2022/23
PLANNING
PERFORMANCE
FRAMEWORK 12

Page 2

About Argyll and Bute
Population (2019):
85,570 9% 
Argyll and Bute as
a proportion of the
total Scottish land
area.
Average Pop. Density (2019):
0.12 persons per ha
43% 
of Argyll and Bute’s
Population live in
areas classified as
“remote rural”.
21
inhabited islands* 
Bute, Coll, Colonsay,
Danna, Easdale, Eilean
da Mheinn,  Erraid,
Gigha, Gometra, Iona,
Islay, Jura, Kerrera,
Lismore, Luing, Mull,
Oronsay, Seil, Shuna
(Luing), Tiree, Ulva 
* not including LLTNP area
80% 
of Argyll and Bute’s
population live within
1km of the coast.
52
of Argyll and Bute’s
125 data zones are
amongst the 20%
most geographically
access deprived
data zones in
Scotland.
Scottish Index of Multiple
Deprivation 2020
£536
average weekly
income 
Compared to Scottish
Average of £577, and
UK Average of £688
(2019)
33%
of employment is in
“Public
Administration,
Education and
Health”
Compared to 29.8% in
Scotland, 26.4% in UK (2018) Front cover Image credits:
Main: DB3 Architecture & Design
Top: Bute Community Forest
Bottom: James Fraser

Page 3

Argyll and Bute Key Challenges:
Our geography – A highly rural area with many small communities, often separated by water.
Access to the area and to key services are perennial challenges.
Reducing population – The projected decline in total population is a real threat to the viability of
the area with a potential to adversely impact on the economy/wealth creation, workforce
availability and efficient service delivery.
Changing population – With more extremes than most of Scotland we face increasing costs
and challenges to deliver services to older people and we need to encourage younger people to
move to the area so that our economy can grow.
Economy – Unlocking the opportunities offered by its significant, sustainable economic assets
for the benefit of its communities and the competitiveness and security of the Scottish and EU
economies.
Employment – Developing education, skills and training to maximise opportunities for all and
create a workforce to support economic growth.
Infrastructure – Improving and making better use of infrastructure in order to promote the
conditions for economic growth including enhancing the built environment and our town centres.
Sustainability – Ensuring a sustainable future by protecting the natural environment and
mitigating climate change.
Health –Improving health and well being and reducing health inequalities.
Deprivation –Inequalities exist in Argyll and Bute so we need to improve how we identify and
implement action to address them. 
People on the fringe – Many of our communities are very isolated and risk collapsing as
population changes take affect alongside urban communities where deprivation can create real
hardships.
The Strand, Isle of Colonsay

Page 4

As the Head of Development and Economic Growth, I am pleased
to submit the annual performance report for Argyll and Bute
Council’s Planning Service, which provides relevant statistics for
2022/23 and case studies highlighting the work of the council’s
planning service that forms part of the wider Development and
Economic Growth Service of the council. This 12th Planning
Performance Framework report is written at a time of sustained
change in the Planning Service with new Government legislation
and increased demands on the planning workforce.  This has
come at the same time of a number of global and national
challenges that continues to impact on the wider development
industry and our communities.  
We continue to make investments in our places with the
completion of the Helensburgh Waterfront project and
Lochgilphead Front Green that have now received two national
awards.  This has also been an important year for community led
development across Argyll and Bute with key projects delivered in
partnership with planners and economic development colleagues. 
Projects as diverse as new campsites, business parks, affordable
homes, spaceports, restoring peatlands and expanding natural forests.  This work will gather
momentum with new investments planned and successful funding bids looking at key worker
housing and improvements to public realm and flood defences.  
The council has now declared a housing emergency and this will require significant investment in
unlocking sites for new homes and some radical thinking on how we can accelerate housing
delivery.  The situation has made more difficult by high inflation and increased borrowing costs but
a wide range of partners are now involved to assist in this process. Another key aspect of this is
the introduction of short term licensing and assessing the need for planning control zones as we
consider new data emerging on second home ownership in many of our rural communities that
also rely on tourism for a large share of our economic activity. 
A key highlight this year has been our design awards that celebrated a number of first class and
innovative  building projects in places such as Iona, Tiree, Helensburgh and Dunoon to name a
few places.  Sustainability was at the heart of most of the award winning designs and this was the
first time in seven years we were able to present the awards due to the pandemic and other factors
getting in our way. 
Our heritage investments and shopfront improvement schemes have helped support small
businesses in our town centres and we continues to work with our growing network of BIDs.
Next year will again be hugely challenging for the Planning Service.  Workloads remain high with
major applications coming forward in renewables and energy, industry, housing and leisure.  A
new Local Development Plan (LDP2) is scheduled to be adopted in 2023/24 as we look to take on
board the full implications of NPF4 and the new duties of the Planning Act.  Experienced Planners
are in short supply and whilst we have had some recent success in recruiting we are also looking
still to expand our team at a time of great budget challenge for our
authority and competition elsewhere. It is hoped that a new workplace
action plan will assist us here including looking at streamlining our
internal processes and improving communication with our customers. 
Foreword:
Fergus Murray
Head of Development &
Economic Growth
Argyll and Bute Council
3

Page 5

Contents:
Planning Performance Framework Report 2022/23
Foreword P3
Part 1: Defining & Measuring a High Quality Planning Service 
Part 4: National Headline Indicators (NHI’s) 2022/23 P38
Part 5: Official Statistics P40
Part 6: Workforce Information P43
Part 7: Planning Committee Information P45   
Case Study 1:  Dunbeg Masterplan - Update 2023 P8 
1.2 Quality of Service and Engagement P11 
Case Study 2:  Lochgilphead Front Green P15 
1.3 Governance P18 
Case Study 3:  Argyll and Bute Design Awards 2022/23 P22 
1.4 Culture of Continuous Improvement P27 
Case Study 4:  Local Authority Officers Aquaculture Group P31
Part 2: Supporting Evidence & Performance Markers P32
Part 3: Service Improvements P36 
1.1 Quality of Outcomes P5
4

Page 6

Defining and Measuring
a High Quality Planning
Service Part 1:
1.1 QUALITY OF OUTCOMES
1.1.1  Throughout 2022/23 the Planning Service has continued to work closely with
communities, developers and partner organisations to deliver a range of developments across
Argyll and Bute.
1.1.2  The adopted Argyll and Bute Local Development Plan 2015 (the LDP) is firmly
embedded into decision making with 12 key policies which seek to promote the delivery of
sustainable long term economic growth to support the retention and growth of our population; to
support the transition to a low carbon economy; to help retain and improve essential services;
to protect and enhance our outstanding natural and built environment, and to maintain and
improve our quality of life. Whilst the LDP is now more than five years old it is still considered fit
for purpose in terms of decision making alongside NPF4 and will remain so until it is replaced
by the Argyll and Bute Proposed Local Development Plan 2 (PLDP2) which is now at an
advanced stage in its preparation and has reached Examination stage (it is noted that the
Examination Report has subsequently been published by the DPEA in June 2023).
1.1.3  Interpretation and implementation of the LDP policy aims is assisted by a suite of
Supplementary Guidance and non-statutory Technical Working Notes. These include
publications on: Masterplanning, Advertisement and Signage Policy, Houses in Multiple
Occupation, and a Biodiversity Technical Note for Planners and Developers. In 2021/22 we
published non-statutory guidance on the handling of requests for Non-Material Amendments
under S64 of the Act was updated. Advice for communities interested in Local Place Plans was
published also online during 2021/22 and updated during 2022/23 alongside the provision of
additional guidance for elected members. Planning fee guidance was also updated in 2022/23.
1.1.4  The Council seeks to promote high quality design through the publication of
Sustainable Design Guidance covering a range of topics including Small Scale Housing
Development, Larger Housing Development, Working with Argyll and Bute’s Built Heritage,
Case Studies on Sustainable Materials and Technologies, and place specific guidance for the
unique circumstances of the Islands of Coll and Tiree. Delivery of quality in design and place
making is celebrated and championed through the Council’s Sustainable Design Award
scheme. The most recent iteration of the Sustainable Design Awards was launched in February
2020 but was subsequently postponed as a result of the Covid-19 pandemic. The Argyll and
Bute Design Awards 2022 were relaunched in October 2022 to recognise work that was carried
out or completed in the period July 2015 to December 2022. The award categories included
Sustainable Design, Aesthetic Design, Community Led Regeneration Project, Built Heritage,
and Design for Under £100k, with two additional categories of a Public Choice and an Elected
Member Choice. The range of categories are intended to highlight good practice across varying
scales and types of development, and include for the promotion of low cost-innovative design,
and community led developments. See Case Study 3 for details.
Planning Performance Framework Report 2022/23
5

Page 7

1.1.5  There are 33 Conservation Area designations across Argyll and Bute providing
protection to the historic built environment. Where resources allow, the Council seeks to review
and update the Conservation Area Appraisal and Character Evaluations that underpin the
management of these designations and to support regeneration activity.
1.1.6  Through considered and targeted investment, the Council is continuing to develop,
deliver and distribute funding to regeneration projects, the foundations of which support more
attractive and prosperous places. A bespoke webpage. Place Based Regeneration - Invest in
Argyll (investinargyllandbute.co.uk), provides information on the many ongoing and completed
regeneration projects which are being delivered by teams across Argyll and Bute Council as well
as by community groups. The projects which were developed and delivered by the Projects and
Regeneration Team during 2022/23 are as follows:
Dunoon CARS  - a partnership project with Historic Environment Scotland. To date this has
delivered the completion of 3 priority buildings with a fourth building currently onsite, 6 full scale
shopfront restorations and 7 Owners Associations formed with a total investment spend of £1.9
million. An additional £68,000 was secured to improve shopfronts and increase footfall into the
town. So far this has seen an additional 32 grants processed for smaller scale shopfront
improvements. During 2021/22 an allocation of £70,000 was made from the Place Based
Investment funds towards improvements to Castle House Gate Lodge and its surrounds. Delivery
of the CARS is continuing through 2022/23. 
Helensburgh CARS - a £3m heritage-led regeneration project in partnership with Historic
Environment Scotland. Three priority buildings have been granted funding and works are planned
to commence early in 2024. One shopfront grant has also been awarded and works are
commencing in Summer 2023. Small repairs discussions are continuing and it is hoped to
progress this aspect during 2023/24. Discussions are currently ongoing to fund an apprenticeship
in traditional building skills via the Developing Young Person’s Programme, and other training
events are being planned for 2023/24.
Lochgilphead CARS - a partnership project with Historic Environment Scotland with total
investment spend of £2m. Two priority buildings are now on site. The remaining two priority
buildings are currently in the development phase with an expected start date of Spring 2024. A
small number of repair grants are being developed including some prominent shopfront
improvement schemes. The traditional skills training programme is progressing well. Local
contractors and building professionals have benefitted from a number of courses including Lead
Working and Bossing Skills, and a Level 3 Award in Energy Efficiency. Additionally, over 100 high
school students have participated in Construction Skills Demo Days.
Rothesay Townscape Heritage 2  - a partnership project with National Lottery Heritage Fund,
Historic Environment Scotland, Highlands & Islands Enterprise, LEADER and SUSTRANs. To
date this has delivered completion of 8 priority buildings, 14 shopfronts, 10 small repairs and 2
window projects with total investment spend of £5.4m. The project is ongoing until the end of
September 2023 due to delays arising from the Covid-19 pandemic. The project was supported
by grant funding from Place Based Investment to help assist with rising construction costs. 
Lochgilphead Front Green / Lochgilphead Public Realm Works - During 2022/23 the £1.6 million
investment planned for the Front Green completed its construction phase delivering a revamped
play area, new public square and new pathways which have opened up the Front Green to all.
The site is identified as an Area for Action within the Local development Plan and the works
6
Planning Performance Framework Report 2022/23

