Democracy Spraffa

Agenda Document Pack - IJB Performance, Finance and Audit Committee - 20/05/2026

North Lanarkshire Council · 20 May 2026
Back to IJB Performance, Finance and Audit Committee — 20 May 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

14 May 2026 
Members of the 
IJB Performance, Finance and Audit Committee
Chief Executive’s Office
Claire Rae
Chief Officer, North Lanarkshire Integration Joint Board
Civic Centre, Windmill Street
Motherwell ML1 1AB
www.hscnl.org.uk 
Notice is given that a Meeting of the IJB Performance, Finance and Audit Committee is to
be held on MS Teams on Wednesday, 20 May 2026 at 09:30 AM which you are requested to
attend. 
The agenda of business is attached. 
Claire Rae       
Chief Officer, North Lanarkshire Integration Joint Board 
Members : 
Clerk Name: Committee Services
Clerk Telephone: 07350435308
Clerk Email: committee@northlan.gov.uk 
C Barclay, B Baudo, B Burgess, P Couser, N Dar, D Henderson, A McCrory, B Moore.  
Page 1 of 146

Page 2

Page 2 of 146

Page 3

Agenda 
1 Welcome and Apologies 
2 Declarations of Interest In Terms of the Ethical
Standards In Public Life Etc. (Scotland) Act 2000 
3 Previous Minute from the Integration Joint Board
Performance Finance & Audit of 18 February 2026
Submit Minute of Previous Meeting of Integration Joint
Board Performance, Finance & Audit  held on 18
February 2026. 
5 - 10 
4 IJB Performance, Finance & Audit Rolling Action
Log
Submit report by the Chair. 
11 - 22 
5 Matters Arising
Verbal Update by the Chair. 
Performance and Finance 
6 Financial Monitoring Report 2025-26
Submit report by the Chief Financial Officer. 
23 - 42 
7 IJB Reserves Strategy 2026-27
Submit report by the Chief Financial Officer. 
43 - 50 
8 Performance Update – 1 October 2025 to 31
December 2025 - Quarter 3 2025/2026
Submit report by the Chief Officer (Planning,
Performance & Quality Assurance). 
51 - 80  
Governance and Policy 
9 Internal Audit Progress Report 2025-26
Submit report by Chief Officer (Audit & Risk) and Chief
Internal Auditor. 
81 - 96 
10  Draft Internal Audit Plan 2026-27
Submit report by Chief Officer (Audit & Risk) and Chief
Internal Auditor. 
97 - 104 
11  Chief Finance Officer Role
Submit report by Chief Officer. 
105 - 112 
12  Annual Governance Statement – Action Plan
Progress
Submit report by Chief Financial Officer. 
113 - 124
Page 3 of 146

Page 4

13  IJB Risk Register
Submit report by the Business Support Manager. 
125 - 142 
14  IJB Performance, Finance and Audit Work Plan
Submit report by the Business Support Manager. 
143 - 146  
For Noting 
15  Risk
Consider from the business discussed any new
emerging risks to be added to the risk register or
whether the discussion materially alters the accessed
levels of risk/risk tolerance or mitigating controls. 
Page 4 of 146

Page 5

INTEGRATION JOINT BOARD (PERFORMANCE, FINANCE AND AUDIT)
COMMITTEE – WEDNESDAY, 18 FEBRUARY 2026 AT 2PM 
PRESENT 
North Lanarkshire Council
Councillors McCrory (Chair); Barclay and Baudo. 
NHS Lanarkshire
Brian Moor (Vice-Chair); Philip Couser and Siobhan White. 
ALSO PRESENT 
Heath and Social Care Partnership:
Claire Rae; Joanne Jenkins; Nicola Scott; Lucy Munro; and Kerry Taylor. 
NHS: 
Nauman Dar; Mark Dell; Jacqui Jones; Jocelyn Lyall; Maggs Thomson; and Siobhan
White. 
North Lanarkshire Council:
Diane Fraser; Francis Scott; Graeme Cowan and Clare Louise McDonald. 
Other Attendees
Eilidh Montgomery – Audit Scotland
Catherine McGinty and John Watson – Unison
Thomas Moan and David Wood – Voluntary Action North Lanarkshire 
Ann Muir – North Lanarkshire Disability Forum 
APOLOGIES 
John Boyd and Callum Green (Audit Scotland); 
Morag Dendy (NLC); 
Harry Robertson (North Lanarkshire Carers Together/Carer Representative). 
WELCOME AND APOLOGIES 
1. The Chair welcomed all attendee’s to the meeting and noted apologies. 
Decided: that apologies be noted. 
DECLARATIONS OF INTERESTS 
2. The Committee noted that there were no declarations. 
Item 3
Page 5 of 146

Page 6

MINUTE OF INTEGRATION JOINT BOARD PERFORMANCE, FINANCE AND
AUDIT COMMITTEE – 22 OCTOBER 2025 
3. There was submitted the minute of the meeting of the Integration Joint Board
Performance, Finance and Audit Committee held on 22 October 2025 for
approval. 
Decided: that the minute of the meeting of the Integration Joint Board
Performance, Finance and Audit Committee held on 22 October
2025, be approved. 
INTEGRATION JOINT BOARD PERFORMANCE, FINANCE AND AUDIT ROLLING
ACTION LOG 
4. There was submitted the rolling action log providing an update on a number of
actions arising from previous meetings. 
Decided: that the update on the rolling action log be noted. 
MATTERS ARISING 
5. The Chair sought any matters arising from the Action Log. 
Decided: that there were no matters arising from the Action Log be noted. 
FINANCIAL MONITORING REPORT 2025/26 
6. There was submitted a report by the Chief Finance Officer, Health and Social
Care Partnership: (1) summarising the financial performance of North
Lanarkshire University Health and Social Care Partnership for the period 1 April
to 30 November 2025; (2) detailing the projected outturn position for 2025/26 is
an overspend of £1.915m; (3) informing that the detail within the report is based
on the NHS Lanarkshire period 8 report, and the North Lanarkshire Council
period 9 report; and (4) highlighting the key financial pressures on the budget. 
Arising from discussion, it was agreed that more information on the health
underspend, offset by out of area and private health care etc be provided in the
next report. 
Decided: 
(1) that the projected outturn for 2025/26 with an overspend of £1.915m be
acknowledged; and 
(2) that the contents of the report be otherwise noted. 
IJB RESERVES STRATEGY 2026/27
Page 6 of 146

Page 7

7. There was submitted a report by the Chief Finance Officer, Health and Social
Care Partnership: (1) providing an update on the review of the North
Lanarkshire Integration Joint Board reserves; (2) setting out the strategic
approach, through the Reserves Strategy; (3) informing that the projected
reserves balance, as at 31 December 2025 had increased to £73.031m, arising
from a review undertaken within Health Services; (4) intimating that a final
review of the 2025/26 reserve balances, and the 2026/207 forecast would be
completed following year end closure of the 2025/26 accounts; (5) summarising
the requirement for realigning the Social Care Services reserve, to support
transparency and ensure the remaining balance is held solely for risk-based
purposes; and (6) seeking approval for the realignments, as detailed within
section 6.4 of the report and to reduce the contingency reserve from 5% to 4%. 
Decided: 
(1) that the realignments outlined in section 6.4 of the report, be approved; 
(2) that the reduction of contingency reserve to 4%, be approved; and 
(3) that the contents of the report be otherwise noted. 
PERFORMANCE REPORT UPDATE – 1 JULY TO 30 SEPTEMBER 2025
QUARTER 2 2025/26 
8. There was submitted a report by the Chief Officer (Planning, Performance and
Quality Assurance), North Lanarkshire Council: (1) setting out an overview of
performance of the Integration Joint Board for the period 1 July to 30 September
2025, Quarter 2; and (2) enclosing within the appendix to the report Areas for
Improvement. 
Arising from discussion, it was agreed that the Chair and Vice Chair write to
Alcohol Brief Interventions Services to congratulate the improvement work
undertaken, on behalf of the Board which was agreed. 
During discussion on this matter, a question was asked in which officers
committed to responding to outwith the meeting. 
“Is the issue with Alcohol Brief Interventions was a National issue, or more of a
local issue?” Brian Moore. 
Decided: that the Performance Report Update, for the period 1 July to 30
September 2025, Quarter 2 and accompanying appendix, be
noted. 
INTERNAL AUDIT PROGRESS REPORT 2024/25 AND 2025/26 
9. There was submitted a report by the Chief Finance Officer: (1) setting out
progress in respect of the Internal Audit work for 2024/25 and 2025/26; (2)
informing that the 2024/25 Internal Audit Plan had been completed; (3)
Page 7 of 146

Page 8

highlighting that the workplan had been agreed to ensure the Internal Audit Plan
2025/26 is delivered to inform the annual internal audit opinion; and (4)
enclosing within the appendices to the report the Progress Report, a Summary
of Relevant Partner Reports and the Final IJB Strategy Report. 
During discussion on this matter, a question was asked in which officers
committed to responding to outwith the meeting. 
“Regarding the Review of NHS Lanarkshire resilience and business continuity,
is there anything for implementation for IJB at this stage?” Brian Moore. 
Decided: that the Internal Audit Progress Report 2024/25 and 2025/26 be
noted. 
NORTH LANARKSHIRE INTEGRATION JOINT BOARD – DRAFT ANNUAL AUDIT
PLAN 2025/26 
10. There was submitted a report by Audit Scotland providing the draft North
Lanarkshire Integration Joint Board Annual Audit Plan 2025/26. 
Thereon, Eilidh Montgomery was heard in further explanation of the report,
highlighting that the North Lanarkshire Integration Joint Board Annual Audit
Plan 2025/26 was no longer in draft form and had now been finalised, with the
only change being the removal of the word ‘draft’. 
Decided: that the North Lanarkshire Integration Joint Board Annual Audit
Plan 2025/26 be noted. 
ANNUAL GOVERNANCE STATEMENT – ACTION PLAN PROGRESS 
11. There was submitted a report by the Chief Financial Officer: (1) outlining the
actions agreed with the External Auditor, Internal Auditor and Senior
Management Team to further develop the IJB governance framework; and (2)
summarising the Annual Governance Statement Action Plan progress. 
Thereon, the Chief Financial Officer was heard in further explanation of the
report, highlighting continuing ongoing progress to complete the actions within
the timeframe. 
Decided: that further progress reports, be presented to future meetings of
the Committee in respect of the ongoing actions, be noted. 
NORTH LANARKSHIRE INTEGRATION JOINT BOARD GOVERNANCE LOG 
12. There was submitted a report by the Business Support Manager detailing an
overview of the governance issues identified. 
Decided: 
Page 8 of 146

Page 9

(1) that further progress reports, be presented to future meetings of the
Committee in respect of the ongoing actions, be noted, and 
(2) that the contents of the report be otherwise noted. 
AUDIT SCOTLAND - COMMUNITY HEALTH & SOCIAL CARE: PERFORMANCE
REPORT 2025 
13. There was submitted a report by the Chief Officer (Planning, Performance and
Quality Assurance): (1) providing an update on the publication of Audit
Scotland’s report into Community Health and Social Care Performance 2025;
and (2) outlining the key findings along with North Lanarkshire Council’s and
Health and Social Care Partnership’s response. 
Decided: that the approach to continue to use the Audit Scotland interactive
data tool to compare performance with other areas, to understand
and explain relative performance in terms of local context,
priorities, policy and operational decisions and to analyse
performance alongside local data to support benchmarking, self
assessment and the development of improvement plans, be
endorsed. 
AUDIT SCOTLAND DELAYED DISCHARGES: A SYMPTOM OF THE
CHALLENGES FACING HEALTH AND SOCIAL CARE 
14. There was submitted a report by the Chief Officer (Planning, Performance and
Quality Assurance): (1) providing an update on the publication of Audit
Scotland’s report Delayed Discharged: A Symptom of Challenges facing Health
and Social Care; and (2) outlining the key findings along with North Lanarkshire
Council’s and Health and Social Care Partnership’s response. 
Decided: that the report be endorsed. 
NORTH LANARKSHIRE INTEGRATION JOINT BOARD PERFORMANCE,
FINANCE AND AUDIT WORK PLAN 
15. There was submitted a report by the Business Support Manager detailing the
Work Plan of the North Lanarkshire Integration Joint Board Performance,
Finance and Audit Committee. 
Decided: that the updated Work Plan of the North Lanarkshire Integration
Joint Board Performance, Finance and Audit Committee be
noted.
Page 9 of 146

Page 10

Page 10 of 146

Page 11

1 
ITEM 4 North Lanarkshire Integration Joint Board 
ROLLING ACTION LOG 
NO  DATE  ITEM
NO 
DESCRIPTION  ACTION BY  ACTION & PROGRESS  DUE DATE  COMPLETION
STATUS                         
Item 4
Page 11 of 146

Page 12

2 
CLOSED ACTIONS 
NO  DATE  ITEM
NO 
DESCRIPTION  ACTION BY  ACTION & PROGRESS  DUE DATE  COMPLETION
STATUS
1. 30/10/18 Item
11
Reserves Strategy A Kilburn  To develop a reserves strategy on receipt of national
guidance on setting minimum levels of reserves.
In the interim period a local reserves strategy will be
progressed. 
Update September 2021: The IJB Reserves Strategy
2021/2022 was approved by the IJB on 22 June
2021.  This report provided an update on the review
of the existing IJB reserves and new reserves were
established in line with planned commitments and
Scottish Government guidance. 
Update on Exit strategies to be presented to PF& A
in November 2021 
8.12.22 Update provided within report Medium to
Long Term Financial Planning. Further work being
June 2021 
November 2021 –
deferred to IJB
December 2021
Complete 
Reserve strategy
presented to IJB
PFA on 16th Nov.
Page 12 of 146

Page 13

3 
undertaken to confirm exit plans and ongoing areas
of work. 
23.3.22 – Update on Financial plan for 2022/23
presented that included update on reserves strategy
but agreed at meeting to provide further more
detailed update to include exit strategy for short term
initiatives funded from reserves and conclusion of all
other areas of reserve funding 
deferred to March
2023. 
Final version to
March IJB
alongside
updated SCP 
Added to March
23 agenda-
complete 
2.  26.5.20 Item
10 
Internal Audit
Report – Due
Diligence Review 
A Kilburn  Further update on the disaggregation of the children,
families and justice social work services budget to be
presented to the IJB.
Update September 2021: The progress in respect of
this action is regularly reported to the IJB
(Performance, Finance and Audit) Committee. 
The updated report to the IJB (Performance, Finance
and Audit) Committee on 24 August 2021 advised
that the budget disaggregation exercise has been
September/Dece
mber 2020
Deferred to March
2021 – deferred
to September
2021 – deferred
to November
2021 
Original Action
complete with
further update on
hosting
arrangements
presented to
PF&A in
November 2021.   
Page 13 of 146

Page 14

4 
concluded.  The revised IJB direction to NLC issued
on 23 March 2021 excludes the total budget transfer
in respect of Children, Families and Justice Services.   
Work is continuing to progress in respect of the
hosting arrangements for cross-cutting and support
services.  The original timeline of March 2021 has
therefore been extended to the revised timeline of
September 2021. 
The Service Level Agreement for the future hosting
arrangements and associated budgets will be
presented to the IJB following consultation and
endorsement by the NLC Adult Health and Social
Care Committee and Education and Families
Committee.  A further report will therefore be
presented to the next meeting of the IJB
(Performance, Finance and Audit) Committee on 9
November 2021. 
Update March
2022 - Further
work required to
conclude
agreements
around hosting
arrangements. 
Complete –
presented to IJB
PFA on 16th Nov 
3.  22.9.20  Item 7  Recovery Process  M Dendy  IJB to receive an update on opportunities presented
during recovery process. 
March 2021
Deferred to
September 2021
Ongoing –
delegated to
PF&A to
complete action. 
Page 14 of 146

