Democracy Spraffa

Internal Audit Follow Up

Perth and Kinross Council · 17 September 2025
Back to Audit and Risk Committee — 17 September 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality 
___________________________________________________________________  
Committee or Board: Audit & Risk Committee 
Date of Meeting: 17 September 2025 
Report Title: Internal Audit Follow Up 
Report Number: 25/238 
Report Author: Jackie Clark, Chief Internal Auditor 
Organisational Lead: 
___________________________________________________________________ 
1. Purpose 
1.1 The purpose of this Report is to present current summary of Internal Audit’s
‘follow up’ work relating to actions due for completion up to April 2025. 
1.2 Sections 
1. Purpose
2. Recommendations
3. Background/Context
4. Follow Up Outcomes
5. Conclusion
6. Impact Value Assessment
7. Appendices 
2. Recommendation 
It is recommended that the Committee notes the current position in respect
of the agreed actions arising from Internal Audit’s work. 
3. Background/Context 
3.1  The Global Internal Audit Standards in the UK Public Sector (GIAS (UKPS))
and the Code of Practice for the Governance of Internal Audit in UK Local
Government require that the Audit Committee should oversee the tracking
and implementation of actions agreed following audits. 
3.2 Internal Audit request evidence from Services which confirms that actions
have been implemented and, therefore, controls have been improved.

Page 2

4. Progress Update 
4.1 There were 10 actions due to be completed up to July 2025. Five actions
has been verified by Internal Audit as having been satisfactorily completed.
The five remaining actions have revised completion dates, as detailed in the
Appendix 1 and 2. Appendix 2 contains actions which were previously
considered in private session of the Audit & Risk Committee. 
5 Conclusion 
5.1 Not applicable. 
6. Impact Value Assessment 
6.1 This report has been classified as being an operational report and as such
does not require a full Impact and Value Assessment.   
7. Appendices 
7.1 Not applicable.