Page 1

Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality 
___________________________________________________________________  
Committee or Board: Audit & Risk Committee 
Date of Meeting: 1 December 2025 
Report Title: Internal Audit Follow Up 
Report Number: 25/331 
Report Author: Jackie Clark, Chief Internal Auditor 
Organisational Lead: Strategic Lead – Legal and Governance 
1. Purpose 
1.1 The purpose of this Report is to present current summary of Internal Audit’s
‘follow up’ work relating to actions due for completion up to September 2025. 
1.2 Sections 
1. Purpose
2. Recommendations
3. Background/Context
4. Follow Up Outcomes
5. Conclusion
6. Impact Value Assessment
7. Appendices 
2. Recommendation 
It is recommended that the Committee: 
2.1 Notes the current position in respect of the agreed actions arising from
Internal Audit’s work. 
3. Background/Context 
3.1  The Global Internal Audit Standards in the UK Public Sector (GIAS (UKPS))
and the Code of Practice for the Governance of Internal Audit in UK Local
Government require that the Audit Committee should oversee the tracking
and implementation of actions agreed following audits. 
3.2 Internal Audit request evidence from Services which confirms that actions
have been implemented and, therefore, controls have been improved.

Page 2

4. Progress Update 
4.1 There were 3 actions due to be completed up to September 2025. Two
actions have been verified by Internal Audit as having been satisfactorily
completed. The remaining action has a revised completion date, as detailed in
the Appendix 1. 
5 Conclusion 
5.1 Not applicable. 
6. Impact Value Assessment 
6.1 This report has been classified as being an operational report and as such
does not require a full Impact and Value Assessment.   
7. Appendices 
7.1 Appendix 1 – Actions with a completion date of up to September 2025 which
have yet to be completed