Page 15

5 
21.9.21 – Report presented setting out proposed use
of a Change Fund. 
Progress reports on each element of the proposed
plan to be presented to the PF&A 
February 2022 – update on progress noted with
further updates to be presented 
February 2022  Ongoing 
Complete 
4.  9.12.20  Item 6
& Item
11 
Addictions
services 
M Dendy 1. An update on accommodation issues
affecting the delivery of the addiction services
was requested.   
21.9.21 – verbal update given – work ongoing to
resolve accommodation issues. 
2. Update requested on funding commitments. 
ADP strategy presented and approved at IJB on
21.9.21. Request for detail on commissioning of
services, evidence of benefits and achievements and
timelines for implementation of funding commitments
to be brought back to IJB. 
June 2021 –
deferred to
September 2021
– deferred to PFA
November 2021 –
deferred to
February 2022   
September 2021 
Complete 
Ongoing updates
on progress
scheduled into
forward plan for
PFA 
Page 15 of 146

Page 16

6 
16.2.22 PF&A – update noted at meeting with
commitment to report back on specifics and
performance objectives 
December 2021 
August 2022 
MAT standards
update given to
Feb IJB PFA 
Further update
on October PFA
agenda
5. 19/6/24 Item 6 Digital System
Transformation
M Dendy Delegate to the IJB PFA committee -To provide
the IJB PFA with additional financial
information relating to the programme 
Report provided to
IJB PFA 21st
August 2024 
Complete 
6. 19/6/24 Item 7 Mental Health &
Wellbeing Delivery
Plan
R McGuffie Shared new action plan with the group in
Sept/October 
Action Planned
shared and
stakeholder sign
off currently
underway. 
Complete 
7.  21.9.21  Item 7  Primary Care
Implementation 
Plan 
Dr L Munro  1. An update on planned engagement events
with local people on the primary care
implementation plan was requested.
Update provided and noted at March 2022
IJB 
December 2021  Complete –
update report to
16th Nov PFA 
Remove 
Page 16 of 146

Page 17

7 
21.6.22 – verbal update on progress noted 
2. Memorandum of Understanding to be shared 
Complete 
8. 22.9.20  Item 5  Mental Health
Continuing Care
Contracted Beds 
R McGuffie  Issue not progressed as planned during 2020 as
engagement process postponed due to lockdown
impact on visits to care homes. 
21.9.21 Business Case to be developed and
presented to IJB, South Lanarkshire IJB and NHSL
Board. 
22.3.22 – Update provided on progress on
engagement and development of business case 
June 2022 
September 2022 
Business case to
be presented at
IJB September
2022 
Delayed following
advice from HIS
around
engagement
standards. Final
business case to
Dec IJB. 
Approved at NL
IJB, SL IJB and
NHS Board in
December 2023.
Complete 
9. 21.9.21  Item
16 
Best Value Audit  M Dendy  An update on the Self Evaluation exercise is to be
presented to the PF&A committee. 
February 2022 –
deferred to
August 2022 as
engagement
event took place
after PF&A
meeting 
Complete  
Page 17 of 146

Page 18

8 
10.  8.12.21  Item
14
Integration review
- Chief Financial
Officer 
R McGuffie  Following approval to proceed from the IJB, reports
were to be presented to NLC and NHSL Board to
seek support for preferred option. 
16.2.22 Update on progress provided at PF&A
meeting. HR process being progressed  
21.6.22 – Update on recruitment of CFO provided 
23.3.22 – Update provided to IJB to note that HR
process has commenced and recruitment to
additional post is underway. 
March 2022 
June 2022 
Complete 
11. 22.6.22 Item 8  Financial Plan -
Provision of
smoke alarms
R McGuffie Agreed that H&SC NL funding towards provision
of smoke alarms to meet new standards
would be included within future Digital
Strategy report.
March 2023 Update provided
after year-end
figures.
Combined report
linked to
community alarms
on August PFA
agenda
Complete 
12. 22.6.22  Item 5 Unaudited
Accounts 
R McG/NL  Content of report to be amended to include more
details around reason for significant underspend 
June 2022 Report updated
accordingly.   
Complete 
13. 22.6.22 Item 8
& Item
9
Equalities
Mainstreaming 
Report & Risk
Register 
R McG/CJ  IJB members suggested additions to the IJB risk
Register on following highlighted risks; 
 Cost of Living Pressures
 Urgent/Unscheduled care 
September 2022 
Complete
Page 18 of 146

Page 19

9 
 Community Alarms (Analogue to digital) 
 National Care Service 
14. 22.6.22 Item 9  Equalities
Mainstreaming 
Report
M Dendy  Progress updates on delivery of equality outcomes to
be presented via Performance, Finance & Audit
Committee 
May 2023 On agenda
Tabled at June
PFA
15. 22.6.22 Item
12
Strategic
Commissioning
Plan 
M Dendy/T
Marshall  
Detailed report on community nursing to be brought
back to future meeting and included within SCP 
On March 23 IJb
agenda –IJB
approved plan
16.  22.6.22  Item 4 Community
Alarms
R McG Provide the committee with an update on community
alarms switching from analogue to  digital and risk to
service users 
Complete
Update provided
at 16th Nov PFA
17. 22.6.22 Item
14
Audited Accounts  R McG Bring audited accounts to Sept committee  
Complete 
19. 16.11.22 Item 5  Risk Management
Strategy
R McGuffie  Reviewing risk management strategy which will
be brought to the committee in due
course.  Reviewing a process to have
shared risks between partnerships and
acute and also review current risk register 
Update planned
for March 2023
IJB
Liaison session
planned to review 
Complete 
20 16.11.22 Item 6 Analogue to digital R McGuffie Share progress report on the work  On April 2023
agenda
Update on
October agenda 
Complete 
21. 14.2.23 Item
11
Performance
Report
R McGuffie  Bring more information on OT Paediatrics and
speech and language 
On April 2023
agenda
Complete 
Page 19 of 146

Page 20

10 
22. 14.2.23 Item
13
MH Strategy R McGuffie Consider dedicating liaison session for a more
in-depth discussion 
Discuss wider thematic work with Brian Moore 
Topic at 8th Nov
Liaison session 
Complete
23 18.10.23 Item 5  Risk Register  R McGuffie  Ross to provide briefing document to offer the
committee assurance that risk are
reviewed against other boards 
November 2023
Liaison Session
Complete 
24. 18.10.23 Item
10
Performance
Report
R McGuffie SWISS update  Future report 
Tabled @ May
PFA 
Complete
18. 31.8.22 Item 6 IJB Self-
Assessment
Report
R McGuffie Consider hosting a development session to
further explore the self-evaluation work 
Picked up at
November Liaison
Session
Complete
25.   Future Meeting C Rae Host a future meeting face to face in Chryston
hub 
19.03.2025 – March date was cancelled new date
to be re-arranged 
Dates set up for
2025 Walk rounds
Ongoing 
Complete – Chair
& Vice-Chair
invited to
Chryston visit &
dates sent of
HSCP SMT walk
rounds
26 25.09.24 Item 9  Integration Joint
Boards Finance
and Performance
Report 2024
C Rae  Ensure that their Medium-Term Financial Plans
are up to date and reflect all current known and
foreseeable costs to reflect short and longer-term
financial sustainability challenges. 
25.02.25 – Due to be discussed at the next IJB in
March
19.03.2025 Discussed on agenda 
19.03.25 
Complete 
Page 20 of 146

Page 21

11 
31. 25.02.25 Item 6 Q2 Performance
Report 
Improved communication about progress and
ensure a shared understanding of what CAMHs
services can offer. 
Complete –
updated provided
in IJB action log
33. 19.03.20
25
Item 4 Matters Arising   Learning Disability Workforce paper to be brought
to PF&A 
Complete – paper
presented to
September IJB 
34. 27.08.20
25
Item 4 Matters Arising  Tackling Poverty Team report  Complete –
added to IJB work
plan
35. 27.08.20
25
Item 4 Matters Arising  Safe Staffing report  Complete –
added to IJB work
plan
27 25.09.24 Item 9  Integration Joint
Boards Finance
and Performance
Report 2024
C Rae  Ensure that the annual budgets and proposed
savings are achievable and sustainable. The budget
process should involve collaboration and clear
conversations with IJB partners, workforce, people
who use services and other stakeholders around the
difficult choices required to achieve financial
sustainability. 
Complete – 
Added to IJB PFA
Governance Log 
28 25.09.24 Item 9  Integration Joint
Boards Finance
and Performance
Report 2024
C Rae  Work collaboratively with other IJBs and partners
to systematically share learning to identify and
develop: 
- Service redesign focused on early intervention
and prevention. 
- Approaches focused on improving the recruitment
and retention of the workforce. 
Complete – 
Added to IJB PFA
Governance Log 
29 25.09.24 Item 9  Integration Joint
Boards Finance
and Performance
Report 2024
C Rae  Work collaboratively with other IJBs and partners
to understand what data is available and how it
can be developed and used to fully understand
and improve outcomes for those using IJB
commissioned services. This should include a
consideration of gaps in data. It should also
include consideration of measures to understand 
Complete – 
Added to IJB PFA
Governance Log 
Page 21 of 146

Page 22

12 
the impact of preventative approaches.
30. 25.09.24 Item 9  Integration Joint
Boards Finance
and Performance
Report 2024
C Rae  Evaluate whether the local commissioning of care
and support services, and the contracting of these
services, adheres to the ethical commissioning
and procurement principles, improving outcomes
for people. 
Complete – 
Added to IJB PFA
Governance Log 
36. 27.08.20
25
Item 4 Matters Arising  Information request on age assessments and carers
during crisis periods 
Complete – 
Discussion at PFA
in October 2026
32. 25.02.25 Item 8 Financial
Monitoring 
Suggestion that Pharmacy Savings Approach could
be brought back to IJB to get a restock of where
things are and where they are going 
Complete – 
Added to work
plan for future
meeting
37. 27.08.20
25
Item 4 Matters Arising  Use of reserves (to be discussed under Finance)  Complete – 
Paper on agenda
for 18 Feb 2026 
Page 22 of 146

Page 23

REPORT 
Item No: 06 
1. PURPOSE OF REPORT
1.1 This paper is coming to the Performance, Finance and Audit (PFA) Committee for:  
For approval  For endorsement  For noting 
1.2 This report provides a summary of the North Lanarkshire University Health and
Social Care Partnership (the Partnership) for the period 1 April 2025 to 31
March 2026 
2. ROUTE TO THE PERFORMANCE, FINANCE AND AUDIT COMMITTEE 
2.1 This paper has been:  
Prepared By:
Chief Finance
Officer
☒ Reviewed By:
Chief Officer
☒ Endorsed By: ☐  
3.       RECOMMENDATIONS
3.1  It is recommended that the PFA Committee: 
(1) Acknowledge the contents of the report.
(2) Acknowledge the outturn for 2025/26 is a £30.511m underspend before the
removal of £26.769m earmarked and ringfenced balances resulting in an
underspend of £3.742m. 
4. VARIATIONS TO DIRECTIONS 
5. BACKGROUND
5.1 In line with the integration scheme, North Lanarkshire IJB directs budget back to
North Lanarkshire Council (NLC) and NHS Lanarkshire (NHSL), the partner
organisations, who provide the associated services.  
5.2 Direction Letters were approved by the IJB and issued to both NLC and NHSL in
March 2025 to direct them to carry out the integrated functions delegated to the IJB
and to confirm the resources to be allocated for the resultant services in the
forthcoming year.1  As detailed within these, the focus for the year ahead will be on
the implementation of the programme of work for the IJB’s Strategic Commissioning
Plan 2023-26. 
1 IJB Directions Letters
SUBJECT: Financial Monitoring Report 2025/26
TO: Performance, Finance and Audit Committee
Lead Officer for Report: Chief Officer
Author(s) of Report Chief Finance Officer 
DATE: 20 May 2026
Yes  No  N/A 
Item 6
Page 23 of 146

Page 24

5.3 Both Partners provide the required information on operational budget performance
from their respective financial systems.  This information is then consolidated to
provide reports to the Board on delegated health and social care services.  Budget
monitoring is undertaken by the finance teams within NLC and NHSL, overseen by
the Chief Finance Officer.
6. 2025/26 BUDGET
6.1 The Medium Term Financial Plan (MTFP) for 2025/26 to 2027/28 was approved in
March 2025 which identified a 3 year budget gap for the Partnership of £51.854m,
of which £14.959m relates to 2025/26.  The budget for the Partnership this year is
£867.391m as detailed in Appendix 1.  
6.2 Throughout the year, adjustments are made to the original budget due to additional
budget allocations and budget transfers.  Appendix 2 provides a reconciliation of the
budget adjustments applied to date.  
7. 2025/26 FINANCIAL PERFORMANCE
7.1 The report uses outturn figures from NHSL and NLC. Although further movement is
not expected, final adjustments may arise during year‑end close. As detailed in
Table 1, the outturn position, prior to removal of ring-fenced / ear marked balances,
is an underspend of £30.511m.   
Table 1 
7.2 The majority of ring‑fenced and earmarked reserves are held within Health Services,
reflecting funding received for commitments extending into 2026/27 as directed by
NHSL and the Scottish Government. Key balances include £8.9m for ligature works,
£2.0m of Marmot funding, £9.5m for unscheduled care, and £1.2m for medicines
growth. These balances will be transferred to reserves and reflected in the opening
balances within the separate Reserves Strategy report.
7.3 Excluding these balances, the IJB’s operating outturn represents an underspend of
£3.742m. This variance reflects an underspend of £3.297m within services
delegated to Health and £0.445m within services delegated to Social Care. Further
detail is provided in Appendix 3.
7.4 An explanation of the significant projected variances within these delegated services
are provided below: 
7.4.1 Employee Costs (Pays) 
There is an underspend in this area of £3.688m.  Recruitment and retention
pressures continue across services, with a number of roles proving difficult to fill due
to skills shortages and competition from other sectors. Section 10 outlines current
vacancy levels and the resulting impact on agency, bank, and overtime expenditure. 
£m £m £m £m £m £m £m
Health Care Services 631.633 -2.528 629.105 599.528 29.577 (26.280) 3.297
Social Care Services 279.068 -2.157 276.911 275.976 0.934 (0.489) 0.445
TOTAL 910.701 -4.685 906.016 875.504 30.511 (26.769) 3.742
Less Ring-
Fenced / Ear
Marked
Underspend                     
Revised Year
End Variance
2024/25                   
Annual
Budget
2025/26Care Group
Projected Year
End Variance
2025/26
Projected Year
End Spend         
2025/26
In Year
Drawdown
From
Reserves
Revised
Budget
2025/26
Page 24 of 146

Page 25

Social Care Services 
7.4.2 Excluding employee costs reported in section 7.2.1, the services delegated to Social
Care are reporting a net overspend of £2.354m, which is represented by
underspends within property costs, transport costs and supplies and services offset
by overspends within admin costs and payment to other bodies (PTOB).  
7.4.3 Expenditure within PTOB is predominantly associated with Care at Home and
Independent Care Homes. The MTFP incorporated £7.548m of savings for 2025/26;
the overspend reflects the shortfall in delivery against these targets. Further
information is set out in Section 9.
7.4.4 The projections for independent care homes and care at home provision are
demand led and the final position on these is as follows:
 Independent care homes have a yearly budget to fund 1,344 care plans however
the actual care plans in place at the close of the year was 1,427 resulting in an
overspend of £2.660m.
 Care at Home costs had an outturn overspend of £0.852m, the budget is based
on funding 2,514 care plans however the actual plans in place were 2,880. 
Health Services
7.4.5 Excluding the ring fenced and ear marked balances, non pay costs are reporting a
year end underspend of £0.470m.   
7.4.6 Prescribing recorded an overspend of £4.757m in 2024/25. In recognition of ongoing
pressures and anticipated growth, the budget was increased by £12.350m, resulting
in a marginal underspend of £0.014m in the current year. Based on data to January
2026, with estimates for February and March, the average cost per item has risen
to £10.31 (from £10.22), alongside a 1.24% increase in items dispensed compared
to the same period last year.
7.4.6 Hosted Services led by North Lanarkshire IJB have reported an overall underspend
of £3.603m.  There are a number of offsetting variances across this area however
the most significant underspends are within Speech & Language Therapy, CAMHS,
Forensic Psychiatry and Psychological Therapies which are partially offset by
overspends in Family Nurse Partnership, Learning Disability Services and Adult
Psychiatry. 
Primary Care Improvement Fund
7.4.7 Previous reports advised of a projected overspend on the Primary Care
Improvement Fund, hosted by South IJB. The final position is an overspend of
£0.484m; however, in line with the treatment of all hosted services, the lead IJB
manages any overspends and retains any underspends. There is therefore no
financial impact on North IJB.
8. GENERAL RESERVES
8.1 Maintaining adequate reserves remains fundamental to the IJB’s long‑term financial
resilience, ensuring capacity to respond to unforeseen pressures. This reflects
statutory requirements and supports the broader framework for prudent financial
management within section 106 bodies.
8.2 The opening reserve balance for 2025/26 was £75.554m. Following in‑year
drawdowns, the revised balance is £70.869m, as summarised in Table 2. 
Page 25 of 146

