Democracy Spraffa

Internal Audit Report - 24-04 - Afforrdable Housing

Perth and Kinross Council · 29 June 2026
Back to Audit and Risk Committee — 29 June 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

1 
Internal Audit Report
Housing & Communities 
24-04 Affordable Housing
June 2026 
Final Report
(Report No. 26/196) 
Legal and Governance
Perth & Kinross Council
Council Offices
2 High Street 
Perth
PH1 5PH

Page 2

2 
PK 24-04 Affordable Housing
Contents by Section 
1. Introduction
2. Executive Summary         
3. Audit Background Information        
4. Scope and Limitations         
5. Assessment of the Control Environment      
6. Summary of Findings         
7. Conclusions          
8. Acknowledgement         
9. Action Implementation & Follow Up     
10. Management Action Plan 
11. Authorisation
12. Distribution
13. Assessment Definitions

Page 3

3 
1.  Introduction 
1.1  The audit of PK 24-04 Affordable Housing was undertaken as part of the
Internal Audit Plan for 2024/2025, which was approved by the Audit &
Performance Committee on 24 June 2024. The period under review for the
purposes of the audit exercise was financial years 2024/2025. 
1.2  The indicative scope for the audit was to review the arrangements in place for
the Affordable Housing Strategy included in the Internal Audit Plan for 2024/25.
1.3  This audit is linked to the Strategic Risk Register SRCP-004 and SRCP-010,
SRCP-004 states that ‘Our actions to tackle poverty and address the
inequalities gap within Perth & Kinross are ineffective’ and this is rated as Very
High Risk, priority 1. SRCP-010 refers to ‘Council buildings and other assets
that are not safe, fit for purpose or providing the best value’ and it was reported
to be priority 2, as High risk for both. 
2.  Executive Summary 
2.1  The audit has found that reasonable assurance can be placed on the Council’s
internal controls in relation to the arrangements in place to support delivering
the Affordable Housing plans of the Council.  
2.2  There are nine actions arising from the findings in Section 6. An action plan is
included in Section 10. Once these actions are completed, Internal Audit should
be able to place substantial assurance on the arrangements in place. 
3.  Audit Background Information 
3.1  Affordable housing delivery refers to the strategic process of planning,
constructing, and providing housing options that are financially accessible to
individuals and families with low to moderate incomes. The Scottish
Government has several initiatives and fundings for affordable housing, which
have a direct impact on Perth and Kinross Council. Each local authority has a
responsibility to develop and implement strategic housing plans that outline
their priorities and targets for delivery. 
3.2 Based on the requirement, Perth and Kinross Council’s Strategic Housing
Investment Plan (SHIP) 25-30 is developed to align with the priorities and
outcomes set out in the Local Housing Strategy (LHS) 22-27. This ensures that
the investment in affordable housing supports the broader housing goals of the
local authority. The SHIP provides a detailed plan for the delivery of affordable
housing projects, including timelines, funding allocations, and resource
planning. 
3.3 The SHIP 25-30 aims to deliver 1,152 affordable homes over the five-year
period committed 210 per year according to LHS. Affordable housing within the
SHIP includes variety of initiatives such as new build projects, refurbishment

Page 4

4 
and renovation projects, regeneration projects, off the shelf acquisitions and
buybacks. Responsibility for Affordable Housing spreads across three Strategic
Lead Areas Economy, Development & Planning; Housing & Communities; and
Property. 
3.4  The PKC Corporate Plan 22-27 explains our vision and priorities. As part of the
strategic approach, Appendix 1 contains a list of priorities and the Local
Housing Strategy is one of them, which is designed in alignment with Scottish
Government strategy Housing to 2040. PKC Risk Register lists the PKC Local
Housing Strategy (LHS) 2022-27 as a control to mitigate the risk, however, it
states that the ‘control effectiveness’ as ‘improvement required’. 
4.  Scope and Limitations 
4.1 The review consisted of identifying measures are in place to ensure the efficient
and effective key controls operating around delivering against all aspects of
affordable housing targets according to the LHS and Strategic Housing
Improvement Plan (SHIP). It is acknowledged that responsibility in this area
spans 3 Strategic Lead areas, namely Economy, Development & Planning;
Housing & Communities; and Property. To arrive at an opinion on the
achievement and transparency of the control objective, the review included:
• Document review in relation to the LHS and SHIP.
• Interviews with key staff who are responsible for LHS and SHIP
• Analysis and review of the effective delivery of Monitoring and Progress and
implementation of the LHS and SHIP.
• Review of any third-party arrangements (financial, process and
communication) 
4.2 The focus of the Internal Audit has been on ensuring that the overall plans of
PKC for affordable housing delivery are in place and of the arrangements in
place for the monitoring and reporting of performance for all partners in
delivering affordable housing. However, the audit did not assess the status of
individual projects assigned to RSL housing providers, as the delivery of their
building projects is the responsibility of the relevant Housing Associations. 
4.3 Internal Audit recognised that a big part of the Action Plan for delivering the
LHS target will be out with the control of the Council and that funding for the
future planning period within the LHS required from Scottish and/or UK
Government may not be forthcoming.  
4.4  The details of the control objectives reviewed and Internal Audit’s assessment
of their strength of control in each area is contained within Section 5 of this
report.

