Annual Update on the Delivery Plan 2024-29 for Perth and Kinross Local Heat and Energy Efficiency Strategy and Local Area Energy Plan 2024-25

Perth and Kinross Council · 23 October 2024
Back to Climate Change and Sustainability Committee — 23 October 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Some pages contain no extractable text. They may be blank, graphics or scanned pages. OCR has not been applied.

Page 1

PERTH AND KINROSS COUNCIL 
Climate Change & Sustainability Committee 
23 October 2024 
ANNUAL UPDATE ON THE DELIVERY PLAN (2024-2029) 
FOR PERTH AND KINROSS 
LOCAL HEAT & ENERGY EFFICIENCY STRATEGY AND
LOCAL AREA ENERGY PLAN (2024-2045) 
Report by Strategic Lead – Environment & Infrastructure
(Report No. 24/286) 
1. PURPOSE 
1.1 To note progress in implementing the Delivery Plan (2024-2029) for the Local
Heat & Energy Efficiency Strategy (LHEES) and Local Area Energy Plan
(LAEP) (2024-2045) approved at Climate Change & Sustainability Committee
on 27 November 2023 and to approve priorities for the next 12-18 months. 
2. RECOMMENDATIONS 
2.1  It is recommended that the Committee: 
(i) Notes the progress made during the first year (November 2023-October
2024) towards the outcomes set out with the Local Heat & Energy
Efficiency Strategy (LHEES) and Local Area Energy Plan (LAEP) (2024-
2045) (Appendix 1).
(ii) Approves the priorities for the next 12-18 months. 
3.  STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
• Section 4: Background
• Section 5: Context
• Section 6: Annual Progress update and priorities for the next 12-18 months
• Section 7: Monitoring and review
• Section 8: Conclusion  
• Appendices

Page 2

4. BACKGROUND 
4.1 In accordance with the Local Heat and Energy Efficiency Strategies (Scotland)
Order 2022 and in fulfilment of its statutory obligations, Perth and Kinross
Council approved the Local Heat and Energy Efficiency Strategy (LHEES) for
the period 2024-2045, along with the corresponding Delivery Plan for 2024-
2029, on 27 November 2023 (Report Ref 23/330). 
4.2 The LHEES and Delivery Plan were subsequently submitted to the Scottish
Government in December 2023, and the approved documents were made
publicly available. 
4.3 A LHEES provides a long-term strategic framework aimed at improving the
energy efficiency of buildings within the local authority's jurisdiction and
reducing greenhouse gas emissions associated with heating these buildings.
The Delivery Plan outlines how the local authority intends to implement its
strategy. 
4.4 Recognizing the importance of a whole energy system approach as a
fundamental element in delivering the LHEES, a Local Area Energy Plan
(LAEP) for 2024-2045 was developed concurrently, with the LHEES at its
core. The LAEP offers insights into the scope, scale, pace, and timing of the
changes necessary for transitioning to a net-zero energy system. It adopts a
whole energy systems approach, addressing the complex interdependencies
among various energy vectors from generation to consumption. The LAEP
was published in January 2024 marking significant progress to support overall
delivery. 
4.5 The following figure illustrates the components of both the LHEES and the
LAEP, as well as their interactions:

Page 3

5. CONTEXT 
5.1 Both LHEES and LAEP are firmly aligned to the priorities and vision of the
Corporate Plan 2022/23 – 2027/28 (approved by Council in December 2022)
for a Perth and Kinross where everyone can live life well, free from poverty
and inequality. They reflect the views of our communities, elected members,
stakeholders, and partner organisations. These views have helped influence
the development of the LHEES/LAEP priorities and outcomes which are most
important for Perth and Kinross. They are also fully aligned with local
strategies, policies and plans including the: 
• Perth and Kinross Climate Change Strategy and Action Plan
• Perth and Kinross Local Outcomes Improvement Plan 2022-2032
• Perth and Kinross Local Development Plan 2019
• Perth and Kinross Local Housing Strategy 2022-2027
• Perth and Kinross Child Poverty Delivery Plan 2022-2026 
• Tay Cities Regional Economic Strategy and Perth and Kinross
Economic Action Plan (in development) 
6. ANNUAL PROGRESS UPDATE AND PRIORITIES FOR THE NEXT 12-18
MONTHS 
6.1 The annual progress update is attached in Appendix 1 and key points are
provided below. 
6.2 The Perth and Kinross LAEP envisions the area as a model for affordable and
equitable access to sustainable energy for all residents, businesses, and
organisations through an integrated, net-zero local energy system by 2045. 
6.3 The Perth and Kinross LHEES envisions that by 2045, our homes and
buildings will be more energy efficient and with more decarbonised heat
sources providing more affordable warmth and no longer contributing to
climate change. 
6.4 The LHEES and LAEP have the following five Strategic Priorities 
- Improving buildings’ energy efficiency aiming for affordable warmth and
regulatory compliance (LHEES specific)
- Decarbonising heat within a transitioning energy system focusing on heat
networks and heat pumps (LHEES specific)
- Reduce transport
- Decarbonise Transport
- Deploy local renewable generation

Page 4

6.5 The following figure illustrates the various priority intervention areas and
ambitions for 2045: 
6.6 Given the interconnected nature of the LHEES and LAEP, the approved
LHEES Delivery Plan has been expanded to encompass both strategies,
resulting in a shared LHEES/LAEP Delivery Plan. Net zero delivery is evolving
rapidly, as are low carbon technologies, policy and funding landscapes. The
shared LHEES/LAEP Delivery Plan is accordingly, more agile and iterative, to
support the rapid decarbonisation that is required. The Delivery Plan is
considered a ‘live’ document and supported by digital platforms use of ‘live’
data and requiring ongoing stakeholder engagement to ensure aligned
investment and delivery with partners. 
6.7 Key areas of progress in delivering the outcomes include the following: 
Improving buildings’ energy efficiency aiming for affordable warmth and
regulatory compliance (LHEES specific) 
6.8 Our aim is reducing energy demand of Perth and Kinross’s buildings through
improved energy efficiency. Improving building fabric will also be crucial for
facilitating the introduction of highly efficient low temperature heating systems
such as heat pumps. This has the potential to reduce energy costs for
residents, supporting vulnerable households facing rising prices. It also moves
towards Scotland's 2040 goal of eliminating fuel poverty. The challenge is
significant, with over half of Perth and Kinross’s domestic properties requiring
some level of retrofit by 2033 to meet the targets set out in Scotland’s Heat in
Buildings Strategy.

Page 5

6.9 Over the past year, we have produced a strategic decarbonisation programme
across the Council’s building stock. In meeting regulatory standards, we have
prioritised social housing with poor energy efficiency but relatively low
intervention costs for "quick wins” and social housing likely to experience a
greater reduction in fuel poor households due to the implementation of low-
cost retrofit measures. We have developed a business case for a One Stop
Shop (OSS) for retrofit through a Innovate UK funded project. 
6.10 The priorities of the next 12-18 months will be to: 
- Further develop the Innovate UK Revitalising Homes Project including the
One Stop Shop (OSS) to provide bespoke retrofit advice to homeowners
and access to funding. Potential outcomes to include (1) a local Green
Skills Trusted Traders’ Network and supplier/installer framework prioritising
local businesses, 2) a viable business model for a OSS for retrofit advice
and support. 
- Through existing funding, such as Home Energy Efficiency Programmes
for Scotland: Area Based Schemes (HEEPS-ABS), continue to deliver
energy efficiency measures including External Wall Insulation (EWI),
Cavity Wall Insulation (CWI) and combined solar PV and battery storage.   
- Explore how the approach of categorising buildings by types  for building
decarbonisation developed as part of the Council’s decarbonisation
programme can be rolled out across the rest of the stock to prioritise
retrofit and clean heating system transition. 
- Work with delivery partners including Home Energy Scotland (HES) and
Energy Savings Trust (EST) to launch a campaign on education targeting
range of topics and groups. 
- Engage with Scottish Enterprise to use LHEES and LAEP to stimulate
supply chain development. Scottish Enterprise to organise and deliver
CleanHeat25, the Scotland’s largest annual event on clean, renewable
heat to buildings. 
Decarbonising heat within a transitioning energy system focusing on heat
networks and heat pumps (LHEES specific) 
6.11 In Perth and Kinross, over 36% of properties are estimated to be off the gas
network, many of which are heated by carbon intensive fuels such as oil.
These areas should be prioritised for air and ground source heat pumps to
maximise carbon savings. Heat networks should be prioritised in the
urban/towns areas, with the potential of rollout to be investigated in line with
the potential Heat Network zones in Perth, Auchterarder, Blairgowrie and
Kinross.

