South Kinross Flood Protection Scheme - Confirmation Without Modification

Perth and Kinross Council · 16 September 2026
Back to Climate Change and Sustainability Committee — 16 September 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality 
___________________________________________________________________  
Committee or Board: Climate Change and Sustainability Committee 
Date of Meeting: 16 September 2026 
Report Title: South Kinross Flood Protection Scheme –
Confirmation Without Modification 
Report Number: 26/245 
Report Author: Rory Stuart, Engineer, Flooding Team
Russell Stewart, Senior Engineer, Flooding Team 
Organisational Lead: Fraser Crofts, Strategic Lead – Environment and
Infrastructure 
1. Purpose 
1.1 The purpose of this Report is to provide an update on the progress of the
South Kinross Flood Protection Scheme, following conclusion of the statutory
objection process. It is proposed that the Council takes the decision under the
Flood Risk Management (Scotland) Act 2009 (the 2009 Act) to confirm the
proposed Scheme without modification as per the recommendation of the
Reporter following conclusion of the Local Authority Hearing. This process
does not obligate the Council to construct the Scheme but ensures it has the
necessary statutory powers to do so subject to completion of detailed design,
deemed planning consent, procurement of a contractor and with full funding in
place. 
1.2 Sections 
1. Purpose
2. Recommendation(s)
3. Background/Context
4. Main Issues
5. Proposals
6. Conclusion
7. Impact Value Assessment
8. Appendices

Page 2

2. Recommendations 
It is recommended that Committee: 
2.1 Notes the valid objections, the environmental impact, the representations
made at the Local Authority Hearing and recommendation of Directorate for
Planning and Environmental Appeals (DPEA) appointed Reporter to ‘confirm
the scheme without modification’. 
2.2 Makes a final decision to confirm the proposed South Kinross Flood
Protection Scheme without modification as outlined in this report and in line
with Paragraph 9(1) of Schedule 2 of the 2009 Act. Council made a
preliminary decision to approve the scheme without modification on 4
December 2024 (report 24/346 refers). This does not obligate the Council to
construct the Scheme but ensures it has the necessary statutory powers to do
so subject to funding. 
2.3 Notes changes by the Scottish Government/COSLA to capital grant funding of
the South Kinross Flood Protection Scheme. 
2.4 Authorises the Strategic Lead – Environment and Infrastructure to carry out all
necessary steps to implement the scheme, including: 
a) Giving notice of the final decision to confirm the Scheme to all of those
required under the 2009 Act including any relevant objectors and in the
relevant newspapers;
b) Seeking deemed planning permission from the Scottish Ministers;
c) Finalising the detailed design for the proposed Scheme;
d) Pursuing the Scottish Government ‘exceptional circumstance business
case’ process, once details are known, to obtain up to 80% capital
funding;
e) The appointment of a contractor to construct the Scheme, subject to full
funding being in place.
3. Background/Context 
3.1  Under the Flood Risk Management (Scotland) Act (the 2009 Act), SEPA and
lead local authorities publish Flood Risk Management (FRM) Plans and Local
FRM Plans. These documents set out a range of actions that SEPA and
responsible authorities will take to manage and, where possible, reduce the
risk of flooding over the following six-year period. 
3.2 Although public authorities are expected to take a proactive role in managing
and, where achievable, lowering flood risk, the primary responsibility for
avoiding or managing flood risk still remains with land and property owners.
The 2009 Act does not alter this. Individuals, businesses and communities
must, therefore, play a critical role in making themselves more resilient and
helping to reduce the impact of flooding.

