Democracy Spraffa

23-00382-PP SR1 Crossaig FINAL

Argyll and Bute Council · 21 June 2023
Back to Planning, Protective Services and Licensing Committee — 21 June 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Argyll and Bute Council
Development and Economic Growth   
Delegated or Committee Planning Application Report and Report of Handling as
required by Schedule 2 of the Town and Country Planning (Development Management
Procedure) (Scotland) Regulations 2013 relative to applications for Planning
Permission or Planning Permission in Principle
_________________________________________________________________________ 
Reference No:  23/00382/PP    
Planning Hierarchy: National 
Applicant:   Scottish Hydro Electric Transmission Plc  
Proposal:   Erection of high voltage electricity substation and formation of
associated access, landscaping, drainage and means of enclosure
(Crossaig (North) Substation)
Site Address: Land Adjacent To Crossaig Sub Station, Skipness . 
________________________________________________________________________
SUPPLEMENTARY REPORT NO. 1
1.0 INTRODUCTION 
The purpose of this report is to:
a) Update Members that the holding Objection by SEPA in respect of the proposals has now
been withdrawn subject to the imposition of the following condition which would replace
condition 7 set out in the main report.
New Condition 7
No development shall commence until a detailed peat management and reinstatement plan
has been submitted to and approved by the Planning Authority in consultation with SEPA. 
This shall be submitted to the planning authority and SEPA no later than two months prior to
the intended commencement of development date and include details of :               
 The written consent of  all  landowners whose land is to be utilised 
 Methodology and volume of extraction, 
 Phasing/timing of any works impacting peat
 Quality/classification of Peat to be extracted
 Details of any onsite peat re-instatement and /or enhancement 
 Details of storage and transportation
 Details of the location, area and condition of onsite or offsite peatland to be  improved 
 Details of peat enhancement measures on this land 
 Details of peatland restoration outcomes to be achieved

Page 2

 Details of ongoing management arrangements of the restored peatland
The restored peatland shall thereafter be maintained in accordance with the terms of the
approved peatland management plan,and retained in perpetuity unless with the written
agreement of the Planning Authority in consultation with SEPA. The restored area shall not
be subject to any works or operations in the future to undermine the objectives of the
restoration objectives contained in the approved Peat Management Plan.
The peat improvement works shall also be undertaken in accordance with the objectives of
the necessary habitat and management plan set out at condition 08 below.
Reason: In order to minimise disturbance of peat and ensure the appropriate reinstatement,
reuse and management of peat in accordance with NPF 4 Policy 5 (c) objectives.
The Concerns previously raised by SEPA have now been addressed through the submission
of further information by the applicants and additional requirements added to the proposed
condition. 
b)  Advise Members that the Examination by Scottish Government Reporters into the Argyll
and Bute Proposed Local Development Plan 2 has now concluded and the Examination
Report has been published. The Examination Report is a material consideration of significant
weight. Consequently, the Proposed Local Development Plan 2 as recommended to be
modified by the Examination Report and the published Non Notifiable Modifications is a
material consideration in the determination of all planning and related applications.
2.0 RELEVANT PLDP2 POLICIES 
Policy 02 – Outwith Settlement Areas 
Policy 04 – Sustainable Development  
Policy 06 – Green Infrastructure  
Policy 08 – Sustainable Siting  
Policy 09 – Sustainable Design  
Policy 10 – Design – All Development  
Policy 30 - The Sustainable Growth of Renewables 
Policy 35 – Design of New and Existing, Public Roads and Private Access Regimes 
Policy 36 – New Private Accesses  
Policy 61 – Sustainable Drainage Systems (SUDS)  
Policy 73 – Development Impact on Habitats, Species and Biodiversity.  Development
Impact on Sites of International and National Importance. 
Policy 77 – Forestry, Woodland and Trees  
Policy 79 – Protection of Soil and Peat Resources  
3.0 IMPLICATIONS OF PLDP 2 AS RECOMMENDED TO BE MODIFIED BY THE
EXAMINATION REPORT
The assessment of the proposal against PLDP2 as recommended to be modified by the
Examination Report is as follows:

Page 3

Policy 02 - Development Outside Settlement Areas: will only be acceptable where it can be
demonstrated that it falls within with indicated criteria. In this instance Parts A and B of the
policy are applicable. The proposal accords with Parts A and B as renewable infrastructure.
There is a presumption in favour of sustainable development where this is of an appropriate
scale, design, siting and use for its proposed location. No substantive change to previous
assessment.
Policy 04 – Sustainable Development: Promotes the principles of sustainable development
and remain generally aligned with the requirements of ABC LDP STRAT 1 and NPF 4 Policies
1 and 2 which have already been applied to the assessment of this matter. No substantive
change to previous assessment.
Policy 05 – Design and Placemaking: Sets out principles for achieving good quality places and
is generally aligned with the requirements of ABC LDP 2015 Policy LDP 9 and SG LDP
Sustainable Design, and NPF4 Policy 14 which have already been applied to the assessment
of this matter. No substantive change to previous assessment.
Policy 06 – Green infrastructure: Sets out a requirement for the developer to demonstrate how
green infrastructure has been integrated into the design of the proposal from the outset. This
policy overlaps with provisions elsewhere to consider enhancements to biodiversity and
sustainable urban drainage which have already been applied to the assessment of this matter.
No substantive change to previous assessment.
Policy 08 – Sustainable Siting: Sets out the principles for successfully integrating new
development into its landscape/townscape setting and is aligned with the provisions of NPF4
and ABC 2015 Policy LDP 9 and SG LDP Sustainable Design which have already been
applied to the assessment of this matter. No substantive change to previous assessment.
Policy 09 – Sustainable Design: Sets out that development proposals should demonstrate
consideration of and where possible utilisation of renewable sources of energy; and
sustainable design and construction methods. No substantive change to previous
assessment.
Policy 10 – Design – All Development: Sets out requirements for the design of new
development and is generally aligned with the provisions of NPF4 and ABC 2015 Policy LDP
9 and SG LDP Sustainable Design which have already been applied to the assessment of this
matter. No substantive change to previous assessment.
Policy 30 - The Sustainable Growth of Renewables: Policy 30  supports renewable energy
developments where these are consistent with the principles of sustainable development and
it can be adequately demonstrated that there would be no unacceptable environmental effects,
whether individual or cumulative, on local communities, natural and historic environments,
landscape character and visual amenity, and that the proposals would be compatible with
adjacent land uses.  This should be read in the context of the development plan as a whole
including the objectives and principles of NPF4 and its topic specific policies including Policy
11.  The current proposals are an essential part of the provision of a robust renewable energy
transmission network vital to address climate change and are therefore considered to accord
with the objectives of policy 30. A detailed assessment of such matters is contained within the
main report of handling. No substantive change to previous assessment.   
Policy 35 – Design of New and Existing, Public Roads and Private Access Regimes: Sets out
that the acceptance of development utilising existing public roads is subject to road safety and
street design issues being addressed to the satisfaction of the Roads Authority and Planning
Authority.  A detailed assessment is set out in the main report of handling of this aspect in

Page 4

relation to ABC LDP 2015 Policy LDP 11 and SG LDP TRAN 4 and SG LDP TRAN 5.  No
substantive change to previous assessment. 
Policy 36 – New Private Access: Sets out the circumstances where a new private access may
be considered to be acceptable. No substantive change to previous assessment.
Policy 61 – Sustainable Urban Drainage Systems: Sets out a requirement that proposal for
SuDS are required in relation to all development prior to determination. The proposal has been
amended to include detail that SuDS are to be designed and installed in accordance to BRE
Digest 365 Soakaway Design and BSEN - 752-4. No substantive change to previous
assessment.
Policy 73 – Development Impact on Habitats, Species and Biodiversity.  Development Impact
on Sites of International and National Importance. The provisions of Policy 73 are generally
aligned with the requirements of NPF4 Policy 3, and ABC LDP 2015 Policy LDP 3 and Sg LDP
ENV 1 which have already been applied to the assessment of this matter. No substantive
change to previous assessment.
Policy 77 – Forestry, Woodland and Trees: Sets out criteria for the assessment of
development impact on woodland and trees. The provisions of Policy 77 are aligned with the
requirements of NPF4 Policy 6; ABC LDP 2015 Policy LDP 3, and SG LDP ENV 6 which have
already been applied to the assessment of this matter. No substantive change to previous
assessment.
Policy 79 – Protection of Soil and Peat Resources: Sets out that the Council will only support
development where appropriate measures are taken to maintain soil resources and functions
through measures that are proportionate to the development. Policy 79 is aligned with the
provisions of NPF4 Policy 5 which have already been applied to the assessment of this matter.
No substantive change to previous assessment.
4.0 CONCLUSION
Proposed Local Development Plan 2 as recommended to be modified by the Examination
Report is now a significant material consideration. However, in this case there is no significant
material change of policy between the Adopted Plan and Proposed Local Development Plan
2 as recommended to be modified by the Examination Report that would require further
assessment or lead to a change in the recommendation.
5.0 RECOMMENDATION
It is recommended that planning permission be approved subject to the revised conditions
listed in Appendix 1 of supplementary report no.1.
Author of Report: David Moore   Date: 19.06.23
Reviewing Officer:  Sandra Davies  Date: 20.06.23 
Fergus Murray 
Head of Development and Economic Growth

