Agenda Document Pack - Economy and Infrastructure Committee - 27/08/2025

Perth and Kinross Council · 27 August 2025
Back to Economy and Infrastructure Committee — 27 August 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Ambition | Compassion | Integrity 
Our vision is for 
a Perth and Kinross where everyone can live life
well, free from poverty and inequality 
Council Building
2 High Street
Perth
PH1 5PH 
20/08/2025 
A hybrid meeting of the Economy and Infrastructure Committee will be held in the
Council Chamber on Wednesday, 27 August 2025 at 09:30. 
If you have any queries please contact Democratic Services on (01738) 475000 or
email Committee@pkc.gov.uk. 
THOMAS GLEN
Chief Executive 
Those attending the meeting are requested to ensure that all notifications are silent
on their device and other devices are in silent mode. 
Please note that the meeting will be broadcast online and recorded.  The recording
will be publicly available on the Council’s website following the meeting. 
Members:
Councillor Eric Drysdale  (Convener)
Councillor Jack Welch  (Vice-Convener)
Councillor Hugh Anderson
Bailie Rhona Brock
Councillor Steven Carr
Councillor Stewart Donaldson
Councillor John Duff
Councillor Angus Forbes
Councillor Ken Harvey
Councillor Noah Khogali
Councillor Grant Laing
Councillor Willie Robertson
Councillor Frank Smith
Councillor Colin Stewart
Councillor Alan Watt
Page 1 of 128

Page 2

Page 2 of 128

Page 3

Economy and Infrastructure Committee 
Wednesday, 27 August 2025 
Agenda 
Members are reminded of their obligation to declare any financial or non-
financial interest which they may have in any item on this agenda in
accordance with the councillors’ code of conduct. 
1 WELCOME AND APOLOGIES/SUBSTITUTES   
2 DECLARATIONS OF INTEREST   
3 MINUTE OF MEETING OF THE ECONOMY AND
INFRASTRUCTURE COMMITTEE OF 28 MAY 2025 FOR
APPROVAL
(copy herewith) 
5 - 8 
4 OUTSTANDING BUSINESS STATEMENT
(copy herewith 25/209) 
9 - 12 
5 ADVERTISEMENT CONTROL NON-STATUTORY PLANNING
GUIDANCE
Report by Strategic Lead - Economy, Development and Planning
(copy herewith 25/210) 
13 - 44 
6 COUNCIL SUPPORT TO BUSINESSES
Report by Strategic Lead - Economy, Development and Planning
(copy herewith 25/211) 
45 - 72 
7 RENEWABLE AND LOW CARBON ENERGY SUPPLEMENTARY
GUIDANCE
Report by Strategic Lead - Economy, Development and Planning
(copy herewith 25/212) 
73 - 128 
Page 3 of 128

Page 4

Page 4 of 128

Page 5

Economy and Infrastructure Committee 
Minute of hybrid meeting of the Economy and Infrastructure Committee held in the
Council Chambers on Wednesday 28 May 2025 at 9.30am. 
Present: Councillors E Drysdale, J Welch, Bailie C Ahern (substituting for Councillor
H Anderson), K Allan (substituting for Councillor A Forbes), D Cuthbert (substituting
for Bailie R Brock), F Smith, S Donaldson, J Duff, K Harvey, N Khogali, G Laing,
S Carr, W Robertson, C Stewart and A Watt. 
In Attendance: S Merone, Strategic Lead – Economy, Development and Planning;
S Cumiskey (up to and including Item 6), A Dobson (up to and including Item 7),
S MacDonald, B Murray (up to and including Item 5), N Sworowski (up to and
including Item 5) (all Economy, Development and Planning); F Crofts, Strategic Lead
– Environment; C Daly, M Findlay, W Mahoney (up to and including Item 4),
D McKeown and B Watt (all Environment and Infrastructure); J Guild, S Hendry,
A Brown and M Pasternak (all Legal and Governance). 
Apologies: Bailie R Brock, Councillors H Anderson and A Forbes. 
Councillor E Drysdale, Convener, Presiding. 
Councillor E Drysdale led on Items 1-7 and Councillor J Welch led on Items 8-9. 
1. Welcome and Apologies 
Convener welcomed everyone to the meeting.  Apologies for absence were
noted as above. 
2. Declarations of Interest 
There were no Declarations of Interests in terms of the Councillors’ Code of
Conduct. 
3. Minute of Meeting of Economy and Infrastructure Committee of
5 February 2025 
The minute of the meeting of the Economy and Infrastructure Committee of
5 February 2025 was submitted and approved as a correct record. 
4. Outstanding Business Statement 
W Mahoney provided an update on Action 18 Road Gully Cleansing, advising
the Committee that information is now live on PKC website to raise awareness
amongst the public including informative videos and an interactive map of all gully
locations across Perth and Kinross and past or future cleansing dates. 
Resolved:
The status of actions in the Outstanding Business Statement (25/127) be
noted and completed actions removed accordingly.
3
Page 5 of 128

Page 6

5. LDP3 – Development Plan Scheme 
There was submitted a report by Strategic Lead – Economy, Development
and Planning (25/128) (1) seeking approval of the updated statutory Development
Plan Scheme which proposes a revised timetable for the preparation of the next
Perth and Kinross Local Development Plan (LDP3); and (2) highlighting the recent
addendum prepared in relation to the LDP2 Delivery Programme. 
Resolved:
(i) The updated Perth and Kinross Development Plan Scheme, be agreed.
(ii) The Strategic Lead – Economy, Development and Planning be authorised to
submit the Scheme to the Scottish Ministers.
(iii) The publication of the addendum to the Delivery Programme for LDP2, be
noted. 
6. Perth and Kinross Tourism Strategy and Action Plan 2025-2030 
There was submitted a report by Strategic Lead – Economy, Development
and Planning (25/129) seeking endorsement of the Perth and Kinross Tourism
Strategy and Action Plan 2025-2030. 
Resolved:
(i) The draft Perth and Kinross Tourism Strategy and Action Plan 2025-2023,
developed by Perthshire Tourism Partnership, be endorsed.
(ii) Officers be requested to bring back annual progress reports to this Committee
for consideration. 
(There followed a short recess and the meeting reconvened at 11.00am) 
7. Review of Perth Harbour Operations to Support ‘Harbour Quarter’ and
Inner River Tay Developments 
There was submitted a report by Strategic Lead – Economy, Development
and Planning (25/130) providing members with an update on the review of Perth
Harbour operations to support the delivery of the ‘Harbour Quarter’ promoted as part
of the Perth City Development and Design Framework and wider Inner River Tay
developments for leisure, tourism and nature. 
Resolved:
(i) It be agreed to proceed with the option of a Harbour Revision Order retaining
Statutory Harbour Authority and health and safety obligations excluding traffic
for commercial vessels over 24 metres and ceasing Competent Harbour
Authority duties in line with Transport Scotland suggestions.
(ii) The Strategic Lead – Economy, Development and Planning be requested to
report any financial implications of the review of Perth Harbour operations to
the Finance and Resources Committee.
(iii) The signification contributions made by the Harbour Board and its dedicated
members be acknowledged and it be noted that that as the Board is no longer
necessary it will be discontinued. 
Page 6 of 128

Page 7

In terms of Standing Order 22, Bailie Ahern requested his dissent to the
decision be noted. 
8. School Exclusion Zone Update 
There was submitted a report by Strategic Lead – Environment and
Infrastructure (25/131) (1) providing an update on the effectiveness of school
exclusion zones in Blairgowrie, Guildtown, Kinloch Rannoch and Perth; (2) proposing
additional pedestrian facilities at Blairgowrie and Perth; and (3) recommending
changes at the Viewlands zone in Perth to encourage better compliance with the
access restriction. 
Resolved:
(i) The effectiveness of the school exclusion zone programme within a defined
road environment, be noted.
(ii) The creation of permanent Traffic Regulation Orders for school exclusion
zones at Blairgowrie Community Campus and at Guildtown, Inch View and
Kinloch Rannoch Primary Schools, be approved.
(iii) The creation of an Experimental Traffic Regulation Order to trial and exclusion
zone at Tulloch Primary School, be approved.
(iv) The public consultation on changes to the Viewlands School Exclusion Zone
to encourage better compliance, be agreed.
(v) The provision of the additional measures to improve pedestrian facilities
around Blairgowrie Committee Campus and at Guildtown, Tulloch and
Viewlands Primary Schools, and the removal of the school exclusion zone
from the old Balhousie Primary School site, subject to consultation and
available budgets, be approved.
(vi) The implementation of a communications strategy to promote each school
exclusion zone, be approved. 
9. Active Travel Prioritisation Delivery Report 
There was submitted a report by Strategic Lead – Environment and
Infrastructure (25/132) (1) providing an update on projects completed in 2024/25; (2)
detailing the funding provided by Transport Scotland in 2025/26; and (3) seeking
approval of the Active Travel Prioritisation Delivery Plan. 
Resolved:
(i) The changes in Active Travel Infrastructure funding, be noted.
(ii) The projects implemented from Teir 1 and other external grant funding for
2024/25, as detailed in Appendix 1 to Report 25/132, be noted.
(iii) The Prioritisation Delivery Plan, as detailed in Appendix 2 to Report 25/132,
be approved.
(iv) Delegation of projects for delivery to the Strategic Lead – Environment and
Infrastructure, within available funding based on the prioritised list of projects
which have been subject to the criteria set out in the Prioritisation Deliver
Plan, be approved. 
Page 7 of 128

Page 8

Page 8 of 128

Page 9

ECONOMY & INFRASTRUCTURE COMMITTEE 
OUTSTANDING BUSINESS STATEMENT (OBS) 
(25/209) 
Please note that this statement sets out outstanding decisions of this committee along with an update and estimated completion date.  Actions
which are overdue are shaded for ease of reference.  Where an update reflects that an action is complete then the Committee’s agreement will be
sought to its removal from the OBS. 
No  Minute
Reference
Subject Title Outstanding Action Update  Lead Officer
/Service
Action Due /
Complete
Action
Expected
23. 28 May 2025
Item 5
LDP3 –
Development Plan
Scheme
Further information to
be provided in relation
to Appendix 3 –
Housing Land Audit
figures beyond Year 10.
Circulated to Members
via email 18/08/25
Brenda Murray /
Nicola Sworowski
COMPLETE 27 August
2025
24. 28 May 2025
Item 6
Perth and Kinross
Tourism Strategy
and Action Plan
2025 – 2030 
Further information to
be provided in relation
to types of businesses
classed as tourism
businesses.
Circulated to Members
via email 23/06/2025.
Suzanne
Cumiskey / Steve
Macdonald
COMPLETE 27 August
2025
25. 28 May 2025
Item 6
Perth and Kinross
Tourism Strategy
and Action Plan
2025 – 2030
Further information to
be provided in relation
to domestic nights and
the extent of overnight
stays this includes.
Circulated to Members
via email 23/06/2025.
Suzanne
Cumiskey / Steve
Macdonald
COMPLETE 27 August
2025
26. 28 May 2025
Item 6
Perth and Kinross
Tourism Strategy
and Action Plan
2025 – 2030
Further information to
be provided in relation
to encouraging visitors
to utilise various forms
of public transport.
Circulated to Members
via email 23/06/2025.
Suzanne
Cumiskey / Steve
Macdonald
COMPLETE 27 August
2025
27. 28 May 2025
Item 8
School Exclusion
Zone Update
Committee to consider,
in conjunction with
relevant officers, a
refresh or review of
Safer Routes to School
Climate Change funding
has recently been
awarded to support a
wider piece of work
around school road
David McArthur /
Craig Daly
DUE Summer /
Autumn
2026
4
Page 9 of 128

Page 10

No  Minute
Reference
Subject Title Outstanding Action Update  Lead Officer
/Service
Action Due /
Complete
Action
Expected
Plans to reflect new
residential
developments.
safety and sustainable
travel which will include a
review of existing school
travel plans.  There will
be a particular focus on
early years to promote
and encourage more
sustainable travel
methods with the
potential for spend to
save investment through
reduced home to school
transport costs.  This is a
medium term project
which would aim to report
back on findings by
summer / autumn 2026.
28. 28 May 2025
Item 8
School Exclusion
Zone Update
Update on the public
consultation exercise
on the proposed
changes to the
Viewlands school
exclusion zone.   
To ensure all parties
have an opportunity to
comment on the
proposed Viewlands
school exclusion zone,
further consultation will
be undertaken with
parents and residents
from the start of
September and conclude
by the end of the month. 
This will involve e-mail to
parents and a maildrop to
residents within and
adjacent to the trialled
zone.  The proposal is for
the access restriction to
be reduced in area to
Daryl McKeown /
Craig Daly
DUE 19
November
2025
Page 10 of 128

Page 11

No  Minute
Reference
Subject Title Outstanding Action Update  Lead Officer
/Service
Action Due /
Complete
Action
Expected
cover those streets closer
to the campus. 
Responses would be
collated in early October
and with a report
presented to E&I on 19
November 2025. 
The Road Safety Team
will be liaising with the
Head Teachers from the
end of August about
possible engagement
with school pupils in early
September.  A progress
meeting is also
scheduled with the Ward
Councillors for the end of
August.  Discussions
have taken place with
Police Scotland about an
enforcement strategy
should the new exclusion
zone be installed.  This
would include an
information campaign by
PKC at the start of each
term followed by
enforcement, although
this latter part will be
subject to Police
resources
Page 11 of 128

Page 12

Page 12 of 128

Page 13

Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality 
___________________________________________________________________  
Committee or Board: Economy & Infrastructure Committee 
Date of Meeting: 27 August 2025 
Report Title: Advertisement Control Non-Statutory Planning
Guidance 
Report Number: 25/210 
Report Author: Dante Sosa (Development Plan Team) 
Organisational Lead: Serge Merone, Strategic Lead – Economy,
Development and Planning
___________________________________________________________________ 
1. Purpose 
1.1 This report summarises updates made to the planning authority’s existing
non-statutory Advertisement Control Planning Guidance Note, including
comments received during the consultation period. It seeks approval to
finalise and adopt the guidance to support the Local Development Plan. Such
guidance would not have the status of being part of the Local Development
Plan, but where relevant to a decision would be a material consideration to
support the determination and enforcement of advertisement consents. 
1.2 Sections 
1. Purpose
2. Recommendations
3. Background/Main Issues
4. Consultation Responses and Final Amendments
5.  Conclusion
6. Impact and Value Assessment
7. Appendices 
2. Recommendations 
It is recommended that the Committee: 
2.1 Approves the Advertisement Control Planning Guidance. 
2.2 Delegates Authority to the Strategic Lead (Economy, Development and
Planning) to make any necessary amendments to the format and layout of the
guidance, and to adapt it for publication in accessible formats including online
and on paper.
5
Page 13 of 128

Page 14

3. Background/Main Issues 
3.1 Historic Information/Context 
3.1.1  The Council has powers to control the display of advertisements in the
interests of amenity or public safety. These powers are derived from Sections
182-187 of the Town & Country Planning (Scotland) Act 1997 (as amended),
and the provisions of the Town and Country Planning (Control of
Advertisements) (Scotland) Regulations 1984. The regulations are
accompanied by Circular 10/1984, which sets out the Scottish Ministers
guidance on the Control of Advertisements. 
3.1.2 The Regulations set out the circumstances in which advertisements need
consent from the planning authority and define limited circumstances where
advertisements may be displayed without the need for an application. There is
provision for planning authorities to set out relevant amenity or public safety
criteria, and these will be material to the determination of advertisement
consent applications. 
3.1.3 The Council’s predecessor authority adopted and issued a planning advice
note on advertisement control to guide applicants seeking advertisement
consent. That advice note set out some locally derived policy and guidelines
on advertisement control and illustrated the provisions of the relevant Act and
Regulations and the matters to be taken into consideration when determining
applications for advertisement consent. 
3.1.4 This advice note has remained unaltered for many years and requires to be
reviewed to ensure it remains relevant and fit for purpose. It is proposed to
prepare and issue the updated note as non-statutory planning guidance. 
3.2 Rationale for Recommendations made in Section 2 
3.2.1 It is proposed that non-statutory Advertisement Control planning guidance be
prepared to assist applicants in the preparation of applications for
advertisement consent. Non-statutory planning guidance does not have the
status of being part of the development plan, but where relevant to a decision
would be a material consideration to be afforded such weight as determined
by the decision maker. It would therefore be used to support the determination
of applications for advertisement consent. 
3.2.2 In terms of the content of the Advertisement Control non-statutory planning
guidance, it is proposed that it should closely follow the original advice note.
Few changes are proposed to the text and illustrations other than minor
technical amendments or corrections. There have been essentially no
changes to the advertisement regulations since they were introduced.
However, given the age of the original advice note, there is considerable
benefit in reviewing it to ensure it remains fit for purpose. 
3.2.3 A copy of the finalised Advertisement Control non-statutory planning guidance
is attached as Appendix 1 to this report. 
Page 14 of 128

Page 15

3.2.4 There are a few significant changes to the guidance note, these are
summarised in more detail as follows: 
3.2.5 Illuminated advertisements – The updated guidance includes reference to
new technical guidance – The Brightness of Illuminated Advertisements
including Digital Displays (2023) – prepared by the Institution of Lighting
Professionals. This reflects changes in technology, including the application of
digital displays. This is an area of the advertisement industry that has
experienced significant growth since the original guidance note and was
important to address in the updated guidance for Perth and Kinross. 
3.2.6 Special protection for rural areas – Section 183 of the Act makes provision
for authorities to establish areas of special control where different
advertisement regulations apply. The updated guidance proposes that the
Council’s area of special control be redefined as land outside of settlement
boundaries, to be consistent with the Local Development Plan. For the
definition of settlement boundaries, it is proposed to use the proposals maps
in the Perth and Kinross Local Development Plan (adopted 2019) and the
Cairngorms National Park Local Development Plan (adopted 2021). 
3.2.7 Window Decals and Manifestations – The updated guidance addresses the
issue of large-scale displays on shop or office windows using posters or
adhesive vinyls. There has been an increased use of these displays which
often have an adverse impact on active frontages, visual amenity and street
vitality. These displays may be acceptable where used to cover windows of
vacant premises, given they are not consisting of advertisement clutter and
work to enhance the streetscape. 
4. Consultation Responses and Final Amendments 
4.1 The consultative draft was circulated internally for comments prior to being
published for external consultation. Views were sought from Development
Management and Development Plans to inform the draft. Once published the
consultation was shared with PKC’s Transport Planning and Roads Network
Management teams for feedback. 
4.2 The draft guidance was published externally on the Consultation Hub from 1-
29 July 2025. The feedback questionnaire seeks input on the clarity of layout
and information included, providing opportunity to comment on any changes
thought to be required. Notice of the consultation was sent to the
Development Plans contact list and advertised on PKC’s social media
channels. 
4.3 Views have been sought from the Cairngorms National Park Planning
Authority on the consultative draft, specifically requesting feedback on the
Areas of Special Control section which references settlements covered in the
park’s Local Development Plan. No response was received. 
4.4 Seventeen members of the public responded to the consultation on the draft
guidance. When asked about the clarity of its layout and content, eleven
answered "yes," five "somewhat," and one respondent did not reply. A
detailed summary of the feedback and the planning authority’s responses is
Page 15 of 128

Page 16

provided in Appendix 2. Five minor amendments have been made to the final
guidance, as outlined below. 
4.5 Stricter enforcement – Respondents welcomed the guidance and expressed
support for efforts to regulate advertising. Several comments emphasised the
need for stronger enforcement, particularly in Perth City Centre, Pitlochry, and
Conservation Areas. In response, Paragraph 10 of the Enforcement section
has been expanded to include a link to the Planning Enforcement webpage,
enabling users to report potential breaches. 
4.6 A-Boards – Several respondents recommended that the guidance address
the use of A-Boards, which were identified as a growing concern in certain
communities, notably Pitlochry. In response, Paragraph 11 of the
Enforcement section has been expanded to clarify that A-Boards fall under
the jurisdiction of the Roads Authority and are not covered by advertisement
control regulations or this guidance. A reference to Perth & Kinross Council’s
A-Board Guidelines—enforceable under Section 59 of the Roads (Scotland)
Act 1984—has been included. 
4.7 Pre-application advice – One respondent requested that PKC offer pre-
application advice for advertisement proposals. In response, Paragraph 12
has been updated to include links to both the advertisement consent
submission checklist and the pre-application service, where guidance can be
sought. 
4.8 Election notices – One respondent recommended strengthening the
guidance regarding electioneering signage. In response, Paragraph 54 has
been added to clarify that, under Regulation 12, election notices related to
pending elections are granted deemed consent, provided they are removed
within 14 days following the poll. 
4.9 Illuminated advertisements – One respondent recommended the guidance
should address illuminated displays near traffic lights. In response, Paragraph
65 has been included to reference proximity of illuminated displays near
roadways. 
5.  Conclusion 
5.1 The non-statutory Advertisement Control Planning Guidance has been
prepared to support the determination and enforcement of advertisement
consents. This document has been prepared through consultation with
internal and external stakeholders. 
6. Impact and Value Assessment 
6.1 https://www.pkc.gov.uk/media/54266/Advertisement-Control-Planning-
Guidance/pdf/Advertisement_Control_Planning_Guidance.pdf?m=175326721
1260 
Page 16 of 128

Page 17

7. Appendices 
7.1 Appendix 1 – Finalised Advertisement Control Planning Guidance 
7.2 Appendix 2 – Summary of Consultation Responses 
7.3 Appendix 3 – PKC Guidelines for A-Boards and Other Advertising Structures
on Footpaths 
Page 17 of 128

Page 18

Page 18 of 128

Page 19

1 
Perth and Kinross Council
Advertisement Control
Non-statutory planning guidance
Final Draft – August 2025 
Perth and Kinross Council (PKC) Policy on Signposting 
1. Advertisements play an important role in our lives: they provide information and an awareness
of services and products. But to serve their purpose, advertisements must command attention
through the careful selection of sites, sizes, colours and, in some cases, methods of illumination.
If there were no planning controls, advertisers would compete with each other by exaggerating
each of these characteristics and the resulting clamour for attention would have serious effects
on the appearance of our towns, villages and countryside. 
2. In order to strike a balance between the conflicting interests of freedom for advertisers and the
appearance of our surroundings, central government has provided regulations for use by
planning authorities that set out the circumstances in which advertisements need permission.
PKC’s Planning Authority’s interpretation of the Town and Country Planning (Control of
Advertisements) (Scotland) Regulations 1984 is set out in this document as a broad guide to
everyone resident and having a business in Perth and Kinross of the standards the Authority is
trying to achieve. 
Areas of Special Advertisement Control
3. The whole of the countryside in Perth and Kinross is an ‘Area of Special Control’ which, as the
name suggests, implies tight control on the erection of signs and general advertisements out
with built-up areas. Within built-up areas, different considerations apply but, again, there is a
need for restraint in the amount of advertising permissible. 
4. The countryside in Perth and Kinross is defined here as any area out with the settlement
boundaries outlined in the current Local Development Plan covering the area. For clarity, this
also includes plans prepared by National Parks Planning Authorities. The ‘Area of Special Control’
will change accordingly should settlement boundaries change. 
Advertisement Signs on Listed Buildings and within Conservation Areas
5. Within Conservation Areas and on Listed Buildings new advertisements must be properly related
to the architectural design of the buildings on which they are displayed. Particular attention will
be paid to the size of lettering, and dignified styles should be employed with illumination
restricted to the lettering only. 
5
Page 19 of 128

Page 20

2 
6. In Conservation Areas with a Regulation 11 Order, the deemed consents for advertisements
listed in Schedule 4 of the regulations may not apply. For clarification, please refer to PKC's
Interactive Heritage Map. 
Advance Warning Signs for Individual Premises
7. Advance signs will be permitted where, in the opinion of the Planning Authority, the display is
‘reasonably necessary’ for the transmission of information to the public, and where signs are not
detrimental to the interests of amenity or road safety. The signs should only contain
information, and the use of any general advertising will be discouraged. 
Official Directional Signs for Individual Premises
8. Official directional road signs (i.e. brown signs) will be considered by the Roads Authority in the
following instances: 
a) If the Council is required to provide its own directional signage to communities along major
roads;
b) If the official directional signs to the nearest town or village are inadequate to guide users to
an establishment;
c) If the signage relates to a tourist destination that has received an official letter of
accreditation from Visit Scotland. 
N.B. Hotels and restaurants are not regarded as tourist destination for the purposes of this
policy. 
Advertisements on Buildings
9. In determining applications for consent to display advertisements on buildings, the Planning
Authority will pay particular attention to design, dimensions, and position of the advertisement
together with its impact on the building. The Planning Authority will not permit advertisements
which would have a detrimental effect on the amenity and character of the street. In the
interests of amenity, and in order to avoid clutter, the numbers of advertisements should be
restricted to a minimum. In the case of signs erected within the curtilage of buildings, no more
than one double sided sign will be permitted at the junction of an access drive with the public
road. 
Illuminated Advertisements (including digital displays)
10. The impact of illuminated advertisements on amenity and public safety requires special
consideration, especially with the growing use of digital displays. When considering applications
for such signage the Planning Authority will refer to the most recent industry guidance on best
practice, further detailed in Appendix 3. 
Enforcement
11. In the case of unauthorised signs on private land, the Planning Authority will use its Planning
Enforcement Charter and will secure the removal of unacceptable signs through the powers
Page 20 of 128

Page 21

3 
contained in Regulations. Information on enforcement, including how to report a planning
breach, can be found on the Planning Enforcement webpage. 
12. Under Section 59 of the Roads (Scotland) Act 1984, it is an offence to place or deposit anything
in a road (including the footpath/pavement), so as to cause an obstruction, except with the
Roads Authority’s written consent. Unauthorised signage may be subject to removal by the
Roads Authority under their enforcement powers, including advertisements on A-boards, in line
with the Council’s A-Board Guidelines. 
Page 21 of 128

Page 22

4 
Detailed Guidelines for Advertisers
13. The detailed guidelines which follow have been produced to assist potential applicants. The
guidelines should be read in conjunction with Appendix 1 which lists those types of signs which
do not require advertisement consent. Applicants are encouraged to visit our Other Consents
and Permissions Application Checklist webpage for information on submission requirements or
refer to the pre-application service webpage if seeking advice on a proposal. 
Advance Warning Signs for Individual Premises
14. Location – Where the principle of an individual sign is accepted, the display should normally
comprise one double sided sign at the public/private road junction leading directly to the
premises advertised. A series of repetitive signs will be unacceptable. In cases where two or
more advance signs are justified at one road junction, the use of a composite sign will be
encouraged. All signs must be erected out with the roads boundary. 
15. Scale And Design – The overall size of individual advance signs will not normally exceed 1200
mm x 600 mm or be more than 1.5 m in height from ground level. The signs should contain only
explanatory information rather than general advertising. 
16. Illumination – Illumination will be permitted providing it can be done without prejudice to road
safety. 
Figure 1: Advance warning signs for individual premises
Page 22 of 128

Page 23

5 
Shops and Offices
17. Location – In general terms, advertisement of commercial premises should be restricted to the
fascia area of those premises having fascia displays. Only one projecting sign per commercial
frontage will generally be allowed. The lower edge of such a sign must be at least 2450 mm
above pavement level and must be set back at least 500 mm from the kerb. 
18. Large-scale displays on windows using posters or adhesive vinyls are discouraged in order to
retain an active frontage, preserve visual amenity and encourage vitality of the street. 
19. Generally, displays covering the windows of vacant premises may be acceptable where they
enhance the streetscape and are not considered to be advertisement clutter. 
20. Scale And Design – the size of any advertisement should be related to the scale and form of the
building on which it is displayed. The depth of any fascia should either be made to fit the space
designed for it or, where no such space exists, its depth should not exceed 700 mm or one half
of the vertical size between the top of the shop front and the sill of the first floor window,
whichever is the smaller. Lettering should generally be restricted to 300 mm unless on a large
scale building. Where lettering is applied directly to the face of the building without the use of a
fascia board, its height will be subject to the same conditions. 
21. Hand-painted fascias and hanging signs are encouraged. 
22. The display of large projecting signs and advertisements on gable walls, forecourt walls, roofs
and fences are generally discouraged.
Figure 2: Fascias
Page 23 of 128

Page 24

6 
Figure 4: Large projecting signs and advertisements on gable walls, forecourt walls, roofs and fences are discouraged.
23. Illumination – Preference will be given to signs with individually illuminated letters. In all cases
where illuminated signs are permitted, conditions will be attached to limit the luminance of the
display. Illuminated signs must not resemble or be erected in close proximity to official highway
or traffic lights. 
24. In Conservation Areas and on listed buildings full length illuminated box type fascia signs and
illuminated box type projecting signs are unlikely to be supported. 
25. When assessing an application for advertisement consent, all illuminated advertisements
(including digital displays) will be evaluated according to the technical guidance provided in
Appendix 3. 
Hotels, Public Houses and Restaurants
26. Location – Generally, a greater amount of display is appropriate due to dependence on passing
trade, although stricter control will be necessary where they relate to listed buildings or are
located in Conservation Areas. 
Figure 3: Hanging signs
Page 24 of 128

