PERTH AND KINROSS COUNCIL 
Economy and Infrastructure Committee 
21 OCTOBER 2024 
PERTH AND KINROSS LOCAL DEVELOPMENT PLAN (LDP3) DEVELOPMENT
PLAN SCHEME 
Report by Strategic Lead – Economy, Development and Planning
(Report No. 24/284) 
1. PURPOSE 
1.1 This report seeks approval for the updated statutory Development Plan Scheme
(DPS) relating to the preparation of the next Perth and Kinross Local
Development Plan (LDP3). The last update was approved by the Environment,
Infrastructure and Economic Development Committee on 1 November 2023
(report 23/288 refers). It was agreed that an annual progress report be submitted
to committee detailing any changes to the Development Plan Scheme. 
2. RECOMMENDATIONS 
2.1 It is recommended that the Committee: 
• agrees the proposed Perth & Kinross Council Development Plan Scheme
incorporating the responses to consultation on the draft Participation
Statement; 
• authorises the Strategic Lead - Economy, Development and Planning to
submit the Scheme to the Scottish Ministers; and 
• remits the Place Strategies Manager & Chief Planning Officer (in post from 2
December 2024) to submit an annual progress report to the Economy &
Infrastructure Committee detailing any changes to the Development Plan
Scheme. 
3. STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
• Section 4: Background/Main Issues 
• Section 5: Proposals 
• Section 6: Conclusion 
• Appendices 
4. BACKGROUND / MAIN ISSUES 
4.1  A Development Plan Scheme is a document setting out a planning authority’s
programme for preparing and reviewing their Local Development Plan. Within
the Development Plan Scheme a participation statement is required which the

Page 2

Town and Country Planning (Scotland) Act 1997, Section 20B (4) (c), sets out as
‘an account of when consultation is likely to take place and with whom and of its
likely form and of the steps to be taken to involve the public at large in the stages
of preparation or review.’ 
4.2 The Planning Authority is required to update its Development Plan Scheme
every year. The last update was approved by the Environment, Infrastructure
and Economic Development Committee on 1 November 2023 (report 23/288
refers). The Development Plan Scheme update for 2024 is attached as Appendix
1. 
4.3 The Development Plan Scheme sets out and explains each stage of preparing
the next Local Development Plan. The first stage concerns production of the
Evidence Report, and the Development Plan Scheme outlines in greater detail
how the Planning Service will organise and consult upon the Evidence Report. 
5. PROPOSALS 
5.1 Legislation requires planning authorities to seek the views of the public at large
and have regard to those views in terms of the content of the Participation
Statement. A Draft of the Participation Statement 2024 was consulted on from 9th
to 27th September 2024. Appendix 2 summarises the responses received and
provides the proposed response to them from the Council. 
5.2 A summary of the responses received to the consultation are set out below: 
• Comments on the list of stakeholders and people that require to be engaged
with in the preparation of the next Local Development Plan;
• Requests to be kept informed of Development Plan progress;
• Opportunity to engage with Council at all stages of plan preparation
welcomed; and
• A range of other issues relating to stages of the LDP such as, comments
relating to the content of the topic papers, site suggestions, comments on
housing matters and site assessment methodologies 
5.3 The majority of comments received relate to matters outwith the content of the
Participation Statement and respondents have been advised of the appropriate
stage in plan preparation to raise these issues. The responses which were
relevant to the Participation Statement focused on the list of stakeholders and
people that require to be engaged with in the preparation of the next Local
Development Plan. These were mainly requests for groups/representative
organisations to be specifically named within the Participation Statement. It is not
proposed to make any changes to the Participation Statement in this regard as
these groups/representative organisations fall within the broader categories of
“Communities of Interest” and “Landowners and Developers” currently included
within the Participation Statement. 
5.4 The Town and Country Planning (Development Planning) (Scotland) Regulations
2023, Regulation 22 (2), states that if the timetable included in a Development
Plan Scheme for a Local Development Plan differs from that identified within its

