Democracy Spraffa

Introduction of Charging for Electric Vehicles

Perth and Kinross Council · 24 August 2022
Back to Climate Change and Sustainability Committee — 24 August 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PERTH AND KINROSS COUNCIL 
Climate Change and Sustainability Committee 
24 August 2022 
Introduction of Charging for Electric Vehicles 
Head of Planning & Development (Report No. 22/191) 
PURPOSE 
1.1 This report invites members to consider the issues associated with the
Council’s current and future Electric vehicle (EV) charging infrastructure, and
to approve the introduction of tariffs to recover the energy and support costs
of providing this service. 
2. RECOMMENDATIONS
2.1  It is recommended that the Committee:- 
• notes the work undertaken to review potential options for charging. 
• approves Option 3 and the recommended tariffs set out below with an
introduction date of 1 January 2023. 
• requests that the Executive Director (Communities) keep tariff rates
under review during the year, with delegation to amend the tariff to
ensure that future costs continue to be recovered, alongside an annual
review to be undertaken as part of the budget process. 
3. STRUCTURE OF REPORT
3.1 This report is structured over the following sections: 
• Section 4: Background/Main Issues 
• Section 5: Proposals 
• Section 6: Conclusion 
• Appendices 
4. BACKGROUND / MAIN ISSUES 
Strategic context & Background 
Why is EV important: 
4.1 Wider strategic emission targets are set both nationally through the Scottish
Government’s Climate Change Plan, and locally through the Council’s Climate
Change Action Plan to decarbonise the transport network. The increased
transition to electric vehicles and the necessary increase in charging points

Page 2

will play a key role in achieving these targets. However, the costs associated
with operating, and maintaining, this infrastructure are anticipated to continue
to increase.  Until relatively recently, electric vehicles were seen as a niche
part of the overall transport network with a very limited choice in vehicles.
However, that is not now the case, with most major mainstream vehicle
producers planning for the growth of the EV market. Preliminary work as part
of the Climate Change Action Plan has identified the growth in Electric
Vehicles as crucial in achieving wider targets for transport emissions. 
Existing Revenue Costs: 
4.2 While initially the provision of free charging was encouraged by the Scottish
Government to incentivise the early adoption of electric vehicles, continuing to
cover the costs of the electricity consumed, along with ongoing maintenance
costs, will create an unsustainable pressure on the Council budget. The
standalone costs solely for facilitating EV charging infrastructure for the
financial year 2021/22 was approximately £120k with estimated electricity
supply costs for 2022/23 currently projected to be in the region of £230k. It is
likely, given the issues with energy costs in all sectors of the market and with
additional electric vehicles on the network, these costs will only increase. 
Capital Funding for charging facilities: 
4.3 To date, the Council’s publicly available EV facilities have been funded
through the Scottish Government’s Local Authority Installation Capital Grant
Programme which is now no longer available. In January 2022, the Scottish
Government published its Draft Vision for Scotland’s Public Electric Vehicle
Network and launched a new fund for local authorities to bid into. From this
fund, the Council has been awarded an initial £60k to develop a public electric
vehicle charging Strategy and Infrastructure Expansion Plan. This will form
the basis of future funding bids to the Scottish Futures Trust’s Electric Vehicle
Infrastructure Fund. 
4.4 The availability, accessibility and reliability of EV charging facilities must
progress in line with increasing customer demand. Given the very varied
geography across the Council area, careful planning and consideration will be
given to serve the residents of all our communities.  This is to ensure that no
community or area is disadvantaged, especially where there is no private
operator provision. This is an area of work that will be taken forward over the
coming months.
Collaborative Working: 
4.5 In recognition of the cross-boundary issues of EV charging, Perth & Kinross
Council is working with regional partners through the development of a
Regional EV Strategy published in November 2019 by TACTRAN (the
Regional Transport Partnership for Angus, Dundee City, Perth & Kinross and
Stirling Council areas). This is to deliver EV charging infrastructure in a
coordinated and collaborative way.