Page 25

7 
27. One projecting sign on each frontage is the preferred arrangement, with any additional signs
being wall mounted. Where the building is set back, consideration will be given to a free
standing sign. 
28. Scale And Design – Scale should be carefully related to that of the building and should not mask
architectural features. Encouragement will be given to the use of individual designed signs in
preference to standard ‘company’ signs. 
29. Illumination – Illumination of signs is acceptable for these types of uses. External illumination of
fascia, projecting or free standing pole mounted signs in preferable to internally illuminated box
signs. 
Garages and Petrol Filling Stations
30. Location – The appropriate levels of display would normally comprise
pole mounted illuminated totem style signage which may also display
price or special offers. If a site has a frontage to more than one road,
pole mounted signs may be permitted on more than one frontage. 
31. Scale And Design – Forecourts should be kept free from the
accumulation of advertising clutter through the rationalisation of
advertisements on display. In particular, the display of banner signs on
boundary fences or free standing structures is discouraged. 
32. Illumination – It is appropriate for the pole mounted sign, and the
company name and logo to be illuminated. Additional illumination,
particularly of the entire canopy fascia, is considered excessive and will
not be permitted. 
Industrial Buildings
33. Location – Advertisements identifying businesses or their products should generally be confined
to the walls of the building, although free standing signs may be allowed where there are large
yards or forecourts. 
34. Scale And Design – Generally, the scale of signs and lettering should not be excessive in relation
to the size of the building. 
35. Illumination – Illumination of advertisements may be appropriate for the identification of
individual properties within an industrial area, but should not be of a level which would cause
nuisance to neighbouring residential areas. 
Display Panels or Hoardings
36. Location – New hoardings should be confined to small gap sites in urban areas, particularly
those of a temporary nature, where it is proposed that a new building is to be erected. There will
Figure 5: Petrol station display
Page 25 of 128

Page 26

8 
be a presumption against new hoardings in rural areas, Conservation Areas, predominantly
residential areas, open areas within towns and villages and on or beside listed buildings. 
37. Scale And Design – The scale and design of a hoarding should be related to the size and layout of
the site. Where a gap site is involved a generous landscaping treatment should be incorporated.
If free standing, it should be integrated into the framework of a wall, fence or purpose designed
structure. 
38. Illumination – In areas where hoardings may be allowed, there will normally be adequate levels
of street lighting. If additional external illumination is considered appropriate the light source
should be screened from any public area. Applications for digital hoardings will be evaluated
according to the technical guidance on illuminated advertisements provided in Appendix 3. 
Bunting/Flags etc.
39. Banners, bunting and commercial flags bearing sponsors names etc. are considered
inappropriate for permanent display. 
Flyposting (including Portable Signs)
40. Any flyposting within the Road boundary is illegal and any instances will be reported the
Council’s Roads Authority for immediate action. In other cases of flyposting on private property
or buildings the practice will be discouraged by use of the Planning Authority’s powers of
enforcement.
Concluding Remarks
41. Whilst this is an advice note, the Planning Authority strongly recommend that note is taken as
Officers will use this as a guide to deem what is reasonable and ensure that in P&K the right
balance is struck allowing advertising while ensuring no clutter or proliferation of adverts. As it is
an advice note, there is scope for interpretation with a thought through design. 
Page 26 of 128

Page 27

9 
Appendix 1: Advertisements for which Consent is not
Required under The Town and Country Planning (Control of
Advertisements) (Scotland) Regulations 1984, as Amended 
42. The classes of advertisements displayed with deemed consent presented below are specified in
Schedule 4 of the Town and Country Planning (Control of Advertisements) (Scotland) Regulations
1984, as amended. Deemed consent is subject to conditions specified in Schedule 4 which
should be referred to for further detail on each class. 
43. It is important to note that not all deemed consents apply where a Regulation 11 Order has been
issued. This is relevant to most Conservations Areas. For more information, please refer to PKC's
Interactive Heritage Map. 
Class 1 – Functional Advertisements
44. Advertisements relating to the functions of local authorities, community councils, statutory
undertakers and public transport undertakers, which are reasonably required. Advertisements
erected by a Planning Authority on land within their area. 
Figure 6: Functional advertisements
Page 27 of 128

Page 28

10 
Class 2 – Advertisements relating to Land on which
Displayed
45. (a) For the purpose of identification, direction or warning. 
46. (b) Relating to any person, partnership or company
carrying on a profession, business or trade at the premises.
Limited to one advertisement per person etc. or two if
entrances on different roads. 
47. (c) Relating to any institution of a religious, cultural,
educational, recreational or medical character, or to any
hotel, public house, block of flats, club or boarding house.
Limited to one advertisement, or two if entrances on
different roads.
Class 3 – Certain Temporary Advertisements
48. Referring to the sale or letting of land or buildings (single
board – 2 sq metres or in the case of joined boards
together 2.3 sq metres). Sale of goods or livestock not on a
regular basis (1.2 sq metres maximum). Building works (2 sq
metres maximum). Announcement of local event (0.6 sq metres maximum). Demonstration of
agricultural methods (display not to exceed 1.2 sq metres and no individual advertisement to
exceed 0.4 sq metres). Advertisements on hoarding enclosing land where building operations
are taking place which is designated in a Development Plan for commercial, industrial or
business purposes and is not in a Conservation Area or an Area of Special Advertisement Control
must be between 1.5 and 3.1 metres in height and between 1.0 and 6.1 metres in length. 
Figure 7: Advertisements relating to land
on which displayed
Figure 8: Certain temporary advertisements
a
b
c
Page 28 of 128

Page 29

11 
Class 4 – Advertisements on Business Premises
49. Advertisement displayed on business premises related to activity carried on, goods sold or
service provided. There are limitations on the area of advertisement, height of letters, and
height above ground level. In the case of shops the wall must contain a display window.
50. Advertisements displayed within forecourts of business premises are limited to an aggregate
area of 4.5 sq metres on each frontage.
Figure 9: Advertisements on business premises
Figure 10: Advertisements on business premises forecourt
Page 29 of 128

Page 30

12 
Class 5 – Advertisements Within Buildings
51. Advertisements displayed within any building where
no one advertisement exceeds 250 sq cm in area,
and where any group of adverts does not total more
than one tenth area of door or window where
displayed. Illuminated advertisements must not
incorporate any moving feature or animation. For
clarification, this applies to advertisements which
are within a distance of one metre from any external
door, window, or other opening through which the
advertisement is visible from outside the building. 
Class 6 – Illuminated Advertisements
52. Individually illuminated letters limited to one
advertisement fixed to the face of the building and
not projecting more than 0.25 metres. The
advertisement must not incorporate a moving feature or be illuminated intermittently.
Minimum height of lowest part of advertisement 2.5 metres and maximum height 4.6 metres
from ground level. There is no change in Conservation Area or Area of Special Advertisement
Control. 
Figure 12: Illuminated advertisements
53. In the case of Classes 2, 3, 4, 5 and 6 advertisements the maximum height of letters is 0.75
metre and 0.3 metre in an Area of Special Advertisement Control. Maximum height above
ground level of highest part of advertisement is 4.6 metres and in an Area of Special
Advertisement Control 3.6 metres unless otherwise stated. It is important to remember that all
advertisements in Classes 1-6 must not obscure any road traffic signs or render hazardous the
use of any road, railway, waterway or airfield.
Figure 11: Advertisements within buildings
Page 30 of 128

Page 31

13 
Class 7 – Advertisements on ground based housing for electronic communications
apparatus
54. Advertisements displayed on ground based housing for electronic communications apparatus
required to be attached to that housing by virtue of Articles 8 and 9 of Commission Regulation
(EC) No 1828/2006 setting out rules for the implementation of Council Regulation (EC) No
1083/2006 laying down general provisions on the European Regional Development Fund, the
European Social Fund and the Cohesion Fund and of Regulation (EC) No 1080/2006 of the
European Parliament and of the Council on the European Regional Development Fund.
Regulation 12: Election Notices, Statutory Advertisements, Traffic Signs 
Figure 13: Election notices, statutory advertisements, traffic signs
55. Advertisements are granted deemed consent if they (a) relate to pending elections, (b) are
statutory notices required by legislation or parliamentary procedure, or (c) are authorised traffic
signs for safety and guidance. These must meet the following conditions: (a) election-related
adverts must be removed within 14 days after polling; (b) temporary statutory or traffic-related
advertisements must be removed promptly authorised period ends, or within a reasonable time
if no period is specified; (c) statutory notices must comply with applicable limits on size, number,
and height in relation to the display of advertisements of that class, and must not exceed what is
necessary to fulfil their intended purpose. 
Miscellaneous Advertisements Exempt from Regulations
56. (a) Advertisements not readily visible from outside the curtilage; (b) within buildings; (c) on a
vehicle (primarily employed as a moving vehicle but not when used primarily for the display of
advertisements); (d) forming part of the fabric of a building; (e) & (f) advertisements on balloons
flown at a height exceeding 60 metres or on a captive balloon advertising the premises to which
it is tethered, limited to ten days in any year providing it is not in a Conservation Area or an Area
of Special Advertisement Control, finally; (g) advertisements displayed on an article for sale or on
a pump from which liquid or gas is sold provided it is not illuminated and does not exceed 0.1 sq
metres in area.
Page 31 of 128

Page 32

14 
Figure 14: Miscellaneous advertisements exempt from regulations  
Page 32 of 128

Page 33

15 
Appendix 2: Standard Conditions
57. Standard conditions are imposed in relation to all consents for the display of advertisements as
set out below: 
1) All advertisements displayed and any land used for the display of advertisements shall be
maintained in clean and tidy condition to reasonable satisfaction of the Local Planning
Authority.
2) Any hoarding or similar structure or any sign, placard, board or device erected or used
principally for the purpose of displaying advertisements shall be maintained in a safe
condition to the reasonable satisfaction of the Local Planning Authority.
3) Where any advertisement is required under the regulations to be removed, the removal
thereof shall be carried out to the reasonable satisfaction of the Local Planning Authority.
4) Before an advertisement is displayed on land the permission of the owner of that land or
other person entitled to grant permission shall be obtained. 
58. Where an advertisement has deemed consent the following standard condition also applies: 
5) Advertisements shall not be sited or displayed so as to obscure, or hinder the ready
interpretation of, any road traffic sign, railway signal or aid to navigation by water or air, or
so as to otherwise render hazardous the use of any road, railway, waterway (including any
coastal waters) or airfield. 
Page 33 of 128

Page 34

16 
Appendix 3: Technical Guidance on Illuminated
Advertisements (including digital displays)
59. Illuminated advertisements are required to meet the conditions specified in Schedule 4 of the
Town and Country Planning (Control of Advertisements) (Scotland) Regulations 1984 to be
eligible for deemed consent. In all cases, the guidance detailed below will apply. 
60. The technical guidance that follows was taken from the Professional Lighting Guide 05/23
(PLG05/23) “The Brightness of Illuminated Advertisements Including Digital Displays” (2023)
published by the Institution of Lighting Professionals. We shall apply new standards where these
are brought forward and update this guidance accordingly. 
61. In accordance with the Institute of Lighting Professionals recommendations in PLG05/23,
advertisements will be illuminated only in a manner as reasonably required to fulfil the purpose
of the advertisement within the appropriate zoning. The PLG05/23 considers five lighting
environmental zones described in the table below:
Table 1: Lighting environmental zones
Zone Surrounding Lighting
Environment
Examples
E0 Protected Dark Astronomical Observable dark skies, UNESCO
starlight reserves, IDA dark sky places
E1 Natural Dark Relatively uninhabited rural areas, National
Parks, Areas of Outstanding Natural Beauty,
IDA buffer zones etc.
E2 Rural Low district
brightness
Sparsely inhabited rural areas, village or
relatively dark outer suburban locations
E3 Suburban Medium
district
brightness
Well inhabited rural and urban settlements,
small town centres or suburban locations
E4 Urban High district
brightness
Town and city centres and other commercial
areas with high levels of night-time activity  
62. The PLG05/23 summarises the latest research on effects of colourful dynamic lighting (including
digital displays) on the day and night-time environment. The maximum levels of display
luminance will not exceed the thresholds specified in PLG05/23, shown in the tables below: 
Page 34 of 128

Page 35

17 
Table 2: Recommended maximum night-time permitted values of display luminance
Light Technical Parameter Maximum sign luminance (L,) cd / m2
Environmental zones
Sign surface area E0 E1 E2 E3 E4
0 to < 5 m2 0 25 200 300 300
5 to < 20 m2 0 0 200 300 300
≥ 20 m2 0 0 100 200 300  
63. Illuminated displays are generally required to be switched off between midnight and 05:00
unless it is agreed with the planning authority that the installation is required to be operational
at this time, in which case the display luminance shall be 50% of the figure in Table 2. 
64. During daytime, the permitted value of display luminance is increased due to higher levels of
background ambient lighting, shown below:
Table 3: Recommended maximum daytime permitted values of sign luminance
Daylight ambient Illuminance (Eh)
[lux]
Sign Luminance
[cd/m2]
Up to 3,500 ≤ 400
3,501 to 8,500 (overcast day) ≤ 1,000
8,501 to 15,000 (bright day with cloud
cover)
≤ 2,500
15,001 to 25,000 (bright sunny day) ≤ 3,500
25,001 to 42,000 (direct sunlight) ≤ 5,000
42,001 and above > 5,000 
Page 35 of 128

Page 36

18 
65. Given the variations in daylight ambient lighting conditions, digital displays shall have a control
device or other appropriate technology to ensure luminance is controlled in response to ambient
light levels, as per the values in the table above.
Image Rate of Change 
66. Illuminated advertisements, including digital displays, are categorized into four classifications as
outlined in Table 4. When positioned in proximity to the road network, particularly at junctions,
this type of advertisement will be carefully considered, as dynamic or variable displays may pose
a distraction to drivers.
Table 4: Image rate of change categories for illuminated advertisements including digital displays
Category Description Example
F1 Static non-changing displays Unchanging display, traditional billboard, paper display in
bus shelter, displays of fuel prices.
F2 Static displays that change
sequentially
Digital displays, large and small format, showing static
advertisements that change sequentially, road
maintenance signage.
F3 Variable displays / partial motion Pharmaceutical cross, stroboscope light.
F4 Dynamic full motion displays Video / movie advertising display, or live transmission. 
Standard Conditions for Illuminated Advertisements, including Digital Displays 
67. In addition to the luminance controls discussed above, the PLG05/23 recommends the following
conditions also apply to illuminated advertisements, including digital displays, that consist of
changing images:
• There shall be no moving images, animation, intermittent or full motion video images, audio,
directional symbols, or any images that resemble road signs or traffic signals, unless consent
has been granted.
• Static images shall not change more frequently than every 10 seconds, unless approved to
do so by the planning authority.
• Where multiple displays appear together, then the rate of change in each display shall be co-
ordinated and consistent. Where such displays appear as a line together, then the
transitions for each display shall be set such that they change all at once, but do not change
in sequence along the road.
• The advertisement shall at all times contain a feature that will turn the display off (showing a
black/blank screen) in the event of malfunction or error.
Page 36 of 128

Page 37

19 
Useful Links
• Adopted Local Development Plan (LDP2) - Perth & Kinross Council
• Cairngorms National Park - Local Development Plan
• Interactive heritage map - Perth & Kinross Council
• Planning enforcement - Perth & Kinross Council
• Other Consents and Permissions Application Checklist
• Pre-application services - Perth & Kinross Council
• A-Board Guidelines
Page 37 of 128

Page 38

Page 38 of 128

Page 39

Advertisement Control Planning Guidance Consultation Report 
Is the layout and information in the Draft Advertisement Control Guidance (2025) clear? 
Comment Summary Received
From
PKC Officer Response Changes to be Made to
Guidance
Respondents welcome the guidance and support
efforts to control advertising. 
Public We welcome the positive feedback. No change.
Stricter enforcement of the guidance is required.
Specific locations mentioned are Perth City Centre,
Pitlochry and Conservation Areas. Issues of poor-
quality, plastic signage in conservation areas and
flyposting of big posters were raised.
Public The guidance addresses both signage within
conservation areas (para. 5) and flyposting (para. 39). 
Information on enforcement, including how to report a
planning breach, can be found Planning Enforcement
webpage.
Paragraph 11 expanded to
include link to PKC’s Planning
Enforcement webpage. 
Request for PKC to provide pre-application advice
on proposals for sign construction and placement.
Public The guidance includes detailed guidelines for
applicants and Appendix 1 provides clarification on
deemed consents. 
Applicants are encouraged to visit our Other Consents
and Permissions Application Checklist webpage for
information on submission requirements or refer to the
Paragraph 13 expanded to
include link to application
checklist and pre-application
service. 
5
Page 39 of 128

Page 40

pre-application service webpage if seeking advice on a
proposal.
States there is no avenue for appeal if a sign is
deemed unacceptable by the planning authority.
Public You have the right to make an advertisement consent
appeal to Scottish Ministers. Please refer to the
following link for further information - Advertisement
consent appeals. 
No change. Information on the
right to appeal is provided when
a Decision Notice is issued.
Guidance should address the use of A-Boards, as
this is a growing issue in certain communities (e.g.
Pitlochry).
Public Under Section 59 of the Roads (Scotland) Act 1984, it is
an offence to place or deposit anything in a road
(including the footpath/pavement), so as to cause an
obstruction, except with the Roads Authority’s written
consent. Unauthorised signage may be subject to
removal by the Roads Authority under their
enforcement powers, including advertisements on A-
boards, in line with the Council’s A-Board Guidelines.
Paragraph 12 expanded to
reference the Road Authority’s
A-Board Guidelines. 
Guidance should limit the number and location of
poles supporting brown tourist signs. These can
look cluttered and impact visual amenity (e.g. Atholl
Road, Pitlochry).
Public The display of brown tourist signs falls under the
responsibility of the Roads Authority, and any related
issues should be reported directly to them. The
guidelines promote the use of composite signs where
multiple signs are required.
No change.
Guidance should be strengthened on electioneering
signage. In particular, the issue of large political
displays on private land along roads (e.g. A9) should
be addressed with clarification around enforceable
restrictions.
Public Regulation 12 states notices relating to pending
elections are granted deemed consent. The only
condition specified is for the notice to be removed
within 14 days after polling. 
Information on enforcement, including how to report a
planning breach, can be found Planning Enforcement
webpage.
Paragraph 55 inserted to provide
further information on
Regulation 12 and clarify Figure
13.
Guidance should address illuminated displays near
traffic lights.
Public When positioned in proximity to the road network,
particularly at junctions, this type of advertisement will
Paragraph 66 included to
address proximity of illuminated
displays near roadways.
Page 40 of 128

Page 41

be carefully considered, as dynamic or variable
displays may pose a distraction to drivers.
Guidance should address signage for seasonal
attractions and provide definitions for “permanent”
and “temporary” advertisements.
Public These cases are assessed on a case-by-case basis
when an application is received, or a planning breach
has been reported.
No change
Guidance should address signage at road junctions.
In particular, the issue of directional signage being
placed after lanes have been divided was raised.
Public Paragraph 13 states the display of advance warning
signs for individual premises should be located at the
public/private road junction leading directly to the
premises advertised. 
No change.
Guidance should address maintenance of
advertisement displays, including cleanliness and
overgrown vegetation obscuring signs. This should
reference obligations for both PKC and private
advertisers.
Public Appendix 2: Standard Conditions specifies that all
advertisements displayed and any land used for the
display of advertisements shall be maintained in clean
and tidy condition to reasonable satisfaction of the
Planning Authority.
No change.
Guidance should address placement of poles
containing signage on pavements. Respondent
raises concerns around these obstructing narrow
pavements for wheelchairs and prams (e.g.
northeast and northwest corners of West Moulin
Road and Atholl Road in Pitlochry).
Public Under Section 59 of the Roads (Scotland) Act 1984, it is
an offence to place or deposit anything in a road
(including the footpath/pavement), so as to cause an
obstruction, except with the Roads Authority’s written
consent. Pavement obstructions should be reported to
the Roads Authority.
Paragraph 12 expanded to
reference Section 59 of the
Roads (Scotland) Act.
Guidance should enable rural businesses (e.g.
village shops, post officers, etc) to display roadside
advertisement at approaches to villages so that, like
hotels, pubs and restaurants, they can benefit from
passing traffic. Council policies should support rural
business to prevent the loss of these local hubs.
Public The guidance provides a framework for the planning
authority to maintain an appropriate balance of
freedom for advertisers and protecting visual amenity
and public safety. 
Paragraph 7 states advance warning signs for individual
premises will be permitted when the display is
reasonably necessary for the transmission of
information to the public, and where signs are not
detrimental to the interests of amenity or road safety.
No change
Page 41 of 128

Page 42

The guidance lacks visual examples of acceptable
or unacceptable in terms of scale or design.
Public The guidance contains diagrams exemplifying
acceptable scale and design. These provide advertisers
a framework within which there is scope to suit site-
specific context. 
No change.
Suggestion for diagrams to be redrawn to make
figures clearer and easier to read.
Public Noted. Diagrams were sourced from the existing
guidance and may be updated in the final document
subject to resource availability.
Final version to have updated
diagrams.
Suggestion for document to be reformatted to clarify
which text and diagrams are associated. 
Public Noted. Document layout will be updated in the final
version of the guidance.
Final version to have updated
layout.
Respondent asks why there is a difference in
allowable sizes for signs outside the illustrated
joiners and hotel in Figure 7.
Public The varying sizes shown in Figure 7 correspond with the
different types of advertisement listed a-c included
under Class 2.
Figure 7 updated to include
reference to relevant text.
Respondent asks why it states that petrol stations
"may" display prices and not "must".
Public There is currently no legal requirement for petrol
stations to display fuel prices.
No change. 
Page 42 of 128

Page 43

If you or someone you know would like a copy of this
document in another language or format, (on occasion, only
a summary of the document will be provided in translation),
this can be arranged by contacting the 
Customer Service Centre on 01738 475000.
You can also send us a text message on 07824 498145.
All Council Services can offer a telephone translation facility.
www.pkc.gov.uk (PKC Design Team - 2017747)
Guidelines
for A-Boards
and other
advertising
structures
on
footpaths.
Keep Clear
and Remove
Obstacles!
A-Boards are used as promotion by businesses
throughout the Council area.  Over the years
the number and size of A-Boards used by
businesses on footpaths and pavements has
increased, and this growth has been brought to
the Council’s attention by local communities.
We recognise that they are an important way for
businesses to communicate with shoppers and
visitors.  However they, and similar structures,
can cause access problems for pedestrians,
particularly people who have a visual impairment,
wheelchair users and people with pushchairs. 
A-Boards can also affect road safety and visibility
if inappropriately used.
It is important therefore that the number, size and
positioning of A-Boards is controlled so they do
not cause difficulty for pedestrians.  We want
to work with businesses and local communities
to achieve a sensible and practical approach
to their use.  In introducing these guidelines,
we expect to improve access for pedestrians
by reducing the number of areas where the
amount of A-Boards has an adverse impact on
free movement for both able-bodied people and
those with a disability.
This scheme has the support of the Centre for
Inclusive Living Perth & Kinross (CILPK).  Both
the Council and CILPK will be pleased to discuss
with businesses any proposals for A-Boards or
provide advice/clarification on suitable locations:
Centre for Inclusive Living Perth & Kinross
90 Tay Street, PERTH, PH2 8NP
Email info@cilpk.org.uk
Perth & Kinross Council
Pullar House, 35 Kinnoull Street, PERTH,
PH1 5GD
Tel 01738 475000
Details correct at time
of going to press March
2018.  These guidelines
may be modified at any
time by Perth & Kinross
Council.
5
Page 43 of 128

Page 44

•  No sign shall be placed on a street corner
and/or obstruct driver/pedestrian visibility or
access to buses etc.
•  Each sign must be removed outwith trading
hours.
•  Anyone who places a sign on the public 
footway should also be aware that any
liability arising from an accident involving an
A-Board remains with the board’s owner.
It is not only A-boards that are an issue -
there are also other display items which
are inconsistently placed, along with waste
containers.
8
Why do we need
these guidelines?
8
84
Under Section 59 of the Roads (Scotland) Act
1984, it is an offence to place or deposit anything
in a road (including the footpath/pavement),
so as to cause an obstruction, except with the
Roads Authority’s written consent.
As a Council we do not wish to impose a blanket
ban on the use of A-Boards, in recognition
of the importance of promotion for local
businesses.  However, due to their excessive
use, it has now become necessary to issue the
following guidelines for acceptable placement of
advertising signs:
• The sign consists of a simple A-Board of
modest size (maximum dimensions 1.0m by
0.5m).
•  The sign must be located within the
frontage of the premises to which it relates,
with one edge of the frame against that
frontage (except in the pedestrianised
zone of Perth City Centre, where it should
be located in line with existing permanent
street furniture).
•  There must only be one sign per premises,
located in a regular position.
•  No part of the sign shall be closer than
1.2 metres to the kerb or other piece of
street furniture, and shall not be physically
attached to any piece of street furniture.
The temporary and mobile nature of these boards
means that blind and partially sighted people
cannot learn where they are, so struggle to avoid
walking into them.
It is the Council’s intention to
enforce these guidelines with
immediate effect.  We would
welcome your full co-operation,
in the interests of public safety
and physical amenity.
Failure to comply with the
above guidelines or with any
reasonable request from a
Council officer regarding a sign
will result in it being uplifted,
and it will not be returned.
Page 44 of 128

Page 45

Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality 
___________________________________________________________________  
Committee or Board:  Economy and Infrastructure Committee 
Date of Meeting:  27 August 2025 
Report Title:  Council Support to Businesses 
Report Number:  25/211 
Report Author:  Steve MacDonald, Economic Development Manager
(Business, Place and Investment) 
Organisational Lead:  Serge Merone, Strategic Lead – Economy,
Development and Planning 
___________________________________________________________________ 
1. Purpose 
1.1 The purpose of this report is to provide a series of actions and
recommendations which enhance interactions between the Council and
businesses. They aim to build on and improve our business-friendly approach
and create a supportive environment with our partners to improve our strong
business start-up and growth performance. 
1.2 Sections 
1. Purpose
2. Recommendations
3. Background/Context
4. Main Issues
5. Proposals
6. Conclusion
7. Impact and Value Assessment
8. Appendices 
2. Recommendations 
2.1 It is recommended that the Committee considers and comments on the
contents of the report. 
2.2 It is recommended that the Committee approves the following
recommendations as set out in the proposals: 
(i) it is recommended that a ‘Business-friendly’ Cross-Service Officer
Group is established chaired by the Strategic Lead (Economy,
Development and Planning).
6
Page 45 of 128

Page 46

(ii) it is recommended that the Council review its interactions with the Local
Employability Partnership (LEP) to improve employability support
services including impact tracking and continue to facilitate synergies
between LEP and Perth and Kinross Economic Partnership.
(iii) it is recommended that the Business, Place and Investment team
carries out a full review of the Business Gateway contract arrangements
with a full delivery options appraisal and report back to the Economy and
Infrastructure Committee in August 2026.
(iv) it is recommended that an update on the Commercial Property
Investment Programme (CPIP) is provided to the Economy and
Infrastructure Committee in Spring 2026. 
3. Background/Context 
3.1 At its meeting on 5 February 2025, the Economy and Infrastructure
Committee noted the ‘Scotland National Strategy for Economic
Transformation’, ‘Tay Cities Prospectus for Regional Growth (2025-2035)’ and
endorsed the ‘Perth and Kinross Economic Action Plan (2025-2030)’.  These
provide national, regional and local context and direction for economic growth. 
3.2 The Action Plan sets out the approach the Perth and Kinross Economic
Partnership will take over the next five years (2025-2030) to grow a stronger,
greener, fairer and more sustainable economy for Perth and Kinross. The
Action Plan was developed using strong evidence base and through
engagement with partners as well as public consultation. 
3.3 The key objectives of the plan include: 
• Supporting our local businesses to grow, attract jobs and investment.
• Tackling inequalities.
• Supporting the transition to net zero. 
3.4 Ensuring that we have the right business support offering in Perth and
Kinross, through both our contracted programmes and general interactions, is
one of the key actions and critical to achieve our objectives. 
3.5 Perth and Kinross has 6,630 private sector registered businesses, employing
57,430 people. We experienced a net increase of 55 registered businesses in
2024 indicating good start-ups trend and are ranked 10th out of 32 local
authority areas in Scotland. 
3.6 The largest number of registered businesses in Perth and Kinross are Small
and Medium Sized Enterprises (SME’s). Overall, SME’s employed 33,330
people in 2024. Of these, 6,105 registered businesses employ less than 50
people (23,370 employed); 195 businesses employ between 50-249 people
(7,960 people employed).  The remaining 24,100 people were employed in
330 businesses that employ 250 plus people. 
3.7 It is important to recognise that Perth and Kinross has a relatively diverse
economy with no one sector dominating. 
Page 46 of 128

