LHEES Strategy – Delivery Plan 2024-2029 November 2023 APPENDIX 2 Perth and Kinross Local Heat & Energy Efficiency Strategy Delivery Plan 2024-2029 DRAFT Perth & Kinross Council November 2023
Page 2
2 LHEES Strategy – Delivery Plan 2024-2029 November 2023 INTRODUCTION This document presents the first 5-year Delivery Plan (2024-2029) accompanying the first Perth and Kinross Local Heat and Energy Efficiency Strategy (LHEES) (2024-2045). This has been developed in partnership with key stakeholders and provides a strong basis for action for local communities, government, investors, developers and wider stakeholders, pinpointing areas for targeted intervention and early, low-regrets measures in the near to medium term. Due to the dynamic nature of this plan, and rapidly evolving regulatory, funding and policy landscapes, it is intended to be kept as a live document and published as a live plan in a digital planning platform being developed through Project RESOP (Regional Energy System Optimisation Planning) by Scottish and Southern Electricity Networks (SSEN) under Ofgem’s Network Innovation Allowance. The Delivery Plan will be reviewed regularly to ensure partners are able to respond flexibly to changes in need across Perth and Kinross particularly how actions would be funded. Full details of the LHEES Delivery Plan actions are detailed in the following tables.
Page 3
3 LHEES Strategy – Delivery Plan 2024-2029 November 2023 STRATEGIC PRIORITY 1: Delivering decarbonised heat within a transitioning energy system DELIVERY PRIORITY 1A: Heat Networks ID ACTION HOW WILL WE GET THERE OUTCOME OWNER STAKEHOLD ERS TIMESCALE PROGRESS FUNDING 1.1 Evaluate delivery models for deploying heat networks in Perth and Kinross, including establishing a Strategic Energy Partnership, and agree development route. Engage with Danish Mentoring Programme, SFT, ZWS, suppliers and other Councils to explore potential delivery models for Perth City centre heat networks and wider heat networks Identify opportunities for stakeholder support and engagement with heat network development PKC Zero Waste Scotland (ZWS), Scottish Futures Trust (SFT), Communitie s By Dec 24 Started Required, but source not identified 1.2 Explore feasibility of connecting non-domestic and domestic buildings to heat network by progressing the requirements of The Heat Networks (Heat Network Zones and Building Assessment Reports) (Scotland) Regulations 2023 following the LHEES Explore the suitability of non-domestic buildings within a heat network zone to connect to a heat network - linked to Council’s Estate decarbonization porgramme Power BI dashboard. Stakeholder s with buildings suitable for connection to heat network identified for engagement . PKC Building owners and estate managers, SSEN, SFT, ZWS By Dec 24 Not started Required, but source not identified
Page 4
4 LHEES Strategy – Delivery Plan 2024-2029 November 2023 modelling (ie finalising Review (Section 47) and preparing for Designation (Section 48). 1.3 Explore feasibility of connecting residential housing to heat networks Feasibility of connecting residential areas in proximity or between Potential Zones and potential impact of this with fuel poverty and energy savings. Investigate suitability of Council owned properties within the Inveralmond and North Muriton Industrial Estates to connect to a heat network Stakeholder s with buildings suitable for connection to heat network identified for engagement . PKC RSLs, HAs By Dec 24 Not started Required, but source not identified 1.4 Assess financial viability of heat network zones in relation to buildings connected Review viability of Selected Potential Zones and assess impact of heat demand errors and secondary school review on viability of zones Improved confidence in viability of Selected Potential Zones PKC SFT, ZWS, SG By Dec 24 Not started Required, but source not identified
Page 5
5 LHEES Strategy – Delivery Plan 2024-2029 November 2023 1.5 Assess financial viability of Perth City Centre Network Initiate development of an Outlline Business Case for heat network in the Perth City Centre PKC HNSU, SFT By Dec 24 Not started HNSU/Inter nal funding. Funding not Secured 1.6 Complete Building Assessment Reports (BARs) for required Council owned building Complete Building Assessment Reports (BARs) for required Council owned building prioritising those with a higher suitability for connection and located within potential Heat Network Zones. Facilitate and support other public sector organisations across Perth and Kinross to discharge this duty. Number of BARs completed PKC public sector organisation s By Dec 24 Not started Required, but source not identified