Page 6

6.12 Over the past year we have: 
- Launched a campaign to encourage and educate businesses,
homeowners, private landlords, and tenants to install heat pumps and
other low carbon heating solutions. This was aided by a number of funding
opportunities including the green heat innovation support fund. 
- Delivered a series of workshops with Tay Cities Local Authorities and
supported by legal advisors to investigate models for delivery of heat
networks and the wider Strategic Energy Programme including power,
heat pumps, retrofit and Electric Vehicle (EV) infrastructure.
- Progressed a funding application linked to Heat Pump Installation through
Tay Cities Engineering Partnership (TCEP). 
6.13 The priorities over the next 12-18 months will be to: 
- Utilise funding from the Strategic Heat Network Unit of the Scottish
Government to build a programme for procuring a partner to deliver heat
networks within a wider energy system. Project to focus on identification of
the build-out from the identified initial Perth City Centre network to the
surrounding area to achieve a city-wide, large- scale, heat network. 
Consideration and alignment of phased, large scale heat network delivery
with the wider strategic energy programme will be a key aspect of this
work. 
- Work to ensure the approach developed through this work can be
replicated in other potential heat network zones in rural areas to discharge
specific duties in relation to review of areas that are likely to be particularly
suitable for heat networks and the designation of Heat Network Zones as
required through Section 54(1) of the Heat Networks (Scotland) Act. 
- Complete Building Assessment Reports (BARs) for required Council
owned buildings. 
- Engage with Scottish and Southern Electricity Networks (SSEN) to explore
the impact of low carbon heating solutions such as heat pumps and heat
networks on grid capacity through the Local Energy Net Zero Accelerator
(LENZA) platform and through the emerging Regional Energy Spatial
Plans (RESPS)

Page 7

Reduce transport 
6.14 Demand changes across all travel modes will be necessary to achieve a fully
decarbonised transportation system in Scotland by 2045. This includes a 15%
reduction in heavy goods vehicle mileage, limiting growth in van demand to
10%, and a 10% increase in bus vehicle miles. Achieving this shift in demand
will require a coordinated approach to how goods and people travel across
Perth and Kinross, focused on reducing overall travel needs, shortening trip
distances, shifting toward alternative sustainable modes like active travel and
public transit, and travelling more efficiently. As Perth and Kinross covers a
large and predominantly rural area with settlements distributed across the
council area, many residents currently travel long distances by private car out
of necessity to meet their mobility needs. It is therefore critical that actions and
policies emerging from the LAEP not only reduce overall car travel but also
ensure improvements in rural accessibility and availability of inclusive,
sustainable mobility options across Perth and Kinross. Additionally, there are
rapid ongoing changes in how people and goods travel, including new
transportation technologies, evolving work and commuting behaviours
stemming from the COVID-19 pandemic, and an increase in online services
and online shopping. 
6.15 Over the past year, we have: 
- Produced the Draft Mobility Strategy and Action Plan which was approved
for consultation by the Climate Change and Sustainability Committee (May
2024). 
- Worked with delivery partners Perth Theatre and Concert Hall to produce a
report, and recommendations released as part of the Transforming
Audience Travel Through Art (TATTA) project, between Perth Theatre and
Concert Hall and Creative Carbon Scotland, sharing key insights on
sustainable audience travel to city centre venues 
- Continued to encourage active travel through public campaigns promoting
the health and environmental benefits. 
6.16 The priorities over the next 12-18 months will be to: 
- Align the actions within the Council’s Mobility and Action Plan and LHEES
and LAEP Strategies and Shared Action Plan to ensure policy synergies
and effective and joined up delivery of actions across the Council and our
Delivery Partners. 
- Through the Innovate UK Connecting Regional Travel project investigate
the viability of two new services focusing on the rural town of Aberfeldy.