Page 5

5 
5.  Assessment of the Control Environment 
5.1  The table below contains a summary of the number of findings and their ratings,
as detailed in Section 12, against each control objective, along with Internal
Audit’s assessment of the adequacy and effectiveness of the controls in place
to meet each of the objectives agreed for this audit. Further details, including
any improvement actions, are set out in the Management Action Plan.
No. Control Objective Action Rating  Control
Objective
Assessment 5 4 3 2 1
1 To ensure that the LHS delivered
through SHIP is achievable, there is
no risk of failing delivery of the plan
of providing more affordable homes
to support liveable places of
average 210 homes per year over 5-
year period.  
2 4 3 Reasonable
assurance 
5.2  The auditor has assessed that reasonable assurance can be placed on controls
overall in relation to Affordable Housing plans of the PKC. Meaning:
‘There is a generally sound system of governance, risk management and
control in place. Some issues, non-compliance or scope for improvement were
identified which may put at risk the achievement of objectives in the area
audited.’
5.3  A summary of the key findings and actions are provided in section 6, please
note however, the following areas of good practice which have been highlighted
during the audit:
5.4  The Council has created a dedicated Strategic Affordable Housing Strategy
Board (SAHB) where meetings are recorded and discussions cover all aspects
of the PKC SHIP, including newbuild projects through Housing Associations.
There is an average of 5 meetings per year, which are focused as per the group
remit objectives. Topics cover project progress, planning updates, current and
potential future opportunities with well monitored financial and timeline
structure. SHIP and LHS projects have clearly set targets allocated in the LHS
Action Plan 2022-2027, where in addition to the yearly updates, there are
additional quarterly performance updates, accessible to the public on Council’s
webpage. 
5.5 SAHB consists of proactive members and considers utilising flexible housing
funding options to deliver the SHIP. From the reviewed resources there was
visible spend in the following areas: £1.5 million from Developer Contributions
to assist in delivering affordable housing initiatives throughout Perth and
Kinross including new build houses in Kinross; delivery of £4m in funding from
Scottish Government’s Gypsy/Traveller Accommodation Fund at the Double
Dykes site to replace 20 chalets, utilising £700,000 from the second home
Council tax income towards purchasing twenty National Trust buildings in

