Democracy Spraffa

Annual Update on the Delivery Plan 2024-29 for Perth and Kinross Local Heat & Energy Efficiency Strategy and Local Area Energy Plan 2024-45

Perth and Kinross Council · 10 November 2025
Back to Climate Change and Sustainability Committee — 10 November 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PERTH AND KINROSS COUNCIL 
Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality 
___________________________________________________________________  
Committee or Board: Climate Change & Sustainability Committee 
Date of Meeting:  10 November 2025 
Report Title: Annual update on the delivery plan (2024-2029) for
Perth & Kinross Local Heat & Energy Efficiency
Strategy and Local Area Energy Plan (2024-2045) 
Report Number: 25/297 
Report Author: Stuart McLaren, Shelley McCann, Divindy Grant 
Organisational Lead: Serge Merone, Strategic Lead – Economy,
Development and Planning
___________________________________________________________________
1. Purpose 
1.1 The purpose of this report is to note progress in implementing the Delivery
Plan (2024-2029) for the Local Heat & Energy Efficiency Strategy (LHEES)
and Local Area Energy Plan (LAEP) (2024-2045) and to approve priorities for
the next 12 months. 
1.2 Sections 
1. Purpose
2. Recommendations
3. Background/Context
4. 2024/2025 Priorities Summary
5. Annual Progress Update 
6. Detailed thematic updates
7. Priorities for the next 12 months
8. Monitoring and Review
9. Conclusion
10. Impact Value Assessment
11. Appendices

Page 2

1.3 Abbreviations 
BAR Building Assessment Reports 
CATCH Climate Action Through Community Heating
DESNZ Department of Energy Security and Net Zero
DFES Distribution Future Energy Scenarios
DNO Distribution Network Operators 
EPC Energy Performance Certificate
EV Electric Vehicle
EVIF Electric Vehicle Infrastructure Fund
HEEPS ABS Home Energy Efficiency Programmes Scotland Area Based Scheme
HiBs Heat in Buildings Bill
HNSU Heat Network Support Unit
HNZ Heat Network Zoning
KPI Key Performance Indicator
LAEP Local Area Energy Plan
LDP Local Development Plan
LENZA Local Energy Net Zero Accelerator
LHEES Local Heat & Energy Efficiency Strategy
MPV Multi-Purpose Vehicle
NESO National Energy System Operator
RAG Red, Amber, Green
RESP Regional Energy Strategic Plan
SEP Strategic Energy Partnership
TCD Tay Cities Deal
tRESP Temporary Regional Energy Strategic Plan 
2. Recommendations 
It is recommended that the Committee: 
2.1 Notes the progress made during the last year towards the outcomes set out
with the Local Heat & Energy Efficiency Strategy (LHEES) and Local Area
Energy Plan (LAEP) (2024-2045). 
2.2 Approves the LAEP priorities for the next 12 months, listed in Section 7. 
3. Background/Context 
3.1 In accordance with the Local Heat and Energy Efficiency Strategies
(Scotland) Order 2022 and in fulfilment of its statutory obligations, Perth and
Kinross Council approved the Local Heat and Energy Efficiency Strategy
(LHEES) for the period 2024-2045, along with the corresponding Delivery
Plan for 2024-2029, on 27 November 2023 (Report Ref 23/330). 
3.2 The LHEES provides a long-term strategic framework aimed at improving the
energy efficiency of buildings within the local authority's jurisdiction and
reducing greenhouse gas emissions associated with heating these buildings. 
3.3 Recognising the importance of a whole energy system approach, a Local
Area Energy Plan (LAEP) for 2024-2045 was developed concurrently, with the
LHEES at its core. The LAEP offers insights into the scope, scale, pace, and
timing of the changes necessary for transitioning to a net-zero energy system.

Page 3

It adopts a whole energy systems approach, addressing the complex
interdependencies among various energy vectors from generation to
consumption. 
3.4 The following figure illustrates the components of both the LHEES and the
LAEP, as well as their interactions: 
3.5 Both the LHEES and LAEP are firmly aligned to the priorities and vision of the
Corporate Plan 2022/23 – 2027/28 (approved by Council in December 2022)
for a Perth and Kinross where everyone can live life well, free from poverty
and inequality. The priorities and outcomes reflect what our communities,
elected members, stakeholders, and partner organisations believe are the
most important for Perth and Kinross. They are also fully aligned with local
strategies, policies and plans including the: 
• Perth and Kinross Climate Change Strategy and Action Plan
• Perth and Kinross Local Outcomes Improvement Plan 2022-2032
• Perth and Kinross Local Development Plan 2019
• Perth and Kinross Local Housing Strategy 2022-2027
• Perth and Kinross Child Poverty Delivery Plan 2022-2026 
• Perth and Kinross Mobility Strategy and Action Plan
• Tay Cities Regional Economic Strategy and Perth and Kinross Economic
Action Plan 
4. 2024/2025 Priorities Summary 
4.1 In Report No. 24/286 (LHEES annual report 2024/25), Members approved the
following delivery priorities for the year November 2024 – October 2025 and
progress updates are provided below.

