Appendix 1 - Actions with a completion date up to July 2026 which have yet to be completed

Perth and Kinross Council · 21 September 2026
Back to Audit and Risk Committee — 21 September 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Appendix 1 
Actions with a completion date up to July 2026 which have yet to be completed
Finding Action  Action owner
& Service
Date(s) Current status Internal
Audit
Opinion
A24-01 - Business Continuity
Management (BCM) Planning 
Action Point : 1.2 
Importance: High 
Audit Committee Date: June
2025 
Our observation highlighted
the need for Business
Continuity Plans (BCPs) to be
regularly updated, particularly
regarding contact details and
emergency actions. Despite
the introduction of a new
template, up to-date BCPs
were not found across all
services. The audit concluded
without verifying signed BCPs
for all services. 
Diarise annual reviews,
with realistic spacing from
2026 onwards.
All Strategic
Leads,
supported by
EP&BC Officer
June 2026 Following on from
other associated
actions being deferred,
this action is now
anticipated to be
completed by
December 2026.
Accepted
A24-01 - Business Continuity
Management (BCM) Planning 
Diarise training and
exercising following each
annual review.
All Strategic
Leads,
June 2026 Following on from
other associated
actions being deferred,
Accepted

Page 2

Action Point : 2.2 
Importance: High 
Audit Committee Date: June
2025 
Our observations revealed
that the previous versions of
the BCPs had not routinely
been subject to adequate
testing and communication
(training and exercise) since
prior to the Covid-19
pandemic. Furthermore, the
latest Business Continuity
Management (BCM)
procedure has not been
finalised, preventing us from
providing any comments on
its effectiveness at this stage 
supported by
EP&BC Officer
this action is now
anticipated to be
completed by
December 2026.