Page 5

Appendix 1
1. The development shall be implemented in accordance with the details specified on the
application form dated 14.12.22; the Environmental Appraisal (December 2022),
supporting information and, the approved drawings listed in the table below unless the
prior written approval of the planning authority is obtained for an amendment to the
approved details under Section 64 of the Town and Country Planning (Scotland) Act
1997.  
Plan Title. Plan Ref. No. Version Date Received
Site Location Plan A01 A01 24.2.23
Site Layout Plan 4534d-DR-P-0017 Rev.5 26.5.23
Existing Substation
Proposed Platform
Extension and Detail
4534d-DR-P-0027 - 24.2.23
Substation Compound
Layout and Electrical
Section Locations
4534d-DR-P-0004 Rev.2 24.2.23
Proposed Site Access
Profiles
4534d-DR-P-0021 Rev.1 24.2.23
Proposed Site Profiles 4534d-DR-P-0018 Rev.1 24.2.23
Site Access Details 4534d-DR-P-0008 Rev.2 24.2.23
Typical Deer Fence
and Gate
4534d-DR-P-0016 - 24.2.23
2.5m High Security
Palisade Fencing
Details
CE/34/2015 Rev. E 24.2.23
Electrical Layout
Elevations 01
4534d-DR-P-0011 Rev.1 24.2.23
Compound layout&
Electrical Section
Locations
4534d-DR_P-0004 Rev.2 24.2.23
Generator Building
Elevations and Floor
Plan
4534d-DR-P-0009 Rev.2 24.2.23
Control Building
Elevations
4534d-DR-P-0006 Rev.1 24.2.23
Control Building Layout 4534d-DR-P-0022 Rev.1 24.2.23
Control Building
Elevations
4534d-DR-P-0023 Rev.1 24.2.23        
Transformer Building
Elevations
4534d-DR-P-0019 Rev.1 24.2.23
Transformer Building
Layout
4534d-DR-P-0020 Rev.1 24.2.23  
Reason: For the purpose of clarity, to ensure that the development is implemented in
accordance with the approved details.

Page 6

2. No construction works shall be commenced until a Finalised Construction
Environmental Management Plan [CEMP] has been submitted to and approved in
writing by the Planning Authority, in consultation with SEPA and other consultees, as
appropriate. The development shall then proceed in accordance with the approved
CEMP unless otherwise agreed in writing by the Planning Authority. The CEMP shall
include:
a. An updated Schedule of Mitigation (SM) highlighting mitigation set out within
each chapter of the Environmental Appraisal (EA), and the conditions of this
consent;
b. Processes to control/ action changes from the agreed SM;
c. Construction Environmental Management Plans (CEMPs) for the construction
phase covering:
i. Habitat and species protection, including ECoW Details, surveys and species
protection plans;
ii. Landscape and Mitigation Restoration Plan including compensatory planting
(refer to Condition 9);
iii. Pollution prevention and control;
iv. Dust management, including construction activity and vehicle movements;
v. Construction noise and vibration
vi. Temporary site lighting;
vii. Watercourse crossings;
viii. Site waste management
ix. Surface and ground water management, including: drainage and sediment
management measures from all construction areas including access tracks,
mechanisms to ensure that construction will not take place during periods of
high flow or high rainfall; and a programme of water quality monitoring;
x. Mapping of borrow pits and associated habitats identified for restoration;
xi. Invasive Non-Native Species Management Plan
xii. Emergency Response Plans;
xiii. Timetable for post construction restoration/ reinstatement of the temporary
working areas and construction compound; and 
xiv. Other relevant environmental management as may be relevant to the
development
d. A statement of responsibility to ‘stop the job/ activity’ if a breach or potential
breach of mitigation or legislation occurs; and
e. Methods of monitoring, auditing, reporting and the communication of
environmental management on site and with client, Planning Authority, and
other relevant parties.  
Reason: To ensure protection of surrounding environmental interests and general
amenity. 
3. No development shall commence until a Construction Traffic Management Plan
(CTMP) and Phased Delivery Plan have been prepared and approved in writing by the
Planning Authority and Transport Scotland as the trunk roads Authority. The Plan shall
include details of:
a. Approved access routes,

