1 
REPORT 
Item No: 5
SUBJECT: Progress Update: Development and Delivery of Chryston
Community Health Clinic
TO: Integration Joint Board Performance, Finance & Audit
Committee 
Lead Officer for
Report:
Ross McGuffie, Chief Officer NL HSCP
Author(s) of
Report 
Maggs Thomson, Head of Health
DATE: 21st February 2024 
1. PURPOSE OF REPORT
This paper is coming to the IJB PFA to provide an update on the development and
delivery of Chryston Community Health Clinic 
For approval  For endorsement  To note 
2. ROUTE TO THE BOARD
This paper has been:
Prepared By:  Reviewed By:   Endorsed By: 
Prepared by Maggs Thomson, Head of Health in consultation with both Chryston
Community Health Clinic Mobilisation Group and the Northern Corridor Service
Repatriation Group.         
3. RECOMMENDATIONS
The IJB PFA is asked to:
1) Note the active and ongoing progress with the delivery of this capital
programme.

Page 2

2 
2) Note the progress with the repatriation of the clinical services from NHS Greater
Glasgow & Clyde (NHSGG&C) and their associated Health and Social Care
Partnerships (HSCP’s)
3) Note the previously identified financial gap reported Feb 2023 and reflect on
work to date to progress towards final conclusion.  
4.  VARIATIONS TO DIRECTIONS?                  
5. BACKGROUND/SUMMARY OF KEY ISSUES
5.1 Background
5.1.1 From 1st April 2014, Health Board boundaries were realigned with those of
the Local Authorities across Scotland, with the aim of reducing administrative
barriers and ensuring full alignment with the integration of health and social
care services as set out in the Public Bodies (Joint Working) (Scotland) Act.
5.1.2 This boundary change aimed to facilitate the development of integrated
services across all areas of Scotland. The change resulted in the Northern
Corridor (covering the areas of Moodiesburn, Muirhead, Chryston, Stepps,
Gartcosh and Auchinloch) being transferred into the NHS Lanarkshire (NHSL)
boundary.
5.1.3 This geographical area has one health facility located within Muirhead
(Muirhead Clinic), which is small and at the time of transfer, dilapidated and
not fit for function. The facility required backlog maintenance and asbestos
work to be undertaken which was completed.
5.1.4 Despite the upgrade and refurbishment which improved compliance with
healthcare standards, the facility could still not support the provision of all
services for the local population.
5.1.5 Consideration was given to providing a new build facility on the existing site,
however the footprint and parking limitations would not allow for the size of
centre required to meet the clinical ask.
5.1.6 Due to the limited capacity of this facility, NHSL was unable to fully repatriate
services from NHSGG&C, resulting in northern corridor residents having to
travel significant distances across Glasgow to access some health services,
with teams and clinics based in a range of areas including Shettleston,
Kirkintilloch, Easterhouse and Bridgeton. 
5.1.7 The services identified below continue to be delivered via a Service Level
Agreement (SLA) with NHSGG&C and the associated HSCP’s.  
• Community Diabetic Service
Yes  No  N/A