Page 26

Table 2 
8.3 A detailed list of all reserve movements during 2025/26 is detailed in appendix 5. 
9. SAVINGS
9.1 As detailed in section 6, the MTFP identified a budget gap for 2025/26 of £14.959m
and the response to this was to develop service redesign and transformation
actions.
9.2 These are summarised in Table 3.    
Table 3 
9.3 Savings are monitored monthly at the Senior Management Team Finance meeting. 
Progress is provided by the Senior Management Team on actions being taken
against the service transformation work.  This includes an update on the following
work streams:  
 A poly pharmacy review
 A review of non pay budgets
 The roll out of “Getting it Right for Everyone”
 Updates on the financial planning assumptions
 Review of all vacant posts. 
Opening
Balance As At
Revised Balance
As At
1st April 2025 31st March 2026
£m £m £m £m
NHSL Ring-Fenced Reserves 14.839 0.000 (0.607) 14.232
NLC/NHSL Earmarked Reserves 25.060 0.267 (3.701) 21.626
NLC/NHSL Risk-Based Reserves 21.536 (0.267) (0.377) 20.892
NHSL Contingency Reserves 14.119 0.000 0.000 14.119
NLC/NHSL Closed Reserves 0.000 0.000 0.000 0.000
75.554 0.000 (4.685) 70.869Total
LEAD SUMMARY
Transfers
To / From
Reserves
Drawdown
from
Reserves
£m
Social Care Services 10.386
Home Support 2.838
Independent Care Homes 4.710
Care at Home 2.838
Health Care Services 4.573
Budget Management Non Pays 0.247
Prescribing 4.326
TOTAL 14.959
SERVICE REDESIGN & TRANSFORMATION
Page 26 of 146

Page 27

9.4 The year end IJB savings position, show total savings achieved of £9.107m (61%). 
This is summarised in chart 1 with more detail provided at Appendix 6.
Chart 1 
10. VACANCY POSITION 2025/26
10.1 Table 4 shows the full time equivalent (FTE) vacancy numbers at 30 November
2025 within each service compared against their budgeted establishment. 
Table 4 
10.2 To help cover the vacant posts throughout the year, agency staff, bankaide,
overtime and excess part time hours are used, the cost of which is included within
the financial position reported.  A detailed analysis of these costs is at appendix 7
and summarised in Table 5. 
Establishment Actual Vacancies
FTE FTE FTE
North West Locality 384.82 360.78 24.04
North East Locality 322.37 294.20 28.17
Adult Services 294.41 267.90 26.51
Children Services 590.61 561.01 29.60
Mental Health 1,208.14 1,277.00 -68.86
Social Care Services 959.34 823.55 135.79
Home Support 971.07 901.13 69.94
Other 207.23 209.58 -2.35
TOTAL 4,937.99 4,695.15 242.84
Position as at 31 March
Service
Page 27 of 146

Page 28

Table 5 
11.  IMPLICATIONS
11.1 NATIONAL OUTCOMES 
People are able to look after and improve their own health and wellbeing
and live in good health for longer 
☐
People, including those with disabilities or long-term conditions, or who are
frail, are able to live, as far as reasonably practicable, independently and at
home or in a homely setting in their community
☐
People who use Health and Social Care Services have positive
experiences of those services, and have dignity respected
☐
Health and Social Care Services are centred on helping to maintain or
improve the quality of life of people who use those services 
☐
Health and Social Care Services contribute to reducing health inequalities  ☐
People who use Health and Social Care Services are safe from harm ☐
People who work in Health and Social Care Services feel engaged with the
work they do and are supported to continuously improve the information,
support, care, and treatment they provide
☐
Resources are used effectively and efficiently in the provision of Health and
Social Care Services 
☒
11.2 ASSOCIATED MEASURE(S) 
Each partner is required to remain within their approved budgetary provision.  
11.3 FINANCIAL 
This paper has been reviewed by Finance:
Yes  No  N/A 
11.4 RISK ASSESSMENT/RISK MANAGEMENT 
The strategic financial risks detailed in the IJB Risk Register has been updated
where necessary and are included in a separate report to the IJB. 
Overtime                            Excess Part
Time Bankaide  Agency   TOTAL
£m £m £m £m £m
North West Locality 0.038 0.027 0.820 0.006 0.891
North East Locality 0.014 0.011 0.460 0.000 0.485
Adult Services 0.043 0.106 0.358 0.000 0.507
Children Services 0.094 0.088 0.912 0.185 1.278
Mental Health 0.322 0.071 5.118 4.188 9.700
Social Care Services 0.878 - - 0.046 0.924
Home Support 3.819 - - - 3.819
Other 0.009 0.014 0.071 - 0.094
TOTAL 5.217 0.317 7.738 4.424 17.697
SERVICE
Costs as at 31 March 2026
Page 28 of 146

Page 29

Relevant Risk Register Details   Current Risk Level   Risk Owner  
Financial Sustainability – Short Term  High  Nicola Scott 
Financial Sustainability – Medium Term  Very High  Nicola Scott 
Financial Sustainability – LongTerm  Very High  Nicola Scott 
Governance Failure  High  Nicola Scott 
Failure to meet Legislative
Requirements 
High  Pauline Izat / Morag
Dendy / Joanne
Jenkins 
11.5 ENGAGEMENT & PARTICIPATION
Please tick the engagement and participation objectives that link(s) with this piece
of work and provide further details on the engagement and participation that was
undertaken.
Objectives  Further details 
☒ Involve stakeholders in the development
work aimed at achieving the national 
outcomes
The Director of Finance of NHSL
and the Chief Officer (Finance)
within NLC both continue to be
consulted on the financial position
of the NL IJB.
☐ Provide stakeholders with information on
how to get involved 
☐ Ensure a diverse range of engagement
and participation and opportunities are in 
place to suit different needs 
☐ Measure how well we involve community
stakeholders in the planning, design, and
delivery of our services 
☒ Provide regular feedback on how
stakeholder engagement and participation is
shaping and influencing service
development and delivery
Financial information is shared with
stakeholders on a regular basis and
is provided to the PFA and IJB on a
quarterly basis.
☒ Provide support to enable stakeholder
representatives to participate meaningfully
and confidently at meetings 
☐ Develop participation guidelines to ensure
a common understanding and set of 
expectations for both stakeholders and
partnership staff 
☒ Support engagement planning and
participation in localities, taking account of 
other engagement activity and local plans
across the Community Planning 
Partnership
IJB Financial Plan and Reserves
Strategy aligns and supports the
IJB Strategic Commissioning Plan
to ensure robust financial
monitoring and scrutiny.
11.6  INEQUALITIES & FAIRER SCOTLAND DUTY
Equality and Diversity Impact Assessment Completed & Fairer Scotland Impact
Assessment Form Completed and EQIA added to website:
Yes  No  N/A  Page 29 of 146

Page 30

12. BACKGROUND PAPERS 
None. 
13. APPENDICES 
Appendix 1   North Lanarkshire IJB Annual Budget 2025/26 
Appendix 2   IJB Budget Reconciliation 2025/26
Appendix 3  North Lanarkshire Revenue Budget Position to 31 March
2026
Appendix 4.1  Hosted Services led by North Partnership to 31 March 2026
Appendix 4.2 Hosted Services led by South Partnership to 31 March 2026
Appendix 5 Movement in Reserves 2025/26
Appendix 6 Savings Progress to 31 March 2026
Appendix 7   Analysis of Additional Employee Costs 2025/26     
Chief Finance Officer   
Members seeking further information about any aspect of this report, please contact
Nicola Scott on telephone number 07816 126362. 
Page 30 of 146

Page 31

Appendix 1 
North Lanarkshire IJB Annual Budget 2025/26
Annual
Budget
2025/26
£m
Health Care Services
Health Care 334.893
Hosted Services 216.815
Set-Aside Budget 77.397
Total Expenditure - NHSL 629.105
Social Care Services
Social Care Services Gross Expenditure 280.206
Social Care Services Gross Income (5.869)
Social Care Services Net Expenditure 274.337
Housing Revenue Account 2.573
Social Care, Housing and Transport Services Net Expenditure 276.911
Total Expenditure - NHSL and NLC 906.016
Annual Budget
2025/26
£m
NHS Lanarkshire Funding (624.420)
Social Care Funding (24.119)
Resource Transfer (24.690)
Commissioned Services (7.226)
Transfer from Reserves (Approved) (2.528)
Total Funding - NHSL (682.983)
NLC Funding - Social Care Services (218.302)
NLC Funding - Housing Services (2.573)
Transfer from Reserves (Approved) (2.157)
Total Funding - NLC (223.033)
Total Funding - NHSL and NLC (906.016)
Care Group
Funded By:
Page 31 of 146

Page 32

Appendix 2
North Lanarkshire IJB Budget Reconciliation 2025/26
2025/26NHSL Financial Allocation to North Lanarkshire HSCP £m 2025/26 NLC Financial Allocation to North Lanarkshire HSCP £m
2025/26 North Lanarkshire HSCP Financial Allocation 274.566 2025/26 North Lanarkshire HSCP Financial Allocation 217.358
2025/26 Area Wide 8.021 NLC Funding - Housing Services 2.573
2025/26 Prescribing 86.525 NLC Financial Allocation at 20 June 2025 219.931
Set-Aside Budget 77.397 Additional NLC Conttribution - Pay Award 1.061
South Hosted @ 52% 43.332 NLC Financial Allocation at 30 January 2026 220.992
Family Health Service South @ 52% 136.482 Reduction for IFRS Adjustment -0.116
NHSL Financial Allocation at 31 May 2025 626.323 NLC Financial Allocation at 31 March 2026 220.876
NHSL Financial Allocation at 30 June 2025 639.102
NHSL Financial Allocation at 31 July 2025 642.015
NHSL Financial Allocation at 31 August 2025 640.805
NHSL Financial Allocation at 30 September 2025 646.681
NHSL Financial Allocation at 31 October 2025 646.730
NHSL Financial Allocation at 30 November 2025 647.461
NHSL Financial Allocation at 31 December 2025 653.276
NHSL Financial Allocation at 31 January 2026 654.837
NHSL Financial Allocation at 28 February 2026 667.314
Budget Adjustments Posted in Month 12
IJB Reserves North 0.079
North Income 0.767
Allocations 12.440
Financia MGT 2.548
Area Wide 1.054
Prescribing -0.145
South Hosted Serv 52% 0.321
FHS 0.761
NHSL Financial Allocation at 31 MARCH 2026 685.139
Page 32 of 146

Page 33

Appendix 3
North Lanarkshire IJB Revenue Budget Position 1 April 2025 to 31 March 2026
Annual
Year To Date
Variance
Budget Budget Actual Total
2025/26 March 2026 March 2026 March 2026
£m £m £m £m
Health Care Services
Locality and Other Services 88.010 88.010 63.073 24.937
Addiction Services 4.460 4.460 4.010 0.450
Medical and Nursing Directorate 4.018 4.018 3.957 0.061
Prescribing 81.000 81.000 80.986 0.014
Out of Area Services 1.723 1.723 1.606 0.116
Area Wide Services 10.065 10.065 9.671 0.394
Family Health Services 145.617 145.617 145.617 0.000
Hosted Services 216.815 216.815 213.211 3.604
Set-Aside Budget 77.397 77.397 77.397 0.000
Total Expenditure - NHSL 629.105 629.105 599.528 29.577
Social Care Services
Social Care Services Gross Expenditure 280.206 280.206 281.834 (1.628)
Social Care Services Gross Income (5.869) (5.869) (8.295) 2.427
Social Care Services Net Expenditure 274.337 274.337 273.539 0.799
Housing Revenue Account 2.573 2.573 2.438 0.136
Social Care, Housing and Transport Services Net Expenditure 276.911 276.911 275.976 0.934
Total Expenditure - NHSL and NLC 906.016 906.016 875.505 30.511
Care Group
Year To Date
Page 33 of 146

Page 34

Appendix 4.1
HOSTED SERVICES
March 2026 March 2026 March 2026 March 2026 March 2026 March 2026
Budget Actual Variance Budget Actual Variance
£m £m £m £m £m £m £m
Sexual Health Services 3.833 1.993 1.848 0.145 1.840 1.840 0.000
Continence Services 3.292 1.712 1.691 0.021 1.580 1.580 0.000
Immunisation Services 5.425 2.821 2.970 (0.149) 2.604 2.604 0.000
Speech and Language Therapy Services 7.464 3.881 3.559 0.323 3.583 3.583 0.000
Children and Adolescents Mental Health Services 16.267 8.459 6.011 2.448 7.808 7.808 0.000
Childrens Services 17.155 8.921 8.893 0.028 8.235 8.235 0.000
Integrated Equipment and Adaptations Store 0.567 0.295 0.523 (0.228) 0.272 0.272 0.000
Dietetics Services 4.811 2.502 2.505 (0.003) 2.309 2.309 0.000
Podiatry Services 4.968 2.583 2.246 0.338 2.385 2.385 0.000
Prisoner Healthcare Services 2.579 1.341 1.094 0.247 1.238 1.238 0.000
Blood Borne Viruses Services 1.843 0.958 0.881 0.077 0.885 0.885 0.000
Hospital at Home 3.373 1.754 1.918 (0.164) 1.619 1.619 0.000
Mental Health and Learning Disability Services 97.921 50.919 50.397 0.521 47.002 47.002 0.000
TOTAL 169.498 88.139 84.535 3.604 81.359 81.359 0.000
Outturn
North Lanarkshire IJB - 52% Share South Lanarkshire IJB - 48% Share
Led by the North Partnership
Annual
Budget
2025/26
Outturn
Page 34 of 146

Page 35

Appendix 4.2
HOSTED SERVICES
March  2026 March  2026 March  2026 March  2026 March  2026 March  2026
Budget Actual Variance Budget Actual Variance
£m £m £m £m £m £m £m
Community Dental Services 8.780 4.108 4.108 0.000 3.792 3.594 0.199
Brain Injury Unit 2.685 1.280 1.280 0.000 1.182 1.172 0.010
Out of Hours Services 10.872 5.141 5.141 0.000 4.745 4.698 0.048
Palliative Care Services 10.739 4.887 4.887 0.000 4.511 4.490 0.021
Physiotherapy Services 12.600 5.894 5.894 0.000 5.440 5.367 0.074
Primary Care Services 0.967 0.458 0.458 0.000 0.422 0.276 0.146
South Improving Cancer Journey 0.410 0.198 0.198 0.000 0.183 0.306 (0.124)
Occupational Therapy Services 10.616 4.738 4.738 0.000 4.373 4.068 0.306
Diabetic Services 7.135 3.107 3.107 0.000 2.868 3.327 (0.459)
Primary Care Improvement Fund 26.189 13.618 13.618 0.000 12.571 13.055 (0.484)
Primary Care Transformation Fund 0.000 0.000 0.000 0.000 0.000 0.000
TOTAL 90.994 43.429 43.429 0.000 40.088 40.352 (0.264)
North Lanarkshire IJB - 52% Share South Lanarkshire IJB - 48% Share
Led by the South Partnership
Annual
Budget
2025/26
Outturn Outturn
Page 35 of 146