Page 4

4.2 Improving buildings’ energy efficiency aiming for affordable warmth and
regulatory compliance 
2024/25 priority  RAG
status
Comments
Develop One Stop Shop for
Home Energy Retrofit 
Innovate UK funded project
completed in July 2024, next phase
in planning
Utilise HEEPS ABS funding to
deliver energy efficiency
measures 
£503,524.11 worth of improvement
works was carried out in 24/25, with
86 properties getting insulation
measures and 9 solar panel systems. 
Campaign developed with
Home Energy Scotland and
energy savings trust 
Heat pump comms campaign
developed,  launched October  2025.
Estate decarbonisation -
Explore how the approach of
categorising buildings by types
for building decarbonisation
can be rolled out across the
rest of the non-domestic and
domestic stock to prioritise
retrofit and clean heating
system transition. 
Utilising council data and
categorising the buildings allows the
transition to be more efficient and
more focused. 
Building categorisation has shown
that there is not one solution to fit
throughout the PKC estate. Every
building needs to be treated
separately in relation to
decarbonisation to make sure that it
can be as efficient as possible. 
Engage with Scottish
Enterprise to stimulate supply
chain 
Through energy efficiency and retrofit
& skills and supply chain delivery
groups 
4.3 Decarbonising heat within a transitioning energy system focusing on heat
networks and heat pumps 
2024/25 priority  RAG
status
Comments
Undertake Perth City heat
network feasibility study (Heat
Network Support Unit (HNSU)
funded) 
Technical and Commercial feasibility
complete, next phase of heat
network design and delivery to be
investigated. Further HNSU funding
being explored.
Work to ensure the approach
developed through this work
can be replicated in other
potential heat network zones in
rural areas. 
Feasibility studies for small scale
rural heat networks looking at hard to
decarbonise Council sites where we
have non-domestic properties in
close proximity to social housing
Decision taken with Development
Plans team to adopt a phased
approach to Heat Network Zoning,

Page 5

signposted in LDP3 local planning
policy to a live web resource to
enable reactive approach to
emerging national policy.
Complete Building Assessment
Reports (BAR) for Council
owned buildings 
Returns received from several
stakeholders. Further action is
awaiting decision from the Scottish
Government regarding funding for
national approach to data collection
and publishing via the Scottish
Government, Improvement Services
and Spatial Hub.
Engage with SSEN to explore
impact of low carbon heating
solutions on grid capacity
through Local Energy Net Zero
Accelerator (LENZA) 
Perth and Kinross to pilot process to
utilise SSEN's LENZA to plan
decarbonisation pathways, which in
turn drive SSEN Distribution’s longer-
term strategic network planning that
will power local net zero ambition 
4.4 Reduce transport 
2024/25 priority  RAG
status
Comments
Align PKC’s Mobility Strategy
with LHEES and LAEP 
Ongoing with new lead mobility
officer in post from June 2025
Innovate UK project on
connecting regional travel -
Aberfeldy 
Project completed in July 2025 
4.5 Decarbonise transport 
2024/25 priority  RAG
status
Comments
Align Mobility Strategy with
LHEES and LAEP 
Ongoing with new lead mobility
officer in post from June 2025
Finalise and deliver the public
charging EV infrastructure
strategy 
EVIF project ongoing with Angus
Council as a partner. Procurement
for private partner ongoing and
expected to be completed by Spring
2026.
Expansion of recharging
network throughout Perth and
Kinross 
Continued growth of public charging
EV infrastructure
Continually assess air quality
across Perth and Kinross to
assess any necessary
mitigation measures 
The Perth Air Quality Action Plan has
been created and has been
approved by the Climate Change and
Sustainability Committee in August
2025.

Page 6

4.6 Deploy local renewable energy generation 
2024/25 priority  RAG
status
Comments
Support community energy
ideas through Scalable Cities
project 
Scalable Cities project complete and
was launched at PKC’s Big Energy
Event on 20 September 2025.
Develop a replicable approach
for how investment from the
public and private sectors in
smart local energy systems
can generate wealth for local
communities and help meet
net zero target. 
Through Scalable Cities community
investment framework, commercial
feasibility completed to identify
delivery models, capable of
leveraging substantial private
investment, for the development and
delivery of heat networks and
pipeline low carbon 
Strategic Energy Partnership
procurement and contract strategy
being progressed
Reassess suitability for
renewable energy sites and
opportunities aligned to the
Local Development Plan 3 
Renewable and Low Carbon Energy
Planning Guidance is currently out
for consultation. 
4.7 Enabling actions 
4.7.1 Developing green skills and the capacity of the supply chain 
2024/25 priority  RAG
status
Comments
Tay Cities Region Deal and
Clean Growth Platform to
identify existing skills and
partnerships 
Through energy efficiency and retrofit
& skills and supply chain delivery
groups linking with the TCD Skills
Programme, Skills Board and Skills
Pathways project.
Engage with Scottish
Enterprise to use the LHEES
and LAEP to stimulate supply
chain development 
Through energy efficiency and retrofit
& skills and supply chain delivery
groups
Through the Innovate UK
funded Revitalising Homes
project, quantify the market
opportunities and risks for local
suppliers 
Work completed and report
published

Page 7

4.7.2 Working in partnership with communities to build community wealth and
wellbeing 
2024/25 priority  RAG
status
Comments
Collaborate with Community
Energy Scotland and partners
SSEN, Bable and CATCH
through the Scalable Cities
project to identify and set up
the pathway for the
development of community
energy schemes 
Completed through the scalable
cities project. Further engagement
and collaboration with CATCH
through the Danish Board of District
Heating mentoring scheme. 
4.7.3  Mobilising partners and public and private investments for projects 
2024/25 priority  RAG
status
Comments
Through HNSU funding work
with a legal advisor to produce
a Delivery Options Appraisal
and progress towards a
Strategic Outline Case for
delivery of the Perth city-wide
heat network as a key anchor
project for a wider energy
projects investment
programme. 
Commercial feasibility work
completed by legal advisors to
assess delivery model options and
progress Strategic Energy
Partnership procurement. Strategic
Energy Partnership Board formed.
Establish the Strategic Energy
Partnership (SEP) and develop
a five-year investment
programme. 
SEP Board now formed and meeting
to progress procurement, but longer
timescales to fit Competitive
Dialogue procurement process.