Page 8

complement the previously completed Colchester Square and Argyll Street public realm
improvements (see PPF 9) and the ongoing Lochgilphead CARS. The project has won the
Scotland Loves Local Awards 2022 category for Streets and Spaces in November 2022 and the
Landscaping/Public Realm category of the Scottish Design Awards 2023. See Case Study 2 for
details.
Tarbert / Ardrishaig Regeneration - Regeneration projects in Ardrishaig were reported on in PPF
5, PPF 6 and PPF 9. During 2022/23 construction work on the Ardrishaig North Public Realm
project commenced with a planned completion date of April 2023. The project will deliver
environmental improvements to the waterfront including a waterside viewing area, improved
pathways and a new public square adjacent to local community facilities. The site is identified as
an Area for Action in the LDP.
Place Based Investment - The Place Based Investment (PBI) Fund, superseded the Town Centre
fund in 2021, which the Scottish Government has committed to allocating on an annual basis
over a five year period. Projects committed within the 2022/23 period are as follows:
£100,000 grant to Oban Communities Trust to create a new outdoor space, which will include a
community wellbeing garden, amphitheatre style seating, new and resurfaced pathways and
signage at the Rockfield Centre which will be utilised by the community as a place that enhances
community wellbeing.
Working with Isle of Bute BID to deliver community-led ambitions of re-instating the fountain on
Rothesay promenade through a £15,000 investment.
Supporting South Islay Development with a £44,000 grant for the Port Ellen Playing Fields
project. This project is funded primarily from the Regeneration Capital Grant Fund (RGCF) to
deliver a Community Hub and Motorhome site which will empower an isolated and disadvantaged
community to become sustainable through economic, physical and social regeneration, creating
transformational change in a place where people want to live, work and invest.
Supporting Tobermory Harbour Association with a £140,000 grant to deliver the Pier and
Quayside Restoration project element of the wider Aros Waterfront Development. The Aros
Waterfront Development is a long-term multiphase project with an overarching objective to create
a hub for community well-being, outdoor activities, and educational opportunities, as well as
opportunities for new enterprises and sustainable tourism experiences.
£100,000 investment to complete Phase 2 of the Tobermory Harbour Wall and Railings Project
that has provided critical seafront infrastructure to the community of Tobermory by adding
resilience against tidal surges and helping to reduce the impact of climate change.
A further £113,000 investment towards public realm enhancements in the masonry pier section of
Helensburgh Pier. The project follows on from the Council’s £22 million Helensburgh Waterfront
Development project as it will uplift the pier’s visual appearance including views out from the new
swimming pool and gym.
£200,000 to assist with the delivery of Lochgilphead Conservation Area Regeneration Scheme
(CARS). The funding was awarded as third party grants to owners of two priority buildings and
enhanced project outcomes, helped safeguard two historic buildings and improved the
appearance of the town. 
7
Part 1 continued on P. 11  Planning Performance Framework Report 2022/23

Page 9

Dunbeg Masterplan -
Update 2023 Case Study 1
8
Themes A: Quality of
Outcomes
B: Quality of
Services & 
Engagement
C: Governance
D: Culture of
Continuous 
Improvement
Performance 
Markers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Key Areas of Work Design, Masterplanning, Affordable Housing, Collaborative Working,
Housing Supply, Community Engagement, Placemaking
Stakeholders Argyll and Bute Council, Scottish Government, LINK Housing, Local
Community
Project Lead Matt Mulderrig
In PPF 8, PPF 9, PPF 10 and PPF 11 we provided an update on the implementation of the
Dunbeg Masterplan, which focussed on the installation of essential infrastructure upgrades, and
provided an overview of cross-service internal and external collaborative working arrangements
that had been put in place to bring the project to fruition. 
The project is being delivered
through a strategic partnership
between Argyll and Bute Council
and LINK Housing Association. The
aim of the project was to provide a
sympathetic extension to the
existing settlement of Dunbeg and
has taken a design-led approach in
addressing the challenges
presented by its rural location and
coastal, moorland landscape to
deliver a development with
placemaking and connectivity firmly
established in its foundation.
Completion of Phase 3 properties has
progressed well during 2022/23 and
remains on track for all properties to be
handed over by December 2023 which will
bring the total number of properties
delivered within the Dunbeg Extension to
375 so far. The project continues to face
significant challenges with supply chains
and workforce availability reflecting post-
Covid impacts at national and global
levels. The innovative design and layout of
the development is now clearly starting to
emerge on the ground and the demand for housing for workers and students in the locality has
been bolstered through further new developments in the immediate locality including further
investment and growth at the adjacent European Marine Science Park, and ongoing work to
expand the offering of the University of the Highlands and Islands Dunbeg campus.

Page 10

Planning Performance Framework Report 2022/23
The Council will continue to work with key partners in the area to ensure that all sections of the
housing market continue to meet demand as this is a key aim of the Council’s Rural Growth Deal.
The main focus during 2022/23 has been to develop further detail of future phases including
housing, commercial and infrastructure development. LINK and the Council have worked in
partnership to develop more
detailed site investigation and
understanding of the
requirements of the development
will require to take this into
consideration. This partnership
working has been extended to
the community and key
stakeholders, most notably
through holding quarterly Dunbeg Partnership
meetings which allows the exchange of views
and information in an open forum.
Development of a Transport Assessment and
engagement with Transport Scotland has
confirmed the Trunk Road junction design,
9

Page 11

and time has been taken to assess and comply with the additional requirements of NPF4
including Biodiversity and Creating Nature Networks. Work is currently on track to submit planning
applications for the residential, infrastructure and commercial developments in August 2023. It is
anticipated that this will include approximately 430 new homes.
Work is also ongoing to create Dunbeg Community woodland working together with the Argyll
Countryside Trust. The first phase of planting is programmed to take place during 2023 and there
is potential for further phases to be delivered with future development.
The Council has continued to engage with Scottish Futures Trust and the Scottish Government to
ensure that Lorn Arc TIF funding will remain available for the project, and it is anticipated that a
Housing Infrastructure Fund bid will be made at the appropriate time.  
10
Planning Performance Framework Report 2022/23
Future Housing Layout
Future Road Network Layout

Page 12

Hermitage Parks for People - £3.9m project for the heritage-led regeneration of Hermitage Park.
The project has been part funded by National Lottery Heritage Funding and is now reaching its
final phase of implementation and is programmed for completion in December 2022 (extended
due to the Covid-19 pandemic). In addition to work reported in the previous PPF, the project has
continued to deliver assorted areas of new or improved planting and a demonstration garden with
bespoke volunteer bothy (with funding from Place Based Investment). In June 2022 Hermitage
Park was awarded its third consecutive Green Flag status recognising not only the park’s green
credentials but also the involvement of the community and educational link to the University of
the Highlands and Islands. 
1.1.7 In PPF 11, Case study 2 reported on partnership working between Argyll and Bute Council,
Scottish and Southern Electricity Networks (SSEN), and the Argyll and the Isles Countryside
Trust (ACT) in a project to create 30 hectares of native woodland as part of a compensatory
planting arrangement. The merits of this ambitious project have since been recognised through
being short-listed in three different awards including the RSPB Nature Scotland Awards 2022, the
Scottish Green Energy Awards, and the National Utility Awards.
1.1.8 Involvement of the Planning Service has been instrumental in facilitating a number of
developments which have/will deliver new housing, infrastructure, schools, employment,
renewable energy, and tourism accommodation/facilities. 
1.2 QUALITY OF SERVICE AND ENGAGEMENT
1.2.1  The LDP and priorities of the Planning Service are closely aligned with the Argyll and
Bute Outcome Improvement Plan 2013-23 (previously known as the Single Outcome Agreement
and Community Plan). The Outcome Improvement Plan remains the sovereign document and the
LDP aims to translate its objectives in to a deliverable spatial strategy. The Council’s Action
Programme is utilised to focus action on priority proposals and allocations, and to identify work
which is required to enable development. The Council’s internal key performance indicators for
the Planning Service all directly tie in and seek to demonstrate a contribution to delivery of the six
long term outcomes identified in the Outcome Improvement Plan. Case Studies 1 & 2 provide an
example of these corporate aims being delivered on the ground by LDP policy.
1.2.2  PLDP2 was submitted to the Scottish Government for  Examination in early 2022 and
subsequently the DPEA issued a statement of conformity. The publication of the Examination
Report by the DPEA was however delayed by the progression of NPF4. In addition the
Development Policy team has fully engaged with the Scottish Government on NPF4. An updated 
project plan for the Development Plan Scheme was last published in March 2022. See also 1.1.2
1.2.3  The Planning Service is located in various offices across the main settlements of Argyll
and Bute providing relatively easy access to a large proportion of the population. Customers on
remoter mainland and island locations are also able to access Council services at Customer
Service Points. The Planning Service also provide website, e-mail, and telephone based services
to customers, and continues to utilise social media as a means of public engagement. The
Council’s response to the Covid-19 pandemic involved the temporary closure of public offices
and delivery of planning services via home working and digital communication channels; these
arrangements have continued throughout 2022/23. The Planning Service has continued to
engage in a wider corporate discussion within the Council on ‘Our Modern Workplace’ that is
11
Planning Performance Framework Report 2022/23