Page 8

Decarbonise Transport 
6.17 Decarbonising transportation across Perth and Kinross will require a full
transition to zero emission vehicles by 2045. This needs to be enabled by
public sector fleets leading the way to shift to low emission vehicles,
incentives and engagement to encourage the uptake of EVs in the private
sector, adequate and expanded charging infrastructure, and the development
of new technologies such as hydrogen fuel cell vehicles. 
6.18 Over the past year, we have: 
- Continued to support and work alongside partners such as Stagecoach,
Network Rail, Sustrans, and Tactran to help operate and enhance existing
transportation systems. 
- Awarded a 10-year contract worth £50 million to treat residual waste and
turn it into energy and appointed Paprec Energies Binn Ltd. We will work in
partnership to manage the waste through a thermal treatment, energy
recovery and recycling solution exploring the option to produce hydrogen
on site and to use of hydrogen to fuel the Council’s Heavy Goods Vehicle
(HGV) Fleet. This would reduce the reliance on fossil fuels and associated
emissions. Meanwhile, we have piloted the use of alternative fuel for our
HGV fleet. 
- In partnership with Transport Scotland, The Office for Low Emission
Vehicles and Energy Savings Trust continue to install publicly accessible
chargers.   
6.19 The priorities over the next 12-18 months will be to: 
- Align the actions within the Council’s Draft Mobility and Action Plan and
LHEES and LAEP Strategies and Shared Action Plan to ensure policy
synergies and effective and joined up delivery of actions across the
Council and our Delivery Partners. 
- Finalise and deliver an EV Infrastructure Strategy that will include on and
off-street charging infrastructure and develop a private/public partnership
for delivery and operation. 
- Support the decarbonisation of Perth and Kinross' transport network by
ensuring there are new and expanding recharging / refuelling networks as
well as technological change. 
- Continually assess air quality across Perth and Kinross to assess any
necessary mitigation measures, such as Low Emission Zones.

Page 9

Deploy local renewable generation 
6.20 Scaling up of local renewables is an essential component of delivering Perth
and Kinross’s net-zero energy system. In addition to the existing ~200MW of
local renewable resources, Perth and Kinross will need an additional 300MW
of local scale renewables (i.e. not feeding into the wider transmission
network). These include home and community scale projects that can also
take advantage of energy storage systems. 
6.21 Over the past year, we have: 
- Engaged regularly with Scottish and Southern Electricity Networks (SSEN)
through providing feedback to shape the continued development of the
roadmap for the LENZA platform. The Council has published the
underlying evidence base for the LHEES and LAEP on the platform and
continue to work to improve data and decarbonisation pathway planning
tools to support alignment of investment and strategic planning. 
- Produced a consultation Topic Paper on Energy, Heat and Cooling as part
of the Local Development Plan 3 Evidence Report identifying existing
energy Infrastructure future opportunities and renewable energy and
decarbonised heat constraints and environmental considerations. 
- Secured EU funding through Scalable Cities working with SSEN, Bable,
Community Energy Scotland, SSEN, and community group CATCH to
explore how to involve communities in local energy generation and heat
decarbonisation as part of a strategic approach to building a local and
decentralised energy system. 
- Engaged with the local supply chain including Perth UHI to establish a
targeted skills programme dedicated to renewable energy generation. 
6.22 The priorities over the next 12-18 months will be to: 
- Through the Scalable cities project, support community energy schemes to
identify and develop local community energy projects supported by local
and national governments and the private sector expanding on
opportunities identified in the LHEES, LAEP and the Climate Action Plan. 
- Develop a replicable approach for how investment from the public and
private sectors in smart local energy systems can generate wealth for local
communities and help meet net-zero target. 
- Reassess suitability for renewable energy sites and opportunities aligned
to the Local Development Plan.

