Democracy Spraffa

IJB - Annual Governance Statement - Action Plan Progress

North Lanarkshire Council · 22 October 2025
Back to IJB Performance, Finance and Audit Committee — 22 October 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

REPORT 
Item No: 9 
1. PURPOSE OF REPORT
1.1 This paper is coming to the Performance, Finance and Audit (PFA) Committee:   
For approval  For endorsement  For noting 
1.2 This report provides an outline of the actions agreed with the External Auditor,
Internal Auditor, and the Senior Management Team to further develop the IJB
governance framework. 
2. ROUTE TO THE PERFORMANCE, FINANCE AND AUDIT COMMITTEE
2.1 This paper has been: 
Prepared By:
Chief Finance
Officer
☒ Reviewed By:
Chief Officer
☒ Endorsed By: ☐ 
3.       RECOMMENDATIONS
3.1  It is recommended that the PFA Committee: 
(1) Acknowledge the contents of the report; and
(2) Agree that further progress reports will be presented to future meetings of the
PFA Committee in respect of the ongoing actions. 
4. VARIATIONS TO DIRECTIONS 
5. ANNUAL GOVERNANCE STATEMENT ACTION PLAN
5.1 As part of the statutory annual accounts, an Annual Governance Statement is
included which reports on the effectiveness of the IJB’s governance arrangements
and system of internal control and explains how the IJB complies with the Code of
Corporate Governance and meets the requirements of ‘Delivering Good
Governance in Local Government’ framework developed by CIPFA and SOLACE in
2016. 
5.2 To ensure continual improvement of the IJB’s governance arrangements, an action
plan is included within the Annual Governance Statement which was approved at
the IJB in June 2025.  Included within this are improvement areas identified by Audit
Scotland within their Annual Audit report, Internal Audit as part of their annual audit
SUBJECT: Annual Governance Statement – Action Plan Progress
TO: Performance, Finance and Audit Committee
Lead Officer for Report: Chief Officer
Author(s) of Report Chief Financial Officer 
DATE: 22 October 2025
Yes  No  N/A

Page 2

work as well as improvements highlighted as part of the IJB self-assessment
process. 
5.3 Following conclusion of the 2024/25 External Audit, the Annual Audit Report
identified 1 recommendation with regards to financial sustainability therefore this
has been added to the action plan. 
6 ACTION PLAN PROGRESS
6.1 Appendix 1 details the actions as well as progress against these actions.  For audit
purposes, all actions will remain on the plan for a full financial year however those
completed during the year will be removed for the first report after April 1st each
year.  Table 1 provides a summary of the status of the actions. 
Table 1 
Year the
action was
identified
Total
Actions
Completed
Actions
Ongoing
Actions
2022/23 2 1 1
2023/24 5 4 1
2024/25 3 1 2
2025/26 1 1 0
TOTAL 11 7 4 
7.  IMPLICATIONS
7.1 NATIONAL OUTCOMES  
People are able to look after and improve their own health and wellbeing
and live in good health for longer 
☒
People, including those with disabilities or long-term conditions, or who are
frail, are able to live, as far as reasonably practicable, independently and at
home or in a homely setting in their community
☒
People who use Health and Social Care Services have positive
experiences of those services, and have dignity respected
☒
Health and Social Care Services are centred on helping to maintain or
improve the quality of life of people who use those services 
☒
Health and Social Care Services contribute to reducing health inequalities  ☒
People who use Health and Social Care Services are safe from harm ☒
People who work in Health and Social Care Services feel engaged with the
work they do and are supported to continuously improve the information,
support, care, and treatment they provide
☒
Resources are used effectively and efficiently in the provision of Health and
Social Care Services 
☒
7.2 ASSOCIATED MEASURE(S) 
The implementation of agreed actions will contribute to the ongoing development of
the internal control framework and will also inform the Annual Governance
Statement for 2025/26.