Page 13

exploring the potential to review future workplace arrangements through permanent home
working / hybrid working arrangements, and rationalisation of the Council’s portfolio of office
accommodation.
1.2.4  The Planning Service, working in partnership with Regulatory Services, initially
attained the  Customer Service Excellence Standard in February 2019. An overview of the work
undertaken to reach this attainment was set out in PPF 8. The CSE Standard was retained
following reassessment and confirmed in April 2021. A wider corporate review of how the CSE
Standard is applied within the Council has precluded undertaking reassessment during 2022/23
however it is currently anticipated that this will be revisited during 2023/24 as part of a joint
application by wider grouping of Council Services. A review and update of the Development
Management Customer Service Charter will also be undertaken during 2023/24.
1.2.5  The Planning Service continues to build partnerships both internally and externally.
The Development Policy and Development Management teams have close links and seek to co-
ordinate activity/resources with Economic Growth, Projects and Regeneration, Building
Standards, Rural Growth Deal, Environmental Health, Strategic Transport, Housing, Access, GIS
and Coastal Development function which all sit under a single Head of Service. Departmentally
the Planning Service is also aligned with Roads and Infrastructure under a single Executive
Director. The Council Service structure facilitates partnership working and promotes symbiosis in
working practice including the merging of Housing with Development Policy to better realise the
synergies between these services in the delivery of effective affordable housing development and
the Strategic Housing Investment Plan (SHIP). During 2022/23 the new Council has identified
that one of its priorities is to deal with the shortage of housing which has become a critical issue
within the area. An internal working group has been set up including senior officers from across
all the Council’s Services to identify potential solutions and possible interventions. This activity is
seeing rapid progress with early quick wins including the refurbishment of a number of redundant
Council properties brought back into active residential use by key workers, and being let in co-
ordination with a local island Community Housing Trust. The Council has also set up a Data
Advisory Group to improve our utilisation of digital information and improve the availability of real
time information.
1.2.6  Customer User Forums have previously been held regularly as a joint exercise
between the Development Management, Development Policy and Building Standards Services
providing a co-ordinated approach to engagement with regular professional customers. The
content of recent User Forums include updates on the PLDP2 process, validation standards,
updates on changes to legislation, details of any revision to staffing and service delivery
arrangements,  performance appraisal, and details of recent publications/guidance. Whilst some
local level engagement was undertaken during 2022/23 it is intended to reinitiate Service level
Customer User Forums during 2023/24.
1.2.7  In addition to engaging with individual companies on application specific issues, the
Planning Service also seeks to engage directly with the aquaculture industry by arranging an
annual liaison meeting with local industry representatives with hosting arrangements alternating
between the Council and Industry. The event intended for 2019/20 was due to be organised and
hosted by the Scottish Salmon Producers Organisation and has still to be revived following the
Covid-19 pandemic. The agenda for the last meeting in 2018/19 meeting included an update on
12
Planning Performance Framework Report 2022/23

Page 14

LDP2, the Clyde Marine Plan, Planning Performance, revised Industry Planning Protocols,
discussion about changes to SEPA’s licensing regime and its implications for planning, wild fish
interactions, and updated EIA Regulations. In the interim meetings have continued with individual
companies however it is hoped that the annual industry liaison meeting can be revived during
2023/24.
1.2.8  The Development Policy Service has developed a remote based assessment of
housing land supply in order to verify that it is fit for purpose and does not act as an impediment
to the delivery of new house building. This has allowed us to carry out a survey despite
‘lockdown’ restrictions. The Council continues  to explore innovative ways in which it can
contribute to or facilitate the further delivery of a variety of housing types as reported in PPF 7.,
and is meeting regularly with all local Registered Social Landlords (RSLs) to identify working
groups as appropriate to find tailored solutions for site specific development impediments.  A
quarterly Housing Forum is chaired by the Leader of the Council. In addition the Council hosts a
forum for Community Housing Trusts with as many as a dozen local communities either already
having or planning to provide housing directly themselves. In one case this is being delivered in
partnership with a key local employer helping to ensure that they can find accommodation for key
workers. In partnetship with our local HSCP, we are financing and additional Empty Homes
Officer post who will assist in finding accommodation for key NHS workers.
1.2.9  The Council remains supportive of national efforts to roll out improved communications
infrastructure. The Council’s Digital Liaison Officer continues to provide assistance and single
point contact for numerous consultants and monitors progress of telecommunications planning
applications as they are developed, submitted and implemented, following internal protocols to
engage planning officers with greater expertise in telecoms development when required.
Feedback from consultants has been complimentary of the processes which the Council have
implemented to assist in the progress of digital connectivity. EE/BT have previously commented 
positively on the streamlined process that the Planning Service have implemented in assisting in
network coverage development. It has also been highlighted internally that cross departmental
working will be intrinsic to the successful development of improved fibre penetration into rural
communities given the challenges and, in some cases, short timeframes for implementation.
1.2.10  The Council recognises that it cannot work in isolation and that collaborative working
will deliver the most productive outcomes for communities. Area regeneration efforts require
substantial involvement from the community as a whole, and relies on private and third party
partnerships and subsequent investment. The Council has previously reported on ongoing
collaborative work with a number of housing sector partners to identify solutions that continue to
deliver new homes where and when they are needed. Amongst others this includes Mull and Iona
Community Trust who we are working with to develop a model where the Council can let them
property to provide accommodation for key workers and temporary seasonal workers on the
island of Mull; this is a new approach which is being piloted and will evolve as we learn. The
Council has also worked with Mull and Iona Community Trust who are delivering improved shore
side facilities at Ulva Ferry with the support of Regeneration Capital Grant Funding secured by
the Council. South Islay Development are delivering a new community hub and motorhome
facilities at Port Ellen with the support of the RCGF and Rural Tourism Infrastructure Fund, both
of which are administered by the Council. We are also working with Tiree Community
Development Trust who are developing new business units at Crossapol with the support of
13
Planning Performance Framework Report 2022/23

Page 15

RCGF; and RCGF funding was also secured during 2022/23 by Mull and Iona Community Trust
for phase 2 of the Nonhebal Business Park and Tobermory Harbour Association for development
of a water sports centre in Tobermory. The Council also supports, and works in partnership with
the area’s Business Improvement Districts. These operate in Oban, Dunoon and Isle of Bute,
delivering projects and events.  There were two re-ballots in the year 2022-2023, which resulted
in a third term for Oban and a second term for Dunoon. 
1.2.11 During 2022/23 consultation was undertaken in relation to proposed public realm
improvements at Gibralter Street, Oban with two events held in June and November 2022.
consultation took place both online and with face to face engagement and has had a significant
impact upon the final scheme which is to be delivered during 2023/24. The Ardrishaig Public
Realm project which was onsite during 2022/23 followed the example of other recent capital
projects by providing regular updates to both internal and external stakeholders throughout the
construction phase.  
1.2.12 The Development Management Service continues to offer a pre-application and
permitted development enquiry service. Previously we have reported on the introduction of
charging, template responses and online submissions to provide timely, consistent, high quality
advice to prospective developers through identification of relevant planning policies, constraints
and requirement for supporting information in advance of the formal application process. The
Planning section of the Council website includes useful customer information including advice on
‘Permitted Development’, relevant publications (including the LDP and non-statutory guidance),
information on the planning process and details of how interested parties can engage with it.
Customer feedback has however identified demand for a  pre-app initiation and follow up advice
service however plans to extend the range of services and undertake a full review and refresh of
website content has not been possible to date due to limited resource availability and a wider
corporate refresh of the website that has restricted the scope at Service level to amend online
content whilst this process was underway and it will now be taken forward in 2023/24.
Throughout 2022/23 details of disruption to the delivery of services and updated arrangements
for contacting the Planning Service have continued to be published and kept up to date on the
Council’s website.
1.2.13 Elected members remain involved  at an early stage of an application for ‘major’
development and are provided with a briefing on all Proposal of Application Notices (PANs). This
protocol requires all PANs to be reported to the PPSL Committee and allows Members the
opportunity to identify matters which they consider would be material to the determination of any
subsequent application. Any issues raised by Members are then fed back to the applicant to take
into account in the preparation of their formal application. Commencement of s23 of the Planning
(Scotland) Act 2019 has also introduced a new requirement to directly notify local, Scottish, and
UK elected representatives when an application for Major development is received. The Council
responded to this additional requirement through the introduction in 2019/20 of a new protocol
providing notification to the relevant parties by e-mail.
1.2.14 We have reported in previous PPFs on the certainty provided through development of
masterplans  and LDP allocations. Recent years have seen development, including affordable
housing, delivered within masterplan/LDP allocations in Bowmore, Campbeltown, Dunoon,
Helensburgh, Lochgilphead, Inveraray, Port Ellen, and Tobermory and we reported in PPF 7,
14
Planning Performance Framework Report 2022/23 Part 1 continued on P. 18

Page 16

Lochgilphead 
Front Green
Regeneration
Case Study 2 
In PPF 10 and PPF 11 we reported on the development and delivery of a £1.6 million pound
investment in the redevelopment of the Lochgilphead Front Green. This development was
completed during Summer 2022. The project forms one part of a wider portfolio of work which
has the aim of improving the environment and built heritage of Lochgilphead, other projects
include the Colcheeter Square/ Argyll Street Public Realm Works, various shop front
improvements and Lochgilphead CARS.
The project aim was to improve the
Lochgilphead Front Green, a key site located
within the Lochgilphead Conservation Area at
the heart of the town centre and particularly
prominent for those travelling through the town
between the central belt to/from Kintyre and the
Islands. The site was identified as an Area for
Action within the current Local Development
Plan and its predecessor. The longstanding
ambition and continued desire to see the site
enhanced was recorded through the ‘Rethink the
Link’ Charrette held in 2016 and previously
reported upon in PPF 5 and PPF 6.
15 
Themes A: Quality of
Outcomes
B: Quality of
Services & 
Engagement
C: Governance
D: Culture of
Continuous 
Improvement
Performance 
Markers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Key Areas of Work Regeneration, Greenspace, Town Centres, Community Engagement,
Placemaking, Design Workshops/Charrettes, Project Management
Stakeholders Argyll and Bute Council, Transport Scotland, Lochgilphead Community
Council, Lochgilphead Phoenix Project
Project Lead Anna Watkiss

Page 17

Further engagement was undertaken with three public consultation events held between March
and August 2019. These were well attended with hundreds of participants providing their views
on the project and advising of the aspects that they liked and disliked. The information collected
helped to shape the final project design which seeks to deliver the key elements which were
identified by the local community as most important to them.
The project is funded by Argyll and Bute Council’s Tarbert and Lochgilphead Regeneration Fund,
the Scottish Government’s Cycling, Walking and Safer Routes and Town Centre Funds, Hi Trans,
Lochgilphead Phoenix Project, and the Co-operative Local Community Fund.
Pre-app advice and planning
permission for the project was sought
and granted in 2019. The subsequent
procurement process was severely
impacted by the Covid-19 pandemic
and resultantly was unable to be
concluded until March 2021.
Construction works commenced in
May 2021 and completed in August
2022.
The project has delivered:
 A new public play park;
Planning Performance Framework Report 2022/23
16

Page 18

 A new public square where community events can take place. This is constructed from
the same local stone as the retained War Memorial and which has also recently been used
in public real improvements to the adjacent Colchester Square and reported on in PPF 10.
 Improved surface water drainage and added protection from flooding resulting from coastal
storm surges;
 Landscaping which retains the majority of the Front Green as an open grassed area;
 Retention of the existing avenue of Chestnut trees along Poltalloch Street, and replacement
of damaged trees with a more salt tolerant species, with additional tree and shrub planting
around the play area.
 Provision of new seating areas including a 200m long seating wall which performs the dual
function of raising ground levels to reduce the impact of frequent storm surge flood events;
 Provision of enhanced walking
and cycling facilities; and,
 Provision of new signage.
The project has contributed to the
wider goals and outcomes of the
Planning Service through supporting
the delivery of town centre
regeneration and place-making
projects which supports Argyll and
Bute to become a more attractive and
prosperous place to work, live, visit
and do business in. The project is
specifically linked to meeting the
aspirations set out for Area for Action
12/1 identified in the Argyll and Bute
Local Development Plan 2015.
The project has been well received and utilised by the local community and has demonstrated
the positive benefits of  delivering physical improvements to our built environment. The project
has subsequently received national recognition picking up the Streets and Spaces Award at the
Scotland Loves Local Awards in
November 2022, and more
recently has won a Gold Award
in the Public Realm and
Landscaping category at the
Scottish Design Awards 2023.
Planning Performance Framework Report 2022/23
17

