Commercial Property Investment Programme (CPIP) Progress Update

Perth and Kinross Council · 22 April 2026
Back to Economy and Infrastructure Committee — 22 April 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality 
___________________________________________________________________  
Committee or Board: Economy & Infrastructure Committee 
Date of Meeting: 22 April 2026 
Report Title: Commercial Property Investment Programme (CPIP)
Progress Update 
Report Number: 26/107 
Report Author: Richard Dobson, Physical Infrastructure Project
Manager - Estate and Commercial Investment Team 
Organisational Lead: Serge Merone, Strategic Lead - Economy, Development
& Planning 
___________________________________________________________________ 
1. Purpose 
1.1 The purpose of this report is to provide a progress update on the Commercial
Property Investment Programme (CPIP), following the decision to allocate an
additional £7 million of capital funding to the Programme for the period 2025/26
to 2027/28. This investment is intended to support the delivery of new
employment land and buildings in line with the priorities set out in the Council’s
Corporate Plan 2022–27. 
1.2 Sections 
1. Purpose
2. Recommendation
3. Background/Context
4. CPIP Phase I Projects
5. CPIP Phase II Projects
6. CPIP Future Phases Projects
7. CPIP Disposals
8. Financial Position
9. Conclusion
10. Impact Value Assessment
11. Appendices 
2. Recommendation 
It is recommended that the Committee: 
2.1 Note the positive progress outlined in this report.

Page 2

3. Background/Context 
3.1  At its meeting on 27 August 2025, the Committee asked for an update on the
Commercial Property Investment Programme (CPIP) to be provided in the
Spring 2026 (Report refer 25/211). 
3.2 There is a shortage of available serviced employment land and small business
units (SBUs) across the Perth & Kinross area. With the private sector currently
unable to meet this demand, there is a clear need for the Council to support and
promote the development of employment land, attract inward investment, and
enable local business growth. 
3.3 The Council’s Corporate Plan 2022–27 identifies building a resilient, stronger,
and greener economy—driven by business growth and investment—as a key
strategic priority. In support of this, the Commercial Property Investment
Programme (CPIP) serves as a central delivery mechanism, enabling the
development of new Small Business Units (SBUs) and the servicing of
employment land (Reports 13/448 and 19/344 refer). Recognising that existing
economic development funding was insufficient to deliver the required
programme of projects, the Council approved an additional £7 million investment
in CPIP for the period 2025/26 to 2027/28 (£3M in 2025/26, £2M in 2026/27 and
£2M in 2027/28). As part of this decision, it was also agreed that progress would
be reported annually to this Committee to ensure continued oversight of
programme delivery, expenditure, and outcomes. 
3.4 A dedicated capital funding stream for CPIP is generated through the sale of
economic development assets such as serviced employment land. This funding
model is cyclical, as many of the assets sold were originally created through
earlier CPIP investment. This allows initial capital expenditure to be continually
reinvested to support future CPIP projects. 
3.5 The Programme has both capital and revenue implications. Borrowing to fund
capital works creates an associated revenue commitment, while the sale of
income‑generating assets to raise capital receipts reduces future rental income. 
3.6 The CPIP Expenditure Programme, provided at Appendix 1, sets out the cost
estimates for active projects scheduled for short and medium-term delivery
during the period 2026–2034. 
3.7 The following sections summarises historic and recent disposals at Northfield
Business Park and Kinross West Business Park, detailing CPIP investment to
date, the serviced land delivered, and the sales and development agreements
progressed. It highlights both the financial returns secured and the wider
economic benefits achieved, demonstrating the ongoing effectiveness of CPIP
investment in supporting business growth, leveraging private‑sector
development, and maintaining a long‑term supply of employment land. 
Northfield Business Park 
3.8 Historic spend of £3.84M on CPIP projects has delivered site infrastructure
including internal roads and 6.47 hectares (16 acres) of development land in the
area now known as Northfield Business Park, Perth.