Page 47

3.8 The 5-year survival rate of 49.5% (2017-2022) for businesses in Perth and
Kinross has been a long-term strength and is the third highest in Scotland. 
3.9 Perth and Kinross was recently rated the highest in the UK for the number of
businesses likely to grow by 20% or more over the next year (Growth Flag
Annual Report 2025), highlighting our strong growth potential. 
3.10 Overall, Perth and Kinross business economic performance is strong. By
building on and improving our business-friendly approach and creating a
supportive environment with our partners we can further improve the number
of start-ups and growth businesses in our region. 
3.11 Several enhancements were identified by the Scrutiny and Performance
Committee in the ‘Review of Interactions between Businesses and the Council
including Business Support activities’ report approved on 23 April 2025
(Report 25/92).  This report recognises these and provides recommendations
for improvement. 
4. Main Issues 
4.1 There are multiple interactions between the Council and businesses. The
diagram below provides some examples of these. It is important to note that
business support activities represent only a small proportion of the
interactions between businesses and the Council. Several of the other areas
are operational and linked to specific services. 
Page 47 of 128

Page 48

5. Proposals 
5.1 ‘Business-friendly’ Cross-Service Officer Group 
5.1.1 As previously mentioned, the Councils activities cut across several services
which provide information, guidance and support to businesses. 
5.1.2 There is a need to create a mechanism to respond to any emergency issues
and identify areas of improvement to strengthen our business-friendly
approach. 
5.1.3 To support this, it is proposed to establish a ‘Business-friendly’ Cross-Service
Officer Group, chaired by the Strategy Lead (Economy, Development and
Planning). The group will include officers who interface with businesses with a
flexible and agile membership to focus on the Council priorities and business
needs. The group could also be mobilised to deal with emergencies. They will
liaise with other established business-related groups such as the Climate
Change Business and Industry Group to avoid duplication and maximise
synergies. Regular update briefings will be produced when needed, and an
annual update will be provided to this committee.   
5.2 Business Intelligence and Customer Relationship Management (CRM)
System 
5.2.1 In January 2025, the Business, Place and Investment Team launched a
bespoke Customer Relationship Management (CRM) system – produced by
Bank Search – as a business engagement management tool. The CRM
allows the team to effectively track all interactions with businesses, focussing
on key growth companies. The Top 100 growth companies are identified using
several measures which helps the team manage interactions with businesses.
This includes significant turnover or employment, and direct support to those
with key growth potential, including the creation of jobs. 
5.2.2 We will continue to develop our CRM system and maximise integration
opportunities with the Master Customer Record (MCR) developed by the
Business Support Partnership at national level as part of our business support
services (see section 5.8.4 below). 
5.3 Business Lead Officer 
5.3.1 The Business, Place and Investment Team has overall responsibility for
business engagement. 
5.3.2 In addition to the ‘Business-friendly’ Cross-Service Officer Group, individual
members of the Business, Place and Investment team will act as a ‘Business
Lead Officer’ for each of those companies identified in our Top 100 and
growth businesses list. This will include being a key point of contact and
liaising with other services as well as supporting Elected Members, Executive
Leadership Team and Strategic Leads in their interactions with businesses
through briefings, meetings or site visits. This would also be in place for
inward investment enquiries of scale, assessed and determined by the Lead
Page 48 of 128

Page 49

Officer. These interactions are essential to understand individual business
needs and priorities and how the Council can respond effectively. 
5.4 Business Promotion and Support (Invest in Perth) 
5.4.1 The Business, Place and Investment Team has overall responsibility for
business promotion and support. The team is working closely with local and
national partners such as the Scottish Cities Alliance (SCA) to promote
investment opportunities. 
5.4.2 The team leads business and investment promotion via Invest in Perth brand
and digital platforms. This includes: 
- Investment Prospectus – highlighting key opportunities (Appendix 1).  The
£530 million investment prospectus was launched at the UK’s Real Estate
Investment and Infrastructure Forum in April 2025, in partnership with the
Scottish Cities Alliance.
- Inward Investment and Land Opportunities – including Perth Eco-
Innovation Park at Perth West / Northfield Business Park / other land and
property enquiries (including working with private sector agents).
- Management of grant and investment programmes, including Green
Capital Development, Beyond Scotland Market Development, Adapt Your
Property and Angel Share.  
- Our monthly Business and Economy Bulletin and Invest in Perth social
media are key communication channels between the Council and
businesses.  This could be further developed through bespoke meetings
or visits by Elected Members, Executive Leadership team or Strategic
Leads supported by Business Lead Officers as described above in the
report. 
5.4.3 Outcomes from the grant programmes will be reported back annually to the
Economy and Infrastructure Committee and through regular briefing notes
including impact tracking and long-term sustainability. 
5.4.4 Bespoke promotional opportunities will continue to be identified which
showcase individual businesses successes and achievements. 
5.5 Business networks 
5.5.1 In addition to direct engagement with individual business, the Council is also
engaging with several business networks. These include Perthshire Chamber
of Commerce, Federation of Small Businesses, Perth and Kinross Business
Partnership, sector-specific networks (Perth and Kinross Tourism Partnership)
or roundtable discussions such as the one organised in January 2025 with the
agricultural sector.  These interactions are essential to understand collective
business needs and priorities and how the Council can respond. 
5.5.2 In addition to individual interactions with each business network, it is
beneficial to bring business networks together to understand collective
business needs and priorities.  Perthshire Chamber of Commerce, Federation
of Small Businesses, Perth and Kinross Business Partnership and Perth and
Kinross Tourism Partnership are all members of Perth and Kinross Economic
Page 49 of 128

Page 50

Partnership.  They have co-developed Perth and Kinross Economic Action
Plan which aligns business needs and priorities to our shared economic
objectives. 
5.5.3 The Council will continue to support the Perth and Kinross Economic
Partnership as a strategic engagement platform with business networks and
collectively with the whole business community in Perth and Kinross.  One
possible action that the Partnership would explore as part of its
communication and marketing plan is the organisation of an annual business
and economic summit or conference. This event could be complemented by a
series of smaller events for business leaders or sector-specific roundtable
discussions. 
5.6 Skills and Employability Support Services 
5.6.1 One key area of engagement with businesses and business networks are the
alignment of skills with economic needs. The Perth and Kinross Economic
Partnership leads on this when the Perth and Kinross Local Employability
Partnership (LEP) leads on employability support activities. The Perth and
Kinross Local Employability Strategy and Action Plan provides a framework
for providing employment support bringing economically inactive and
unemployed people back to the job market. Business engagement is essential
to both. The Council, through its skills and employment support, engage with
and support businesses in several ways, including recruitment assistance,
skills support, financial assistance and incentives. 
5.6.2 It is proposed that the Council review its interactions with the LEP to improve
employability support services including impact tracking and continue to
facilitate synergies between LEP and Perth and Kinross Economic
Partnership. This could be done in close liaison with UHI Perth which is a
member of both partnerships and has a key role to play in this area. 
5.7 Business Support Non-Departmental Public Bodies 
5.7.1 The Council is interacting with business support Non-Departmental Public
Bodies, namely Scottish Enterprise (including Scottish Development
International), Skills Development Scotland and Visit Scotland. The Council
has regular meetings with each to deliver on local and national priorities as
well as supporting business individually or collectively.  All are members of the
Perth and Kinross Economic Partnership and/or LEP. 
5.7.2 We will continue to strengthen our interactions with them individually and
develop synergies collectively through the Perth and Kinross Economic
Partnership and LEP to maximise impact of business support. 
5.8 Business Support Services 
5.8.1 Business support services provided by the Council sit within the context of a
variety of organisations involved in business support in Scotland, co-ordinated
through the national Business Support Partnership. 
Page 50 of 128

Page 51

5.8.2 Almost all the organisations work at a national level, with local delivery
delegated to regions and local authority areas, principally through the
Business Gateway contract. 
5.8.3 One of the challenges of co-ordinating business support across Scotland is
that each agency uses different Customer Relationship Management (CRM)
systems to record interactions with businesses.  This can result in duplication
and inefficiency. 
5.8.4 The Business Support Partnership has started work on a Master Customer
Record (MCR) for all of Scotland. This will deliver efficiencies and help to
inform and target support better. 
5.8.5 We will continue to support the creation of MCR and contribute towards its
development while maximising integration opportunities with our own CRM
system.  This will be led by the Business, Place and Investment Team. 
5.8.6 The Council, as part of the wider Tay Cities Region, commissions Elevator to
deliver the Business Gateway contract on our behalf.  This is covered by a
Service Level Agreement as part of a nationally funded contract managed by
Dundee City Council. The total award is £1,512,666 across the Tay Cities
Region. Funding is distributed at a regional level across Scotland, based on
population. The contract covered the period April 2023 to March 2025 with the
option to extend for up to three additional single years until March 2028.  The
contract is in its first additional year (25/26). 
5.8.7 Business Gateway has 12 staff across Tayside with a team of 5 focussing on
Perth and Kinross located at the Creative Exchange. The Business Gateway
team works closely with the Business, Place and Investment Team to co-
ordinate individual or collective business support activities. 
5.8.8 Performance is monitored by the Business, Place and Investment team
through quarterly meetings and has remained strong throughout the contract. 
Targets against both business start-ups and growth were achieved in 2024-25
and remain on track for 2025-26.  A Business Gateway Board meets
quarterly, providing strategic direction and ensuring delivery against set
targets.  The Convener of the Enterprise and Infrastructure Committee, or an
alternate, attend the Board on behalf of the Council. 
5.8.9 Whilst performance is strong, we should continue to review performance,
value for money and how the support aligns and contributes to our growth
aspirations at a local level, including alignment with key sectors.  At the last
meeting on 31 May 2025, the Board discussed a process to review the
contract arrangements for further extension. The process would start in
October with the Board considering one additional year extension in
November and the contractor informed in January. This would run from April
26 – March 27. 
5.8.10 It is proposed that the Business, Place and Investment Team will carry out a
full review of the Business Gateway contract arrangements with a full delivery
options appraisal and report back to the Economy and Infrastructure
Committee in August 2026. The agreed delivery options could then be in
Page 51 of 128

Page 52

place from April 2027 (for third extension year) or from April 2028 (outwith
existing contract) if agreed. 
5.8.11 The Council financially supports GrowBiz to deliver business support services
in rural Perth and Kinross via a team of self-employed Enterprise Facilitators. 
GrowBiz also has an accredited mentoring programme which trains volunteer
mentors, runs peer-to-peer and training events and specialised groups via
Perthshire Artisans. 
5.8.12 The Council is providing £140k to deliver outputs and outputs agreed through
a Service Level Agreement (SLA) monitored by the Business, Place and
Investment Team. Key areas include: 
- 1-2-1 business support
- Learning and networking sessions
- Social enterprise support and development
- Specialist creative sector support
- Specialist care and wellbeing sector support
- Young entrepreneurship
- Net zero awareness and learning. 
5.8.13 Whilst performance is strong, the Business, Place and Investment Team will
continue to review, through the SLA, performance, value for money,
qualitative information on outcomes such as jobs, business turnover and
social inclusion and how the support contributes to our growth aspirations at a
local level, including alignment with key sectors. 
5.9 Provision of Employment Land and Commercial Properties 
5.9.1 The private sector is usually the primary provider of employment land and
commercial properties, but the market conditions must be supportive.  Market
conditions include land availability and costs, development costs, sufficient
demand and level of rents or sales to ensure a return on investment.
However, when market conditions are not supportive, public-sector can
intervene and stimulate development and demand. 
5.9.2 The Perth and Kinross Employment Land and Property Market Analysis
Report (December 2022) recognised that while the employment land market
benefits from a generous planning allocation, the majority of allocated
employment land supply is constrained to some extent and is unlikely to be
developed in the short-medium term without public sector intervention. 
5.9.3 A survey of local businesses found that 43% of occupiers have, or will shortly
have, a requirement to expand or relocate.   
5.9.4 The Council’s Commercial Property Investment Programme (CPIP) includes
projects to deliver new small business units and serviced employment land.
Following initial capital investment, the CPIP is using sale receipts to fund
itself.  Demonstrating a commitment to supporting local businesses, the
Council, at its budget on 26 February 2025, agreed additional borrowing of
£7m over the next 3 years in addition to £2m the previous year.  This will allow
the development of new employment land and small business units across the
Page 52 of 128

Page 53

area, supporting new business start-ups and growth. The CPIP is being
delivered and managed by the Estates and Commercial Investment Team.  A
Board has been established to support delivery. 
5.9.5 An update will be provided to the Economy and Infrastructure Committee in
Spring 2026. 
6. Conclusion 
6.1 Perth and Kinross has a strong economy both in terms of number of
businesses, sectoral mix, survival rate and growth potential.  This is
evidenced by our rating from Growth Flag as having the strongest growth
potential (likely to grow by at least 20%) amongst businesses in the UK for the
year ahead. 
6.2 The Council has many interactions with businesses individually or collectively.
By fostering collaborative working across services and partners, the
recommendations contained within this report will help to build on and
improve the ‘Business-friendly’ approach adopted by the Council, improving
our economic performance and the opportunities for our businesses and
residents. 
7. Impact and Value Assessment 
7.1 Not applicable. 
8. Appendices 
8.1 Appendix 1 – Perth and Kinross Investment Prospectus 
Page 53 of 128

Page 54

Page 54 of 128

Page 55

PB 1
Invest in Perth and Kinross
A vibrant, forward-thinking business destination
full of investment opportunity and potential.
6
Page 55 of 128

Page 56

2 3
This Investment Prospectus presents the current investment
opportunities in Perth and Kinross and provides an overview of our
priorities, ambitions and business support for interested investors
and partners.
The prospectus also highlights the strength of our connections,
recent successful investments, and the supportive environment we
offer for driving forward leading innovations and sustainable growth.
Please contact our dedicated team to understand more about our
latest investment opportunities and for support with your interests.
Welcome Contents
INTRODUCTION
Choose Perth and Kinross
Perth and Kinross at a Glance
Our Sectors and Capabilities
The Best Place to Start and Grow a Business
INVESTMENT OPPORTUNITIES
Investment Opportunities Overview
1. Eco-Innovation Park
2. Perth City Heat Network
3. Strategic Energy Partnership
4. Advanced Plastics Sorting and Upcycling Factory
5. Binn Eco Park
6. Northfield Business Park
7. Culture Quarter
8. Mill Quarter
9. Station Quarter
10. Harbour Quarter
CASE STUDIES
SSE Energy Solutions
Aviva
4
6
8
10
11
12
14
16
18
20
22
26
28
30
31
32
33
Kirsty Easton
Senior Economic Development Officer
KEaston@pkc.gov.uk
Key Contacts
Oliver Johnstone
Economic Development Officer
OJohnstone@pkc.gov.uk
Page 56 of 128

Page 57

4 5
Choose Perth and Kinross
Perth and Kinross is consistently ranked as one of the top five places to live and work in the UK, and we
have a perfect balance that suits flexible working.
With the vibrant city of Perth, surrounded by stunning
scenery, home to a thriving arts and cultural scene,
excellent schools, and a competitive housing market,
it’s easy to see why. Globally renowned in our key
sectors of food and drink, energy, finance, creative
industries and tourism, our innovation and forward-
thinking make Perth one of Europe’s most sustainable
and attractive small cities.
In a prime location in Scotland’s central belt, Perth
and Kinross is a central hub for national rail, with fast
connections to international airports and all major
UK road networks. We are at the centre of the Tay
Cities, a region with a long track-record of successful
partnership working backed by transformational public
investment. The Tay Cities Region Deal brings £300m
of investment into a range of economic development
projects including digital skills, biomedical, agri-tech,
and low carbon and renewable technologies, and we
connect fantastic talent, research and infrastructure to
unlock sustainable growth.
We have a diverse and resilient business
community - from being Scotland’s independent
business champion to proudly being home to
major national and international brands, including
Highland Spring, Stagecoach, SSE, Aviva, and
Castle Water, amongst others.
Our national and international connectivity, digital
and energy infrastructure, and developer-ready
sites mean Perth and Kinross is an innovative
business and investment location.
Here in Perth and Kinross, our connected
infrastructure and dynamic sites can help
provide your launchpad for sustainable growth.
The Business, Place and Investment Team is
continually working on developing a range of
opportunities and is here to help unlock your
investment.
Offering a rich heritage, entrepreneurial spirit and exceptional
connectivity, Perth and Kinross is a word-class environment for
business and investment success.
Perth and Kinross
Glasgow
Mancester
Belfast
Edinburgh
Newcastle
London
Aberdeen
Dundee
Inverness
Page 57 of 128

Page 58

6 7
Perth and Kinross at a Glance
Innovative, Sustainable, Connected
Perth and Kinross is a vibrant region, full of
opportunity and potential. Located within
the innovative and skilled Tay Cities region,
our rich heritage, entrepreneurial spirit and
exceptional connectivity offer a word-class
environment for business and investment
success.
Economic Opportunity
Forward-thinking
Entreprenurial Mindset
• £4bn GVA per annum.
• 12% growth in the past 10 years.
High Levels of Productivity
• 17% higher than the Scotland average.
Strongly Positioned to Lead in the Green Transition
and Unlock Sustainable Economic Growth
• Publicly committed to making Perth one of Europe’s
most sustainable small cities.
• Abundant natural resources and biodiversity, and
considerable opportunities in renewable energy.
• A leading destination for innovation,
entrepreneurship and higher than average
business survival rates.
Region of World-Leading Expertise
• Home to the largest University of the Highlands
and Islands campus, close to St Andrews,
Edinburgh, Dundee and Abertay Universities;
and the James Hutton Institute, an agri-tech
world leader.
Talented and Skilled
Labour Market
Life in a Stunning Environment
Home to Diverse and
Innovative Businesses
• 65,000 working age residents in the Perth Travel
to Work Area.
• A highly skilled workforce with 47% qualified to
post-secondary levels.
Outstanding Business Growth Potential
• Named UK’s Top Local Authority with the
Strongest Business Growth Potential for 2025.
• 12% Business Expected To Grow by 20% 
(Growth Flag, 2025).
• A world-leader in food and drink, financial
industries and tourism, and positioned to lead in
energy transitions and future sustainability.
• Higher business growth potential than UK average
in all key sectors, and resilient businesses
throughout the region - 43% in rural areas, 57% in
rural areas.
Thriving Culture Hotbed
• Home to the UK’s only UNESCO City of Craft and
Folk Art.
• Consistently ranked among top five places to live
and work in the UK.
Public Investment Track Record
• £700m+ public investment with ambitious plans to
support future sustainable growth.
Quality of Life
• Unrivalled outdoor countryside.
• Offers a competitive housing market.
• Top-rated schools and a university campus within
Perth, many other academic institutions within 1hr.
• Good hospitals and health care facilities.
Page 58 of 128

Page 59

8 9
Our Sectors and Capabilities
Energy Transition
Food and Drink
The Circular Economy
Perth and Kinross is a proven world-class leader in food and drink, tourism and the financial industries. Home to a thriving creative community and
at the leading edge of the UK’s journey to net zero, we connect a broad range of capabilities to unlock investments and drive economic growth.
Financial and Business Services
Tourism
• Recognised as one of 119 areas across the globe
taking bold leadership on environmental action and
transparency.
• Home to Binn Group and a growing supply chain, the
Binn Eco Park is our flagship initiative at the cutting
edge of waste and circular economy focused resource
management.
• We are committed to
placing the region firmly
at the forefront of net zero
and clean growth.
• Perth is the growth home
of choice for major energy
transition businesses,
including SSE and Paprec
Energies, through to
innovative startups.
• Investments in Perth West
and the Strategic Energy
Partnership will unlock
more dynamic spaces and
opportunities.
• A strong cluster of financial and business services
expertise play a key role in the local and regional
economy.
• Perth is home to multiple national and international
insurers such as GS Group, and Aviva – the UK’s largest
insurer serving more than 31 million customers across 16
countries.
• Perth and Kinross is globally renowned for its food and
drink industry, home to 7 Scotch Whisky distilleries,
the world-famous Tay Salmon fishing, and the James
Hutton Institute International Barley Hub.
• We play a pivotal role, from being the
distribution hub for global brands, to providing
the testbed for food innovation and advances
in food security.
• Over 900 businesses,
public investment
and established
sites such as
Northfield Business
Park support sector
growth.
• Our region is a thriving creative hotbed and part of the
UNESCO Creative Cities Network.
• The new £27m Perth Museum opened in 2024 and 
attracted over 250,000 visitors in its first year of opening.
• Perth and Kinross
has unique incubator
spaces to support
digital and creative
SMEs, these are
situated within Perth
Creative Exchange,
which was a £4.5m
public sector
investment.
Creative and Digital
• A frontrunner for leisure, business and eco-tourism,
Perth and Kinross offers an unrivalled natural
landscape, colourful history and rich cultural offering.
• Events are a major tourism driver, with our region
hosting national and international events.
• Over 2 million visits in 2022, supported by exceptional
infrastructure and connectivity.
Page 59 of 128

Page 60

10 11
The Best Place to Start and Grow a Business
2019
Perth Transport Futures
Phase 1 – essential
local infrastructure
and connectivity 
improvements.
Our commitment to sustainable growth and securing investment in Perth
and Kinross is underpinned by a £600m+ public investment programme,
supporting essential infrastructure, key sectors, and arts and culture. Recent,
current and future projects include:
2021
Perth Creative Exchange,
winner of the Regeneration
Project of the Year, £4.5m
partnership project
between Perth and Kinross
Council and Wasps which
transformed the former
St John’s School building
into a hub for creative
industries.
2023
Award-winning Pitlochry
Festival Theatre £21.3m
capital project, 90%
funded by Tay Cities Deal.
Nov 2023
Increased digital
connectivity for around
1,400 digitally-hard-to-
connect households - with
more improvements
planned.
Mar 2024
Perth Museum opens, a
new £27million attraction
that  has attracted over
250,000 visitors in the first
year since opening.
Jun 2024
The Broxden Hub – Perth
low carbon transport hub
opens.
Dec 2024
Tay City Region
investments in innovation,
include the International
Barley Hub,  and the
Advanced Plant Growth
Centre, new  innovation
centres forming part of The
James Hutton Institute,
officially opened.
Mar 2025
Perth Transport Futures
Phase 2, The £150m Cross
Tay Link Road (CTLR),
opened. This was the
biggest infrastructure
project ever undertaken by
Perth and Kinross Council.
2025
Perth Transport Futures,
Phase 3. Funding has been
approved for Phase 3 to
connect Phases 1 and 2.
Dec 2025
£1.5m of EV charging
infrastructure expansion.
2026/27
Perth Transport Futures
Phase 4 will focus on
traffic management
measures within the city
centre.
2028/29
A new leisure centre for the
centre of Perth with £90m
funding committed by
Perth and Kinross Council.
Investment Opportunities
Perth and Kinross has a range of unique developer-ready investment opportunities, and a strong
pipeline of future opportunities, set out in this prospectus.
These include opportunities in:
• Energy and Net Zero
• Circular Economy
• Food and Drink
• Light Industrial
The strong foundation of public investment in the region demonstrates our commitment to
building resilience and supporting growth, and gives investors confidence that Perth and Kinross
is a location that is delivering for the future. The Business, Place and Investment Team believes
partnership working is the best way to deliver the region’s vision and will work closely with you to
realise this future.
Current opportunities
1 Eco-Innovation Park
2 Perth City Heat Network
3 Strategic Energy Partnership
(area wide)
4 Advanced Plastics Sorting and
Upcycling Factory (Project
Beacon)
• Travel and Logistics
• Leisure and Retail
• Accommodation
5 Binn Eco Park
6 Northfield Business Park
7 Culture Quarter (city centre)
8 Mill Quarter (city centre)
Pipeline opportunities
54
6
1
72
9
10
8
Station Quarter (city centre)
Harbour Quarter
9
10
Page 60 of 128

Page 61

12 13
Opportunity Description
A fully serviced 26ha Perth Eco-Innovation Park
(PEIP) is under development within the wider Perth
West mixed-use development with phase 1 (11ha)
at design and marketing stage.
The first stage of Perth West, a proposed national
hub of excellence for Net Zero activities, will be
the Eco-Innovation Park, a 26ha commercial hub
for companies focused on driving the transition for
Net Zero through innovation, green technology and
smart eco-investment.
The Eco-Innovation Park will provide opportunities
from flexible working environments for innovative
small start-ups, to innovative manufacturing space
for large companies, and dynamic lab-based areas
for research & development. Early opportunities
will be given to enterprises focused on stimulating
growth in next generation logistics, last mile
distribution and R&D around Mobility as a Service
(MaaS), active travel and blue-green infrastructure.
By being based alongside like-minded organisations
with interests in similar sectors, there will be
greater opportunities for cross-selling, collaboration
and idea generation. Eco-Innovation Park partners
will be able to access services across the wider
Perth West development, which includes:
	The Innovation Highway (a smart mobility corridor for testing MaaS, active travel and last mile
distribution developments)
	The National Green Transport Hub (a low carbon fuelling stop for EVs, hydrogen-fuelled HGVs and
coaches)
	DR.ECO (a 20MW solar park linking local smart grids with residents, businesses and transport
hubs)
By investing early, financial investors have a unique opportunity to influence planning and development
in the initial phases of the Eco-Innovation Park at Perth West, with a fully supported Masterplan strategy
currently being developed to secure long-term returns for investors through a proactive approach. Jones
Lang LeSalle are currently contracted to provide marketing and commercial development expertise and
experience for the PEIP.
1. Perth Eco Innovation Park
Size 26 ha (1st phase 11ha)
Investment Type Innovation Park – travel, logistics and Net Zero tech/
engineering
Total investment value £150M+
Timeframes for development Land ready to develop mid-late 2028
Units available early-mid 2029
Access to services and utilities Fully serviced sites
(Anticipated) Portfolio of onsite
organisations
Green Transport Hub partners, innovation/R&D partners,
engineering, technology organisations, hotel, retail and
last mile logistics
Investor Benefits A world-class destination for investors and companies
focused on Net Zero to collaborate
Contacts Kirsty Easton KEaston@pkc.gov.uk
Fact File
INVESTMENT OPPORTUNITIES
Page 61 of 128

Page 62

14 15
Opportunity Description
The proposed Perth City Heat Network is an ambitious project that will power a green and sustainable
future in Perth and Kinross, providing heat to numerous public buildings and social housing in Perth.
The development of a Heat Network as the anchor project of the Perth and Kinross Strategic Energy
Partnership will provide low-cost and low-carbon energy to homes and businesses across Perth and invest
in renewable energy projects across Perth and Kinross. 
Perth and Kinross Council, supported by ARUP, is currently developing its strategic heat network vision
supported by Scottish Government Heat Network Support Unit. Appraisal and analysis will determine the
potential to expand the city centre heat network opportunity to a wider area.
The appraisal and analysis will inform and enable an Outline Market Prospectus to be developed. This will
set out in more detail the investment opportunity for low carbon heat and decarbonisation energy projects
across Perth and Kinross and will include maps, technical development information, a high-level cost plan,
techno-economic model, risk register and the Outline Market Prospectus.
This project offers a fantastic opportunity to investors seeking to develop a leading heat network and
other renewable energy projects that will offer transformative clean energy to the city.
Size 2km2
Investment Type Heat Network. Linear heat density 5000 kWh/m/year. Total
annual heat demand 75 GWh. 15 Perth and Kinross Council
buildings connected. Fuel poverty 33%
Total investment value £100m
Timeframes for development Commence 2030-2040
Access to services and utilities Sewer network, river source (R Tay), or geothermal.  Full fibre
network, 5G mobile network.
(Anticipated) Portfolio of onsite
organisations
Large number of Perth and Kinross Council buildings (15), new
Leisure Centre, Perth Museum, Police HQ, Perth Prison, Perth
Royal Infirmary
Investor Benefits New Heat Network development as anchor project
Contacts Graham Pinfield GPinfield@pkc.gov.uk
Fact File
2. Perth City Heat Network
*Images are for illustrative purposes only
DN125
DN100
DN100
DN80
DN100
DN80
DN65
DN100
DN150
DN100
DN250
DN100
DN100
DN100
DN125
DN100
DN150
DN80
DN65
DN200
DN65
DN100
DN80
DN100
Esri Community Maps Contributors, Esri UK, Esri, TomTom, Garmin, GeoTechnologies, Inc, METI/NASA, USGS
Building Connections
Phase 1
Phase 2
Phase 3
Phase 4
Pipe Routing
Phase 1
Phase 2
Phase 3
Phase 4
INVESTMENT OPPORTUNITIES
Page 62 of 128

