Appendix 1 - Actions with a completion date up to January 2026 which have yet to be completed

Perth and Kinross Council · 23 March 2026
Back to Audit and Risk Committee — 23 March 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Appendix 1
Actions with a completion date up to January 2026 which have yet to be completed
Finding Action Action owner
& Service
Date(s) Current status Internal
Audit
Opinion
A24-01 - Business Continuity
Management (BCM) Planning
Action Point: Action Point 1.3
Importance: High
Audit Committee Date: June
2025
Our observation highlighted
the need for Business
Continuity Plans (BCPs) to be
regularly updated, particularly
regarding contact details and
emergency actions. Despite
the introduction of a new
template, upto-date BCPs
were not found across all
services. The audit concluded
without verifying signed BCPs
for all services
Ensure all Business
Continuity Plans are signed
by the Strategic Leads
Strategic
Leads,
supported by S
Terras,
Emergency
Planning &
Business
Continuity
Officer
June 2025
Dec 2025
Mar 2026
Three Strategic Leads
have still to finalise
and sign their Plan. 
The Emergency
Planning & Business
Continuity Officer has
been busy dealing with
the aftermath of the
Scott Street fire. She
is gradually reducing
the time she needs to
be at Scott Street as it
should be finished
soon and all families
home. She thinks that
this should leave
enough time for her to
arrange sessions with
the three Strategic
Leads to complete and
sign their Plans. 
Accepted
A24-01 - Business Continuity
Management (BCM) Planning
Action Point : 2
Importance: High
Arrange training and
exercising of all plans once
approved and as per the
BCP tracker.
S Terras,
Emergency
Planning &
Business
Jun 2025 
Nov 2025
Mar 2026
As above. Accepted

Page 2

Our observations revealed that
the previous versions of the
BCPs had not routinely been
subject to adequate testing
and communication (training
and exercise) since prior to the
Covid-19 pandemic.
Furthermore, the latest
Business Continuity
Management (BCM)
procedure has not been
finalised, preventing us from
providing any comments on its
effectiveness at this stage. 
Continuity
Officer
24-03 - Multi-Agency
Screening Hub (MASH)
Action Point : 1.1
Importance: Medium
Audit Committee Date:
December 2025
There are some discrepancies
between the Memorandum of
Understanding (MOU) and the
actual practice.
MOU will be updated (as
the list of children, as well
as their personal data on
the MASH spreadsheet, is
available for participants).
S Wilson,
Improvement
Officer
Dec 2025
Apr 2026
This action has yet to
be completed, due to
availability of
resources. This is now
due to be completed
by April 2026.
Satisfactory