North Lanarkshire Council
Report
Enterprise, Growth and Fair Work Committee 
Does this report require to be approved? ☐ Yes   ☒ No
Ref PH/DG Date 29/08/22 
External Funding update 
From  Pamela Humphries, Head of Planning and Regeneration 
E-mail GreerD@northlan.gov.uk Telephone
David Greer, Growth
Programme Manager
07583 059816 
Executive Summary
This report provides information on a range of external funding opportunities
which are available for physical regeneration activity. In addition, this report will
provide an update on the work which the council is currently undertaking to secure
this funding or deliver strategic programmes and projects to ensure full spend of
external funding secured. 
This includes updates on: 
 the UK Government’s Levelling Up Fund;
 the Scottish Government’s Place Based Investment
Programme (including the Regeneration Capital Grant Fund and
Town Centre Demonstrator);
 the Scottish Government’s Vacant and Derelict Land Fund and
Vacant and Derelict Land Investment Programme; and
 the Scottish Government’s Green Growth Accelerator. 
Recommendations
It is recommended that committee acknowledges: 
1) the update provided on both first and second round Levelling Up Fund applications 
2) the funding allocation made through the Scottish Government’s Place Based
Investment Programme, the council’s plans for using its allocation and current
work aimed at securing additional funds from the Programme 
3) the successful bids for the 2022-23 Regeneration Capital Grant Fund and Vacant
and Derelict Land Investment Programme 
4) the bids submitted for 2023-24 Regeneration Capital Grant Fund and Vacant and
Derelict Land Investment Programme 
5) the update provided on the Council’s 2022-23 ‘Local Delivery Plan’ for the Vacant
and Derelict Land Fund

Page 2

1. Background 
Levelling Up Fund 
1.1 The UK Levelling Up Fund (LUF) will provide £4.8bn worth of capital investment across
the UK by 2025-26. Funding is expected to be made available across three rounds, the
first of which took place during 2021-22. Local authorities are eligible to make a bid for
each UK Parliament constituency in their areas, plus an additional bid for a transport
infrastructure project. 
1.2 The LUF supports town centre and other physical regeneration, culture and transport
projects. Local authorities can bid for up to £20m in LUF support for each project, with
the exception of large transport projects (up to £50m). The LUF will also provide more
than £20m in funding for up to two large cultural projects. 
1.3 The second round of the LUF, for 2022-23, closed for bids on 2 August 2022. UK
Government has committed to spending 9% of all monies allocated from this round to
projects in Scotland. 
Placed Based Investment Programme 
1.4 The Scottish Government has established a Place Based Investment Programme
(PBIP), linking and aligning place-based funding initiatives. The PBIP will provide £325m
in funding for place-based regeneration projects over the lifetime of the current Scottish
Parliament. 
1.5 The main objectives of the PBIP are: 
 to link and align place based initiatives and establish a coherent local framework
to implement the Place Principle;
 to support place policy ambitions such as town centre revitalisation, community
led regeneration, 20 minute neighbourhoods and Community Wealth Building;
 to ensure that all place based investments are shaped by the needs and
aspirations of local communities; and
 to accelerate ambitions for net zero, wellbeing and inclusive economic
development, addressing inequality and disadvantage and community
involvement and ownership 
1.6 £140M of this funding will be allocated directly to local authorities, which will be 
provided with annual allocations for spend in each of the five financial years from 
April 2021. 
6) the development of a full business case which aims to secure Green Growth
Accelerator support to deliver the low-carbon redevelopment of Strathclyde
Country Park.  
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (21) Continue to identify and access opportunities to leverage
additional resources to support our ambitions