Page 6

6 
Dunkeld; as well as utilising the major funding through prudential borrowing via
the Housing Revenue Account (HRA) as evidenced in the delivery of the last
phase of 5 modern homes in Methven and few more as per SAHB plan. 
5.6  The assigned Team Leader, Affordable Housing Strategy and connected team
members, have in depth and broad knowledge of the government requirements
of delivery of affordable housing. This was visible, through well organised
delivery plans and implemented communication flow, internally between
departments and externally, through Housing Associations, including to the
Housing Regulator and Scottish Government. PKC Affordable Housing
Strategy Team updates the yearly plan (SHIP), which is annually approved and
continuously reviewed between PKC and Scottish Government, as observed
on the received Resource Planning Allocation letter (RPA), September 2024.
The RPA confirms the allocated funding for 2025-26. It should be noted that
while the overall SHIP covers a five-year period, the specific funding allocations
within the RPA can be adjusted and confirmed only for that year. 
5.7 Considering the limited confirmation of future government funding, which is out
of the audit scope, it is observed through compelling evidence that PKC is
committed to the delivery of the SHIP. As a result, if a delay in new builds
occurs, PKC can react promptly and fulfil the annual affordable housing target
quantities, through quick response with the well- established Affordable
Housing Strategy Team. 
5.8 The latest Strategic Housing Investment Plan (SHIP) for 2025/26 forms the
basis of the plan to deliver the affordable housing of overall £87
million investment. It includes the delivery of 1,152 homes, which has a
significantly higher investment than the previous SHIP 2024-29 with a target of
delivering 1,435 homes. The latest SHIP 2025-30 has an increased target with
already incorporated modern design standards, focusing on higher quality and
more complex projects with expanded scope, such as sustainability and energy
efficiency. 
5.9 The reviewed evidence presents a greater programme performance in 2024/25
than the previous year’s delivery, due to exceeding the target of buybacks; as
of March 2025, the data showed that there was a total of 238 additional
affordable housing units against a projection of 223, compared to a total of 170
additional affordable housing units against a target of 210 in 2023/24.   
5.10 The associated finance team members within SAHB, demonstrate well-
established practices through the overall Capital Financial Monitoring Plan; this
confirms projects match the SAHB plan. Capital planning includes close
monitoring of all undergoing RSL projects with PKC involvement as well as
additional future projects. The SAHB Monitoring Projects Plan indicates a clear
view of how current or future projects could potentially affect the budget plan.
During the interview with the Finance Team Leader, we observed lessons learnt
over the years in adapting the capital budget and expenditure. Current
monitoring sheets reflect more accurately this adaptability in relation to
additional affordable housing projects, as shown in the approach to progressing
buybacks. Before reaching for PKC prudential borrowing to purchase buybacks
over the agreed target, there is communication with the Scottish Government

Page 7

7 
to consider the potential of using the SHIP’s funding. The agreement to proceed
with additional buybacks subsequently supports the meeting of the overall
yearly SHIP targets. In March 2025, the buybacks properties totalled 116, in
comparison to the previously expected 40 properties; this has maximised the
use of the available budget and has supported the overall annual additional
affordable housing units set out in the SHIP for 2024/25. 
5.11 All updates regarding acquiring any property as part of the PKC stock is
communicated between Economy, Development & Planning; Housing &
Communities; and Property, which is then subsequently reflected on their
databases. Approval to proceed above the agreed target of 40 is also discussed
and agreed at regular SAHB meetings and at regular Housing Management
Team meetings. 
5.12 An initiative-taking approach to identifying and addressing additional potential
projects, which are suitable for the Council needs and where the Council can
increase housing quantities to meet the housing needs and reach the annual
PKC target, has been observed. Team officers are working with external
agencies and housing associations to find more flexible and creative options to
obtain additional stock. We can evidence that through the variety of projects
discussed in the SAHB meetings. 
5.13  PKC demonstrates strong tenant and community involvement, following a
consultation with over 3000 responses with the latest tenancy increase
proposals. The latest approved Housing Revenue Account (HRA) Strategic
Financial Plan 2025-2030 presented at the Housing and Social Wellbeing
Committee on 22 January 2025, agreed a 6% increase on the rent-setting for
Council social housing tenants. The income from the rent increase will continue
to support the buyback funding of £20m over 5 years and addresses the
Council’s active approach of addressing funding options for financial
sustainability of the affordable housing projects. 
5.14 We have observed that PKC manages the above Affordable Housing projects
accurately. An effective method for implementing a strong plan is to create
focused responsibilities. This group’s focus is on detailed review on new build
projects, matching latest standards and housing requirements, reflecting good
practices. This has been reflected in the formation of the PKC New Builds Team
meetings in autumn 2023, which collaborates closely with related parties
Finance, Legal, Procurement, Property and Economy, Development &
Planning. 
6.  Summary of Findings 
6.1  Below is a summary of key findings and actions, which are reflected in the
Management Action Plan, detailed in section 10. 
6.2  Strategic Affordable Housing Board (SAHB) 
6.2.1 The SAHB oversees the implementation of the Strategic Housing Investment
Plan (SHIP). During document review, it was noticed that the buyback