Page 7

 All HGV construction traffic to use the Cross Kintyre Haul Route.
 The B8001 Redhouse - Skipness Road and the B842 Claonaig - Southend
Road must not be used by HGV's. 
 The B8001 Redhouse - Skipness Road and the B842 Claonaig - Southend
Road may be used by LGV related to these works
b. Agreed operational practises (including avoidance of convoy movements,
specifying conduct in use of passing places, identification of turning areas,
information of wheel cleansing facilities, signage to be installed on the A83
warning of construction traffic, signage or temporary traffic control measures
to include for larger or abnormal loads, reporting of verge damage); 
c. The provision of an appropriate Code of Practice to drivers of construction
and delivery vehicles. 
d. Abnormal load route surveys and finalised plan (including any
accommodation measures required including the removal of street furniture,
junction widening, traffic management).  
The development shall be implemented in accordance with the duly approved Traffic
Management Plan  
Reason: To minimise the interference with the safety and free flow of traffic on the
trunk road and to ensure that the transportation of abnormal loads will not have any
detrimental effect on the trunk or local road network.  
4. No development or ground breaking works shall commence until a programme of
archaeological works in accordance with a written scheme of investigation, has been
submitted to and approved in writing by the Planning Authority in consultation with the
West of Scotland Archaeology Service. The scheme shall be prepared by a suitably
qualified person and shall provide for the recording, recovery and reporting of items of
interest or finds within the application site. Thereafter the development shall be
implemented in accordance with the duly approved details with the suitably qualified
person being afforded access at all reasonable times during ground disturbance
works. 
Reason: In order to protect archaeological resources  
5. No development shall commence, until a strategy for housing incoming construction
workers shall be submitted to and approved in writing by the Planning Authority.
Thereafter the development shall be carried out in accordance with the approved
details. 
Reason: In order to ensure that any potential adverse impacts on the functioning of
the local housing market and tourist accommodation to the detriment of the interests

Page 8

of the local community are identified and mitigated in accordance with the
requirements of NPF4, and in particular Policy 11C and Policy 25 Objectives. 
6. No development shall commence until an appraisal of the wholesomeness and
sufficiency of the intended private water supply and the system required to serve the
development has been submitted to and approved by the Planning Authority. 
The appraisal shall be carried out by a qualified hydrologist/ hydrogeologist or other
suitably competent person and shall include a risk assessment having regard to the
requirements of Schedule 4 of the Private Water Supplies (Scotland) Regulations 2006
or Part 3 of the Water Intended for Human Consumption (Private Supplies) (Scotland)
Regulations 2017 (as appropriate) which shall inform the design of the system by
which a wholesome and sufficient water supply shall be provided and maintained. The
appraisal shall also demonstrate that the wholesomeness and sufficiency of any other
supply in the vicinity of the development, or any other person utilising the same source
or supply, shall not be compromised by the proposed development. 
The development shall not be brought into use or occupied until the required water
supply system has been installed in accordance with the agreed specification and is
operational. 
Reason: In the interests of public health and in order to ensure that an adequate
private water supply in terms of both wholesomeness and sufficiency can be provided
to meet the requirements of the proposed development and without compromising the
interests of other users of the same or nearby private water supplies.  
7. No development shall commence until a detailed peat management and reinstatement
plan has been submitted to and approved by the Planning Authority in consultation
with SEPA. 
This shall be submitted to the planning authority and SEPA no later than two months
prior to the intended commencement of development date and include details of :               
 The written consent of  all  landowners whose land is to be utilised 
 Methodology and volume of extraction, 
 Phasing/timing of any works impacting peat
 Quality/classification of Peat to be extracted
 Details of any onsite peat re-instatement and /or enhancement 
 Details of storage and transportation
 Details of the location, area and condition of onsite or offsite peatland to be 
improved 
 Details of peat enhancement measures on this land 
 Details of peatland restoration outcomes to be achieved

