Perth and Kinross Council · 19 December 2022
Back to Climate Change and Sustainability Committee — 19 December 2022 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
2.4.4 Kinross, Milnathort And Glenrothes (02/10/03) Kinross, Milnathort and Glenrothes have been designated as a potentially vulnerable area due to the various risks of flooding, within these areas. Surface water pluvial flooding is the most prevalent flooding facing Glenrothes and Markinch, whilst fluvial flooding from the Lochty Burn is the most prevalent flooding risk facing Kinglassie. The main source of flooding in Kinross is from surface water and river flooding from the South Queich, the Gelly Burn and the Clash Burn. The main source of flooding in Milnathort is river flooding from the Back Burn, however there is also a risk of surface water flooding. There are three target areas within this potentially vulnerable area, which have been the focus of further assessment. These are listed below. Further information on the objectives and actions to manage flood risk within this area is provided below. List of target areas Kinross (target area 239) Milnathort (target area 303)
Page 2
Local Flood Risk Management plan datasheet Kinross (target area 239) Summary Location Map The town of Kinross is located around 20km south of Perth. The main sources of flooding in Kinross are surface water and river flooding from the South Queich, Gelly Burn and Clash Burn. The local authority has carried out a flood study in this area in support of the proposed flood scheme. The study indicates that 129 homes and 55 businesses are currently at risk of flooding from the South Queich, the Gelly Burn and the Clash Burn. Current understanding of Flood Risk This section provides a summary of information, which has helped to develop an understanding of flood risk in the area. Since 2011 SEPA has developed and updated national assessments of flooding from rivers, surface water and coastal sources. The national assessment for river flooding is improved by flood study work supporting the ongoing development of proposals for the South Kinross Flood Protection Scheme. The understanding of surface water flooding was also improved by Scottish Water’s sewer flood risk assessment. There is a long record of flooding in this target area. Flooding occurred in January 1993, January 1999, December 2006, January and August 2008 and November 2009. In February 2020 a number of homes and roads suffered river flooding. Most recently, flooding was recorded in August 2020 when homes flooded as a result of unprecedented rainfall in the area. Objective ID Description Avoid flood risk 2391 Avoid inappropriate development that increases flood risk in Kinross Avoid flood risk 2392 Avoid an increase in flood risk by the appropriate management and maintenance of the South Kinross Flood Protection Scheme
Page 3
Prepare for flooding 2393 Prepare for current flood risk and future flooding as a result of climate change in Kinross Reduce flood risk 2394 Reduce the risk of river flooding from the South Queich, Gelly Burn and Clash Burn in South Kinross Reduce flood risk 2395 Reduce the risk of surface water flooding in Kinross Action ID Kinross 23901 Action Type Flood Protection Scheme Action Delivery Lead Perth and Kinross Council Indicative Delivery 2022 - 2025 Description The development of the outline design for the South Kinross Flood Protection Scheme will continue and will consider long term flood risk and climate change. The development of the proposals will also be informed by community engagement. The scheme will then progress to the statutory process set out under the Flood Risk Management (Scotland) Act 2009. The detailed design will be completed thereafter. Following completion of the detailed design, the proposed scheme will be procured and will progress to construction. As built drawings will be made available to SEPA, for inclusion in the Scottish Flood Defence Asset Database, flood map updates and flood warning scheme updates. Funding The South Kinross Flood Protection Scheme will be subject to available capital funding (up to 80% capital grant funding from the Scottish Government with the remaining funding being provided from Perth & Kinross Council's capital programme). Coordination The South Kinross Flood Protection Scheme will be coordinated through the Forth Estuary Local Plan District Partnership. Action ID Kinross 23902 Action Type Maintain Flood Protection Scheme Action Delivery Lead Perth and Kinross Council Indicative Delivery On-going Description Once built, Perth and Kinross Council will implement an inspection and maintenance regime for the South Kinross Flood Protection Scheme. Funding The maintenance of flood protection schemes will be subject to funding from Perth and Kinross Council's revenue budget.