Page 19

PPF 8 and PPF 9 that the Dunbeg masterplan area was the subject of a detailed application for
300 affordable dwelling units which is now on site. Case Study 1 provides an update on activity at
Dunbeg over the past 12 months where significant progress has been made toward delivery of
300 affordable houses with completion now anticipated during late 2023. In PPF 11 we reported
on a new masterplan for a designated Potential Development Area in Scalasaig, Colonsay to
support community led aspirations spearheaded by the Colonsay Community Development
Company in partnership with MOWI for social housing and economic development on the island
and are pleased to report that during 2022/23 there has been significant progress on the
implementation of housing development within this site with completion of phase 1 expected
during 2023/24. 2022/23 has also seen planning permission granted for the delivery of essential
infrastructure and enabling works within the Kilmory Business Park Masterplan Area in
Lochgilphead, and a planning application submitted for phase 4 of the Bowmore Masterplan Area
along with the initiation of pre-application discussions on future phases of that development.
1.3 GOVERNANCE
1.3.1  Development Management and Development Policy items are reported to the
centralised Planning, Protective Services and Licensing (PPSL) Committee which meets monthly
(except for July) and convenes for site visits and discretionary Local Hearings as required. The
PPSL Committee met on 11 occasions during 2022/23. Local Review Bodies operate flexibly to
demand with 15 LRB meetings convened during 2022/23 in relation to 7 LRB cases. PPSL
continued to operate in a virtual format during 2022/23 and continued to facilitate public access to
meetings; although discretionary hearings have been held both in person and as virtual meetings.
The Council has embraced the use of virtual meetings for committees and discretionary hearings,
and whilst some concerns have been raised about the prospect of digital exclusion, experience to
date would indicate that conducting Committee business online provides additional opportunities
for participation, particularly for populations located in remoter mainland, and island locations.
The Full Council decided in 2021/22 to augment this position with improved functionality, scope
for hybrid meeting formats, and functionality for live streaming/broadcasting of Council meetings
through recent approval of a roll out of MS Teams to replace Skype from August 2021. 
1.3.2  The Council’s Scheme of Delegation to officers was reviewed by Full Council and
updated in September 2022. The scheme of delegation continues to operate effectively with
98.2% of decisions being made under delegated powers in 2022/23. During this period 99.5% of
applications were approved demonstrating the effectiveness of a plan-led system, flexible/pro-
development policies which are aligned to the corporate priority of sustainable economic growth,
and a commitment to delivering positive outcomes.
1.3.3  Argyll and Bute Council continues to face significant budget pressures with an
estimated budget gap of more than £13 million in 2023/24 and more than £54.5 million for the
period 2023-2028. The Council has already made £70 million of recurring savings since 2010-11.
In previous PPFs we have outlined the significant contribution towards Council savings which
have been delivered by both the Development Management and Development Policy Services
over this period which has involved a downsizing of staff resource and the introduction of
charging for a number of non-statutory services including the handling of pre-application
enquiries and non-material amendments. The Covid pandemic also had a significant impact on
resourcing with a substantial downturn in fee income experienced during both 2020/21 and
2021/22 impacting significantly on the ability of Planning Service to respond to these challenging
circumstances. The reform of statutory planning fees from 1st April 2022 was therefore
18

Page 20

particularly welcome and has partially addressed the concerns previously raised by the Council
highlighting that the fees associated with local applications are insufficient to deliver a cost
neutral service (PPF 8 – Costing the Planning Service in Scotland). Planning fee reform has
delivered a marked increase in statutory fee income during 2022/23 but it remains evident that
there is still a reliance on fee income from a small number of high value major applications to
subsidise the wider delivery of the Council’s Planning Service. In this respect it is highlighted that
a more frequent review of statutory planning fees is necessary particularly in a climate where
costs are rising on a regular basis - in this respect it is disappointing that the recent reform of
planning fees did not make any provision for an annual increase in line with inflation. An
improving financial position during 2022/23 has however better placed the Planning Service to
review the availability of resources to address its current challenges which includes the
processing of a significant backlog of planning application casework and succession planning
with 2.5 additional fte posts being created during 2022/23 within the Development Management
Service and a further 3fte to follow during 2023/24 along with 1 additional fte within the
Development Policy Service demonstrating a commitment by the Council to reinvesting planning
fee income in the longer term resourcing of both Services and improvement of service delivery.
Budgets and efficiency measures continue to be considered at management meetings with
updates provided regularly to the Executive Director and elected Policy Lead. Participation in the
Costing the Planning Service in Scotland project, as detailed in PPF 8, has confirmed that the
cost efficiency of Argyll and Bute’s Planning Service compares favourably with that of other Local
Authorities and has provided additional insight to assist with budget planning for future years.
The outcomes of this project were reported to the Council’s PPSL Committee in June 2019.
1.3.4  During 2022/23 Planning Enforcement continued to be delivered by two dedicated
Enforcement Officers based in Lochgilphead and Oban covering the West of Argyll and Bute with
the undertaking of enforcement duties being combined with Development Management casework
in the East of the Council area. It has however been identified during the development of the DM
Service Transformation Action Plan that the provision of an additional dedicated enforcement
resource to cover the East of Argyll would improve enforcement performance and release
existing planning officer resource for other statutory casework. Funding has been agreed for this
additional post in 2022/23 although recruitment and appointment will be undertaken during
2023/24.  Enforcement is delivered on a priority basis which is set out in the Enforcement and
Monitoring Charter which was  reviewed, updated and approved in March 2022. The Council also
published an addendum to the Charter in November 2020  which remained in force until 30th
September 2022 clarifying the manner in which unauthorised development arising from a
necessary response / unavoidable impacts of the Covid-19 pandemic was to be addressed in the
planning enforcement process. The temporary relaxation of planning enforcement in relation to
town centre recovery from Covid-19 was adopted as a Position Statement in July 2020 under
emergency powers, these provisions were subsequently extended up until 30th September 2022
following involvement of elected members.
1.3.5  The Planning Service continue to engage with key partners to facilitate a number of
significant strategic development investments in and around Oban. These include Dunbeg,
SAMS and the European Marine Science Park, Saulmore Golf and Marina Development, and
Oban Airport Business Park. However there is a need to prioritise co-ordination and planning of
long term strategic growth in the Ona area through development and production of the Oban
Strategic Development Framework. Preliminary work has begun on the OSDF which will continue
throughout 2023 in order to allow wider engagement in 2024.
19
Planning Performance Framework Report 2022/23

Page 21

1.3.6  Changes to the Council’s corporate structure in 2019 included the functions provided
by Planning and Regulatory Services, and the Economic Development Service being brought
under a single Head of Service which is now titled Development & Economic Growth. Whilst the
corporate restructure was primarily intended to deliver budget savings the new service structure
provides closer alignment and co-ordination of the Council’s regulatory functions, including
Development Management, with the Council’s plan making, business support, and project
delivery activities. Increasing reliance on virtual working has had the benefit of providing
improved opportunities for collaboration and partnership working across Council services with
virtual project teams capable of being readily assembled without the need for extensive travel
and time demands. Examples of this approach include Rural Growth Deal Working Groups, the
Council’s Climate Change Board, and the Care Homes and Housing Programme Board which
bring together stakeholders from across a number of Council Services and other key external
agencies.
1.3.7  The Planning Service continues to engage with other Council Services through Area
Property Action Groups (APAGs). This award winning approach and some of its successful, high
quality outcomes have been highlighted within previous PPFs, and examples of this innovative,
inter-disciplinary approach to problem solving have been highlighted in PPF 8 and PPF 11.
1.3.8  The Council continues to explore the delivery of shared services with other authorities.
During 2022/23 the Planning Service has continued to share service delivery of Conservation and
Design advice to Loch Lomond and the Trossachs National Park Authority, and has also
delivered a small amount of charged Biodiversity consultancy.  Collaboration with neighbouring
authorities also remains ongoing and during 2022/23 this has included case officer discussion
with the LLTNP on the administration of cross-boundary applications.
1.3.9  The Development Management Service continues to seek to review and refine existing
processes to deliver efficiency savings and improve performance and outcomes for customers.
During 2018/19 the Development Management Service invested and delivered an upgrade of
Public Access improving stability of this customer engagement tool and allowing greater scope to
improve the customer experience. The Service also invested in the purchase of IDOX Enterprise
for Uniform during 2018/19 and undertook initial development work during 2019/20 however the
development and roll out of Enterprise, which will implement improved workflow processes and
performance management, was postponed during 2020/21 due resource implications arising from
the Covid-19 pandemic. During 2021/22 a wider project involving Building Standards and
Regulatory Services and led by ICT has been implemented to replace the existing Document
Management System (DMS) to deliver improved functionality for both officers, stakeholders and
the public; Planning and Regulatory Services have engaged with the Council’s ICT Service to
implement a project managed approach to development, implementation and roll out across three
Council Services which was originally programmed for completion in 2022/23 but is now delayed
into 2023/24 due to technical issues with the transfer of data into the new systems that requires
to be resolved between the software providers. Initial implementation of Enterprise remains
scheduled to run alongside completion of the DMS project and will also now take place during
2023/24. As previously reported in PPF 10, the Covid-19 pandemic enforced a requirement to
adapt to restrictions on travel and social distancing which expedited the adoption of online
working practices, including online validation and e-decision notices, which will be retained in the
long term. 
Planning Performance Framework Report 2022/23
20