Page 8

4.7.4  Data and scenarios building tools and platform 
2024/25 priority  RAG
status
Comments
Continue to work to evolve the
LHEES/LAEP evidence base
and tools to support whole
systems energy planning with
delivery partners and data
providers. 
Work with SSEN to pilot
development to support alignment
with grid investment planning (e.g.
Distribution Future Energy Scenarios
(DFES) and pathways for the
Regional Energy Strategic Plan
(RESP). Potential Heat Network
zones updated.  
Work with SSEN, Ordnance
Survey, Energy Savings Trust
and additional delivery
partners to map user access
journeys to digital evidence
underlying LHEES/LAEP
including data sharing and
licensing arrangements. 
We continue to work with our delivery
partners as part of the LHEES/LAEP
delivery groups. User access groups
for stakeholders including community
groups, commercial and contracted
consultants, LAEP partners.  Open
data access supported.  Onboarding
of staff to facilitate continued use and
update of data. CATCH onboarded.  
Prioritise and publish
LHEES/LAEP and related
energy projects data on
corporate systems and
develop a process for update
and improvement with support
from the Corporate Data
Team. 
Corporate Data and Analytics Work
Programme dedicated onboarding
resource established to ensure
LHEES and LAEP related data
products are available to
stakeholders using ArcGIS and
establishing data management plans.
Potential Heat Networks zones
published corporately, and improved
renewables pipeline data process
established.

Page 9

4.7.5  Governance 
2024/25 priority  RAG
status
Comments
Develop a monitoring and
evaluation plan (MEP) building
on and aligning with supporting
strategies such as the Local
Housing Strategy, Mobility
Strategy and Action Plan and
Climate Action Plan 
KPI framework developed 
Continually monitored and updated
during coordination team meetings
with associated KPIs. 
Develop a Communication and
Engagement Plan through the
delivery group setting out that
the Council and Steering
Group will conduct regular
consultation and engagement
with stakeholders 
Communication and engagement
through delivery groups quarterly and
events such as the energy event in
September 2025. 
Communication and engagement
plan for heat pumps and solar PV for
owner occupied and landlords. 
5. Annual progress update 
Overall Performance against LAEP Action Plan 
5.1  Out of the 35 actions in the LHEES action plan, across seven themes, 22 of
the actions are either complete, ongoing or moving into the next phase of the
project that requires additional funding. The other actions are in progress but
delayed due to lack of funding, lack of resources or require further policy
updates from the Scottish Government to move forward. The graphic below
shows the split of the actions in relation to RAG status. 
0 1 2 3 4 5 6 7 8
Energy Efficiency
Heat Decarbonisation - Heat Network
Heat Decarbonisation - Heat Pumps
Reduce Transport Demand
Decarbonise Transport
Local Renewable Generation
Enabling Actions
RAG status of actions
Green Amber

Page 10

5.2 The performance of the actions and associated plan are monitored through
the LHEES/LAEP Coordination group that meet every 2 months to discuss
any actions that need progressed. The group consists of lead officers from all
LHEES/LAEP themes so actions can be discussed and progressed if
necessary. 
5.3 Some of the challenges associated with delivering the action plan include: 
• Supply Chain, Skills and Staff Shortages: A lack of specific skilled
workers and retrofit supply chain capacity slows down implementation,
especially in rural or remote areas. This has been highlighted as a major
issue in the roll-out of cleaner technology including heat pumps and solar
PV. Working alongside agencies such as Perth UHI, Scottish Enterprise
and Energy Skills Partnership we hope to identify the key areas where
investment is required to develop or transition of existing trades into
greener skills. 
• Grid Infrastructure Limitations: Many areas face grid capacity issues
which means engaging with Distribution Network Operators (DNO) like
SSEN is vital in planning the roll- out of solutions such as heat pumps. We
are working alongside SSEN to identify areas that require development
and investment through Distribution Future Energy Scenarios (DFES) and
the Regional Energy Strategic Plan (RESP). These projects will allow
DNOs to see where energy users are looking to expand into and look at
grid expansion and upgrades. Additionally, we continue to utilise and
codevelop the SSEN LENZA tool which shows live grid capacity on the
network and predicted constraints, enabling better decisions on the siting
of new energy assets and roll out low-carbon programmes.  It uses a
traffic light system to show whether a new energy asset could be
accommodated on the existing network or where further development is
required. 
• Stakeholder Engagement:  Efficient delivery requires collaboration
across local authorities, communities, private sector, and national
government. This can be challenging due to differing priorities and
resources. Engagement is vital to deliver the LHEES/LAEP actions. PKC
is engaging through delivery groups, steering group and focused events
like the energy event that was held on 20 September 2025. In addition,
PKC is part of groups that contain officers from a range of local authorities
to collaborate and share ideas on the delivery of the LHEES and LAEP. 
• Financial and funding Constraints: There are funding limitations and
there can be uncertainty around long-term investment which can delay
key projects.  PKC continue to seek and utilise funding opportunities to
help push forward the actions outlined in the LHEES and LAEP.
Challenges exist for the Council to provide the investment required to
decarbonise at scale. We are progressing with a procurement to create a
Strategic Energy Partnership with a private sector partner to bring needed
capital investment into this area. Expected to be in place September
2026.