Page 6
6 LHEES Strategy – Delivery Plan 2024-2029 November 2023 1.7 Explore and quantify viability of low carbon or renewable heat sources for potential heat networks including though not limited to: • Deep geothermal • Heat from wastewater treatment plants/wastewater network • Ground Source heat pumps • Other sources of waste heat Work with stakeholders, including Scottish Water Horisons, Waste Heat Steering Group etc., to quantify the renewable or low carbon heat opportunities to support the designation of heat networks zones and inform development of feasibility studies and business cases for Potential Heat Network Zones Quantified assessment of the potential for low carbon heat supply to inform designation of Heat Network zones PKC Scottish Govenment, Scottish Water Horizons, SEPA By Dec 24 Not started Required, but source not identified 1.8 Work with Business Energy Scotland to engage the non-domestic sector to develop awareness and engagement campaigns, and identification and engagement with non- domestic building owners on suitability for heat networks, within Potential Zones. Support a local business programme that provides practical support to business owners. Use information generated as part of dedicated engagement plan for the non- domestic sector to inform this Increased awareness and buy in from non- domestic sector PKC Business Energy Scotland, Perth Chamber of Commerce, FSB, Business Gateway By Dec 2025 Not started Required, but source not identified
Page 7
7 LHEES Strategy – Delivery Plan 2024-2029 November 2023 1.9 Engage with Historic Environment Scotland and SSEN to assess considerations impacting viability of heat networks Engage with Historic Environment Scotland to understand implications that conservation area status might have on heat network development. Engage with SSEN on the impact of the proposed heat network on electricity infrastructure, and potential capacity for expansion of the proposed heat network Limitations for potential heat networks understood PKC Historic Environment Scotland (HES), SSEN By Dec 24 Not started Not required 1.10 Explore expansion and boundaries of potential heat network zones in the Perth City Centre Explore long-term potential for interconnection with Perth HMP, Perth Royal Infirmary, Perth College UHI, Perth Grammar School, nearby residential estates and through connecting the heat network to planned HMP, PRI, Perth College UHI, Perth Grammar, Perth Leisure Active By June 25 Not started Required, but source not identified
Page 8
8 LHEES Strategy – Delivery Plan 2024-2029 November 2023 redevelopment of the bus and railway station, Perth Leisure Centre and Dewars Centre. Further analysis of viability and potential socio-economic impacts of connecting Letham to a heat network (Zone 7) 1.11 Explore expansion and viability of potential heat network boundaries in Auchterarder, Kinross and Blairgowrie. Assess the suitability for nearby housing stock for connection to a heat network. Consider potential for connecting to heat networks at early stages of site development for future housing and employment sites. Appetite and viability of heat network in Selected Potential Zone understood PKC Housing Association, RSLs, Strategic Housing Forum By June 25 Not started Required, but source not identified
Page 9
9 LHEES Strategy – Delivery Plan 2024-2029 November 2023 1.12 Explore expansion and viability of potential heat network boundaries in Kinross. Engage with local community in Kinross and CATCH around appetite for connection of domestic properties to heat network. Conduct a deeper dive of suitability for housing stock in proximity to Loch Leven Leisure Centre for connection to a heat network (Zone 5). Consider potential for connecting to heat network at early stages of site development for future housing proposals near Loch Leven Leisure Centre Appetite and viability of heat network in Selected Potential Zone understood PKC CATCH By June 25 Started Required, but source not identified
Page 10