Page 36

Appendix 5
MOVEMENT IN RESERVES 
Opening
Balance as at
Revised Balance
as at
1st April 2025 31st March 2026
£m £m £m £m £m
NHSL Alcohol and Drug Partnership Funding 3.681 3.681 0.000 2024/25 2024/25
NHSL Area Wide Services - Refugees and Displaced Persons 0.123 (0.002) 0.121 (0.002) 2024/25 2025/26
NHSL Blood-Borne Viruses Services 0.318 0.000 0.318 0.000 2023/24 26/27 proposed reduction
NHSL Community Living Change Fund 0.055 (0.011) 0.044 (0.011) 2023/24 2025/26
NHSL District Nursing 0.373 0.373 0.000 2024/25 2024/25
NHSL Hospital at Home Services 0.915 (0.102) 0.813 (0.102) 2024/25 2025/26
NHSL Learning Disabilities Health Checks 0.491 0.491 0.000 2022/23 Noy yet utilised
NHSL Long Covid Pathways 0.289 (0.289) 0.000 (0.289) 2023/24 2025/26
NHSL Mental Health Action 15 0.730 0.730 0.000 2023/24 2024/25
NHSL Mental Health Diagnostic Support Service Dementia Post 1.057 1.057 0.000 2024/25 2024/25
NHSL Mental Health Digital Therapy Post 0.221 (0.000) 0.221 (0.000) 2024/25 2024/25
NHSL Mental Health Distress Brief Intervention 2.704 2.704 0.000 2024/25 2024/25
NHSL North Planning Band 2-4 Posts & Multi-Disciplinary Teams 2.719 (0.023) 2.696 (0.023) 2024/25 2025/26
NHSL Pharmacy Mental Health Recovery & NES Training 0.800 (0.629) (0.171) 0.000 (0.800) 2024/25 2025/26
NHSL School Nursing 0.274 0.629 0.903 0.629 2024/25 2024/25
NHSL Third Sector Initiatives To Improve Health 0.075 0.075 0.000 2024/25 2024/25
NHSL Upper GI Dietetics Band 4 0.014 (0.008) 0.006 (0.008) 2024/25 2025/26
14.839 0.000 0.607 14.232 0.607TOTAL RING-FENCED RESERVES
LEAD RING-FENCED RESERVES
Transfers
To / From
Reserves
Drawdown
from
Reserves
Movement in
Reserves
2025/26
Financial
Year Reserve
Established
Financial Year
Reserve Last
Utlised
Page 36 of 146

Page 37

Appendix 5 (Contd) 
Opening
Balance as at
Revised Balance
as at
1st April 2025 31st March 2026
£m £m £m £m £m
NHSL MH Funding 1.500 1.500 0.000 2025/26 Noy yet utilised
NHSL Children and Adolescent Mental Health Services 2.774 0.000 2.774 0.000 2022/23 26/27 proposed reduction
NHSL Frailty Nursing 1.715 (1.714) 0.001 (1.714) 2023/24 2025/26
NHSL Unscheduled Care Funding 2.790 2.790 0.000 2023/24 2023/24
NHSL Mental Health Recovery Renewal - Facilities Projects 1.029 1.029 0.000 2022/23 2023/24
NHSL Adult Social Care Winter Preparedness Fund 1.000 1.000 0.000 2022/23 2023/24
NHSL Staff Wellbeing 0.254 0.000 0.254 0.000 2022/23 Noy yet utilised
NHSL Minor Capital Works 1.027 (0.079) 0.948 (0.079) 2022/23 2025/26
NHSL Children and Adolescent Mental Health Services - Udston Top Up Funding 0.268 0.268 0.000 2024/25 2024/25
NHSL Development of Chryston Community Health Clinic 0.212 0.212 0.000 2023/24 26/27 proposed reduction
NHSL Kylepark Works 0.134 0.134 0.000 2023/24 Proposed Closure
NHSL HR Employability Team (2 year funding, 50:50 split between North and
South)
0.087 0.087 0.000 2024/25 Proposed Closure
NHSL Breast Feeding Team (2 year funding) 0.345 0.000 0.345 0.000 2023/24 26/27 proposed reduction
NHSL Dietetics Services - Double Running Costs 0.055 0.055 0.000 2022/23 2024/25
NHSL Health Inequalities - Screening 0.016 (0.016) 0.000 (0.016) 2021/22 2025/26
NHSL Health Visiting Students/Trainees 0.029 0.029 0.000 2023/24 2024/25
NHSL Mental Health Wards Window Replacement 0.650 0.650 0.000 2022/23 Noy yet utilised
NHSL Neonatal & Paediatrics Dieteics Intervention (3 year funding) 0.293 (0.099) 0.194 (0.099) 2023/24 2025/26
NHSL Paediatric Diabetes Insulin Pumps and Additional Staff 0.538 (0.009) 0.529 (0.009) 2022/23 2025/26
NHSL Podiatry Services - Foot Screening 0.342 (0.004) 0.338 (0.004) 2022/23 2025/26
NHSL Scottish Clinical Leadership Fellowship 0.060 0.000 0.060 0.000 2022/23 2023/24
NHSL Sexual Health Services - Long-Acting Reversible Contraception (LARC) 0.297 0.297 0.000 2019/20 26/27 proposed reduction
Financial Year
Reserve Last
Utlised
LEAD EARMARKED RESERVES
Transfers
To / From
Reserves
Drawdown
from
Reserves
Movement in
Reserves
2025/26
Financial
Year Reserve
Established
Page 37 of 146

Page 38

Appendix 5 (Contd) 
NHSL Staff Training Academy 0.335 0.000 0.335 0.000 2023/24 26/27 proposed reduction
NHSL Vulnerable and Complex Cases - Test of Change 0.501 0.000 0.501 0.000 2023/24 26/27 proposed reduction
NLC Business Case - Non-Recurring NLC Costs 0.309 0.065 (0.352) 0.022 (0.287) 2022/23 2025/26
NLC Carers Act 2018 - Support 2.604 (0.182) 2.422 (0.182) 2022/23 2025/26
NLC Digital and IT Strategy Technology Improvements - Community Alarms 0.230 (0.119) 0.111 (0.119) 2022/23 2025/26
NLC Digital and IT Strategy Technology Improvements - Home Support
Scheduling System
3.332 (0.287) 3.045 (0.287) 2022/23 2025/26
NLC Digital and IT Strategy Technology Improvements - SWIS 0.084 (0.084) 0.000 (0.084) 2022/23 2025/26
NLC Home Support Resilience (2 year funding) 0.577 (0.090) 0.487 (0.090) 2023/24 2025/26
NLC IJB Helpline (2 years funding) 0.137 (0.137) 0.000 (0.137) 2022/23 2025/26
NLC Mental Health Social Workers 2 x NL10 x 24 months 0.149 0.000 0.149 0.000 2022/23 2024/25
NLC Staff Training Academy 0.704 (0.278) 0.426 (0.278) 2022/23 2025/26
NLC MHO Capacity Funding 0.388 (0.097) 0.291 (0.097) 2025/26 2025/26
NLC Statutory Appropriate Adults 0.161 0.000 0.161 0.000 2025/26 Noy yet utilised
NLC Participation & Engagement Locality 0.006 (0.006) 0.000 (0.006) 2025/26 2025/26
NLC Sessional - School summer placements 0.128 0.202 (0.148) 0.182 0.054 2025/26 2025/26
25.060 0.267 (3.701) 21.626 (3.434)TOTAL EARMARKED RESERVES
Page 38 of 146

Page 39

Appendix 5 (Contd) 
Opening
Balance as at
Revised Balance
as at
1st April 2025 31st March 2026
£m £m £m £m £m
NHSL Prescribing Fund 5.066 5.066 0.000 2017/18 Noy yet utilised
NLC Social Care Demand 16.470 (0.267) (0.377) 15.826 (0.644) 2021/22 2025/26
21.536 (0.267) (0.377) 20.892 (0.644)
Opening
Balance as at
Revised Balance
as at
1st April 2025 31st March 2026
£m £m £m £m £m
NHSL Contingency Balance Held By NHSL 14.119 (0.000) 14.119 0 2022/23 Noy yet utilised
14.119 0.000 (0.000) 14.119 0
75.554 0.000 (4.685) 70.869 (4.685)
TOTAL CONTINGENCY FUND RESERVES
TOTAL RESERVES
LEAD CONTINGENCY FUND RESERVES
Transfers
To / From
Reserves
Drawdown
from
Reserves
Movement in
Reserves
2025/26
Financial
Year Reserve
Established
Financial Year
Reserve Last
Utlised
Financial
Year Reserve
Established
Financial Year
Reserve Last
Utlised
TOTAL RISK-BASED RESERVES
LEAD RISK-BASED RESERVES
Transfers
To / From
Reserves
Drawdown
from
Reserves
Movement in
Reserves
2025/26
Page 39 of 146

Page 40

Appendix 6
Description of Approved Saving Target Value
Achieved to
Date
Savings
Gap Description Value Budget Gap Commentary RAG Status
£m £m £m £m £m
Home Support
Home Support re-design which will include the introduction of the dynamic scheduling tool to support the
process of streamlining shift patterns alongside service provision. The re-design will further develop the
enabling approach as the operating model.
2.838 0.224 2.614 - 0 2.614
Independent Care Homes
Focus the strategic direction to reduce both the length of stay in care homes and the number of people
being placed.
4.71 2.049 2.661 - 0 2.661
Care at Home
A review of the guided self-assessment process to align with a more strategic assessment and planning
practice.
2.838 2.247 0.591 - 0 0.591
TOTAL SOCIAL CARE SERVICES 10.386 4.52 5.866 0 5.866
Budget Management Non Pays
A review of budget lines including (but not limited to) travel, training and printing costs. 0.247 0.246 0.001 - 0 0.001
Prescribing
A review of prescribing will be undertaken with a 5% savings target being applied. 4.326 4.341 -0.015 - 0 -0.015
TOTAL HEALTH CARE SERVICES 4.573 4.587 -0.014 0 -0.014
TOTAL HEALTH & SOCIAL CARE PARTNERSHIP 14.959 9.107 5.852 0 5.852
RAG Status Key
Saving achieved
Saving partially achieved and has reached expected year to date target
Saving not achieved to date
HEALTH CARE SERVICES
Any year end
shortfall in
savings will be
met from
reserves.
Approved Savings Replacement Saving / Funding Source
SOCIAL CARE SERVICES
Any year end
shortfall in
savings will be
met from
reserves
Page 40 of 146

Page 41

Appendix 7 
Analysis of Additional Employee Costs 2025/26
North West
Locality                           
£
North East
Locality                        
£
Adult
Services                 
£
Children
Services            
£
Mental
Health                 
£
Other           
£
TOTAL       
£
1 72,607 48,337 22,545 90,803 384,899 3,492 622,683
2 71,418 41,152 29,022 80,792 379,200 7,439 609,024
3 77,695 42,872 20,265 77,774 415,502 7,207 641,315
4 81,834 58,168 38,071 59,872 461,851 7,115 706,911
5 71,192 47,421 34,659 47,566 467,144 7,003 674,985
6 72,699 39,771 27,262 77,790 449,717 3,924 671,163
7 65,717 44,422 37,135 75,456 427,579 4,702 655,010
8 64,068 40,948 42,731 74,818 425,132 4,660 652,357
9 65,107 44,527 33,415 90,786 395,917 7,466 637,218
10 40,866 24,562 36,474 69,457 438,949 6,943 617,251
11 62,528 4,960 22,228 74,613 353,269 5,420 523,018
12 74,096 22,630 14,203 92,115 519,218 5,232 727,493
TOTAL       819,827      459,769      358,011    911,841     5,118,377      70,604  7,738,429
North West
Locality                         
£
North East
Locality                        
£
Adult
Services             
£
Children
Services               
£
Mental
Health                 
£
Social
Care
Services                 
£
TOTAL      
£
1 0 0 0 26,054 303,197 -52,687 276,564
2 0 0 0 20,182 373,625 52,462 446,269
3 475 0 0 18,789 383,482 0 402,746
4 477 0 0 22,984 319,872 0 343,333
5 235 0 0 5,668 330,604 28,875 365,382
6 476 0 0 4,671 453,163 25,082 483,392
7 479 0 0 22,128 293,388 0 315,995
8 479 0 0 -8,620 403,019 0 394,878
9 0 0 0 6,608 367,934 0 374,543
10 1,074 0 0 3,355 264,358 0 268,788
11 479 0 0 19,814 310,844 3,717 334,854
12 1,348 0 0 43,205 384,382 9,903 438,838
13 -21,486 -21,486
TOTAL           5,522               -                 -      184,838     4,187,869      45,866  4,424,095
North West
Locality                         
£
North East
Locality                        
£
Adult
Services             
£
Children
Services               
£
Mental
Health                 
£
Social
Care
Services                 
£
Home
Support     
£
Other           
£
TOTAL        
£
1 3,378 3,213 6,503 3,183 32,198 -18,944 -68,736 2,540 -36,666
2 4,489 1,471 2,956 1,922 20,113 50,355 342,967 694 424,967
3 4,835 1,466 5,689 3,419 22,245 55,865 306,838 625 400,982
4 4,960 1,535 4,862 3,466 22,181 52,258 310,071 696 400,029
5 2,591 1,056 3,022 1,451 35,317 61,502 299,004 451 404,394
6 1,793 2,447 4,268 1,908 26,013 59,997 334,742 731 431,899
7 2,982 1,099 4,093 4,524 21,290 65,883 331,970 167 432,009
8 3,580 1,256 2,565 6,912 28,227 65,515 316,239 343 424,637
9 -90 1,945 2,852 3,850 32,470 72,573 292,877 232 406,709
10 1,644 754 2,335 10,076 27,419 82,917 213,306 1,607 340,057
11 5,538 -2,632 293 19,853 25,389 63,314 289,870 394 402,018
12 2,657 593 3,131 33,257 29,262 105,522 329,668 731 504,820
13 160,901 520,099 681,000
TOTAL          38,358        14,202        42,568      93,821        322,123    877,658  3,818,915      9,211     5,216,856
North West
Locality                         
£
North East
Locality                        
£
Adult
Services             
£
Children
Services               
£
Mental
Health                 
£
Other           
£
TOTAL       
£
1 2,694 532 9,955 9,215 5,993 1,168 29,556
2 1,669 437 6,550 6,378 6,579 1,074 22,687
3 2,635 488 10,986 7,952 5,225 737 28,022
4 1,459 416 10,736 7,854 3,191 1,065 24,721
5 2,123 325 10,235 5,141 5,013 1,729 24,566
6 2,161 200 9,100 6,090 4,699 733 22,983
7 2,790 1,429 12,425 6,990 7,250 1,408 32,292
8 2,607 1,692 10,079 5,943 6,773 1,489 28,582
9 1,733 2,533 7,066 7,782 7,024 558 26,696
10 1,037 847 7,118 9,457 6,566 1,111 26,135
11 3,224 933 5,977 6,819 4,529 1,041 22,523
12 2,931 1,527 6,027 8,120 8,315 1,752 28,672
TOTAL         27,061        11,361      106,254      87,740          71,156      13,865     317,436
Period
Period
EXCESS PART TIME COSTS YEAR TO DATE
OVERTIME COSTS YEAR TO DATE
Period
BANKAIDE COSTS YEAR TO DATE
Period
AGENCY COSTS YEAR TO DATE
Page 41 of 146

Page 42

Page 42 of 146

Page 43

REPORT 
Item No: 07 
SUBJECT: IJB Reserves Strategy 2026/27
TO: Performance, Finance and Audit Committee
Lead Officer for
Report:
Chief Officer
Author(s) of Report Chief Finance Officer 
DATE: 20 May 2026 
1. PURPOSE OF REPORT
1.1 This paper is coming to the Performance, Finance and Audit (PFA) Committee for: 
For approval  For endorsement  For noting 
1.2 This report provides an update on the review of the North Lanarkshire Integration
Joint Board (IJB) reserves. 
2. ROUTE TO THE INTEGRATION JOINT BOARD
2.1 This paper has been: 
Prepared By:
Chief Finance
Officer
☒ Reviewed By:
Chief Officer
☒ Endorsed By: ☐ 
3.        RECOMMENDATIONS
3.1  It is recommended that the PFA Committee:
(1) Acknowledge the contents of the report.
(2) Approve the proposed realignments and new reserves detailed in Appendix 1.
(3) Approve the retention of the 4% target for risk‑based and contingency reserves,
as detailed in section 7.
4. VARIATIONS TO DIRECTIONS 
5. 2025/26 FINAL OUTTURN AND RESERVE ALLOCATION
5.1 Maintaining adequate financial reserves is critical to the IJB’s long-term stability and
sustainability, providing capacity to respond to unforeseen financial pressures. The
statutory importance of holding reserves forms part of the wider framework designed
to ensure section 106 public bodies manage their finances responsibly. 
Yes  No  N/A 
Item 7
Page 43 of 146