Page 11

The Council has recently agreed to sign the UK City Net Zero Declaration
and network and use this platform to attract business and project
investments at national and international levels. 
• Policy delays and uncertainty: Delays in policy reform from Scottish
Government and uncertainty are impacting the delivery of certain actions.
Lack of clarity on the timelines for the publishing of the Heat in Buildings
Bill (HiBs) have led to delays in Heat Network Zoning designation and
completion of supporting Building Assessment Reports (BARS). HiBs will
include provisions to boost heat network development by developing
requirements for large, non-domestic premises, including powers to
require public sector buildings to connect to district heating when available
and therefore, is considered a key policy mechanism for delivery of HNZs.
The Council will adopt a phased approach to Heat Network Zoning as a
way forward to ensure current work funded through the HNSU for Perth is
considered in designation and where zones have been formally assessed
to ensure a high-level financial viability has been established. 
5.4 In addition, the delay to EPC reform from 2025 to 2026 is impacting the
delivery of many of the housing actions relating to energy efficiency. This
delay may impact local authorities in the delivery of net zero ambitions in
relation to building energy efficiency and emissions. 
5.5 Some of the opportunities for LHEES/LAEP delivery include: 
• Community Wealth Building: Energy efficiency and heat
decarbonisation projects can stimulate local economies, create jobs, and
build resilience. The creation of the Strategic Energy Partnership will allow
PKC to work alongside a private partner that values community wealth
and will help enhance the areas in which they invest and develop. The
procurement process will be an opportunity to highlight that PKC want a
partner to invest in local areas, including job creation and supporting local
businesses. 
• More locally led planning: The LHEES and LAEP allows PKC to tailor
projects and strategies to support local needs, enabling more relevant and
impactful interventions such as supporting community energy projects
through the scalable cities project. Updating of the renewable policy in line
with the LDP 3 and prioritising local initiatives allows PKC to focus in
areas that help the communities within Perth and Kinross. The
procurement of a Strategic Energy Partner will allow us to collaborate with
the private sector to decarbonise our energy usage for the benefit of
communities, the environment and the wider economy. Helping residents
and communities that are in fuel poverty is also a high priority as part of
the LHEES. This can be focused on as part of a more local approach
when planning projects and engaging with partners.

Page 12

Key Performance Indicators (KPIs) 
5.6 The LHEES/LAEP action plan has been developed to assign certain actions to
designated teams and team leads so there is accountability to deliver. This
year a KPI framework has been developed that is presented in Appendix II,
with relevant KPIs selected for each of the priority themes. Where possible,
the KPIs have been designed to align with those of the Council’s Climate
Change Action Plan, Mobility Strategy and Local Housing Strategy. The
associated KPIs will be monitored by the LHEES/LAEP coordination group
and annually reviewed using a variety of PKC owned and other data sets.   
5.7 Of the 23 KPIs, we currently have data for 16. Of the KPIs we have data for,
10 showed improvement. For some KPIs we have 24/25 data, while other
datasets are published with a 1–2-year data lag, so data from 2023 is the
latest data set available. 
5.8 The KPIs across the LHEES/LAEP themes show that they are improving year
on year, especially with regards to energy efficiency with CO2 emissions and
energy consumption reductions and increases in the energy efficiency EPC
levels of social housing within Perth and Kinross. 
5.9 There is a decrease in overall consumption of heating oil throughout the non-
domestic estate. Hopefully this will increase further with increased
communication and engagement on alternative solutions e.g. heat pumps. 
5.10 There has been a slight increase in percentage of households in fuel poverty.
This has been impacted by global energy price rises and subsequent cost of
living crisis, bringing more people into fuel poverty. Much of this is beyond
PKC control but demonstrates the importance of all energy efficiency
measures the Council is taking or promoting. 
5.11 The Heat Networks Planning Database (HNPD) published by the Department
of Energy Security and Net Zero (DESNZ) tracks the progress of both
communal and district heat networks from inception, through planning,
construction, operation and decommissioning. 
5.12 The majority of the transport KPIs are heading in the right direction with an
increase in the provision of electric vehicle charge points and a steady
increase in the transition of fleet vehicles to electric and alternative fuel
sources. There has been an overall reduction in emission caused by transport
but a slight increase in total car miles. This increase could be caused by more
workers having to travel into the workplace as work from home policies have
changed. 
5.13 There has been a slight reduction in renewable energy generated across the
PKC estate. This decrease has been impacted as biomass boilers are out of
commission, causing the reduction in energy produced. Significant investment
is required to bring the boilers back into use, alternative solutions are being
reviewed to help reach the Council’s net zero targets, with reduced risk.

Page 13

5.14 The Renewable Energy Planning Database (REPD) published by DESNZ
tracks the progress of renewable projects, and electricity storage projects from
inception, through planning, construction, operation and decommissioning.
Perth and Kinross ranks tenth in Scotland for installed renewable energy
generation capacity and eleventh in terms of the future the project pipeline. 
We are one of the lead authorities, fourth in Scotland, in terms of installed
operational discharge capacity, and rank fifth nationally for the future project
pipeline, largely due to a growth in battery storage. 
Risk register 
5.15 The risk register is an evolving document and is continuously monitored to
make sure that it is up to date as possible. Additional risks and mitigation
measures are inserted to make sure it is a live document. 
5.16 One of the major risks of delivery is the lack of internal capacity and resource
within PKC. The Council does not have the technical skills or resources to
develop and implement complex energy plans, leading to a reliance on
external consultants. 
5.17 Another major risk is the short-term nature of funding. We require sustained
investment to support infrastructure upgrades, community engagement, and
delivery mechanisms, but current funding models are often competitive and
time-limited. This creates disparities between well-resourced and under-
resourced Councils, potentially exacerbating regional inequalities. 
5.18 The success of LHEES/LAEP delivery depends heavily on access to high-
quality data and coordination with stakeholders such as Distribution Network
Operators (DNOs), energy providers, and communities. Without clear
governance structures and long-term policy support, PKC will struggle to
attract private investment and deliver the systemic change needed to meet
our net zero targets. 
6. Detailed thematic updates 
6.1 Please note that many actions across all LAEP themes will be reported on in
more detail within other committee report updates, such as the Mobility
Strategy.   
Theme 1: Improving buildings’ energy efficiency aiming for affordable
warmth and regulatory compliance
6.2 HEEPS ABS: £503,524.11 of improvement works was carried out in 24/25,
with 86 properties getting insulation measures and 9 solar panel systems.  
• External Wall Insulation: In the Hillyland area of Perth, a total of 23 private
owner properties and 60 PKC properties had external wall installation
installed.
• Cavity Wall Insulation: A total of 3 installations were completed, all at privately
owned properties.