Page 3

previous Development Plan Scheme, the Local Authority must identify these
changes and set out the reasons for them. 
5.5 The November 2023 Development Plan Scheme update aimed to have the next
Local Development Plan adopted by Q3 2027 (Oct-Dec 2027). It included
timescales for the first stage of the process (production of the Evidence Report)
which, based on experience of the amount of work involved in compiling all the
necessary evidence during the intervening period, did not allow sufficient time for
this important stage of plan production. 
5.6 Significant progress has been made on the Evidence Report including
engagement with communities in the form of the Big Place Conversation and
consultation on policy themed topic papers including links to the proposed
evidence to be used to inform the Evidence Report. The success of these
engagement activities has been born out in the level of responses received
necessitating a lengthier period than anticipated for analysis, and inclusion
where appropriate, within the Evidence Report. 
5.7 While engagement overall has been good there were initial difficulties engaging
with Transport Scotland and NHS Tayside, both of which are key infrastructure
providers whose input to the Evidence Report is vital. They are complex
organisations and identifying who has the data within them has proved
challenging. Recent discussions with Transport Scotland have, however, proved
fruitful and led to collaborative working to ensure the required level of information
expected by Scottish Government on the state of transport infrastructure in the
area within the Evidence Report. 
5.8  Likewise, the current position with NHS Tayside is   also more encouraging in
that a meeting with Senior  officials  has recently taken place. Several key issues
were  discussed including: the immediate short-term need for NHS Tayside
support on the preparation of Evidence Reports in Perth & Kinross, Angus, and
Dundee; the short/medium-term need to progress the Draft Protocol for joint-
working on the key planning processes (LDP, Development Management, and
Contributions); and the medium/longer-term need to discuss, at a corporate
level, approaches to infrastructure planning and delivery in conjunction with
Planning/Property and Asset Management. Moving forward a follow up meeting
is to be held with relevant representatives from each Council, each HSCP and
NHS Tayside to progress these issues and most importantly to ensure we have
the necessary level of information for the Evidence Report. 
5.9 The Evidence Report is required to highlight areas where the authority is aware
through discussions, forums or exchanges that stakeholders agree or disagree
with the evidence, and the reasons for this. The aim is to have minimal areas of
dispute outstanding when submitting to the Scottish Ministers for the Gate Check
(assessment and approval to proceed) to minimise delay. Discussions with
stakeholders in this regard are currently ongoing. 
5.10 In addition, decisions have been issued by the Scottish Government’s
Department of Planning & Environmental Appeals (DPEA) in relation to the
consideration of Evidence Reports submitted by Fife Council and Moray Council.
Fife Council’s was considered insufficient and has been returned for further work
and re-submission to Gate Check.  Moray Council’s was considered sufficient to

Page 4

allow them to progress preparation of their Proposed Plan, however, the
Reporter also highlighted further matters for them to address.  It is considered
prudent to take the time now to review and learn lessons from these two
decisions to improve our Evidence Report before submission, rather than take
the risk of having it returned for further work and re-submission. This approach is
further supported by the fact that the cost for the Gate Check, circa £12,500
each for Fife and Moray, is to be paid by the Planning Authority. 
5.11 Having taken account of these factors, the main change from the Development
Plan Scheme 2023 is that the updated Development Plan Scheme 2024 allows
approximately 6 additional months to produce the Evidence Report. However, it
then aims to recover this time by shortening later stages of plan production. This
means that the intended adoption date for the new Local Development Plan
remains unchanged at  Q3 2027 (Oct-Dec 2027). This is in line with Scottish
Government expectations for all local authorities to have a new style Local
Development Plan in place by May 2028. 
6. CONCLUSION 
6.1 The Development Plan Scheme has been drafted to update the Committee on
the preparation of the new Perth and Kinross Local Development Plan. It revises
the proposed timetable previously proposed in 2023 and sets out a participation
statement outlining the key stages of plan preparation and when engagement is
planned to take place. 
Author
Name  Designation Contact Details
Brenda Murray  Development Plan Team
Leader (Place Strategies)
(01738) 475000
EPLCommitteeReports@pkc.gov.uk 
Approved 
Name Designation Date
David Littlejohn  Strategic Lead - Economy,
Development & Planning
11 October 2024 
APPENDICES 
Appendix 1 - Perth & Kinross Development Plan Scheme 2024
Appendix 2 - Local Development Plan Scheme Participation Statement Consultation
Responses