Page 3

3 
• Community Mental Health Teams
• Dietetics
• Physiotherapy
• Sexual and Reproductive Health Services
• Substance Misuse  
5.1.8 An opportunity emerged with the development of North Lanarkshire Council’s
(NLC) ‘The Plan for North Lanarkshire’ which set out an ambitious estates
strategy that looked to develop Community Hubs / Campuses.  Further to
consideration of this approach, NHSL working in partnership with NLC, invited
hub South West Scotland to deliver a single campus for the replacement of
Muirhead Community Health Clinic and Chryston Primary School.
5.1.9 There was extensive engagement with all stakeholders including NLC and
NHSL project teams which resulted in the optimum design being developed to
the satisfaction of all the stakeholders. The agreed design went through wide-
ranging routes of engagement with key stakeholders including NHSL staff,
H&SCP staff, teachers, support staff and pupils at Chryston Primary School.
This process also included joint engagement with representatives of the
Parent Council and elected members, culminating in an online public
consultation to inform residents of the design outcome.
5.1.10 The business case for the Development of Chryston Community Health Clinic
was considered by the NHSL Board on December 2021 at a cost of £3.65M
and signed off with all legal agreements completed in January 2022.
5.1.11 The build programme began on Monday 14th February 2022 with a completion
date of early August 2023 identified. 
5.1.12 In tandem with the facility development, a process was initiated with NHSGG&C
(and associated H&SCP’s) to begin the process of repatriation of the identified
clinical services.
5.1.13 A Service Level Agreement (SLA) continues to be in place and as of January
2024 a notice of cessation is now formally lodged with GG&C.   This exposed
H&SCNL to a £392k financial gap if services where to be delivered with the
known funded establishment and skill mix of the NHS Lanarkshire service
model.
5.1.14  It was also recognised in February 2022 that to support the smooth transition,
clinical safety and continuity of care there would be an expectation of double
running costs for a period of 3 months, equating to an increased cost of £212k
for that quarter.
5.1.15 All work was progressed on the basis of the funding being agreed in February
2022 calculation.

Page 4

4 
Update
5.2 Chryston Community Health Clinic
5.2.1 The build programme experienced a delay and handover completed to NLC in
late September 2023.  To support school term and safe transfer of equipment
it was agreed to open the school for business on 25th October 2023 following
the mid-term break (see Appendix 1 for visual update). 
5.2.2 H&SCNL mobilisation group progressed their operational plan in line with the
school timeline and worked towards mid-November transfer of Muirhead clinic.
Unfortunately, due to some critical snagging and IT challenges this further
delayed to December 2023 with the first patient being received on the 18th. 
5.2.3 At time of reporting all Muirhead Clinic services have transferred to Chryston
Community Clinic.
5.2.4 Midwifery and CAMHS have also been supported to provide services the new
health clinic
5.2.5   The intention was to decommission Muirhead Clinic, however NHSL has offered
this accommodation to another service and the site responsibility will transfer
to SLH&SCP at the end of January 2024.  
5.3  Repatriation of Services 
5.3.1 This process has proved challenging due to build delays and agreements with
NHSGG&C resulting in the mutual agreement to repatriate services from 1st
April 2024. 
5.3.2 Finance has now been agreed and recruitment is progressing to repatriate all
services identified above (5.1.7). 
5.3.3 The finance identified from the SLA exceeds what was previously reported and
gives a level of comfort that the shortfall previously reported may be closer to a
break even.  At time of reporting this has not been confirmed, however a verbal
update will be provided.   
6. CONCLUSIONS
6.1 In conclusion, this paper confirms that Chryston Community Health Centre
has been delivered for service provision from 18th December 2023. 
6.2 All services have transferred from Muirhead Clinic and are being delivered in
Chryston Community Health Clinic with the addition of Midwifery and CAMHS

Page 5

5 
6.3     Muirhead Clinic will not be decommissioned but handed over the SLH&SCP
by 31st January 2024.
6.4 The IJB has already approved additional funding (£212K) to support double
running costs for one quarter to allow safe transition of repatriated services.
There is however some comfort that the £392K funding gap previously
identified may not be required.  The confirmed finance position will be verbally
updated when this report is presented. 
7. IMPLICATIONS 
Noted within the content of the paper
7.1 NATIONAL OUTCOMES
The repatriation of services will support improvements in a range of service
performance measures, particularly around mental health and substance
misuse. 
Link(s) to National Health and Wellbeing Outcomes
People are able to look after and improve their own health and wellbeing
and live in good health for longer 
☒
People, including those with disabilities or long-term conditions, or who are
frail, are able to live, as far as reasonable practicable, independently and at
home or in a homely setting in their community
☐
People who use Health and Social Care Services have positive
experiences of those services, and have dignity respected
☒
Health and Social Care Services are centred on helping to maintain or
improve the quality of life of people who use those services 
☐
Health and Social Care Services contribute to reducing health inequalities  ☒
People who use Health and Social Care Services are safe from harm ☐
People who work in Health and Social Care Services feel engaged with the
work they do and are supported to continuously improve the information,
support, care and treatment they provide
☒
Resources are used effectively and efficiently in the provision of Health and
Social Care Services 
☒
7.2 ASSOCIATED MEASURE(S) 
None.
7.3 FINANCIAL 
This paper has been reviewed by Finance: 
Yes   No  N/A

