Perth & Kinross Council
Perth & Kinross Active Travel Prioritisation 
Delivery Plan
Summary Report
Reference: REP / 001 
1 | 24 March 2025 
© Arup 
This report takes into account the particular instructions and requirements of our client.  It is not
intended for and should not be relied upon by any third party and no responsibility is undertaken to
any third party. 
Job number  305915-00
Ove Arup & Partners Limited
4th Floor  10 George Street
Edinburgh  EH2 2PF
United Kingdom
arup.com

Page 2

REP / 001 | 1 | 24 March 2025 | Ove Arup & Partners Limited 
Document Verification 
Project title Active Travel Prioritisation
Document title  Summary Report
Job number 305915-00
Document ref REP / 001 
File reference 001 
Revision Date Filename 
V1 26/03 Description First draft for client review 
Prepared by Checked by Approved by
Name Anna Dougan John Townsend Mark Bowman
Signature   
Filename 
Description 
Prepared by Checked by Approved by
Name   
Signature   
Filename 
Description 
Prepared by Checked by Approved by
Name   
Signature   
Issue Document Verification with Document  ✓

Page 3

REP / 001 | 1 | 24 March 2025 | Ove Arup & Partners Limited 
Contents 
Click or tap here to enter text.  3
1. Introduction 1
1.1 Project Background 1
1.2 Report Structure 1
2. Multi-Criteria Assessment Methodology 3
2.1 Specifying the List of Routes 3
2.2 Data Collection / Compilation 3
2.2.1 ArcGIS Pro and Feature Manipulation Engine 4
2.3 Cost 4
2.4 Active Mode Appraisal Toolkit 4
2.5 Questions and Criteria 4
2.6 Scoring Method / Weighting 5
2.6.1 5/3/1 Criteria 6
2.6.2 Weightings 6
2.7 Collaboration 6
3. Prioritisation 10
4. Summary 10
4.1 Incorporating Additional Routes 10  
Click or tap here to enter text.
Tables 
Table 1: Data sources. 3
Table 2: Assessment Criteria. 5
Table 3: Scoring Criteria. 7
Table 4: List of projects ranked by standardised (per km) score, including tiering. 11 
Figures
Figure 1. Map of all routes within the MCA. The colours of the routes are to visually distinguish
between routes and have no other meaning. Routes with dashed lines are those which overlap at some
point with others. 2
Figure 2. Project Stages. 3 
Drawings
No table of figures entries found.

Page 4

REP / 001 | 1 | 24 March 2025 | Ove Arup & Partners Limited 
Pictures 
No table of figures entries found. 
Photographs 
No table of figures entries found. 
Attachments 
No table of figures entries found.

Page 5

Perth & Kinross Council Active Travel Prioritisation
REP / 001 | 1 | 24 March 2025 | Ove Arup & Partners Limited Summary Report Page 1 
1. Introduction
Arup has been commissioned by Perth and Kinross Council (PKC) to develop an Active Travel Prioritisation
Delivery Plan for active travel routes identified in masterplans and strategies across the PKC area, as well as
other route proposals developed by the PKC Network Team and local community groups.
1.1 Project Background
A number of Active Travel Masterplans (ATMs) have previously been developed for the Perth and Kinross
region. These include:
• Perth Cycle Network Masterplan (2018), which aims to create a coherent cycle network in Perth by
defining route alignments, identifying major destinations, and assessing the likely benefits.
• Kinross-shire Active Travel Masterplan (2024), which identifies and prioritises active travel
interventions to encourage short everyday journeys, as well as placemaking interventions.
• Tactran Regional Active Travel Network (2023), which establishes a framework for developing
regional active travel routes, with the aim of providing connections between settlements,
neighbourhoods, and major trip destinations. This covers the local authorities of Angus, Dundee
City, Perth and Kinross, and Stirling.
The interventions proposed in these masterplans are a starting point to enable PKC to identify funding
opportunities to develop feasibility and design of potential options, undertake public and stakeholder
consultation, and move towards implementation.
The purpose of this commission is to develop a robust and evidence-led Multi-Criteria Assessment (MCA) to
prioritise routes in the ATMs and additional routes identified by the PKC Network Team and local
community groups. The methodology used to develop the prioritisation is informed by and aligns with key
policies and objectives outlined in the Perth and Kinross Mobility Strategy. This strategy sets out future
direction and policy focus for transport in the Perth and Kinross Council area. 
1.2 Report Structure
This report summarises the methodology of the Multi-Criteria Assessment and the recommended prioritised
delivery of interventions.
1. Introduction
2. Multi-Criteria Assessment Methodology
3. Prioritisation
4. Summary

