 2,521 Energy Efficiency Works - Various Properties 12 12 12 12 0 0 0 0 0 12 Revenue Contribution (Salix Reserve) (12) (12) (12) 0 0 0 0 0 (12)
Page 5
PERTH AND KINROSS COUNCIL COMPOSITE CAPITAL PROGRAMME SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2024/25 to 2029/30 APPENDIX II Revised Approved Proposed Revised Actual Projected Revised Revised Revised Revised Revised Revised Budget Budget Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Adjustment Adjustment 28-Feb-26 Report 3 04-Mar-26 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 Report 4 2025/26 2025/26 2025/26 2025/26 2025/26 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 TOTAL (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) Letham Community Wellbeing Hub 338 338 323 338 0 0 0 0 0 338 PH2O 300 (180) 120 32 120 1,700 2,000 10,000 30,000 30,027 73,847 Bells Sport Centre 414 (284) 130 59 130 1,784 1,500 3,500 3,000 0 9,914 Kinross Community Campus Sports Facilities 0 0 0 900 5,000 1,000 0 0 6,900 Crieff Community Campus Sports Facilities 0 0 0 0 1,000 4,000 1,300 0 6,300 Crieff Drummond Arms - Regeneration 750 750 645 750 2,192 0 0 0 0 2,942 Perth Concert Hall 200 (50) 150 118 150 500 1,000 695 550 0 2,895 Perth Museum 113 (67) 46 23 46 67 0 0 0 0 113 Sub-Total 7,160 0 (2,731) 4,429 2,806 4,429 12,267 13,350 24,339 41,200 41,877 137,462 Prudential Borrowing Projects Decarbonisation 178 178 31 178 350 0 0 0 0 528 Energy Conservation & Carbon Reduction Programme 189 189 162 189 150 150 150 150 150 939 Third Party Contribution (41) (41) (41) 0 0 0 0 0 (41) Pullar House - Purchase & Re-Purposing 7,000 (900) 6,100 5,449 6,100 1,800 2,099 0 0 0 9,999 Sub-Total 7,326 0 (900) 6,426 5,642 6,426 2,300 2,249 150 150 150 11,425 TOTAL - PROPERTY SERVICES 33,923 0 (5,912) 28,011 23,158 28,011 40,790 49,120 36,056 42,350 43,027 239,354 CUSTOMER & DIGITAL SERVICES ICT Infrastructure Replacement and Upgrade Programme 2,079 2,079 1,691 2,079 2,987 8,666 3,940 3,550 9,487 30,709 Data & Analytics 733 (58) 675 57 675 718 850 900 804 845 4,792 Supporting Digital 681 681 54 681 966 1,106 1,063 1,230 1,085 6,131 Software Licences (Revenues & Benefits) 50 2 52 52 52 78 82 85 87 90 474 School Audio-Visual (AV) Equipment Replacement Programme 27 27 30 27 26 27 226 359 749 1,414 Mosaic - Swift Social Work System Replacement 659 659 217 659 197 497 0 0 0 1,353 Revenue Contribution (124) (124) (124) (124) (124) (124) 0 0 0 (372) Case Management System 80 80 80 80 0 0 0 0 0 80 TOTAL - CUSTOMER & DIGITAL SERVICES 4,185 (58) 2 4,129 2,057 4,129 4,848 11,104 6,214 6,030 12,256 44,581 HEALTH & SOCIAL CARE Occupational Therapy Equipment 250 250 250 250 300 300 300 284 256 1,690 Technology Enabled Telecare 650 650 616 650 1,000 1,000 1,000 1,000 1,000 5,650 Software Licences 53 53 27 53 53 69 70 70 70 385 TOTAL - HEALTH & SOCIAL CARE 953 0 0 953 893 953 1,353 1,369 1,370 1,354 1,326 7,725 Unallocated Capital Resources 4,743 (4,743) 0 0 5,258 0 0 0 0 5,258 TOTAL COMPOSITE NET EXPENDITURE 115,320 (4,801) (16,068) 94,451 70,877 94,451 123,018 104,556 81,231 69,775 76,012 549,043 (NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS) CAPITAL INCOME & RECEIPTS General Capital Grant - Scottish Government (12,438) (12,438) (12,988) (12,438) (12,481) (21,752) (12,750) (12,750) (12,750) (84,921) Developer Contributions (5,344) 3,844 (1,500) (1,500) (1,800) (2,000) (2,000) (2,000) (2,000) (11,300) General Fund - Capital Receipts/Disposal (570) 497 (73) (27) (73) (497) 0 0 0 0 (570) Commercial Property - Capital Receipts/Disposal (619) 0 (619) (226) (619) (235) (2,398) (2,530) (645) (800) (7,227) Total: Capital Receipts (18,971) 3,844 497 (14,630) (13,241) (14,630) (15,013) (26,150) (17,280) (15,395) (15,550) (104,018) Annual Composite Borrowing Requirement 96,349 (957) (15,571) 79,821 57,636 79,821 108,005 78,406 63,951 54,380 60,462 445,025 CAPITAL RECEIPTS BROUGHT FORWARD (1,332) 0 (1,332) (1,332) (1,332) (2,614) (2,449) (3,947) (4,577) (5,022) (1,332) CAPITAL RECEIPTS CARRIED FORWARD 2,614 0 0 2,614 384 2,614 2,449 3,947 4,577 5,022 1,922 1,922 TOTAL NET COMPOSITE BORROWING REQUIREMENT 97,631 (957) (15,571) 81,103 56,688 81,103 107,840 79,904 64,581 54,825 57,362 445,615
Page 6