Page 3

4.6 The Regional EV Strategy, Regional EV Delivery Plan, Baseline Report and
Demand Forecast are available to download from the TACTRAN website. 
4.7 Discussions have taken place with partner organisations at the Regional EV
Steering Group, which included Transport Scotland.  These have confirmed
that a move towards charging would be welcomed at a strategic level. 
4.8 It should be noted that under the Local Government (Scotland) Act 1973,
Scottish Local Authorities are not permitted to make profit. Therefore, any
potential revenue generated over  the direct costs associated with the
provision of the EV chargers and energy will need to be reinvested in the
network. A stable funding stream to support asset investment & maintenance
is crucial to ensure network reliability and to build users’ confidence to allow
the switch to low carbon travel. 
Private network operators: 
4.9 There are now several national charge points operators (CPOs) with locations
within Perth & Kinross and the wider region. All operate on a single cost per
kWh, ranging from around 28p – 70p per kWh, with some offering discounts
as part of a subscription model and some offering free charging at certain
sites on lower powered chargers (e.g. supermarkets). 
4.10 Most commercial networks offer differential rates depending on charge point
output rates, with lower costs for low powered (7-22kW) and higher costs
associated with rapid/ultra-rapid chargers (50-350kW). 
4.11 Perth has already benefited from significant investment from ultra-rapid
private charge point network operators, with Ionity (4x350kW), Tesla (12 x
150kW), BP Pulse (3x150kW) all already offering 150kW-350kW charging.
Gridserve has recently announced its intention to construct a hub at Perth
Dobbies. 
4.12 Transport Scotland have also confirmed that approaches have been made to
the private sector to assume greater responsibility for installation, operation
and maintenance of public EV charge points as well as accepting any
potential revenue risk. 
4.13 This could be achieved, for example, through 5-to-10-year concession-type
agreements with local authorities and other public sector partners. This is
clearly an avenue of interest to the Council in future discussions.
4.14 However, to ensure continued investment from the private sector, it is
important that realistic costs are charged for public charging, to ensure that a
business case can be made for future private sector investment. In reality, it is
likely, there will be very limited private sector interest in investing in EV
facilities if the public sector continue to offer low or discounted tariff levels.

Page 4

Other Local Authorities: 
4.15 There are currently a wide range of tariffs and associated charges across
Scotland’s local authority areas for EV charging and full details of all Scottish
Local Authority tariffs are shown in Appendix 2. Dundee City Council also
offer a discounted rate for their residents of 15p/kWh on non-rapid chargers
(7-22kW), although this is a subsidised arrangement. 
PKC operational arrangements: 
4.16 The Council owned assets (as detailed in Appendix 1) are all administered by
Charge Place Scotland (CPS).  This was set up by Transport Scotland who
provide this service for all local authorities in Scotland as well as private
sector businesses which have installed charge points through Transport
Scotland funding streams. 
4.17 This provides the administrative back office, including tariff setting and
invoicing of users who receive an invoice monthly for all usage across the
CPS network. Administrative costs associated with the CPS network will
continue to be paid by Transport Scotland up until 2025. The arrangements
beyond this period are unknown.  However, if future costs have to be met by
the Council, this will need to be incorporated within an amended tariff level. 
4.18 The historical usage data of the Council’s charge points is shown in Table 1
below and it highlights the significant growth in use since the first charge
points were installed in 2013.The data for the first six months of 2022 show
that this trend of significant growth is likely to continue. 
Table 1 - PKC Charge Point Usage
Year
Total
Charging
Sessions
Total kWh
Consumption
Average
Consumption per
Charging Session
(kWh)
2013 (Jan - Dec) 252 2,027 8.04
2014 (Jan - Dec) 1,862 16,431 8.82
2015 (Jan - Dec) 3,962 34,318 8.66
2016 (Jan - Dec) 9,525 92,314 9.69
2017 (Jan - Dec) 16,097 169,907 10.56
2018 (Jan - Dec) 24,240 264,219 10.90
2019 (Jan - Dec) 37,385 414,292 11.08
2020 (Jan - Dec) 32,798 437,642 13.34
2021 (Jan - Dec) 50,307 818,524 16.27
2022 (Jan - Jun) 42,971 806,312 18.76 
5. PROPOSALS 
5.1 A comprehensive review of charging options as part of this report has been
undertaken, looking at both the existing tariffs and associated charges levied
by both the public and private sector CPOs. The Electric Vehicle Association