Page 3

3.3 The Climate Change and Sustainability Committee approved the publication
of the current (2022-2028) Local FRM Plans on 19 December 2022 (Report
22/307 refers). The Climate Change and Sustainability Committee
subsequently approved the content of an Interim Report on the progress
made in implementing the current Local FRM Plans on 10 November 2025
(Report 25/300 refers). The published documents can be viewed at the
following link: http://www.pkc.gov.uk/frmplans 
3.4 Since the publication of the FRM Plans and Local FRM Plans, the Council has
been moving forward with the implementation of the actions set out therein. 
3.5 The 2009 Act provides local authorities with discretionary powers to promote
new flood protection schemes. Only those flood schemes which have been
included in the published FRM Plans, the Local FRM Plans, and the national
priority list will be taken forward in each six-year period. 
Flood Risk Management in South Kinross 
3.6 One of the key actions included within the Forth Estuary Local FRM Plan is to
implement a flood protection scheme in South Kinross. The flood scheme was
ranked as the 28th highest scheme on SEPA’s national flood scheme priority
list published as part of the original FRM Plans in 2016. 
3.7 Kinross is located in the River Leven catchment within Potentially Vulnerable
Area (PVA) 02/10/03. There are three watercourses in this area - the South
Queich, the Gelly Burn and the Clash Burn – which all flow into Loch Leven to
the east. There has been a history of flooding in the town, and it is estimated
that 194 businesses and residential properties are currently at risk of flooding. 
3.8 Perth and Kinross Council engaged consulting engineers to investigate and
promote a flood protection scheme for South Kinross. The progress of the
Scheme has been periodically reported to the former Enterprise and
Infrastructure Committee, Environment Committee, Environment and
Infrastructure Committee, Climate Change and Sustainability Committee and
Perth and Kinross Council. 
The Proposed Scheme 
3.9 The Council, along with consulting engineers, RPS/Tetra Tech, have
developed the outline design of the proposed flood scheme, which was put to
public consultation in 2023. 
3.10 The proposed flood scheme includes the construction of flood walls and
embankments along the South Queich, culvert improvements on the Clash
Burn and a flood storage embankment adjacent to the M90 motorway services
at Turfhills. Property flood resilience measures will be adopted for a small
number of properties next to Loch Leven.

Page 4

3.11 The proposed scheme has been designed to protect properties up to the
predicted 1 in 200-year magnitude flood event (the flood that has a 0.5%
chance of occurring in any one year). 
3.12 In order to make the scheme adaptable to the future effects of climate change,
the foundations for the proposed flood defences will be designed to allow
them to be increased in height in the future. The proposed improvements to
the Clash Burn culverts will also be designed to allow for future climate
change. 
3.13 A plan of the proposed scheme is shown in Appendix A. The full suite  of the
Scheme documents are available on the Council’s website, including Flood
Order Notice, Outline Design Report, design drawings, Scheme Description
Report, Environmental Impact Assessment Report (EIAR), and Public
Consultation Report. https://www.pkc.gov.uk/southkinrossfloodschemedocs 
Scheme Publication 
3.14 The Notice for the South Kinross Flood Protection Scheme was published
under the Flood Risk Management (Scotland) Act 2009 on 26 March 2024. 
3.15 Those potentially affected by the Scheme were notified and information
(including an Environmental Impact Assessment Report (EIAR)) was made
available for public inspection on 26 March 2024. The 2009 Act requires that a
period of 28 days is allowed from the date of publication for objections to be
submitted; this period being slightly increased to 30 days in relation to the
EIAR. 
3.16 Two valid objections and three submissions were received. The three
submissions were from statutory consultees providing technical advice on the
EIAR and outlining any future environmental requirements or considerations.
The two objections (both from landowners) were received by the Council
within the 28-day period. 
3.17 Council officers held extensive discussions with the two landowners, but their
objections were not withdrawn. 
3.18 On 4 December 2024, Perth and Kinross Council was provided with an
update on the progress of the South Kinross Flood Protection Scheme
(Report 24/346 refers). Having considered the valid objections and the
Environmental Impact Assessment Report, in line with Paragraph 5(1) of
Schedule 2 of the 2009 Act, the Council took a preliminary decision to confirm
the proposed Scheme without modification. 
4. Main Issues 
4.1 In order to progress the statutory process, under Paragraph 6(1) of Schedule
2 of the 2009 Act, the Council referred the Scheme to the Scottish Ministers
for their consideration.