Page 14

• Solar PV and Battery Storage: A total of 9 installations were completed, all at
privately owned properties. 
SCARF energy advice contract 
6.3 Over the 2024/25 financial year 1,788 residents received guidance over a
wide range of topics, resulting in 108 participants being referred to trusted
contractors for installation of energy efficiency measures. 
6.4 In the 2024-25 financial period SCARF eradicated £3,360 in fuel debt for
residents. As a result of the energy advice provided to residents, it is
estimated that £51,660 was saved throughout the year. 
Innovate UK One Stop Shop Retrofit - Revitalising Homes 
6.5 Revitalising Homes looked at a whole systems approach to retrofit through
engagement with householders, local suppliers and installers, identifying
green skills gaps, exploring and modifying a customer re-claim model for
funding and creating a viable business model for a sustainable retrofit project. 
6.6 The Council is currently working with project partners to develop this idea
further, with the next steps being: 
1) Create a Knowledge Hub as a central source of trusted information on the
retrofit process and home improvement measures. 
2) Implement a viable business model for a one-stop-shop for retrofit advice
and support. 
Non-domestic improvements 
6.7 Over the last year the PKC non-domestic stock has seen an overall 5%
decrease in energy consumption, even though there was an increase in Gross
Internal Floor Area (GIFA). There has also been a reduction in carbon
emissions, making it the lowest value since records began within PKC. 
Theme 2: Decarbonising heat within a transitioning energy system
focusing on heat networks and heat pumps 
Perth City centre heat network report and commercial modelling 
6.8 Funding from the Scottish Government’s Strategic Heat Network Support Unit
(HNSU) was utilised to procure a consultant to assess the technical and
commercial viability of the Perth City Heat Network and build a programme for
procuring a partner to deliver heat networks within a wider energy system.
The project focussed on identification of the build-out from the initial Perth City
Centre network to the surrounding area to achieve a city-wide, large-scale,
heat network. This will be a key anchor project in the wider pipeline of energy
projects and be used in the procurement to establish a Strategic Energy
Partnership (SEP).

Page 15

6.9 Work comprised of two separate work packages: 
1. Technical Heat Network Design and Delivery supported by our technical
partner (£100k – HNSU funded)
2. Commercial Delivery Models and Procurement supported by our
commercial advisors (£35k – Council funded). 
6.10 The technical report outlines a preferred option for the Perth City Heat
Network which uses a combination of air source heat pumps (ASHPs) and
sewer source heat pumps (SSHPs) to supply heat to the network. The first
phase is located in Perth City Centre, extending from the west bank of the
River Tay to the railway line west of the city, and from South Inch in the south
to Balhousie North Inch care home in the north. It will serve 13 key Council-
owned buildings such as Pullar House and Perth Playhouse (Cinema), with a
southern extension to supply HM Prison Perth. 
Commercial Delivery Models and Procurement – Strategic Energy
Partnership (SEP) 
6.11 The Council is committed to delivering net zero targets and to changing the
energy system so that we can transition away from fossil fuels and deliver a
resilient and clean local energy system supporting economic growth and
tackling inequalities in the energy transition. To support these ambitions, PKC
is establishing a Strategic Energy Partnership (SEP) with a private sector
partner. This work builds upon the Prior Information Notice for the SEP sent
out in summer 2024. Work funded by the Council and supported by the HNSU
involved legal advisors reviewing delivery models for heat networks and other
energy projects. This resulted in a number of outputs including a Delivery
Model Options Assessment and Preferred Option Delivery Model Report, an
advice note on the procurement and contracting strategy, a procurement
timetable and ‘route map’ for SEP highlighting options for moving forward and
an indicative timetable for the procurement process.   
6.12 A SEP Board has been established and has met monthly to continue to
progress this work and a Procurement Strategy is being progressed. 
Additionally, the Council has agreed to join a network of UK local authorities
that will share experience of developing SEPs. 
6.13 The Council is currently seeking a continuation of funding through HNSU to
further progress this work towards an Outline Business Case (OBC). 
Recommended next steps include additional technical feasibility work
alongside financial modelling to support the economic and financial case for
the Perth HN opportunity and Procurement and Contract Strategy support
including the development of a Strategic Partnering Agreement (SPA) and
assistance with financial bundling of additional pipeline energy projects
including (renewable energy development and battery storage, private wire,
hydrogen refuelling, and estate decarbonisation).

Page 16

Housing heat pump installs 2024-25  
6.14 In the period of April 24- March 25, 58 heat pumps have been installed
throughout the Council owned stock. From April 25 to date a further 29 heat
pumps have been installed. As part of the planned installation programme up
to March 2026, 35 additional heat pumps will be installed as part of a pilot
project. 
Theme 3: Reduce transport 
Investigate the use of multi-modal transport hubs and of inner-city car
parking to increase public transport usage 
6.15 An options appraisal has been completed for the redevelopment of Perth’s
Bus and Railway Station and improving connectivity with the city centre. It
sets out preferred options for delivery including: 
• a redeveloped new bus station
• a new public space in the existing railway station car park
• an enhanced the pedestrian connection between the station and the  city
centre
• An active travel hub 
The outline business case will be complete by spring 2026, with the full
business case complete in the summer. The allocated funding must be spent
by March 2030. 
Deliver behaviour change initiatives to encourage active travel and
public transport use 
6.16 In 2024/25, Tactran allocated behaviour change funding to projects in Perth to
encourage active travel in places where traffic-free active travel infrastructure
has already been built or will be soon. Interventions included active travel
promotion in schools and engagement in workplaces. 
Theme 4: Decarbonise Transport 
Decarbonising Bus Services 
6.17 Further electric buses have been added to bus operator fleets in 24/25 and
new electric bus services continue to be introduced. 
6.18 Glenfarg Community Transport has purchased an electric minibus to pilot a
demand responsive transport service in the Kinross-shire area and Ember are
continuing to expand electric coach services. Ember have introduced their first
electric service through Blairgowrie linking Dundee and Aberdeen daily in
each direction.