Page 22

1.3.10 All professional staff within Planning Services are provided with laptops to facilitate
their ability to travel efficiently and work flexibly across the Council area. The Development
Management Service invested in tablets which were deployed during 2020/21 to allow use of e-
documents as a replacement for hard copy planning application documentation used for
examination of plans outwith the office environment, and recording site visit activity. The
Council’s longer term investment in ICT that supports flexible working arrangements was crucial
to our reaction to the Covid-19 pandemic and allowed the majority of Planning Services staff to
seamlessly move to home working. Services providing frontline contact services now continue to
provide a primarily virtual service although face to face engagement has resumed where
required. In some instances this has involved the delivery of new solutions such as the utilisation
of Health Service Near Me portal by the Council’s Housing Service to deliver virtual face to face
interviews with clients, and the further dissemination of smart phones.
1.3.11 Customer appetite for Processing Agreements remains indifferent. The Development
Management Service did not determine any applications with a Processing Agreement during
2022/23 despite engaging with all applicants for Major development. Information on the
availability of Processing Agreements is available on the Council’s website, is highlighted in all
pre-application reports, and has previously been promoted in User Forums.
1.3.12 Argyll and Bute Council has a corporate complaints process; customer information is
provided on the Council website and in customer Charters. All complaints are subject to
performance reporting and ‘Stage 2’ complaints require review by senior management with the
option to seek further review by the Scottish Public Services Ombudsman (SPSO) where
customers are not satisfied with the outcome.
1.3.13 Legacy cases (applications which have been valid for more than 12 months) are
reviewed regularly as part of caseload management however the resource required to undertake
this proactive review has remained diminished during 2022/23 due to reduced staffing capacity.
Ordinarily, caseload reviews on longstanding applications is undertaken weekly/biweekly at team
level and monthly with involvement of a senior manager. During 2022/23, only 18 legacy
applications were concluded representing an downturn on the previous period. The continuing
legacy of the Covid-19 pandemic upon workflow, the continuing difficulty in recruiting to vacant
posts and interruption of workflow caused by the introduction of NPF4 has all impacted on the
capacity of the Development Management Service to determine planning applications during
2022/23 and has resulted in 60 additional legacy cases (125 legacy cases in total) accruing as of
31st March 2023. Ordinarily legacy cases are subject to regular review by the DM Management
team and targeted for conclusion; however during both 2021/22 and 2022/23 a long term
vacancy at Team Leader level and the impact that this has had on the wider DM Management
team has precluded this as a regular activity. Gaps in the management team were eventually
resolved in February 2023 closing off a 16 month period where the DM Management Team have
operated short-handed. The return to a fully staffed DM management team is expected to result
in a marked improvement in the handling of legacy applications during 2023/24.
1.3.14 Applications which are to be subject to planning legal agreements are flagged up on
lists of undetermined applications to ensure that the progress can be reviewed on a regular basis,
as noted in 1.3.13 above, a requirement to operate with long-term vacancies has reduced
resources and availability of staff to undertake this activity. The average  time period for
processing applications with legal agreements increased from 33.6 weeks to 49.9 weeks during
2022/23.
21
Part 1 continued on P. 27

Page 23

22
Argyll and Bute Design
Awards 2022/23 Case Study 3
Themes A: Quality of
Outcomes
B: Quality of
Services & 
Engagement
C: Governance
D: Culture of
Continuous 
Improvement
Performance 
Markers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Key Areas of Work Design, Conservation
Stakeholders Elected Members, General Public, Local Developers, Architects/Agents
Project Lead Kim de Buiteleir
The Argyll and Bute Design Awards 2022/23 were re-launched in September 2022 after being delayed by
the Covid pandemic. This is the fourth iteration of an award scheme and covered projects completed
between 2015 and 2022. The Awards promote the importance of design and sustainability and provide
recognition to those who have managed to deliver high quality development within Argyll and Bute. The
launch of the Awards was accompanied by a press release and creation of a webpage for submission of
entries.
Almost 60 nominations were received across the six main categories which were judged by a panel
comprised of both planning professionals and elected members who decided on the shortlist for each
category and visited each property prior to their final deliberations. The shortlisted entries were also
subject to separate votes in the Members Award and Public Award categories which were new additions
this year which were intended to secure more direct public and elected member interest in the Awards. 
The  panel were impressed with the extremely high standard of
entries and noted that a number of the projects have recently won
or been shortlisted for other awards including the RIAS Awards;
Heritage Angel Awards, and the National Planning Awards.
The Design Award Ceremony was held in the Helensburgh Civic
Centre. This was hosted by the Council’s Chief Executive Officer,
Pippa Milne and the Head of Development and Economic Growth
Fergus Murray, in addition to the elected members and
professional officers of the judging panel. Following the success
and positive feedback on this year’s award ceremony it is
intended that the Design Awards will  become a biannual fixture. 
The Design Award Categories 2022/23:
 Sustainable Design
 Aesthetic Design (Large Scale)
 Aesthetic Design (Small Scale)
 Community Led Regeneration
 Built Heritage
 Design for Under £100,000
 Member’s Award
 Public Award
Design Award Winners at the Award Ceremony

Page 24

Planning Performance Framework Report 2022/23
23

Page 25

Planning Performance Framework Report 2022/23
24

Page 26

25
Planning Performance Framework Report 2022/23

Page 27

Planning Performance Framework Report 2022/23
26

Page 28

1.3.15 An audit of the Council’s system of internal control and governance in relation to planning
applications within Council’s internal audit plan for 2021/22. The internal audit was undertaken
during 2022/23 and reviewed the planning application handling process to assess compliance
with both statutory requirements and Council Policy. This included consideration of risks relating
to the Council’s ability to deliver core services as a result of the Covid pandemic, failure to meet
statutory requirements, and performance monitoring. The internal audit confirmed that the
Development Management Service was compliant in respect of these factors but highlight a
requirement to update detailed procedure notes to reflect revised ways of working that had been
introduced; this documentation will be updated alongside the introduction of new Enterprise
workflow and a DMS during 2023/24 - see also 1.4.12.
1.4 CULTURE OF CONTINUOUS IMPROVEMENT
1.4.1  During 2022/23 the Planning Service delivered and progressed on a range of
Improvement Actions identified in PPF 11. An overview of progress is set out in Part 3 of this
document.
1.4.2  The Council continues to benchmark its performance on the determination of planning
applications against the National average and the performance of other rural local authorities. 
1.4.3  Internally, team meetings are held on a regular basis. The Executive Director attends
fortnightly Executive Leadership Team meetings. The Head of Development & Economic Growth
attends the fortnightly Departmental Management Team meeting and monthly meetings of the
Executive Leadership Team, provides a regular update to Policy Leads, and holds their own
Service meetings on a regular basis. Service level management teams also meet regularly/
quarterly; within Development Management area teams also meet weekly to assign casework,
and review caseload performance.
1.4.4  In January 2022 the Council replaced a corporate requirement for all staff to prepare
an annual Performance Review and Development plan (PRD). The new approach seeks to
recognise that an annual PRD meeting was not always the best way to approach performance
and career conversations and instead now recognises that conversations about objectives,
behaviours, skills and development form part of an ongoing regular dialogue between employees
and line managers although this will be supported by corporate activity monitoring outcomes in
an annual survey of employers and managers.
1.4.5  Since 2014, the Planning Service has delivered a series of short training events for
elected Members which are intended to improve their breadth of knowledge and competence in
the  undertaking of planning decisions. These are normally undertaken in bite size sessions in the
hour prior to a meeting of the PPSL Committee but have also previously included half day
workshops and site visits. Training has previously included Competent Motions, Aquaculture
Development, Landscape Character Assessment, Low Carbon Technology, Food Growing
Strategy, and an update on new legislation. In house planning training covering Development
Planning, Development Management and Planning Enforcement was provided for all elected
members  following the Local Government Elections in May 2022. In addition to this, the member
training programme for 2022/23 included a detailed session on processing planning applications,
a session provided by SEPA on managing flood risk, new regulations on the production of Local
Development Plans, and National Planning Framework 4.
27
Planning Performance Framework Report 2022/23

Page 29

Planning Performance Framework Report 2022/23
1.4.6  The Annual Planning Conference was held in March 2023 both at Helensburgh Civic
Centre and online as a hybrid event for a second time. In comparison to the previous years
conference, this year prompted a return to a large proportion of staff attending in person and was
as a valuable opportunity to meet face to face, particularly for new members of staff. The
conference was open to professional staff across the Council who engage in or with the planning
process; the conference is promoted as a CPD event to staff in addition to an opportunity to
recognise and promote collaborative working not only across the Council but also with other key
stakeholders. With NPF4 having come into effect on a few weeks earlier and the Examination
Report for PLDP2 anticipated, the changing policy landscape provided the main focus for the
conference. The conference included presentations and workshop sessions focussing on
Biodiversity, Huts and Soils. Officers were also provided with a presentation on the short listed
entries for the Argyll and Bute Design Awards. 
1.4.7  Planning Services representatives regularly attend meetings of Heads of Planning
Scotland (inc. DM and DP subgroups), Scottish Planning Enforcement Forum, the Local Authority
Aquaculture Forum, Clyde Marine Planning Partnership, West of Scotland Archaeology Service,
and the e-Development/Digital Taskforce. During 2022/23 the Development Management Service
has continued to have regular meetings with Highland’s and Islands Enterprise, SEPA, Scottish
and Southern Electricity Networks, and Forestry Scotland to discuss upcoming projects/
casework, and to identify and prioritise resource for submission and determination of
applications. Whilst it is recognised that there is a downside to the removal of face to face contact
there is a significant time and cost saving for authorities like Argyll and Bute through removal/
reduction in the significant travel requirements. 
1.4.8  In addition to benchmarking performance, the Planning Service also seeks to engage
directly with other local authorities to share best practice and develop new ways of working.
Previously officers visited Dumfries and Galloway Council, and Glasgow City Council to learn
from their experience in the development and roll out of bespoke IDOX Enterprise workflow
systems; and more recently have engaged more widely with other rural local authorities on
reviewing and updating procedures for handling Prior Notification/Prior Approval submissions,
have provided advice to North Ayrshire Council and Loch Lomond and the Trossachs National
Park to assist with their handling of aquaculture submissions/cross boundary applications.
1.4.9  Work to review and improve the rate of applications which are valid upon receipt has
remained on hold due a lack of staff resource to progress this workstream although it is noted
that issues relating to the resourcing and performance of the Central Validation Team (as
reported in PPF 11) have been successfully resolved during 2022/23 with 1 additional fte
recruited, and commitment of additional resource to fund overtime to deliver a return to
undertaking a first check within 5 working days of receipt. The Development Management
Service previously hosted a visit from Loch Lomond and the Trossachs National Park Authority in
2019/20 to compare arrangements, experience, and resources for the validation of planning
applications. During 2020/21, the closure of Council offices required the rapid development and
implementation of new process to facilitate home working in the validation process; limited office
presence continues to be maintained to manage incoming/outgoing hardcopy mail (including
issue of neighbour notifications), and for the conversion of hardcopy submissions into electronic
workflow upon receipt. 2022/23 has however seen an improvement in the percentage of
applications valid upon receipt which are up from 18% (in 2021/22) to 30.6%. 
28

