Contract Award for Design and Build of New Bellshill Waste and Fleet Depot

North Lanarkshire Council · 24 August 2022
Back to Environment and Place Committee — 24 August 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

North Lanarkshire Council
Report
Environment and Place Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref: NLC-CPT-21-066 Date: 24 August 2022 
Contract Award for Design and Build of New Bellshill Waste and Fleet
Depot 
From  Andrew McPherson  
E-mail mcphersona@northlan.gov.uk Telephone 07939 280467 
Executive Summary 
This report is to advise Committee of the decision taken in accordance with condition 21.3.2 of the
Council’s General Contract Standing Orders (GCSO’s) where in the absence of committee, the Chief
Executive approved the award of a contract for Design and Build of New Bellshill Waste and Fleet
Depot (the ‘Contract’) to Tilbury Douglas Construction Limited. 
The Contract was formally awarded on 15 June 2022 and is for a period of circa nine (9) months
anticipated to commence on 1 August 2022. 
The value of the Contract is FIVE MILLION, THREE HUNDRED AND TWENTY THOUSAND, FOUR
HUNDRED AND FORTY POUNDS, FIFTY PENCE Sterling (£5,320,440.50) exclusive of VAT. 
Recommendations 
It is recommended that Committee acknowledges the award of the Contract (in accordance with
GCSO 21.3.2 ) to Tilbury Douglas Construction Limited at the value of FIVE MILLION, THREE
HUNDRED AND TWENTY THOUSAND, FOUR HUNDRED AND FORTY POUNDS, FIFTY PENCE
Sterling (£5,320,440.50) exclusive of VAT. 
This recommendation follows the completion of a procurement procedure, where the tender
recommended for award has been evaluated as providing the most economically advantageous
tender in terms of cost and quality for the Council. 
The Plan for North Lanarkshire 
Priority Improve North Lanarkshire's resource base 
Ambition Statement (3) Maximise the use of our marketable land and assets through improved
development in business and industrial infrastructure

Page 2

1. Background 
1.1 An options appraisal exercise was undertaken by the Service Department that considered all
aspects of the Councils ambition agenda. It concluded that the new build facility was the most
viable and appropriate option aligning best with the Plan for North Lanarkshire and associated
programmes of work including overall service delivery.  
1.2  In line with the Council’s objectives and vision to ensure best value for service delivery, depot
rationalisation was identified. Two main areas of service delivery will be accommodated
within a new building, which is to be in the existing Transport Services Depot, Old Edinburgh
Road, Bellshill ML4 3JG. 
1.3 The current Fleet Depot building has been partially closed and deemed unsafe and following
costing exercise it was found to be unviable to repair/refurbish the existing properties. 
1.4 The design and construction of a new vehicle workshop consisting of a maintenance repair
area, MOT facilities, VOSA lane, stores, office, welfare and toilet facilities will provide a new
transport hub which is in keeping with the Council’s objectives and vision. 
2. Report 
2.1 A user intelligence group (the ‘UIG’) of technical and procurement representatives was
formed to review technical specifications, discuss trading processes, market conditions and
trends, ways to maximise community benefits and sustainability and to agree the
procurement strategy that would deliver maximum benefit for the Council via the Contract. 
2.2 The initial estimated value of the Contract dictated that the procurement procedure be
undertaken in accordance with the Public Contracts (Scotland) Regulations 2015. An advert
for the contract opportunity was published on the Public Contracts Scotland utilising the Quick
Quote facility. 
2.3 The procurement procedure was undertaken as a “Mini Competition” from the Crown
Commercial Services Framework (CCS) framework agreement for Construction Works and
Associated Services Lot 2.4 (Works £3m - £10m - Scotland). 
2.4 The Contract award recommendation is made on the basis of the tenderer who submitted the
most economically advantageous tender. 
2.5 The tender submitted by Tilbury Douglas Construction Limited has been evaluated as
representing the most economically advantageous tender for this Contract. 
2.6 Appendix 1 confirms the scoring achieved by each tenderer, further details of the
procurement procedure is provided in Appendix 2 and the SME status and location of all
tenderers is located within Appendix 3. 
2.7 The value of the Contract is FIVE MILLION, THREE HUNDRED AND TWENTY THOUSAND,
FOUR HUNDRED AND FORTY POUNDS, FIFTY PENCE Sterling (£5,320,440.50) exclusive
of VAT including any option to extend the Contract. 
2.8 The costs associated with contract delivery will be contained within the capital budget for
Enterprise & Communities, Regulatory Services and Waste Solutions. 
Price Savings / Increases

Page 3

2.9 There are no price savings / increases related to this Contract. 
Price Stability 
2.10 This is a NEC4 contract which contains fixed price schedule of work items, allowing full
transparency and detailed scrutiny to enable accurate monthly payment draw downs. 
Community Benefits 
2.11.1 The Council is committed to maximising the delivery of community benefits. The procurement
included a community benefit requirement, this approach is designed to deliver local
community benefits where possible. 
2.11.2 Within their tender, Tilbury Douglas Construction Limited committed to deliver the following
community benefits within the Contract:  
Community Benefit Type Quantity Committed
Recruitment for those removed from
labour market
• 3 work placements for those with at least 2 barriers to
work
• 2 Kickstart positions
• 30 hours of training and coaching for those with
multiple barriers to work
Local SME involvement
• 80% of build cost will be spent locally
• 50% of subcontractor work will be
with SMEs / social enterprises
• Meet the buyer event
Employment or training opportunities
• 2 school pupil work experience
placements
• 2 modern apprenticeships
• 2 employability skills workshops
• 4 school talent taster session
Educational benefits
• 6 site visits for school pupils
• 5 STEM based “construction in a box” talks to primary  
schools
• Provision of 2 masterclasses
• 2 FE construction skills lectures
Engagement with community
organisations
• 2 construction related workshops
• 2 employability skills workshops
• 20 hours of mentoring
• 10 hours to help with facilities
Other • 30 hours of community clean up
• 10 hours of local charity evet support 
2.11.3 The community benefits delivered as part of the Contract includes the creation of
apprenticeships. 
Fair Work First  
2.12 Within their tender submission, Tilbury Douglas Construction Limited advised that they
commit to the following the Scottish Governments “Fair Work First” initiative and commit to
ensuring their staff and the staff of their partners and subcontractors are paid The Living
Wage 
Contract Strategy