Page 17

Electric Vehicle Infrastructure Fund (EVIF) 
6.19 In March/April 2025 in various locations across the Council area, 5 x 50kW
Rapid chargers were replaced as they were not contactless payment
compliant. 
6.20 The Electric Vehicle Infrastructure Fund (EVIF) project funded by Transport
Scotland is progressing well. A Prior Information Notice (PIN) has been
uploaded to Public Contracts Scotland (PCS), and we have received around
14 submissions so far. 
6.21 A project board has now been created with representatives from PKC and
Angus Council. It is proposed that a contract will be awarded around April
2026 with migration of all chargers from the CPS back office to the new back
office by August 2026. 
Hydrogen 
6.22 A related Tay Cities Deal project (TCD008c – Perth Hydrogen Refuelling
Station) is proposing a change request to TCD to change hydrogen proposal
from a public access hydrogen station to an internal hydrogen refuelling
station likely to be at Friarton Depot. 
Fleet transition 
6.23  Over the last 12 months the fleet team has incorporated 17 Refuse Collection
Vehicles (RCVs) that are powered by Hydrotreated Vegetable Oil (HVO)
instead of diesel.  
6.24 Three Electric Van Derived MPVs have also been added to the fleet through
the year. The composition of the Council fleet also changed from diesel to
more petrol and electric cars for its pool vehicle fleet. This has resulted to
significantly less (98%) usage for all small, medium and large diesel cars. 
The Council has also purchased more battery electric vehicles, noting a 34%
mileage increase for this reporting year.   
Theme 5: Deploy local renewable generation 
Scalable Cities project 
6.25 This EU funded project explored how to involve communities in local energy
generation and heat decarbonisation as part of a strategic approach to
building a local and decentralised energy system in Perth & Kinross. The
project focused on how local renewable energy projects could be funded
through a Community Energy Investment Framework bring public, private and
community finances together.

Page 18

6.26 Outputs include: 
• A template where local community groups can be engaged in the
development of a smart local energy system supported by local and
national governments and the private sector – Community investment
framework.  
• Expands upon the LHEES/LAEP and climate change action plan on
developing local energy projects such as district heating systems and
renewable energy projects from Community Energy Scotland. 
• The report demonstrates how investment from the public, private and
community sectors in smart local energy systems can generate wealth
for local communities and help meet overall net zero targets. 
• During the project we have been engaging and working with all local
stakeholders across the energy system to bring support and action. A
stakeholder engagement event was held during the project where ideas
on community energy projects were shared and the support from PKC
and Community Energy Scotland was outlined to those community
groups in attendance. 
6.27 The overall impact of this project is to allow better collaboration and
communication with communities in delivering the LHEES/LAEP actions
across Perth and Kinross. 
SSEN LENZA 
6.28 The Council has worked alongside SSEN and other partners to build evidence
in the Local Energy Net Zero Accelerator (LENZA) platform which will utilise
the outputs of our LHEES, LAEP and our live Delivery Plans to plan
decarbonisation pathways by enabling low carbon technologies (LCTs) such
as heat pumps to be sited in cost-effective locations whilst providing early
warning to SSEN of additional demand on the network. 
6.29 This will help us to ensure alignment with grid investment planning in the near
to medium term, while helping to improve and shape longer term roll out and
investment required up to 2045. Alignment of our investment planning with
SSEN and other key delivery partners will support the development and
triaging of a pipeline of low carbon projects through to delivery avoiding risks
and barriers posed by grid capacity. 
Regional Energy Strategic Plans (RESP) 
6.30 Ofgem awarded National Energy System Operator (NESO) the RESP role in
November 2023. Following their public consultation in July 2024, Ofgem
published its final decision on the details of the RESP role on 2 April 2025.
The RESP framework policy sets out the scope of the role and what NESO
and its stakeholders will be doing to enable the development of RESPs across
Great Britain.

Page 19

6.31 The RESP role has been set up to develop regional plans that span across all
energy vectors – electricity, gas, and hydrogen networks – as part of one
integrated energy system. The RESP for Scotland will be produced in full by
the end of 2027 once it has been approved by Ofgem. 
6.32 PKC has been selected as the pilot to test the process of how data streams
from LHEES/LAEP and additional data within LENZA can be used to inform
the SSEN Distribution Future Energy Scenarios (DFES) and pathways for the
Regional Energy Strategic Plan (RESP) going forward. Engagement has
taken place both internally and externally with large energy users within Perth
and Kinross to try and help inform the temporary regional energy strategic
plan (tRESP). The tRESP is to consist of more granular level data and is due
for completion in January 2026.  More information on the RESP and tRESP
can be found here. 
Enabling Actions 
6.33 The delivery of the LHEES/LAEP priorities are supported by the following
mechanisms: 
6.34 Delivery groups 
Established the Council’s LHEES/LAEP delivery groups focussing on   
different themes including: 
• Energy efficiency and retrofit
• Industrial and commercial (including heat networks)
• Renewable energy generation
• Skills and supply chain 
These groups focus on the specific theme and consist of internal and external
stakeholders helping to drive and deliver the actions identified in the
LHEES/LAEP.   
6.35 Stimulate supply chain and skills – work with key partners including Perth UHI
and Energy Skills Partnership (ESP) to assess priority green skills. The
business case for the Sustainable Construction Skills Project funded under
the Tay City Region Deal (TCRD) Skills Programme has had Tay Cities Joint
Committee approval in June but is still being reviewed by the Scottish
Government. Activities over the next 12 months will be focussed on further
curriculum development and career pathways. 
6.36 Engaged with Scottish Enterprise to use the LHEES and LAEP to stimulate
supply chain development and explore how they can shape planning of
upcoming events to articulate opportunities and raise awareness of potential
solutions and innovation across the industry.