Page 3

1.7 The PBIP also now incorporates the Scottish Government’s Regeneration Capital
Grant Fund, committing up to £25M a year over each of the next 5 years, and other
discrete funding schemes, including the £8m Town Centre Demonstrator fund which
will support a small number of town centre regeneration projects. 
1.8 RCGF provides capital grant funding for physical regeneration projects and is open to
Scotland’s 32 local authorities and special purpose vehicles (SPVs) established by
local authorities for the purpose of urban regeneration activity. Local authorities and
SPVs can apply on behalf of ALEOs and other partners, including community groups,
and will act as a conduit for grant funding. 
1.9 The PBIP also includes a new £8m national Town Centre Demonstrator fund which
was launched earlier in 2022 to support innovative projects which can provide lessons
for similar towns across Scotland.  This fund is being run as a closed competition, with
only invited local authorities allowed to submit bids which will be considered by a
Scottish Government panel. 
Vacant and Derelict Land Fund and Vacant and Derelict Land Investment   
Programme 
1.10 The Vacant & Derelict Land Fund (VDLF) is a ring-fenced capital grant allocation which
provides financial support from the Scottish Government to assist with the regeneration
of registered vacant and derelict land sites across selected local authority areas. The
Scottish Government has committed to maintaining the VDLF for 2022-23 but there is
no guarantee of funding for those authorities (including the council) in subsequent
years. 
1.11 Funding provided through the VDLF programme is subject to the submission (and
approval by the Scottish Government) of an annual Local Delivery Plan which sets out
local authority investment proposals to meet the objectives of the VDLF programme.
These objectives are to: 
 tackle long term vacant and derelict land (and in particular sites which have
been registered as vacant or derelict for at least 15 years);
 stimulate economic growth and job creation;
 develop a diverse sustainable environment with a focus on temporary
and permanent greening; and
 support communities to flourish and tackle inequalities. 
1.12 There is a range of activity which this fund cannot support including major infrastructure
works, flood mitigation, retail and housing projects. 
1.13 Whilst organisations other than local authorities and SPVs cannot apply directly to this
fund, the council can apply on behalf of ALEOs and other partners and act as a conduit
for this grant funding. 
1.14 In addition to the existing VDLF programme, the Scottish Government launched their
Vacant and Derelict Land Investment Programme (VDLIP) in early 2021, providing £50M
over the five years between 2021 and 2026 to support placed based approaches for
tackling persistent vacant and derelict land and delivering regeneration and sustainable
growth as part of the green recovery.

Page 4

Green Growth Accelerator
1.15 The Green Growth Accelerator (GCA) aims to unlock £200 million of additional
investment in infrastructure projects to support Scotland’s transition to an inclusive net-
zero emissions economy. 
1.16 The GGA is a financial tool where successful applicants invest initial capital in ‘green
infrastructure’ with this investment repaid across future years based upon their success
in meeting targets for carbon reduction and related measures. The successful applicant
has discretion over how it funds the initial infrastructure investment, for example through
capital grant, borrowing or receipts and flexibility over timescales for repayment. 
1.17 The GGA was announced in the 2020-21 Budget and a call for ‘Pathfinder Projects’
launched in June 2021. The Scottish Government committed to provide successful
pathfinder authorities with initial revenue funding to help develop business cases for
submission for full funding awards during 2022-23. Where projects are approved, local
authorities are eligible for revenue payments which meet up to £10m of initial capital
investment (including any borrowing costs), subject to achieving agreed outcomes. 
2. Report 
Levelling Up Fund 
2.1 The first round of the LUF was launched in March 2021, for bid submissions by June
of the same year. Due to the restricted timescales and resources available to develop
bids, the council took forward only one bid to this round, for enabling works to kick-start
the reshaping and renewal of Cumbernauld Town Centre in line with the recently
approved Cumbernauld Town Centre Vision. This bid was unsuccessful however UK
Government officials provided positive feedback to officers and encouraged the bid to
be revised and resubmitted in future rounds. 
2.2 The second round of LUF was launched in April 2022. As agreed at previous Enterprise
and Growth committees in November 2021 and February 2022 the following bids have
been developed and submitted by the revised deadline of 2 August 2022 for each of
the four Westminster constituencies: 
 Airdrie and Shotts: delivering town centre living by repurposing prominent
vacant or derelict buildings and sites for mid-market rent homes in Airdrie.
 Coatbridge, Chryston and Bellshill: the redevelopment of Summerlee
Museum of Scottish Industrial Life, which will be transformed into a world-
class visitor destination and outstanding community asset.
 Cumbernauld, Kilsyth and Kirkintilloch East: enabling acquisition and
demolition works to support the later development of a new Town Hub and
reshaped, repopulated Cumbernauld town centre.
 Motherwell and Wishaw: enabling groundworks to support the development
of new community facilities and affordable homes for Ravenscraig. 
2.3 These bids were subject to engagement with local members, MPs and MSPs.  The
outcome of the bids is expected in the Autumn.