Page 9

 Details of ongoing management arrangements of the restored peatland
The restored peatland shall thereafter be maintained in accordance with the terms of
the approved peatland management plan, and retained in perpetuity unless with the
written agreement of the Planning Authority in consultation with SEPA. The restored
area shall not be subject to any works or operations in the future to undermine the
objectives of the restoration objectives contained in the approved Peat Management
Plan.
The peat improvement works shall also be undertaken in accordance with the
objectives of the necessary habitat and management plan set out at condition 08
below.
Reason: In order to minimise disturbance of peat and ensure the appropriate
reinstatement, reuse and management of peat in accordance with NPF 4 Policy 5 (c)
objectives.
8. No works to excavate any peat on the site shall be undertaken until a Habitat
Management and Enhancement Plan has been submitted to and approved by the
Planning Authority in consultation with its biodiversity advisor.  
Reason: To ensure that works result in habitat enhancement works being undertaken
in accordance with NPF 4 and LDP Objectives. 
9 No development shall commence until a detailed Compensatory Planting Plan (CPP)
and Long Term Forestry Management Plan (LTFMP) are submitted to and approved
in writing by the Planning Authority, in consultation with Scottish Forestry. The
approved CPP and LTFMP shall be implemented in full and in accordance with the
approved timing, unless otherwise agreed in writing by the Planning Authority. 
Reason: To enable appropriate woodland removal to proceed, without incurring a net
loss in woodland related public benefit, in accordance with the Scottish Government's
policy on the Control of Woodland Removal.  
10. No development shall commence, until a revised Landscape Planting Plan and
Maintenance Plan in accordance with BS EN ISO 11091:1999 has been submitted to
and approved in writing by the Planning Authority. The revised plans must include:
a. A plan showing numbers and locations of each tree and shrub species;
b. Planting schedule to show for each species, the total number, type and size
at planting;
c. Specification for planting to include ground preparation, planting operations
and protection from herbivores;
d. Compensatory planting scheme for tree loss
e. Schedule of implementation and phasing;  
The approved Landscape Planting Plan and Maintenance Plan shall thereafter be
implemented in full in accordance with the implementation schedule and maintained

Page 10

in accordance with the approved details. Any plant losses within the first five years will
be replaced at the next planting season.  
Reason: To ensure the development conserves and enhances the landscape
character and biodiversity interests of the area.  
11. Any watercourse crossings, hereby permitted, shall be designed to at least the
capacity of the existing channel and to the 1 in 200 year plus climate change flow and
an allowance for freeboard, unless otherwise agreed in writing by the Planning
Authority.    
Reason: To ensure that new watercourse crossings do not affect the existing flows in
the interests of flood risk.  
12. No external lighting shall be installed on the site other than with the prior written
approval of the planning authority. In that event the location, type and luminance of
the lighting units to be installed shall be specified, and any duly approved lighting shall
be installed in a manner which minimises illumination and glare outwith the boundary
of the application site. The completed site shall not be illuminated other than in the
event of staff being present on site.  
Reason: In order to avoid unnecessary visual intrusion in the interests of the visual
amenity of an area otherwise unaffected by the presence of light sources.  
13. No development shall take place outside the following hours:  
07.00hrs and 19.00hrs Mon to Friday (inclusive)
07.00hrs and 18.00hrs Saturday
No construction works shall take place on Sundays or Scottish Bank Holidays  
unless as otherwise may be agreed in writing with Environmental Protection Officers
in advance of the operations  
Non-construction work and switching works can be carried out on Sundays and
Scottish Bank Holidays between the hours of 08.00 and 13.00.

Page 11

Reason: Reason: To minimise the impact of noise, generated by construction
activities, on occupiers of residential properties.