Appendix 3 – Flooding at Feus Road, Perth 
Advantages
• Works would protect properties from flooding up to the 1 in 30 year rainfall event – minor residual
flooding would still occur (on the road carriageway);
• Former Crieff Road nursery site could be re-used to provide below ground storage;
• Removal of surface water from combined sewer system has wider benefits – reduced water
treatment energy use/CSO spills;
• Phased approach – could be delivered over multiple investment periods.
Disadvantages
• There will still be a risk of flooding to properties during rainfall events that exceed the design standard
(the 1 in 30 year flood), although the works would reduce the frequency and total volume of flooding;
• No allowance for increase in future flood risk due to the effects of climate change
• High Capital cost (£10.7M)
• Benefit cost ratio (0.54) is below 1 .0 – the estimated cost of the works therefore exceeds the
potential benefits over time. The works are therefore not economically viable.