Page 63

16 17
Opportunity Description
The Perth and Kinross Strategic Energy Partnership is a unique opportunity to partner with the Council to
create a de-carbonised energy system fit for the future.
Perth and Kinross aims to reach net zero carbon emissions by 2045 in a fair, equitable and economically
viable way. In doing so, we need to focus on securing long-term sources of low cost and low carbon
energy that can effectively support the needs of residents and businesses throughout the area. Leading
businesses such as SSE by SSEN, Scottish Water, Scottish Gas Network, and others, are united behind our
ambitious energy transition targets and there are significant opportunities to realise the potential of green
technologies and infrastructure in the region.
The Strategic Energy Partnership will play a key role in placing Perth and Kinross at the forefront of net
zero and clean growth. The partnership will help unlock investment and facilitate the delivery of heat,
renewable energy and decarbonisation projects. Recommended by the Local Heat and Energy Efficiency
Strategy (LHEES) approved by the Council in 2023, the partnership will support a range of projects
benefiting community, social, residential, commercial and industrial developments.
In addition to the Perth City Heat Network, there are opportunities for investors to contribute to the
successful achievement of green energy transformations in the region. Opportunities will continue to
emerge as the partnership is further developed, with projects including battery and energy storage
infrastructure, low carbon and active travel infrastructure, EV charging, and solar projects.
This is a fantastic opportunity to join us in laying the foundations for sustainable growth across the
region and beyond.
3. Strategic Energy Partnership
Fact File
Investment Type Heat networks, EV charging, renewable energy (solar - ground
mount and rooftop PV, wind, HEP) battery storage.
Total investment value £1bn
Timeframes for development Strategic Energy Partnership to 2050 (25 years)
Access to services and utilities Access to Perth and Kinross Council land and buildings estate
(£1bn valuation)
(Anticipated) Portfolio of onsite
organisations
Perth and Kinross Council, public sector organisations, private
sector estates, P&K Economic Partnership, SSEN.
Investor Benefits Contributing to net-zero and clean growth outcomes in the local
area
Contacts Graham Pinfield gpinfield@pkc.gov.uk
*Images are for illustrative purposes only
INVESTMENT OPPORTUNITIES
Page 63 of 128

Page 64

18 19
4. Advanced Plastics Sorting and Upcycling Factory (Project Beacon)
Opportunity Description
Located at Binn Eco Park, an Advanced Plastics Sorting and Upcycling Factory (APSuF) will be a regional,
scalable Residual Plastics Waste (RPW) treatment facility, suitable for networking with other similar
facilities. It will deliver a systems change for the improved management of plastic waste, addressing the
many issues this complex group of materials presents.
The project is forecast to make an operating profit of £1.85 million p.a. once it is fully operational and will
help solve some aspects of micro plastic and marine litter risks.
The factory will provide safe, inventoried, long term material conservation (Land Banking) for excess
plastics. Through the factory, waste will be separated for reuse into:
• additional mechanical recyclates value (granulate/flake/pellet);
• sources of plastic waste for chemical feedstock recycling systems; and
• materials for direct on-site product manufacture
The APSuF system will support process and system optimisation, training and R&D for the development
of new distributed plastics economies. It encourages the proximate and regional management of RPW at
a global level and significantly reduces non-biogenic carbon emissions from incineration and the wider
plastics system.
There is an exciting opportunity for investors to partner with the project, helping to realise the potential of
the Factory and to be part of its circular economy innovations.
*Images are for illustrative purposes only
Fact File
Size Design capacity sufficient to accept, process and recycle up to
30,000 tonnes of single stream recyclates and RPW per annum
Investment Type Energy and circular economy
Total investment value £9.2m (includes £5.2m of City Deal Funding)
Timeframes for development Construction 2027/28 
Operational 2028/29
Access to services and utilities On site renewable energy and potential private wire
(Anticipated) Portfolio of onsite
organisations
Paprec, EcoideaM Ltd, The Binn Group
Integration with the Tay Cities Clean Growth Initiative and its
partners including:
Michelin Scotland Innovation
St Andrews University
The James Hutton Institute
Investor Benefits Engagement with concept optimisation and system disseminations.
Concept utilisation rights including access to the Polymer Fusion
Moulding technology for product manufacture for mixed waste
plastic flows.
Operating profit of £1.85m pa.
Contacts John Ferguson (Binn Eco-Park)  john.ferguson@binnecopark.com
INVESTMENT OPPORTUNITIES
Page 64 of 128

Page 65

20 21
5. Binn Eco Park
Size 200-acre site
Investment Type Plastics recycling; Renewable Energy; Energy from Waste plant
(£120m - in construction); green hydrogen production (planned);
food waste recycling; wind energy
Total investment value £100m
Timeframes for development Advanced plastics recycling 2028/29
Access to services and utilities Potential for private wire connection to Perth City heat network
(Anticipated) Portfolio of onsite
organisations
Binn Group (lead organisation)
SUEZ UK
Earnside Energy
Pi Polymers
Investor Benefits Controlled environment for organisations developing innovative
approaches in the circular economy
Contacts John Ferguson  john.ferguson@binnecopark.com
Opportunity Description
Binn Eco Park is located near Glenfarg six-miles from Perth and is one of the most fully integrated re-
source recovery complexes in the UK. It employs over 160 people and provides significant economic ben-
efits and added value to the local economy.  A former landfill site it is now focuses on the circular economy
and a £120m Energy from Waste facility is currently under construction in a joint venture with French
waste company Paprec.
Binn Eco Park is also currently home to:
• two separate Material Reclamation Facilities (MRF) treating commercial, industrial and municipal
waste
• a 30,000 tonne per annum food waste anaerobic digestion facility.
• in-vessel and green-waste composting facilities.
• a residual waste Solid Recovered Fuel (SRF) facility.
• waste wood processing and storage facilities.
• 4x 2.3MW wind turbines with complementary battery systems to be added in due course.
Planning consent has recently been secured for an Advanced Plastics Recycling Facility (A-PRF) combining
mechanical and chemical plastics recycling systems, an energy from waste plant and a four-turbine wind-
farm.
Investors can partner to play a role in the future development of these leading facilities, supporting growth
and innovation in the circular economy.
INVESTMENT OPPORTUNITIES
Page 65 of 128

Page 66

22 23
Inveralmond Industrial Estate
Northfield
6. Northfield Business Park
Opportunity Description
Located on the outskirts of Perth this prime location offers efficient distribution and logistics, in a fully
serviced business park with plots currently available.
Northfield Business Park offers a competitive edge for industry of all sizes. This prime location with
great connections to all major Scottish road and rail networks offers efficient distribution and logistics
capabilities, proximity to the national talent pool, and a cost-effective, no compromise, alternative to its
large city counterparts.
There are a number of plots currently available, totalling 12.8 acres, with plot sizes ranging from 1.2 acres
to 5 acres – catering for businesses at all stages of their development journey. By bringing together cost-
effective production facilities, with a desirable location on the edge of the city, Northfield Business Park
presents a significant strategic opportunity to be part of a hub for businesses with significant logistics and
distribution considerations.
High-profile organisations such as John Deere, McLaughlan Transport and Eastern Western Motor Group
are currently headquartered at Northfield. Other organisations with operations nearby include SSE,
Dingbro, Praveen Kumar and the Inveralmond Business Centre. There are considerable opportunities for
businesses of all sizes to engage and collaborate.
Businesses linked to the Food and Drink industry are encouraged, but the land is also suitable for
Business, Industrial, and Storage and Distribution uses with planning permission granted for Use Classes
4 (Business), 5 (General Industrial) & 6 (Storage or Distribution).
Size 12.8 acres, spread across five plots ranging from 1.2 – 5 acres
Investment Type Food and Drink industry manufacturing, logistics and distribution
centre, flexible light industrial demand
Total investment value £10M+
Timeframes for development Shovel-ready
Access to services and utilities Fully serviced sites
(Anticipated) Portfolio of onsite
organisations
John Deere Forestry, McLaughland Transport and Eastern Western
Motor Group
Investor Benefits Prime location for efficient distribution and logistics across
Scotland
Contacts Kirsty Easton KEaston@pkc.gov.uk
RIVER TAY
SUDS PONDSOLAR  
ARRAYS (X3)
FOOD & DRINK UNITS
RAILWAY LINE
ARRAN
ROAD
KILDA ROAD
SITE 6
SITE 7
SITE 8
SITE 9
SITE 12
5 acres
2.4 acres
2.0 acres
2.2 acres
1.2 acres
A
B
INVESTMENT OPPORTUNITIES
Page 66 of 128

Page 67

24 25
7–10: City Quarters
The Perth City Centre Development and Design Framework offers a range of
investment opportunities that will drive sustainable economic growth and
revitalise the city centre.
Already an exceptional hub of creative activity, home to a wide array of independent businesses and
increasingly developing a reputation as a food town, Perth attracts visitors from across the region and
beyond. Major public investments have helped revitalise the city centre over recent years, including
award-winning public realm projects. There are now opportunities to invest in and be part of specific sites
that will be key to the city’s future.
In line with the aim of the Perth City Plan for 2040 to make Perth one of Europe’s great ‘small cities’, we
have an ambitious agenda for shaping a growing, sustainable, connected and equitable city. We have
carefully developed plans for the next phase of developments, including for the creation of new focal
points, landmarks and community facilities that will further enhance the city.
Our latest opportunities and pipeline opportunities for development in our quarters, are displayed over the
following pages. Through a range of attractive developments, the quarters will support the creation of a
sustainable mixed-use economy in Perth and attract more residents and repeat visitors to the thriving city
centre.
Perth City Centre Development & Design Framework
guidance - presenting a series of ‘intervention
options for streetscape enhancements, property
improvements and new developments and uses
within the city centre and designated investment
areas. It also promotes a city-wide initiative to
improve connectivity between the areas and wider
neighbourhoods through improved active travel
routes. The proposed interventions aim to drive
sustainable economic growth and revitalise and
support the city centre.
The series of proposed investment areas are shown
below and include the city centre as a whole and a
number of designated ‘quarters’.
• Guiding and promoting property development
on vacant and underdeveloped sites in P
city and its city centre.
• Provide guidance and support for local
businesses to revitalise and/or adapt their
operations and properties.
• Attract consumers and visitors back to the city
centre through promotion, information, and
incentives.
MILL QUARTER
Mixed-use development to include
residential in key city centre location.
Key streetscape improvements
for historical streetscape including
connection to Mill Street and High Street
to St Paul’s Church.
CULTURE QU
Extended pedestrian priority public
space within the city centre supporting
the cultural offer
Streetscape improvements, al fresco
dining and opportunity to reflect the
historic conte
engaging with the P
CITY CENTRE & Wider Area
Series of Streetscape and Building
Improvements.
New and improved active travel
connections between the city centre,
investment areas and wider Perth
neighbourhoods. 
The series of proposed investment areas are shown
below and include the city centre as a whole and a
number of designated ‘quarters’.
incentives.
STATION QUARTER
New masterplan for gateway to Perth
city centre with transport interchange,
active travel routes and development of
adjacent development sites for mixed-
use.
MILL QUARTER
Mixed-use development to include
residential in key city centre location.
Key streetscape improvements
for historical streetscape including
connection to Mill Street and High Street
to St Paul’s Church.
CULTURE QUARTER
Extended pedestrian priority public
space within the city centre supporting
the cultural offer.
Streetscape improvements, al fresco
dining and opportunity to reflect the
historic context of the city through
engaging with the Perth Lade.
CITY CENTRE & Wider Area
Series of Streetscape and Building
Improvements.
New and improved active travel
connections between the city centre,
investment areas and wider Perth
neighbourhoods. 
Introduction
Background
The Perth City Development and Design
Framework serves as a comprehensive document
outlining guidelines and principles for urban
development in Perth. It provides a framework
for architects, planners, and developers to create
a cohesive and sustainable urban environment
in the city. The Framework aims to enhance the
overall design quality, functionality, and liveability of
Perth through informed and strategic development
practices.
The Perth City Development and Design Framework
is being developed to build upon existing
planning, economic design, and development
guidance - presenting a series of ‘intervention’
options for streetscape enhancements, property
improvements and new developments and uses
within the city centre and designated investment
areas. It also promotes a city-wide initiative to
improve connectivity between the areas and wider
neighbourhoods through improved active travel
routes. The proposed interventions aim to drive
sustainable economic growth and revitalise and
support the city centre.
The series of proposed investment areas are shown
below and include the city centre as a whole and a
number of designated ‘quarters’.
The aims and objectives of the Perth City
Development and Design Framework include:
• Support the creation of a sustainable mixed-
use economy in Perth city centre.
• Creating a comprehensive public and private
investment design-focussed framework aligned
with the Corporate Plan, Perth City Plan, and
Economic Wellbeing Plan objectives.
• Informing transport investment and
management, optimising key routes and
spaces for various transport modes, supporting
development, and enhancing active use of
public space.
• Guiding and promoting property development
on vacant and underdeveloped sites in Perth
city and its city centre.
• Provide guidance and support for local
businesses to revitalise and/or adapt their
operations and properties.
• Attract consumers and visitors back to the city
centre through promotion, information, and
incentives.
HARBOUR QU
New alternative marine and leisure
uses.
Improve connection and water access
infrastructure from harbour area and
adjacent Moncreiffe Island.
STATION QUARTER
New masterplan for gateway to Perth
city centre with transport interchange,
active travel routes and development of
adjacent development sites for mixed-
use.
UNIVERSITY QUARTER
Primary/Secondary/Further and Higher
Education campus development.
Improved transport links to Perth city
centre and Train/Bus Stations.
MILL QUARTER
Mixed-use development to include
residential in key city centre location.
Key streetscape improvements
for historical streetscape including
connection to Mill Street and High Street
to St Paul’s Church.
CULTURE QUARTER
Extended pedestrian priority public
space within the city centre supporting
the cultural offer.
Streetscape improvements, al fresco
dining and opportunity to reflect the
historic context of the city through
engaging with the Perth Lade.
CITY CENTRE & Wider Area
Series of Streetscape and Building
Improvements.
New and improved active travel
connections between the city centre,
investment areas and wider Perth
neighbourhoods. 
Introduction
Background
The Perth City Development and Design
Framework serves as a comprehensive document
outlining guidelines and principles for urban
development in Perth. It provides a framework
for architects, planners, and developers to create
a cohesive and sustainable urban environment
in the city. The Framework aims to enhance the
overall design quality, functionality, and liveability of
Perth through informed and strategic development
practices.
The Perth City Development and Design Framework
is being developed to build upon existing
planning, economic design, and development
guidance - presenting a series of ‘intervention’
options for streetscape enhancements, property
improvements and new developments and uses
within the city centre and designated investment
areas. It also promotes a city-wide initiative to
improve connectivity between the areas and wider
neighbourhoods through improved active travel
routes. The proposed interventions aim to drive
sustainable economic growth and revitalise and
support the city centre.
The series of proposed investment areas are shown
below and include the city centre as a whole and a
number of designated ‘quarters’.
The aims and objectives of the Perth City
Development and Design Framework include:
• Support the creation of a sustainable mixed-
use economy in Perth city centre.
• Creating a comprehensive public and private
investment design-focussed framework aligned
with the Corporate Plan, Perth City Plan, and
Economic Wellbeing Plan objectives.
• Informing transport investment and
management, optimising key routes and
spaces for various transport modes, supporting
development, and enhancing active use of
public space.
• Guiding and promoting property development
on vacant and underdeveloped sites in Perth
city and its city centre.
• Provide guidance and support for local
businesses to revitalise and/or adapt their
operations and properties.
• Attract consumers and visitors back to the city
centre through promotion, information, and
incentives.
HARBOUR QUARTER
New alternative marine and leisure
uses.
Improve connection and water access
infrastructure from harbour area and
adjacent Moncreiffe Island.
STATION QUARTER
New masterplan for gateway to Perth
city centre with transport interchange,
active travel routes and development of
adjacent development sites for mixed-
use.
UNIVERSITY QUARTER
Primary/Secondary/Further and Higher
Education campus development.
Improved transport links to Perth city
centre and Train/Bus Stations.
MILL QUARTER
Mixed-use development to include
residential in key city centre location.
Key streetscape improvements
for historical streetscape including
connection to Mill Street and High Street
to St Paul’s Church.
CULTURE QUARTER
Extended pedestrian priority public
space within the city centre supporting
the cultural offer.
Streetscape improvements, al fresco
dining and opportunity to reflect the
historic context of the city through
engaging with the Perth Lade.
CITY CENTRE & Wider Area
Series of Streetscape and Building
Improvements.
New and improved active travel
connections between the city centre,
investment areas and wider Perth
neighbourhoods. 
The Culture Quarter is a
major strategic asset to
Perth, at the heart of ongoing
developments to deliver
cultural-led regeneration
in the city centre and wider
region.
The Mill Quarter will be
home to a new £61m
swimming pool and
leisure centre, adding to
Perth’s thriving culture
and leisure attractions in
the city centre
The Station Quarter and
the Harbour Quarter
are complementary
components of the vision
for Perth city. These are
longer term opportunities
for investors that continue
to develop, and we
welcome any enquiries and
future discussion.
7
9 10
8
INVESTMENT OPPORTUNITIES
Page 67 of 128

Page 68

26 27
7: Culture Quarter
Opportunity Description
The Culture Quarter is a major strategic asset to Perth, at the heart of ongoing developments to deliver
cultural-led regeneration in the city centre and wider region.
Building on the award-winning Mill Street regeneration, the further development of the Culture Quarter
offers a range of opportunities, including for new leisure and residential developments in the centre of
a vibrant city. The quarter is home to a thriving cultural scene, with outstanding assets including Perth
Theatre, Perth Concert Hall, Perth Art Gallery and the new Perth Museum.
The Culture Quarter celebrates the history of Perth and the current creative and cultural transformation
underway in the city. There are currently opportunities to refurbish and convert parts of existing historic
buildings into new residential use, and there are vacant sites available to support new public realm,
residential, leisure and experiential developments.
The area will be a catalyst for the greening of the city and new developments will broaden the appeal of
the city centre, which is already known for its independent shops and a growing reputation as a food town.
This is a tremendous opportunity to help shape the future of Perth, with the potential to realise strong
returns from new developments.
The vision for the area is to build on the initial success of the Culture Quarter and extend the Mill Street
public realm project westwards to Mill Street/ Murray Street area, including: traffic reduction, streetscape
improvements, areas for events and al fresco dining use for adjacent hospitality businesses. Several
development opportunities exist at the St. Johns Shopping Centre; former Debenhams building on High St;
former Beales Dept Store and several gap sites for residential or student accommodation developments.
Fact File
Investment Type Residential/leisure development/public realm
Total investment value £100m
Timeframes for development Estimated by 2040
Access to services and utilities Full fibre broadband and 5G mobile network services, Perth City
public Wi-Fi, planned heat network for city centre
(Anticipated) Portfolio of onsite
organisations
PKC has large number buildings in city centre, St John Shopping
Centre, Culture PK manage Perth Museum and Art Gallery,
Investor Benefits Potential for investors to realise strong returns through rising
yields, and to support the catalysing of green developments in an
exciting Cultural Quarter with existing public sector investment.
Contacts Steve MacDonald stevenmacdonald@pkc.gov.uk
Lower City Mills: New Project
Opportunity
South to North Methven Street:
Streetscape Improvements with
New Raingardens, Tree Planting,
Parking and Designated Bus Stops
Expose Existing Lade for
New Blue Infrastructure
Public Space
Towards Mill Quarter
Area
Infill / Gapsite Development: with
New Residential Upper Floors and
Ground Floor Retail
Extension of Existing Mill Street
Public Space into Murray/Mill
Street Area. To include New
Surface Treatments, Greenspace,
Tree Planting
Towards Existing Culture
Quarter Area
INVESTMENT OPPORTUNITIES
Page 68 of 128

Page 69

28 29
8: Mill Quarter
Opportunity Description
The Mill Quarter will be home to a new £61m swimming pool and leisure centre, adding to Perth’s
thriving culture and leisure attractions in the city centre and offering new opportunities for city residential
developments.
The Council is seeking a high-quality development for residential and other complementary uses that
promotes city centre living, communal open and green spaces, active travel and that celebrates the area’s
historic setting. Overall, the development will help contribute to a greener, more accessible and more
pedestrian and cycle friendly area of the city.
The Mill Quarter is close to the historic Lower City Mills area and the Old High Street, which connects
the area towards the main High Street and central retail and cultural area. The existing Mill Quarter is
characterised by the Thimblerow carparking area (the site for the proposed leisure centre) which are at
the edge of the city centre but could form an ideal mixed residential and leisure development close to the
attractions and facilities of the city centre.
The leisure site is expected to be ready for development within 2 years, with the leisure centre set to
open in 5 years. The development of the Mill Quarter will also unlock further land elsewhere including for
residential and student living opportunities. A planned Perth City Heat Network is further being explored
to enhance the sustainability of buildings on the site.
This Quarter will benefit from significant public investment into the area, with the opportunity for
developers to be involved in the project through residential opportunities, and through the leisure facilities
and surrounding green infrastructure.
Investment Type Leisure and residential developments
Total investment value £60m+
Timeframes for development 2040 for Mill Quarter and 2030 for leisure centre
development
Access to services and utilities Full fibre broadband, 5G mobile network, Perth public WiFi;
planned Perth City Heat Network
(Anticipated) Portfolio of onsite
organisations
Many PKC buildings; Pullar House to become multi-agency
public service hub; Perth Concert Hall and Perth Theatre run
by Horsecross Arts.
Investor Benefits Series of new residential developments with part mix-use,
public and private amenity spaces, connections to active
travel routes and low/zero-carbon affordable heating.
Contacts Kirsty Easton keaston@pkc.gov.uk
Perth City Centre Development & Design Framework
41
01 Mill Quarter
40
New Public Park Space,
to include: Greenspace,
Tree Planting and Play
Opportunities
Inner Ring Road to include:
New Cycle Infrastructure,
Improved Pedestrian
Crossings and Opportunity
for Gateway Public
Artwork
Public Space Gateway
to Leisure Site: Public
Space with upper-storey
connection between
Leisure Developments
New Leisure Development
Opportunity 01, to include:
Swimming Pool, Leisure Pool,
and Gym
New Leisure Development
Opportunity 02, to include:
Indoor Football and Racket
Sports Courts
Lower City Mills Area:
Pedestrianised area and
Improved link to Culture
Quarter; with reuse of Lower
City Mills Building
Parking Areas: Car parking
provision for Leisure Site, to
include: EV charging points,
cycle infrastructure and tree
planting/rain gardens around
edges of parking areas
Old High Street: Pedestrianised
area and Improved Streetscape
with Seating and Tree-Planting;
Connecting to St Paul’s Public
Space and towards City Centre
Fact File
INVESTMENT OPPORTUNITIES
Page 69 of 128

Page 70

3130 31
9: Station Quarter 10: Harbour Quarter
The Station Quarter and the Harbour Quarter are complementary components of the
vision for Perth city. These are longer term opportunities for investors that continue to
develop, and we welcome any enquiries, requests for further information, or discussions
with potential partners to progress these opportunities as they evolve.
The Harbour Quarter is a significant leisure, tourism and food and drink opportunity.
The existing Perth Harbour area has been identified as an additional key investment area within the
city area. The harbour currently operates as a commercial port but has recently been the subject of an
appraisal to consider the viability of the harbour continuing to operate in such a manner. 
The Station Quarter will create a new and improved gateway to Perth. Station and public realm
improvements, and new housing and enterprise spaces will transform this Perth city site. Plans for
redevelopment of the station have already been made by Network Rail under the Perth Station Masterplan
linking with the nearby bus station.
Opportunities in development include the former bus station site, to be developed to include a new
centre for business enterprise and start-up accommodation, while there are also opportunities for a new
residential neighbourhood.  £15m of funds for a bus and rail interchange are committed for development
from the Tay City Deal. Further opportunities will be unlocked as the nearby Mill Quarter is progressed.
Although currently still operating as a commercial port, the Council is proposing a number of new
commercial and leisure uses for the Harbour including: alternative marine, leisure and water-based
activities and uses, and renewable energy production/storage. This can also be supported by the delivery
of new infrastructure to improve access to the water and land within the harbour area and the adjacent
Moncrieffe Island.
New Entrance Building with
Retail
New and Improved Train
Station Operational Areas
Reinstate Original Train
Station Building and
Entrance with New Public
Realm Area
Development
Opportunity: New
Residential Site alongside
retained Dewars Centre
Sports Facilities
Development Opportunity in
Existing Bus Station Site, to
include: New Business Start-
Ups and Residential Area
Improved ‘Green Corridor’
Connection to City Centre with
Streetscape Improvements,
Cycle Infrastructure and Public
Artwork
New Gateway Public Space
with Greenspace, Seating,
Active Travel Hub
New and Improved
West to East Pedestrian
Connections for
Pedestrians New Bus Station in
Location Connecting to
Public Realm of new Train
Station Area
Perth City Centre Development & Design Framework04 Harbour Quarter
82
New Landmark Cultural Building
e.g. New Museum Celebrating
the History of Salmon Fishing on
the River Tay
New Watchtower
Structure For Views and
Connections to Perth’s
Natural Surroundings
New Dock Side Marina for
Recreational Use, to include:
Swimming, Watersports,
Seating Areas and Boat Area
New Waterside
Promenade Public
Space with Seating,
Tree Planting and Public
Artwork
New Boat House for Boat
Building, Storage and to be
used by Local Community
Groups e.g. Perth Sailing Club.
To include new Connections to
Rover Tay
New Container ‘Village’ for
New Business Use, Food
and Drink Retail and Local
Community Groups
New Development
Opportunity for Business Use
and Local Services. Adapt and 
Reuse of Existing Units for
Manufacturing Use
INVESTMENT OPPORTUNITIES
Page 70 of 128

Page 71

32 3332
With roots in Perth dating back to the formation
of General Accident in 1885, Aviva now proudly
employs over 1,200 staff in our Perth office. As we
look to the future, we are excited about continuing
to expand our footprint in the city, with further
growth in our General Insurance
business planned in 2025 and
beyond.
Our operations are driven
by a strong commitment to
sustainability. As the first
major insurer worldwide to
aim for Net Zero by 2040, we
have continuously invested in
our Perth site. Recently, we installed a 77-meter
wind turbine, which, combined with existing solar
and battery technology, ensures that 100% of
our electricity demand is met through renewable
energy.
We are also pleased to announce our investment
in a new training facility at our Perth office,
designed to accommodate a brand new leadership
CASE STUDIES CASE STUDIES
SSE plc is proud to be headquartered in
Perth, positioning the city at the heart
of Scotland’s transition to a low carbon
future. As a leading UK energy company,
we are investing £20 billion in green energy
projects by 2027 through our Net Zero
Acceleration Programme Plus, supporting
innovation, resilience, and green careers.
Perth and Kinross is an ideal place to lead
the green transition, providing excellent
access infrastructure, a skilled workforce,
and a forward-thinking approach to
sustainable development. From our HQ in
Perth, we’re delivering the UK’s net zero
future.
One recent example is our partnership with
Highland Spring, where we’re delivering a
7MW solar array on the Ochil Hills to power
their Perthshire operations, demonstrating
how bespoke renewable energy solutions can reduce
carbon footprint, while also enhancing energy
resilience for industry.
SSE Energy Solutions: Powering net zero from Perth Aviva – Why Perth
Above: Ross McLory, SSE, and Donald MacBrayne, Scottish
Water Horizons discuss wastewater horizons plans.
Credit: Iain Ferguson, The Write Image
Left: Stuart Batty, SSE Energy
Solutions; Simon Oldham, Highland
Spring Group; councillor Liz Barrett,
Perth and Kinross Council; and Jim
Fairlie MSP at the site of the new
7MW Solar Array in the Ochil Hills.
We’ve also announced a strategic
partnership with Scottish Water Horizons
to develop low-carbon district heat
networks across Scotland, showing
how businesses and local communities
can benefit from innovative heat
solutions.
With deep roots in Perth and a national
outlook across Scotland and the rest of
the UK, SSE is proud to be a key player
in the UK’s energy transition, bringing
together world-class expertise, long-
term investment, and a passion to power
change.
programme for all 4,500 leaders at Aviva. This
long-term investment in leadership will create a
consistent development framework, enhancing and
expanding the capabilities needed now and into the
future.
Over the next two years, Aviva
will invest over £2 million in the
local economy through travel
and accommodation, as leaders
from across the UK and Ireland
come to Perth for training. In
the long term, the site will serve
as a primary centre for training
and development, supporting
both leadership initiatives and the broader Aviva
University curriculum.
We continue to work closely with Perth and Kinross
Council, the Scottish Government, local businesses,
and the third sector to develop our place-based
social action strategy. This collaborative effort aims
to benefit the local communities we represent and
drive economic growth for the region.
The turbine will produce
3000 megawatt hours of
clean energy per year
Page 71 of 128

Page 72

34
Invest in Perth is the inward investment brand of
Perth and Kinross Council. We are here to ensure your
investment journey can achieve its full potential and to
help you to realise your ambitions for growth.
If any of the opportunities discussed in this brochure are
of interest to you, please get in touch with Kirsty Easton:
KEaston@pkc.gov.uk
or visit our website for more information about the
business support we offer, the opportunities we
have and to stay up-to-date with the latest news and
developments around Perth and Kinross.
Page 72 of 128