Page 10

Enabling actions 
6.23 The delivery of the LHEES/LAEP priorities are supported by the following
mechanisms: 
I. Developing green skills and the capacity of the supply chain: 
There is a need to assess skills provision and support providers as well as the
local supply chain to meet the demand arising from heat transition and energy
efficiency works, operations and maintenance. 
Over the past year, we have: 
- Through the Regional Skills Investment Plan updated and progressed Tay
City Deal (TCD) Digital Skills Strategic Outline Case 2026 – 2030 
The priorities over the next 12-18 months will be to: 
- Work with Skills Board Tay Cities Region Deal and Clean Growth Platform
to identify existing skills and partnerships that could support LHEES
delivery. 
- Work with HES and SCARF and through the Innovate UK Revitalising
Homes project quantify the market opportunities and risks for local
suppliers and develop a local Green Skills Trusted Traders’ Network and
supplier/installer framework prioritising local businesses. 
- Engage with Scottish Enterprise to use the LHEES and LAEP to stimulate
supply chain development and explore how they can shape planning of
upcoming events to articulate opportunities and raise awareness of
potential solutions and innovation across the industry. 
II. Working in partnership with communities to build community wealth and
wellbeing: 
Over the past year, we have: 
- Engaged with Kinross CATCH project providing access to LHEES and
LAEP evidence via SSEN LENZA platform and tools to support
Community Energy Potential Mapping. 
- Engaged with community groups to refine the LHEES/LAEP delivery
programme and align with the actions of our community groups and
partners for delivery.

Page 11

The priorities over the next 12-18 months will be to: 
- Collaborate with Community Energy Scotland and partners SSEN, Bable
and CATCH through the Scalable Cities project to identify and set up the
pathway for the development of community energy schemes. 
III. Mobilising partners and public and private investments for projects: 
Over the past year, we have: 
- Published a Strategic Energy Partner Request for Information and
analysed responses. 
- Consulted with the market and stakeholders through a series of workshops
to evaluate a possible Strategic Energy Partnership to unlock delivery of,
though potentially not limited to, heat networks and to improve delivery
capability into large and complex energy projects. 
The priorities over the next 12-18 months will be: 
- Through Scottish Government Heat Network Unit funding, work with a
legal advisor to produce a Delivery Options Appraisal and progress
towards a Strategic Outline Case for delivery of the Perth city-wide heat
network as a key anchor project for a wider energy projects investment
programme. 
- Establish the Strategic Energy Partnership and develop a 5-year
investment programme. 
IV. Data and scenarios building tools and platform: 
Over the past year, we have:   
- Worked with delivery partners to develop standardised decarbonisation
pathway planning tools to quantify deployment rates and investment
required to meet regulatory targets. 
- Worked with SSEN to publish LHEES and LAEP evidence and develop a
road map for the LENZA platform used to plan and coordinate retrofit and
roll out of low carbon technologies which will facilitate collaboration
between network operators, local authorities and other energy transition
stakeholders to achieve our strategic priorities and plan investment
strategically. 
- Supported Integrated Environmental Solutions (IES) funded by Innovate
UK in a the 3D-UP project (Dynamic, Digitised Decarbonisation investment
and engineering roadmaps for Upgrading building portfolios) to develop a
digital twinning infrastructure and methodology for the development of
decarbonisation pathways for building portfolios.