Page 6

Perth & Kinross Council Active Travel Prioritisation
REP / 001 | 1 | 24 March 2025 | Ove Arup & Partners Limited Summary Report Page 2 
Figure 1. Map of all routes within the Multi Criteria Assessment Framework. The colours of the routes are to visually
distinguish between routes and have no other meaning. Routes with dashed lines are those which overlap at some
point with others.

Page 7

Perth & Kinross Council Active Travel Prioritisation
REP / 001 | 1 | 24 March 2025 | Ove Arup & Partners Limited Summary Report Page 3 
2. Multi-Criteria Assessment Methodology
This section outlines the evidence-led methodology that has been used to analyse and prioritise the routes. It
was agreed with PKC officers that a data led MCA was the most appropriate method to compare the routes
as it enables a consistent and transparent approach to comparing and prioritising interventions, while also
allowing for policy objectives to underpin and inform the process. The stages of the development of the
MCA, weighting and tiering can be seen in Figure 2. 
2.1 Specifying the List of Routes
It was agreed that only route-based interventions would be included as part of the prioritisation, and that
other types of active travel proposals (such as wayfinding, new crossings, cycle parking, etc.) would be
excluded. This was to ensure consistency in the scoring approach while also supporting the delivery of the
larger scale route-based interventions.
It was also decided that only the primary routes from the Perth Cycle Masterplan would be brought into the
prioritisation assessment. The secondary routes followed very similar alignments to the primary routes and
therefore would not provide significant differentiation in the scoring. 
The finalised list of 47 routes contained projects from the following strategies:
• Perth Cycle Network;
• Tactran regional Active Travel Network;
• Kinross-shire Active Travel Masterplan; and
• Additional Routes provided by PKC for inclusion in the MCA.
2.2 Data Collection / Compilation
Prior to undertaking the analysis and scoring, data was collated to understand the current transport,
demographic and economic context of the council area, as well as to inform the assessment process. Data
was sourced from a variety of publicly available open sources, as well as existing data from previous ATMs.
The routes were mapped in ArcGIS Pro, along with any supporting data sources. Table 1 outlines the data
which was used in the MCA.
Table 1: Data sources.
Type of Data Source
Adopted Road Boundary PKC
Typical Costs of Cycling Interventions Department for Transport (DfT), Office for
National Statistics, recent project experience
Railway Lines ArcGIS Open Data
Trunk Roads Transport Scotland
SIMD Scottish Government
Population National Records Scotland
Figure 2. Project Stages. Figure 2. Project Stages.