10 LHEES Strategy – Delivery Plan 2024-2029 November 2023 1.13 Explore expansion and viability of potential heat network boundaries in Blairgowrie. Explore opportunity for a heat network connecting Blairgowrie Campus, including connecting to residential area between the anchor loads, noting that low heat demand and low number of social housing (Zone 4). Engage with HEAT project and Proctor Production Facilities to understand existing project, appetite for connection to a heat network and potential for waste heat opportunity from the site. Appetite and viability of heat network in Selected Potential Zone understood PKC HEAT project, Proctor Production Facilities By June 25 Not Started Required, but source not identified
Page 11
11 LHEES Strategy – Delivery Plan 2024-2029 November 2023 1.14 Explore expansion and viability of potential heat network boundaries in Auchterarder. Explore feasibility of connecting residential areas in proximity to Auchterarder Community School (Zone 6) Feasibility and impact of connecting residential areas to a heat network understood PKC Communitie s, Housing developers By June 25 Not started Required, but source not identified
Page 12
12 LHEES Strategy – Delivery Plan 2024-2029 November 2023 STRATEGIC PRIORITY 1: Delivering decarbonised heat within a transitioning energy system DELIVERY PRIORITY 1B: Heat Pumps ID ACTION HOW WILL WE GET THERE OUTCOME OWNER STAKEHOLD ERS TIMESCALE PROGRESS FUNDING 1.15 Target social housing with immediate potential for heat pump retrofit Develop and implement a heat pump retrofit plan within the Council’s social housing stock, targeting properties first with inefficient, carbon intensive systems (e.g., LPG and Oil). Direct funding and advice for retrofit through EES:ABS and wider funding sources into Delivery Areas identified within the LHEES. Collaborate with housing associations to encourage heat pump installations. This could Strategic and delivery priorities used to target PKC Housing Association, RSLs, Strategic Housing Forum By Dec 24 started Social Housing Net Zero Heat Fund EES:ABS PKC, Housing Associatio ns
Page 13
13 LHEES Strategy – Delivery Plan 2024-2029 November 2023 involve providing support in securing funding and grants, such as the Social Housing Net Zero Heat Fund. The Council could also work to streamline the installation process for registered social landlords through partnerships with heat pump suppliers and installers. 1.16 Work with key delivery partners to target privately owned, off gas grid properties suitable for heat pump retrofit Continue to collaborate with local energy groups (e.g. HEAT Project) to engage with residents by providing informative materials to promote the benefits of heat pumps and promote existing funding options. Prioritise working with Strategic and delivery priorities used to target PKC Housing Associations , RSLs, Strategic Housing Forum, Communitie s, HEAT projects By Dec 27 Started Private EES:ABS
Page 14
14 LHEES Strategy – Delivery Plan 2024-2029 November 2023 private landlords that own large portfolios to decarbonise to their housing stock. Develop awareness campaigns to educate property owners about heat pumps, installation, and funding. 1.17 Work with key delivery partners to target off-gas private homes suitable that requires energy efficiency improvements to enable suitability for heat pumps Continue to collaborate with local energy groups (e.g. HEAT Project) to engage with residents by providing informative materials to promote the benefits of heat pumps and promote existing funding options. Prioritise working with private landlords that own large portfolios to decarbonise to their housing stock. Develop awareness campaigns Strategic and delivery priorities used to target PKC Housing Associations , RSLs, Strategic Housing Forum, Communitie s, HEAT projects By Dec 27 started Private EES:ABS
Page 15
15 LHEES Strategy – Delivery Plan 2024-2029 November 2023 to educate property owners about heat pumps, installation, and funding. 1.18 Work with key delivery partners to target privately owned non-domestic properties suitable for heat pump and retrofit Continued engagement with the private sector, to identify barriers associated with building retrofit to provide tailored solutions aimed at addressing the specific challenges. Work with Business Energy Scotland to engage the non- domestic sector to develop awareness and engagement campaigns, and identification and engagement with non- domestic building owners. Promote awareness of funding incentives available for Strategic and delivery priorities used to target PKC Communitie s, HEAT projects, Businesses By Dec 27 started Private EES:ABS