Page 12

- Developed a toolkit that will allow us to filter projects and develop business
cases to triage delivery actions and areas into a pipeline of investable
energy projects based on a range of priorities. 
The priorities for the next 12-18 months will be to:- 
- Continue to work to evolve the LHEES/LAEP evidence base and tools to
support whole systems energy planning with delivery partners and data
providers. 
- Work with SSEN, Ordnance Survey, Energy Savings Trust and additional
delivery partners to map user access journeys to digital evidence
underlying LHEES and LAEP including data sharing and licensing
arrangements. 
- Continue to support the 3D-UP project. 
- Prioritise and publish LHEES/LAEP and related energy projects data on
corporate systems and develop a process for update and improvement
with support from the Corporate Data Team. 
V. Governance: 
Over the past year, we have: - 
- Established the Council’s LHEES/LAEP Coordination Team which will also
action as the LHEES/LAEP Programme Board and will provide strategic
directions and monitor progress and performance. 
- Identified an Executive Sponsor and a Senior Responsible Owner. 
- Established a LHEES/LAEP Steering Group supporting coordination of
Delivery Plan actions with wider stakeholders and delivery partners and
held a series of workshops to align delivery actions with partner actions to
support joint delivery. 
- Recruited a coordinator who will monitor the Delivery Plan actions and will
report to the Board to support coordination and governance administration,
engagement and monitor and report on progress and performance of
Delivery Plan actions. 
The priorities for the next 12-18 months will be to: - 
- Develop a monitoring and evaluation plan (MEP) building on and aligning
with supporting strategies such as the Local Housing Strategy, Draft
Mobility Strategy and Action Plan and Climate Action Plan. The MEP will
set out actions and progress towards national targets and strategic
priorities and where possible align with existing Key Performance
Indicators (KPIs) to measure progress towards strategic priorities and
outcomes alongside a detailed risk assessment.

Page 13

- Develop a Communication and Engagement Plan through the Steering
Group setting out the Council and Steering Group will conduct regular
consultation and engagement with stakeholders. Engagement with
residents, communities, businesses and private landlords would be
particularly important. It will also ensure there is awareness of the key heat
transition and energy efficiency priorities for Perth and Kinross until 2029. 
7. MONITORING AND REVIEW 
7.1 Actions are being implemented through the Council’s LHEES/LAEP
Coordination Team and LHEES/LAEP Steering Group and by operational
teams. Both continue to build on the strong partnerships already in place,
recognising that achieving LHEES/LAEP priorities will require a collective
effort from delivery partners, stakeholders, communities, and residents of
Perth and Kinross. 
8. CONCLUSION   
8.1 The report outlines the progress in implementing the Delivery Plan (2024-
2029) for the Local Heat & Energy Efficiency Strategy (LHEES) and Local
Area Energy Plan (LAEP) (2024-2045) approved at Climate Change &
Sustainability Committee on 27 November 2023 and the priorities for the next
12-18 months. 
Authors
Name  Designation Contact Details
Shelley McCann 
Stuart McLaren 
Serge Merone
Climate Change –
Strategic Planning &
Sustainability Officer 
Climate Change &
Energy Officer 
Business &
Investment Manager 
(01738) 475000
EPLCommitteeReports@pkc.gov.uk 
Approved 
Name Designation Date
Fraser Crofts Strategic Lead –
Environment and
Infrastructure
8 October 2024 
APPENDICES 
• Appendix 1 – LHEES/LAEP Shared Delivery Plan 2024-2029 Annual
Progress Update.

Page 14

No embedded text on this page.