Page 8

Perth & Kinross Council Active Travel Prioritisation
REP / 001 | 1 | 24 March 2025 | Ove Arup & Partners Limited Summary Report Page 4 
Transport Hubs UK Government 
Collision Hotspots Department for Transport (DfT)
Amenities, Leisure, GPs, Hospitals, Green Spaces,
Schools
Open Street Map and Open Data – Improvement
Service
Employment Tactran Story Map
National Cycle Routes and Core Paths Sustrans Open Data, Scottish Government
Air Quality Management Area PKC
Rural Areas National Records Scotland
Car / Van Ownership National Records Scotland
Visitor Attractions Association of Leading Visitor Attractions
Urban / Rural Area Classifications Scottish Government
Planned Developments PKC
Active Travel Route Extents PKC, Tactran
Roads and Highways OS Open Data 
2.2.1 ArcGIS Pro and Feature Manipulation Engine
An ArcGIS Pro database was set up for use during the project. Any spatial data utilised was collated into this
database, to allow visual mapping of data alongside the routes. 
Given the number of projects being assessed and the data-driven approach to the MCA, a Feature
Manipulation Engine (FME) workspace was used to automate most of the processes outlined in Table 3.
FME is a software platform developed for geospatial data integration and can be used to automate data
processing and transformation tasks. This significantly improved the efficiency and accuracy of the
assessment process.
2.3 Cost
High level cost estimates for each route were developed using DfT cost estimates (2017) amended for
inflation using the ‘Building Cost Inflation Index’, as well as recent project experience. All estimates were
based on routes adhering to Cycle by Design guidance, such as having a protected space for cycling
alongside roads with high vehicle numbers and/or speeds.
2.4 Active Mode Appraisal Toolkit
After assessment of the available data and discussion with the PKC client team, it was agreed that the Active
Mode Appraisal Toolkit (AMAT) would not be used to calculate the Benefit Cost Ratio (BCR) of the routes.
This decision was taken both due to the lack of high-quality data required to accurately calculate the BCR,
but also as the MCA itself provided an assessment of the impact and costs of the proposed routes.
2.5 Questions and Criteria
The assessment criteria for the MCA were developed through:
• Reviewing assessment criteria used in the Perth, Kinross-shire, and Tactran active travel
masterplans;
• Aligning with Transport Planning Objectives in the PKC Mobility Strategy; 
• Applying best practise criteria relating to the delivery and impact of active travel routes; and

Page 9

Perth & Kinross Council Active Travel Prioritisation
REP / 001 | 1 | 24 March 2025 | Ove Arup & Partners Limited Summary Report Page 5 
• Working with available data. For example, there was no available data relating to existing active
travel conditions on each route or potential political support meaning evidence led scores could not
developed based on these factors.
The eight assessment criteria selected to inform the MCA are shown in Table 2 below. 
Criteria Sub-Criteria Question
Deliverability  Adopted Road How much of the route is on PKC adopted road?
Cost What is the anticipated cost of the route?
Additional
Permissions
Will the route require significant additional
permissions? E.g. from Network Rail or Transport
Scotland? 
Social Deprivation SIMD 1-2 Will the route serve areas with high levels of
deprivation? 
Potential Users Population How many people will be able to access the route? 
Public Transport Transport Hubs Does the route connect to the wider public transport
network? 
Safety Collision Hotspots Will the route improve safety in an area with frequent
road traffic accidents? 
Connectivity  Amenities / Leisure Does the route connect people to amenities and leisure
facilities? 
Employment Does the route connect people to their workplaces? 
Access to GPs Does the route connect people to GPs? 
Access to Hospitals Does the route connect people to hospitals? 
Education Does the route provide a safe connection to schools and
educational facilities? 
Planned Developments Will the route provide connections to new
developments? 
Other Active Travel
Infrastructure
Does the route connect with the wider active travel
network?   
Air Quality
Management 
AQMA Will the route help to reduce traffic in areas with poor
air quality? 
Rurality Rural area Does the route provide connections to rural areas? 
Table 2: Assessment Criteria.
For each of the criteria and sub-criteria a data-driven methodology was developed to quantify the impact of
each proposed route. Refining the criteria was an iterative process dependant on the usability and availability
of recent, high-quality data, as well as continuous input from PKC officers.
The scoring approach for each of the criteria has been specified in as much detail as possible, to remove any
subjectivity from the scoring. Table 3 shows the MCA criteria name, the relevant question, and the
methodology used for scoring.
2.6 Scoring Method / Weighting
Each of the sub-criteria was given a score of high/medium/low (5/3/1) based on the methodology outlined in
Table 3. Key scoring metrics (such as counts of amenities, population, and distance to key sites) were