Project Project Description Traffic & Road Network Road Safety Initiatives (20mph Zones etc.) A programme of works to improve road safety Road Safety Initiatives - A94 Safety Improvements A programme of works to improve road safety on the A94 Active Travel Grant - Traffic & Road Safety Schemes A programme of works to improve active travel 20mph Signage Programme A programme of works to introduce 20mph speed limits. Schools Road Safety Measures A programme of works to improve road safety in the vicinity of schools Additional Road Safety - Pedestrian Crossings A programme of works to provide pedestrian crossing facilities Traffic Signal Renewals - Upgrading A programme of works to upgrade existing traffic signal infrastructure Investment in Local Footpaths A programme of works to improve and provide local footpaths Car Parking Investment - Pitlochry Purchase of land and construction of a public car park A977 Upgrades A programme of works to improve road safety along the A977. Broich Road, Crieff - Road Realignment & Safety Measures Realignment of Broich Road, Burrell Street and Gallowhill Junction Street Lighting Partnership Street Lighting Replacement of existing street lighting lanterns, columns and cable network. Roads Maintenance Partnership Structural Maintenance Road maintenance to extend the life of roads, including predominately road resurfacing, surface dressings, installing new drainage infrastructure and repairs to and replacement of defective embankments and retaining walls Footways Replacement of existing deteriorated footway surfaces Perth Flood Protection Scheme (South Inch Culvert Reinstatement) Ground investigation and monitoring then design project to refurbish existing culvert Road Safety Barriers Renewal of existing barriers where unrecoverable damage has occurred and renewal of barriers where timber posts have been used in construction Bridges Bridge Refurbishment Programme Used to appoint specialist external inspection teams and consultants to carry out specialist access bridge inspections and assessments Old Perth Bridge - Strengthening Carry out works recommended by the 2018 Bridge Assessment study, including a range of assessment, investigation, strengthening and improvement works Perth Queens Bridge - Strengthening Carry out works recommended by the 2018 Bridge Assessment study, including a range of assessment, investigation, strengthening and improvement works Culteuchar Culvert Replace existing temporary steel bridge (on hire) with culvert ENVIRONMENT & INFRASTRUCTURE
Page 7
Project Project Description Garry Viaduct Replacement of Bearings and Parapets; including strengthening of deck for bearing replacement jacking up, and to cater for increased parapet vehicular deterrent capacity Bolfrack River Retaining Wall Replacement of failed section of retaining wall supporting A827 adjacent to River Tay Bridge of Tilt Repairs to masonry bridge and installation of major scour mitigation measures Corb Bridge Culvert, Kinross Installation of structural lining to dilapidated culvert Blairgowrie Bridge Major scour mitigation scheme Aldour Vehicular Bridge Parapets Programme - Assess & Upgrade Assessment and Upgrading of Vehicle Parapets Programme Flooding Comrie Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in Comrie Milnathort Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in Milnathort South Kinross Flood Protection Scheme Design and construction of a scheme to reduce the risk of flooding in South Kinross Flood Mitigation Measures - Dunkeld and Craigie Burn Design and construction of schemes to reduce the risk of flooding in Dunkeld and Craigie Burn Investment in Surface Water Management Schemes - Leaky Dam, Rattray Burn Design and construction of a natural flood management measure (Leaky Dam) to reduce the risk of flooding in Rattray Coastal Change Adaptation Design and construct projects to deal with incidents of coastal erosion Climate Change and Zero Waste Climate Change Programme A programme of projects to meet the priorities to deliver the Top and High Priority Projects in the Council's Climate Change Strategy and Action Plan. Proposed projects will be scrutinised by the Council's Climate Change and Sustainabliltiy Group Nature Restoration Protection and restoration of biodiversity