Page 44

5.2 The Financial Monitoring report presented to the Committee confirms an underspend
of £30.511m for 2025/26, including £26.769m of ring-fenced and ear marked funding
for commitments and national priorities. The Partnership must now determine how this
underspend is to be applied to reserve balances.
5.3 The IJB Reserves Strategy 2025/26 provides a framework to support this
decision‑making and presents an opportunity to strengthen long‑term financial
sustainability. It does so by reviewing all existing reserves to ensure they remain
appropriate, necessary, and sufficient to meet ongoing and emerging financial
pressures. Through the application of the Reserves Strategy, the IJB will be better
positioned to balance current commitments while proactively planning for, and
managing, future financial risks.
6. IJB RESERVES STRATEGY 2026/27
6.1 As set out in Table 1, reserve balances at 1 April 2026 totalled £75.554m.
6.2 In‑year drawdowns were applied against approved commitments funded from
ring‑fenced and earmarked reserves. Following these movements, the Partnership’s
closing reserves position was £70.869m. Further detail is provided in Appendix 5 of
the Financial Monitoring report.
6.3 The closing balance comprises £14.232m of ring‑fenced reserves to support specific
Scottish Government programmes, £21.626m of earmarked reserves for time‑limited
commitments, and £35.011m of risk and contingency reserves. These uncommitted
balances provide financial flexibility to respond to emerging pressures and risks. 
Table 1 
6.4 As part of the year‑end process, a comprehensive review of all reserves was
undertaken by both partners to confirm that balances held for 2025/26 remain
appropriate and sufficient to address ongoing financial pressures. This review also
incorporated the proposed allocation of the 2025/26 surplus.
6.5 Following this review, a revised reserves position has been developed and is detailed
in Appendix 1 and summarised in Table 2. This includes:
 Allocation of the 2025/26 surplus
 Transfer of £0.304m from risk reserves to establish four new reserves within Social
Care
 Creation of new reserves, primarily reflecting funding received from NHSL and the
Scottish Government for specific commitments in 2026/27
 Increases to existing reserves, largely driven by late‑year funding for 2026/27
commitments
 The closure or reduction of £2.225m of reserves, reallocated to general
contingency and risk‑based reserves. 
Opening
Balance
as at
Closing
Balance as
at
1st April
2025
31st March
2026
£m £m £m £m
NHSL Ring-Fenced Reserves 14.839 0.000 (0.607) 14.232
NLC/NHSL Earmarked Reserves 25.060 0.267 (3.701) 21.626
NLC/NHSL Risk-Based Reserves 21.536 (0.267) (0.377) 20.892
NHSL Contingency Reserves 14.119 0.000 0.000 14.119
NLC/NHSL Closed Reserves 0.000 0.000 0.000 0.000
75.554 0.000 (4.685) 70.869Total
LEAD SUMMARY
Transfers
To / From
Reserves
Drawdown
from
Reserves
Page 44 of 146

Page 45

Table 2
SUMMARY
Proposed
transfers
from
reserves
New reserves
awaiting IJB
approval
Proposed
increase to
reserves
Proposed
closure /
reduction
of
reserves
Net
Movements
£m £m £m £m £m
Movements 0.000 19.431 13.332 (2.252) 30.511 
6.6 The opening reserves for 2026/27 are summarised in Table 3. 
Table 3 
7. RISK
7.1  In line with the Partnership’s Medium‑Term Financial Plan, risk‑based and
contingency reserves continue to be maintained as a defined percentage of the core
financial envelope. This approach provides a proportionate safeguard against financial
uncertainty and supports the Partnership’s ability to manage emerging risks.
7.2 Members will recall approving a reduction in the target level for risk‑based and
contingency reserves from 5% to 4% in May 2025, reflecting the significant financial
challenges facing the Partnership at that time and the limited opportunity to generate
underspends to support reserve growth.
7.3 The 2025/26 financial outturn has been more favourable than anticipated.
Lower‑than‑expected drawdowns, the application of a £3.7m underspend, and the
rationalisation of a number of existing reserves have enabled an increase in risk‑based
and contingency reserves. As a result, these reserves now represent approximately
6% of the core financial envelope.
7.4 This position should be viewed as an over‑achievement against the agreed 4% target
rather than a change in strategic intent. Given the scale of the forecast budget gap
facing the Partnership and the lead‑in time required to deliver service transformation
and savings plans, it is considered appropriate to retain the 4% target at this stage.
Maintaining reserves above the target level provides additional short‑term resilience
while avoiding the need for frequent revisions to agreed policy parameters.
7.5 The level of risk‑based and contingency reserves will continue to be reviewed as part
of the annual financial planning and year‑end process, ensuring alignment with the
Partnership’s risk profile, financial outlook, and medium‑term sustainability.   
Opening Balance
As At
1st April 2026
£m
NHSL Ring-Fenced Reserves 14.985
NLC/NHSL Earmarked Reserves 45.697
NLC/NHSL Risk-Based Reserves 21.574
NHSL Contingency Reserves 19.124
101.380Total
PARTNER SUMMARY
Page 45 of 146

Page 46

8. IMPLICATIONS
8.1 NATIONAL OUTCOMES
People are able to look after and improve their own health and wellbeing
and live in good health for longer 
☐
People, including those with disabilities or long-term conditions, or who are
frail, are able to live, as far as reasonably practicable, independently and at
home or in a homely setting in their community
☐
People who use Health and Social Care Services have positive
experiences of those services, and have dignity respected
☐
Health and Social Care Services are centred on helping to maintain or
improve the quality of life of people who use those services 
☐
Health and Social Care Services contribute to reducing health inequalities  ☐
People who use Health and Social Care Services are safe from harm ☐
People who work in Health and Social Care Services feel engaged with the
work they do and are supported to continuously improve the information,
support, care, and treatment they provide
☐
Resources are used effectively and efficiently in the provision of Health and
Social Care Services 
☒
8.2 ASSOCIATED MEASURE(S) 
Each partner is required to remain within their approved budgetary provision. 
8.3 FINANCIAL 
This paper has been reviewed by Finance:
Yes  No  N/A 
8.4 RISK ASSESSMENT/RISK MANAGEMENT 
The strategic financial risks detailed in the IJB Risk Register has been updated where
necessary and are included in a separate report to the IJB. 
Relevant Risk Register Details  Current Risk
Level 
Risk Owner 
Financial Sustainability – Short Term High Nicola Scott
Financial Sustainability – Medium Term Very High Nicola Scott
Financial Sustainability – Long Term Very High Nicola Scott
Governance Failure High Nicola Scott
Failure to meet Legislative
Requirements
Medium Pauline Izat / Morag
Dendy / Joanne
Jenkins 
8.5 ENGAGEMENT & PARTICIPATION
Please tick the engagement and participation objectives that link(s) with this piece of
work and provide further details on the engagement and participation that was
undertaken. 
Objectives  Further details 
☒ Involve stakeholders in the development
work aimed at achieving the national 
outcomes
The finance teams of both Partners
have been actively involved in the
reserves review.
Page 46 of 146

Page 47

☐ Provide stakeholders with information on
how to get involved 
☐ Ensure a diverse range of engagement
and participation and opportunities are in 
place to suit different needs 
☐ Measure how well we involve community
stakeholders in the planning, design, and
delivery of our services 
☒ Provide regular feedback on how
stakeholder engagement and participation is
shaping and influencing service
development and delivery
Financial information is shared with
stakeholders on a regular basis and
is provided to the PFA and IJB on a
quarterly basis.
☒ Provide support to enable stakeholder
representatives to participate meaningfully
and confidently at meetings 
☐ Develop participation guidelines to ensure
a common understanding and set of 
expectations for both stakeholders and
partnership staff 
☒ Support engagement planning and
participation in localities, taking account of 
other engagement activity and local plans
across the Community Planning 
Partnership
IJB Financial Plan and Reserves
Strategy aligns and supports the
IJB Strategic Commissioning Plan
to ensure robust financial
monitoring and scrutiny. 
8.6  INEQUALITIES & FAIRER SCOTLAND DUTY
Equality and Diversity Impact Assessment Completed & Fairer Scotland Impact
Assessment Form Completed: 
Yes  No  N/A 
9. BACKGROUND PAPERS 
None. 
10. APPENDICES 
HSCP Reserves Increases and  Realignments   Appendix 1     
Chief Finance Officer 
Members seeking further information about any aspect of this report, please contact Nicola
Scott on telephone number 07581 007187. 
Page 47 of 146

Page 48

Appendix 1 
2025/26
Closing
Balance
Proposed
Transfers from
Reserves
New reserves
Awaiting IJB
Approval
Proposed
Increase to
Reserves
Proposed
Closure /
Reduction of
Reserves
2026/27
Opening
Balance
£m £m £m £m £m £m
NHSL Alcohol and Drug Partnership Funding Increase 0.450 3.681 0.450 4.131
NHSL Area Wide Services - Refugees and Displaced Persons No change 0.000 0.121 0.121
NHSL Blood-Borne Viruses Services Partial Reduction (0.043) 0.318 (0.043) 0.275
NHSL Community Living Change Fund Closure (0.044) 0.044 (0.044) (0.000)
NHSL District Nursing No change 0.000 0.373 0.373
NHSL Hospital at Home Services Increase 0.068 0.813 0.068 0.881
NHSL Learning Disabilities Health Checks No change 0.000 0.491 0.491
NHSL Mental Health Action 15 No change 0.000 0.730 0.730
NHSL Mental Health Diagnostic Support Service Dementia Post Increase 0.074 1.057 0.074 1.131
NHSL Mental Health Digital Therapy Post No change 0.000 0.221 0.221
NHSL Mental Health Distress Brief Intervention Increase 0.702 2.704 0.702 3.406
NHSL North Planning Band 2-4 Posts & Multi-Disciplinary Teams Partial Reduction (0.600) 2.696 (0.600) 2.096
NHSL Pharmacy Mental Health Recovery & NES Training New: 2026/27 0.146 0.000 0.146 0.146
NHSL School Nursing No change 0.000 0.903 0.903
NHSL Third Sector Initiatives To Improve Health No change 0.000 0.075 0.075
NHSL Upper GI Dietetics Band 4 No change 0.000 0.006 0.006
0.753 14.232 0.000 0.146 1.295 (0.687) 14.985
NHSL MH Funding No change 0.000 1.500 1.500
NHSL Children and Adolescent Mental Health Services Partial Reduction (0.172) 2.774 (0.172) 2.602
NHSL Frailty Nursing Closure (0.001) 0.001 (0.001) 0.000
NHSL Unscheduled Care:  Contribution to Set Aside Increase 5.962 2.790 5.962 8.752
NHSL Unscheduled Care:  Hospital at Home New: 2026/27 1.112 0.000 1.112 1.112
NHSL Unscheduled Care:  Paediatrics New: 2026/27 0.982 0.000 0.982 0.982
NHSL Unscheduled Care:  NLC Winter New: 2026/27 1.541 0.000 1.541 1.541
NHSL Unscheduled Care:  General New: 2026/27 0.867 0.000 0.867 0.867
NHSL Mental Health Recovery Renewal - Facilities Projects No change 0.000 1.029 1.029
NHSL Adult Social Care Winter Preparedness Fund No change 0.000 1.000 1.000
NHSL Staff Wellbeing No change 0.000 0.254 0.254
NHSL Minor Capital Works Increase 0.003 0.948 0.003 0.951
NHSL Children and Adolescent Mental Health Services - Udston Top Up Funding No change 0.000 0.268 0.268
NHSL Development of Chryston Community Health Clinic Partial Reduction (0.078) 0.212 (0.078) 0.134
NHSL Kylepark Works Closure (0.134) 0.134 (0.134) 0.000
NHSL HR Employability Team (2 year funding, 50:50 split between North and South)
Closure (0.087) 0.087 (0.087) 0.000
NHSL Breast Feeding Team (2 year funding) Partial Reduction (0.291) 0.345 (0.291) 0.054
NHSL Dietetics Services - Double Running Costs No change 0.000 0.055 0.055
NHSL Health Visiting Students/Trainees No change 0.000 0.029 0.029
NHSL Mental Health Wards Window Replacement No change 0.000 0.650 0.650
NHSL Neonatal & Paediatrics Dieteics Intervention (3 year funding) Partial Reduction (0.115) 0.194 (0.115) 0.079
NHSL Paediatric Diabetes Insulin Pumps and Additional Staff Partial Reduction (0.028) 0.529 (0.028) 0.501
NHSL Podiatry Services - Foot Screening No change 0.000 0.338 0.338
NHSL Scottish Clinical Leadership Fellowship No change 0.000 0.060 0.060
NHSL Sexual Health Services - Long-Acting Reversible Contraception (LARC) Partial Reduction (0.017) 0.297 (0.017) 0.280
TOTAL RING-FENCED RESERVES
Partner HSCP RESERVES INCREASES AND REALIGNMENTS Action
Net
Movement
£m
Page 48 of 146

Page 49

Appendix 1 
NHSL Staff Training Academy Partial Reduction (0.237) 0.335 0.050 (0.287) 0.098
NHSL Vulnerable and Complex Cases - Test of Change Partial Reduction (0.118) 0.501 (0.118) 0.383
NHSL Paediatric Acute Funding New: 2026/27 0.235 0.000 0.235 0.235
NHSL Ligature Spend New: 2026/27 8.886 0.000 8.886 8.886
NHSL MMRV Funding New: 2026/27 0.415 0.000 0.415 0.415
NHSL Mental Health Improvement Post (18 months) New: 2026/27 0.090 0.000 0.090 0.090
NHSL Neuro Psych New: 2026/27 0.264 0.000 0.264 0.264
NHSL Psychiatry Liaison New: 2026/27 0.611 0.000 0.611 0.611
NHSL GJ Coathill New: 2026/27 0.200 0.000 0.200 0.200
NHSL North IJB Staff Wellbeing New: 2026/27 0.254 0.000 0.254 0.254
NHSL Marmot monies New: 2026/27 2.000 0.000 2.000 2.000
NHSL Medicine Growth Fund New: 2026/27 0.620 0.000 0.620 0.620
NHSL Carehomes New: 2026/27 0.750 0.000 0.750 0.750
NLC Business Case - Non-Recurring NLC Costs No change 0.000 0.022 0.022
NLC Carers Act 2018 - Support Increase 0.017 2.422 0.017 2.439
NLC Digital and IT Strategy Technology Improvements - Community Alarms No change 0.000 0.111 0.111
NLC Digital and IT Strategy Technology Improvements - Home Support Scheduling System No change 0.000 3.045 3.045
NLC Digital and IT Strategy Technology Improvements - SWIS No change 0.000 0.000 0.000
NLC Home Support Resilience (2 year funding) Partial Reduction (0.237) 0.487 (0.237) 0.250
NLC Mental Health Social Workers 2 x NL10 x 24 months No change 0.000 0.149 0.149
NLC Staff Training Academy No change 0.000 0.426 0.426
NLC MHO Capacity Funding No change 0.000 0.291 0.291
NLC Statutory Appropriate Adults Increase 0.014 0.161 0.014 0.175
NLC Sessional - School summer placements No change 0.000 0.182 0.182
NLC SDS Transformational Funding New: 2026/27 0.458 0.458 0.458
NLC FAI legal costs New: 2026/27 0.083 0.083 0.083
NLC Child and Adult Protection - resourcing multi agency reviews New: 2026/27 0.060 0.060 0.060
NLC MARR CHARTS / HOME SUPPORT New: 2026/27 0.110 0.110 0.110
NLC Pharmacy tech post New: 2026/27 0.050 0.050 0.050
24.071 21.626 0.304 19.286 6.046 (1.565) 45.697
NHSL Prescribing Fund No change 0.000 5.066 5.066
NLC Social Care Demand Increase 0.682 15.826 0.682 16.508
0.682 20.892 0.000 0.000 0.682 0.000 21.574
NHSL Contingency Balance Held By NHSL Increase 5.005 14.119 (0.304) 5.309 19.124
5.005 14.119 (0.304) 0.000 5.309 0.000 19.124
30.511 70.869 0.000 19.431 13.332 (2.252) 101.380
TOTAL EARMARKED RESERVES
TOTAL RISK-BASED RESERVES
TOTAL CONTINGENCY FUND RESERVES
MOVEMENT
Page 49 of 146