Page 73

Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality 
___________________________________________________________________  
Committee or Board: Economy and Infrastructure 
Date of Meeting: 27 August 2025 
Report Title:  Renewable and Low Carbon Energy Supplementary
Guidance 
Report Number: 25/212 
Report Author:  Robert Wills, Planning Officer, Development plans
team 
Organisational Lead:  Serge Merone, Strategic Lead – Economy,
Development and Planning 
___________________________________________________________________ 
1. Purpose 
1.1 This report presents the most recent draft of the Renewable and Low Carbon
Energy supplementary guidance for planning proposals (the draft Guidance).
Planning guidance does not form part of the development plan. When relevant
to a decision, the guidance will be a material consideration to be afforded
such weight as determined by the decision maker. This report provides a
summary of changes necessary since the previous draft due to the
introduction of National Planning Framework 4 and current practice. The
report seeks consent to proceed to public consultation. 
1.2 Sections 
1. Purpose
2. Recommendation
3. Background/Main Issues
4. Impact and Value Assessment
5. Appendices 
2. Recommendation 
2.1 It is recommended that the Committee: 
• Approve the draft Renewable and Low Carbon Energy supplementary
Guidance and Strategic Environmental Assessment screening report to
proceed to public consultation. 
7
Page 73 of 128

Page 74

3. Background/Main Issues 
3.1 Historic Information/Context 
3.1.1  The Renewable and Low Carbon Energy supplementary guidance was first
produced and consulted on in 2016 as statutory guidance. An updated draft
was further consulted on in 2019. These drafts were not finalised due to
concerns from key agencies with regards to landscape sensitivity mapping
which did not provide for interrogation of the underlying layers. 
3.1.2 National Planning Policy as set out in National Planning Framework 4 (NPF4)
superseded Scottish Planning Policy in February 2023. NPF4 also
supersedes policies in LDP2 where they are incompatible. Some LDP2
policies, or parts of policies, remain in force where they are compatible with
NPF4, for example by providing local detail or filling a policy gap. This means
that both NPF4 Policy 11: Energy and parts of LDP2 Policy 33: Renewable &
Low Carbon Energy are in force. 
3.1.3 The Planning (Scotland) Act 2019 also removed planning guidance as part of
the development plan. The draft Guidance can therefore not override National
Planning Policy in NPF4, nor introduce new policy. The draft Guidance does
however set out how policy will be interpreted and the information required by
decision makers in Perth & Kinross to determine whether current policy is
satisfied. 
3.1.4 The draft Guidance is not an indication of future policy in the next Local
Development Plan (LDP3). Any new policy will be introduced through LDP3.
Further engagement will be carried out with members, stakeholders and
communities as part of the LDP3 proposed plan preparation to inform future
policy. 
3.1.5 The draft Guidance therefore sets out the Council’s interpretation of current
planning policy and the information expected to be submitted by applicants to
allow a fully informed determination of applications. 
Need for Updated Guidance 
3.1.6 The Guidance is based on established best practice and policy interpretation.
Much of the best practice guidance and the intent of policies remains the
same to previous drafts. However, there have also been substantive changes
which require the draft guidance to be updated. 
3.1.7 NPF4 introduced a more supportive approach to renewable energy. In
summary these changes include:
• The removal of a spatial framework for wind,
• The significant weight to be given to the Climate emergency in NPF4
Policy 1,
• The expectation of significant adverse landscape impacts from some
forms of renewable energy,
• Express provision for renewable energy installations on prime
agricultural land, carbon rich soils, flood risk areas and the greenbelt. 
Page 74 of 128

Page 75

3.1.8 The draft Guidance sets out the Council’s expectations as to how these
policies will be interpreted and the evidence required by proposals. 
3.1.9 Some NPF4 policies also introduced complexity and uncertainty. Where
relevant, the preferred policy interpretation of these policies is set out. This
includes biodiversity enhancement in NPF4 Policy 3, the definition of
renewable energy as “essential infrastructure” in several policies and the
introduction of a requirement to “maximise net economic impact”. 
3.1.10 The Guidance requires a statement of net economic impact to include those
elements set out in Policy 25(a) Community Wealth Building. This addresses
issues such as employment, training, business and utilising local supply
chains. Opportunities should be explored with local communities and address
local priorities such as those set out in Local Place Plans. 
3.1.11 It should be noted that “community benefit” is a consideration separate from
planning which typically involves a monetary payment to a community fund,
but can also include community ownership of a scheme or discounted power.
Community benefit cannot be taken into account in planning decisions. A
separate members’ briefing note distributed on 6 July 2025 discusses
community benefit in more detail.  
3.1.12 Since the previous draft, and with the introduction of NPF4, there has been an
increase in applications of Battery Energy Storage Systems (BESS).
Experience of these applications and additional guidance with regards to fire
safety has informed the guidance for these applications. 
3.1.13 In addition the land use requirements of solar and BESS installations has
required an increased focus on cumulative impacts. The draft Guidance
ensures that applicants provide decision makers with information describing
cumulative impacts on soils, landscape and noise. 
3.1.14 The draft Guidance emphasises that the cumulative loss of prime agricultural
land must be addressed in planning applications and requires demonstration
of specific locational needs, no other non-prime site being available and
consideration of alternative sites. Applicants are asked to quantify the loss of
prime land from their application. This is intended to provide greater certainty
for decision making. As noted above, policy changes such as how much loss
of prime land is acceptable cannot be introduced by the draft Guidance but
can be considered through the preparation of LDP3.   
3.1.15 Engagement to Date 
3.1.16 The previous draft guidance on which this guidance is based was a result of
extensive engagement with key agencies, internal consultees and a public
consultation. 
3.1.17 NatureScot and SEPA have been engaged with to assist in clarifying specific
areas of concern leading to improved clarity in interpretation. 
3.1.18 Engagement with elected members has been carried out leading to additional
information being introduced in this report on cumulative impacts, net
Page 75 of 128

Page 76

economic impact and community benefit. At a members briefing for LDP3
these topics were also discussed and a briefing note distributed on 6 July. 
3.1.19 Consultations have also been carried out on specific areas of interest with:
• Biodiversity/Tree Officer
• Flood Team
• Development Management
• Environmental Heath
• Development Plans Team
• Transport Planning
• Community Greenspace
• Conservation Team
• Elected Members
• NatureScot
• Highland Council and South Lanarkshire Council (due to a shared
interest in BESS applications). 
3.1.20 NatureScot, Historic Environment Scotland and SEPA were also consulted on
the screening assessment resulting in the Strategic Environmental
Assessment screening report. 
3.2 Rationale for Recommendations made in Section 2 
3.2.1 By approving the draft Guidance for public consultation, the Committee will
ensure that wider input can be made to the interpretation and information
requirements set out in the Guidance from the expertise and experience of
communities, renewable energy providers, NGOs and key agencies. This will
help to provide a robust framework to ensure complete, consistent information
for fully informed decision-making. Members may provide further input during
this public consultation period if desired and the resultant amended Guidance
will be further subject to committee approval and adoption. 
4. Impact and Value Assessment 
https://www.pkc.gov.uk/media/53970/Renewable-and-Low-Carbon-Energy-
Supplementary-
Guidance/pdf/Renewable_and_Low_Carbon_Energy_Supplementary_Guidan
ce.pdf?m=1745935591020 
5. Appendices 
5.1 Draft Renewables Guidance (2025) 
5.2 SEA Screening Report 
Page 76 of 128

Page 77

Renewable and Low
Carbon Energy
Planning Guidance
Consultation Draft
2025  
Appendix 1
7
Page 77 of 128

Page 78

Contents
1. Introduction .............................................................................. 1
1.1 Background ...................................................................... 1
1.2 Addressing NPF4 and LDP2 Policy Criteria ......................... 1
1.3 Preparing Submissions ..................................................... 1
1.4 Submitting Applications .................................................... 3
2 Renewable, Low Carbon and Zero Emissions Technologies ......... 4
2.1 Wind ................................................................................ 4
2.2 Hydropower...................................................................... 4
2.3 Enabling works including grid infrastructure ....................... 5
2.4 Energy storage .................................................................. 5
2.5 Solar Arrays ...................................................................... 5
2.6 Bioenergy ......................................................................... 6
2.7 Negative emissions technologies and carbon capture ........ 6
2.8 Co-location ...................................................................... 7
3 Planning Considerations ........................................................... 7
3.1 Socio-Economic Impacts .................................................. 7
3.2 International and National Designations ............................ 8
3.3 Impacts on Communities and Individual Dwellings ............ 8
3.4 Landscape and Visual Impacts ....................................... 10
3.5 Public Access, Recreation and Scenic Routes .................. 21
3.6 Aviation and Defence Interests ....................................... 21
3.7 Telecommunications and Broadcasting Installations ....... 22
3.8 Roads and Transport ...................................................... 22
3.9 Historic Environment ...................................................... 23
3.10 Hydrology, Water Environment and Flood Risk ................. 24
3.11 Biodiversity .................................................................... 26
3.12 Trees, Woods and Forests ............................................... 32
3.13 Hazardous Installations .................................................. 33
3.14 Construction Impacts .................................................... 34
3.15 Soils .............................................................................. 34
3.16 Cross Boundary Applications .......................................... 37
3.17 Decommissioning & Restoration ..................................... 38
3.18 Renewable Energy Generation and Greenhouse Gas
Emissions Reduction Targets .......................................... 39
3.19 Grid Capacity ................................................................. 40
3.20 Cumulative Impacts ....................................................... 40
3.21 Permission Lifetime and Extensions ................................ 41
4 Appendices ............................................................................ 43
4.1 NPF4 and [LDP2] Policies ............................................... 43
4.2 Construction Method Statement Template ...................... 45 
Page 78 of 128

Page 79

Renewable and Low Carbon Energy Guidance          1 
1. Introduction
1.1 Background
This document sets out the key considerations in the Development Plan for
renewable energy applications. The Development Plan includes National
Planning Framework (NPF4) and Perth & Kinross Local Development Plan
2019 (LDP2). All policies in NPF4 apply. Policies in LDP2 apply where they
are not incompatible with NPF4. This includes parts of Policy 33:
Renewable and Low Carbon Energy as set out in Appendix 1. 
NPF4 Policy 11: Energy is strongly supportive of renewable and low carbon
energy technologies, recognising – alongside other key NPF4 policies – the
need to address the climate crisis through supporting the move to net zero.
Significant upscaling in renewable energy technologies and infrastructure
is needed to meet renewable energy generation and greenhouse gas
emissions reduction targets. 
Guidance is provided here on policy interpretation, how impacts are
expected to be avoided and minimised, and the information that is to be
submitted with planning applications.  The Guidance will be a material
consideration in the determination of planning applications and will help
inform any Perth & Kinross Council (PKC) consultations on Energy Consent
Unit (ECU) applications.
1.2 Addressing NPF4 and LDP2 Policy Criteria
The Guidance provides information in relation to each of the criteria in
NPF4 Policy 11. Relevant additional criteria contained in LDP Policy 33 are
also included for consideration and are set out in Appendix 1. Other
relevant NPF4 and LDP2 policies and associated guidance are referenced
and should be addressed in submissions as relevant. 
Each policy section in this guidance contains:
• information relevant to all technologies
• additional advice specific to each technology.
Applicants should apply both the general and technology specific advice.
Proposals must address NPF4 and LDP2 as a whole and all relevant
policies. The applicability of policies and guidance will be relative to the
scale, location and nature of the proposal.
Spatial Guidance
NPF4 Policy 11(b) reaffirms that wind farms will not be acceptable in
National Parks and National Scenic Areas. LDP2 Policy 33D: Spatial
Framework for Wind and the associated map no longer apply. 
1.3 Preparing Submissions
Applicants should refer to the Council’s website for information on the
application process, fees and submission requirements including
application checklists. A pre-application enquiry is strongly advised to help
ensure appropriate and proportionate information. 
Information on existing renewable installations is available on the
Renewable energy proposals map
Small scale renewable energy generation technology
Small scale renewable generation can provide clean energy for individual
homes, businesses, and community-scale projects. Examples include
ground and air source heat pumps, roof-mounted solar, domestic/small
scale wind. Small scale schemes should consider key impacts on amenity,
air quality, landscape and visual impact, and if there are any particular
sensitivities or designations within the site/surrounding area including
birds, protected species, protected areas, and heritage interests. 
Micro-renewables with an output less than 50kW electricity or 45kW
thermal within the curtilage of a dwelling may be covered by permitted
development rights (with limits and conditions), but proposals in a
conservation area or where heritage assets are affected will need planning
permission and/or listed building consent. 
Page 79 of 128

Page 80

Renewable and Low Carbon Energy Guidance          2 
• Circular 1/2024 (Domestic)
• Circular 2/2024 (Non Domestic)
• Renewable | Scottish Environment Protection Agency (SEPA)
• Micro-renewables | NatureScot
• Managing Change in the Historic Environment: Micro-renewables |
HES
• What work needs a building warrant? | PKC
Major Applications
Major developments are subject to additional requirements including Pre-
Application Consultation with relevant communities and affected parties.
Major applications include all developments in Schedule 1 of the EIA
(Scotland) Regulations 2017, and all electricity generating developments
over 20MW, or extensions resulting in a development over 20MW.
• Major Planning Applications (PKC)
EIA Developments
Environmental Impact Assessment (EIA) is a process which identifies and
helps address significant environmental effects. Applicants are strongly
encouraged to request a screening opinion at an early stage to ascertain if
an EIA will be required. 
• EIA Guidance (PKC) 
• EIA Guidance (Scottish Government)
• Circular 1/2017 EIA Regulations (Scottish Government)
• EIA Guidance | NatureScot
• EIA Guidance | Historic Environment Scotland
National Development
Strategic Renewable Electricity Generation and Transmission Infrastructure
is identified as National Development. This includes: 
• Electricity generation and storage from renewables exceeding 50MW
capacity
• Electricity transmission lines, cables and interconnectors of 132kv or
more
• Infrastructure supporting high voltage lines, cables and
interconnectors including substations
Pumped storage hydro infrastructure that would otherwise be a major
application is identified as National Development.
Applications for national developments and network projects are made to
the Scottish Government Energy Consents Unit. This guidance is relevant
as Perth & Kinross Council is a statutory consultee for Energy Consent
applications within Perth & Kinross.
• Energy Infrastructure |Scottish Government
• Energy Consents Guidance | Scottish Government
• Energy Consents Unit Website | Scottish Government
• Applications to the Scottish Ministers under s37 of the Electricity
Act 1989 without an EIA Report
• Standard Onshore Wind Conditions (S36) | Scottish Government
Applicants to the ECU are encouraged to engage with PKC as consultee at
an early stage. Where necessary PKC will submit a tracked changes version
of the standard conditions for Wind to Scottish Ministers with
recommended and justified amended or additional conditions to ensure
proposals accord with the Development Plan. New requirements for
consultation may be introduced during the lifetime of this guidance.
Additional Requirements
Further permissions including building warrants, listed building consents
or environmental licences are additional to planning permissions.
Information to inform a Habitat Regulations Appraisal may be required for
any application that may affect a European Site. 
Page 80 of 128

Page 81

Renewable and Low Carbon Energy Guidance          3 
1.4  Submitting Applications
Submissions should address:
• The written advice in this Guidance
• The policies in NPF4
• The policies in LDP2 and associated guidance where relevant.
• The additional relevant assessments and surveys indicated
throughout the Guidance.
• Relevant information from assessments or licence applications
required by external bodies 
All submissions should provide:
• Capacity of renewable energy in kW / MW for all generation,
transmission, distribution and storage proposals
• Number, design, specifications and description of renewable energy
technology and expected operational lifespan
• Site photos and/or visual representation of the installation
• Red line of the site including all areas of the development
Submissions for applications except micro-renewables should provide a
plan of the site, and surrounding area showing where relevant:
• Proposed permanent and temporary infrastructure including all
plant and buildings, cable and pipeline routes, tracks, compounds,
excavations and abstractions.
• Grid connection location and route; or route of heat network
• Nearest receptors including buildings, dwellings, roads, and
recreation areas and routes
• Onsite, adjacent and connected environmental sensitivities
including: watercourses; waterbodies; water supplies and
abstractions; peatland, carbon rich soils, habitats; trees, woodlands
and natural heritage designations; and historic environment assets. 
Page 81 of 128

Page 82

Renewable and Low Carbon Energy Guidance          4 
2 Renewable, Low Carbon and Zero
Emissions Technologies
2.1 Wind
Wind plays a significant role in the renewable energy mix with potential
contributions to producing clean energy through the siting of the right
turbines in the right place including new sites, and repowering/extending
existing sites. Height of turbines is measured by height to blade tip (hbt) or
to hub.
An EIA may be required for any turbine over 15m (hub height), more than
two turbines of any height, or in a sensitive area.
There are a range of different wind power proposals in terms of scale:
• Fixed micro turbines: fixed on buildings. These are building-level
solutions and may not be efficient, or suitable, in all locations.
Limited permitted development available for detached
dwellinghouses. 
• Free standing micro turbines: up to 15m hbt and <50kW are suitable
for rural domestic/agricultural use and are potentially covered by
permitted development rights (PDR) for domestic use. PDR is limited
and subject to prior notification and approval.
• Small turbines: 15m-30m hbt will require planning permission if over
50kW or not covered by PDR. Foundations and underground cabling
may be required.
• Medium turbines: 30m-50m hbt can have significant impacts if
poorly sited and will require planning permission.
• Large turbines: >50m hbt. Large turbines require deep foundations,
turbine delivery, crane pad construction and electricity
infrastructure including transformers. Individual turbines can be
sized 200+m in height with larger blades and a greater energy
generation capability and will require planning permission 
1 Reservoir (Scotland) Act 2011 reduced this to 10,000m3 but is not yet in force
• Wind farms: 3 or more turbines over 30m. Greater land take and
infrastructure including substations and grid connections. Wind
farms can vary in scale from a small number of turbines to
proposals for a large array and will require planning permission. 
• Renewable | Scottish Environment Protection Agency (SEPA)
• Onshore wind energy | NatureScot
• Historic Environment Policy for Scotland | Historic Environment
Scotland
• Circular 1/2024 Permitted Development Rights (Domestic)
• Circular 2/2024 Permitted Development Rights (Non Domestic)
• Standard Onshore Wind Conditions (S36) | Scottish Government
2.2 Hydropower
Hydropower has a high level of efficiency and predictability and even small-
scale hydropower can provide a reliable source of electricity to support
rural communities and business.
All Hydropower installations require planning permission and include:
• Impoundment: a dam holding back a large head of water allowing
water flow, and energy production, to be regulated. Impoundment
with capacity >25000m3 will need to be registered with SEPA as a
reservoir.1 
• Pumped Storage Hydroelectric (PSH): where water can be pumped
back up to an impoundment dam for energy storage. These can be
on an open waterbody or in closed artificial storage ponds.
• Run of River: a proportion of water flow is diverted via a weir to pass
through a penstock to a powerhouse and discharged back into the
watercourse. The components of an installation will vary depending
on location and vertical drop (head) and may require penstocks,
lades, weirs, and water drawn from multiple sources.
Note that proposals for PSH dams or associated infrastructure that would
otherwise be considered major applications are national development. 
Page 82 of 128

Page 83

Renewable and Low Carbon Energy Guidance          5 
An EIA may be required depending on the scale/location of the proposal,
including in sensitive areas. All National Development applications will
require an EIA (see Section 1.3 Preparing Submissions).
A water use (CAR) licence under the Water Environment (Controlled
Activities) Regulations 2011 will be required for all applications. This may
include impoundment and abstraction licences. Engineering works
including where penstock routes or tracks cross water courses will also
require SEPA authorisation. Applicants should contact SEPA at an early
stage to discuss requirements, check whether the scheme is licensable,
and progress both applications concurrently. Proposals will need to meet
SEPA criteria to be provisionally acceptable to SEPA.
• Hydropower | SEPA
• Hydroelectric power | NatureScot
• Historic Environment Policy for Scotland | Historic Environment
Scotland
2.3 Enabling works including grid infrastructure
To facilitate new or extended generation capacity enabling works may also
be required. This includes grid infrastructure such as transmission and/or
distribution network upgrades. For the Perth and Kinross Council area,
SSEN are both the transmission and distribution network operators.
PKC will be consulted or notified on new transmission or distribution
infrastructure and ECU applications are expected to demonstrate
compliance with NPF4 and LDP2 policies and this guidance document. 
Grid infrastructure works may involve new and/or upgraded infrastructure
including overhead and underground cables, overhead lines on wooden
poles or steel towers, and electricity substations. There are currently
several SSEN transmission upgrade ‘pathway to 2030’ projects within the
PKC area. 
Connections to the grid may have adverse impacts such as habitat loss
and fragmentation, impacts on the water environment, bird collision risk
and significant visual impacts. NPF4 Policy 11e highlights that in the case
of proposals for grid infrastructure, consideration should be given to
underground connections where possible. This is subject to consideration
of impacts on archaeology and the natural environment.
NPF Policy 11(e) states that grid capacity will not constrain applications for
renewable energy, however applicants connecting to the grid should
discuss connection with the relevant network operator at an early stage.
To enable the full implications of applications to be understood applicants
should indicate the route and location of infrastructure to be used to
connect to the grid within the site, including transformers, substations and
associated fencing and access. The Council will need to agree the
connection point and method of connecting to the grid before
commencement. For section 37 applications provision of the above
information will inform the Council’s consultation response.
2.4 Energy storage
Energy storage enables energy generated from renewable sources to be
stored and released when most needed. Energy storage can maximise
efficiency of intermittent technologies such as wind and solar. Examples
can include battery storage, pumped storage hydro and hydrogen
generation from renewable energy.
Large-scale battery energy storage systems (BESS) are being used to
balance energy demand and supply across the UK energy network either as
stand alone or in association with solar or wind installations. For the
purposes of National Planning Policy, battery storage is considered to be
generation. Battery Storage guidance is in preparation by Scottish
Government. 
Storage proposals co-located with other renewable technologies are
supported as they improve efficiency and reduce energy loss. 
Battery Energy Storage Systems | SEPA
2.5 Solar Arrays
Electricity from solar photovoltaic panels (Solar PV) or hot water from solar
heat collectors (Solar Thermal) provide or supplement energy needs with
Page 83 of 128

Page 84

Renewable and Low Carbon Energy Guidance          6 
low visual and environmental impacts and can utilise unused or underused
roof-space or land. 
Solar Thermal: usually roof mounted, utilises heat from the sun through a
heat exchanger to supplement hot water or central heating.
Solar PV: produces electricity from photovoltaic panels and is useful for
supporting domestic use, supporting or supplementing other low carbon
technologies such heat pumps, and providing energy to the grid. Forms
include:
• Roof mounted PV: solar panels, PV roof tiles, flexible panels, and
wall mounted PV. Permitted development rights exist for domestic
and non-domestic microgeneration
• Ground mounted PV: range from domestic scale to large solar farms
and involve PV panels, mounting structures, fencing, lighting and
CCTV, inverters, cabling, and transformers, and can take up a large
amount of land.
o Microgeneration <50kW arrays are useful for domestic or
agricultural use with limited infrastructure. Limited PDR are
possible for these schemes.
o Solar Farms >50kW will require planning permission and can
have a greater impact from land take and use of infrastructure
including transformers, inverters and fencing.
o Large scale solar farms over 0.5ha or in a sensitive area may
require an EIA.
Key information for solar arrays:
• Renewable | Scottish Environment Protection Agency (SEPA)
• Solar energy | NatureScot
• Managing Change in the Historic Environment: Micro-renewables |
HES
2.6 Bioenergy
Bioenergy refers to the burning of organic matter (biomass) or breakdown of
organic matter (anaerobic digestion - AD) to produce heat and energy. The
most efficient use of bioenergy is to provide combined heat and power
(CHP) for industrial or heat network use. AD can also produce synthetic gas
for use in CHP or transport. Where demonstrated to be low carbon or zero
emission or bioenergy “associated with negative emissions technology”
(BECCS) such proposals are supported by NPF4 Policy 11. Bioenergy
proposals must therefore comply with strict land and greenhouse gas
criteria to be considered low carbon including harvesting, processing,
storage and transport emissions of feedstock and the use of carbon capture
technology where possible. 
To protect soils and woodland and to maximise GHG savings, bioenergy
proposals must source UK feedstocks only from:
• Primary waste sources such as brash, manure
• FSC sustainable certified products 
• Short rotation coppice or energy crops on:
o  class 4.1 – 6.01 land on the land capability for agriculture
1:50,000 maps
o Class 0 mineral soils on the Carbon and Peatland Map; or
• Short rotation forestry in accordance with the Forest & Woodland
Strategy 
• Bioenergy Policy Statement (draft) | Scottish Government
2.7 Negative emissions technologies and carbon
capture
NPF4 defines negative emissions technologies (NETs) as “an emerging field
of technologies that remove greenhouse gases from the atmosphere and
utilising carbon capture and storage sequester them permanently.”
Examples of technologies include:
• Carbon capture, utilisation and storage (CCUS) which captures
carbon dioxide generated by large-scale energy intensive processes,
and transports it for permanent storage underground
• Forms of Direct Air Capture with Carbon Storage (DACCS),
• Bioenergy with Carbon Capture and Storage (BECCS), or
• Other more experimental means such as enhanced weathering or
biochar.
Page 84 of 128

Page 85

Renewable and Low Carbon Energy Guidance          7 
2.8 Co-location
Co-location of more than one renewable technology can provide benefits
such as using energy storage to deliver energy to the grid when needed, and
potentially reduce land-take and environmental impacts. Co-location is
supported subject to policy considerations including landscape and land
use compatibility.
LDP2 Policy 33(i) requires all proposals to consider whether onsite energy
storage is suitable for their site. 
All major and EIA proposals should set out the energy storage opportunities
that have been explored and reasons for decisions taken on co-locating
energy storage.
3 Planning Considerations
The following considerations and guidance follow the requirements set out
in NPF4 Policy 11 with additional considerations in LDP2 Policy 33. The list
of considerations and their source are contained in Appendix 4.1.
3.1 Socio-Economic Impacts
Key Policies:
• NPF4 Policy 11(c)
• NPF4 Policy 25: Community Wealth Building
Key Guidance: 
• Big Place Conversation 2023 Results
• Local Place Plan Register
• Community Benefits Toolkit | Local Energy Scotland
• Good practice principles for Community Benefits from Onshore
Renewable Energy Developments (2019) | Scottish Government
• Shared Ownership | Local Energy Scotland
• Community Funds for Transmission Infrastructure | UK Government
• Community Energy Generation Growth Fund | Local Energy Scotland
All proposals
“ Development proposals will only be supported where they maximise
net economic impact, including local and community socio-economic
benefits such as employment, associated business and supply chain
opportunities.„ NPF4 Policy 11(c)
All local proposals should demonstrate a commitment to maximising the
net economic impact addressing the elements in Policy 11(c). 
All major and EIA proposals must provide a statement setting out measures
taken or committed to, which maximise net economic benefit including
local benefits and to the wider Perth and Kinross economy. Scottish
Government guidance is expected to be released during lifetime of this
guidance which should be adhered to. 
Page 85 of 128

Page 86

Renewable and Low Carbon Energy Guidance          8 
NPF4 Policy 25: Community wealth building sets out the positive socio-
economic impacts of proposals that will be supported. Discussions with
community bodies and reference to local place plans and/or community
action plans will help inform the development of socio-economic
statements. NPF4 Policy 25 also states that development proposals linked
to community ownership and management of land will be supported.
All large wind and wind farm applications and all hydropower applications
should consider their land use impacts on other commercial users. For
example, wind farms can disrupt airflow on neighbouring wind farms, and
hydropower developments may affect flows for other hydropower,
agricultural or recreational business uses.
Community Ownership and Community Benefits 
Community benefits are voluntary monetary or other benefits unrelated to
the impacts of the project, provided by the developer. These offer
opportunities to support community action plans such as through
discounted supply of free electricity for local use, or share of ownership. 
However, monetary benefits are not material to planning and will not be
taken into account in decisions on planning applications nor will
community ownership justify environmentally damaging proposals.
3.2 International and National Designations
International and National designations relate to National Parks,
landscape, biodiversity and geodiversity designations. National Parks and
landscape issues are addressed in chapter 3.4 on Landscape and Visual
Impacts and biodiversity and geodiversity in chapter 3.11 on Biodiversity
3.3 Impacts on Communities and Individual Dwellings
Key Policies:
• NPF4 Policy 11(e)(i): Energy
• NPF4 Policy 23(d): Health & Safety
• LDP2 Policy 33: Renewable and Low Carbon Energy
• LDP Policy 55: Nuisance from Artificial Light and Light Pollution
• LDP Policy 56: Noise Pollution
• LDP2 Policy 57: Air Quality
Key Guidance
• Guidance Biomass | SEPA
• Supplementary Guidance Air Quality | PKC
• Local air quality management policy guidance | Scottish
Government
• Wind Turbine Noise | Institute of Acoustics
All proposals
NPF4 11(e)(i) requires proposals to demonstrate through project design
and mitigation how impacts on communities and individuals are
considered including residential amenity, visual impact, noise, shadow
flicker. LDP2 Policy 33 also requires air quality to be addressed.
The operation and construction of most proposals can impact on amenity
through dust, odour, lighting, and vibration, and should be addressed in
addition to the main issues below. All Technologies should address the
impacts of noise generating equipment early during site selection and
siting, design and technical controls. Construction should be time-
controlled to limit impacts. 
Noise assessments should address sensitive receptors and demonstrate
that nearby residents’ enjoyment of their dwellings or gardens is not
adversely affected. Receptors in a rural environment may be more sensitive
to noise impacts. Cumulative assessments will be required where
equipment including substations, storage and transformers are located in
close proximity including from existing installations. All noise generated
from equipment should be acoustically insulated where possible and
where there is potential for a significant impact on receptors including
priority species. 
Where construction or security lighting is required, sensitive siting,
shielding and passive infrared technology should be used to minimise
impacts on residents.
Measures should be taken to reduce air borne emissions in construction,
transport and operation including abatement, utilising methane, reducing
Page 86 of 128