Page 5

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  None
Resource Implications  
Financial  None
Workforce None
Asset Management (land, property, IST) None
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  No
External  No
Communication 
Communications Plan  None 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 This report and the attached appendix have no direct impact on the Local
Outcomes Improvement Plan, although ultimately the implementation of the
Local Development Plan will. 
Corporate Plan 
1.2 This report and the attached appendix have no direct impact on the Corporate
Plan, although ultimately the implementation of the Local Development Plan will
particularly in relation to priorities i, iii and iv:- 
(i) Working in partnership with communities; 
(ii) Tackling poverty; 
(iii) Tackling climate change and supporting sustainable places; 
(iv) Developing a resilient, stronger, and greener local economy; 
(v) Enabling our children and young people to achieve their full potential;
(vi) Protecting and caring for our most vulnerable people;
(vii) Supporting and promoting physical and mental wellbeing. 
2. Resource Implications 
Financial 
2.1 None.

Page 6

Workforce 
2.2 None. 
Asset Management (land, property, IT) 
2.3 None. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate discrimination,
advance equality of opportunity, and foster good relations between equality
groups.  Carrying out Equality Impact Assessments for plans and policies allows
the Council to demonstrate that it is meeting these duties.   
3.2 The Development Plan Scheme was considered under the Council’s Integrated
Appraisal Toolkit. No impacts on equality were identified and so a full Equality
Impact Assessment was not required. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its proposals. 
3.4 The matters presented in this report were considered under the 
Environmental Assessment (Scotland) Act 2005 and in relation to the Local 
Development Plan, referred to in the Development Plan Scheme, further action
is required. 
3.5 Due to the nature of the plan there are likely to be significant environmental 
effects, as a consequence, an environmental assessment of the Local 
Development Plan is compulsory under the Act. The local Development Plan 
is considered to be a ‘qualifying’ plan under the Act so it does not require 
screening. 
3.6 The next stage is to prepare a scoping report as part of the Local 
Development Plan process. This will determine the scope of the 
environmental assessment and will be submitted to the Consultation 
Authorities for comment. 
Sustainability 
3.7 Under the provisions of the Local Government in Scotland Act 2003 the Council
has to discharge its duties in a way which contributes to the achievement of
sustainable development.   Under the Climate Change (Scotland) Act 2009 the
Council also has a duty relating to climate change and, in exercising its functions
must act:

Page 7

• in the way best calculated to delivery of the Act’s emissions reduction
targets;
• in the way best calculated to deliver any statutory adaptation
programmes; and
• in a way that it considers most sustainable. 
3.8 The Development Plan Scheme was considered under the Council’s Integrated
Appraisal Toolkit. The Development Plan Scheme is a vehicle for establishing
the LDP process and as such no impacts on sustainability will arise from the
Programme itself. 
Legal and Governance 
3.9 None. 
Risk 
3.10 None. 
4. Consultation 
Internal 
4.1 We have consulted with colleagues in Community Planning & Policy and the
Housing and Social Care Partnership in the development of the proposals and
they agreed that using the Place Standard tool to engage with communities on a
locality basis was appropriate. 
External 
4.2 None. 
5. Communication 
5.1 None. 
2. BACKGROUND PAPERS 
2.1 The following background papers were referred to during the preparation of this
report: 
Perth & Kinross Council Local Development Plan 2
Town and Country Planning (Scotland) Act 1997
The Town and Country Planning (Development Planning) (Scotland) Regulations
2023, Regulation 22