Page 10

Perth & Kinross Council Active Travel Prioritisation
REP / 001 | 1 | 24 March 2025 | Ove Arup & Partners Limited Summary Report Page 6 
calculated using an automated FME workflow, as described in Section 2.2.1. Scores of 5/3/1 were then
assigned in the MCA Workbook Excel file based on the scoring thresholds set out in Table 3. 
Given that some of the criteria have multiple sub-criteria, the following formula was used to ensure that each
of the criteria had an equal weighting in the final score:
Criteria Score = Sum of sub-criteria scores / Number of Sub-Criteria
The final score for each route was the sum of all the criteria scores, divided by the length of the route. The
“per KM” approach was agreed in collaboration with PKC officers to ensure that the prioritisation was not
biased towards longer routes.
2.6.1 5/3/1 Criteria
The following approach was taken to ensure consistency when choosing thresholds for the scores of one,
three, or five:
• Where the raw data for a given criteria was within a small range of integer values, the score
thresholds were chosen manually to obtain a reasonable spread. For example, almost all routes were
near either zero, one, or two schools, and so the following thresholds were chosen to assign scores in
a way which split the data evenly:
o Score 1: Near zero schools.
o Score 3: Near one or two schools.
o Score 5: Near more than two schools.
• Where the raw data for a given criteria had a broad range of values, the score thresholds were set at
the 30th and 70th percentile values of the range of the data recorded. This approach was chosen to
maintain consistency when scoring across a varied range of criteria, and to ensure that outlying
values did not unfairly skew the thresholds for what was considered a high, medium or low score.
An exception was made to this approach when the raw data for a given criteria contained a
significant number of zero-values. In this case, a score of one was given to any route with a value of
zero, and the cut-off between a score of three and five was the 50th percentile non-zero value.
Details of the scoring thresholds for each criteria can be found in Table 3.
2.6.2 Weightings
To tailor the results of the MCA to support different planning objectives, a variable weighting approach was
tested, where different criteria could be given a higher or lower weighting in the final score. A range of
different approaches were tested, including weighting all criteria equally, prioritising deliverability over all
other criteria, and weighting each criteria according to how well they aligned with the PKC Mobility
Strategy Transport Planning Objectives. It was found that varying the weightings had a negligible impact on
the final rankings, and so an equal weighting was chosen for the final prioritisation results. 
Note that the weightings can still be adjusted in the accompanying Excel Workbook.
2.7 Collaboration
As previously mentioned, the development of the MCA was an iterative process which involved regular
collaboration with the PKC officers to refine and finalise the methodology. In addition to an online inception
meeting there were regular online catch-up meetings to discuss project progress and make key decisions. 
An in-person workshop was held on 6th February 2025 in the PKC office in Pullar House, Perth with PKC
officers, including representatives from planning, roads, and greenspace teams. The purpose of this
workshop was to share the draft MCA and prioritisation, and to discuss potential changes to weighting the
scores.

Page 11

Perth & Kinross Council Active Travel Prioritisation
REP / 001 | 1 | 28 February 2025 | Ove Arup & Partners Limited Summary Report Page 7 
Table 3: Scoring Criteria.
Criteria Sub-Criteria Methodology 1 3 5
Deliverability  Adopted Road The total length of the route which
is not within the PKC Adopted
Highway Boundary, and is not on a
trunk road.
Greater than 0.8km. Between 0.1 and 0.8km
(where 0.1km is the
lowest non-zero value,
and 0.8km is the 50th
percentile non-zero
value).
0km.
Cost High level cost estimate for
delivering the route to Cycle by
Design guidance (e.g. protected
space for cycling alongside roads
with high vehicle volumes and/or
speeds). Cost estimates developed
using DfT cost estimates (2017)
amended for inflation using the
'Building Cost Inflation Index'
combined with recent project
experience.
The estimated cost of the
route is greater than
£8,695,520. 
The estimated cost is
between £5,553,160 and
£8,695,520 (where
£8,695,520 is the 70th
percentile value).
The estimated cost of the
route is less than
£5,553,160 (the 30th
percentile value).
Additional
Permissions
(such as
Network Rail
or Transport
Scotland)
The number of times a route
crosses under or over a railway. 
The length of route within 100m of
a trunk road.
The route crosses a
railway line in more than
one location.
The route crosses a
railway line in one
location.
The route does not cross
a railway line.
More than 0.8km of
route aligns with a trunk
road.
Between 0.04km and
0.8km of the route
(where 0.04km is the
smallest non-zero length,
and 0.8km is the 50th
percentile non-zero
length) aligns with a
trunk road.
The route does not align
with a trunk road.
Social
Deprivation
SIMD 1-2 The length of each route within
Data Zones with SIMD score of 1-
2.
0km. Between 0.01km and
0.17km (where 0.01km is
the lowest non-zero
score, and 0.17 is the
50th percentile non-zero
score).
Greater than 6.315km.