Page 3

3.9 To date, six sites at Northfield have been disposed of for a total income of
£910K. 
3.10 Drainage infrastructure capacity issues hindered further disposals, but the
servicing of employment land sites was fully completed in 2024 and Graham +
Sibbald were appointed as external marketing agents. Sites 9 and 12 went to
closing dates in 2025, and the Property Sub-Committee approved the
acceptance of offers (Reports 25/125 and 25/220 refer) for an anticipated total of
£2.240m Both disposals will be by way of development agreements to ensure
that the sites are developed prior to transfer of ownership. 
3.11 £2.4M of CPIP funds were spent on the development of five SBUs at Site 5,
which are now known as the Perth Food and Drink Park units. These units were
completed in 2014. At the time of writing, four of the units are let to tenants that
are active in the food and drink sector, with the fifth unit being under offer of let. 
3.12 Site 7 and part of Site 6 are earmarked for a Gypsy Traveller Transient Site
(Reports 25/220 refer), subject to community engagement and all necessary
consents and approvals being secured. 
Kinross West Business Park 
3.13 In 2015, £1.1m of CPIP funding delivered the site infrastructure, internal roads
and 10 acres of development land at Kinross West which comprises five sites
(see appendix 5). Three of these sites (sites 1, 2 and 3) have been sold Site 5 is
at completion development stage for a total of £986,385. Site 4 will be developed
as a Council-led scheme for SBUs. 
3.14 A development lease for Site 1 at Kinross West has been completed with HGV
auto mechanics firm AJ Spence, who were due to receive title transfer and
commence operations in October 2025 (see Appendices 9 and 10). The family
run business will create two additional skilled fulltime positions, along with one
office role and one apprenticeship. 
3.15 A development lease for Site 5 at Kinross, progressed by AM AGRI Limited, has
received an amendment to the building warrant and is now awaiting a completion
certificate from Building Standards. Additional time has been granted to allow the
development to be finalised, reflecting the progress made to date (see
Appendices 11 and 12). 
3.16 Together, these historic CPIP projects demonstrate the sustained effectiveness
of the programme in delivering serviced employment land, supporting business
expansion, and enabling private sector development that might not otherwise
have taken place. This strong foundation provides the context for the sections
that follow, which outline the current Phase I and Phase II projects, longer term
future phases, and the associated programme of planned disposals. 
4. CPIP Phase I Projects 
4.1 Section 4 provides an overview of the Phase I projects that are enhancing the
quality, performance, and market competitiveness of the Council’s commercial
estate. Refurbishment works at Mercian and Crioch, alongside new SBU

Page 4

developments at Northfield and Kinross West, are progressing on schedule and
are already generating increased market interest and higher rental values.
Collectively, these projects strengthen the Council’s commercial offer and
position the portfolio for continued economic growth and long-term revenue
improvement. 
4.2 All Phase I projects were procured through the SCAPE framework, which offers
a compliant public-sector procurement route designed to accelerate and
streamline the delivery of construction and consultancy projects. As a not-for-
profit framework focused on social value and sustainability, SCAPE ensures
access to high-quality contractors while supporting net zero objectives and
delivering broader community benefits. 
Mercian Buildings Refurbishment 
4.3 Nine business units are located at Mercian Buildings (see Appendix 11). Three
units have undergone internal refurbishment, while the entire business centre—
originally constructed in the 1980s—has benefited from wider improvement
works. These included reinstating the original three unit layout and replacing key
components such as external doors, roller shutters, and sections of external
cladding (see Appendix 12). 
4.4 £451,000 of funding delivered the refurbishment of Mercian small business units
using the SCAPE framework. 
4.5 One new lease agreement has been secured, with entry scheduled for February
2026. Strong market interest indicates that full occupancy is likely to be achieved
shortly, with significantly higher rental levels across the portfolio. Prior to
refurbishment, the average rent at Mercian Buildings was £5.90 per sq. ft; the
refurbished units are now achieving lease agreements at £8.19 per sq. ft. 
Crioch Business Centre Refurbishment   
4.6 At Crioch Business Centre (see Appendix 13), two units underwent significant
refurbishment to reinstate the original two separate business units and upgrade
them to an appropriate, modern, and tenantable standard. 
4.7 £316,000 of funding delivered the refurbishment of Crioch small business units
using the SCAPE framework. 
4.8 Two lease agreements are in the final stages of concluding missives and
securing occupancy. Current tenant interest indicates that the refurbished units
will achieve higher rental rates than previous agreements. Before refurbishment,
a typical rental rate at Crioch Business Centre was £6.38 per sq ft; the upgraded
units are now securing lease agreements at £10.10 per sq. ft. 
Northfield Business Centre SBUs   
4.9 The CPIP is progressing an active project at Northfield Business Park to deliver
eight new SBUs on Site 8, forming the Northfield Business Centre (Phase I). A
site plan is provided at Appendix 4. The design team—appointed through the
SCAPE framework—includes Perth based mechanical and electrical engineers