Page 15

ANNEX
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce None
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment None
Sustainability (community, economic, environmental) Yes
Legal and Governance  Yes
Risk Yes
Consultation 
Internal  Yes
External  Yes
Communication 
Communications Plan  Yes 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 The activities detailed in the report supports the delivery of Perth and Kinross
Community Plan/Single Outcome Agreement in terms of the following
priorities: 
(i) Giving every child the best start in life; 
(ii) Developing educated, responsible, and informed citizens; 
(iii) Promoting a prosperous, inclusive, and sustainable economy; 
(iv) Supporting people to lead independent, healthy, and active lives; and 
(v) Creating a safe and sustainable place for future generations. 
1.2 This report relates to all priorities. 
Corporate Plan 
1.3 The activities detailed in the report supports the achievement of the Council’s
Corporate Plan Priorities: 
(i) Giving every child the best start in life; 
(ii) Developing educated, responsible, and informed citizens; 
(iii) Promoting a prosperous, inclusive, and sustainable economy; 
(iv) Supporting people to lead independent, healthy, and active lives; and 
(v) Creating a safe and sustainable place for future generations.

Page 16

1.4  This report relates to all priorities. 
2. Resource Implications 
Financial 
2.1 Financial implications arising directly from this report emanate from the local
authority domestic and non-domestic decarbonisation programme. Funding
from the Scottish Government, other public bodies and private finance will
apply in relation to particular actions. Allocated LHEES funding from the
Scottish Government (75K/year over 2024/25, 2025/26 and 2026/27) will be
used to support and strengthen the LHEES coordination and overall delivery.
The post of Climate Change Energy Officer has been created and recruited
using this funding. 
Workforce 
2.2 There are no workforce implications arising from the recommendations in the
report. However, allocated LHEES funding from the Scottish Government has
been used to create the post of Climate Change Energy Officer. 
Asset Management (land, property, IT) 
2.3 Asset implications of this report relate to the local authority domestic and non-
domestic decarbonisation programme and the use of land or other assets in
Council’s ownership. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups. Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the 
Corporate Equalities Impact Assessment Process (EqIA) and has been
assessed as not relevant for the purposes of EqIA. However, it is anticipated
that the LHEES outcomes would benefit positively all age groups and people
with a disability. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals.

Page 17

3.4 The proposals have been considered under the Act. Having consulted the
three consultation authorities, and having considered the criteria set out in the
Act, the Council considers that the LHEES Strategy & Delivery Plan is unlikely
to have significant environmental effects. The Council has therefore
determined that SEA is not required. 
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council must discharge its duties in a way which contributes to the
achievement of sustainable development. Under the Climate Change
(Scotland) Act 2009, the Council also has a duty relating to climate change
and, in exercising its functions must act: 
• in the way best calculated to delivery of the Act’s emissions reduction
targets;
• in the way best calculated to deliver any statutory adaptation
programmes; and
• in a way that it considers most sustainable. 
3.6 The information contained within this report has been considered against the
Council’s Principles for Sustainable Development and the report aims to
ensure compliance with the reporting requirements under the Acts. 
Legal and Governance 
3.7 The Strategic Lead - Legal and Governance has been consulted and there
are no direct legal implications in this report. However, the development of a
Strategic Energy Partnership Framework will lead to agreements with
selected partners which will have to comply with procurement rules. 
Risks 
3.8 Risks associated with the delivery of LHEES actions are covered within the
LHEES/LAEP Delivery Plan. A Risk register is being developed.  
Communication 
3.9 The decisions from the report will be communicated to stakeholders and the
press through the media team. A Communication Plan is being developed. 
4. Consultation 
Internal 
4.1 There has been internal consultation with Strategic Leads and Service
Managers through Climate Change Board and LHEES/LAEP working groups.

Page 18

External 
4.2 Consultation with a range of stakeholders, including businesses, residents
and groups progressed through online and in person external meetings. 
2. BACKGROUND PAPERS 
2.1 No background papers, as defined by Section 50D of the Local Government 
(Scotland) Act 1973 (other than any containing confidential or exempt 
information) were relied on to a material extent in preparing the above report.