Page 50

Page 50 of 146

Page 51

1 
REPORT 
Item No: 8 
SUBJECT: Performance Update – 01st October 2025 to 31st December 2025,
Quarter 3 2025/26 
TO: Integration Joint Board Performance, Finance & Audit Committee
Lead
Officer for
Report:
Morag Dendy, Head of Planning, Performance and Quality
Assurance 
Author(s) of
Report
Stephen Forrest, Performance Manager
DATE: 20 May 2026 
1. PURPOSE OF REPORT 
This paper is coming to the IJB for: 
For approval ☐ For endorsement ☐ To note ☒ 
2. ROUTE TO THE BOARD 
This paper has been: 
Prepared By: ☒ Reviewed By: ☒ Endorsed By: ☐
Prepared by:      
Performance Manager 
Reviewed by: 
Senior Manager, Strategy
& Performance   
Item 8
Page 51 of 146

Page 52

2 
3. RECOMMENDATIONS
It is recommended that the IJB/IJB PFA Committee:
(1) Note the contents of the report and the appendix. 
4.  VARIATIONS TO DIRECTIONS? 
5. BACKGROUND/SUMMARY OF KEY ISSUES
The Chief Officer has joint quarterly performance review meetings with the Chief Executives
of NHS Lanarkshire and North Lanarkshire Council. These meetings are supported by a
Chief Executives Performance Framework comprising a range of performance measures
taken from across both the health and social work systems, including relevant targets and
trajectories for the measures presented. 
Each quarter there are areas for improvement identified within the performance framework;
these are identified using a RAG rating and those measures that are flagged as Red or
Amber are subject to improvement or corrective action. The performance review meetings
are used as a means for jointly agreeing these actions. 
6. CONCLUSIONS
The areas for improvement and corrective action identified as RAG Red and Amber are
attached as Appendix 1. The areas for improvement identified in Appendix 1 are being
progressed as a matter of priority, and progress updates will be reported at future meetings
of the Board and the Performance, Finance & Audit Committee.  
7. IMPLICATIONS 
7.1 NATIONAL OUTCOMES
Link(s) to National Health and Wellbeing Outcomes 
People are able to look after and improve their own health and wellbeing
and live in good health for longer 
☒
People, including those with disabilities or long-term conditions, or who are
frail, are able to live, as far as reasonable practicable, independently and at
home or in a homely setting in their community
☒
Yes  ☐ No ☐ N/A ☒
Page 52 of 146

Page 53

3 
People who use Health and Social Care Services have positive
experiences of those services, and have dignity respected
☒
Health and Social Care Services are centred on helping to maintain or
improve the quality of life of people who use those services 
☒
Health and Social Care Services contribute to reducing health inequalities  ☒
People who use Health and Social Care Services are safe from harm ☒
People who work in Health and Social Care Services feel engaged with the
work they do and are supported to continuously improve the information,
support, care and treatment they provide
☒
Resources are used effectively and efficiently in the provision of Health and
Social Care Services 
☒
7.2 ASSOCIATED MEASURE(S)
None. 
7.3 FINANCIAL
This paper has been reviewed by Finance: 
7.4 RISK ASSESSMENT/RISK MANAGEMENT 
Relevant Risk Register Details  Current Risk
Level 
Risk Owner 
IJB 11.21 - Oversight of
Performance Activity
Low Claire Rae
NLC RIA0000460 –
Performance & planning
High NLC – Social  Work/Social care 
7.5  ENGAGEMENT & PARTICPATION
Please tick the engagement and participation objectives that link(s) with this piece of
work and provide further details regarding the engagement and participation that was
undertaken.
Objectives  Further Details 
☐ Involve stakeholders in the development
work aimed at achieving the national 
outcomes 
☐ Provide stakeholders with information on
how to get involved 
Yes  ☐ No ☐ N/A ☒
Page 53 of 146

Page 54

4 
☐ Ensure a diverse range of engagement
and participation and opportunities are in 
place to suit different needs 
☐ Measure how well we involve community
stakeholders in the planning, design 
and delivery of our services 
☐ Provide regular feedback on how
stakeholder engagement and participation is 
shaping and influencing service
development and delivery 
☒ Provide support to enable stakeholder
representatives to participate meaningfully
and confidently at meetings
The performance information, with
the corresponding improvement
and corrective actions will enable
stakeholder representatives to
participate in wider discussion
about performance.
☐ Develop participation guidelines to
ensure a common understanding and set of 
expectations for both stakeholders and
partnership staff 
☒ Support engagement planning and
participation in localities, taking account of 
other engagement activity and local plans
across the Community Planning 
Partnership
The performance information, with
the corresponding improvement
and corrective actions supports
locality planning. 
7.6 INEQUALITIES & FAIRER SCOTLAND DUTY 
EQIA Completed & Fairer Scotland Impact Assessment Form Completed and
attached to report: 
EQIA added to website: 
8. BACKGROUND PAPERS
Yes  ☐ No ☐ N/A ☒
Yes /
Date
added 
☐ No ☐ N/A ☒
Page 54 of 146

Page 55

5 
None. 
9. APPENDICES
Appendix One - Areas for Improvement – 01st October 2025 to 31st December 2025,
Quarter 3 2025/26 
CHIEF ACCOUNTABLE OFFICER (or Depute)  
Head of Planning, Performance and Quality Assurance 
Members seeking further information about any aspect of this report, please contact
the following;
Stephen Forrest – Performance Manager Stephen.Forrest@lanarkshire.scot.nhs.uk 
Page 55 of 146

Page 56

6 
1.  Alcohol Brief Interventions Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
Alcohol Brief Interventions North  3047
*annualised 508 453   RED
Alcohol Brief Interventions (all settings) NHSL  7381
*annualised 1601 1474   RED
Narrative & Corrective Action
Performance for Alcohol Brief Interventions in Q3 shows that there has been a reduction in activity when compared to Q2, with 453 interventions recorded across North
Lanarkshire. Delivery therefore remains below the revised trajectory and continues to reflect the longer-term downward trend observed in recent reporting periods.
As noted previously, ABI delivery remains sensitive to wider system pressures including workforce availability and competing clinical priorities. This continues to result in
variation across the various delivery settings and limits the pace at which improvement can be realised. The Q3 position therefore does not yet suggest any sustained
recovery in delivery levels.
Recording practices also continue to influence reported performance. A range of services and settings deliver ABI and it is known that interventions are not recorded
consistently within core reporting systems, meaning that not all activity is captured in the calculation for this performance indicator. This limits the extent to which
reported figures fully reflect the activity undertaken in practice and remains an area for continued improvement.
Engagement with delivery teams and the ongoing embedding of ABI pathways into routine practice continue to be key areas of focus. Given the preventative nature of
the intervention and the time lag between engagement activity and measurable impact, improvement is expected to remain incremental and dependent on wider system
capacity. 
2.  Cervical Screening Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
Cervical Screening 80% 69.9% 69.8%   RED
Narrative & Corrective Action
Performance for Cervical Screening in Q3 shows a slight decrease compared to the previous quarter, with uptake across North Lanarkshire recorded at 69.8%, compared
to 69.9% in Q2. Uptake remains below the national target of 80% across all localities. Locality-level variation remains relatively modest. Airdrie showed a small
improvement, while Motherwell and North localities remained broadly stable. Bellshill, Coatbridge and Wishaw recorded marginal reductions. Overall uptake therefore
continues to reflect the longer-term decline seen across recent years.
Page 56 of 146

Page 57

7 
Uptake is lowest in the following age bands in Lanarkshire:
 40-44 = 37.2%
 45-49 = 34.0%
 50-54 = 31.7%
It is important to interpret the Q3 position within the wider national context. Recently published Scottish Cervical Screening Programme statistics indicate there has been
a significant reduction in participation rates across Scotland and Lanarkshire. (7.9% decrease for Lanarkshire and an 8% decrease nationally). Analysis of the data by SIMD
quintiles shows that there is a 13.8% difference between SIMD 1 and 5 for Lanarkshire, compared to a 9.2% difference across Scotland; inequality is greater across
Lanarkshire, however Lanarkshire performs better across all SMID quintiles when compared to the overall Scottish position. In addition, the change to the screening recall
interval from three to five years, for women aged 25–49, has influenced the way uptake is recorded within the national statistics and is expected to affect the reported
figures for a transitional period.
Work to improve our screening uptake continues to be coordinated through the Lanarkshire-wide Inequalities in Screening Steering Group. Activity during the quarter has
included targeted engagement events, strengthened awareness activity in community settings and direct support to GP practices with lower uptake by using screening
system data to identify and engage non-attenders. Further initiatives are planned to support improvement, including the introduction of patient navigators and
participation in the HPV self-sampling pilot within several North Lanarkshire practices. This pilot aims to increase participation among individuals who are currently under-
screened, particularly those living in areas of higher deprivation. A summary of the improvement activity is presented below: 
Pan-Lanarkshire
 Targeted Support to Lowest-Uptake Practices – Public Health QI team supporting practices to use SCRRS to proactively identify high-risk non-attenders.
 Short-Term Workforce Support – Two redeployed staff assisting practices to engage non-attenders.
 Patient Navigator Pilot (Starts March 2026) – SG-funded pilot introducing patient navigators and additional community clinics, aligned with HPV self-sampling
work.
 Pregnancy Exclusion Audit – System Fix Required – Audit shows midwifery teams are not routinely notifying GPs of pregnancies, preventing appropriate
application of pregnancy exclusion and timely post-birth invites. Public Health now engaging midwifery to implement consistent notifications.
 HPV Self-Sampling Pilot – North Lanarkshire Practices – Five participating practices (Airdrie Adam Ave, Airdrie Wellwynd, Coatbridge Waverly, Motherwell
Orchard, Wishaw Logan). Evidence indicates significantly improved uptake in deprived/minoritised populations; national rollout expected in 2–3 years.
 Health Improvement Activity Across Localities
 Screening materials and QR posters distributed across all NL community hubs.
 Lived-experience video/podcast embedded in community conversations.
 Screening included in all menopause education sessions.
Page 57 of 146

Page 58

8 
 Comms planning underway for Cervical Cancer Prevention Week 2026. 
Wishaw Locality
 6-Week Post-Natal ‘One-Stop’ Pilot – Developing a combined post-natal check offering physical review, Edinburgh Depression Score and smear at one
appointment.
 Digital Engagement – Text reminders now used to reduce DNAs for smear appointments.
 Professional Education Video – Health Improvement and Public Health producing a short video on benefits/risks of cervical screening; led by colposcopy clinical
lead (in Comms production).
 HPV Self-Sampling Pilot – Logan Practice participating in the North Lanarkshire pilot targeting under-screened women in high-deprivation areas.
 Local Health Improvement Work
 Screening promotion across Wishaw community hubs and venues.
 Use of lived-experience materials and QR-coded resources in community engagements.
 Menopause sessions integrating cervical screening messaging.
 Joint working with Treatment Room staff to embed screening conversations into chronic disease clinics.
 Health Visitor awareness sessions delivered as part of locality action plan. 
Other locality-specific actions
 Airdrie/Coatbridge/North – Newsletters, Early Years distribution, routine awareness sessions.
 Coatbridge – Engagement with parents at school events.
 North – Outreach to community groups (e.g., seniors events).
 Bellshill/Motherwell/Wishaw – Digital screens in public venues, QR posters in health centres, Health Visitor awareness, Treatment Room staff training,
quarterly Milan data sharing. 
While this range of activity demonstrates continued focus on improving uptake, the cyclical nature of screening programmes and the behavioural factors influencing
engagement mean that improvement is expected to be gradual. Continued emphasis on community engagement, practice-level support and national programme
development will therefore be required to support recovery in the level of performance toward the targeted level. 
Page 58 of 146

Page 59

9 
3.  Childhood Immunisations Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
Immunisations – %s of 5 year olds   95% 89.5% 90.5%   RED
Immunisations – %s of 2 year olds   95% 94.4% 94.3%   RED
Narrative & Corrective Action
Childhood immunisation uptake in North Lanarkshire has generally compared well with the national position. However, current rates for several key age groups remain
below the 95% performance standard. This shortfall is concerning given the importance of maintaining high vaccination coverage to protect population health, prevent
disease outbreaks, and sustain herd immunity.
Uptake within the two-year-old immunisation programme continues to fall slightly short of the national target. Although the variation is small, the consistency of this
downward trend means it requires close monitoring.
For preschool aged children, uptake remains further from the 95% standard, although this quarter has shown a modest improvement of 0.9%.
A range of factors appear to be contributing to the reduction in uptake. These include a gradual increase in vaccine hesitancy among a small but growing number of
families, delays in providing consent, refusal of consent, challenges accessing clinics, and missed appointments. In addition, a notable proportion of families in each
locality have actively withdrawn consent, as reflected in the table below.
Locality % Opt out
Airdrie 5.0%
Bellshill 5.94%
Coatbridge 5.8%
Motherwell 7.42%
North 5.5%
Wishaw 6.8% 
All areas also report a substantial number of children transferring into the area, which further affects overall uptake figures.
Workforce capacity continues to be a concern; the number of vacancies for Staff Nurses are a limiting factor on the service’s ability to maintain the existing immunisation
schedule and place additional pressure on both delivery and follow-up activity.
Page 59 of 146

Page 60

10 
Vaccination Teams remain fully engaged in addressing these challenges. Ongoing improvement work includes strengthened reminder and recall processes, closer
coordination with Health Visiting Teams to maximise every contact as an opportunity to promote vaccination and targeted outreach to families who do not attend. In
addition, to counter the declining trend, Health Visiting Teams across NHS Lanarkshire have implemented a range of focused actions.
Operational and Workforce Measures
 Streamlined Processes: In response to staffing instability within the North East Sector, a sector-wide model for clinic coverage was introduced to ensure safe
delivery and prevent clinic cancellations. Standardised operating procedures (SOPs) were developed to support consistent, safe cross-cover arrangements.
Improving Access and Reducing Backlogs
 Enhanced Monitoring of Q-Print: Backlogs were proactively reduced through additional clinics scheduled during the 5th week of the month, traditionally a
non-clinic week. Home visits were also offered to improve accessibility for families experiencing barriers.
Strengthened Engagement and Communication
 Enhanced Health Visitor Engagement: Vaccinations are routinely discussed during pathway visits, with targeted scripts used to ensure clear, consistent
messaging that supports informed decision-making.
Data-Driven Oversight and Governance
 Robust Review by AOVIC: The Area Oversight Vaccination and Immunisation Committee continues to lead detailed data analysis and identify systemic changes
required to maintain uptake levels above 95%. 
Combined, these efforts reflect a sustained commitment to improving immunisation uptake, reducing inequality and preventing avoidable outbreaks to protect the
health of children and families across Lanarkshire. Continued focus and cross-system collaboration will be essential to reverse the downward trajectory and consolidate
the progress made in previous years. 
4.  Addictions Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
Addictions – Ongoing Waits NHSL 90% 80.2% 59.4%   RED
Narrative & Corrective Action
Medication Assisted Treatment (MAT) Standards continue to demonstrate that addictions services in North Lanarkshire are operating within a stable and well‑established
clinical framework, with the majority of standards consistently met. This provides ongoing assurance regarding the quality, safety, and consistency of treatment and
recovery pathways.
Page 60 of 146