Page 5

and architects. The estimated project cost is £3.654M. Planning permission
(25/01083/FLL) was granted on 23 December 2025, and building warrant
approval (25/01007/NDOM8) was issued on 13 January 2026. Construction is
scheduled to begin in the second quarter of 2026, with completion expected in
the first quarter of 2027 
Kinross West Business Centre SBUs   
4.10 £2.863 million of CPIP funding has been allocated to the development of Site 4
at Kinross West. This capital project covers the costs of servicing employment
land and delivering six SBUs of 7500 sqft (see Appendix 10). The design team—
appointed through the SCAPE framework—includes Perth based architects and
mechanical and electrical engineers, along with a Dundee based structural and
civil engineer. 
4.11 Full planning permission (25/01082/FLL) was granted on 21 January 2026. The
building warrant application (25/01009/NDOM8) was submitted on 10 September
2025 and is currently awaiting approval. The RIBA Stage 4 budget cost has been
completed, and contractor proposals under the SCAPE framework are due to be
submitted and reviewed prior to awarding the construction contract. 
4.12 Construction is scheduled to begin in the second quarter of 2026, with
completion anticipated in the first quarter of 2027. 
5. CPIP Phase II Projects 
5.1 Section 5 sets out the next pipeline of SBU developments, which are currently at
early design or feasibility stages. While these projects carry a lower degree of
cost and programme certainty, they represent an important part of the Council’s
longer-term investment strategy to expand commercial accommodation and
support local economic growth. Each proposal will progress subject to detailed
design work, statutory approvals, and confirmation of funding. 
New SBUs – Northfield Business Centre (Phase 2) 
5.2 The Northfield Business Centre has been intentionally structured as a two-phase
development. All enabling infrastructure required for Phase II—including roads,
parking, and utilities—has already been delivered through Phase I, ensuring the
site is fully serviced and ready for construction when needed. Delivering the
project in phases allowed CPIP funding to be distributed more evenly across
Perth & Kinross in the initial programme, while also providing time for market
testing and for refining the design and delivery approach based on lessons
learned from Phase I. This phased strategy also provides flexibility to respond to
any potential oversupply of small business units in the area and to tailor the
Phase II buildout to changing market conditions. 
5.3 An additional four SBUs are proposed at Site 8 as Phase II of the Northfield
Business Centre. A total of £1.34 million of CPIP funding has been allocated to
this phase, which is projected for completion in 2029.

Page 6

New SBUs - Welton Road, Blairgowrie 
5.4 The site to the south of the Welton Road Industrial Estate has been safeguarded
for employment use for several years, and Blairgowrie has consistently been
identified as an area with strong demand for modern light industrial
accommodation. This capital project proposes servicing the land and delivering
associated infrastructure works to create six SBUs of 1,250 sq. ft each, at an
estimated cost of £2.6 million funded through CPIP (see Appendix 14). 
5.5 A design team will be appointed and instructed to begin work in 2026. An
architectural concept—integrating key engineering requirements and aligned
with the cost plan, project strategies, and outline specification—will be
developed, with project completion anticipated in 2028. 
Inveralmond Small Business Centre 
5.6 The closure of several ATS Euromaster branches across the UK has resulted in
the ground lease for the site on Ruthvenfield Road reverting to Council’s Estates.
Inveralmond is one of Perth’s prime industrial areas, with consistently strong
occupier demand. Although the building could be relet to a similar operator, the
existing structure requires significant repairs and mechanical upgrades, and
automotive workshop uses are not considered desirable within the Council’s
Estates portfolio. This capital project therefore proposes converting and
upgrading the former ATS Euromaster building (see Appendix 15), along with
associated works, to create four modern, energy efficient SBUs with a total
lettable area of 4843 sqft. The estimated cost of the project is £1.2 million,
funded through CPIP. 
5.7 A design team will be appointed and instructed to begin work in 2026. An
architectural concept—incorporating key engineering requirements and aligned
with the cost plan, project strategy, and outline specification—will be developed,
with completion anticipated by the end of 2028. 
New SBUs - Burnside Road, Pitlochry 
5.8 The disused Burnside Toilets building on Burnside Road, Pitlochry, along with
the surrounding land, had previously been marketed for disposal. However, site
constraints and areas of contaminated land significantly reduced market interest,
and earlier options for residential redevelopment proved unviable. Consequently,
concept designs (see Appendix 16) have been prepared proposing the site’s
regeneration through CPIP, bringing the land back into productive economic use. 
5.9 This capital project covers the costs of demolishing the former Burnside Toilets,
servicing the land, and delivering associated works to develop two SBUs of
2500sqft each. The estimated project cost is £600,000, funded through the
CPIP. 
5.10 Early pre-application discussions with Planning have been positive. A design
team will be appointed and instructed to begin work in 2026 to develop an
architectural concept that incorporates key engineering requirements and aligns
with the cost plan, project strategy, and outline specification. Completion is
anticipated in 2028.