Page 5

Notice of the Council’s preliminary decision to confirm the Scheme was
provided to the Scottish Ministers and those residents who submitted an
objection on 12 December 2024. 
4.2 On 30 January 2025, the Scottish Ministers responded, confirming under
Paragraph 7(1) of Schedule 2 of the 2009 Act, that it was their decision not to
call the Scheme in and noting the issues raised in the objections did not
appear to warrant a formal public local inquiry or further consideration by
them. As a result, under Paragraph 8(1) of Schedule 2 of the 2009 Act the
Council was required to hold a Local Authority Hearing to consider the
proposed Scheme. 
Local Authority Hearing 
4.3 Council officers approached the Scottish Government Directorate for Planning
and Environmental Appeals (DPEA) to supply a suitable independent
Reporter for the Local Authority Hearing. Mr Paul Cackette was duly
appointed as the independent Reporter on 25 February 2025. 
The Reporter was appointed to make a recommendation to the Council on
whether the Council should: 
• Confirm the proposed Scheme without modification,
• Confirm the proposed Scheme with modifications, or
• Reject the proposed Scheme. 
4.4  In advance of the Local Authority Hearing, the Reporter required the Council
to submit a Statement of Case in support of the proposed Scheme and their
assessment of the objections. The objectors were then invited to submit their
Statement of Case in response, and a site visit of the proposed Scheme took
place with all parties in attendance on 30 June 2025. 
4.5 On 18 September 2025 an invitation to the Local Authority Hearing was
issued to both objectors and a notice providing details of the Local Authority
Hearing was published in a local newspaper on 25 September 2025 as
required by the 2009 Act. 
4.6 The Local Authority Hearing to resolve the objections was held over a three-
day period (28-29 October 2025 and 03 February 2026). The Local Authority
Hearing took place online and members of the public were able to view the
live proceedings. Recordings of each day of the Local Authority Hearing can
be viewed at: 
https://www.pkc.gov.uk/article/24813/South-Kinross-Flood-Protection-
Scheme-Local-Authority-Hearing 
4.7 The Local Authority Hearing was chaired by the Reporter and attended by
officers from the Council’s Flooding Team and Legal Service, appointed
consultant engineers (RPS/Tetra Tech), and both objectors including their
legal and technical representatives.

Page 6

4.8 On conclusion of the final day of the Local Authority Hearing the Reporter
requested the Council and both objectors submit Closing Statements by 24
February 2026. All parties submitted Closing Statements accordingly. 
4.9 The Reporter provided his Recommendation Report on 12 March 2026, which
recommended that the proposed South Kinross Flood Protection Scheme be
‘Confirmed without Modification’. A copy of the report can be viewed at: 
https://www.pkc.gov.uk/article/24813/South-Kinross-Flood-Protection-
Scheme-Local-Authority-Hearing 
4.10 Following the production of the Reporter’s Recommendation Report, Council
officers have, and continue to, liaise with both objectors to address their
concerns in relation to maintaining access to their land over or around the
proposed flood defences. This process will continue as part of the
development of the Scheme detailed design. 
Funding 
4.11 The South Kinross Flood Protection Scheme has been prioritised in the
published Forth Estuary Flood Risk Management (FRM) Plan and Local FRM
Plan. The flood scheme is therefore able to apply for Scottish Government
capital grant assistance, attracting 80% of the project value at tender stage.
The Council is required to fund the remaining 20% in addition to any cost
increases beyond tender stage. 
4.12 The estimated capital cost of the Scheme in 2023 was £15.08M. It was
anticipated that the Scottish Government would contribute £12.06M (80% of
£15.08M) and the Council’s contribution was expected to be £3.02M (20% of
£15.08M). The Scheme is included in the Council’s current capital
programme. 
4.13 However, in January 2026 the Scottish Government/COSLA agreed that a
‘funding cap’ is applied to flood schemes that were subject to a Local
Authority Hearing or Public Inquiry, and as such this applies to the South
Kinross Flood Protection Scheme. The recommendation notes that the
‘funding cap’ falls short of the original 80% capital grant assistance but there
may be a mechanism to apply for the shortfall in funding through ‘the
exceptional circumstances business case’. There are limited details at this
time on how the process will be administered, but it is proposed to submit a
business case at the appropriate time. 
4.14 The implementation of the flood scheme has, however, been significantly
delayed due to the Local Authority Hearing process. The current outline
design for the proposed scheme requires further development as part of the
detailed design process and some further statutory consents require to be
obtained. Construction is now anticipated to commence in Summer/Autumn
2027 assuming no further delay to the statutory process and the current
detailed design programme.