Page 8

8 
quantities for September 2024 of the legal team were much higher than listed
on the SAHB plan (40 against the actual 90). The total estimated expenditure
figure on buybacks was not reflected as the number of properties increased.
Although not all buyback properties are funded through the SHIP, all the
purchased quantities can be reflected in the planning sheet to increase the total
number of affordable housing units against the target for PKC. At each SAHB
meeting the total buyback quantity increased from 40, to 64, then to 90,
however this change was not reflected in the total projected spend column in
the SAHB spreadsheet.
[Action Point 1]
6.2.2 In our observation of the SAHB meetings minutes are recorded, however the
discussions blend in with the action points. There is no further clear outcome
and separate follow up Action Plan.  This could result in some action points
remaining unaddressed. Clearly defined actions with designated responsible
persons and timelines would assist in leading to clearer responsibilities. 
[Action Point 2]
6.2.3. We acknowledge that although there is strong control of affordable housing
delivery through SAHB, a clear flow outlining each delivery group and its
responsibilities within and exactly which areas are being covered in the delivery
plan, is not evident. The responsibilities between Property, Economy,
Development & Planning and Housing & Communities are very closely related.
There is a risk of misalignment between the groups, which may result in
conflicting information and inefficiencies during decision-making processes,
and ultimately delivery of outcomes, especially during acquiring new build
properties.
[Action Point 3]
6.2.4 While we recognize the importance of evaluating the PKC New Build Delivery
Group’s performance, we believe it is too soon to draw definitive conclusions at
this stage.   
6.3 Processing Buyback Properties
6.3.1 Affordable housing, particularly the buybacks programme, is delivered through
plans with specified quantities of properties. The buybacks process of acquiring
each property includes different departments, before it becomes part of PKC
stock. It was observed lack of transparency of upcoming plans between
buybacks in Property Team and paralegal team. Each team had their own
stand-alone records with no shared access of other team’s progress. Shared
detailed information or access to upcoming work can improve on wider team’s
planning schedule.   
[Action Point 4]
6.3.2  It was noted that the meetings between Property buybacks team and paralegals
were not regular and not recorded. Structured plan with feedback from both
departments working in collaboration, can improve efficiency in delivery of the

Page 9

9 
Affordable Housing Plan and reduce potential delays during conveyancing
process.
[Action Point 5] 
6.3.3   Currently, the property criteria of buybacks are quite generic when submitting
to paralegals for an offer letter to be sent out. We understand that detailed
information for each property can be added during the assessment process
from the initial viewing. All the unique applicable information can be reflected to
its acquisition form for use of the paralegal team. All additional information can
expedite the conveyancing process by reducing the need for feedback at a later
point.
[Action Point 6]
6.3.4 The buyback policy for processing properties will need to be optimized and
further developed. This should include purpose, scope, responsibilities,
procedures, and compliance measures, approved by, date of issue and last
revision.  Strong and clear instructions, formalised within the PKC template, will
ensure quality assurance in the process. 
[Action Point 7]
6.3.5  Conveyancing process can be lengthy with various bottleneck points occurring
during legal work. We acknowledge the experience of the paralegal team,
however lessons learned practises during conveyancing are not captured. A
database of past issues serves as a valuable information resource for future
training and educating of the wider paralegal team.
[Action Point 8] 
6.3.6  The paralegal team involved in the buyback process is experienced and
efficient, using well-established work routine and process. However, the steps
of the conveyancing process are not captured and reflected directly on a
process-based sheet or work instruction.
[Action Point 9] 
7.  Conclusion 
7.1  The Internal Audit review can place reasonable assurance on the overall control
environment for the delivery for the affordable housing plans of the Council. The
agreed actions, once implemented, should enable Internal Audit to place
Substantial assurance on these. 
8.  Acknowledgements 
8.1  Internal Audit would like to thank all officers who were involved in this audit: 
N Sworowski, Place Strategies Manager & Chief Planning Officer

Page 10

10 
N Lennon, Service Manager - Capital Projects & New Build
H Hatfield, Project Officer
B Mitchell, Paralegal
A Smith, Paralegal
W O’Connor, Paralegal
S Coyle, Team Leader - Finance & Governance 
9.  Action Implementation & Follow up 
9.1  Responsibility for the maintenance of adequate and effective controls rests with
management. Where the audit has identified areas for management action,
these are identified in the Management Action Plan. Where a decision is taken
by management not to act in response to finding from this review, it is the
responsibility of management to assess and accept the risk arising from non-
implementation. 
9.2  Achievement of the agreed actions is monitored through Internal Audit’s ‘follow
up’ arrangements.