Page 5

Place Based Investment Programme
2.4 The council was allocated £2.436m for spend from the PBIP in 2022-23.  Details of the
projects to be funded which meet the PBIP criteria, including the requirement for
funding to be spent or legally committed by 31 March 2023, and which align to the
priorities set out in the Economic Regeneration Delivery Plan (ERDP) are outlined in
Appendix 1.   
2.5 The Regeneration Capital Grant Fund (RCGF) now also forms a separate part of the
Scottish Government’s PBIP. 
2.6 The council succeeded with bids to earlier rounds of RCGF, including funding in 2021-
22 for projects in Motherwell (Reeltime Community Music Facility) and Shotts
(Springhill Community Hub). 
2.7 The council was successful for its bid for £1.8m in RCGF funding during 2022-23 to
support the low-carbon redevelopment of Braidhurst Industrial Estate. 
2.8 The current round of RCGF sought initial ‘stage 1’ bids by 17 June 2022.  Following a
‘call for bids’ advertised to community organisations and within the council, five bids
were submitted for projects: 
 ‘Active travel connections’, providing the ‘missing links’ in the active travel
network to connect Bellshill, Motherwell and Wishaw.
 A new ‘community memory store’ for collections and social history at
Summerlee Museum of Scottish Industrial Life.
 Development of a new health and wellbeing hub by Motherwell FC
Community Trus.t
 Redeveloping a former NHS clinic to create a community hub in Croy
 Supporting the low-carbon redevelopment of Strathclyde Country Park (see
Green Growth Accelerator for further information) 
2.9 Decisions on these bids are expected in August 2022, with those succeeding at stage
1 invited to make stage 2 (award stage) bids in October, with funding decisions
expected in December. 
2.10 The council was invited to apply for Town Centre Demonstrator (TCD) funding and,
after initial discussion with Scottish Futures Trust (which manages the competition on
the Scottish Government’s behalf) on the types of projects which may be suitable for
the TCD and its timescales for spend, the council submitted initial proposals for projects
in both Airdrie and Motherwell. Following feedback, a full application for funding has
been submitted for Airdrie, which aims to establish a land assembly and reuse fund
which will enable both site acquisition and follow-on development in the town centre to
support delivery of the town vision and help increase residential provision in the town
centre.  A decision on this proposal is expected in the autumn. 
Vacant and Derelict Land Fund and Vacant and Derelict Land Investment Programme
2.11 The Scottish Government allocated £1.938m from the Vacant and Derelict Land Fund
(VDLF) to North Lanarkshire Council, subject to the submission and approval of a
2022/23 VDLF Local Delivery Plan (LDP).  The proposed projects to be delivered from
the 2022/23 VDLF were approved at Enterprise & Growth Committee in February 2022.