focusing on over- exploitation of the natural environment and addressing its consequences; habitat loss and fragmentation; and invasive non-native species. Prudential Borrowing Projects Wheeled Bin Replacement Programme - Domestic Bins Replacement of damaged and end of life wheeled bins for households. Also suppling bins for new properties Wheeled Bin Replacement Programme - Commercial Bins Replacement of damaged and end of life wheeled bins for commercial customers. Also suppling bins for new customers and changes to collection contracts Recycling in Schools - Waste Bin Purchases This project will improve the recycling infrastructure in PKC learning establishments and will improve positive behaviours with staff and pupils.
Page 8
Project Project Description Recycling Containers, Oil Banks & Battery Banks Replacement Programme Replacement of damaged and end of life oil and battery banks Litter Bins Replacement of damaged and end of life litter bins and/or for general supply of litter bins where required. Vehicle Replacement Programme Fleet vehicle replacement programme Additional Electrical Vehicles (EVs) Purchase of 20 additional electrically powered pool vehicles Street Lighting Renewal - LED & Column Replacement Street Lighting LED conversion and column replacement programme Community Greenspace Community Greenspace Sites Main fund for all Community Greenspace Sites which is drawn down to support the overall capital programme of refurbishments and upgrades Play Areas and Parks Refurbishment of 'Settlement and Neighbourhood' classification parks working in partnership with communities to improve, update and renew worn out or obsolete infrastructure. Small budget to facilitate refurbishment of former Premier Park upgrades 3G Pitch, Blairgowrie Two phase community led project to provide a new full sized 3G football pitch and pavilion Countryside Sites Refurbishment of more natural parks and open spaces Community Greenspace Bridges Refurbishment programme for all bridges on Community Greenspace sites Core Path Implementation Holding budget for Crieff Comrie Core path development mainly funded through Sustrans Kinnoull Hill Complete Crematorium Access Road Cemetery Extensions Funding to allow the extension of existing or development of new cemeteries to address the pressure for burial space Improvements New Gypsy Traveller Site Feasibility Study for Gypsy Traveller Transient Site Parking, Public Transport Unit and Civil Contingencies Community Transport Initiatives Purchase of vehicles and charging infrastructure for community transport/resilience groups to use to deliver on unmet need in the local area. Bus Infrastructure Fund Improving the infrastructure needed to operate buses Community Learning and Development and Equalities Community-Led Asset Transfers Financial assistance for community groups wishing to take on PKC assets using the community asset transfer process Prudential Borrowing Projects Community Transport Vehicles Providing vehicles to community transport groups HOUSING & COMMUNITIES
Page 9
Project Project Description Kinnoull Street Car Park - Purchase Purchase of Kinnoull Street Multi-Storey Car Park to increase Perth and Kinross Council car parking capacity to support delivery of the Perth City Integrated Investment Proposal Roads Infrastructure A9/A85 Road Junction Improvements (PTF Phase 1) New infrastructure including a new A9 overbridge, a bridge over the River Almond and road linking the A85 to Inveralmond and Bertha Park (Phase 1 of Perth Transport Futures Project) Destiny Bridge and New Kingsway (PTF Phase 2) New road and major structure over the River Tay, linking the A9 north of Inveralmond and the A94 north of Scone (Phase 2 of Perth Transport Futures Project) Bertha Park Link Road (PTF Phase 3) Phase 3 of Perth Transport Futures Project which is a new link road (1.4km) running through Bertha Park, connecting Phases 1 and 2. Perth Eco-Innovation Park at Perth West Provision of enabling infrastructure (access road, A9 underpass and unit platforms) to develop 25ha of employment land supporting clean growth, business innovation and jobs - Phase 1 (11ha). Tourism, Culture and Place Perth City Improvements (PTF Phase 4) Design and development of sustainable