Page 61

11 
However, the NHS Lanarkshire-wide ongoing waits indicator shows a significant decline in Q3. This movement reflects pressures across the wider system rather than a
deterioration in North Lanarkshire service delivery. There have been some extended waits within the Airdrie locality, which were anticipated and directly attributable to
short‑term staff absence. Despite this, local performance across North Lanarkshire remains comparatively stable, and treatment pathways continue to operate in line
with national expectations.
Work to address NHS Lanarkshire–wide waiting time pressures continues to be coordinated through corporate processes and sits outside the scope of the MAT Standards
framework.
The detail on MAT Standards below should therefore be read as a supplementary assurance measure rather than a proxy for wider addictions performance; focus
remains appropriately directed towards addressing NHS Lanarkshire-wide access pressures. 
RAGB Colour | Definition 
Colour Definition
Red There is no or limited evidence of implementation of the standard in MAT services
Provisional amber There is no or limited evidence of implementation of the standard in MAT services
Amber There is evidence of partial implementation of the standard in MAT services including benefit to people
Provisional green There is evidence of implementation and benefit to people, however, full implementation is not confirmed by all three
evidence streams – usually the experiential stream is lacking
Green There is evidence of full implementation and benefit to people in all unique combinations of setting and service that
offer MAT and opioid substitution therapy (OST) across the ADP area 
ADP Reporting Year MAT 1 MAT 2 MAT 3 MAT 4 MAT 5 MAT 6 MAT 6 &
10
MAT 7 MAT 8 MAT 9 MAT 10
North Lanarkshire
2022           
2023           
2024           
2025           
5.  6 – 8 Week Reviews Target 2025/26 2024/25 Q4 2025/26 Q1 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
Page 61 of 146

Page 62

12 
Percentage of people who have completed 6-8 week
review 90% 84.4% 81.0%  ... RED
Narrative & Corrective Action
The partnership continues to face challenges in achieving the 90% performance target for 6–8 week child health reviews. Although performance is relatively stable, it
remains well below the required standard.
Because of reporting time lags, the current data reflects activity prior to the full implementation of the new pathway developed by the 6–8 Week Review Sub-Group.
During this quarter, the process documentation has been have been recirculated and Health Visiting (HV) Team Leads have reiterated the expectations on GP Practices
and Clinical Leads for reviews, highlighting the specific detail on the responsibilities of GP within the process. Despite these actions, several recurring issues continue to
limit the effectiveness of the pathway and, in turn, overall performance.
Some practices continue to schedule appointments earlier than the recommended timeframe, typically at 5 weeks and 6 days, which delays the timely availability of HV
forms. This leads to duplicate forms being generated, contrary to recommended guidance. Further concerns include GP submissions with missing information, particularly
absent completion dates. In these instances, the date received by the Child Health department is recorded instead, frequently placing the review outside the required
timescales.
There also remains considerable variation in processes across GP practices, making it difficult to embed consistent improvement across North Lanarkshire. Engagement
work has revealed that at least one practice had been waiting for the HV form before offering an appointment, causing avoidable delays; this practice has now agreed to
schedule appointments from birth. In another locality, neither the practice, nor the wider team monitored the assessment form’s journey, making it difficult to track
whether both HV and GP components were completed within the appropriate timeframe for those reviews. In addition, Child Health continues to experience issues
issuing paperwork during the fifth week of certain months, further contributing to delays in arranging and completing appointments.
Reviews for premature babies add further complexity, however many cases of missed reviews relate to parental choice or difficulty attending within the required
window.
The transition to digital CHSP forms is scheduled to go live in May. Initially, only the HV section will be digital. The system is currently undergoing testing and with most
fields becoming mandatory, adherence to the process, and therefore performance, is expected to improve. Other improvement work will continue and the service
recognises that a sustained and consistent effort will be required to return performance to the expected standard. 
6.  Assistive Technology  Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
Assistive Technology - Number Of People With
Technology (0-17 yrs) 1452
22 25   RED
Assistive Technology - Number Of People With
Technology (18-64yrs) 303 348   RED
Page 62 of 146

Page 63

13 
Assistive Technology - Number Of People With
Technology (65+) 745 879   RED
Narrative & Corrective Action
Performance for Assistive Technology remained below target during Q3. Interpretation of this position requires recognition that recent improvements to reporting
through ELMS2 have significantly improved data completeness. As a result, the current figures provide a more accurate representation of operational activity and
comparisons with earlier reporting periods should be made with caution.
Demand for Assistive Technology is believed to be increasing, driven by hospital discharge pressures and the strategic emphasis on enabling individuals to remain safely
at home wherever possible. Alongside core service delivery, the Tech team provides significant support to people in the community that is not captured within the
scorecard indicators. This includes supporting individuals who are purchasing technology independently and providing advice and demonstrations through the Assistive
Technology “Tech Flat”. While these activities are resource intensive, they are not reflected in the current performance metrics and therefore under-represent the overall
level of activity undertaken in this area. The volume of Adult Social Care Assessments undertaken by the Tech team is significant, again without being directly captured
within the current indicator set.
Work continues to strengthen the role of Assistive Technology within assessment and discharge pathways, including closer alignment with Home Assessment Teams and
Reablement services. This will support greater integration of technology-enabled care within community support pathways. Capacity constraints within the service,
particularly related to staffing levels, continue to affect the pace at which assessments, installations and reviews can be completed.
A desktop review of the Assistive Technology indicators and associated targets is planned ahead of the 2026/27 performance scorecard refresh. This review will consider
improved data maturity, workforce capacity and the need to ensure indicators reflect the breadth of operational activity undertaken by the Tech team, as well as the
number of people who use assistive technology.
Linked to this activity, the Equipment and Adaptation Service continues to demonstrate improvement in operational delivery. Performance against the delivery time
target has improved and is now slightly exceeding the 80% target following sustained work to strengthen operational processes. The service is focusing on improving
stock management, recycling equipment and strengthening ordering processes through closer collaboration with NHS Lanarkshire and North Lanarkshire Council
procurement teams. A service redesign review is also underway and is currently evaluating role profiles and operational arrangements to support further service
improvement. 
7.  Reablement and Rehabilitation  Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
Reablement - Number Of People Completing Reablement
Process
2000 (500 per
quarter)  604 940   RED
Reablement - % Of New or Increased Home Support
Packages Which Are Reablement 70% 60.4% 66.9%   RED
Page 63 of 146

Page 64

14 
Reablement - % Of People With No or Reduced Home
Support Service Required At End Of Process 70% 56.8% 51.1%   RED
Narrative & Corrective Action
Performance for the Reablement indicators during Q3 reflects progress in embedding the revised operating model for assessment and support at home.
During the quarter, more individuals were supported through the Reablement pathway than the previous quarter; however, this number remains below the quarterly
target of 500. Although below the targeted level of performance, the proportion of new or increased Home Support packages delivered through Reablement has also
improved, reflective of the continued focus on enabling approaches. This shift in practice is expected to continue supporting improvement in the proportion of individuals
receiving Reablement prior to longer-term care decisions being made.
However, the proportion of individuals requiring no or reduced Home Support following completion of Reablement has declined. This may reflect the increasing
complexity of needs among individuals entering the pathway, including higher levels of frailty, comorbidity and age-related complexity. 
8.  Adult Protection  Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
For Referrals in Period, Proportion Going to Case
Conference From DTI With Investigatory Powers Within
Timescale
60% 28.6% 22.2%  ... RED
Narrative & Corrective Action
The majority of referrals where there is a Duty to Inquire are progressing to investigation and assessment within the required timescales, demonstrating that appropriate
immediate safeguarding responses are being delivered in localities. North Lanarkshire Social Work Services received 875 ASP referrals in Quarter 3 2025/26, which is a
33% increase in comparison to Q3 last year when 658 referrals were received. The care home sector accounts for 25% (210) of all AP1 referrals received by social work; in
comparison to Q3 last year, referrals from care homes have increased 26% (from 167 to 210). 
Page 64 of 146

Page 65

15 
The data shows that Coatbridge, Cumbernauld and Wishaw interchange as the localities receiving the most ASP referrals in any quarter, likely linked to the higher
populations of those localities. In addition, all localities in North Lanarkshire experience multiple areas of deprivation, which contributes to poorer health and wellbeing
outcomes, and is a key factor driving ASP activity. 
Page 65 of 146

Page 66

16 
Physical harm and emotional/psychological harm remain the primary harm type within ASP referrals and this is a consistent trend over time. Many physical harm referrals
orginate from the care home sector, with a high number of referrals from care homes detailing falls, or altercations between residents. The volume of self-neglect
referrals remain high and it is recognised as a harm type that requires a multi-agency response in order to mitigate the associated risks.  It should also be noted that
multiple harm types often impact on service users and this cannot always be reflected in the data. Harm types relating to suicidal ideation, online harm, hoarding and
domestic abuse are new categories that we are now trackable with the implementation of Mosaic. Although the numbers for these harm types are low, they serve as a
useful indicator of emerging harm types.
The proportion of investigations progressing to case conference within the expected timescale is low for the Q3 reporting period. The position is influenced by ongoing
recording and data quality issues. Work is underway with operational teams to review those recording practices and address data quality issues. Once resolved, the
indicator is expected to more accurately reflect safeguarding activity.
The high proportion of adult welfare concerns recorded as requiring no further action reflects the fact that many individuals are already receiving appropriate support
from services or partner agencies. Internal audit work has confirmed that these cases frequently involve individuals who are already known to services or who are
Page 66 of 146

Page 67

17 
receiving support through alternative pathways. As such, the indicator does not necessarily indicate unmet need but rather reflects appropriate decision-making within
our safeguarding processes. 
9.  Adult Mental Health Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
18 Week RTT Performance – Psychology (NHSL) (NORTH
HOSTED) 90% 83.9% 81.2%   RED
Consultant Outpatient WT - Adult Mental Health - 12wks
(NHSL) (NORTH HOSTED) 90% 19.4% 18.4%   RED
Consultant Outpatient WT - Older Adult Psychiatry -
12wks (NHSL) (NORTH HOSTED)  90% 73.7% 75.4%   RED
Consultant Outpatient WT - Learning Disability - 12wks
(NHSL) (NORTH HOSTED) 90% 100.0% 75.0%   RED
Narrative & Corrective Action
18 Week RTT Performance – Psychology (NHSL) (NORTH HOSTED) 
Page 67 of 146

Page 68

18 
In Q3, 81.2% of patients commenced treatment within 18 weeks. Whilst this is a 2.7% decrease from the previous quarter, when compared to the same quarter in 2024
there is an overall improvement of 8.9%.
Over the last 12 months, the number of patients waiting over 18 weeks has decreased by 4.7%. The number of patients waiting for treatment exceeds the expected
trajectory, although it is still broadly in line with the trend. In December 2025, the waiting list reduced for the third consecutive month, since consecutive increases
between May and September 2025.
The average compliance with the 18-week referral to treatment target for 2025, for NHS Lanarkshire, was 78.9%, which is 3.8% more than for the calendar year in 2024.
All over-52 week waits continue to be within Neuropsychology, where waits have grown in line with expected trajectory following changes to the referral criteria
introduced in November 2023. Additional clinical resource will be provided to this service on a temporary basis during 2026 in order to address long waits and stabilise
the system. This will happen whilst a review of the service delivery model is carried out to understand future sustainability. 
The PHS analyst is currently reviewing and updating the DCAQ trajectories to provide further detail on the anticipated impact of the reduced working week on clinical
activity levels.
Whilst not captured in performance reporting data, clinical activity is ongoing across the majority of Psychological Services to offer, where appropriate, early assessment
appointment within 12 weeks of referral. In keeping with the expectations set out in SG's National Specification for the Delivery of Psychological Therapies and
Interventions, this approach ensures patients can be appropriately directed to the service that best meets their clinical needs at the earliest point in time. 
Consultant Outpatient WT - Adult Mental Health - 12wks (NHSL) (NORTH HOSTED)
The current scorecard metric reflects the position of the waiting list, calculated as the proportion of patients waiting within 12 weeks (i.e., the number of people waiting
≤12 weeks, divided by the total number of people on the waiting list). This approach is consistent with the methodology traditionally used for many other partnership
services and represents ongoing waits (rather than completed waits). These data are robust and long standing, having been used for many years by the partnership for
performance reporting. They are not, however, directly comparable to other performance measures such as the RTT for Psychological Therapies or CAMHS.
North HSCP now has an ambition to move towards all services using completed waits as a more consistent measure of performance. We will require to do this in a
stepwise, considered fashion, with an action plan given that to be robust, data recording practices will need to be reviewed across a high number of disciplines. 
In the instance of General Adult Psychiatry, the service has already been developing more robust reporting data that will meet that ambition. Early indications are that for
Q3 and the proportion of individuals actually seen within 12 weeks, 50.1% of patients were seen within the 12-week target. This metric is itself affected by ADHD waits
and psychiatry vacancies. Clinical directors have been asked to meet with all consultants to review the numbers of people being seen in clinics and to discuss how they
ensure that the data supplied is robust. 
Consultant Outpatient WT - Older Adult Psychiatry - 12wks (NHSL) (NORTH HOSTED)
Performance for Older Adult Psychiatry outpatient waiting times improved during Q3 and continues to show a gradual upward trajectory when compared with earlier
reporting periods.
Page 68 of 146

Page 69

19 
Despite this improvement, performance remains below the targeted level and continues to reflect the wider workforce and capacity pressures affecting specialist mental
health services.
Operational focus remains on maintaining service stability and improving access where possible within the available capacity. 
Consultant Outpatient WT - Learning Disability - 12wks (NHSL) (NORTH HOSTED)
Performance for Learning Disability outpatient waiting times reduced during Q3, with 75.0% of patients commencing treatment within 12 weeks. This represents a
change from the previous quarter, when performance was 100%, which was the level of performance reported consistently for a significant period of time.
The change in performance reflects the impact of cancellation of offered and then subsequently declined appointments within a small specialist cohort. The data has
been reviewed and per the recording rules, the recording practice is correct and reflects waits beyond the 12-week threshold at the end of the reporting period.
Given the low volume of referrals within this specialist service, a small number of cases can have a disproportionate impact on the quarterly percentage reported and
performance for this indicator can fluctuate significantly when individual cases fall outside the expected waiting time threshold. The current position should therefore be
interpreted cautiously and does not reflect a broader deterioration in service performance. 
10.  Medical Paediatrics Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
Medical Paediatrics WT - 12 wks (NHSL) (NORTH
HOSTED) 90%* 71.1% 77.2%   RED
Narrative & Corrective Action
Medical Paediatrics has found delivery of 90% target challenging to deliver throughout 2025/26. Positively, the Q3 result of 77.2% represents a 6.1% improvement on the
previous quarter and reverses the trend of a continued decline in the reported level of performance for this indicator.
The challenges and issues experienced by the service that prevent compliance with the targeted level of performance are multi-factorial, including a significant volume of
inappropriate referrals to specialist services and a reduced medical capacity due to absence. Despite the challenges and issues experienced by the service, local
unvalidated data suggests that there is further improvement likely to be realised in Q4, with an expected result of over 80% for this performance indicator. However,
there remains variance across areas and specialisms, which requires additional analysis.
The service continues to engage positively in service improvement activity, including stringent vetting of referrals to the service and work with universal pathways to offer
advice and support with earlier intervention alternatives to referral (sleep and toilet training). 
Page 69 of 146

Page 70

20 
11.  SLT Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
SLT - Paediatrics - 12wks (NORTH HOSTED) 90%* 79.9% 87.8% … … RED
Narrative & Corrective Action
Performance for both Paediatric and Adult Speech and Language Therapy waits improved significantly during Q3.
Paediatric waits performance of 87.8% represents a substantial improvement from the 16% reported in Q3 of 2024/25, demonstrating the impact of sustained service
redesign and operational improvement work undertaken over the past two years.
This improvement has been driven by targeted investment in service transformation and strong professional leadership across both universal and CYP pathways. The
service reports that early Q4 operational data shows continued positive momentum, with unvalidated figures indicating performance exceeding the 90% target for the
universal pathway.
The service will now focus on sustaining this level of performance and strengthening the consistency and accuracy of activity recording across universal, targeted, and
specialist pathways to ensure future reporting fully reflects delivery.
Adult Speech and Language Therapy also demonstrated strong performance during Q3. Earlier challenges had been associated with staffing absences; however, with
staffing levels now stabilised, performance has recovered. Early Q4 data indicates that this positive trajectory has been maintained, with the local data suggesting that
the performance is currently around 94.3%. 
12.  Complaints Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
Complaints Processed 20 Working Days (NHSL) 50% 26.0% 37.0%   RED
Narrative & Corrective Action
Performance for complaints processed within 20 working days remains below the 50% target for Q3. Analysis of complaints activity indicates that many complaints are
now resolved at Stage 1, reflecting an increased emphasis on early resolution where appropriate. While this approach supports a more responsive service for individuals
raising concerns, it can influence the overall performance indicator as the more complex complaints, where every effort has already been made to expedite a quick
resolution, progress to Stage 2 investigations and by their nature will necessitate a more complex and resource intensive, response.
Stage 2 complaints often involve multiple services or require detailed clinical review and therefore require more time to investigate and respond appropriately. This
complexity contributes to extended response times.
Page 70 of 146