Page 16
16 LHEES Strategy – Delivery Plan 2024-2029 November 2023 small and medium-sized enterprises (SMEs) 1.19 Work with SSEN to align investment planning and grid reinforcement to support heat pump roll out. Use RESOP and LAEP+ platform to collate and share data and feed into SSEN investment plan Strategic and delivery priorities used to target PKC SSEN By Dec 27 started NA
Page 17
17 LHEES Strategy – Delivery Plan 2024-2029 November 2023 STRATEGIC PRIORITY 2: Improving buildings’ energy efficiency aiming for affordable warmth and regulatory compliance DELIVERY PRIORITY 2A: Improving buildings’ energy efficiency to meet regulatory standards ID ACTION HOW WILL WE GET THERE OUTCOME OWNER STAKEHOLD ERS TIMESCALE PROGRESS FUNDING 2.1 Target social housing and privately owned homes with energy efficiency requirements to meet regulatory standards Prioritise social housing with poor energy efficiency but relatively low intervention costs for "quick wins.” Prioritise areas with substantial energy savings and CO2 emissions reductions potential at a lowest cost. Collaborate with partners and Scottish Government to incentivise improving energy efficiency in privately owned homes. Direct funding and advice for retrofit through EES:ABS and Strategic and delivery priorities used to target PKC Housing Association RSLs, Strategic Housing Forum, Scottish Government By Dec 24 started EES:ABS Private PKC
Page 18
18 LHEES Strategy – Delivery Plan 2024-2029 November 2023 wider funding sources into Delivery Areas identified within the LHEES. 2.2 Work with delivery partners to target non-domestic buildings that require retrofit to meet regulatory targets Facilitate collaboration between the public and private sectors and align strategic energy planning potentially through Strategic Energy Partnership. Promote awareness of funding incentives available for small and medium-sized enterprises (SMEs) Continued engagement with the private sector, to identify barriers associated with building retrofit to provide tailored solutions aimed at addressing the specific challenges. Work with Business Strategic and delivery priorities used to target PKC Business Energy Scotland, Public sector non domestic By Dec 25 Not started Private
Page 19
19 LHEES Strategy – Delivery Plan 2024-2029 November 2023 Energy Scotland to engage the non- domestic sector to develop awareness and engagement campaigns, and identification and engagement with non- domestic building owners
Page 20
20 LHEES Strategy – Delivery Plan 2024-2029 November 2023 STRATEGIC PRIORITY 2: Improving buildings’ energy efficiency aiming for affordable warmth and regulatory compliance DELIVERY PRIORITY 2B: Improve buildings’ energy efficiency aiming for affordable warmth ID ACTION HOW WILL WE GET THERE OUTCOME OWNER STAKEHOLD ERS TIMESCALE PROGRESS FUNDING 2.3 Target delivery areas for social housing that does not meet regulations (e.g., below EPC B) identified for energy efficiency retrofit Prioritise social housing likely to experience a greater reduction in fuel poor households due to the implementation of low-cost retrofit measures. Strategic and delivery priorities used to target PKC Housing Association RSLs By Dec 25 started Required, but source not identified 2.4 Target deliver areas for privately owned homes that do not meet targets (e.g., below EPC C) and potential suitability for EEPS:ABS funding Promote retrofitting in targeted areas though awareness campaigns about available funding to support fuel-poor households. Direct funding and advice for retrofit through EES:ABS and wider funding sources into Delivery Areas identified within the LHEES Strategic and delivery priorities used to target PKC Communitie s, HEAT projects, By Dec 25 Not started EES:ABS
Page 21
21 LHEES Strategy – Delivery Plan 2024-2029 November 2023 2.5 Target privately owned domestic properties below EPC band E Promote retrofitting in targeted areas though awareness campaigns about available funding to support fuel-poor households. Direct funding and advice for retrofit through EES:ABS and wider funding sources into Delivery Areas identified within the LHEES Strategic and delivery priorities used to target PKC Communitie s, HEAT projects, Businesses By Dec 25 Not started EES:ABS