Page 6

6 
At this time the £212k non-recurring allocation will still be required to support
any potential double running costs.  The £392k recurring revenue gap has
been reduced with the possibility of a break-even position (yet to be
confirmed)..  Finance teams are reviewing our known position and will provide
contemporary costs by the end of February 2024. 
7.4 RISK ASSESSMENT/RISK MANAGEMENT 
Risks around the repatriation of services, including the transfer of complex
treatment packages, ongoing recruitment challenges and the funding gap
already identified and will be built into the operational risk register. 
Relevant Risk Register
Details 
Current Risk Level  Risk Owner 
Choose an item. 
7.5  ENGAGEMENT & PARTCIPATION
Please tick the engagement and participation objectives that link(s) with this
piece of work and provide further details regarding the engagement and
participation that was undertaken.
Objectives  Further Details 
☒ Involve stakeholders in the development
work aimed at achieving the national 
outcomes
There was full stakeholder
involvement at every level of the
development of this new health
clinic.  This ranged from
presentation of project, through
design development and delivery of
the facility.  There were dedicated
meetings to progress the project
and all updates were provided
locally via community board
structures.
☒ Provide stakeholders with information on
how to get involved
a/a
☒ Ensure a diverse range of engagement
and participation and opportunities are in 
place to suit different needs 
a/a
☒ Measure how well we involve community
stakeholders in the planning, design 
and delivery of our services 
a/a
☒ Provide regular feedback on how
stakeholder engagement and participation is 
shaping and influencing service
development and delivery
a/a

Page 7

7 
☒ Provide support to enable stakeholder
representatives to participate meaningfully
and confidently at meetings 
☐ Develop participation guidelines to
ensure a common understanding and set of 
expectations for both stakeholders and
partnership staff 
☐ Support engagement planning and
participation in localities, taking account of 
other engagement activity and local plans
across the Community Planning 
Partnership 
A significant programme of engagement has taken place as part of the development
of the business case. 
7.6 INEQUALITIES & FAIRER SCOTLAND DUTY 
EQIA Completed & Fairer Scotland Impact Assessment Form Completed and
attached to previous report as an appendix 
Developed as part of the business case.   
EQIA added to website: 
8. BACKGROUND PAPERS 
NHS Lanarkshire Chryston Community Health Clinic Business Case 
https://www.nhslanarkshire.scot.nhs.uk/download/2021-december-20-board-
papers/ 
9. APPENDICES 
Please include a glossary of terms if not already included. 
Yes  ☒ No ☐ N/A ☐
Yes /
Date
added 
☐ No ☐ N/A ☐

Page 8

8 
Appendix 1 Photographic views of the completed exterior and internal
reception and waiting area December 2023.   
CHIEF ACCOUNTABLE OFFICER (or Depute)   
Members seeking further information about any aspect of this report, please contact
the following; Maggs Thomson, maggs.thomson@lanarkshire.scot.nhs.uk

Page 9

9 
Direction from North Lanarkshire Integration Joint Board (IJB) 
1 Reference Number  
2 Report Title  
3 Date direction issued by IJB 
4 Date from which direction
takes effect 
5 Direction to: 
6 Does this direction
supersede, revise or revoke a
previous direction – if yes,
include reference number(s) 
7 Functions covered by
direction 
8 Full text of direction 
9 Budget allocated by
Integration Joint Board to
carry out direction 
10 Performance Management /
Governance arrangements 
11 Date direction will be
reviewed

Page 10

10 
Appendix 1 
1: Main Entrance 
2: Reception and Waiting Area