transport corridors to improve access to and from Perth and enable additional development and improvement within Perth city centre Perth City Centre Golden Route (Rail Station) Design and development of improvements to access, signage and animation from rail and bus station to Perth city centre to complement improvements to integration of transport City Greening Improvements to support enhancement of retail trading environment and residential areas and enhanced use of space for markets, events and alfresco use Perth & Kinross Lighting Action Plan Architectural and creative lighting to enhance city and towns appearance, reduce energy cost and increase safety at nighttime to increase dwell time, support the hospitality sector, events and grow the evening economy Low Carbon Transport & Active Travel Hub - Broxden EV Chargers Provision of fast EV chargers combined with solar power generation and battery storage at Broxden Park & Ride - Near completion Adapt Your Property - Vacant Town & City Centre Space Adapt Your Property supports capital adaptation works to empty and underused commercial property in city & town centres, looking at adaptation to attract new commercial, community or residential use. Adapt Your Property - Royal Bank Building, South Street, Perth Glover Street, Perth Masterplan ECONOMY, DEVELOPMENT & PLANNING
Page 10
Project Project Description Commercial Property Investment Programme Capital investment in economic development in serviced units and land Prudential Borrowing Project Land Purchase & Development (Hotel Development) This scheme involves the redevelopment of 1-5 High Street as serviced apartments courtesy of a heritage grant funding award that includes disposal to a developer subject to conclusion of a development agreement Project Support Investment in the Learning Estate Investment to upgrade the infrastructure and environment of our existing school estate Braco Primary School Upgrade Replacement school on adjacent land School Toilet Upgrade Programme Major toilet upgrades in various schools Methven Primary School Refurbishment Upgrade of Methven Primary School facilities including new dining and gym hall North/West Perth - New Primary School New primary school located at Bertha Park Riverside Primary New School Replacement of North Muirton and Balhousie primary schools Perth Academy - Refurbishment Investment to upgrade the infrastructure and environment of the Perth Academy including structural work to sports block, lighting upgrades, classroom upgrades and science block cladding Perth Grammar School - Upgrade Programme Phase 3 Investment to upgrade the infrastructure and environment of the Perth Grammar School including structural work to assembly hall, AV and WiFi upgrades, classroom refurbishment and door upgrades Perth High School - New School Investment Replacement of the existing Perth High School Pitlochry High School Extension (Pitlochry Leisure Review) Creation of community campus including sports facilities including 4 court sports hall and associated works Harris Academy/Invergowrie - Extension Extension and reconfiguration of existing space at Harris Academy in Dundee for continuation of access for pupils based in Invergowrie Blairgowrie Recreation Centre - Replacement Replacement of the Recreation Centre in Blairgowrie Technology Upgrades Upgrade to practical teaching environment within the existing school estate Community School of Auchterarder (FSM) Upgrading kitchen and dining facilities to provide the enhanced Free School Meals programme Community Campus Access Adaptations To support adaptations in schools and community campuses to help facilitate increased community access Roof Upgrade Programme Property Service Management DDA Adaptation & Alteration Works Programme To provide unhindered accessibility to all Council Buildings - e.g. Ramps/Lifts/Door Access/Accessible Toilets and Changing Areas PROPERTY SERVICES
Page 11