Page 22
22 LHEES Strategy – Delivery Plan 2024-2029 November 2023 SUPPORTING MECHANISMS ID ACTION HOW WILL WE GET THERE OUTCOME OWNER STAKEHOLD ERS TIMESCALE PROGRESS FUNDING Taking a Whole Energy Systems Approach 3.1 Develop a sustainable data sharing model and platform. Develop the data and mapping capability and tools to support the LHEES and LAEP process Work with RESOP Project (Regional Energy System Optimisation Planning) and partners to migrate LHEES/LAEP outcomes to LAEP+ platform Live data platform for LHEES/LAE P PKC SSEN/AITL/ ARUP By Dec 24 Started SSEN Innovate UK 3.2 Develop decarbonisation pathways through to project business case development. Engage as part of RESOP pilot and potential IUK funding to develop product roadmap to support standardisation of decarbonisation pathways through to business case Strategic investment framework and delivery plan for key partners SSEN SSEN/AITL By Dec 24 Started SSEN Innovate UK
Page 23
23 LHEES Strategy – Delivery Plan 2024-2029 November 2023 development to provide a prospectus for investment with key partners 3.3 Biennial review of actions that could be added to the Delivery Plan and/or are enabling actions once initial ones are completed. Determine whether the outcomes of EESSH2 review necessitate a re- run of the LHEES models - Review Council Decarbonisation Plan and LAEP outcome to integrate area and building level actions for specific geographic areas and building types (archetypes) - maintaining a "live" delivery plan incorporating the actions of key stakeholders Improved knowledge, awareness and accessibility to key policies, targets and data to inform the ongoing development and live delivery of LHEES PKC SSEN/AITL/ ARUP Ongoing Not started Not required
Page 24
24 LHEES Strategy – Delivery Plan 2024-2029 November 2023 3.4 Develop a sustainable data sharing model and platform to address gaps and improve future LHEES iterations Ensure appropriate feedback mechanisms between SCARF/HES and EST at regular intervals to enable planning to reflect progress towards building decarbonisation. Enable a join up approach across organisations by removing barriers to data sharing (e.g. Warmworks, HES, EST, PKC and SSEN) Improved data for future LHEES. PKC SCARF/HES /EST/WARM WORKS Ongoing Started Not required
Page 25
25 LHEES Strategy – Delivery Plan 2024-2029 November 2023 Improve fuel poverty reporting Work with Energy Savings Trust and CDT to improve fuel poverty reporting in Home Analytics. Improved data for future LHEES. LHEES more accurate helping to identify further low risk and high certainty actions PKC EST By Dec 25 Started Not required 3.5 Ensure data for installations and Council housing stock is updated. Work with EST and PKC CDT to ensure updated data for installations and Council housing stock included in Home Analytics as part of a wider sustainable data model Improved data for future LHEES. PKC EST By Dec 25 Started Not required
Page 26
26 LHEES Strategy – Delivery Plan 2024-2029 November 2023 3.6 Liaise and inform development of a Climate Intelligence Service Work with Improvement Service and partners to inform development of a Climate Intelligence Service to meet LHEES requirements and build capacity within other Local Authorities to improve decision making for area-wide emissions reduction by providing the data and tools, and building skills Improved data model for future LHEES Improve ment Service, Edinburg h Climate Change Institute, the Sustaina ble Scotland Network, COSLA and Scottish Governm ent PKC By Dec 24 Started COSLA funding 3.7 Produce a Council Estate Decarbonisation Plan The Council is currently undertaking work to design and deliver a major programme of retrofitting both for its domestic and non- domestic building stock, Improved data and planning PKC By Dec 24 Started PKC
Page 27
27 LHEES Strategy – Delivery Plan 2024-2029 November 2023 focusing on how decarbonising projects should be prioritised. The work will consider detailed programming, risk analysis, supply chain capacity and the Council’s operating model, to identify how the Council could progress and where critical gaps exist (such as in the local retrofit supply chain) that the Council can start to influence in preparation for major retrofit projects.