Page 11

11 
10.  Management Action Plan
Action
Point
Para.
No Finding
Risk
Ratin
g
Agreed Action & Evidence Suggested
Action Owner
Target
Completion
Date
1 6.2.1 During document review, it was noticed
that the buyback quantities for September
2024 of the legal team were much higher
than listed on the SAHB plan (40 against
the actual 90). The total estimated
expenditure figure on buybacks was not
reflected as the number of properties
increased. Although not all buyback
properties are funded through the SHIP,
all the purchased quantities can be
reflected in the planning sheet to increase
the total number of affordable housing
units against the target for PKC. At each
SAHB meeting the total buyback quantity
increased from 40, to 64, then to 90,
however this change was not reflected in
the total projected spend column in the
SAHB spreadsheet.
3 Agreed action: 
•  Add a column on the SAHB
Monitoring Sheet reflecting the
current spend amount on
Buyback Properties, based on
the increased number of
properties. 
Agreed evidence:
• Updated SAHB Monitoring
sheet
N. Sworowski,
Place
Strategies
Manager &
Chief
Planning
Officer
June 2026
2 6.2.2 In our observation of the SAHB meetings
minutes are recorded, however the
discussions blend in with the action points.
There is no further clear outcome and
separate follow up Action Plan.
3 Agreed action: 
• Create an Action Plan table as
part of the meeting minutes
outcomes. 
Agreed evidence:
• Action Plan Appendix
E. Ritchie
Strategic
Lead -
Housing &
Communities 
Completed

Page 12

12 
3 6.2.3 We acknowledge that although there is
strong control of affordable housing
delivery through SAHB, a clear flow
outlining each delivery group and its
responsibilities within and exactly which
areas are being covered in the delivery
plan, is not evident. The responsibilities
between Property, Economy,
Development & Planning and Housing &
Communities are very closely related.
2 Agreed action: 
• To create Process Flow Map
covering each department
within Affordable Housing
Delivery. 
• Communicate the outlined
Responsibilities and keep
within shared folder 
Agreed evidence:
• Flow Map
N.Sworowski,
Place
Strategies
Manager &
Chief
Planning
Officer
N.Lennon,
Service
Manager -
Capital
Projects &
New Build
J Beveridge,
Strategic
Lead -
Property
Services
September
2026
4 6.3.1 It was observed lack of transparency of
upcoming plans between buybacks in
Property Team and paralegal team. Each
team had their own stand-alone records
with no shared access of other team’s
progress. Shared detailed information or
access to upcoming work can improve on
wider team’s planning schedule.
2 Agreed action: 
• Access to paralegal team of
spreadsheets with upcoming
property volumes 
Agreed evidence:
• Buybacks Master Spreadsheet
Access Granted 
N. Lennon,
Service
Manager -
Capital
Projects &
New Build
Completed

Page 13

13 
5 6.3.2 It was noted that the meetings between
property buybacks team and paralegals
were not regular and not recorded.
Structured plan with feedback from both
departments working in collaboration, can
improve efficiency in delivery of the
Affordable Housing Plan and reduce
potential delays during conveyancing
process.
1 Agreed action: 
• Biannual, suitable for both
teams (buybacks officer and
paralegal team) reviewing
current position, process
improvement and feedback. 
• Record and Email outcomes
from each meeting.
Agreed evidence: 
• Email outcomes from each
meeting
N. Lennon,
Service
Manager -
Capital
Projects &
New Build 
G. Fogg,
Legal
Manager
Legal and
Governance 
September
2026
6 6.3.3 Currently, the property criteria of buybacks
are quite generic when submitting to
paralegals for an offer letter to be sent out.
We understand that detailed information
for each property can be added during the
assessment process from the initial
viewing. All the unique applicable
information can be reflected to its
acquisition form for use of the paralegal
team. All additional information can
expedite the conveyancing process by
reducing the need for feedback at a later
point.
1 Agreed action: 
• The covering email from the
buyback officer will include
a standard separate paragraph
with specific instructions on
what paperwork/permissions
are to be requested in the formal
offer to purchase & what works,
if any, that have been carried
out.
• Attach all related property
documents to the acquisition
form for paralegal use. 
Agreed evidence:
• Covering emails with
detailed information
N. Lennon,
Service
Manager -
Capital
Projects &
New Build 
September
2026