Page 7

New SBUs - Aberfeldy Industrial Estate 
5.11 This capital project covers the costs of developing vacant serviced land, along
with associated infrastructure works, to deliver two SBUs of 1250 sqft each. The
estimated project cost is £700,000, funded through the CPIP. The project is
expected to be completed in 2028. 
6. CPIP Future Phases Projects 
6.1 Beyond 2028, further phases across various sites in Perth & Kinross will require
additional feasibility assessment due to several factors that must be fully
understood before any firm commitments can be made. These projects remain
part of the long-term development pipeline; however, their progression is likely to
depend on potential joint venture arrangements with private sector partners or on
decisions made by other Council services. As such, the scope, timing, and
funding requirements for these projects are expected to evolve as feasibility work
advances and partnership options are explored. 
7. CPIP Disposals 
7.1 Section 7 sets out the programme of disposals as currently agreed under the
CPIP, including assets affected by compulsory purchase, SBUs that have
become increasingly resource intensive to manage, ground lease sites identified
through the options appraisal, and serviced land suitable for private sector
development. In line with the Council’s disposal strategy, income generated from
these disposals will be reinvested directly into the CPIP, ensuring that capital
receipts continue to support the delivery of new industrial and commercial
developments. 
Compulsory Purchases 
7.2 The A9 dualling programme affects existing business units and employment land
at both Birnam and Pitlochry. The small business units at Station Road, Birnam,
located adjacent to the A9, are subject to compulsory purchase as part of the
Birnam–Tay Crossing works scheduled to begin in autumn 2028. Likewise, the
1.02 acres of previously allocated employment land at Fonab Business Park,
Pitlochry, will no longer be available for CPIP development. All five marketed
plots at Fonab are expected to be acquired through compulsory purchase as part
of the Pitlochry–Killiecrankie dualling works, with acquisitions anticipated to
commence in autumn 2026. 
Small Business Units 
7.3 Within the Council’s Estates portfolio, several small business centres are
becoming increasingly challenging to manage due to rising repair requirements
and falling below the energy efficiency standards set out in the strategic plan.
While disposal of these centres would reduce the rental income currently
generated, the resulting capital receipts can be reinvested into the CPIP to fund
modern, energy efficient units that offer higher long-term rental values and
significantly lower maintenance liabilities. This approach ensures that short-term
revenue reductions are offset by long-term improvements in asset performance
and financial sustainability. Modernising the commercial employment portfolio

Page 8

also helps prevent future management burdens from exceeding the Council’s
operational capacity. 
Ground Lease Disposals 
7.4 The Council approved the sale of five industrial ground lease sites to a private
landowner (report 25/126 refers). While this approach places some pressure on
the revenue budget, it increases the capital available for economic development,
supports the delivery of the proposed Inveralmond South development, and
strengthens the overall supply and market potential for serviced employment
land and small business units across the region. No additional Ground lease
disposals are planned in line with Council’s Property Investment Strategy. 
Serviced Land Disposals 
7.5 The CPIP originally enabled the development of the Northfield and Kinross West
industrial estates, creating fully serviced employment land for small and medium
sized businesses expanding beyond traditional small business units. These plots
offer opportunities for companies to design and construct bespoke premises
tailored to their long-term operational needs, making them more suited to private
sector development than Council led construction. Accordingly, these plots could
be considered for disposal, with the resulting capital receipts reinvested into the
CPIP to support future projects and maintain a pipeline of modern, fit for purpose
commercial accommodation. 
Asset Revenue Anticipated
income baseline
for Disposal 
Target
Date for
disposal
CPOs   
Birnam CPO £5,001 £130,000 2029
Fonab CPO £0 £243,000 2028
Existing SBUs   
*Fonab SBUs £16,000 £160,000 2028
*Mercian Buildings £73,000 £550,000 2030
*Crioch Business Centre £50,250 £400,000 2028
*Food and Drink Park  £69,250 £645,000 2029
Ground Leased Land   
Inveralmond & Whitefriars £78,580 £1,445,000 2028
Serviced Land Disposals £0 £2,848,000 2029
Total £292,081 £6,421,000 
* Subject to Property Sub-Committee consideration in terms of preferred offers. 
8. Financial Position 
8.1 Section 8 presents the financial assessment for Phases 1 and 2 of the CPIP,
incorporating capital costs, projected rental income, and the revenue impact of
planned disposals. 
Projects Rental income Project Costs
Phase 1  
Mercian Refurbishment £24,450* £451,000
Crioch Refurbishment £13,900* £316,000