Page 3

7.3 FINANCIAL 
This paper has been reviewed by Finance: 
Yes  No  N/A 
7.4 RISK ASSESSMENT/RISK MANAGEMENT 
The strategic financial risks detailed in the IJB Risk Register has been updated
where necessary and are included in a separate report to the IJB. 
Relevant Risk Register Details  Current Risk Level  Risk Owner 
Ineffective Governance Arrangements Low Claire Rae 
7.5 ENGAGEMENT & PARTICIPATION 
Please tick the engagement and participation objectives that link(s) with this piece
of work and provide further details on the engagement and participation that was
undertaken. 
Objectives  Further details 
☒ Involve stakeholders in the development work aimed at   
achieving the national 
outcomes
This report
includes all
engagement and
participation
objectives as
effective
governance
arrangements
ensure the IJB
can fulfil its
statutory duties. 
Good governance
enables the IJB to
pursue its vision
effectively as well
as underpinning
that vision with
mechanisms for
control and
management of
risk.
☒ Provide stakeholders with information on how to get
involved
☒ Ensure a diverse range of engagement and participation
and opportunities are in 
place to suit different needs 
☒ Measure how well we involve community stakeholders in
the planning, design, and delivery of our services 
☒ Provide regular feedback on how stakeholder engagement
and participation is shaping and influencing service
development and delivery
☒ Provide support to enable stakeholder representatives to
participate meaningfully and confidently at meetings
☒ Develop participation guidelines to ensure a common
understanding and set of 
expectations for both stakeholders and partnership staff
☒ Support engagement planning and participation in
localities, taking account of 
other engagement activity and local plans across the
Community Planning 
Partnership 
7.6  INEQUALITIES & FAIRER SCOTLAND DUTY
Equality and Diversity Impact Assessment Completed & Fairer Scotland Impact
Assessment Form Completed and EQIA added to website: 
Yes  No  N/A

Page 4

8. BACKGROUND PAPERS 
None. 
9. APPENDICES 
Appendix 1   Annual Governance Statement – Action Plan Progress   
Chief Finance Officer   
Members seeking further information about any aspect of this report, please contact
Nicola Scott on telephone number 07581 007187.

Page 5

Appendix 1 
Annual Government Statement - Action Plan Progress                        
Reference Improvement Area Agreed Action Responsible
Person
Projected
Completion
Date
Current Status Ongoing /
Complete
2022/23: 1 Service Level
Agreement (SLA)
To agree an SLA with Children, Families and
Justice for future hosting arrangements
following the budget disaggregation exercise. 
Work is currently underway to agree, approve
and implement the new SLA in partnership with
Children, Families and Justice Services. 
Chief Officer
Claire Rae
September
2025
Work on this is progressing.  The budget data has been
gathered to inform the arrangements, key points for
consideration are being collated, and the final task will be for
all relevant chief officers to meet and finalise this SLA.  The
current timeline for completion is no later than 31st March
2026.  
Ongoing
2022/23: 2 National Care Service To develop a sound understanding of the
impact for the Partnership of the National Care
Service legislation.   Paper presented to the
IJB in January 24 giving an update on
timescales for implementation.  Further
updates will be presented to the board as
details are released.
Chief Officer
Claire Rae
September
2025
This action is no longer relevant given the changes from the
proposed NCS to the Care Reform Bill.  The Senior
Management Team will keep abreast of ongoing
developments and report to the IJB as necessary.
Complete.       
2023/24: 1 2023/24 Self-
Assessment Agreed
actions
1. Development of a revised framework for
North Lanarkshire which will ensure
engagement and participation in the
development of the Strategic Commissioning
Plan across the entire health and social care
system. 
Chief Officer
Claire Rae
December
2025
The development of a new Strategic Commissioning Plan is
underway with a view to the new plan coming into effect from
April 2026, upon expiry of the current Strategic
Commissioning Plan 2023-2026. 
An engagement and consultation process has been initiated
to ensure a wide range of staff, people who use services,
carers and partner organisations have an opportunity to
participate in shaping the next commissioning plan. 
This was reported to the IJB on 17th September 2025
Strategic Commissioning Plan 2026 and Beyond
Complete  
2.  Undertake an exercise to review
performance output and associated data from
other Health Boards and Local Authorities. 
Chief Officer
Claire Rae
December
2025
Benchmarking is undertaken within our family group of local
authorities against all national performance indicators and
reported within the Annual performance report.
Annual Performance Report 2024/25 - DRAFT
Complete  
3.  Recognition that there is a formalised risk
sharing agreement in place with NHSL, NLC
and SL IJB within the risk management
strategy but no reference to similar in relation
to performance and finance.
Chief Officer
Claire Rae
December
2025  This is currently under review to consider whether a
formalised agreement is required and what this would consist
of.  
Ongoing
2023/24: 2 Presentation of
financial and non-
financial information
in the annual
accounts
In the production of future accounts, the IJB
should review the presentation of both financial
and non-financial information to ensure this
reflects the organisation’s role as a strategic
commissioning body.
Chief Finance
Officer
Nicola Scott
September
2025
A review of other IJB’s accounts was undertaken to ascertain
the style and content of their Annual Reports.  Using this, the
format of the 2024/25 Annual Report was updated which has
been accepted by Audit Scotland.
Complete
2023/24: 3 Presentation of
financial and non-
financial information
in the financial
performance reports
The financial reports will be further defined to
give an overview in the delivery of services
against the overall funding aligned to the
Strategic Commissioning Plan and Medium-
Term Financial Plan/Long Term Financial Plan
including earmarked reserves. 
Chief Finance
Officer
Nicola Scott
September
2025
An updated report, taking into account Audit Scotland’s
recommendations, has been prepared for the first quarter. 
This was presented to PFA in August 2025 and has been
accepted by Audit Scotland as part of their 2024/25 External
Audit.  
Complete