Page 30

Planning Performance Framework Report 2022/23
1.4.10 The Planning Service have engaged with/contributed to Scottish Government
consultations, in particular during 2022/23 to the consultation on Local Development Plan
Evidence Report—Defining Gypsies and Travellers; in recent times input has also been provided
on Local Place Plan Regulations, Short Term Lets, Onshore Wind Policy Statement,  Local
Development Planning Regulations and Guidance, Open Space Strategies, Draft Heat Networks
Delivery Plan, Marine Litter Strategy, A New Deal for Tenants and NPF4. We have also engaged
with the Independent review of the Current Regulatory Framework for Aquaculture  with
consultations by other National agencies including SEPA’s Proposals for a Risk-Based
Framework for Managing Interaction Between Sea-Lice and Wild Atlantic Salmon, and with the
Improvement Service on 20 Minute Neighbourhoods in Rural and Island Areas.
1.4.11 Aquaculture is an area of planning that relatively few authorities have expertise in.
Argyll and Bute is one of five Scottish Local Authorities that deal with the majority of fin fish
planning applications. The aquaculture industry is currently seeking to expand into new locations
across Scotland to meet national growth targets. In PPF 8 we reported that we had provided
assistance to colleagues in North Ayrshire Council and Loch Lomond and the Trossachs National
Park following receipt of EIA Screening and Scoping requests for aquaculture development within
their respective areas and informal support has continued to be provided during 2021/22 as these
projects progressed to formal applications. In 22019/20 Argyll and Bute took up the role of Chair
within Local Authority Aquaculture-working group, an online event was held in 2021 however a
resumption of the group as a physical meeting with site visit learning opportunities was
undertaken in September 2022, see Case Study 4 for details. Officers also continue to participate
in the Fish Welfare Multiagency group which is hosted by the Department for Environment Food
& Rural Affairs (DEFRA) and includes Marine Scotland, SEPA, and Local Authority
representatives from both a planning and animal welfare perspective. 
1.4.12 We reported in PPF 8 and PPF 9 of investment in updated software/systems to deliver
a more resilient Public Access service resulting in the availability of the Public Access system
rising to 99.9% for the second half of 2018/19. Whilst issues with the day to day resilience of this
service have been addressed there is now a focus on delivering improvements to the usability of
the Public Access System. It has been identified that delivery of the desired improvements are
very much dependent on providing improved compatibility with back office Document
Management Systems (DMS) and accordingly work has been progressed with IT, Building
Standards and Regulatory Services a project was planned and initiated during 2021/22 to move
to the IDOX DMS that will enable improvements to Public Access but also to the functionality of
other existing back office workflow systems across a range of Council services. The project has
been delayed by matters outwith the Council’s control and has been rescheduled for completion
in 2023/24.
1.4.13 Internal processes for handling pre-applications and the management of e-mail
correspondence and file attachments were subject to review and updating throughout 2019/20
having regard to the implications of GDPR with updated data retention policies, procedure notes
for staff and training sessions delivered, and deletion of data/documents that no longer required
be held from systems was undertaken during 2020/21. Enforced homeworking arrangements
implemented in response to Covid-19 restrictions have resulted in new workflow processes that
remove/minimise the requirement for hardcopy process in mail handling, issuing of decision
being expedited in their development in order to allow the planning process to continue operating
29

Page 31

during ’lockdown’, a lack of staff resource has however to date precluded the further development
of a number of temporary processes put in place. The requirement to update detailed procedure
notes to reflect new ways of working was highlighted as an improvement action from the internal
audit (see para 1.3.14) undertaken during 2022/23 and the production of a new user manual has
been identified as a requirement to accompany the implementation of new back office systems
(see. 1.4.12). 
1.4.14 The online and mobile capabilities of the Council’s Geographic Information Systems
(GIS) continue to be developed saving officer time and providing customers with quicker access
to information. In PPF 9 we reported that the GIS team developed the ‘story map’ for the
proposed LDP 2 public consultation, and enhanced the photographic data layer in the online map
based footpath guide to include key view points from an increasing number of paths. The GIS
team also played a valuable role in the Council’s response planning to the Covid-19 pandemic
and have assisted with a great many of the planning and logistical challenges that have arisen.
During 2021/22 the team have continued work to enhance the Strategic Housing Investment Plan
(SHIP) with enhanced GIS functionality which is now being used to facilitate easier and earlier
identification of impediments to development within the SHIP programme. The GIS team has
developed a GIS based Storymap which allows spatial analysis of all RSL stock, new builds,
ongoing and future development sites.  This is an invaluable input to updating and planning the
annual SHIP.  As this is further developed it will also be launched online.  Going forwards the
service is seeking to replicate this for all housing tenures in order to further inform our
understanding and analysis of the housing market within Argyll and Bute.
1.4.15 Engagement with Forestry Scotland was initiated during 2020/21 on a review of the
effectiveness of consultation with the Council on proposals for new plantations, forest accesses,
and long term forest plans. This workstream has however been put on hold during 2021/22 due
to a lack of resources although liaison meetings with Forestry on other matters has continued
Once completed it is expected to deliver a streamlined consultation process with improved quality
of consultation response that is tailored to meet the requirements of Forestry Scotland officers in
their assessment of planning proposals. The publication of technical note on Upland Hill Tracks
has been progressed and was intended to be completed for publication concurrently with
completion of this workstream but has been placed on hold indefinitely following announcement
by the Scottish Government in November 2019 that related ’permitted development rights’ would
be subject to an upcoming review. 
1.4.16 The Planning Service has engaged with consultation on both planning controls and
licencing for short-term letting, and form part of the Council’s working group involving Legal,
Regulatory Services, Housing and external stakeholders which will initially seek to implement a
licencing scheme from 1st October 2022 and then consider the requirement for planning control
areas in the medium to longer-term. In the short term it has been identified that, in the absence of
national guidance, local advice requires to be provided by the Council for both officers and the
public on planning requirements for short-term lets outwith control areas. During 2022/23, internal
guidance has been prepared to assist in the provision of planning responses to STL Licence
consultations. Further guidance is also being prepared to respond to the updated policy position
set out in NPF4 and will be published in 2023/24.
30

Page 32

Local Authority Officers
Aquaculture Working
Group
Case Study 6
31
Themes A: Quality of
Outcomes
B: Quality of
Services & 
Engagement
C: Governance
D: Culture of
Continuous 
Improvement
Performance 
Markers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Key Areas of Work Interdisciplinary Working, Collaborative Working, Staff Training, Skills
Sharing
Stakeholders Argyll and Bute Council, Scottish Local Authorities, Scottish Government,
Marine Scotland, Crown Estate
Project Lead Sandra Davies / Peter Bain
The Council’s Planning Service continues to invest significant officer time and effort into
supporting the sustainable growth of marine finfish and shellfish aquaculture across Argyll and
Bute.
Officers from both the Development Management and
Development Policy Services are members of the Local
Authority Officers Aquaculture Working Group which also
includes officers from Highland, Orkney, Shetland and the
Western Isles. The working group was originally
established in response to legislative change that brought
marine aquaculture activity under direct planning control
with a view to sharing good practice and ensuring a
consistency of approach and delivery of planning
services. The group has since established itself as a body
of expertise which has not only informed the reform of
planning legislation in relation to planning requirements for aquaculture development but has
also provided a local authority representation to a number of the various steering groups and
parliamentary committees which have and continue to discuss the salmon farming industry.
Prior to the Covid pandemic, the Local Authority Officer group held an annual meeting which
included site visits to operational aquaculture facilities providing opportunities for CPD and
sharing of good practice. Argyll and Bute Council took over the chair of the Local Authority
Officers group in 2019/20 and an online meeting was held in 2021. The annual meeting was
reinstated as a face to face event with a two day conference held in Oban in September 2022
and funded by a grant from the Scottish Government. The event was attended by seventeen
delegates with representatives from all five of the Local Authorities with a significant interest in
aquaculture along with representatives from the Scottish Government, Marine Scotland, and the
Crown Estate.
The agenda included discussion on application of the revised planning fee regime to shellfish
and prospect for future amendment, procedural issues raised by recent casework, a discussion
on the issue of potential health implications from the release of fish farm medications upon wild
swimmers, the handling of planning enforcement for aquaculture, interim measures and
emerging new provisions in relation to the management of sea lice including a presentation from
SEPA on the emerging Sea Lice Framework, and ongoing matters relating to regulatory review.
The conference concluded with an opportunity for delegates to tour Scottish Sea Farms onshore
hatchery at Barcaldine.
Scottish Sea Farms Hatchery Visit
Planning Performance Framework Report 2022/23

Page 33

Supporting Evidence &
Performance Markers Part 2:
Wherever possible weblinks have been provided
within the body text of the report.
This report was compiled drawing on evidence from
a variety of sources including:
 Argyll and Bute Outcome Improvement Plan 2013-
2023 
 Argyll and Bute - Economic Development Action
Plan 2016 - 2021
 Argyll and Bute—Renewable Energy Action Plan
 Argyll and Bute Local Development Plan 2015 
 Argyll and Bute Local Development Plan 2
Development Plan Scheme March 2022
 Argyll and Bute - Main Issues Report 2017 
 Argyll and Bute Council Website
 Argyll and Bute Council Monitoring and Enforce-
ment Charter March 2022 & Covid-19 Addendum
 Argyll and Bute Council Planning Performance
Framework Online Publication/Archive
 Argyll and Bute Council, PPSL Committee Minutes
 Argyll and Bute Council Scheme of Administration
and Delegation 
 Argyll and Bute Council, Development & Economic
Growth Service Plan 2020-23
 Argyll and Bute Housing Land Audit 2021 
 A range of committee reports
 Customer feedback
 Reports from IDOX Uniform
 Scottish Government Statistical Returns 
32
Case Study Topics
Issue
cov-
ered by
Case
Study
No.
Case Study Topics
Issue
cov-
ered by
Case
Study
No.
Case Study Topics
Issue
cov-
ered by
Case
Study
No.
Design 1, 3 Affordable Housing  Performance Monitoring 
Climate Change  Economic Develop-
ment 
Process Improvement 
Conservation  Enforcement  Project Management 2
Biodiversity  Development Manage-
ment Processes 
Skills Sharing 4
Regeneration 2 Planning Applications  Staff Training 4
Environment  Interdisciplinary Work-
ing
4 Online Systems 
Greenspace 2 Collaborative Working 1, 4 Data & Information 
Town Centres 2 Community Engage-
ment
1, 2 Digital Pracice 
Masterplanning 1 Placemaking 1 Transport 
LDP & Supplementary
Guidance 
Design Workshops/
Charrettes
2 Other 
Housing Supply  Place Standard

Page 34

33
PERFORMANCE MARKERS REPORT 2022/23 
PERFORMANCE MARKER EVIDENCE / COMMENTS
1. Decision-making: Authorities
demonstrating continuous evidence of
reducing average timescales for all
development types.
Part 4—Table B & Part 5—Table A.
Contextual commentary setting out factors affecting  performance on
decision-making are set out under Part 5 C and also within Case
Study 5.
2. Project management: Offer of
processing agreements (or other
agreed project plan) made to
prospective applicants in all major
applications and availability publicised
on planning authority website.
Part 1—1.3.11
Processing Agreements for major and ‘locally significant’
developments are promoted through pre-application discussion, user
forums and online. 
Argyll and Bute Council - Processing Agreements 
3. Early Collaboration with applicants
and consultees on planning
applications:
 Availability and promotion of pre-
application discussion for all
prospective applications.
 Clear and proportionate
requests for supporting
information.
Part 1—1.2.12 Case Studies 1 & 2 & Part 4 - Table B
The Development Management Service provides a pre-application
advice service. This is promoted on the Council website, through
user forums, and by officers  when  engaged by prospective
applicants. 
Pre-application assessment of proposals  seeks to identify  all
relevant issues which will be material to the determination of a
subsequent application, and will involve engagement with consultees
where appropriate. The  report template issued to applicants was
revised during 17/18 to include a dedicated section identifying the
requirement for supporting information  - this list is populated
following a review of relevant planning constraints and the advice of
consultees (including other Council Services) to ensure that any
request for further information is  specific and proportionate to the 
development proposed. Where applicants do not engage at pre-
application stage a similar approach is undertaken to identify issues
and any requirement for further information at an early stage in the
handling of the application.
Applications are validated against the National Validation Standard
published by HoPS to ensure that submissions and requirements for
supporting information are quality checked on a consistent basis.
This  document is also promoted and published on the Council
website to assist applicants in the preparation of their application.
During 2021/22 updated guidance on the submission and processing
of applications under S64 of the Act was prepared and published.
4. Legal agreements: Conclude (or
reconsider) applications within 6
months of ‘resolving to grant’.
Part 1—1.3.13 & Part 5—Table A
Applications subject to legal agreements were determined with an
average time period of 49.9 weeks during 2022/23. Applications
requiring a legal agreement are reviewed regularly and are
highlighted on officers outstanding items case lists.
Planning Performance Framework Report 2022/23