Page 6

2.12 This LDP was approved by the Scottish Government in July and the projects which will
be delivered through the council’s VDLF Programme are: 
 Ravenscraig Plot 1: £1.3m in enabling earthworks, including drainage, to
allow for later access roads, services and utilities to be brought in to provide
a development ready site. This project is expected to lever in £9m in private
investment for 65,000 square feet of industrial development which will
create 128 permanent new jobs.
 Ravenscraig Plot 1 Microgeneration feasibility study: £38,000 to review
options for follow-on industrial development to meet the council’s
aspirations for a Net Zero North Lanarkshire.
 Gartcosh Business Interchange Phases 3 and 4: £600,000 for enabling and
remediation works to allow for follow-on development, building on the
success of Phases 1 and 2. 
2.13 In addition to VDLF, the council also made two Stage 1 applications to the second round
of the Vacant and Derelict Land Investment Programme (VDLIP) for projects in 2022-
23. A bid for £230,911 to deliver ‘Glenmanor Greenspace’, a community greening
project in Moodiesburn, was successful while an application for the second phase of
the Ravenscraig Active Travel Link (RATL), connecting Craigneuk with New College
Lanarkshire, was unsuccessful but has been held in reserve should any other funded
projects not proceed. 
2.14 The council has submitted stage 1 bids for phase two of the RATL and for a separate
project which will deliver enabling groundworks to support the development of 21 new
affordable housing on a long-term vacant and derelict site at Caledonian Road in
Wishaw. Outcomes of these stage 1 bids is expected in August, with those bids
succeeding at stage 1 invited to make stage 2 (award stage) bids in October, with
funding decisions expected in December. 
2.15 The council will continue to engage with local communities to develop projects that can
be submitted to future rounds of both RCGF and VDLIP in 2023 and subsequent years. 
Green Growth Accelerator (GGA) 
2.16 The council’s bid proposal for GGA support for the low-carbon redevelopment of
Strathclyde Park was selected as one of five GGA Pathfinder projects in September
2021. NLC was awarded £120,000 in funding to help develop a business case for full
support of up to £10m in funding to support capital investment. 
2.17 Consultants were appointed to carry out extensive surveys and provide costed design
proposals based around three key elements: 
 The net zero redevelopment of the Park’s Watersports Centre and
Bothwellhaugh Cottage, ‘retrofitting’ the existing buildings and installing
solar photovoltaic array to meet energy demand
 The installation of a water source heat pump in Strathclyde Loch to meet
the Park’s heat demand
 The installation of new renewable-fuelled EV charging points and street
lighting.

Page 7

2.18 These proposals were received in early July and formed the basis of the council’s
business case for GGA funding, which was submitted to the Scottish Government for
consideration at the end of that month. A decision on funding the project is expected
later in the year and officers have been preparing additional bids for support to meet
any prospective funding gaps (see RCGF above). 
3. Measures of success 
3.1 The primary measure of success arising from the work and updates outlined in this
report would be to: 
 maximise the funding drawdown from the external funding opportunities
outlined in this report; and
 ensure that the funding drawdown from these sources is used to best enable
the council to achieve its wider goals for community and environmental
regeneration and inclusive economic growth.     
4. Supporting documentation 
Appendix One: Place Based Investment Programme List 2022/23 
Pamela Humphries
Head of Planning and Regeneration

Page 8

5. Impacts ( http://connect/report-template-guidance ) 
5.1 Public Sector Equality Duty and Fairer Scotland Duty
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The funding programmes outlined in this report are very much focused on promoting
inclusive growth and a fairer Scotland and will do so by: 
 delivering physical regeneration projects that will improve the local
environment and tackle problems which continue to constrain community
regeneration;
 creating infrastructure that will help improve health and well-being and
provide North Lanarkshire’s most disadvantaged communities with new
leisure, learning and economic opportunity; and
 ensuring that our place based investments are shaped by the needs and
aspirations of all of our local communities. 
Consideration will also be given to equalities issues as part of the bids and projects
developed in response to the identified funding opportunities whilst the council will
also work closely with ALEOs, partners and third-party organisations involved in the
delivery of these to ensure that equality considerations remain core throughout. 
If Yes, has an assessment been carried out and published on the council’s website?
https://www.northlanarkshire.gov.uk/your-community/equalities/equality-and-fairer-
scotland-duty-impact-assessments
Yes ☐ No ☒
5.2 Financial impact
Does the report contain any financial impacts?
Yes ☒ No ☐
If Yes, have all relevant financial impacts have been discussed and agreed with
Financial Solutions?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
Scottish Government external funding programmes such as PBIP, VDLF, RCGF and
VDLIP can provide up to a 100% project funding and as such do not require match
funding. However, challenge fund bids to programmes such as RCGF and VDLIP are
more likely to be successful where match is provided to overall project costs. In
these cases, where such funding is invested in council owned assets, it is likely that
the Scottish Government would expect NLC to contribute funding to these (although
there is no set percentage). 
The UKLUF provides up to a maximum of £20M per project and 90% of total project
costs. As such, the development and delivery of these projects, unless already
included as part of the Capital Programme, could result in the need to reprioritise
budgets to ensure that the drawdown of this external funding can be maximised. 
It should also be noted that due to the complexity of bids and requirement for
detailed costs, there will be a requirement for feasibility, design and site investigation
works to support the UKLUF bids. However, the UK Government has provided a
‘one-off’ payment of £125,000 to manage Levelling Up projects and future bids to this