Page 4
Coordination Perth & Kinross Council's Roads Maintenance Partnership will maintain any existing flood protection schemes and works through a programme of inspections carried out in accordance with the recommendations set out in the scheme maintenance manuals. Maintenance works will be coordinated with SEPA, NatureScot, landowners and other stakeholders as required. Action ID Kinross 23903 Action Type Sewer Flood Risk Assessment Action Delivery Lead Scottish Water Indicative Delivery 2023 - 2025 Description Scottish Water will undertake a modelling assessment in the Kinross sewer catchment to improve knowledge and understanding of flood risk in this area as required under Section 16 of the Flood Risk Management (Scotland) Act 2009 Funding Funding for this action is secured within Scottish Water's business plan. Coordination Outputs of this modelling assessment will be shared with local authorities and SEPA. Action ID Kinross 23904 Action Type Surface Water Management Plan Action Delivery Lead Perth and Kinross Council Indicative Delivery 2024 - 2026 Description Perth and Kinross Council will develop a surface water management plan for Kinross. This will improve the understanding of surface water flood risk, and in the longer term look at possible action to manage the risk. The results of the sewer flood risk assessment will be considered. Current and long term flood risk will be considered and if climate change impacts are found to be significant, surface water management will include adaptive planning. Funding The surface water management plan will be subject to funding from Perth and Kinross Council’s revenue budget. Coordination The surface water management plan is programmed to commence in the 2024/25 financial year. Perth and Kinross Council will engage consulting engineers to investigate the surface water flood risk and identify potential options for managing that risk. The surface water management plan will be coordinated through the Forth Estuary Local Plan District Partnership. Scottish Water will work with and support surface water management planning through ensuring that best available
Page 5
knowledge and data is used to input into the surface water management plans. Action ID Kinross 23905 Action Type Community Engagement Action Delivery Lead SEPA and Responsible Authorities Indicative Delivery On-going Description Community engagement will continue in connection with on- going projects and activities. This will include engaging with the community on the development of the flood scheme proposals and the surface water management plan (Action ID's 23901 & 23904). Funding Community engagement activities will be subject to funding from Perth and Kinross Council’s revenue budget. SEPA's community engagement activities are funded by the Scottish Government through SEPA’s grant in aid settlement. Scottish Water is funded by customer charges as set by their economic regulator; all business activities required under this action by Scottish Water are accounted for in their capital or operational expenditure. Coordination The action delivery lead is Perth and Kinross Council. Awareness raising and community engagement will take place around any projects and will be coordinated through the Local Plan District Partnership. Action ID Kinross 23906 Action Type Community Resilience Group Action Delivery Lead Community Indicative Delivery On-going Description Perth and Kinross Council will continue to liaise with the Kinross Flood Resilience Group. Funding Funding for Community resilience groups will be provided by private individuals, businesses, organisations or communities at risk of flooding. Coordination Perth and Kinross Council will work with the Kinross Flood Resilience Group to reduce flood risk, improve preparedness and increase resilience against flooding. The Council will continue to co-ordinate with the Kinross Flood Resilience Group on a priority needs basis where resources allow. The Council will coordinate community resilience groups with any related actions.
Page 6
Local Flood Risk Management plan datasheet Milnathort (target area 303) Summary Location Map Milnathort is a small town in Perth and Kinross located just north of Kinross. The main source of flooding in Milnathort is river flooding, however there is also a risk of surface water flooding. There are approximately 200 people and 130 properties currently at risk from flooding. This is likely to increase to 300 people and 180 properties by the 2080s due to climate change. A flood protection scheme is in place in the area, protecting homes and businesses to a 1 in 100 year standard of protection. Current understanding of Flood risk This section provides a summary of information, which has helped to develop an understanding of flood risk in the area. Since 2011 SEPA has developed and updated national assessments of flooding from rivers, surface water and coastal sources. The national assessment for surface water is improved by an on-going surface water management plan, a sewer flood risk assessment and flood study work in support of a proposed surface water flood protection scheme. National understanding of river flooding is improved by flood study work carried out for the existing Milnathort Flood Protection Scheme on the Back Burn. There is a long record of flooding in this area. The Back Burn flooded in January 1993, affecting properties in the town centre. In December 2006 a prolonged period of heavy rainfall caused flooding to houses and a local pub, necessitating residents to be evacuated from their homes. The most recent significant flood was recorded in July 2013 when surface water flooded a number of homes and businesses. Since then, smaller scale surface water flooding occurred in 2020 but did not cause any damage to properties.