Page 20

Working in partnership with communities to build community wealth
and wellbeing:   
Over the past year, we have:  
6.37 Engaged with Kinross CATCH project providing access to LHEES and LAEP
evidence via SSEN LENZA platform and tools to support Community Energy
Potential Mapping. In addition, CATCH was given access to the Danish Board
of District Heating mentorship through PKC, a forum to understand how to
incorporate lessons from Danish district heating into Perth & Kinross. 
6.38 Worked with SCARF to identify and target homes in Perth & Kinross that are
eligible for ECO 4/ECO 4 FLEX funding for energy efficiency improvements.
SCARF have sent letters to homes identified as EPC Bands E-G that require
fabric first energy efficiency solutions. SCARF also offer funding to help
eradicate fuel debt for households that have not been able to pay energy bills. 
6.39 We held an energy event on 20 September 2025 in the Civic Hall to gain
exposure to a wide audience, including potential customers and partners. The
overall aims of the market were to educate the community, promote
sustainable practices and hopefully show how the public could save money on
energy bills. There were stalls, speakers, and energy themed workshops
running throughout the day all covering different aspects of the energy market. 
Mobilising partners and public and private investments for projects:   
6.40 Over the past year, we have consulted with the market and stakeholders
through a series of workshops to evaluate a possible Strategic Energy
Partnership to unlock delivery of, though potentially not limited to, heat
networks and to improve delivery capability into large and complex energy
projects.   
Data and scenarios building tools and platform:   
Over the past year, we have:   
6.41 Continued to work to evolve the LHEES/LAEP evidence base and tools to
support whole systems energy planning with delivery partners and data
providers. Data sets have been uploaded onto the SSEN LENZA platform to
better understand the connection requirements to help decarbonise all assets
throughout Perth and Kinross. 
6.42 Started a Corporate Data Team (CDT) supported data and analytics work
programme targeted at identifying, prioritising and publishing LHEES and
LAEP related datasets corporately, in ArcGIS and ensuring improved data
processes, management and sharing plans are in place.

Page 21

7. Priorities for the next 12 months for LHEES and LEAP 
7.1 Improving buildings’ energy efficiency aiming for affordable warmth and
regulatory compliance by: 
Priority Actions Comment
Deliver the HEEPS ABS
programme for 2025/26
Grant funding has been awarded of
£1,942,800. This will target support for areas
of private homeownership where EPC Bands
are low and will also align to assist and
support our multi-storeys strategy.
Continue with “quick win” projects
for non-domestic properties
aligning with LHEES.
Target off gas grid and inefficient electric heat
sources. Projects at Arngask and Glendelvine
Primary schools to be progressed and
continue to liaise with SSEN regarding
potential network upgrades for other areas.
Develop decarbonisation pathway
for all PKC non-domestic
properties aligning with the
Scottish Government’s updated
Heat in Buildings bill. 
Develop decarbonisation pathway
for all PKC non-domestic
properties aligning with the
Scottish Government’s updated
Heat in Buildings bill. 
Develop One Stop Shop Home
Retrofit Advice service for Perth
and Kinross together with the
HEAT Project. 
7.2 Decarbonising heat within a transitioning energy system focusing on 
heat networks and heat pumps by: 
Priority Actions Comment
PKC has agreed an approach
of phased heat network zoning
(HNZ) and link to a live web
resource to include a web map
and completed HNZ proforma
for zones as they are
designated. 
There is an opportunity for knowledge sharing in
HNZ LDP local policy development potentially
with advice from Scottish Government. PKC’s
LDP 3 will have a heat network policy which will
signpost to a separate designated heat network
zones document/web map (this will allow us to
update heat network zones as required).
Seek and utilise continued
further funding from the
Strategic Heat Network Unit of
the Scottish Government to
build a programme for
procuring a partner to deliver
heat networks within a wider
energy system.
Consideration and alignment of phased large
scale heat network delivery with the wider
strategic energy programme will be a key aspect
of this work.  Recommendations for next steps
and funding include development of a Strategic
Outline Case (SOC), review of the techno-
economic/financial modelling and development of
a Strategic Partnering Agreement (SPA).

Page 22

The development of a Strategic
Energy Partnership will provide
an opportunity to inform how
heat networks, and other low
carbon opportunities identified
in the wider LHEES/LAEP,
could be delivered.
The establishment of an energy partnership may
help to unlock heat network development in
those areas of Perth and Kinross that are less
commercially attractive but could benefit the
most from what district heating can offer. 
Look to complete the Building
Assessment Reports (BARs)
for required Council owned
buildings. 
The project had been paused until further action
and funding from the Scottish Government. 
Continue to engage with
Scottish and Southern
Electricity Networks (SSEN) to
explore the impact of low
carbon heating solutions such
as heat pumps and heat
networks on grid capacity. 
We plan to do this through the Local Energy Net
Zero Accelerator (LENZA) platform and through
the emerging temporary Regional Energy
Strategic Plans (tRESP) and overall Regional
Energy Strategic Plan. 
7.3  Reduce transport 
Priority Actions Comment
Investigate the use of multi-modal hubs
and of city centre parking to improve
public transport usage 
The Council has appointed a
consultant to assist in developing an
Outline Business Case and Full
Business Case for the Perth Bus and
Railway Station
Project supported by £15m from the Tay
Cities Deal. 
Deliver behaviour change initiatives to
encourage active travel and public
transport use. 
The Council will promote specific local
bus services, community transport
initiatives and continue to promote free
bus travel offers.
Also, in partnership with Stagecoach,
PKC staff and elected members can
access the recently introduced
discounted bus travel scheme. 
The Council is currently reviewing
potential projects to be delivered using
Local Authority Direct Award funding
from Transport Scotland
Potential projects include support for a
bike share scheme, development of
active travel maps, reviewing active
travel signage and supporting education
programmes.
A Mobility Working Group will be
established with an early action to
review the Mobility Strategy monitoring
and evaluation framework and identify
transport data gaps.
This will allow PKC to effectively monitor
active travel and private car use against
set targets within the region.