Page 87

Renewable and Low Carbon Energy Guidance          9 
transport distances, dust mitigation, using sustainable fuel sources and
adhering to the waste hierarchy. 
Wind
Shadow flicker and strobe effects from moving blades can create
distraction and have potential health effects on some individuals. Shadow
flicker occurs when blades rotate and cast a shadow over neighbouring
properties at certain times of day and year. Impacts should be avoided
primarily through site selection, siting and separation distances, and
design, with residual impacts mitigated through technical controls.
Applicants for large turbines and wind farms should identify dwellings that
may be significantly affected. This includes dwellings within 10 rotor
diameters distance and within 130 degrees either side of North taking into
account turbine height, topography and latitude. Impacts on affected
dwellings should be for no more than 30minutes per day or 30 hours per
year at any dwelling.
Noise impact will depend on distance, turbine design, topography,
prevailing wind direction and speed, and siting. Turbines may also have
temporary impacts from amplitude modulation: a ‘thump’ caused by the
movement of the blades through the air. 
Assessments should also be carried out for construction noise including
blasting for foundations and borrow pits where relevant. 
A Noise Impact Assessment (NIA) for receptors within a 35db contour of
turbines may be required and should be updated following any material
change in the proposed design. The Environmental Health team will help
identify requirements and the appropriate receptors and should be
engaged early in preparing submissions. Submissions for medium turbines
and above should show that noise will not exceed 35dB at noise sensitive
premises (LA90, 10min of 35dB, <=10m/s wind speed, at 10m height) – with
a 5dB penalty for any tonal noise generated. Assessments should be
undertaken in accordance with standard ETSU-R-972 and guidance. 
2 ETSU R 97 is due to be updated during 2025.
Large wind farms and complex cumulative impacts will be considered by
the Council. A cumulative assessment should demonstrate increases in
noise levels are acceptable. These will be required for large turbines, wind
farms, and for small turbines where there are other wind installations
within 2km.
Hydro
Noise may be an issue from powerhouses. Providing the powerhouse
location and manufacturer’s data will allow the Environmental Health team
to advise potential impacts, noise limits and any Noise Impact Assessment
(NIA) requirements. 
Vibration from powerhouse operation may also affect nearby dwellings. The
design, construction and maintenance of powerhouses should ensure
standards are not exceeded (see Table 1 of BS 6472-1:2008).
Solar
Noise may arise from poorly maintained tracking mechanisms and
construction particularly from pile driven foundations, and potential
operational noise from inverters and transformers. Proposals should
ensure nearby dwellings are not adversely affected. An assessment and
mitigation, such as limiting construction times, acoustic housing of
transformers and maintenance plans may be required. 
Glint and Glare is a limited issue with modern PV panels, but submissions
for solar farms should show no adverse impacts on sensitive receptors
including residential dwellings and roads taking into account tracking
movements and seasonal adjustments. Glint and Glare assessments will
be required where properties within 1km to the east and west of the
development have line of sight of the solar panels. Glint and glare can be
mitigated through siting, screening and limiting the angle of panels.
The visual impact of security lighting should also be minimised through
sensitive siting, passive infra-red technology and shielding.
Page 87 of 128

Page 88

Renewable and Low Carbon Energy Guidance          10 
Energy Storage
Noise impact from the operation of battery units including cooling systems,
inverters and transformers will need to be considered, particularly where
these are proposed close to residential properties. Providing the location of
associated infrastructure and manufacturer’s data will allow the
Environmental Health team to advise on potential impacts, noise limits
and any Noise Impact Assessment (NIA) requirements. This will include
cumulative assessments of sites situated near substations, solar farms or
other energy storage sites. A condition to control noise will be applied. 
Sites should avoid impacts on sensitive receptors in the first instance.
Acoustic fencing or bunding will be required to address residual impacts. 
Bioenergy
Biomass installations can increase local concentrations of particulate
matter (PM) and Nitrogen Dioxide (NO2). For applications over 50kW an Air
Quality Assessment (AQA) may be required, and will be required within the
Perth Air Quality Area. SEPA guidance should be referred to for installations
over 20MW. All biomass applications should include:
• boiler size (kW)
• manufacturer’s brochure. 
• Stack height above ground level
• Stack internal diameter
• Height of nearby buildings within 5 times the stack height including
the boiler building
• Maximum emission rates for NO2 and PM10 in g/s
When choosing a location for Biomass neighbouring properties, relative
heights, window locations, topography and dispersion effects should be
taken into account. Dispersion modelling may need to be mapped for large
installations. Manufacturer’s recommendations must be adhered to with
regards the fuel type and moisture content and covered fuel storage. 
Gases produced from anaerobic digestion and associated CHP can impact
on air quality. Most proposals will need an AQA and to demonstrate
exhaust emissions and flare operations adhere to SEPA Waste Guidance.
AD plants should re-use their own low grade waste heat where possible
3.4 Landscape and Visual Impacts
Key Policies:
• NPF4 Policy 11: Energy
• NPF4 Policy 4: Natural Places
• NPF4 Policy 7: Historic Assets and Places
• NPF4: Policy 8: Greenbelt
• LDP2 Policy 39: Landscape
Key Guidance:
• Planning and development: landscapes | NatureScot
• Planning and development: renewable energy | NatureScot
• Wind farm impacts on landscape | NatureScot
• PKC Supplementary Guidance - Landscape 
• Guidance on Aviation Lighting Impact Assessment | NatureScot
Landscape Policies
• LDP2 Policy 39 sets out locally important impacts to address in
submissions including factors such as local distinctiveness and the
experience of the night sky. 
• NPF4 Policy 4(a) states that unacceptable impacts on the natural
environment will not be supported. This includes landscape
impacts.
• NPF4 Policy 11(b) bars wind farms from National Parks and National
Scenic Areas. The relevant National Park should be referred to for
guidance on other renewable development. 
• NPF4 Policy 11(d) refers applicants to Policy 4 for impacts on
international and national designations, this includes landscape
designations.
• NPF4 Policy 11(e)(ii) states significant landscape and visual impacts
from all forms of renewable energy proposals must be addressed. 
• NPF4 Policy 4(c) sets out requirements in relation to impacts on
National Parks and National Scenic Areas 
• NPF4 Policy 4(d) addresses local landscape areas. 
• NPF4 Policy 4(g) addresses Wild Land Areas and wild land impact
assessments. 
• NPF4 Policy 7 includes landscape protections of historic features
Page 88 of 128

Page 89

Renewable and Low Carbon Energy Guidance          11 
• NPF4 Policy 8 addresses applications in the Greenbelt
Interpretation of Policy 11(e)(ii)
“ Significant impacts… are to be expected from some forms of
renewable energy. Where such impacts are localised and/or
appropriate design mitigation has been applied, they will generally be
considered to be acceptable„ NPF4 Policy 11(e)(ii)
Some forms of renewable energy:  refers to wind installations only.
Localised: refers to the immediate neighbouring location only.
Appropriate design mitigation: requires that all reasonable mitigation has
been applied to reduce significant impacts taking into account the factors
in LDP2 Policy 39 including the local importance and use of the landscape,
and the qualities of landscape character types and designated landscapes.
Generally be considered acceptable.  Acceptability is subject to the tests
in NPF4 Policy 4 including Policy 4(a) and consideration of matters
addressed in other policies including greenbelt, heritage, and quality of
place. 
Interpretation of Greenbelt Policy
NPF4 Policy 8 Greenbelt sets out requirements to be met for proposals in
the greenbelt informed by LDP2 Policy 43. These are additional to NPF4
Policy 11 and include the following:
“reasons are provided as to why a green belt location is essential and
why it cannot be located on an alternative site outwith the green belt;„
LDP2 requires a statement setting out reasons why a green belt location is
essential and must identify the search area and the site options assessed 
“the purpose of the green belt at that location is not undermined; „
The purpose of the greenbelt in LDP2 is to protect and enhance the
character, landscape setting and identity of settlements
“the proposal is compatible with the surrounding established countryside
and landscape character;
the proposal has been designed to ensure it is of an appropriate scale,
massing and external appearance, and uses materials that minimise
visual impact on the green belt as far as possible; and
there will be no significant long-term impacts on the environmental
quality of the green belt„
Long-term impacts are less than permanent and those beyond short-term
changes such as construction or as planted screening develops. This is
regardless of whether the impacts are theoretically reversible. Wind
proposals are assumed to be a permanent change. 
All Proposals
Renewable energy installations can impact on the character of the
landscape as a result of the design, size, and layout of the installation, and
associated infrastructure against the landscape. 
Visual impacts also arise from people’s perception of installations as seen
from homes and public locations (receptors). 
All submissions should consider whether the proposal will affect:
• The landscape character taking into account scenic value, and
areas sensitive due to historic and cultural or recreational value.
• Impacts on the landscape of, and views from and to Local
Landscape Areas, National Parks, National Scenic Areas, Wild Land
Areas
• Impacts on the setting of, and views to and from, scheduled
monuments, historic battlefields and Gardens and Designed
Landscapes 
• Views to iconic and locally important landmarks including the
Highland Boundary Fault and iconic viewpoints
• Views from important viewpoints including Munros, and viewpoints
indicated on OS maps.
• Views from neighbouring receptors including dwellings, core paths
and other popular recreation routes, Principal Tourist and Amenity
Routes and recreation areas
• Landscape character of the greenbelt 
Page 89 of 128

Page 90

Renewable and Low Carbon Energy Guidance          12 
Submissions should also address any cumulative impact on the issues
above. See section 3.20 
Landscape and Visual Impact Assessments (LVIA) 
The assessment required of the landscape and visual impact of the
proposal will be proportional to the scale and nature of the development
and the sensitivity of the location ranging from simple site photographs
and design drawings, through Landscape and Visual Appraisals (LVA)
and Landscape and Visual Impact Assessments (LVIA). The Planning
Authority will help identify the extent of assessment required, the zone of
theoretical visibility (ZTV) and relevant viewpoints and receptors. 
All appraisals and assessments must follow: 
• Guidelines for Landscape and Visual Impact Assessment (3rd ed)
| The Landscape Institute 
Small and medium wind turbines submissions will be assessed in
accordance with:
• Assessment of The Impact of Small Scale Wind Energy Proposals
on the Natural Heritage | NatureScot 
Large Turbines and Wind Farm submissions must adhere to:
• Visual Representation of Wind Farms | NatureScot
• Siting and designing wind farms in the landscape | NatureScot
The Landscape character of Perth and Kinross is described in:
• Landscape Study to Inform Planning for Wind Energy| DTA
• Landscape Character Type Descriptions | NatureScot. 
All assessments should take into account any changes in landscape
capacity since the publication of these studies using professional
judgement
Assessment information required
All proposals Site photographs, design details and
technology specifications
All photographs and visualisations should
clearly demarcate the site boundary including
access tracks.
Micro wind Basic ZTV and photomontages in sensitive
locations.
Small & Medium
turbines
Detailed design and location information and
visualisations. A 15km ZTV and LVA with
visualisations from key viewpoints
Large turbines & wind
farms
LVIA with a ZTV to a minimum of 20km.
Visualisations from key viewpoints in
proportion to proposal. Cumulative map of
proposals within 20km
Hydro Site photographs of watercourses and
affected construction areas. LVA for local
applications, LVIA for major, EIA or where
sensitive landscape affected
Solar Farms & Energy
Storage
Visualisations. LVA if affecting heritage or
landscape designation; LVIA for major, EIA and
cumulative assessment of both solar and
energy proposals
Enabling Infrastructure Visualisations. LVA if affecting a heritage
interest or landscape. LVIA for major, EIA
All proposals should demonstrate how landscape and visual impacts have
been mitigated through:
• Careful selection of site and route of tracks at design stage
• Considering the siting and design of infrastructure at an early stage
in consultation with communities and stakeholders
• Using design, materials, and colour that best fit with the built,
historic and natural environments
• Using scale appropriate to nearby buildings, trees, pylons and
landforms
• Siting infrastructure near existing structures
Page 90 of 128

Page 91

Renewable and Low Carbon Energy Guidance          13 
• Siting all turbines and large installations to avoid significant adverse
visual and landscape impacts as seen from Principal Tourist and
Amenity Routes
• Using existing topography, landscaping and natural screening to
minimise impacts
• Undergrounding of pipework, penstock and cabling where possible;
and the use of landscaping and natural screening where
undergrounding is not possible
• Timely restoration of tracks, trenches, construction compounds,
laydown areas and borrow pits to match the surrounding
environment
• Demonstration of effective mitigation through a Habitat
Management Plan or Landscape Management Strategy.
• Planted screening should be multilayered, and of sufficient height to
screen impacts through all seasons. 
Iconic Viewpoints and the Highland Boundary Fault
Major and EIA proposals including grid infrastructure visible from
important viewpoints including Munros and iconic viewpoints
should assess impacts on those views and provide visualisations 
The Highland Boundary Fault is a distinctive, topographical,
cultural and geological feature running through Perth and Kinross
which is sensitive to wind turbines on its top or, as seen from the
Lowlands side, in front of or on the fault slope itself. Visual
impact assessments will be required for large turbines and wind
farm proposals within 2km of the northern edge, and 5km of the
southern edge of this feature to demonstrate that views of the
skyline or natural beauty of this feature are not significantly
adversely affected. 
Page 91 of 128

Page 92

Renewable and Low Carbon Energy Guidance          14 
Landmark Features and Iconic Viewpoints
Dotted Line indicates potential visibility for wind turbines
Source: David Tyldesley and Associates (2010) Landscape
Study to Inform Planning for Wind Energy
Page 92 of 128

Page 93

Renewable and Low Carbon Energy Guidance          15 
National Scenic Areas and National Parks 
Under NPF4 Policy 11b wind farms proposed in National Scenic Areas
(NSAs) and National Parks will not be supported. 
Any turbine >12 m in an NSA needs planning permission and consultation
with NatureScot. Most turbines, hydro installations and hill tracks, and
other large installations can have adverse landscape and visual impacts at
a distance including across boundaries to both NSAs and National Parks.
Where in or visible from NSAs and National Parks submissions should
show they do not have a significant adverse impact on the special
landscape qualities of the designation or their gateways with reference to
the relevant guidance. Proposals will specifically be assessed in relation to
NPF4 Policy 4c.
See Guidance:
• The Special Landscape Qualities of LL&TNP (NatureScot, 2010)
• The Special Landscape Qualities of Cairngorms National Park
(NatureScot, 2010)
• The Special Qualities of National Scenic Areas (NatureScot, 2010) 
Wild Land Areas 
NPF4 Policy 4(g) sets out the requirements for assessment in relation to
Wild Land Areas and the requirement for a Wild Land Impact Assessment
to demonstrate minimisation of significant impacts. Policy 4(g) is subject to
the qualification in policy 4(a).
• Wild Land Area descriptions and assessment guidance |
NatureScot.
Local Landscape Areas 
Local Landscape Areas (LLAs) in Perth & Kinross and neighbouring
authorities should be considered of regional importance in LVIA. Views
both to and from these landscapes should be addressed. Significant
impacts on these areas must be localised or appropriately mitigated with
reference to Policy 4(a), 4(d) and PKC Supplementary Guidance on
Landscape.  
Page 93 of 128

Page 94

Renewable and Low Carbon Energy Guidance          16 
Page 94 of 128

Page 95

Renewable and Low Carbon Energy Guidance          17 
Wind
For the siting and design of all wind turbines above 15m in height and
associated infrastructure, applicants will be assessed against:
•  Siting & Designing Wind Farms in the Landscape | NatureScot 
• Guidance on Aviation Lighting Impact Assessment | NatureScot
This will help submissions to address:
• The fit of turbines within the landscape depending on the number,
scale, pattern and colour of turbines against the scale, form,
complexity and cover of the landscape
• The prominence of turbines including on ridge lines, on loch and
river shores and in areas of wildness, remoteness or tranquillity
• The siting of turbines on the site in relation to each other, other
structures and site topography, as viewed from different receptors
• The location and fit within the pattern of existing turbine(s)
• The relation of turbine(s) in size, character and location in the
context of nearby dwellings and other buildings, monuments,
conservation interests and locally important natural features
• The cumulative impact of all sizes of turbines with existing and
proposed turbines and other infrastructure including pylons
• The landscape and visual impact of foundations, transformers,
cranes, crane pads, tracks, construction compounds, borrow pits,
and grid connection infrastructure
• The impacts of aviation lighting on the night sky.
Cumulative impacts from new turbines that risk coalescence between
existing wind farms or turbine clusters leading to a wind farm landscape
should be avoided. Repowering applications may provide an opportunity to
reduce existing cumulative impacts by removing or redesigning elements in
the landscape. 
A Cumulative Landscape and Visual Impact Assessment (CLVIA) will be
required for large turbines and wind farms where there are existing, or
proposed turbines within a cumulative zone agreed with the Planning
Authority. CLVIAs should adhere to NatureScot guidance Assessing the
Cumulative Impact of Onshore Wind Energy Developments (2021) and
should address:
• All existing, consented or submitted wind applications
• Other large or tall industrial features including pylons
• Structures outside the Council area, including for sequential
impacts
• Effects on landscape character; and the qualities of landscape
designations including Local Landscape Areas and Wild Land
• Combined and successive cumulative impacts
• Sequential impacts on amenity, tourist and recreational routes
• Impacts of infrastructure such as tracks, crane pads and borrow
pits.
Proposals for small and medium turbines should consider other existing
turbines within 1km. Siting and design choice will help avoid creating
confusion or clutter through different designs or heights.
The siting and design of micro wind turbines should use scale, design,
materials and colour that best fit with the surrounding environment and
any other turbines. Micro wind is best sited in association with existing
buildings or structures and can be located carefully or screened to avoid
visual impacts.
Hydro
Impacts from hydro schemes will depend on the sensitivity of the location
and the extent of infrastructure. National Parks, NSAs, LLAs, and WLAs
should be avoided if impacts cannot be sufficiently mitigated. 
The contrast of hill tracks and penstock routes with the existing landscape
during and post construction should be minimised through siting, such as
using natural features like narrow valleys to reduce the extent of
construction required and using existing tracks or alternative delivery
methods. 
Impacts of artificial materials in semi-natural and rural environments
should be minimised by:
• ensuring a low profile of in-river structures
• choosing appropriate materials and finishes of buildings, railings,
fencing and pipework 
• reusing or restoring historic weirs. 
Page 95 of 128

Page 96

Renewable and Low Carbon Energy Guidance          18 
Any visible pipework including pressure release valves can be aligned with
land use patterns and vegetation, and transformers and associated fencing
can be screened. Powerhouses should be placed underground, in existing
buildings, or in new buildings in keeping with local character. 
Cumulative impact assessments may be required where the proposal is
affecting a landscape designation, and/or other hydro installations or
proposals are in the ZTV.
• Hydro Schemes and Natural Heritage | NatureScot
• Guide to Hydro Construction Good Practice | NatureScot
Solar
Micro-generation solar installations will have minimal impacts but should
demonstrate they do not have a detrimental impact on heritage features. 
Solar farm impacts may include the visual impacts of the panels and
frames themselves although due to the sunlight absorbing nature of panels
and their low profile, from a distance they can seem like water or a
ploughed field. 
The size and layout of the solar farm should be commensurate with the
surrounding landscape to reduce significant effects. Contours and
enclosure patterns of the landscape created by topography, field patterns,
paths, woodland, walls and hedges should be reflected and reinforced
through layout and landscaping. 
Local impacts including that of inverters and transformers, other electricity
infrastructure, and security fencing can be softened by use of topography
or planting as screening. 
Proposals must be set back from recreational routes and intervening native
vegetation introduced to ensure the experience of the wider countryside is
maintained. Screening landscaping should be selected and maintained to
ensure views on wider landscapes are not blocked. Any security lighting
must be on an infrared trigger only.
Except on brownfield land, hardstanding should be avoided wherever
possible.
• General pre-application and scoping advice for solar farms |
NatureScot
Cumulative impact assessments are required where there are other
existing or proposed solar or energy storage installations within the agreed
ZTV. This must also address sequential impacts along recreational or
tourist routes.
Energy Storage
Proposals should address landscape and visual impacts arising from the
battery storage/container units, transformers, inverters, switchrooms,
welfare units, fencing, substations, access tracks, water towers, and
security fencing. 
Due to the industrialised nature of battery storage proposals are best sited
immediately next to substations or associated renewable energy
developments. 
Industrial sites in the countryside and greenbelt risk having an
unacceptable landscape and visual impact. Impacts on the setting of
landscape and historic designations, recreational routes and settlement
character must be addressed. 
Local impacts can be softened by use of topography, bunds or planting as
screening but may need to be well set back from roads or recreation routes
in countryside settings. The existence of vertical infrastructure such as
pylons in the landscape do not necessarily result in a lesser impact of an
installation on the horizontal character of a setting or landscape,
particularly where situated at a distance. 
Proposals must be set back from recreational routes and intervening native
vegetation introduced to ensure the experience of the wider countryside is
maintained. Screening landscaping should be selected and maintained to
ensure views on wider landscapes are not blocked. 
Cumulative impact assessments are required where there are other
existing or proposed solar or energy storage installations within the agreed
ZTV. This must also address sequential impacts along recreational or
tourist routes.
Page 96 of 128

Page 97

Renewable and Low Carbon Energy Guidance          19 
Enabling Infrastructure
Proposals for substations should be associated with other industrial
infrastructure as far as possible, and screened with materials and
landscaping appropriate to the location. Refer to energy storage above. 
Routing options of new/extended/upgraded transmission or connection
lines should address impacts on landscape character types, local
landscape areas, settlement visibility and recreational and tourist routes.
Early engagement with PKC and NatureScot is essential.  
Page 97 of 128

Page 98

Renewable and Low Carbon Energy Guidance          20 
Source: David Tyldesley and Associates (2010) Landscape
Study to Inform Planning for Wind Energy
Page 98 of 128

Page 99

Renewable and Low Carbon Energy Guidance          21 
3.5 Public Access, Recreation and Scenic Routes
Key Policies:
• NPF4 Policy 11e (iii)
• LDP2 Policy 14: Open Space Retention and Provision
• LDP2 Policy 15: Public Access
• LDP2 Policy 33: Renewable and Low Carbon Energy
• LDP2 Policy 40: Green Infrastructure
Key Guidance
• Green & Blue Infrastructure Guidance | PKC
• Core Paths Plan | PKC
All Proposals
Large scale applications can impact on recreation through land take and
applicants should engage with recreational organisations to help identify
users and evaluate recreational value. LDP2 Policy 14A: Existing Areas
requires protection of areas of land with value to the community including
for recreational or amenity purposes including outside settlement
boundaries subject to limited exceptions. 
LDP2 Policy 15: protects all designated and well-used routes. Recreational
routes or access to recreational activities should be identified and adverse
impacts addressed including through provision of alternative routes. An
access management plan will help ensure safety. 
Infrastructure should be sited and designed to minimise impacts on views
from key locations for public access and recreation, as well as scenic
routes. Enhancement to recreational access or facilities should be
considered. See Section 3.4 on Landscape and Visual Impact for more
information.
Wind
Wind farms can have substantial visual impacts on recreational and
tourism use. Proposals should avoid having significant visual impacts on
views from the A9 corridor and iconic viewpoints. Submissions should
address impacts on views to National Park gateways, the Highland
Boundary Fault and local landmarks. 
Hydro
Hydropower can impact through visual impacts and access restrictions
during construction. Weirs should be designed and sited to address
impacts on, or enhance, recreational experience and consider
enhancements such as public access across weirs. Changes in water flow
may also affect water-based tourism and recreation. Submissions should
provide a notification plan for water releases affecting users.
Solar
Large solar farms may impact recreation through land take and disruption
to recreation routes. In addition to access considerations, submissions
should address views of and from local tourist landmarks and principal
tourist routes. 
Energy Storage, Bioenergy and Enabling Infrastructure
In addition to any access considerations, submissions should address
views of and from local tourist landmarks and principal tourist routes.
3.6 Aviation and Defence Interests
Key Policies:
• NPF4 Policy 11(e)(iv)
• LDP2 Policy 61: Airfield Safeguarding
Key Guidance
• Airfield Safeguarding Guidance | PKC
All Proposals
All tall structures, including construction cranes, turbines, flues and
flarestacks, can present a hazard to air navigation. Consultation is required
for applications within the safeguarding zone of Perth, Fife and Dundee
airports, or any Perth and Kinross airfield as shown on the Aviation and
Defence Safeguarding Map. Any proposed technical mitigation measures
will need to be agreed by the relevant authorities.
Page 99 of 128

Page 100

Renewable and Low Carbon Energy Guidance          22 
Wind
Wind turbines can disrupt communication and navigation, and along with
cranes and anemometers can interfere directly with aviation. Applicants
are encouraged to engage with the planning team and relevant aviation
bodies before committing to a site or design. 
Applicants should consult the airport or airfield operator where wind
proposals are located within the safeguarding zones of airfields and Perth,
Fife, Dundee or Edinburgh airports shown on the Aviation and Defence
Safeguarding Map. CAA and NATS will be consulted for all turbines.
The Ministry of Defence (MOD) will also be consulted on all applications
over 11m or with a rotor diameter of 2m and all wind applications within the
Munduff Hill weather radar safeguarding zone. Mitigation measures such as
lighting, siting and technical features will need to be agreed by the relevant
authorities and included in visual impact assessments.
Solar
Large arrays have limited potential for impacts on navigation from
reflection, glare and security lighting. The relevant aerodrome or airfield
operator should be contacted for any ground mounted Solar PV application
within the airfield safeguarding zones.
Applications proposing solar tracking systems will also require
consultation with Ministry of Defence (MOD), Civil Aviation Authority (CAA)
and National Air Traffic Services (NATS).
3.7 Telecommunications and Broadcasting
Installations
Key Policies:
• NPF4 Policy 11e (v) 
Wind
Interference with radio communication and local television and radio
reception should be assessed prior to development. Ofcom can provide
advice on relevant operators and the Joint Radio Company can undertake
screening for telemetry used by energy utilities. 
Developers will be expected to resolve any potential issue with the relevant
operators or, in the case of interference with TV and radio signals, with
individual occupiers.
3.8 Roads and Transport
Key Policies:
• NPF4 Policy 11(e)(vi) 
• NPF4 Policy 13: Sustainable Transport
• LDP2 Policy 33A(g)
• LDP2 Policy 60: Transport Standards and Accessibility
Requirements
Key Guidance
• National Roads Development Guide | SCOTS
• Transport Planning Guidance | PKC
All Proposals
Construction vehicles, delivery of infrastructure and materials, and
ongoing fuel deliveries can cause significant disruption to transport routes,
rural roads, and safety, amenity and air quality in towns and villages. Road
alignment or widening, and physical impacts on the road surface condition
will also need to be addressed. In consultation with the relevant road
authorities, a Transport Assessment, covering impacts on the road
network, and a Construction Traffic Management Plan (CTMP), are likely to
be required for large proposals. 
Transport assessments and associated CTMP should show adverse
impacts are avoided, mitigated or minimised including:
• Routes, timing, and number of vehicles for construction and
ongoing fuel, feedstock or digestate movements are designed to
minimise disruption
• Consideration of the cumulative impacts of fuel delivery where
routes are affected by existing HGV deliveries
Page 100 of 128