Page 28
28 LHEES Strategy – Delivery Plan 2024-2029 November 2023 3.8 Develop a decision-making toolkit to filter projects and develop business cases The Council has developed a toolkit that will allow us to filter projects and develop business cases to triage delivery actions and areas into a pipeline of investable energy projects based on a range of priorities. This will lead to the development of an investment programme enabling Smart Local Energy Systems. Improved business case development PKC By Dec 24 started PKC
Page 29
29 LHEES Strategy – Delivery Plan 2024-2029 November 2023 Developing green skills and the capacity of the supply chain 3.9 Quantify risk for installers Work with HES/SCARF to quantify risk for installers, especially in rural areas by exploring the number of referrals vs. the number of installs to identify the skills gap Identification of existing skills development programmes and partnerships that could support LHEES delivery in PKC. PKC HES/SCARF By Dec 24 Not started Not required 3.10 Identify existing skills and partnerships Work with Skills Board Tay Cities Region Deal and Clean Growth Platform to identify existing skills and partnerships that could support LHEES delivery Identification of existing skills development programmes and partnerships that could support LHEES PKC Tay Cities Region Skills Board and Clean Growth Platform By Dec 24 Not started Not required
Page 30
30 LHEES Strategy – Delivery Plan 2024-2029 November 2023 delivery in PKC. 3.11 Explore opportunities to further develop local skills and supply chains. Take action to increase the number of skilled workers in the region, to help towards closing the skills gap. Skills required include retrofit design and coordination, installation of retrofit measures and understanding of whole house systems, ventilation and heating design and installation, Strong and resilient local supply chain for retrofit and low carbon heat technologies . PKC CITB, Perth UHI, College, Tayside Region Deal Skills Board (others?) By Dec 24 Not started Required, but source not identified
Page 31
31 LHEES Strategy – Delivery Plan 2024-2029 November 2023 renewables design and installation. Build an understanding of the current and future skills and training requirements to “green” the construction sector to ensure we can deliver quality homes with affordable warmth, zero emissions and SMART technology. Work in partnership with the CITB, local construction companies and training providers including Perth UHI to ensure Perth and Kinross is well placed to provide appropriate reskilling and training opportunities.
Page 32
32 LHEES Strategy – Delivery Plan 2024-2029 November 2023 Seek to incorporate a commitment within publicly funded contracts to support training, retraining and upskilling in the future/ existing workforce to support supply chain development. 3.12 Explore opportunities to further develop local skills and supply chains. ‘Engage with Scottish Enterprise to explore how LHEES can shape planning of upcoming events to articulate opportunities and raise awareness of potential solutions and innovation across the industry Understand opportunities for innovation and technologies across the industry PKC Scottish Enterprise, Supplier Developmen t Programme By Dec 25 Not started Required, but source not identified Working in partnership with communities to build community wealth and wellbeing
Page 33
33 LHEES Strategy – Delivery Plan 2024-2029 November 2023 3.13 Help develop existing and create new community renewable energy projects to support community energy projects across Perth and Kinross. Share LHEES priorities to inform and be informed by community groups and identify opportunities for projects Understand opportunities to support community energy projects PKC Community groups e.g. CATCH, HEAT project By Dec 25 Not started Not required 3.14 Develop and support Community-led actions to address non-technical barriers to net zero. Use experience from ‘Dialogue to accelerate Net Zero’ project funded by Innovate UK to scale up Understand opportunities to support community energy projects PKC Community groups e.g. HEAT project By June 25 started Innovate UK
Page 34
34 LHEES Strategy – Delivery Plan 2024-2029 November 2023 Mobilising partners and public and private investments for projects 3.15 Explore the development of a Strategic Energy Partnership and possible procurement route to unlock delivery of, though potentially not limited to, heat networks. Work with Scottish Futures Trust to identify commercial model and procurement route. Test the market via Prior Information Notice (PIN) and make recommendations to the Council Improved business case development and delivery PKC SFT By Dec 24 Started Not required 3.16 Develop a programme of investable projects and an investment plan for taking new projects forward that are linked to priorities Develop from the LHEES and LAEP a programme of investable projects and an investment plan that can be taken to the market for funding Investment plan comprising a series of projects PKC SG, UKIB, SNIB By Dec 27 Not started Required, but source not identified