Page 7
Objective ID Description Avoid flood risk 3031 Avoid inappropriate development that increases flood risk in Milnathort Avoid flood risk 3032 Avoid an increase in flood risk by the appropriate management and maintenance of the flood protection schemes in Milnathort Prepare for flooding 3033 Prepare for current flood risk and future flooding as a result of climate change in Milnathort Reduce flood risk 3034 Reduce the risk of surface water in Milnathort Action ID Milnathort 30301 Action Type Flood Protection Scheme Action Delivery Lead Perth and Kinross Council Indicative Delivery 2022 - 2025 Description The development of the outline design for the Milnathort Surface Water Flood Protection Scheme will continue and will consider long term flood risk and climate change. The development of the proposals will be informed by community engagement. The scheme will then progress to the statutory process set out under the Flood Risk Management (Scotland) Act. The detailed design will be completed thereafter. Following completion of the detailed design, the proposed scheme will be procured and will progress to construction. As built drawings will be made available to SEPA, for inclusion in the Scottish Flood Defence Asset Database, flood map updates and flood warning scheme updates. Funding The Milnathort Surface Water Flood Protection Scheme will be subject to available capital funding (up to 80% capital grant funding from the Scottish Government with the remaining funding being provided from Perth & Kinross Council's capital programme). Coordination The Milnathort Surface Water Flood Protection Scheme will continue to be coordinated through the Forth Estuary Local Plan District Partnership. Action ID Milnathort 30302 Action Type Maintain Flood Protection Scheme Action Delivery Lead Perth and Kinross Council Indicative Delivery On-going
Page 8
Description Maintenance of the existing Milnathort Flood Protection Schemes (on the Back Burn) will continue in accordance with the inspection and maintenance regime. Maintenance of the new Milnathort Surface Water Flood Protection Scheme will commence once construction of the scheme is complete. Funding The maintenance of flood protection schemes will be subject to funding from Perth and Kinross Council's revenue budget. Coordination Perth & Kinross Council's Roads Maintenance Partnership will maintain any existing flood protection schemes and works through a programme of inspections carried out in accordance with the recommendations set out in the scheme maintenance manuals. Maintenance works will be coordinated with SEPA, SNH, landowners and other stakeholders as required. The maintenance of the flood scheme/works will also be coordinated with related actions. Action ID Milnathort 30303 Action Type Sewer Flood Risk Assessment Action Delivery Lead Scottish Water Indicative Delivery 2024 - 2026 Description Scottish Water will undertake a modelling assessment in the Milnathort sewer catchment to improve knowledge and understanding of flood risk in this area as required under Section 16 of the Flood Risk Management (Scotland) Act 2009. Funding Funding for this action is secured within Scottish Water's business plan. Coordination Outputs of this modelling assessment will be shared with local authorities and SEPA. Action ID Milnathort 30304 Action Type Surface Water Management Plan Action Delivery Lead Perth and Kinross Council Indicative Delivery 2022 - 2023 Description The development of a surface water management plan for Milnathort in on-going. This is being coordinated with the development of the proposed Milnathort Surface Water Flood Protection Scheme (Action ID 30301). Current and long term flood risk is being considered and, if climate change impacts are found to be significant, the plan will consider how the area can adapt to increased flood risk in the future.
Page 9
Funding The surface water management plan will be subject to funding from Perth and Kinross Council’s revenue budget. Coordination Work to develop a surface water management plan is on- going. Perth and Kinross Council engaged consulting engineers, Sweco UK Ltd, to investigate the surface water flood risk and identify potential options for managing that risk. The plan/study will be coordinated through the Forth Estuary Local Plan District Partnership. Scottish Water will work with and support surface water management planning through ensuring that best available knowledge and data is used to input into the surface water management plans. Action ID Milnathort 30305 Action Type Community Engagement Action Delivery Lead SEPA and Responsible authorities Indicative Delivery On-going Description Community engagement will continue in connection with on- going projects and activities. This will include engaging with the community on the development of the flood scheme proposals and the surface water management plan (Action ID's 30301 & 30304). Funding Community engagement activities will be subject to funding from Perth and Kinross Council’s revenue budgets. SEPA's community engagement activities are funded by the Scottish Government through SEPA’s grant in aid settlement. Scottish Water is funded by customer charges as set by their economic regulator, all business activities required under this action by Scottish Water are accounted for in their capital or operational expenditure. Coordination Community engagement will be coordinated through the Local Plan District partnership between SEPA and the responsible authorities. SEPA and the responsible authorities will use any studies, projects and flood schemes to engage with communities and raise awareness of flood risk. Communications activity will be coordinated through existing arrangements within Local Plan District Partnerships. Information will be disseminated through website, social media and other community engagement activity.