Page 35

34 
PERFORMANCE MARKER EVIDENCE / COMMENTS
5. Enforcement charter: updated /
republished.
Part 1—1.3.4 Part 4—Table C, Case Study 5
The Planning Enforcement and Monitoring Charter was reviewed and
updated in March 2022. In 2020/21 the Charter was augmented by a
Position Statement on the temporary relaxation of planning control
within town centres, and an addendum to the Charter covering more
general Covid-19 related issues both of which remained in place until
30th September 2022.
6. Continuous improvement: 
 Show progress/improvement in
relation to PPF National
Headline Indicators;
 Progress ambitious and
relevant service improvement
commitments identified through
PPF report. 
Part 4—Tables A, B, C & Context D, Case Study 5. The legacy impact
of the Covid-19 pandemic on workflow and a lack of availability of
planning professionals has continued to have a significant adverse
effect upon performance of decision-making timescales during
2021/22.
Part 3 details previous and committed Service Improvements.
Contextual commentary on delivery/identification of improvements is
included within:
Part 1—1.1.4, 1.1.6 1.2.2, 1.2.4, 1.2.6, 1.2.12, 1.3.3, 1.3.4, 1.3.9,
1.3.10, 1.3.13, 1.3.14, 1.4.2, 1.4.3, 1.4.8, 1.4.9, 1.4.12, 1.4.13, 1.4.15,
1.4.16, Case Studies 2 & 3, and Part 5 Table A
7. Local Development Plan: Less than
5 years from adoption.
The Local Development Plan was adopted in 2015.
Argyll and Bute Local Development Plan 2015 
8. Development plan scheme:
Demonstrates next LDP
 On course for adoption within 5
year cycle.
 Project planned and expected
to be delivered to planned
timescale.
LDP2 is project planned with careful management and reporting of any
adjustments, at 31.03.2023 LDP 2 was at Examination stage and is
currently scheduled for adoption in 2023 - see Part 1 - 1.2.2
Argyll and Bute Local Development Plan Scheme March 2022
It is further noted that the DPEA published the Examination Report for
LDP2 on 9th June 2023.
9. Elected members engaged early
(pre– MIR) in development plan
preparation: if plan has been at pre
-MIR stage during reporting year.
N/a
10. Measure no longer required -
numbering maintained for data
continuity
N/a
Planning Performance Framework Report 2022/23

Page 36

35 
PERFORMANCE MARKER EVIDENCE / COMMENTS
11. Production of regular and
proportionate policy, advice, for
example through supplementary
guidance, on information required
to support applications.
The Make a Planning Application section of the Council website
provides applicants with information that they need to consider before
making an application, this includes updated planning fee guidance.
Argyll and Bute - Planning Application Info
The Central Validation Team contributed to the development of and
have subsequently adopted the National Validation Standard
published by HoPS in 2017. Officers have participated in HoPS
ongoing review of this document during 2020/21. Part 1 - 1.4.9
HoPS National Validation Standard
Supplementary non-statutory planning guidance is reviewed and
updated regularly. Current publications include Houses in Multiple
Occupation, and Advertisements, Masterplanning, and Biodiversity.
During 2021/22 the Council has published updated guidance on S64
submissions and Local Place Plans.
12. Corporate working across services
to improve outputs and services for
customer benefit (for example:
protocols; joined up services; single
contact; joint pre-application
advice.)
Part 1 - 1.1.6, 1.2.1, 1.2.3, 1.2.4, 1.2.5, 1.2.6, 1.2.8, 1.2.9, 1.2.10,
1.2.11, 1.2.12, 1.2.13, 1.2.14, 1.2.15, 1.3.1, 1.3.4, 1.3.5, 1.3.6, 1.3.7,
1.3.12, 1.4.3, 1.4.5, 1.4.6, 1.4.12, 1.4.13, 1.4.15, 1.4.16, 1.4.18 &
Case Studies 1, 2, 4
13. Sharing good practice, skills and
knowledge between authorities.
Part 1 - 1.1.3 1.1.4, 1.1.6, 1.2.7,. 1.2.15, 1.3.8, 1.4.2, 1.4.6, 1.4.7,
1.4.8,  1.4.9, 1.4.10, 1.4.12, 1.4.17, 1.4.18 & Case Study 4
14. Stalled sites / legacy cases:
Conclusion / withdrawal of planning
applications more than one year old.
Part 1 - 1.3.13, 1.3.14, Part 3, Part 4 - Table B, & Part 5 C
During 2022/23 18 legacy cases were cleared. At  31st March 2022
there were  125 ‘live’ legacy applications undetermined. The
declining performance on this measure has been identified as a
specific area for improvement in 2023/24
15. Developer contributions: Clear
expectations set out in development
plan and in pre-application
discussions.
The adopted Local Development Plan sets out  expectations in
respect of Developer Contributions for affordable housing and green /
play space and is supported by Supplementary Guidance which sets
out that the Council will seek appropriate elements of planning gain
proportionate to the scale, nature, impact and planning purposes
associated with the development.
Where Developer Contributions are required these will be flagged up
at pre-application stage where applicable, or where no pre-
application engagement is sought then officers will seek to make the
developer aware of the requirement and justification for any
developer contribution as soon as such a requirement is identified in
the assessment process. 
The Council has reviewed its approach to Developer Contributions
and has set out a specific policy approach to this issue within PLDP 2
(proposed Policy 48) Where appropriate the Council shall seek
appropriate developer contributions in liaison with participating
partners and developers which are proportionate to the nature,
impact and planning purposes associated with the development, and
shall be in accord with the Policy Tests set out in Circular 3/2012.
Planning Performance Framework Report 2022/23

Page 37

36
Service Improvements Part 3:
UPDATE ON DELIVERY ON SERVICE IMPROVEMENTS ACTIONS FOR 2022/23
SERVICE IMPROVEMENT STATUS / EVIDENCE
1. Retain Customer Service Excellence Award On Hold - Revised action for 2023/24 see Part 1 -
1.2.4
2. Deliver LDP 2
Progressing - Adoption planned late 2023 - see
Part 1 - 1.2.2, Part 2 - KPI Table (8),Part 4 - Table A
& C
3. Run Sustainable Design Awards Completed- see Part 1 - 1.1.4 and Case Study 3
4. Production of Short Term Letting Planning Guidance  Progressing - see Part 1 - 1.4.16
5. Production of Hill Tracks Guidance (subject to Scottish
Government review of ‘PDR’)
On Hold - Awaiting outcome of Scottish
Government review of ‘Permitted Development
Rights’ - see Part 1 - 1.4.15
6. Implement improved workflow and performance
management systems within the Development
Management Service (project initiated 2021/22 to replace
existing systems with IDOX Enterprise and DMS)
Progressing - Part 1 - 1.3.9, 1.3.10, 1.3.13, 1.3.14,
1.4.2, 1.4.3, 1.4.8, 1.4.9, 1.4.12, 1.4.13
7. Review of Validation Processes (on-going engagement
with regular customers and review/promotion of HoPS
National Validation Standards to improve proportion of
applications valid upon receipt)
On Hold - see Part 1 - 1.4.9
8. Deliver Dunoon CARS (Conservation Area
Regeneration Scheme) project (ongoing - 90% delivery
complete)
Progressing - see Part 1 - 1.1.6
9. Deliver Rothesay TH (Townscape Heritage) project 
(ongoing - completion due 2022/23) Progressing - see Part 1 - 1.1.6
10. Deliver Ardrishaig Public Realm Works (programmed
to commence 2022/23) Progressing - see Part 1 - 1.1.6
11. Deliver Lochilphead CARS (Conservation Area
Regeneration Scheme) (project ongoing - 15% complete) Progressing - see Part 1 - 1.1.6
12. Deliver Lochilphead Front Green Public Realm Works
(project ongoing—due completion in 2022/23) Completed- see Part 1 - 1.1.6 and Case Study 2
Planning Performance Framework Report 2022/23

Page 38

COMMITTED SERVICE IMPROVEMENTS TO BE DELIVERED IN 2023/24 37
Planning Performance Framework Report 2022/23
SERVICE IMPROVEMENT STATUS / BACKGROUND
1. Delivery of LDP 2 to Adoption
Ongoing - see  Part 1 - 1.2.2, Part 5 C, and Argyll
and Bute Local Development Plan Scheme March
2022 
2. Production and Publication  of Short Term Letting
Planning Guidance 
Ongoing re-scheduled for completion in 2023/24 -
see Part 1 - 1.4.16
3. Production of Hill Tracks Guidance 
On Hold during 2022/23 to be progressed subject
to Scottish Government delivery of review of ‘PDR’ -
see Part 1 - 1.4.15
4. Implement Improved Workflow and Performance
Management Systems within the Development
Management Service (replace existing systems with IDOX
Enterprise and DMS)
Ongoing project initiated 2021/22 see Part 1 -
1.3.9, 1.3.10, 1.3.13, 1.3.14, 1.4.2, 1.4.3, 1.4.8,
1.4.9, 1.4.12, 1.4.13)
5. Review of Validation Processes (engagement with
regular customers and review/promotion of HoPS National
Validation Standards to improve proportion of applications
valid upon receipt) 
On Hold during 2022/23 see Part 1 - 1.4.9
6. Performance Improvement for Development
Management (demonstrate improving trends in
determination time periods, reducing volume of case work
backlog and legacy cases during 2023/24)
New Action forming part of wider
Transformational Action Plan for Development
Management see Part 1 - 1.3.3, 1.3.13, 1.3.14, and
Part 5 A and C
7. Undertake a Review and Implement a Refresh of the Pre
-application Enquiry Service 
New Action forming part of wider
Transformational Action Plan for Development
Management see Part 1 - 1.1.12
8. Review and Implement an Updated Customer Charter
for the Development Management Service / Renew
Customer Service Charter
Revised Action - see 1.2.4
9. Review and Update Planning Enforcement Charter  New Action programmed to be completed by
March 2024 see Part 1 - 1.3.4, and Part 4 C
10. Re-establish Customer User Forums during 2023/24  New Action - see Part 1 - 1.2.6
11. Create and Recruit 5 fte New Posts in Development
Management and 1fte in Development Policy 
New Action forming part of wider
Transformational Action Plan for Development
Management see Part 1 - 1.3.3, 1.3.4, Part 5 C and
Part 6
12. Deliver Rothesay TH (Townscape Heritage) project   Ongoing Project see Part 1 - 1.1.6
13. Deliver Ardrishaig Public Realm Works  Ongoing Project programmed to complete in
2023/24 see Part 1 - 1.1.6
14. Deliver Lochilphead CARS (Conservation Area
Regeneration Scheme)  Ongoing Project see Part 1 - 1.1.6
15. Deliver Helensburgh CARS (Conservation Area
Regeneration Scheme)  Ongoing Project see Part 1 - 1.1.6
16. Deliver Dunoon CARS (Conservation Area
Regeneration Scheme)  Ongoing Project see Part 1 - 1.1.6