Page 101

Renewable and Low Carbon Energy Guidance          23 
• Sites are designed for safe access and operation including in
emergency situations
• Works and final installations are designed, sited and screened to
prevent distraction to passing drivers.
3.9 Historic Environment
Key Policies:
• NPF4 Policy 11(e)(vii)
• NPF4 Policy 7 (Historic Assets and Places)
• LDP2 Policy 33 (Renewable and Low Carbon Energy)
• LDP2 Policies 26-31 (Historic Environment Policies)
Key Guidance
• Historic Environment Policy for Scotland | Historic Environment
Scotland (HES)
• Managing Change: Setting | HES
• Managing Change: Micro-Renewables | HES 
• Planning Advice Note 2/2011 Planning and Archaeology 
• Interactive Heritage Map | PKC
• Listed Building Consent and Conservation Area Checklists | PKC
All proposals
Installation can affect the fabric and setting of historic interests and
underlying archaeology. Reducing energy consumption and improving
energy efficiency must be addressed before considering more intrusive
measures that installations that may have an adverse impact on the
historic character and interest. 
While some permitted development rights apply for the installation of
renewable energy measures in listed buildings or conservation areas, listed
building consent and/or planning permission will likely be required. 
Roof mounted technology and flues may impact on the historic fabric and
special interest of listed buildings, and must be carefully considered on a
case by case basis. In conservation areas they should be carefully installed
and discretely sited to protect the historic character or and appearance of
the area. 
The visual impact on heritage assets including historic battlefields, gardens
and designed landscapes, listed buildings, and conservation areas and
their settings must be taken into account in the development of renewable
energy projects. Large installations may affect the setting of or views
to/from heritage assets and will not be acceptable where they have
significant adverse effects, as assessed against NPF4 Policy 7. Landscape
and visual appraisals should clearly address potential adverse effects and
appropriate mitigation. 
All installations requiring ground disturbance should identify known
archaeology and the potential for archaeology across construction sites
through discussions with the Perth and Kinross Heritage Trust (PKHT).
Where known or potential archaeological resources may be affected, a
mitigation plan should be developed in association with PKHT. Mitigation
may include recording finds or providing enhancement for acceptable
proposals such as interpretative signage. 
Proposals with significant transport requirements for construction or
ongoing fuel delivery should also ensure historic structures are protected
from vibration, ground disturbance or overly heavy loads. 
There may be potential to incorporate existing historic buildings and
structures into proposals. Hydro proposals, for example, could include
sensitivity repair and reuse of historic weirs, waterwheels and mill lades. 
The use of existing ancillary buildings for heat pump plant rooms and
bioenergy could ensure new renewable proposals are more sensitive to
historic settings, where it is ensured that new pipework or vibrations will
not damage historic fabric. 
Page 101 of 128

Page 102

Renewable and Low Carbon Energy Guidance          24 
3.10 Hydrology, Water Environment and Flood Risk
Key Policies:
• NPF4 Policy 2(b): Climate Mitigation and Adaptation
• NPF4 Policy 11(e) (viii)
• NPF4 Policy 20: Blue and Green infrastructure
• NPF4 Policy 22: Flood Risk and Water Management
• LDP2 Policy 45: Lunan Lochs Catchment Area
• LDP2 Policy 47: River Tay Catchment Area
• LDP2 Policy 52: New Development and Flooding
• LDP2 Policy 53: Water Environment and Drainage
Key Guidance
• Guidance and advice notes | SEPA
• Flood Risk Standing Advice | SEPA
• Vulnerability Guidance | SEPA
• Diffuse pollution in the urban environment | SEPA
• Guidance on assessing the impacts of development proposals on
groundwater abstractions | SEPA
• Abstractions Guidance | SEPA
• Flood Risk and Flood Risk Assessments | PKC
• Flood Risk Management Plans | PKC
• SUDS manual C753F | CIRIA
• Engineering in the Water Environment Guidance | SEPA
All proposals: Hydrology and Water Environment
Activities affecting the water environment may require a Controlled
Activities Licence (CAR) licence from SEPA including in river engineering
work; this includes all hydropower applications and water source heat
pumps; and drainage. Authorisation  may also be required for abstraction
of water for construction, water storage or to de-water excavations, and
surface water and construction run-off. The planning team will consult
closely with SEPA to assess applications, identify conditions and co-
ordinate with CAR applications. SEPA guidance contains checklists to
assess whether proposals will be able to obtain a water use licence. 
See: CAR A Practical Guide | SEPA 
Any large installation or excavation works may impact on the water
environment through changes to hydrology, water supplies and water
quality through construction excavation, drainage, and de-watering while
compacted areas, tracks and hardstandings may lead to increased runoff.
These changes may lead to impacts on private water supplies, aquatic and
terrestrial habitats and species including Ground Water Dependent
Terrestrial Ecosystems (GWDTEs).
Assessments and Evidence Required:
• Where required Construction Method Statements should map
construction areas and storage compounds and identify all onsite,
and connected, watercourses, lochs, water supplies, and wetlands;
and appropriate buffers 
For all major and EIA proposals, and all hydropower proposals:
• A draft CEMP 
• Identify all private and public water supplies in the site catchment,
assess impacts and identify mitigation for water supplies
• Consult Scottish Water for advice on precautions where
development may affect a Protected Water Area
• Consult NatureScot on any proposals that may affect a Protected
Area or Protected Species
• Surveys should extend beyond the site boundary to recommended
distances taking micro-siting into account
• A Phase 1 habitat survey can identify wetlands. A National
Vegetation Classification (NVC) of each wetland will identify
GWDTEs and other habitats dependent on surface and ground
water.
• Identify and avoid impacts on groundwater abstractions and
GWDTEs within a minimum of 10m from all development, 100m of
excavations < 1m and 250m from excavations >1m.
Early consideration of site and route selection is the best way to avoid
sensitive habitats including wetlands and water supplies, abstractions and
drinking water supply. 
Impacts are best managed by adherence to best practice construction per
NatureScot and SEPA Guidance. 
Page 102 of 128

Page 103

Renewable and Low Carbon Energy Guidance          25 
Roads, tracks and trenches (excavations <1m depth) should be
sited/routed 100m from abstractions and GWDTES; and excavations and
buildings (>1m) 250m away. A site-specific assessment will be required if
these buffers cannot be achieved. Any effects on GWDTEs should be
assessed, avoided and mitigated in line with SEPA guidelines. 
Water crossings should be avoided where possible and where unavoidable
address SEPA and PKC Guidance mitigation requirements. 
Minimising vegetation removal and timeous post construction remediation
can reduce sedimentation. SUDS are required for construction and
operation to treat and control run-off. Drainage to SUDS must be in place
before any excavation with construction drainage and SUDS separated
from clean water flows.
Natural waterflows must be maintained across habitats. This can be
helped by minimising the use of impermeable surfaces and using
permeable access tracks. Drainage must be designed in line with PKC and
SEPA Guidance. 
All Proposals: Flood Risk 
NPF4 Policy 22(a) provides an exception for essential infrastructure in a
flood risk area (as defined in NPF4 glossary) “where the location is required
for operational reasons” provided it will:
“  (i) not increase the risk of surface water flooding to others, or itself be at risk 
(ii) manage all rain and surface water through [SUDS]…
(iii) seek to minimise the area of impermeable surface„ Policy 22(c) 
SEPA and PKC Guidance on flood risk and Flood Risk Assessment, and
drainage impact and Drainage Impact Assessment must be adhered to.
Roads and tracks should avoid the functional floodplain. Secondary egress
for safety reasons may be considered. Buildings and structures will depend
on adherence to flood risk guidance in line with SEPA vulnerability
guidance. 
If development in a flood risk area as defined in NPF4 is required,
proposals must demonstrate why this is the case for operational reasons
including reasons why alternative areas outwith flood risk areas are not
suitable. Operational reasons will be assessed in terms of the criticality of
having the proposal within a flood risk area, for it to be able to operate, and
not financial reasons. Mitigation must be in place to ensure the
requirements of policy 22(c) are addressed.
Local Flood Risk Management Plans must be referenced and proposals
should contribute to and must not adversely affect the mitigation actions
contained within.
Drainage management of the site must avoid any increase in flooding
downstream, particularly on Potentially Vulnerable Areas identified in Local
Flood Risk Management Plans. Inappropriately designed weirs, tracks and
river crossings can introduce an increase in flood risk. 
• A Drainage Impact Assessment may be required where there are
new tracks or hardstandings, or where the proposal may affect a
sensitive area as set out in PKC Guidance on flood risk and Flood
Risk Assessment.
• A Flood Risk Assessment will be required if a development is
proposed within a flood risk area as defined in the NPF4 glossary.
Wind
Large Turbines and Wind Farms are likely to have significant impacts due to
construction de-watering, excavations, tracks and crane pads. 
Following careful site selection, siting of turbines and design of tracks and
hardstandings must take into account existing ground cover, waterlogging
and slope, the proximity and connection of the water environment. 
Submissions must show how potential run-off and pollution are addressed
through SUDS and drainage and a drainage impact assessment is likely to
be required. Drainage proposals must be designed to allow maintenance
per the SuDS Manual requirements. 
Mitigation as recommended by Ecological Clerk of Works must be followed
and further measures may be required including:
• a water quality management plan to ensure water protection
measures are monitored and maintained
Page 103 of 128

Page 104

Renewable and Low Carbon Energy Guidance          26 
• Monitoring of identified water sensitivities and GWDTEs; with plans
for remedial action.
See: Good Practice During Windfarm Construction | NatureScot
Hydro
Given the in-stream nature of hydro construction and operation particular
care must be taken for both site selection, construction and operation. See
SEPA guidance for in stream works.
Water quality and hydrology can be affected by construction run off and
scouring, sedimentation, and submerged vegetation. 
Areas sensitive to changes in hydrology and morphology must be avoided.
Submissions must address how water quality, hydrology and morphology
of both construction and operation will be mitigated with best practice
construction shown through the CMS and CEMP. A water quality
management plan may be required to ensure water quality protection
measures are monitored and maintained.
Changes to water flow from flow diversion, transfers from other
catchments, engineering works, weirs, intakes and outfalls may also
change morphology and hydrology with impacts on fish passage,
recreation and tourism and water supplies. Inflow and outflow must be
carefully designed and sited and transfers between otherwise
unconnected watercourses avoided. Impacts on areas sensitive due to
water abstraction, and agricultural abstraction and groundwater quality
must be avoided or impacts mitigated. 
Information on flow including compensation flow, must be provided along
with an assessment of downstream effects. 
All weirs will give rise to some degree of local water level change and
potentially temperature change and should be taken into account in
assessing aquatic ecology. 
All submissions must demonstrate that watercourse crossings and in-river
engineering can cope with extreme rainfall, and powerhouses and other dry
land infrastructure is designed and sited in accordance with NPF4 Policy
22.
A cumulative impact assessment will be required where there are existing
hydropower structures or proposals on the tributary particularly where
there are agricultural abstractions or good groundwater quality.
Guidance:
• Hydroelectric power | NatureScot
• Hydropower | SEPA
Solar, Energy Storage & Enabling Infrastructure
Impacts on the water environment from surface run-off from panels, non-
permeable foundations, areas of hard-standing, erection of buildings,
compaction and tracks must be considered. 
Vegetation around and under solar arrays should be retained for wildlife or
grazing, and permeable access tracks used along with localised SUDS for
any run-off (per NPF4 Policy 22(c)(ii). 
Site selection should take into account electricity infrastructure
vulnerability to flood risk, with careful siting and design of inverters and
transformers to reduce flood risk in line with NPF4 Policy 22. Battery
storage is unlikely to be suitable in flood risk areas.
Run-off from battery storage firewater is not covered by SEPA authorisation
and must be contained to prevent pollution of the water environment (See
section 3.13). Containment ponds/impoundments for firewater from an
authorised abstraction will not need SEPA approval but should be filled
during winter months.
3.11 Biodiversity 
Key Policies:
• NPF4 Policy 3: Biodiversity
• NPF4 Policy 4: Natural Places
• NPF4 Policy 11(d): Energy
• LDP2 Policy 42: Green Infrastructure
• LDP2 Policy 33: Renewable & Low Carbon Energy
• LDP2 Policy 45: Lunan Lochs Catchment Area
• LDP2 Policy 47: River Tay Catchment Area
Page 104 of 128

Page 105

Renewable and Low Carbon Energy Guidance          27 
Key Guidance:
• Renewable energy | NatureScot
• Planning and development advice | NatureScot
• Biodiversity | SEPA
• Planning for Nature Guidance | PKC
• NPF4 Policy 3 Interim Guidance Note | PKC
• Perth & Kinross Nature Networks | PKC
• Tayside LBAP | Tayside Biodiversity Partnership (TBP)
• TBP Development Guidance | TBP
• Local Nature Conservation Sites | PKC
• Planning and development: protected areas | NatureScot
• Site Link for Protected Areas | NatureScot
• Bats and onshore wind turbines survey assessment and mitigation |
NatureScot 
• Guidance on SACs and SPAs | PKC
• Habitats Regulations Appraisal (HRA) | NatureScot  
• Planning and development: protected species | NatureScot
Natural Places 
NPF4 Policy 4 sets out the requirements for new developments in relation
to natural places. This includes a general statement in policy 4(a):
“ Development proposals which by virtue of type, location or scale will have an
unacceptable impact on the natural environment, will not be supported„
NPF4 Policy 4(a)
NPF4 Policy 4 sets out tests for protected areas, local designations and
protected species. These cover national parks, landscape, biodiversity, and
protected species.  Note Landscape and Visual impacts are addressed in
section 3.4. 
The following guidance and supporting information should be referred to in
preparing submissions:
Biodiversity
NPF4 Policy 3 sets out the requirements for new developments in relation
to biodiversity including significant biodiversity enhancement for national,
major and EIA developments, and enhancement for local proposals. The
mitigation hierarchy and nature networks are key to all proposals. For the
avoidance of doubt all submissions should demonstrate that the mitigation
hierarchy has been addressed in the order as set out in the NPF4 Glossary.
Major and EIA proposals should refer to Scottish Government guidance,
and local proposals must be in accordance with NatureScot’s Developing
with Nature guidance. 
The Council Planning & Biodiversity webpage provides our Planning for
Nature Guidance including minimum mitigation requirements, an Interim
Guidance Note on information required to support NPF4 Policy 3, and
information on nature networks and local biodiversity sites.
Geodiversity 
NPF4 Policy 4(c) and 4(d) includes impacts on nationally significant SSSIs
and candidate Local Nature Conservation Sites which are designated for
their geological value. Geological Review Sites (GCRs) are generally
covered by one of these designations but are of national or international
significance requiring notification to NatureScot. Impacts on GCRs fall
within the scope of NPF4 Policy 4(a). Mitigation of impacts on geodiversity
should be based on the qualities for which sites are designated. In general
proposals should not impede the access, visibility or experience of these
sites. 
Relevant habitat and species records
• Scottish Biodiversity List
• Tayside Local Biodiversity Action Plan
• NBN Atlas
• Tayside Raptor Study Group
• Scottish Badgers
• NatureScot (FWPM)
• Tay District Salmon Fisheries Board
• BSBI
• Fife Nature (Kinross area only) 
Page 105 of 128

Page 106

Renewable and Low Carbon Energy Guidance          28 
Page 106 of 128

Page 107

Renewable and Low Carbon Energy Guidance          29 
Page 107 of 128

Page 108

Renewable and Low Carbon Energy Guidance          30 
All Proposals
All proposals should show how impacts on natural heritage have been
avoided, mitigated and compensated for, and how biodiversity will be
enhanced, in line with the above policies and associated guidance.
Surveys will be relative to the size, location and sensitivity of the site and
surrounding habitat and can be identified during pre-application enquiries
or EIA scoping discussions. 
All proposals except small scale renewables must be accompanied and
informed by an Ecological Impact Assessment (EcIA) in accordance with
CIEEM Guidelines and include an assessment of the level of biodiversity
enhancement in accordance with our Interim Guidance on NPF Policy 3.
EcIA are expected to be proportionate and for small scale proposals may
be based on a Preliminary Environmental Assessment Report (PEAR).
However, a PEAR alone will not normally be considered sufficient. 
Submissions without EcIA, biodiversity enhancement assessments,
recommended surveys, or with surveys outwith the correct season will
result in applications being delayed or refused. 
Annex 4 of the PKC Planning for Nature guidance provides a helpful
checklist of information required to inform a planning application regarding
biodiversity. Information should be submitted in accordance with the
checklist to reduce future information requests and delays.
Biodiversity, green infrastructure and nature network protection and
enhancement should be implemented throughout the design of the project
from initial design to construction, compensation, restoration, operation
and decommissioning. Submitted designs and landscaping plans should
clearly show where protections, mitigation and enhancement
recommended in the EcIA is being applied.
Site selection and development design is expected to demonstrate
adherence to the mitigation hierarchy in order. Compensation will not be
accepted in place of an impact that could have been avoided by design.
Any unavoidable loss must be compensated in accordance with guidance
before positive measures can be considered enhancement.
Renewable installations can avoid direct loss and fragmentation of
habitats, woodland and green infrastructure through carefully sited
infrastructure and access tracks. 
Considered early, indirect damage to plants and habitats from changes to
soils and hydrology can also be avoided. Infrastructure may also disrupt or
displace wildlife from their foraging, roosting, breeding and commuting
habitats. This may include displacement of birds, badgers, reptiles and
amphibians from breeding and foraging/ hunting grounds; disruption to bat
roosts in woodland, or disturbance/fragmentation of bat foraging habitats
in and near woodland, woodland edges, watercourses, wetlands, lochs
and hedgerows. Even small domestic installations will need to address
impacts on bat roosts and breeding birds in buildings and trees. 
Best practice construction includes working in the correct season for
relevant species, and providing a safe site for wildlife particularly where
there are open trenches or pipework. Measures must be taken on site to
minimise risks of transfer of invasive non-native species. Restoration,
compensation, landscaping and/or enhancement should be carried out as
early as possible and promote biodiversity, climate resilience, flood
protection, and recreation in line with the Council’s Forest and Woodland
Strategy, LBAP and Green Infrastructure guidance.
A landscape plan or habitat management plan should detail mitigation,
restoration, enhancement and monitoring. For Major and EIA proposals, 
conclusions from the EcIA and the requirements detailed in PKC’s Planning
for Nature Guidance should be used to create a Site Biodiversity Action
Plan. This will contain quantity, locations, techniques, timescales, and
monitoring arrangements. Priority species are available in the Tayside
Biodiversity Action Plan and Scottish Biodiversity List. 
Wind
All wind turbines larger than micro turbines can provide a collision risk to
birds’ commuting, hunting or migration flight paths as well as loss or
displacement of birds from breeding, foraging and hunting habitat.
Turbines also pose a collision and barotrauma risk to bats. 
Page 108 of 128

Page 109

Renewable and Low Carbon Energy Guidance          31 
Desktop search areas for protected sites and species must consider
ecological connectivity. For example:
• 20km search area for geese and goose SPAs and SSSIs
• 10km search for bats and bat SACs
Additional surveys required include detailed surveys and collision risk
modelling of wintering, breeding, foraging and migrating birds for all EIA
developments. For non-EIA development the level of assessment will be
relative to the risk and connectivity to sensitive areas and populations. 
Cumulative impact assessments on birds and bat populations will be
required for EIA developments in line with NatureScot guidance. 
Site location, layout and choice of turbines should be shown to avoid
adverse impacts. Additional mitigation expected will include a buffer
between turbines and hedges or woodland edges appropriate to bird and
bat species present. A monitoring, shut down or slow turbine plan will
provide further precautionary mitigation. 
Enhancement opportunities for wind include bog and peatland restoration,
woodland restoration to create alternative corridors and contribute to
Nature Networks.
• Onshore wind energy | NatureScot
• Renewable | SEPA
Hydro
Hydropower development can have significant impacts through the
installation of tracks and penstocks, but also operational impacts on the
water environment. 
Changes to water quality, quantity, flow, depth, sediment and temperature
can affect the habitat, food availability, spawning and migration of a wide
range of species. 
Information on the impacts of hydrological changes on relevant species
should be provided. Species include fish surveys as required by SEPA,
aquatic invertebrates, aquatic birds, otters, beavers and bryophytes. 
Impacts on species throughout their lifecycle including migration should
be considered and addressed in site selection and design. Negative
impacts can be avoided or mitigated by using degraded watercourses with
poor ecological status, sites upstream of existing fish barriers, avoiding
sites with poor hydrology, and ensuring the design and location of intakes
and tailraces does not detrimentally affect habitat through changes to
morphology and hydrology. 
Cumulative impacts on protected species should be addressed where
there are other installations in the local catchment. 
Weir location and design should demonstrate that they do not prevent fish,
lamprey and eel access to feeding, breeding and spawning areas. Fish and
mammals can be injured by poorly designed or inadequately screened
intake structures, weirs, tailraces, outfalls and fish passes. Intakes and
outfalls must be screened to protect wildlife.
Use of existing weirs will prevent new fish barriers, or can be upgraded to
restore fish passage where NatureScot advise this is appropriate. Other
enhancement opportunities include natural flood management and
riparian planting to provide shading, water quality improvements and
erosion control.
• Hydroelectric power | NatureScot
• Renewable | SEPA
Solar
Roof mounted PV or solar thermal should not disturb or block access to bat
roosts and bird nests in or on roofs. 
Solar farms, even on arable land, have potential to displace breeding and
wintering birds, mammals, amphibians and reptiles from foraging and
breeding areas. Surveys should assess the existing resource and consider
the location and design of the site and fencing. Siting the solar farm on land
with low biodiversity value with a view to enhancement is encouraged with
a substantive buffer between the site and existing trees or waterbodies. 
The remaining habitat can continue to have value with wildflower meadows
or grasslands under arrays that can support pollinators and ground-nesting
Page 109 of 128

Page 110

Renewable and Low Carbon Energy Guidance          32 
birds. Vegetation should be cut manually in accordance with the plan or by
low intensity grazing. 
Native hedges around the site in addition or substitution to fences can
provide security, screening and habitat. Where fences are used badger
gates and low level gaps for amphibians and hedgehogs will allow
continued use of the site, while passive infrared lighting will reduce
impacts on birds and bats.
• Solar energy | NatureScot
• Renewable | SEPA
Energy Storage and Enabling Infrastructure
Battery storage and enabling infrastructure have potential to displace
breeding and wintering birds, mammals, amphibians and reptiles from
foraging and breeding areas. Surveys should assess the existing resource
and consider the location and design of the site and fencing. Siting the
scheme on land with low biodiversity value with a view to enhancement is
encouraged with a substantive buffer between the site and existing trees or
waterbodies. 
Proposals for enabling infrastructure that involve a corridor of development
e.g. transmission lines, will need to consider impacts across the length of
the site and the impacts on commuting species. Bird surveys in
accordance with NatureScot guidance may be required. 
Native hedges around the site rather than fences can provide security,
screening and habitat. Where appropriate badger gates and low level gaps
for wildlife in fencing will allow continued use of the site, while passive
infrared lighting will reduce impacts on birds and bats.
3.12 Trees, Woods and Forests
Key Policies:
• NPF4 Policy 11(e)(x)
• NPF4 Policy 6: Forestry, Woodland and Trees 
• LDP2 Policy 40: Forestry, Woodland and Trees
Key Guidance
• Forest & Woodland Strategy | PKC
• Planning for Nature | PKC
• Interim Guidance on NPF4 Policy 3 | PKC
• Management of Forestry Waste | SEPA
• Use of trees cleared to facilitate development on afforested land |
SEPA 
• Control of Woodland Removal Policy| Scottish Forestry
• CWRP Implementation Guidance | Scottish Forestry
• Woodfuel Advice Note | Ofgem
All proposals
Tree surveys are required for all developments where there are trees on
site, to inform design and mitigation taking into account the protection of
trees and avoidance of impacts on their ecological condition, through both
NPF4 and LDP2. This includes:
• Ancient and veteran trees
• Individual trees of high biodiversity interest
• Trees of high natural, historic and cultural heritage value, including
orchards
• Trees or groups of trees of high amenity value
• Trees in conservation areas
Woodland surveys may be required where identified through Preliminary
Ecological Appraisals or for potentially affected ancient woodland
categories including LEPO. See PKC’s Planning for Nature Annex 1 for
advice on tree and woodland surveys.
Proposals must then demonstrate how construction of installations and
tracks will avoid adverse impacts, fragmentation and loss of hedgerows,
woodland and trees in accordance with the mitigation hierarchy. LDP2 sets
out that tree removal is only permitted where unavoidable. NPF4 sets out
that woodland loss is only supported in accordance with the policy on
woodland removal. All loss must be restored or compensated in line with
PKC and national guidance.
Proposals should also seek to expand and enhance connectivity between
areas of natural and ancient woodland. Proposals affecting forestry should
Page 110 of 128

Page 111

Renewable and Low Carbon Energy Guidance          33 
adhere to SEPA and Scottish Forestry standards and guidance, and the
Council’s Forest and Woodland Strategy.
Wind
In non-native plantation forestry, restructuring for wind optimisation may
be supported if SEPA guidelines are followed subject to impacts on soil,
biodiversity and timber production. Keyholing is preferred, except on peat
where clear felling and peat restoration should be pursued.
Hydro
Particular care should be taken with hydro schemes to avoid loss of, and to
enhance, riparian woodland. Impacts on land capable for timber
production should be minimised.
Solar
Sites for solar farms are expected to avoid trees, hedges and woodland,
and an appropriate buffer should be applied between site fencing and
surrounding woodland to protect roots and provide a maintenance
corridor. Native hedges with hedge trees are encouraged as enhancement.
Bioenergy
Unsustainable biomass fuel can impact GHG emission savings and
habitats. See section 2.7 for guidance on sustainable fuel sources. 
Fuel sustainability can be demonstrated by providing a management plan,
long term forestry plan, or meeting Ofgem sustainability criteria.
3.13 Hazardous Installations
Key Policies: 
• LDP Policy 33A(a): Renewable Energy
• NPF4 Policy 23: Health and Safety
Key Guidance:
• Developers’ planning application advice | HSE
• Grid Scale BESS planning Guidance for FRS | NFCC
• Guidance for Pollution Prevention: major spillages and firewater |
NIEA / SEPA
All Proposals
Site searches should address pipeline and HSE consultation zones set out
in LDP2 and where applicable set out mitigation as required to accord with
NPF4 Policy 23.  
Energy Storage
Applicants must address the associated risks with battery storage. Fires
are rare but may produce toxic gases and chemical run-off into soils and
waterways. Applicants should carry out a site specific risk assessment and
develop a robust risk management plan and emergency response plan.
Proposals must address matters contained in NFCC guidance including: 
• Fault, fire and gas detection and monitoring
• Water based fire suppression systems.
• Deflagration venting and explosion protection
• Two access points and tracks suitable for fire service vehicles
including passing places with no overhead obstructions
• 6 metres between units unless tests demonstrate a safe smaller gap
• 30m separation to occupied buildings subject to mitigation
• 10m separation from combustible material 
• Suitable water provision within 90m of the site or tanks that can
provide 1500L/min for 2 hours (180,000L). 
• Impervious surface
• Sufficient storage e.g. tanks, bunded lagoons, for run off from
firewater as demonstrated in a firewater management plan. This
may need to be for a greater volume than the water provision. 10m
separation between BESS units and water tanks. 
Submissions should provide a plan showing sensitive receptors within 1km
of the site. 
Page 111 of 128

Page 112

Renewable and Low Carbon Energy Guidance          34 
3.14 Construction Impacts
Key Policies:
• NPF4 Policy 11: Energy
• LDP2 Policy 33A(e): Renewable and Low Carbon Energy
Key Guidance
• Good practice guide for contractors | NatureScot
• Good Practice during windfarm construction | NatureScot
• Hydropower | SEPA
• Guide to hydropower construction good practice | SEPA
• Appendix 2: CMS Template
All Proposals
Construction best practice must be followed and consideration given to all
temporary and permanent infrastructure including hill tracks and borrow
pits, staff and storage compounds, crane pads, weirs, penstock and
cable/pipework routes, excavations and bunding.
Guidance on best practice construction methods and approaches is also
included under separate chapters, where relevant.
A draft Construction Method Statement (CMS) will be required as part of a
submission or an EIA Report:
• Where there is potential for impacts on the water environment, good
quality soils, carbon rich soils, priority habitats, or archaeology
• Where there is potential for impacts on a site designated for its
natural heritage such as SSSIs, SPAs and SACs.
• For all large turbines and wind farms
• For all hydropower
• For all major and EIA proposals
Most renewable energy projects will require a Construction Environmental
Management Plan (CEMP) by condition. A draft CEMP may also be
requested at the planning stage to inform proposals in sensitive
environments. A full CEMP will be required before construction, and the
advice of an independent Ecological Clerk of Works (ECOW) as agreed by
the Council, in consultation with NatureScot and SEPA where relevant. 
3.15 Soils
Key Policies:
• NPF4 Policy 5: Soils
• LDP2 Policy 33: Renewable and Low Carbon Energy
• LDP2 Policy 51: Soils
Key Guidance
• Soil | SEPA
• SEPA Position Statement on Planning and Soils
• Soil carbon management | NatureScot
3.15.1 All Soils
Soils provide a wide range of services from carbon storage to food growing.
Erosion, compaction, disturbance and loss can impact habitats and
waterways and negate Greenhouse Gas (GHG) reductions. Many of these
effects can be avoided, minimised and mitigated through good practice
construction and management. 
NPF4 Policy 5(a) only supports proposals where they are designed and
constructed in accordance with the mitigation hierarchy and in a manner
that protects soil from damage including from compaction and erosion,
and that minimises soil sealing. 
Soils stripped onsite should be minimised and stored for post-construction
restoration which should be appropriate to the surrounding environment.
Restoration should take place as soon as tracks or areas are completed or
no longer required and aim to enhance soils and vegetation and prevent
further erosion.
Impacts on soils and peatland considered should include all aspects of the
development including any borrow pits, tracks, and areas required during
construction. 
Construction of tracks, cable and pipeline routes particularly on the steep
ground typical of hydropower, can lead to erosion which can be
exacerbated by changes in drainage patterns. Drainage strategies should
demonstrate that erosion is not exacerbated by changes in hydrology
Page 112 of 128