Page 12

Perth & Kinross Council Active Travel Prioritisation
REP / 001 | 1 | 28 February 2025 | Ove Arup & Partners Limited Summary Report Page 8 
Criteria Sub-Criteria Methodology 1 3 5
Potential
Users
Population Each route had a 400m buffer
applied. For each route, the
population metric was the sum of
the proportion of the population of
each Output Area within the buffer.
Fewer than 888 people. Between 888 and 3804
people (30th and 70th
percentile).
Greater than 3804
people.
Public
Transport
Transport hubs An 800m buffer was applied to
each route. The total number of
park and rides, railway stations and
bus stations within the buffer was
used as the scoring metric.
Zero public transport
hubs.
One or two public
transport hubs.
Greater than two public
transport hubs.
Safety Collision
Hotspots
The number of collision "hot-spots"
within a 100m buffer of each route,
with a hot-spot defined as three or
more collisions with a 100m
diameter circle.
Zero collision hotspots. One collision hot spot. More than one collision
hot spot.
Connectivity  Amenities /
leisure
The total number of amenities
within a 100m buffer of the route.
Amenities include community
centres, shops, pharmacies, police
stations, places of worship, post
offices, cafes, cinemas, etc.
Fewer than 3.5 amenities
(where 3.5 is the 30th
percentile count).
Between 3.5 and 20.5
amenities (where 20.5 is
the 70th percentile
count).
Greater than 20.5
amenities.
Employment The total number of jobs at major
employment sites within a 400m
buffer of the route. 
Zero jobs Between 640 and 2605
jobs (where 640 is the
smallest non-zero value,
and 2605 is the 50th
percentile non-zero
value).
Greater than 2605 jobs.
Access to GPs Total number of GPs within an
800m buffer of the route.
No GPs. One or two GPs. Greater than two GPs.
Access to
Hospitals
Total number of hospitals within an
800m buffer of the route.
Zero hospitals. One hospital. More than one hospital.
Education Total number of educational
facilities (primary schools,
secondary schools, higher and
further education facilities) within a
200m buffer of the route.
No educational facilities. One or two educational
facilities.
Greater than two
educational facilities.

Page 13

Perth & Kinross Council Active Travel Prioritisation
REP / 001 | 1 | 28 February 2025 | Ove Arup & Partners Limited Summary Report Page 9 
Criteria Sub-Criteria Methodology 1 3 5
Connectivity
(continued)
Planned
Developments
Total number of "Proposed" or
"Major" developments within a
400m buffer of the route. 
One or fewer proposals
or developments.
Two or three proposals
or developments.
Greater than three
proposals or
developments.
Other AT
Infrastructure
Total length of the route which
overlaps with the National Cycle
Network, Core Path Network or
River Tay Way, with a 100m buffer
applied. 
A separate 5/3/1 score was
calculated for the three
infrastructure types, and the final
score was the average of these
three, rounded to the nearest of one,
three or five.
0km NCN overlap. Between 0.2km and
0.66km (where 0.2km is
the lowest non-zero
value, and 0.66km is the
50th percentile non-zero
value).
Greater than 0.66km.
Less than 1.225km Core
Path overlap (where
1.225km is the 30th
percentile value).
Between 1.225km and
3.470km Core Path
overlap (where 3.470km
is the 70th percentile
value).
Greater than 3.470km
overlap with Core Paths.
0km RTW overlap. Between 0.2km and
0.74km RTW overlap
(where 0.2km is the
smallest non-zero value,
and 0.74km is the 50th
percentile non-zero
value).
Greater than 0.74km
RTW overlap.
Air Quality
Management 
AQMA Total length of the route within the
Perth Air Quality Management
Area.
0km in AQMA. Between 0.090km and
2.88km in AQMA
(where 0.09km is the
smallest non-zero value,
and 2.88km is the 50th
percentile non-zero
value).
Greater than 2.88km in
AQMA.
Rurality Rural area The total length of the route in rural
Data Zones.
Less than 2.34km in a
rural area (where 2.34km
is the 30th percentile
value).
Between 2.34 km and
7.21km in a rural area
(where 7.21km is the
70th percentile value).
Greater than 7.21km in a
rural area.