Page 9

fund, which has been used to support bid development. 
The GGA Pathfinder also gives rise to potential financial impact particularly in
relation to how initial capital investment is met, how risk of ‘under repayment’ can be
minimised or negated and timescales for repayment. The council will continue to
work with the Scottish Government to minimise these risks, including through
agreeing realistic outcomes for which revenue payments are based on. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts?
Yes ☐ No ☒
If Yes, have all relevant HR impacts have been discussed and agreed with People
and Organisational Development?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)?
Yes ☐ No ☒
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic Solutions?
Yes ☐ No ☐
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?  
Yes ☐ No ☒
If Yes, is the processing of this personal data likely to result in a high risk to the data
subject?
Yes ☐ No ☐
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management, or
connectivity / broadband / Wi-Fi?
Yes ☐ No ☒
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for technology, has an assessment been
carried out (or scheduled) by the Enterprise Architecture Governance Group
(EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact?

Page 10

The implementation of the programmes supported through capital programmes such
as the VDLF, PBIP and the LUF provide significant opportunity for local environment
improvements to greenspace, town centres and community facilities. Moreover, the
proposals put forward as part of the GGA Pathfinder would bring forward significant
carbon savings and develop a demonstrator project to help support the council to
meet its future net zero carbon targets. 
5.8 Communications impact
Does the report contain any information that has an impact on the council’s
communications activities?
Yes ☒ No ☐
If Yes, please provide a brief summary of the impact? 
The promotion of opportunities delivered through new funding programmes or
success in gaining external funding for projects will continue to be managed and co-
ordinated through Corporate Communications. 
5.9 Risk impact
Is there a risk impact?
Yes ☒ No ☐
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or Service
or Project Risk Registers), and how they are managed? 
External funding programmes do bring a measure of risk to the council particularly in
relation to potential budget overspend for projects and/or the requirement to repay
funds due to failure to deliver projects properly (a risk which is increased where
delivery is through a third-party). 
To help reduce and mitigate risk, a full risk assessment is undertaken for all funding
programmes and/or externally funded projects as part of the council’s project
management process and where complex/high risk projects are being developed or
delivered, risk workshops will be set up to ensure all service and partner risks are
identified.

Page 11

Appendix 1: North Lanarkshire’s Place Based Investment Programme 2022/23 
THEME PROJECT DESCRIPTION TOTAL COST Match/ other
funding
Projected   
22/23 PBIP
Spend/
Commitment
Town Centre
Regeneration
Braidhurst
Industrial Estate
New / refurbished industrial units
and environmental improvements.
Contribution will focus on micro
generation
£5,000,000 tbc £4,500,000 £500,000 
Motherwell
Library
Immersive classroom/digital
learning & access to be
incorporated within Mother Library
- this builds upon recently
completed external works and
rewiring recently contracted
£414,778  £414,778 
Orrs, Airdrie Contribution for the commercial
units at the new development
£3,200,000 £3,040,000 £160,000 
Café Refresh,
Motherwell
Continuation of existing PBIP
supported project 
£75,000 £0 £64,000 
20 Minute
Neighbourhoods 
Active Travel Ph2,
Ravenscraig
Continuation of existing PBIP
supported project 
£1,100,000 £750,000 £350,000 
Active Travel
Hubs,
Motherwell
Continuation of existing PBIP
supported project
£144,000 £0 £115,000 
Motherwell
Station Active
Travel Links   
City Deal Project – application
being prepared and external match
funding being sought for creation
of active travel routes at
Motherwell Station.
£1,200,000 £700,000  £500,000
Placemaking/
Community
Wellbeing Glenmanor,
Moodiesburn
PBIP contribution to community
greenspace project being
supported by VDLIP 
£298,000  £238,000  £60,000 
Newmains 
Feasibility study and potential
acquisition of commercial property
in Newmains for future demolition
and conversion to community
garden. 
£150,000  £0  £150,000 
Cumbernauld
Community
Allotments
PBIP supported this project in
21/22. Due to an increase in
groundworks, additional funds
are required. 
£370,000  £350,000  £20,000
Other To Be Allocated Funding for projects under
development.
£0 £0 £102,222
Total   £10,277,000 £7,841,000 £2,436,000