Page 35
35 LHEES Strategy – Delivery Plan 2024-2029 November 2023 3.17 Align LHEES/LAEP investment planning with utilities investment plans Progress the staged approach set out in the decision-making toolkit guidance to support potential projects develop towards strategic and outline business case and beyond. Progress potential projects through a systematic approach towards development and execution. PKC SSEN, SGN By Dec 24 Not started Not required Aggregate projects across Scotland to create a programme of projects with Scottish Government and other local authorities to promote larger publicly funded schemes to help support opportunities and projects arising from LHEES Seek to work with Scottish Government and other local authorities to develop a new mechanism to support residents to affordably retrofit their homes. Long-term pipeline of funded projects. PKC Scottish Government, SNIB By Dec 28 Not started Required, but source not identified
Page 36
36 LHEES Strategy – Delivery Plan 2024-2029 November 2023 3.18 Work with key stakeholders to develop/align Priorities, success factors, targets and ability to support onward delivery of LHEES strategy and projects. Identify opportunities for stakeholder support with LHEES delivery Identify opportunities for stakeholder support with LHEES delivery PKC Key stakeholders By Dec 24 Not started Not required 3.19 Identify existing or planned energy retrofit and net zero energy projects by universities, NHS Boards and other organisations with large estates to consider how the LHEES Delivery Plan can build on any new or emerging projects. Progress the staged approach set out in the decision-making toolkit guidance to support potential projects develop towards strategic and outline business case and beyond. Progress potential projects through a systematic approach towards development and execution. PKC NHS, large estates By Dec 27 Not started Required, but source not identified
Page 37
37 LHEES Strategy – Delivery Plan 2024-2029 November 2023 GOVERNANCE ID ACTION HOW WILL WE GET THERE OUTCOME OWNER STAKEHOLD ERS TIMESCALE PROGRESS FUNDING 4.1 Create a Council’s LHEES co-ordination team Identify existing staff and recruit additional staff Improved co-ordination PKC By May 24 PKC SG 4.2 Update data and support access to data to all stakeholders Co-ordination team to track and update data Improved data PKC LHEES Steering Group ongoing started Not required 4.3 Develop and co-ordinate a communication and engagement plan Create an internal engagement pack to support communication Create a public facing prospectus that sets out the long-term vision and outcomes for the LHEES Strategy, the near-term actions it is planning, and an invitation to engage. Communicat ions strategy in place and material developed PKC/AR UP SG By May 24 Started Not required 4.4 Develop and update a risk register for all actions Co-ordination team to set-up with LHEES Steering Group Improved risk managemen t PKC LHEES Steering Group By May 24 Not started Not required
Page 38
38 LHEES Strategy – Delivery Plan 2024-2029 November 2023 4.5 Produce monitoring reports Co-ordination team to produce monitoring reports will be produced every quarter for the Steering Group and the Board and annually for the Climate Change & Sustainability Committee with a full review of the Strategy and Delivery Plan every 5 years. The next full review will be in 2029. Improved monitoring PKC LHEES Steering Group Ongoing Not started NA 4.6 Prepare and co-ordinate LHEES Strategy and Delivery Plan reviews Co-ordination team to prepare a project plan for reviews Improved monitoring and evaluation PKC LHEES Steering Group By May 24 Not started Not required 4.7 Develop and provide support to project managers Co-ordination team to prepare templates, best practices and a training plan. Improved monitoring and evaluation PKC LHEES Steering Group By May 24 Not started Not required 4.8 Coordinate and support LHEES Steering Group Co-ordination team to organize meetings, agendas and communication Improved co-ordination PKC LHEES Steering Group Ongoing Not started Not required
Page 39
39 LHEES Strategy – Delivery Plan 2024-2029 November 2023 4.9 Develop a communications strategy for LHEES delivery comprising long term vision and outcomes for LHEES and short- medium terms actions including awareness raising measures for support and advisory services and home upgrades. Scottish Government to "deliver a public communications programme to raise awareness of the support and advisory services available and to encourage home upgrades, in order to maximise uptake of these schemes" Improved public awareness of LHEES Scottish Governm ent EST and HES TBD Started Required, but source not identified