Page 14

Perth & Kinross Council Active Travel Prioritisation
REP / 001 | 1 | 28 February 2025 | Ove Arup & Partners Limited Summary Report Page 10 
3. Prioritisation
After each route had been scored and weighted the final ranked list was split into three tiers to clearly
distinguish a group of priority projects and allow opportunity for a strategic approach to delivery which
builds upon the MCA.
The first tier was defined by the significant difference in score between the top seven routes and the
remaining list. The second and third tiers were defined to ensure an even split between the remaining tiers. 
The final ranked list of routes, including tiering, can be found in Table 4.
4. Summary
The prioritisation methodology resulted in the identification of 7 first tier routes, 20 second tier routes, and
19 third tier routes.
The additional routes provided by the PKC Network Team and those within the Perth Cycle Masterplan all
received high scores. This is due to their relatively short length and proximity to areas with high population
density and onwards connectivity, meaning they score highly in terms of deliverability and impact.
4.1 Incorporating Additional Routes
The Excel Workbook allows for the incorporation of future additional routes into the existing prioritisation
by manually inputting the relevant raw data. Note that this will require the user to generate their own data,
however the calculation of scores will be automated by the Workbook. 
Note that the existing data and score thresholds specified within the workbook are representative of January
and February 2025, and so a fair comparison with newer projects and project data may not be possible if
newer data sources are used for future projects and the scoring is not updated for all routes.

Page 15

Perth & Kinross Council Active Travel Prioritisation
REP / 001 | 1 | 28 February 2025 | Ove Arup & Partners Limited Summary Report Page 11 
Table 4: List of projects ranked by standardised (per km) score, including tiering.
Tier  Project ID Masterplan Description Overall
Score
Per
km
Score
Route
Length
(km) 
Tier 1 
1 AD3 Additional Routes Tay Street to North Inch 22.0 27.5 0.8 
1 AD4 Additional Routes Marshall Place Road 21.7 27.1 0.8 
1 Phase 2 ID 20  Kinross-shire AT masterplan Between Kinross Park & Ride and Kinross High Street 18.9 26.9 0.7 
1 AD2 Additional Routes Woodside to Coupar Angus Phase 2 12.0 15.0 0.8 
1 AD7 Additional Routes Errol To Grange  12.6 14.0 0.9 
1 AD1 Additional Routes Scone to Scone Airport 16.3 11.6 1.4 
1 Phase 3 ID 34 Kinross-shire AT masterplan Kinross and Milnathort  24.0 9.6 2.5 
Tier 2 
2 PCN_6 Perth Cycle Network Burghmuir to City Centre - Burghmuir Jeanfield Road 22.7 7.6 3 
2 PCN_5 Perth Cycle Network Broxden to City Centre - Glasgow Road A83 31.9 7.3 4.4 
2 PCN_2 Perth Cycle Network Scone to City Centre - Scone Road A94 31.8 6.8 4.7 
2 AD5 Additional Routes The Feus A824 12.0 6.7 1.8 
2 PCN_3 Perth Cycle Network Walnut Grove to City Centre - Dundee Road A85 27.9 6.6 4.2 
2 PCN_7 Perth Cycle Network Burghmuir to City Centre - Burghmuir Jeanfield Road 33.4 4.7 7.1 
2 AD6 Additional Routes Errol to Errol Station  16.5 4.6 3.6 
2 PCN_1 Perth Cycle Network Luncarty to City Centre - Dunkeld Road A9 A912 30.5 4.1 7.4 
2 PCN_4 Perth Cycle Network Bridge of Earn to City Centre - Edinburgh Road A912 33.1 4.0 8.2 
2 Phase 3 ID 38  Kinross-shire AT masterplan Wester Balgedie and Milnathort   16.3 3.5 4.6 
2 P16 Tactran Regional AT Network Methven to Almondbank 18.8 3.1 6 
2 P12 Tactran Regional AT Network
Stanley to Bankfoot (PKC and Cairngorms National Park
Authority) 18.7 3.1 6 
2 P5 Tactran Regional AT Network Blairgowrie - Craigie  21.3 3.0 7 
2 D3 Tactran Regional AT Network
Inchture to Ninewells (PKC, Dundee & Perth & Kinross
Countryside Trust) 21.3 2.8 7.5 
2 P21 Tactran Regional AT Network Abernethy to Newburgh 15.5 2.8 5.5 
2 P4 Tactran Regional AT Network Coupar Angus to Blairgowrie 21.0 2.8 7.5 
2 P10 Tactran Regional AT Network
Pitlochry to Killiecrankie (PKC and Cairngorms National Park
Authority) 18.4 2.6 7