Page 23

7.4 Decarbonise Transport 
Priority Actions Comment
Finalise and deliver an EV
Infrastructure Strategy.
Through the EVIF we will support the
decarbonisation of Perth and Kinross' transport
network by ensuring there are new recharging
networks as well as investment in new
technology.
The Council will be applying for
funding to install additional PKC
chargers (for fleet vehicles) at
more public locations.
The use of hydrogen in HGVs is currently being
reviewed but this is not likely to be
implemented in the next 12 months. 
7.5  Deploy local renewable generation 
Priority Actions Comment
Through the Scalable cities project, support
community energy schemes.
Help Identify and develop local
community energy projects
supported by local and national
governments and the private sector
expanding on opportunities identified
in the LHEES/LAEP and the Climate
Action Plan.  
Develop a replicable approach for how
investment from the public and private
sectors in smart local energy systems can
generate wealth for local communities and
help meet net-zero target.   
Assess the suitability for renewable energy
sites and opportunities aligned to the Local
Development Plan. 
Renewable energy site suitability to
be aligned with LDP 3 renewables
local policy development, which is
currently out for consultation. 
Continue to collaborate with Community
Energy Scotland, SSEN and CATCH after
the Scalable Cities project
Help develop a clear pathway for the
development of community energy
schemes through the community
investment framework from the
project. 
Use the experience from the scalable cities
engagement to help stimulate community
ideas for renewable energy generation.
Record and give advice to
communities on funding
opportunities and feasibility studies
to advance the community project. 
Coordination of local energy system inputs
to the transitioning national energy system
planning to support delivery of 8GW
commitment to local and community energy
projects through the Local Power Plan and
GB Energy.

Page 24

Support and raise awareness re Council
readiness to adapt to significant changes in
local government powers, including funding
and delivery of net zero and by evolving
approaches to local net zero planning and
role of net zero plans in the wider context
of the energy system. 
7.6 Data and scenarios building tools and platform:   
The priorities for the next 12 months will be to 
Priority Actions Comment
Prioritise and publish
LHEES/LAEP and related energy
projects data on corporate
systems 
Develop a process for update and
improvement with support from the Council’s
Corporate Data Team. 
The Council will continue to work,
with partners, to further target
areas at a granular level such as
neighbourhood or postcode level
to prioritise a pipeline of projects
for delivery. 
Working through with SSEN, using the LENZA
platform, digital twins for the Council estate
and through development of commercial
delivery models for strategic investment (e.g.
Strategic Energy Partnership), the Council can
continue to prioritise low carbon projects and
programmes, informed by a whole energy
systems approach, through to delivery. 
7.7  Governance 
The priorities for the next year are to: 
Priority Actions Comment
Continue to host the
LHEES/LAEP delivery groups to
work collaboratively and help
deliver some of the non-PKC
owned actions with other
agencies.   
Continue to monitor and evaluate
the LHEES/LAEP master action
plan and associated Key
Performance Indicators (KPIs’).
Report on annual changes and make sure it
aligns with changing national targets and
strategic priorities. 
Publish communications on the
overall benefits of heat pumps
and solar PV.
Overall engagement with residents,
communities, businesses and private landlords
is important to decarbonise properties and
reach our net zero targets. It also ensures
there is awareness of the key heat transition
and energy efficiency priorities for Perth and
Kinross until 2029.

Page 25

Strategic Energy Partnership
Board has been established
spanning several services across
PKC and is meeting regularly to
progress the procurement.
The Competitive Dialogue procurement
process is due to launch in November 2025
with a view to contract award in September
2026. 
PKC has also joined a UK Net
Zero network of cities that will
share experience and encourage
investment in Strategic Energy
Partnerships. 
8.  Monitoring and Review 
8.1 Actions are being implemented through the Council’s LHEES/LAEP
Coordination Team, LHEES/LAEP Steering Group, delivery groups and by
operational teams. All associated groups continue to build on the strong
partnerships already in place, new collaborators, while recognising that
achieving LHEES/LAEP priorities will require a collective effort from delivery
partners, stakeholders, communities, and residents of Perth and Kinross. 
8.2 The LHEES/LAEP action tracker is a live document and continually reviewed
during coordination team meetings to make sure any actions that have stalled
or not been started, can be discussed and remedied. 
8.3 The LHEES/LAEP KPIs have been developed in line with other strategies
including the climate change action plan, mobility strategy, local housing
strategy, local development plan, investment blueprint and PKC
decarbonisation programme. The associated KPIs will be monitored at
coordination group meetings and continually assessed using a variety of PKC
owned and external data sets. The KPIs relate to the overall target of the
LAEP theme and have an associated measurement to show how the KPI can
be monitored and completion date reviewed effectively. 
9. Conclusion 
9.1 The report outlines the progress in implementing the Delivery Plan (2024-
2029) for the Local Heat & Energy Efficiency Strategy (LHEES) and Local
Area Energy Plan (LAEP) (2024-2045) approved at Climate Change &
Sustainability Committee on 27 November 2024 and the priorities for the next
12 months. 
10. Impact Value Assessment 
10.1 This report has been classified as being an operational report and as such
does not require a full Impact and Value Assessment.

Page 26

11. Appendices 
11.1 Appendix I - Updated LHEES/LAEP delivery plan 
11.2 Appendix II - KPI Spreadsheet