Page 5

for Scotland (EVAS), a community interest company set up to represent the
views of EV users, have published guidance on setting of tariffs which has
been referred to during the review. 
5.2 To continue to support the uptake of EVs, it is important that a simple and fair
system is adopted if the public are to have the confidence to make the move
to EVs. The range of vehicles and charge points available and the variety of
access methods means the transition to EVs can be confusing. It is likely an
overly complex tariff structure will exacerbate this, potentially alienating users
and increasing administration for the Council. 
5.3 While it is likely that charging electric vehicles at home will play an
increasingly important part as the market develops (which the Council will
encourage), it is important to note that many residents will not have off street
parking available or stay in flatted developments which are not conducive to
home charging. This is an area of work that will need to be taken forward to
ensure that potential electric vehicle owners are not penalised. Charge Place
Scotland have indicated that the back office system will soon be able to offer
differential tariffs which will have the potential to allow residents to take
advantage of cheaper off peak energy usage and also allow more targeted
overstay fees that would allow residents to charge overnight without incurring
penalty fees.   
Options for Charging: 
5.4 From the review undertaken as part of this paper, there are three main
options for charging for the use of EV charge points: 
• Option 1 - Fixed rate: A single rate is charged regardless of amount of
electricity consumed
• Option 2 - Fixed rate plus energy charge: A fixed rate/connection fee is
charged to use the charge point and customers are also charged per unit
of electricity consumed
• Option 3 – Charge based on energy use only: Customers are charged
per unit of electricity consumed, which could have a minimum charge. 
5.5 Option 1, while offering a simple option, is not considered appropriate as this
would unduly penalise vehicles with smaller batteries and unduly influence
driver behaviour. This option was initially introduced by several local
authorities but has subsequently been dropped in favour of a metered tariff.   
5.6 A considerable number of local authorities have opted for Option 2 and
introduced “connection charges” that apply in addition to the energy costs.
However, this is not the approach adopted by the private sector who have
adopted a single per kWh charge. 
5.7 A connection, or standing charge, is also not something that is recommended
by the Electric Vehicle Association of Scotland, who advocate a minimum
charge with costs based on energy used. A connection charge can unduly
influence behaviour whereby users stay on charge longer than they would

Page 6

otherwise to minimise the impact of the standing charge on the overall cost. It
also can unfairly penalise users with more affordable vehicles which typically
have smaller batteries which require more frequent but shorter charging
sessions. 
5.8 However, an alternative is to adopt a minimum charge to ensure that
administrative and other costs associated with a charging session are
covered. This is similar to traditional liquid fuel sales where a minimum
amount is always charged 
Preferred Option: 
5.9 Having considered the available cost recovery options, it is recommended that
Option 3 offers the most equitable and flexible charging model for both the
user and the Council, while being simple and transparent for drivers. 
5.10 Incorporating all cost elements (energy, maintenance and administrative) into
the cost per unit of electricity consumed allows for full cost recovery to be
borne equally by all customers based on actual usage. However, there are
significant additional costs, including network capacity charges, associated
with the provision of rapid (50kW) charging which should be reflected in the
tariff for these units. This price differential will also encourage drivers to use
the slower chargers, wherever possible, to retain rapid charging availability for
users that require it. 
5.11 The Council benefits from significant purchasing power for energy with the
actual rate paid dependant on time of day and other factors. The current rate
paid ranges from around 10p/kWh to 20p/kWh. This compares with the April
2022 price cap rate for domestic customers of approx. 28p/kWh. 
5.12 It is also recognised that there is a requirement for overstay fees to manage
demand for chargers. This is to avoid the situation where a user remains
plugged into a unit beyond the time required to charge the vehicle, thereby
blocking the charger for other users. This approach to demand management
is supported by the Electric Vehicle Association Scotland and has been
adopted across other authorities. 
5.13 Firstly, if the Charger is located in a Council controlled car park where
charging for parking is required, then any length of stay is related to the
parking fee and associated time limit. However, if an EV user enters the car
park, to ensure a faster turnaround, it is proposed for a rapid charger (50Kw)
to limit the stay to 1hour with an overstay fee of £10. If the user would like to
stay in the car park, they will need to move to another space. Similarly for less
powerful 22kw chargers, it is proposed to limit the stay to 3 hours with a
similar overstay fee of £10. 
5.14 Secondly, if the charger is located in a Council car park with no parking
charges, then currently a single EV user could in effect use the facility for
most of the day without penalty.  In that event, we would impose a time
charge on any EV charging use as set out above.  As with the Council car
parks, where parking charges are in place an overstay fee of £10 would be

Page 7

applied. The overstay fees in all charging locations will be administered as
part of the back-office system. 
5.15 Using Option 3 as the basis for charging, it is proposed that the tariffs and
overstay fees initially be set as follows. The tariffs have been done in
cognisance of other local authority charge rates and in consultation with the
Council’s Property and Energy colleagues. 
Table 2 – proposed tariff 
Charger Type Energy Cost  Overstay Fee 
AC charging (7-22kW) 30p per kWh – minimum £1  £10 after 3 hours
Rapid charging (43kW+)  35p per kWh – minimum £1 £10 after 1 hour 
5.16 It is proposed that these tariffs be introduced from 1 January 2023. This will
allow time for the back-office administration systems to be set up, appropriate
signage to be installed and information provided to drivers and users through
our communication channels. 
5.17 It is recognised that introducing tariffs may have an impact on the usage of the
Council’s charge points.  As a result, it is, therefore, recommended that
regular reviews and monitoring are undertaken to ensure that the rates remain
appropriate to recover costs. Members are therefore asked to delegate this
authority to the Executive Director of Communities.  This will allow the Council
to maintain and improve the existing network but importantly make it more
accessible and financially sustainable as the growth in the number of electric
vehicles on the network continues. There will also be the annual review as
part of the Council’s budget setting process. 
6. CONCLUSION   
6.1 The increased transition to electric vehicles and the necessary increase in
charging points will play a key role in achieving these targets. However, the
costs associated with operating and maintaining this infrastructure are
anticipated to continue to increase.  As a result, and in line with other local
authorities, the introduction of charging is being recommended.  Considerable
work has been undertaken on three options, looking at practice elsewhere
and taking into account the expertise offered by the Electric Vehicle
Association of Scotland.  It would be intended, if approved, to introduce
charges on 1 January 2023 to allow for signage installation and a
communications campaign.