Page 14

14 
7 6.3.4 The buyback policy for processing
properties will need to be optimized and
further developed. This should include
purpose, scope, responsibilities,
procedures, and compliance measures,
approved by, date of issue and last
revision.  Strong and clear instructions,
formalised within the PKC template, will
ensure quality assurance in the process.
1 Agreed action: 
• To revise the Policy 
• To create a Procedure for
Buyback properties 
Agreed evidence:
• Finalised Policy and
Procedure
N Lennon,
Service
Manager -
Capital
Projects &
New Build 
September
2026
8 6.3.5 Conveyancing process can be lengthy with
various bottleneck points occurring during
legal work. We acknowledge the
experience of the paralegal team, however
lessons learned practises during
conveyancing are not captured. A
database of past issues serves as a
valuable information resource for future
training and educating of the wider
paralegal team.
2 Agreed action: 
• Introducing Lessons Learnt
Register/ Database 
• Share lessons learnt database
with Buybacks team for
process improvement 
Agreed evidence:
• Guidance Notes 
G Fogg,
Legal
Manager,
Legal &
Governance
Services 
August
2026
9 6.3.6 The paralegal team involved in the
buyback process is experienced and
efficient, using well-established work
routine and process. However, the steps
of the conveyancing process are not
captured and reflected directly on a
process-based sheet or work instruction.
2 Agreed action: 
• Creating a work instruction of
conveyancing steps within
paralegal team. 
• Checklist. 
Agreed evidence:
•  Work Instructions/ Procedure
G. Fogg,
Legal
Manager,
Legal &
Governance
Services 
Completed

Page 15

15 
11.  Authorisation 
11.1 The auditor for this assignment was T Philip.  The supervising auditor was D
Arachchilage.
This report is authorised for issue: ............. 
12.  Distribution 
12.1 This report has been distributed to:
T Glen, Chief Executive
C Mailer, Depute Chief Executive
E Ritchie, Strategic Lead – Housing & Communities
S Marone, Strategic Lead – Economy, Development & Planning
S Walker, Strategic Lead – Finance & Business Support
L Simpson, Strategic Lead - Legal & Governance 
J Beveridge, Strategic Lead – Property Services
N Lennon, Service Manager - Capital Projects & New Build 
N Sworowski, Place Strategies Manager & Chief Planning Officer
Geoff Fogg, Legal and Governance Manager, Legal & Governance Services
Steven Coyle, Team Leader – Finance & Governance
Committee Services
External Audit

Page 16

16 
13.  Assessment Definitions 
13.1 The following table contains the definitions of the control objective assessment. 
Control Objective Assessment
Level of assurance Definition
Substantial Assurance A sound system of governance, risk management and control
exist, with internal controls operating effectively and being
consistently applied to support the achievement of objectives in
the area audited.
Reasonable Assurance There is a generally sound system of governance, risk
management and control in place. Some issues, non-compliance
or scope for improvement were identified which may put at risk
the achievement of objectives in the area audited.
Limited Assurance Significant gaps, weaknesses or non-compliance were identified.
Improvement is required to the system of governance, risk
management and control to effectively manage risks to the
achievement of objectives in the area audited.
No Assurance Immediate action is required to address fundamental gaps,
weaknesses or non-compliance identified. The system of
governance, risk management and control are inadequate to
effectively manage risks to the achievement of objectives in the
area audited. 
13.2 The following table contains the definitions applied by Internal Audit in rating
audit findings/actions. 
Risk Rating for Individual Findings
Rating Rating
description
Definition
5 Critical Significant observations/ major concerns which require
immediate action. Management will need to add these to the
appropriate Service risk register.
Issue represents a control weakness which could cause, or is
causing, severe disruption of the process or severe adverse
effect on the ability to achieve process objectives
4 High Significant observations regarding the absence / failure of key
controls requiring urgent action. Management should consider
adding these to the appropriate Service/ divisional risk register.
Issue represents a control weakness which could have, or is
having, major adverse effect on the ability to achieve process
objectives
3 Medium Observations regarding the effectiveness of key controls
requiring reasonably urgent action. Management should consider
these when updating any divisional / team risk registers.

Page 17

17 
Issue represents a control weakness which could have, or is
having, significant adverse effect on the ability to achieve process
objectives
2 Low Minor observations regarding the adequacy of controls which
require action to improve the efficiency, effectiveness, or
economy of operations or which otherwise require to be brought
to the attention of Senior Management
Issue represents a minor control weakness with minimal but
reportable impact on the ability to achieve process objectives
1 Trivial / Minor Very minor observations which will be raised during the audit and
may not be included within the final report.
Issue represents a very minor control weakness with negligible
impact on the ability to achieve process objectives. The issue will
be raised during the audit and may not be included within the final
report.