Project Project Description Property Compliance Works Programme To ensure compliance with current and changing legislation including - New Fire Alarms; Lighting; Wiring; Fire Protection Works; Gas pipework within buildings and Roof Restraint safety systems Capital Improvement Projects Programme Roof Upgrades; Full internal refurbishment works; New Heating Systems; Boilers and pipework; Structural Upgrades; Small extensions; New Windows/Doors; New Fencing; New Cladding Pitlochry High School - Upgrade Programme Upgrades to Mechanical and Electrical Infrastructure, including rewiring, heating and controls systems, replacement lighting and consequential building works such as new ceilings, painting and flooring Friarton Depot - Waste Transfer Station This project aims to refurbish the main waste transfer station building to provide a safe environment for workers. The project will involve a complete re-cladding of the existing structure, new doors and new services installation. Some initial enabling work are being carried out currently. Energy Efficiency Works - Various Properties Focusing on a spend to save with projects aiming to reduce energy cost across the property estate Letham Community Wellbeing Hub Complete PH2O Replacement of Perth Leisure Pool and Dewars Ice Rink. Bells Sport Centre Development of Bells' as an unheated, covered sports pitch and events space Kinross Community Campus Sports Facilities Improvements to the building fabric and energy efficiency of Live Active Loch Leven Crieff Community Campus Sports Facilities Improvements to the building fabric and energy efficiency of Strathearn Community Campus Leisure Facilities Crieff Drummond Arms - Regeneration Demolition of former hotel, regeneration of site for housing use Perth Concert Hall Roof and plant upgrades and compliance works Perth Museum Redevelopment of former Perth City Hall to New Perth Museum Prudential Borrowing Projects Decarbonisation This budget will support PKCs path to NetZero and focus primarily on the de-carbonisation of heat and replacing inefficient direct emissions heat sources Energy Conservation & Carbon Reduction Programme This budget is focused on works to reduce PKC energy consumption and help achieve annual KPI energy reduction of 3% Pullar House - Purchase & Re-Purposing Purchase and development of Pullar House to create a shared Public Sector Hub Customer & Digital Services
Page 12
Project Project Description ICT Infrastructure & Replacement and Upgrade Programme This Programme delivers the IT / digital environment, digital resources and systems required by staff and young people. The programme maintains, supports and develops computers; networks; telephony; Microsoft systems; connectivity and equipment; datacentres; servers; file storage and back up; security systems and video conferencing Data & Analytics Delivers the governance, tools, technologies and organisation-wide skills required for optimising value from Council data, driving informed decision making around resources, priorities and service delivery targets Supporting Digital Develops the capabilities we need to be an innovative digital organisation. Including developing the Council’s corporate employee (mobile working) and customer (online services) platforms, to create new digital products and services; investment in tools such as Microsoft; resourcing innovation and building digital skills, insight and expertise Software Licences (Revenues & Benefits) NAC Live system licensing for Revenues & Benefits team School Audio-Visual (AV) Equipment Replacement Programme Ensures all Perth and Kinross classrooms have equitable access to audio visual panels and the digital skills to exploit these resources for learning and teaching Mosaic - Swift Social Work System Replacement Purchase and Development of a new Social Work system to replace SWIFT Hardware Funding of additional or bespoke IT Hardware for Communities Staff Licenses Funding of software contracts Case Management System New system for management of client cases Occupational Therapy Equipment Supply and install of occupational therapy equipment following referral from health and social care professionals. Technology Enabled Telecare Replacement of existing analogue Community Alarm devices to digital alarm units prior to UK switch-off of analogue network, as well as ongoing rolling replacement programme. Moving & Handling Office Refurbishment Relocate staff base, currently under review Software Licences Various licences for essential social care systems HEALTH & SOCIAL CARE