Page 8

Authors
Name  Designation Contact Details
Alex Deans 
Niall Moran
Transportation &
Development Team Leader 
Transportation &
Development Project Officer 
(01738) 475000
ComCommitteeReports@pkc.gov.uk 
Approved 
Name Designation Date
Barbara Renton  Executive Director
(Communities) 
12 August 2022 
APPENDICES 
• Appendix 1 – PKC EV Charge Point Assets
• Appendix 2 – Scottish Local Authority Tariffs

Page 9

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION  
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  No
Corporate Plan  No
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment No
Strategic Environmental Assessment No
Sustainability (community, economic, environmental) Yes
Legal and Governance  Yes
Risk Yes
Consultation 
Internal  Yes
External  Yes
Communication 
Communications Plan  Yes 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 N/A. 
Corporate Plan 
1.2 N/A. 
2. Resource Implications 
Financial 
2.1 The development and growth of the number of Electric Vehicles on local
roads has been relatively recent. While all installations in Perth and Kinross
were funded via the Scottish Government, there was a request in order to
incentivise EV ownership to make charging costs free. However, we are now
at a point where the number of vehicles and the number of charging stations
is putting considerable pressure on the Council’s budget. This clearly is not
sustainable in the long term. The Council are seeking, through the charges,
cost recovery which includes the costs of charging while addressing the need
to maintain and develop new infrastructure.

Page 10

Workforce 
2.2 The growth in this area has meant existing staff having to take on additional
duties. However, as part of the Council’s Budget setting for 2022/23, a new
Post of EV Infrastructure Project Officer has been created. 
Asset Management (land, property, IT) 
2.3 The Council will ultimately operate, own and maintain both existing and any
new EV related infrastructure. The cost recovery element of the new charging
regime will allow costs which are currently borne by the Council to be
removed. 
3. Equality Impact Assessment 
3.1  Under the Equality Act 2010, the Council must eliminate discrimination,
advance equality of opportunity, and foster good relations between equality
groups. Carrying out Equality Impact Assessments (EqIA) for plans and
policies allows the Council to show that it is meeting these duties. 
3.2  The EV Tariffs proposals have been considered under the Council’s
Integrated Appraisal Toolkit. No impacts on equality were identified and the
document was assessed as not relevant for the purposes of EqIA. A full EqIA
was not needed. 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. However, no action is required as the Act does not apply to the
matters presented in this report.  This is because the Committee are
requested to note the contents of the report only and the Committee are not
being requested to approve, adopt or agree to an action or to set the
framework for future decisions. 
Sustainability 
3.4 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development.   Under the Climate Change
(Scotland) Act 2009 the Council also has a duty relating to climate change
and, in exercising its functions must act: 
• in the way best calculated to delivery of the Act’s emissions reduction
targets;
• in the way best calculated to deliver any statutory adaptation
programmes; and
• in a way that it considers most sustainable.

Page 11

3.5 The proposals introduce a more financially sustainable way of making sure
infrastructure which is required for the development and growth of Electric
Vehicles is in place. As set out in national and local climate strategies the
growth of EV is crucial in achieving in our wider transport emission targets. 
Legal and Governance 
3.6 The necessary signage which will need to be in place as part of the required
statutory orders in the car parks or on any public road will be in place prior to
the introduction of charges. This will include any new or amended orders to
current signs. 
3.7 There is no impediment to charging for the use of the EV infrastructure. The
Scottish Government have actively encouraged charging as the market has
begun to develop to a point of maturity. It is analogous to traditional methods
of fuel sales. 
Risk 
3.8 The Council has been providing electricity for EV users free of charge up to
this point. This has obviously been a benefit for most current EV users. We
will as part of our wider Communications strategy explain the reasoning and
the financial requirements for the reasons behind the introduction of charging. 
4. Consultation 
Internal 
4.1 A full Communication Strategy will be undertaken prior to the implementation
of charges. Colleagues from Property and Finance have been involved in the
preparation of this report. 
External 
4.2 As above. 
5. Communication 
5.1 This will be developed subject to the approval of charges by the Elected
Members in association with our Communications team. 
2. BACKGROUND PAPERS 
2.1 None.