Page 4

2.13 Officers from external design consultants Faithful & Gould Limited, together with the Council’s
Technical and Design Team (Asset and Procurement Solutions) will be responsible for
managing the Contract which will be undertaken in accordance with the Councils agreed
approach to contract and supplier management. 
3. Measures of success 
The Contract will deliver the following outcomes; 
3.1 Improve economic opportunities and outcomes; 
3.2 Market and promote NLC as the place to live, learn, work, invest and visit; 
3.3 Improve the Council’s resource base; and 
3.4 Form part of the asset rationalisation strategy, continuing to build a workforce with the
capability of delivering on our priorities and ambition. 
4. Supporting documents 
Appendix 1 Summary of Tender Evaluation Process
Appendix 2 Summary of Procurement Process
Appendix 3 SME Status and Location of All Tenderers 
Andrew McPherson
Head of Regulatory Services and Waste Solutions

Page 5

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public Sector
Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-scotland-
duty-impact-assessments 
Yes ☐ No ☐ 
5.2 Financial Impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with Financial
Solutions? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Overall build of new facility sits within the budget allocated. However, due to the delivery of
a new Eco Park facility on the same site the surrounding civil works may have to be changed
to accommodate the new Eco Park. Discussions are to commence with Scottish Power over
the coming weeks with potential to share costs associated with works to ensure that all costs
remain within the overall budget. If additional capital budget is required Fleet Services will
review its spend profile on other areas of the business in partnership with Financial Solutions. 
5.4 Legal Impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal and
Democratic Solutions? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data Protection Impact 
Does the report / project / practice contain or involve the processing of personal data?   
Yes ☐ No ☒

Page 6

If Yes, is the processing of this personal data likely to result in a high risk to the data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-mailed to
dataprotection@northlan.gov.uk 
Yes ☐ No ☐ 
5.6 Technology / Digital Impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?  
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been carried
out (or scheduled) by the Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐ 
5.7 Environmental / Carbon Impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?   
Centralised location of the Fleet and Waste service adjacent to the new Eco Park will deliver
efficiencies in fuel consumption and as a consequence a reduced carbon footprint. 
5.8 Communications Impact  
Does the report contain any information that has an impact on the council’s communications
activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk Impact 
Is there a risk impact?  
Yes ☒ No ☐

Page 7

If Yes, please provide a brief summary of the key risks and potential impacts, highlighting
where the risk(s) are assessed and recorded (e.g. Corporate or Service or Project Risk
Registers), and how they are managed? 
A separate project risk register will be maintained as part of the overall build programme
and monitored through appointed consultant Faithful + Gould Limited

Page 8

Appendix 1 – Summary of Tender Evaluation Process 
Final
Rank Tenderer Name
Total
Tender
Score (%)
Recommended
for Contract
Award (Y / N)
1 Tilbury Douglas Construction Limited 91.20% Yes
2 ISG Limited 87.04% No
3 Heron Bros Limited 82.05% No
4 Henry Brothers Limited 78.64% No

Page 9

Appendix 2 – Summary of Procurement Process 
Response
Procurement Procedure Utilised:
“Mini Competition” utilising the Crown
Commercial Services Framework (CCS)
framework agreement for Construction
Works and Associated Services Lot 2.4
(Works £3m - £10m - Scotland)
Governing Legislation / Regulations: Public Contracts (Scotland) Regulations
2015
Date Contract Strategy Approved: 01 June 2022
Date Contract Notice Published: 24 December 2021
Number of Companies Invited to Take Part: 6
SME % of Expressions of Interest: 0%
NLC Based % of Expressions of Interest: 0%
Tender Return Deadline: 07 March 2022
Number of Tenders Received: 4
Tenders Received from SME’s: 0
Tenders Received from NLC Based Tenderers:  0
Number of Non−compliant Tenders: 0
Number of Compliant Tenders: 4
Number of Recommended Tenderers: 1
Basis of Contract Award: Quality: 30 Price: 70
Evaluation Team:
Officers from the Council’s Technical and
Design Team (Asset and Procurement
Solutions) and consultants Faithful +
Gould Limited
Approval Obtained via GCSO 21.3.2: 14 June 2022
Contract Award Date: 15 June 2022
Anticipated Contract Start Date: 01 August 2022
Total Contract Period (Months): 9
Maximum Total Contract Value: £5,320,440.50

Page 10

Appendix 3 – SME Status and location of all Tenderers 
Name of Tenderer
Size of Tendering
Organisation
(Micro, Small,
Medium or Large)
Location
(Local Authority /
Council Area)
Henry Brothers Limited Large Londonderry County
Council
Heron Bros. Limited Large Londonderry County
Council
ISG Limited Large City of London
Tilbury Douglas Construction Limited Large City of London