Page 9

Northfield Business Park £100,000 £3,654,000
Plot 4 Kinross West £75,000 £2,683,000
Phase 2  
Welton Road SBUs £75,000 £2,600,000
Northfield Business Park
(Phase 2) £50,000
£1,340,000
Burnside Street SBUs £25,000 £600,000
Inveralmond SBUs Road £50,000 £1,200,000
Aberfeldy SBUs £25,000 £700,000   
Total £438,350 £13,544,000
*Rental uplift for refurbished industrial units 
8.2 Current borrowing rates are 3.5%, which equates to a revenue cost of £35,000
per £1 million borrowed. Total CPIP expenditure across Phases 1 and 2 is
estimated at £13,544,000, of which £6,421,000 is expected to be met through
planned disposals, resulting in revenue implications of £292,081 over the period.
While this introduces some financial pressure, the CPIP remains a critical
mechanism for enabling development that would not be delivered by the private
sector alone. 
8.3 By providing modern commercial space, servicing employment land, and
unlocking constrained sites, the programme supports business expansion and
stimulates further private sector investment. Although borrowing costs are not
fully offset by direct financial returns, the wider economic, social, and
regeneration benefits—including job creation, improved business infrastructure,
and enhanced conditions for local growth—demonstrate the programme’s
strategic value and justify continued investment. 
9. Conclusion 
9.1 The CPIP continues to make strong progress in delivering new and improved
commercial assets that address the shortage of serviced employment land
across Perth & Kinross. Phase 1 projects are already strengthening the Council’s
commercial estate, while Phase 2 and future phases will further expand
opportunities for business growth and investment. 
9.2 The programme remains a key mechanism for tackling market failure and
supporting sustainable economic development across the region. The additional
borrowing approved for CPIP has significantly enhanced the Council’s capacity
to deliver development at scale, enabling projects that would not have been
achievable under previous funding levels. This investment has accelerated the
delivery of modern commercial space and unlocked sites that the private sector
could not viably develop alone. 
9.3 Continued commitment to the programme will ensure the Council is well placed
to meet future demand and maintain a competitive, high-quality commercial
property portfolio that supports sustained business growth and contributes to
wider regional prosperity.

Page 10

10. Impact and Value Assessment 
10.1 This report has been classified as being an operational report and as such does
not require a full Impact and Value Assessment. 
11. Appendices 
Appendix 1 - CPIP Expenditure Programme 
Appendix 2 - Site Plan - Northfield Business Park
Appendix 3 - Site Plan - Food & Drink Park SBUs
Appendix 4 - Site Plan - Northfield Business Centre (Phase I)
Appendix 5 - Site Plan - Kinross West
Appendix 6 - Site Plan - Site 1, Kinross West
Appendix 7 - Photographs - Site 1, Kinross West
Appendix 8 - Site Plan - Site 5, Kinross West
Appendix 9 - Photographs - Site 5, Kinross West
Appendix 10 - Site Plan - Kinross West Business Centre
Appendix 11 - Site Plan - Mercian Buildings
Appendix 12 - Photographs - Mercian Buildings
Appendix 13 - Site Plan - Crioch Business Centre
Appendix 14 - Site Plan - Welton Road Business Centre
Appendix 15 - Site Plan - Inveralmond Business Centre
Appendix 16 - Site Plan - Burnside SBUs