Page 7

4.15 The current global economic and financial climate has seen significant cost
increases since the scheme economic appraisal was carried out in 2023. An
updated accurate cost appraisal of the Scheme will be provided upon
completion of Detailed Design and any subsequent Tender Returns. 
4.16 The on-going maintenance costs for the scheme are estimated at £38,000 per
annum. This additional cost will require to be considered through the Council’s
revenue budget process once the scheme has been completed. 
5 Proposals 
5.1 As a result of receiving two valid objections, a Local Authority Hearing was
held across 28-29 October 2025 and 03 February 2026. The Reporter has
recommended that the Council make a final decision to confirm the Scheme
without modification. 
5.2 Therefore, the Council must make a final decision under Paragraph 9 of
Schedule 2 of the 2009 Act to either: 
a) Confirm the proposed Scheme without modification,
b) Confirm the proposed Scheme with modifications, or
c) Reject the proposed scheme. 
5.3 Prior to making the above decision, the Council must consider: 
a) The valid objections – these can be viewed in Appendix B and;
b) The representations made at the local hearing. These are set out in the
report provided by the Reporter in Appendix C.
c) The proposed scheme layout as provided in Appendix A (and scheme
documents available on the Council’s webpage below) and ongoing
discussions with both objectors to address concerns regarding access
over or around the proposed flood defences.
https://www.pkc.gov.uk/southkinrossfloodschemedocs
d) The scheme’s environmental impact as set out within the Environmental
Impact Assessment Report (EIAR). The EIAR is available online at:
https://www.pkc.gov.uk/southkinrossfloodschemedocs 
5.4 It is proposed that the Council make a final decision to ‘Confirm the proposed
Scheme without modification’. Once this final decision has been made, the
Council is required to: 
a) notify all parties required by the 2009 Act, 
b) notify every relevant objector, and
c) place a Notice in a local newspaper and the Edinburgh Gazette. 
5.5 A period of 6 weeks is then allowed for an appeal to be lodged by any person
affected by the Scheme. The grounds of appeal are that in reaching a
decision to confirm the Scheme, the Council erred in law or that there was a
failure to comply with the procedural requirements contained in Schedule 2 of

Page 8

the 2009 Act (or any Regulations made under that Act). If no appeals are
lodged, the Scheme would become operative after this 6-week period. 
5.6 Subject to the Scheme being confirmed, consulting engineers will progress
and finalise the necessary detailed design work in consultation with affected
landowners and the local community. Subject to funding, construction works
are anticipated to commence no earlier than Autumn 2027, assuming no
further delay to the statutory process, the current detailed design programme,
and that the tender process can be concluded successfully. 
5.7 The 2009 Act does not require a separate planning application for flood
protection schemes. If such schemes are confirmed under the 2009 Act, then
the Scottish Ministers must also direct that planning consent is deemed to
have been granted. 
5.8 It is, therefore, proposed that further work be undertaken with Planning
colleagues, when the Scheme is confirmed, towards writing to the Scottish
Government setting out proposed planning conditions and requesting that
planning permission shall be deemed to be granted and be subject to those
conditions. 
5.9  The Council shall seek to recover up to 80% of the capital cost of the Scheme
from the Scottish Government through ‘the exceptional circumstances
business case’ once details are known. An updated accurate cost appraisal of
the Scheme will be provided upon completion of Detailed Design and any
subsequent Tender Returns thereafter.  
6 Conclusion 
6.1 The purpose of the flood protection scheme is to manage fluvial flood risk in
Kinross. 
6.2 The Scheme was published on 26 March 2024 and received two objections.
Extensive consultation with both landowners was carried out but an
agreement could not be reached to allow the withdrawal of either objection. 
6.3 The Council appointed an independent Reporter and held a Local Authority
Hearing across 28-29 October 2025 and 03 February 2026 to consider the
objections. 
6.4 The Reporter recommended that the Council confirm the Scheme without
modification. 
6.5 This report proposes that the Council consider the valid objections, the
Scheme’s environmental Impact, the Reporters Recommendation Report, and
makes a final decision to confirm the proposed South Kinross Flood
Protection Scheme 2024 without modification.

Page 9

6.6 The report seeks the Council’s acknowledgement of the Scottish
Government’s funding decision and the requirement to enter into the
‘exceptional circumstance business case’ process. 
6.7 The report seeks the Council’s approval to authorises the Strategic Lead -
Environment and Infrastructure to carry out all necessary steps to complete
the statutory process and implement the Scheme, subject to full funding being
in place. 
7. Impact Value Assessment 
7.1 This report has been classified as being an operational report and as such
does not require a full Impact and Value Assessment. 
8. Appendices 
8.1 Appendix A: Plan of Proposed Scheme Design 
8.2 Appendix B: Objections to South Kinross Flood Protection Scheme 
8.3 Appendix C: Local Authority Hearing Reporter’s Recommendation Report