Page 6

Appendix 1 
Reference Improvement Area Agreed Action Responsible
Person
Projected
Completion
Date
Current Status Ongoing /
Complete
2024/25: 1 2024/25 Self-
Assessment   
Agreed actions
1. Holding to Account - effective scrutiny,
challenge and support of services by the
Management Team and IJB members when
reviewing presented papers. 
Chief Officer
Claire Rae
December
2025 
Work on this will be undertaken as part of updating the
standing orders in Q1 2026.
Ongoing  
2.  Vision for IJB should be clear and ambitious
with membership being diverse and engaged. 
Management team to review induction process
and liaison sessions. 
Chief Officer
Claire Rae
December
2025
This is under review and will be updated along with the
renewal of the Strategic Commissioning Plan in April 2026.
Ongoing  
3. Review what goes to IJB and PFA and
ensure there are appropriate development
sessions to support the financial picture. 
Chief Officer
Claire Rae
December
2025
A workplan has been prepared for 12months for both PFA
and IJB and presented to both for approval.  This is a live
document that can be added to as necessary.
There has also been a series of IJB Development Sessions
scheduled for the remainder of 2025 and Q1 2026 with
specific topics allocated including Finance and Risk.
Complete 
2025/26 Financial
Sustainability
The IJB should continue to:
 Develop and refine the arrangements it has
in place for securing financial sustainability,
including its medium and long term financial
plans and savings plans. 
 Work effectively in partnership with the local
council and the health board on service
transformation. 
 Apply its reserves strategy to effectively
manage the use of reserves to supplement
savings and efficiencies when required.
Chief Finance
Officer 
Nicola Scott
Ongoing It was agreed with the Audit Director that this action will
remain ongoing as there is no end date to this.  The
management response provided and included in the Final
Audit Report was as follows: 
A financial outlook for the 3 year period has been prepared
and is being presented to Board Members on 17th September
2025.  This outlines the forecast budget gaps for the next 3
years and will lead into Board Development sessions where
savings will be discussed for approval at a later Board.   
The outlook clearly identifies the current reserves position
and the impact non achievement on savings will have on
reserves. 
Discussions have taken place with both NLC & NHSL on the
forecast position and an Elected Members briefing session
within NLC was undertaken in June this year with another
scheduled in the Autumn to ensure all relevant parties are
aware of the forecast. 
The medium term and long term outlooks will continue to be
reviewed throughout the year with budget setting for 2026/27
set for March 2026. 
Complete 
There will be
ongoing
review as part
of the annual
financial
planning
arrangements. 
Key 
Complete 
Ongoing – within projected completion timescale 
Ongoing – has exceeded projected completion date