Page 16

Perth & Kinross Council Active Travel Prioritisation
REP / 001 | 1 | 28 February 2025 | Ove Arup & Partners Limited Summary Report Page 12 
2 P9 Tactran Regional AT Network
Logierait to Pitlochry (PKC and Cairngorms National Park
Authoirty) 22.0 2.5 8.7 
2 P3 Tactran Regional AT Network Alyth - Blairgowrie 21.3 2.5 8.5 
2 Phase 3 ID 40  Kinross-shire AT masterplan Gateside Farm and Cleish 10.7 2.5 4.3 
Tier 3 
3 P20 Tactran Regional AT Network Bridge of Earn to Abernethy  17.2 2.5 7 
3 P13 Tactran Regional AT Network
Bankfoot to Dunkeld (PKC and Cairngorms National Park
Authority) 24.1 2.4 10 
3 P1 Tactran Regional AT Network Walnut Grove to St Madoes (PKC & Countryside Trust) 15.6 2.4 6.5 
3 Phase 3 ID 35  Kinross-shire AT masterplan Kinross-shire to Fife 17.9 2.3 7.7 
3 P14 Tactran Regional AT Network
Stanley to Luncarty (PKC and Cairngorms National Park
Authority) 18.1 2.3 8 
3 P17 Tactran Regional AT Network Broxden to Forteviot 19.2 2.1 9 
3 Phase 3 ID 33 Kinross-shire AT masterplan
National Cycle Network Route 775 between Glenfarg and
Glenfarg Railway Tunnels Circular Route 13.9 2.0 6.8 
3 Phase 3 ID 43  Kinross-shire AT masterplan Gairney Bank, Scotlandwell, and the Westfield Energy Park 13.0 2.0 6.5 
3 P15 Tactran Regional AT Network Crieff to Comrie 20.6 1.9 11 
3 P6 Tactran Regional AT Network Craigie to Dunkeld 18.5 1.8 10 
3 S1 Tactran Regional AT Network Dunblane to Braco 22.1 1.8 12.5 
3 P18 Tactran Regional AT Network Forteviot to Auchterarder 20.6 1.6 12.5 
3 Phase 3 ID41  Kinross-shire AT masterplan Gairney Bank, Scotlandwell, and the Westfield Energy Park 14.7 1.6 9.2 
3 P11 Tactran Regional AT Network
Killiecrankie to Pitagowan (PKC and Cairngorms National Park
Authority) 19.0 1.6 12 
3 P19 Tactran Regional AT Network Auchterarder to Braco  18.4 1.4 13 
3 P2 Tactran Regional AT Network St Madoes - Inchture (PKC & Countryside Trust) 17.4 1.4 12.5 
3 P8 Tactran Regional AT Network Logierait to Dunkeld 20.8 1.4 15 
3 Phase 3 ID 42  Kinross-shire AT masterplan Kinross-shire and Clackmannanshire  17.1 1.4 12.4 
3 P7 Tactran Regional AT Network Alberfeldy to Logierait 18.7 1.2 16