Appendix 1 - Short-listed Options 
Option Description Progress to
Modelling?
Progress to Further
Evaluation?
Capital
Cost (£M)
Benefit/Cost Ratio (BCR)
1 Upstream flood storage and
natural flood management south
of M90
Yes Yes Not fully costed as required land take (10% of
upper catchment) to achieve benefit would
take BCR significantly below 1.
2 Improve drainage on M90 and
Broxden area
Ruled out prior to modelling as no data available from Trunk Road operator. To be
investigated further as part of the Perth Surface Water Management Plan.
3 Increase flood storage at
existing Perth Flood Scheme
‘wet’ ponds, Glasgow Road
Yes Yes £0.47M 0.66
4 Increase flood storage at
existing Perth Flood Scheme
‘dry’ pond, Glasgow Road
Yes Ruled out due to increased flood risk in more frequent flood events (1
in 5-year and 1 in 10-year floods)
5 Culvert upsizing and flood
storage area, Necessity Brae
(Cherrybank)
Yes Ruled out as only provides limited localised benefit at high cost
6 Culvert upgrade, Buckie Brae  Ruled out prior to modelling – would increase flood risk; main issue is blockage, not
capacity
7 Channel modification (dredging)
Buckie Braes to South Inch
Yes Yes £0.21M 1.0 (was found to be of limited
benefit; additional costs for
culvert upgrades and bank
stabilisation would reduce BCR
well below 1.0) 
8 Flood storage area, Low Road
to Orchard Place
Yes Yes £0.55M 0.60
9 New flood defences, Orchard
Place 
Yes Ruled out due to limited benefit

Page 2

10 Improve culvert capacity,
Queen’s Avenue
Yes Yes £0.27M 1.39
11 Improve culvert capacity,
Queens Avenue and modify
adjacent river channel  
Yes Yes £0.31M 1.42
12 New flood defences, Croft Park
& improve Craigie Burn to South
Inch reservoir spill mechanism
Yes Ruled out due to high cost and increased flood risk from reservoir in
extreme flood events
13 Improve Craigie Burn to South
Inch reservoir spill mechanism
Yes Yes £0.31M 0.88
14 Options 11+13 combined Yes Yes £0.62M 1.0 (not considered a robust
enough economic case at this
stage).

Page 3

Location Plan of Short-Listed Actions