Page 113

Renewable and Low Carbon Energy Guidance          35 
through direct erosion or drying out. In areas likely to be prone to erosion,
applications should avoid disturbance of trees and vegetation. Where
unavoidable, measures to safeguard soils during construction, and
planting of natural protection during restoration should be provided.
Solar applications can minimise erosion through careful site selection,
avoiding steep slopes and maintaining vegetation. Using driven, screw or
floating mounts can minimise soil impacts.
See section 2.7 for guidance on bioenergy feedstocks to protect soils.
3.15.2 Prime Agricultural Land and Good Quality Soils
NPF4 Glossary defines prime agricultural land as that identified as being
Class 1, 2 or 3.1 in the land capability classification for agriculture
developed by Macaulay Land Use Research Institute (now James Hutton
Institute). LDP2 Policy 51 includes this land and classes 1-3.2 as Good
Quality Soils
Submissions must refer to the 1:50K Scale Land Capability Map in the first
instance and only the National Scale Land Capability map where 1:50k is
not available. 
NPF4 Policy 5(b) sets out three qualifications for renewable energy which
will be supported on these soil types; all of which must be demonstrated in
submissions:
• there is a specific locational need and there is no other suitable site
• there is secure provision for restoration; and
• the layout and design of the proposal minimises the amount of
protected land that is available.
Submissions should set out the operational reasons why a site is required
over sites of a lower grade classification within a site search appropriate to
the technology. Site searches must set out each area investigated, and the
reasons why the alternative site was not considered suitable.
Submissions should ensure designs demonstrate that restoration of land
to its previous use is feasible following decommissioning. Note that the
temporary nature of an installation is expected except for wind energy
where proposals must be suitable in perpetuity.
Submissions should clearly set out how the design minimises the use of
prime agricultural land, in accordance with the mitigation hierarchy
including decisions taken to reduce the footprint. 
LDP2 Policy 51: Soils requires development on all Good Quality Soils to:
• Minimise impacts
• Implement appropriate soil management 
• Adopt best practice when moving, storing and reinstating soils
• Consider opportunities to re-use soils necessarily excavated 
This information should be set out in a draft Soil Management Plan with
submissions.
The cumulative loss of prime agricultural land is an important
consideration. Major and EIA proposals must set out the cumulative loss of
prime agricultural land including consented and submitted proposals
under consideration. This should show:
• The loss of land in hectares
• The loss of prime land as a % of each affected soil class of prime
agricultural land within:  
o the local area and
o Perth and Kinross as a whole
Wind
The loss of any prime agricultural land will be appraised as a permanent
loss of land so should be minimised through careful layout and design and
continued use as productive land as far as possible. 
Solar 
Large solar farms can require a large land area and are often proposed in
lowland areas where prime agricultural land is typically located. Proposals
must not lead to an unacceptable cumulative loss of prime land and
proposals should maximise continued productive use of the land beneath
panels. 
Energy Storage & Enabling Infrastructure
Battery storage and substation developments typically have specific
locational requirements in terms of proximity to existing/planned
Page 113 of 128

Page 114

Renewable and Low Carbon Energy Guidance          36 
infrastructure. Site searches for Energy Storage must extend at least 3km
from the substation where need is identified.
3.15.3 Carbon Rich Soils, Peatland and Priority Peatland
Habitat
• Carbon and Peatland Map | NatureScot
• Restoring Scotland's Peatlands | NatureScot
• Advising on peatland, carbon-rich soils and priority peatland
habitats in development management | NatureScot
• Waste position statement for developments on peat | SEPA
• Development on peatland guidance – waste | SEPA
• Assessment the impact on peatland and carbon rich soils
(forthcoming) | SEPA
• Developments on peatland: Site surveys | Scottish Government
• Floating roads on peat | SNH & FCS
• Guidance on the assessment of peat volumes, reuse of excavated
peat and minimisation of waste
NPF4 Glossary sets out the definition of:
• Peatland
• Carbon rich soils
• Priority peatland habitat
Note that developments on peatland and priority peatland must also
comply with policy 3(b) and 3(c) Biodiversity.
NPF4 Policy 5(c) sets out two qualifications for renewable energy which will
be supported on these soil types; both must be demonstrated in
submissions:
• Essential infrastructure must demonstrate a specific locational
need and that there is no other suitable site.
• Renewable energy must optimise the contribution of the area to
GHG emissions targets. 
Development on these soils types must be accompanied by:
• a site specific assessment as set out in NPF Policy 5(d); 
• a peat management plan setting out how the assessment has
informed the projects application of the mitigation hierarchy
• plans for restoration and enhancement and associated studies and
plans. Proposals on peatland are expected to provide
compensatory restoration for damaged peatland in line with
NatureScot guidance which requires  a 1:10 ratio. 
The mitigation hierarchy requires:
• Avoidance and minimisation of impacts through site selection, route
and design with buffers between infrastructure and carbon soils.
• Minimising unavoidable impacts by minimising the footprint of
compounds and tracks and using floating roads or alternative
delivery mechanisms. 
• Restoring disturbed peatland and restoring and enhancing peatland
in the wider area as compensation.
Wind
Turbine foundation excavations and the large footprint of wind farms can
impact across a large area of peatland, carbon rich soils, and priority
peatland habitat, through direct loss as well as indirect impacts on
drainage and water flows. Information required for developments on peat is
included in SEPA windfarm guidance.
Hydro
Changes to water flows and drainage, and construction of track and
penstock routes, can disturb or drain peatland and carbon rich soils,
leading to impacts on the water environment, the loss of rare habitats and
any GHG emission savings. 
Submissions should ensure changes to watercourses do not impact on
peatland viability, directly or indirectly.
Solar
Solar farms may impact these soils through changes to water flow from
panels, trenches, drainage and tracks and they should be avoided through
site selection unless impacts can be avoided through design.
Battery Storage, Bioenergy & Enabling Infrastructure
Page 114 of 128

Page 115

Renewable and Low Carbon Energy Guidance          37 
Large-scale battery storage, substations and bioenergy proposals can have
sizeable footprints leading to direct loss as well as indirect impacts of
hardstanding and tracks on drainage and water flows. Proposals are
expected to minimise hardstanding on these soils. Cross-boundary
Impacts
Key Policies
• NPF4 Policy 11e
• LDP2 Policy 33
Key Guidance:
• Loch Lomond & Trossachs National Park - Planning
• Cairngorms National Park - Planning
3.16 Cross Boundary Applications 
Proposals may have effects across neighbouring planning authority
boundaries particularly with regards to Roads and Transport, Landscape
and Visual Impacts, and Biodiversity. Applicants should consider the plans
and policies of these authorities, and they will be consulted where there
may be an effect. 
Cumulative assessments should include applications and installations
within other planning authorities’ boundaries where there is a
landscape/visual, transport, or ecological connection.
National Parks 
Part of Perth and Kinross is in Loch Lomond & The Trossachs National Park.
Proposals here are made to the National Park Authority (NPA) in line with
their LDP. 
In the Cairngorms National Park, proposals are made in line with the
Cairngorms LDP and submitted to Perth & Kinross Council for
determination. The Cairngorms NPA may then opt to ‘call in’ and determine
the application.  
Page 115 of 128

Page 116

Renewable and Low Carbon Energy Guidance          38 
3.17 Decommissioning & Restoration
Key Policies
• NPF4 Policy 11(e)
• LDP2 Policy 33
Key Guidance
• Life Extension and Decommissioning of onshore wind farms | SEPA
• Decommissioning and Restoration Plans for wind farms |
NatureScot 
• Batteries | SEPA
• Waste Batteries and Accumulators Regulations 2009
All proposals
NPF4 Policy 11(e) paragraphs (xi) and (xii) require all proposals to show how
the following considerations are addressed:
• proposals for the decommissioning of developments, including
ancillary infrastructure, and site restoration
• the quality of site restoration plans including the measures in place
to safeguard or guarantee availability of finances to effectively
implement those plans
Decommissioning should be considered when designing and choosing
components of all renewable developments. Electronics should be
recycled in accordance with the Waste Electrical and Electronic
Equipment Regulations 2013.
Restoration can involve works both post-construction as well as post-
operation of the development. Restoration requirements are relevant
across a range of planning considerations and have been included under
the relevant section. In line with NPF4 Policy 11(e), the Council will seek
appropriate measures, including restoration bonds or other appropriate
financial mechanism, are included as part of any permission, where
relevant. 
Submissions for all EIA and major installations, or proposals potentially
affecting sensitive environments including peatland and the water
environment should include a draft Decommissioning and Restoration Plan
(DRP). A full updated DRP will need to be agreed with the Planning
Authority and consultees prior to decommissioning. 
A draft DRP should contain:
• Proposed timing, options, associated impacts and mitigation
particularly regarding impacts on habitats, peat, the water
environment and transport
• Reuse and recycling options
• Proposals for restoration of borrow pits and tracks
• Proposals for habitat, agricultural land, peatland and/or recreation
enhancement
• Provisional, index linked, costs for restoration
A Decommissioning Method Statement demonstrates how
decommissioning will take place while protecting the environment and
should include:
• Proposed timing, options, associated impacts and mitigation
associated with removal of in-ground and in-water infrastructure.
• How materials will be reused or recycled in compliance with the
waste regulatory framework
• How potential contaminants will be safely disposed of including
heat pump units and heat transfer fluid, AD waste
• Measures to ensure no contamination of soils or the water
environment
• Timing and method of restoration and enhancement, particularly of
habitat and agricultural land, waterways and riparian habitat.
• Proposed restoration monitoring and aftercare
Wind
As noted under NPF4 Policy 11(f), wind farms are expected to be suitable
for use in perpetuity. Decommissioning will be required at the end of the
permission period or where operation ceases and should be considered at
design stage. 
Removal of all infrastructure will be required unless the adverse impacts of
removal are shown to outweigh the benefits, such as wind turbine bases
below ground.
Page 116 of 128

Page 117

Renewable and Low Carbon Energy Guidance          39 
Hydro
Hydropower schemes will need to be decommissioned once they are
deemed to have ceased operation. Decommissioning of above ground and
in-water infrastructure and associated restoration must be considered at
design stage. 
Solar
Decommissioning will be required as a condition for all installations at the
end of the permission period, based on the expected life of the technology,
or once operation has ceased. Removal of all infrastructure will be required
unless outweighed by adverse impacts.
The design of roof mounted, and small ground-mounted installations
should ensure decommissioning can be carried out with minimal impacts
particularly in historic environments. 
Energy Storage, Bioenergy, Enabling Infrastructure
Decommissioning will be required as a condition for energy storage at the
end of the permission period, based on the expected life of the technology,
and for all installations once operation has ceased. Removal of all
infrastructure will be required unless outweighed by adverse impacts.
Batteries must be sent for recycling to an approved battery treatment
operator or exporter. 
A financial mechanism may be required by legal agreement to ensure
decommissioning and restoration can be undertaken.
3.18 Renewable Energy Generation and Greenhouse
Gas Emissions Reduction Targets
Key Policies:
• NPF4 Policy 1: Tackling the climate and nature crises
• NPF4 Policy 2: Climate mitigation and adaption
• NPF4 Policy 11(e): Energy
• NPF4 Policy 5(d)(iii): Soils
• LDP2 Policy 33A (b): Renewable and Low Carbon Energy
Key Guidance
• Draft Bioenergy Policy Statement | Scottish Government
• Assessing Greenhouse Gas Emissions and Evaluating Their
Significance | IEMA
• Carbon Calculator for Wind Farms on Scottish Peatlands |
ClimateXChange
All proposals
In considering the assessment of proposals against NPF4 Policy 11(e),
significant weight will be placed on the contribution towards:
• renewable energy generation targets, and
• greenhouse gas emissions (GHG) reduction targets
Proposals should include information detailing the contribution(s) of the
proposed development towards UK and Scottish Government targets for
renewable energy generation and GHG reductions. 
The contribution of proposals to renewable energy targets should be
presented using the following information, where relevant:
• Electrical or heat generation capacity (kWh/MW)
• Expected annual generation (kWh/MWh)
• Equivalent number of homes powered or heated
• Fuel used and source (where relevant)
• Fuel and/or generation technology being replaced or displaced
LDP2 Policy 2(a) requires that:
“ Development proposals will be sited and designed to minimise lifecycle
greenhouse gas emissions as far as possible„
EIA Development must provide a Greenhouse Gas Emissions Assessment
in accordance with IEMA guidance. 
Major proposals must present a proportionate assessment of lifetime
carbon emissions including embedded carbon, transport and soil loss and
describe the steps taken to minimise emissions. This will be taken into
account alongside GHG reductions of the technology. 
Page 117 of 128

Page 118

Renewable and Low Carbon Energy Guidance          40 
All proposals on peatland and carbon rich soils must carry out an
assessment of the likely net effects of the development on climate
emissions and loss of carbon. 
Bioenergy proposals must demonstrate adherence to greenhouse gas and
land sustainability criteria for feedstocks to be considered low carbon as
set out in Section 2.7. 
3.19 Grid Capacity
Key Policies:
• NPF4 Policy 11e
• LDP2 Policy 33 (Renewable and Low Carbon Energy)
• LDP2 Policy 35 (Electricity Transmission Infrastructure)
Key Guidance
• Network Capacity Information - SSEN
• SSEN Network Maps
All proposals
NPF4 Policy 11e states that grid capacity should not constrain renewable
energy development and it is for developers to agree connections to the
grid with the relevant network operator. For the PKC area, this is SSEN.
For proposals involving grid infrastructure, underground connections
should be considered where possible. This will be informed by wider
considerations including landscape and visual impact, and potential
impact on, for example, natural heritage, biodiversity, peatland/carbon rich
soils/priority peatland habitat, prime land, and the historic environment.
Proposals for grid infrastructure including reconfigured, extended and/or
new substation infrastructure, should involve early engagement with
relevant stakeholders including the planning authority, key agencies, and
affected communities.
3.20 Cumulative Impacts
Key Policies
• NPF4 Policy 11e
• LDP2 Policy 33
Key Guidance
•  Assessing the cumulative landscape and visual impact of onshore
wind energy developments| NatureScot 
• Renewable Map | PKC
All Proposals
The impact of a technology may be exacerbated by existing, consented or
proposed installations in the area with a similar effect. An assessment of
the cumulative effects may be required for large applications and even
small applications in sensitive locations.
NPF4 Policy 11(e) requires proposals to demonstrate cumulative impacts
are addressed. The scale of infrastructure required to help meet the
national targets for renewable energy generation and GHG emissions
reduction is such that cumulative impacts will need to be carefully
considered to ensure developments are steered to the right locations and
of an appropriate design and scale.
Cumulative impacts are particularly relevant to: 
• landscape/visual amenity, 
• natural places
• biodiversity 
• peatland/carbon rich soils/priority peatland habitat
• prime agricultural land
• roads and transport
Proposals should address:
• Existing installations
• Submitted proposals
• Proposals with permission not yet implemented
• Proposals and installations in neighbouring planning authorities.
• Impacts from all industrial installations including energy storage,
substations and other grid infrastructure.
The cumulative search area will be defined by the nature and scale of the
proposal and impacts and is best discussed with PKC through pre-
application enquiries. 
Page 118 of 128

Page 119

Renewable and Low Carbon Energy Guidance          41 
See the relevant section for policy specific information.
3.21 Permission Lifetime and Extensions
Key Policies
• NPF4 Policy 11(f)
• LDP2 Policy 33B 
Key Guidance
• Life extension and decommissioning onshore windfarms | SEPA
3.21.1 Permission lifetime
NPF4 Policy 11(f) advises that consents for development proposals may be
time-limited. This includes wind farms, but wind power sites are expected
to be suitable for use in perpetuity.
Solar farms and most wind turbines will be time limited. Other proposals
will be required to carry out decommissioning once they cease operating.
Submissions should nevertheless identify the expected life-time of the
development. 
3.21.2 Life Extensions and Repowering
Both upgrading existing technology (repowering) and extending the life of
an existing installation planning permission (life extension) can maximise
resource availability. Repowering and extension applications will be treated
as new applications subject to the contemporary legal and policy
framework, but applications in suitable sites where impacts have been
shown to be capable of mitigation are encouraged, where submitted well
before the existing permission expires. The impacts of the existing
installation will be a material consideration including environmental or
operational issues, and results of monitoring. New environmental studies
may be required if monitoring is insufficient, and applicants are
encouraged to improve upon the existing site and review community
benefits and shared ownership.
Wind
Repowering can involve full or partial replacement of turbines at any time
during the life of the installation, and may involve fewer, larger turbines on a
larger footprint with potential for a significant change to landscape, visual
and other impacts. Additional considerations include:
• Changes to renewable target contribution and GHG payback
• Changes to and history of community support
• Effects on soils and the water environment through revised height,
footprint and layout
• Revised landscape and visual impacts due to changes in height,
rotor size and layout.
• Revised cumulative impacts
• Impacts on natural heritage and biodiversity including on successful
restoration and changes to habitats and wildlife
• Impacts from changes to, retention of or decommissioning of
infrastructure including tracks, crane pads and foundations
• Innovation that provides future flexibility, reuse and recycling
• Reuse of materials, tracks and cables
• Recycling of materials that cannot be reused
• Changes to restoration plans
Hydro
Hydropower permissions including PSH will not normally be time limited.
Any material alteration to hydropower installations is likely to require a
fresh application for planning permission particularly if an increase of the
size or height of the weir or dam is proposed. 
Alterations to a hydro scheme are also likely to require authorisation under
CAR so applicants should contact SEPA at an early stage.
Solar
Solar farms will be time-limited but life extension or repowering can
maximise resource availability. Proposals for repowering with material
change involving more or larger panels, trenching or cabling - will require a
new application. New permissions may include an option for life extension,
subject to approval and identified limitations including the
presence/availability of prime agricultural land.
Page 119 of 128

Page 120

Renewable and Low Carbon Energy Guidance          42 
3.21.3 Geographical Extensions
Wind
Adding additional turbines to an existing wind farm will be treated as a new
application taking into account the existing wind farm and cumulative
impacts on the environment. Extensions should fit naturally with existing
turbines and layout. If the proposed extension is intended to outlast the
existing turbines, additional visualisations and impact assessments will be
required to address the impact of the extension on its own.
Solar
Adding additional panels to an existing solar installation may make the best
use of the available resource dependent upon the scale, nature and layout
of the existing/proposed scheme. Geographical extensions will be treated
as new applications taking into account the existing installation and
cumulative environment particularly with regard to soils and landscape
and visual effects. Extensions should aim to fit with, or improve on, the
existing panels and layout, and use as much of the existing infrastructure
as possible.
Page 120 of 128

Page 121

Renewable and Low Carbon Energy Guidance          43 
4 Appendices
4.1 NPF4 and [LDP2] Policies
The following shows NPF4 Policy 11 alongside additional requirements in
[LDP2 Policy 33]. References to directly relevant (NPF4 Policies) and extant
[LDP2 Policies] are also highlighted. 
Policy 11
a) Development proposals for all forms of renewable, low-carbon and
zero emissions technologies will be supported. These include:
i. wind farms including repowering, extending, expanding and
extending the life of existing wind farms;
ii. enabling works, such as grid transmission and distribution
infrastructure;
iii. energy storage, such as battery storage and pumped storage hydro;
iv. small scale renewable energy generation technology;
v. solar arrays;
vi. proposals associated with negative emissions technologies and
carbon capture; and
vii. proposals including co-location of these technologies. [33A…
taking into account…(i) Opportunities for energy storage] 
b) Development proposals for wind farms in National Parks and National
Scenic Areas will not be supported.
c) Development proposals will only be supported where they maximise
net economic impact, including local and community socio-economic
benefits such as employment, associated business and supply chain
opportunities.
d) Development proposals that impact on international or national
designations will be assessed in relation to Policy 4.
(NPF4 Policy 4: Natural Places)
e) In addition, project design and mitigation will demonstrate how the
following impacts are addressed:
i. impacts on communities and individual dwellings, including,
residential amenity, visual impact, noise and shadow flicker;[air
quality…including impacts from construction]
ii. significant landscape and visual impacts, recognising that such
impacts are to be expected for some forms of renewable energy.
Where impacts are localised and/or appropriate design mitigation
has been applied, they will generally be considered to be
acceptable. [taking into account landscape character, Local
Landscape Areas, Wild Land Areas and other considerations in
LDP2 Policy 39 ]
(NPF4 Policy 4: Natural Places)
(NPF4 Policy 8: Greenbelt)
iii. public access, [recreation and tourism interests] including impact
on [core paths,] long distance walking and cycling routes and
scenic routes [including the A9 trunk road; and other established
routes for public walking, riding or cycling.]
iv. impacts on aviation and defence interests including seismological
recording;
v. impacts on telecommunications and broadcasting installations,
particularly ensuring that transmission links are not compromised;
vi. impacts on road traffic and on adjacent trunk roads, including
during construction;
vii. impacts on historic environment;
viii. effects on hydrology, the water environment and flood risk;
ix. biodiversity including impacts on birds [and natural heritage];
(NPF4 Policy 3; NPF4 Policy 4)
x. impacts on trees, woods and forests;
[LDP2 Policy 40](NPF4 Policy 6)
[33A: Proposals… will be supported subject to the following factors being
taken into account…]
• [(a)…hazardous installations (including pipelines)][and
[(e) Construction and service tracks and borrow pits associated with any
development]
[(f) Effects on soils including: 
Page 121 of 128

Page 122

Renewable and Low Carbon Energy Guidance          44 
• Carbon rich soils, deep peat and priority peatland habitats; or
• Prime agricultural land]
(NPF4 Policy 5)
[(j) Cross-boundary impacts including any impacts on the qualities of the
Cairngorms and Loch Lomond and the Trossachs National Parks]
xi. proposals for the decommissioning of developments, including
ancillary infrastructure, and site restoration; [Decommissioning
including any conditions/bonds considered necessary for site
restoration] [Policy 33C: Decommissioning and Restoration of
Existing Facilities: In cases where the permission expires or the
project ceases to operate for a specific period, the removal of the
development and associated equipment and the restoration of the
site will be required to a standard agreed with the Council…] 
xii. the quality of site restoration plans including the measures in place
to safeguard or guarantee availability of finances to effectively
implement those plans; [Appropriate financial bonds or other
financial mechanism(s) for site restoration may be required]; and
xiii. cumulative impacts.[and…]
In considering these impacts, significant weight will be placed on the
contribution of the proposal to renewable energy generation targets and on
greenhouse gas emissions reduction targets.
Grid capacity should not constrain renewable energy development. It is for
developers to agree connections to the grid with the relevant network
operator. In the case of proposals for grid infrastructure, consideration
should be given to underground connections where possible.
f) Consents for development proposals may be time-limited. Areas
identified for wind farms are, however, expected to be suitable for use
in perpetuity.
[Policy 33B: Repowering and Extending Existing Facilities]
[As a result of the potential to make the best use of existing sites and
through the continued use of established infrastructure such as grid
connections, proposals for the repowering (including life extensions) of
existing renewable and low-carbon energy facilities will be encouraged,
subject to detailed assessment against the same factors and material
considerations as apply to proposals for new facilities. The current use of
the site will be a material consideration in any such proposals.
Geographical extension of existing facilities will also be assessed against
criteria (a) to (j) above and any other material considerations [including
NPF4 Policy 11], with particular emphasis on any potential cumulative
impacts arising as a result of the proposed development. Further guidance
on the key considerations when dealing with proposals for repowering and
extending existing facilities will be provided in Supplementary Guidance to
this Policy.]  
Page 122 of 128

Page 123

Renewable and Low Carbon Energy Guidance          45 
4.2 Construction Method Statement Template
What are the environmental/ecological risks and where are they?
All areas of risk to ecology, the water and built environment must be
considered.
• Provide a plan of the site, clearly showing the areas of potential pollution.
These should be highlighted and numbered, with a simple key.  An
example of this is provided, for guidance.  
• All sensitive habitat should be considered and mitigated.
Who is aware of these risks?
All on-site staff must be made aware that pollution has to be prevented and
ecological impact mitigated.
• Indicate how everyone is made aware of this requirement e.g. in
induction, clearly displayed CMS, as part of daily monitoring checks,
signed information sheet and site diary. 
What can be done to prevent pollution/harm?
Mitigation measures appropriate to prevent pollution have to be considered
and must be routinely monitored and replaced where required. 
• Using individual numbers from the site map above, indicate exactly what
mitigation measures will be used to prevent siltation, run-off and oil spills
etc.
• Clearly defined, robust Construction Exclusion Zones. 
What will you do if the mitigation fails?
There will be circumstances where mitigation measures e.g. overloaded silt
curtains are in need of repair and replacement. A thorough monitoring regime
and adequate replacement kits must be in place.
• Detail what spill kits etc. will be available and where these will be located.
These should be marked on the map.
Who will you contact?
The appropriate authorities and water users will have to be made aware of
environmental incidents as they occur.
• List the names and contact numbers of the interested parties who you will
contact in the case of emergency.
Page 123 of 128

Page 124

Renewable and Low Carbon Energy Guidance          46 
Page 124 of 128

Page 125

Housing & Environment
Executive Director (Housing & Environment) Barbara Renton 
SEA Gateway team
2-J (South)
Victoria Quay
Edinburgh
EH6 6QQ 
Economy, Development & Planning
Head of Service Serge Merone 
Pullar House, 35 Kinnoull Street, Perth, PH1 5GD
Tel 01738 475300 
Contact  Robert Wills  
Direct Dial 01738 475315                             
Email: AFinlayson@pkc.gov.uk                             
www.pkc.gov.uk 
Our ref  LDP2 SG  
Date 08 May 2025 
Dear Sir or Madam 
Environmental Assessment (Scotland) Act 2005
Screening Determination 
Perth and Kinross Local Development Plan: 
Renewable and Low Carbon Energy Supplementary Guidance 
This statement sets out the Council’s determination under Section 8(1) of the
Environmental Assessment (Scotland) Act 2005 on whether or not a Strategic
Environmental Assessment (SEA) is required for the above Supplementary Guidance. 
SEA Screening Procedure 
The screening process involved consulting the following Consultation Authorities on
whether the Supplementary Guidance is likely to have significant environmental effects: 
• Historic Environment Scotland
• Scottish Environment Protection Agency
• Scottish Natural Heritage 
As well as consulting the above bodies, responsible authorities are required to take into
account the criteria set out in Schedule 2 of the Act when determining whether or not
the Supplementary Guidance is likely to have significant environmental effects. 
In this instance, the Council wrote to the Consultation Authorities on 2 May 2025and
the responses are summarised in the following table: 
Delayed Office Opening
for Employee Training
This office will be closed from
8.45 am - 11.00 am on the first
Thursday of each month.
Appendix 2
7
Page 125 of 128

Page 126

Consultation
Authority Comment
Likely to have
significant
environmental
effects
Historic
Environment
Scotland
We understand that this guidance will support the
relevant renewable and low carbon energy policies
within NPF4 and the PKC LDP 2. As these policies
have been subject to environmental assessment
through the SEA’s of those plans we note that you
consider that significant environmental effects
resulting from the guidance itself is unlikely. We are
content to agree with the view that significant effects
on the historic environment are unlikely. 
No
Scottish
Environment
Protection
Agency
In accordance with Section 9(3) of the
Environmental Assessment (Scotland) Act 2005 we
have reviewed the screening report using the criteria
set out in Schedule 2 of the Act. In regard to our
main areas of interest (air, water, soil, human health,
material assets and climatic factors) we agree with
the conclusions of the screening report that the
proposed supplementary guidance is unlikely to
have significant environmental effects.
No
NatureScot In terms of our interests, we agree that the above
guidance is not likely to have significant
environmental effects. We understand that the
supplementary guidance will provide support, further
information for renewable and low carbon
submissions, and clarify interpretation of policy. We
also note that the supplementary guidance will not
introduce new criteria or policy.
No 
The Council has also considered the Supplementary Guidance against the criteria set
out in Schedule 2 of the Act, an analysis of which is attached. 
Reasons for Determination 
Having consulted the three consultation authorities, and having considered the criteria
set out in the Act, the Council considers that the Renewable and Low Carbon
Supplementary Guidance is unlikely to have significant environmental effects. 
The relevant policies have been subject to assessment through the SEA of LDP2 and
National Planning Framework 4, and the guidance does not introduce any new policy.
Therefore, significant environmental effects as a result of the guidance that have not
already been assessed elsewhere are unlikely. 
The Council has therefore determined that SEA is not required. 
Page 126 of 128

Page 127

Yours faithfully 
Robert Wills
Planning Officer 
Enc. Renewable and Low Carbon Energy Supplementary Guidance: Screening Report.
Page 127 of 128

Page 128

Page 128 of 128