Page 39

National Headline
Indicators (NHI’s)
2022/23 Part 4:
A: KEY OUTCOMES—DEVELOPMENT PLANNING 2022/23 2021/22
Local and Strategic Development Planning 
Age of local development plan(s) at end of reporting period. Require-
ment: less than 5 years.
8 years 7 years
Will the local development plan(s) be replaced by their 5th anniversary
according to the current development plan scheme?
No No
Has the expected date of submission of the plan to Scottish Ministers
in the development plan scheme changed over the past year?
No Yes
Were development plan scheme engagement / consultation commit-
ments met during the year?
Yes Yes
Effective Land Supply and Delivery of Outputs 
Housing approvals 302 units 507 units
Housing completions over the last 5 years 1367 units 1201 units
Marketable employment land supply 83.98 ha  85.0 ha
Employment land take-up during the reporting period 0.8 ha 0.7 ha
B: KEY OUTCOMES—DEVELOPMENT MANAGEMENT 2022/23 2021/22
Project Planning 
Percentage and number of applications subject to pre-application ad-
vice
Data incomplete 7%(84)
Percentage and number of major applications subject to processing
agreement
- -
Decision Making 
Application approval rate 99.5% 98.0%
Delegation rate 98.2% 97.7%
Validation 30.6% 19.2%
Decision-making Timescales 
Major Developments 43.1 weeks 40.8 weeks
Local Developments (non-householder) 16.3 weeks 13.6 weeks
Householder Developments 12.7 weeks  10.3 weeks
Legacy Cases 
Number cleared during reporting period 18 27
Number remaining 125 65
38
1
C: KEY OUTCOMES—ENFORCEMENT 2022/23 2021/22
Time since enforcement charter published / reviewed 16 months  1 months
Complaints lodged and investigated 184 228
Breaches identified - No further action taken 135 - 49  177 - 51
Cases Closed 85 109
Notices served 18 18
Direct Action 0 0
Reports to Procurator Fiscal 0 0
Prosecutions 0 0
2
3

Page 40

D: NHI KEY OUTCOMES COMMENTARY:
1. It is noted that this NHI is not wholly reflective of the uptake of employment land within
Argyll and Bute where the rural nature of the Council area and local economy stimulates
demand for development in locations that are not readily addressed through take up of
allocated land. The Council’s settlement strategy seeks to promote sustainable economic
development and focuses allocation of employment land in and around existing key
settlements where there is demand of employment, existing housing provision and
infrastructure to support new development. The LDP does however recognise that the
requirements of traditional rural industries, particularly those which are island based
including the whisky industry and aquaculture, will give rise to occasional demand for
development in countryside locations - our settlement strategy is sufficiently flexible to
accommodate this demand but it also means that take up of land for employment purposes
is not wholly captured in the NHIs.
2. It is has been established that this data set is incomplete and does not currently provide an
accurate reflection of the number of planning applications that have been subject to pre-
application advice. 570 pre-application enquiries were received during the reporting period,
this figure is representative of 54.7% of the volume of statutory determinations within the
same period.
3. It is noted that the data subset for ‘major’ applications is small and easily skewed.
Contextual commentary on other factors affecting decision-making timescales are set out
within Part 5 C of the report. 
Planning Performance Framework Report 2022/23
39

Page 41

Official Statistics Part 5:
A: DECISION-MAKING TIMESCALES (based on ‘all applications’ timescales) 
Timescales 2022/23
No of Cases (%)
2022/23
Weeks
2021/22
Weeks
Overall 
Major developments 8 43.1 40.8
Local developments (non-householder) 533 16.3 13.6
 Local: less than 2 months 205 (38.5%) 6.6 7.1
 Local: more than 2 months 328 (61.5%) 22.4 13.6
Householder developments 300 12.7 10.3
 Local: less than 2 months 112 (37.3%) 6.8 7.0
 Local: more than 2 months 188 (62.7%) 16.2 18.8
Housing Developments
Major 1 46.6 76.3
Local housing developments 235 16.6 13.1
 Local: less than 2 months 96 (40.9%) 6.7 7.2
 Local: more than 2 months 139 (59.1%) 23.5 18.8
Business and Industry 
Major - - 9.7
Local business and industry developments 17 19.5 11.9
 Local: less than 2 months 4 (23.5%) 6.9 7.3
 Local: more than 2 months 13 (76.5%) 23.4 14.2 
EIA Developments 1 15.0 25.2
Other Consents 109 14.4 13.0
Planning / Legal Agreements 5 49.9 33.6
 Major: average time 1 85.4 76.3
 Local: average time 4 41.0 30.3
B: DECISION-MAKING: LOCAL REVIEWS AND APPEALS
Total Number
of Decisions
Original Decision Upheld
Type
2022/23 2021/22
No. % No. %
Local reviews 2 2 100 6 33.3
Appeals to Scottish Ministers 3 1 33.3 1 20.0
Planning Performance Framework Report 2022/23
40

Page 42

C: Context
Development Management Service:
Argyll and Bute Council’s Development Management Service continues to process planning
applications with the aspiration to deliver positive outcomes in all cases. This approach is
reflected in our high approval rates but is often achieved by providing applicants with additional
time beyond prescribed statutory determination periods where this is required to negotiate and
address resolvable deficiencies in their submissions. Whilst it is recognised that this approach
can have a negative impact upon performance in decision-making time periods it is contended
that this is outweighed by the economic benefits of delivering on improved development
proposals which might not otherwise have obtained permission had the Council sought to
determine within prescribed statutory time periods; additionally resources required to handle
amended applications, appeal and LRB work is minimised. 
Service delivery arrangements continue to be impacted by the legacy impact of the Covid-19
pandemic; in particular the Service is experiencing a high volume of demand as a wide range of
major developments delayed by the pandemic have sought planning permission during 2022/23.
This period of high demand has coincided with a period of high staff turnover, continued
difficulties in recruiting  in a market where there is a lack of available planning professionals (an
issue known to be a national rather than local issue and are discussed by Heads of Planning
Scotland and the RTPI in their Future Planners Project Report July 2022) and higher absence
rates attributable to stress related illness. During this period the Service has required to operate
with vacancies in key positions for extended periods of time in some cases for 16 months. The
resilience of the Service to operate efficiently with reduced resource and high volume of
casework had already been eroded through previous requirements to make budget cuts and
reduce staffing numbers in previous years. Whilst temporary measures have been taken to
maintain a critical level of service delivery through use of overtime and use of external resources
to process planning applications it is expected that overall performance will remain impacted until
staffing issues are addressed through filling of vacancies. The Scottish Government’s reform of
statutory planning fees from 1st April 2022 is welcomed but came too late to factor into budget
plans for 2022/23. A resultant significant increase in planning fee income has however been
monitored during the course of the last financial year and has provided confidence to support a
business case which will see an increase staff resource within DM with two new posts created
within the Major Applications team during 2022/23 and additional posts planned in 2023/24 to
bolster enforcement and validation functions. 
The ongoing issues in relation to the management of a significant backlog of casework and
reduced staffing arising from recruitment difficulties has continued to have an adverse impact
upon performance of the DM Service and in particular the time taken for determination of
planning applications. The continued deterioration in performance has been highlighted at a high
level with regular reports provided to both Executive Management and Elected Members and has
informed the initiation of a programme of transformational actions which will include review and
addressing of resourcing issues, internal processes and procedures, attraction of new staff and
staff retention, development, morale and mental health, and communication and engagement
with customers and stakeholders that will be further developed and implemented during 2023/24
with the primary purpose of improving performance and efficiency of service delivery.
41
Planning Performance Framework Report 2022/23

Page 43

Development Policy Service:
Progression of LDP2 during 2022/23 has been on hold whilst awaiting the publication of DPEA
Examination Report. During this hiatus the DP team have progressed the development of draft
guidance in anticipation of the Reporters comments; this work will support LDP2 upon its
adoption. The publication of NPF4 in November 2022 delayed the issue of the Examination
Report and the DP Team were required to respond to a variety of information requests issued by
the DPEA in response to new matters raised by NPF4. It is noted that the Examination Report
was subsequently published in May 2023 and will allow progression of LDP2 toward adoption
later in the year.
It should be noted that until the new Local Development Plan (LDP2) is adopted, the current
Local Development Plan’s (the Argyll and Bute Local Development Plan 2015) statutory status
remains, including that of the associated Supplementary Guidance. The current LDPs made
plans for ten years from adoption, so until 2025, and are still considered to be robust. The LDP
contains an effective land supply with the latest Housing Land Audit showing an effective supply
of 3738 units or 5.02 years supply as at 1 April 2022, thus taking us to 2026 well beyond the
proposed adoption date of LDP2. The proposed growth areas of Tobermory – Dalmally and
Helensburgh and Lomond have sufficient supply to take us beyond the adoption of LDP2.
Planning applications will continue to be processed as normal during the delay period, being
assessed against the Adopted plan. An updated Development Plan Scheme was approved by
elected members in March 2022 that re-programmed the planned adoption date to early 2023,
this period has however been impacted by delays in the publication of the Examination Report by
the DPEA.
42
Planning Performance Framework Report 2022/23

Page 44

Workforce Information
(at 31.03.23) Part 6: 
Tier 1 
Chief Executive
Tier 2
Director
Tier 3
Head of Service
Tier 4
Manager
Head of Planning Service    
RTPI Qualified Staff Number
Head of Service 1
Development Management 12
Development Policy 4
Enforcement 2
Projects and Regeneration 3
Staff Age Profile %
Under 30 3.5
30 - 39 17.2
40 - 49 27.6
50 and over 51.7
Service Overview
Planning Services includes: 
Development Management;
Development Policy &
Housing; and 
Projects and Regeneration. 
Planning Services sit within the
Development & Infrastructure
Services Department, and
within the portfolio of the Head
of Development & Economic
Growth which also includes
responsibility for the
complimentary activities of: 
Regulatory Services;
Economic Growth;
Rural Growth Deal Programme; 
Strategic Transportation &
Infrastructure; and, project
specific activity relating to Oban
Strategic Development
Framework including Lorn Arc
regeneration activities.
43
Planning Performance Framework Report 2022/23
Staff Structure Diagrams as at 31.03.2023
Development & Economic
Growth

Page 45

Planning Performance Framework Report 2022/23
44
Development Policy & Housing (at 31.03.2023)
* Note: Housing Services Staff not shown
Development Management (at 31.03.2023)
Denise Stacey
E-Planning Technical
Officer

Page 46

Planning Performance Framework Report 2022/23
45 Projects and Regeneration (at 31.03.2023)
Planning Committee
Information Part 7:
Committees & Site Visits Number
Full Council Meetings 8
Planning Committees 11
Planning Committee Site Visits 3
Area Committees 16
Local Review Body 15
LRB Site Visits 1