Page 71

21 
For North Lanarkshire, 37% of Stage 2 complaints were responded to within 20 working days.
 48% (10/21) MH & LD     
 0% (0/1) Adult Services 
 33%  (3/9) Specialist Children’s Services   
 0%  (0/2)  Prison
 0%  (0/2)  Primary Care 
From the information available, 67% of delays were system related and 33% were justified.  Receiving comments from relevant colleagues regarding the complaint
continues to be the largest cause of delay (50%). 
Page 71 of 146

Page 72

22 
Work continues to strengthen complaints processes and improve reporting through the development of enhanced digital tools and improved statement collection
processes. This includes the introduction of a LanQip module to streamline statement collection and improve tracking of complaint investigations.
Further improvement activity focuses on strengthening the quality of learning from complaints, improving thematic reporting and ensuring that identified improvement
actions are monitored through governance structures.
A pan Lanarkshire ‘Learning and Improvement from complaints’ update was presented to CMT 5 January 2026. As part of this work, a thematic analysis was carried out
and found that between September – November 2025, across all complaint types, the top 5 pan-Lanarkshire themes that proceeded directly to Stage 2, given the severity
of the issues raised or multiple issues spanning multiple services, relate to:
 Care Planning/Co-ordination 
 Examination/monitoring  
 Disrespect 
 Communication – absent 
 Safety – Error
A learning actions dashboard has been developed on InPhase that tracks evidence of learning that has been communicated to complainants.  To maximise impact of this
dashboard, this development will require a refresh of processes and educational materials for colleagues to ensure that learning and root causes are actively identified,
communicated and then recorded for follow-up. This will be a NHSL True North action for 2026/27. 
13.  Care Homes Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
RAG Status
Page 72 of 146

Page 73

23 
Quarter Previous
Year
Care Home - Average Length of Stay 865 26.0% 37.0%   RED
Narrative & Corrective Action
The average length of stay in care homes increased during Q3 and remains above the target level. The length of stay in care homes is influenced by a range of structural
factors including complexity of need, availability of community alternatives and wider system pressures affecting hospital discharge and community flow. As such, short-
term movement in the indicator should be interpreted with caution.
Current operational activity continues to focus on strengthening Home First approaches and supporting discharge pathways that enable individuals to return home
wherever possible. Further analysis would be required to determine whether targeted interventions could meaningfully influence care home length of stay in future
reporting periods.
The number of care home placements per 1,000 population aged 65+ and 75+ reflects the continued emphasis within North Lanarkshire on supporting individuals to
remain in their own homes wherever possible through community-based support and enabling approaches. The relatively low rate of care home placements aligns with
the strategic direction of the Partnership’s balance of care approach, which prioritises independence and community-based care. 
14.  Smoking Cessation Target 2025/26 2024/25 Q4 2025/26 Q1 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
Sustain and embed successful smoking quits, at 12-
weeks post quit, in 40% of SIMD areas. (AOP) (NORTH
HOSTED)
545 *cumulative 239 for
2024/25 68 ... ... RED
Narrative & Corrective Action
Performance against the smoking cessation target remains below the expected trajectory. The indicator measures the cumulative number of individuals achieving a
successful quit at 12 weeks within the most deprived communities. The data is presented two quarters in arrears. Activity remains affected by lower referral volumes and
challenges associated with engagement within priority groups.
Table 1: All - North locality data April to June 2025/26 Q1 (40% most deprived) 
Locality Number of QDS
Number of 12 week
quits
Cumulative
target +/-
RAG on
Target
% 12 week quit
success % Lanarkshire rate
Airdrie 40 8 22.8 -14.8 35% 20% 24%
Coatbridge 50 9 22.8 -13.8 40% 18% 24%
Page 73 of 146

Page 74

24 
North 32 13 18.8 -5.8 69% 41% 24%
Bellshill 37 5 15.8 -10.8 32% 14% 24%
Motherwell 34 12 20.3 -8.3 59% 35% 24%
Wishaw 59 14 20.5 -6.5 68% 24% 24%
Please note: Table 1 includes both specialist and community pharmacy services 
Table 2: Specialist - North locality data April to June 2025/26 Q1 (40% most deprived)
Locality Number of QDS
Number of 12 week
quits
Cumulative
target +/-
RAG on
Target
% 12 week quit
success % Lanarkshire rate
Airdrie 10 4 7 -3.0 57% 40% 57%
Coatbridge 15 6 7 -1.0 86% 40% 57%
North 3 3 5.8 -2.8 52% 100% 57%
Bellshill 4 3 4.8 -1.8 63% 75% 57%
Motherwell 11 6 6.3 -0.3 95% 55% 57%
Wishaw 9 5 6.3 -1.3 79% 56% 57%
Please note: Table 2 includes community, pregnancy and mental health only 
QYW Community Pharmacy Service 
In 2025/26 (Q1) for all pharmacies in North Lanarkshire there were a total of 346 quit dates set (QDS) (All SIMD areas)
 108 clients (31%) had no smoking status recorded at their 4-week follow-up (i.e. blank follow-up).
 15 clients (13%) who had a successful quit at their 4-week follow-up had no smoking status recorded at their 12-week follow-up (i.e. blank follow-up).
Despite efforts made by the QYW Pharmacy Support Team to support community pharmacies there continues to be discrepancies in the completeness and accuracy of
data entered into the PCR system. These gaps may be affecting the accuracy of performance reporting to Scottish Government. 
Table 3: Pharmacy - North locality data April to June 2025/26 Q1 (40% most deprived)
Locality Number of QDS
Number of 12 week
quits
Cumulative
target +/-
RAG on
Target
% 12 week quit
success % Lanarkshire rate
Airdrie 30 4 15.8 -11.8 25% 13% 17%
Coatbridge 35 3 15.8 -12.8 19% 9% 17%
North 29 10 13.0 -3.0 77% 34% 17%
Bellshill 33 2 11.0 -9.0 18% 6% 17%
Page 74 of 146

Page 75

25 
Motherwell 23 6 14.0 -8.0 43% 26% 17%
Wishaw 50 9 14.3 -5.3 63% 18% 17% 
Operational work continues to strengthen referral pathways and improve engagement with communities experiencing the highest levels of deprivation. This includes
strengthening links with primary care, pharmacies and community partners to increase awareness and referral to cessation services. This includes:
 A Stop Smoking clinic specifically for clients with mental health will be made available within the Newmains Community Hub.
 Immunisation teams in North Lanarkshire will receive brief intervention and carbon monoxide monitor training in January 2026.
 A SBAR is being developed and will be presented to the Community Pharmacy Contractors Committee in February 2026, highlighting QYW current performance
and will provide recommendations for future improvement work.
 A test of change will be implemented within two community pharmacies located in North Lanarkshire.  The QYW Pharmacy Support Team will provide
behavioural support in addition to the support provided by the community pharmacies to improve the success of the client stopping smoking.
Data recording processes are also being reviewed to ensure that the activity delivered through partner services is appropriately captured within the reporting system.
While improvement initiatives continue, smoking cessation performance remains influenced by behavioural factors and engagement challenges that are likely to affect
the pace of improvement. 
15.  Unscheduled Care Target 2025/26 2025/26 Q1 2025/26 Q2 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
A&E Attendances - NL Residents 116,456  30,588 30,616  … AMBER
Emergency Admissions - NL Residents  44,001  11,750
Quarterly/ 2
quarters
behind
 … AMBER
Unscheduled Bed Days - all specialties, NL residents  294,999  82,077
Quarterly/ 2
quarters
behind
 … AMBER
Narrative & Corrective Action
These indicators represent different stages of the unscheduled care pathway and must be interpreted with recognition of the reporting lags associated with the available
data. A&E attendances are reported one quarter in arrears, while emergency admissions and unscheduled bed days are reported two quarters in arrears. As such, the
scorecard position does not reflect activity occurring during Q3 itself.
Page 75 of 146

Page 76

26 
Operational intelligence derived from the yet to be validated Q3 data indicates that pressure across the unscheduled care system remains significant. NHS Lanarkshire’s
compliance with the national 4-hour emergency department standard was 51.1% in December 2025, remaining below the Scottish average. Performance at site level was
50% at University Hospital Monklands and 54% at University Hospital Wishaw. Weekly performance during the period showed considerable variation, reflecting the
impact of fluctuating operational pressures.
Both acute sites experienced challenges affecting patient flow during the Q3 period, including Infection Prevention and Control restrictions, increased levels of seasonal
illness including flu and norovirus and higher levels of bed occupancy. Overall hospital occupancy across NHS Lanarkshire was 99.5% during December 2025. These
pressures contributed to longer lengths of stay, an increase in patients remaining in hospital for more than 14 days, and delays to admission and first clinical assessment.
Workforce pressures also affected operational capacity, including a short-term increase in staff sickness absence. In response, winter operational arrangements were
implemented, including the use of surge capacity and a system-wide command and control structure to manage emerging pressures.
A number of improvement actions are underway across NHS Lanarkshire to support improvement in patient flow. These include continued use of surge areas, expansion
of virtual ward capacity and testing of direct admission pathways to frailty services. Weekly Criteria to Reside audits continue to be undertaken collaboratively between
acute services and the Health and Social Care Partnership.
System-wide improvement continues through implementation of the Flow Foundation Bundle, the Target Operating Model and the Operation Flow improvement
programme. The Health and Social Care Partnership has also developed updated Unscheduled Care Improvement and Implementation Plans for 2025/26, which are
aligned to the Operation Flow strategy and informed by feedback from the Centre for Sustainable Delivery.
A continued focus remains on discharge planning processes and reducing same-day cancellations of supported discharges. A revised standard operating procedure has
been implemented in collaboration with the Flow Navigation Centre to address this issue and strengthen discharge planning arrangements.
Work is also underway to improve operational reporting across acute and community services, including development of enhanced digital reporting through Milan to
support improved oversight of discharge activity, social care referrals and discharge delays.
Despite these ongoing improvement efforts, demand and system pressures remain high. Continued collaboration between the acute sector and Health and Social Care
Partnerships is required to achieve sustained improvement in flow and system performance. 
16.  Training and Development Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
Sickness Absence (NHSL, North)  4% 7.05% 7.75%   RED
Sickness Absence (NLC) - days lost per person 9.22 8.15 12.99   RED
Narrative & Corrective Action
Page 76 of 146

Page 77

27 
There was a slight increase in the level of sickness absence among NHS Lanarkshire staff within University North Lanarkshire HSCP during Q3. For 2025/26, the target for
NHS Lanarkshire and University North Lanarkshire HSCP is to reduce sickness absence by 1%, bringing performance to 6% and moving closer to the national target of 4%.
Sickness absence levels increased during December 2025, reaching 8.74%. Local intelligence indicates that seasonal illness contributed significantly to this increase.
Absences related to colds, influenza and other respiratory illnesses were reported more frequently during December, which is consistent with patterns observed in
previous years. Historically, sickness absence levels tend to increase during the winter period due to seasonal illness pressures affecting the workforce.
Sickness absence continues to be monitored and managed in accordance with the relevant policies and procedures of each partner organisation. The NHS Lanarkshire
Absence Management Escalation Framework, implemented in April 2025, provides a structured approach to supporting staff during periods of sickness absence and
ensuring timely management intervention.
The framework ensures that appropriate support is offered to staff at an early stage of absence, including proactive engagement from Human Resources and
Occupational Health services. A range of contact methods are used to maintain engagement with staff during periods of absence, including written communication, direct
contact and discussion through sickness absence governance meetings.
Support mechanisms available to staff include occupational health assessment, counselling services and other wellbeing resources aimed at supporting staff recovery and
facilitating a timely and sustainable return to work where appropriate. 
17.  Training and Development Target 2025/26 2025/26 Q2 2025/26 Q3 Performance
Compared to
Previous Quarter
Performance
Compared to Same
Quarter Previous
Year
RAG Status
Records and information management 80% 80.0% 79.6%   AMBER
Fire Safety Training 90% 87.6% 88.9%   AMBER
Hand Hygiene Training  90% 86.0% 87.5%   AMBER
TURAS compliance (NHSL, North) 80% 75% 74%   RED
Narrative & Corrective Action
The majority of mandatory training indicators are assessed as RAG Green and targets are being met in most areas, however compliance with some mandatory training
courses remains below the targeted level for Q3. Workforce pressures and competing operational priorities are likely impacting on compliance with mandatory training
requirements. Local teams continue to encourage staff completion of mandatory training and monitor compliance. Work also continues at NHS Lanarkshire level to
review training systems and support improved recording and reporting. TURAS appraisal data is visible at senior levels and is available to support proactive management
of appraisal compliance
Performance for the NLC Records and Information Management training reduced marginally during the quarter to 79.6%, falling just below the 80% compliance
threshold. Compliance with mandatory training requirements continues to be monitored through Adult Social Work management arrangements, with services
Page 77 of 146

Page 78

28 
encouraged to prioritise completion of outstanding modules. Operational pressures and workforce availability continue to influence completion rates, particularly within
front-line services where releasing staff for training can present challenges.
Mandatory training and TURAS appraisal compliance remains an area of continued focus for operational managers and improvement activity will continue throughout the
remainder of the financial year to support progress toward the required compliance thresholds. 
Page 78 of 146

Page 79

29 
Direction from North Lanarkshire Integration Joint Board (IJB) 
1 Reference Number  
2 Report Title  
3 Date direction issued by IJB 
4 Date from which direction
takes effect 
5 Direction to: 
6 Does this direction
supersede, revise or revoke a
previous direction – if yes,
include reference number(s) 
7 Functions covered by
direction 
8 Full text of direction 
9 Budget allocated by
Integration Joint Board to
carry out direction 
10 Performance Management /
Governance arrangements 
11 Date direction will be
reviewed 
Page 79 of 146

Page 80

Page 80 of 146

Page 81

1 
REPORT   
Item No: 9 
SUBJECT: Internal Audit Progress Report 2025/26
TO: Integration Joint Board Performance, Finance & Audit Committee.
Lead
Officer for
Report:
Nicola Scott, Chief Finance Officer
Author(s) of
Report
Francis Scott, Chief Officer (Audit and Risk), North Lanarkshire
Council
Jocelyn Lyall, Chief Internal Auditor, NHS Lanarkshire
DATE:  20 May 2026 
1. PURPOSE OF REPORT
This paper is coming to the IJB for: 
For Approval: ☐ For Endorsement: ☐ To Note: ☒ 
2. ROUTE TO THE PFA
This paper has been: 
Prepared By:
Chief Officer
(Audit and
Risk), North
Lanarkshire
Council and
Chief Internal
Auditor, NHS
Lanarkshire)
☒ Reviewed By:
Chief Finance
Officer
☒ Endorsed By:
Chief Officer
☒
Item 9
Page 81 of 146

Page 82

2 
3.  EXECUTIVE SUMMARY
The progress in respect of the internal audit work for 2025/26 is summarised in
Appendix 1.  A workplan has been agreed to ensure the Internal Audit Plan
2025/26 is delivered to inform the annual internal audit opinion. 
4. RECOMMENDATIONS
4.1  It is recommended that the IJB Performance, Finance & Audit Committee: 
1) Consider the attached Progress Report at Appendix 1, the summary of
relevant partner reports at Appendix 2 and the final Financial Sustainability
report at Appendix 3. 
5.  VARIATIONS TO DIRECTIONS?
This section outlines if the report requires a direction to be issued to the Local
Authority, the Health Board, to both, or that no direction is required. 
6.  BACKGROUND
As stated in the Integrated Resources Advisory Group guidance, it is the
responsibility of the Integration Joint Board (IJB) to establish an adequate and
proportionate internal audit of the arrangements for risk management,
governance and control of the delegated resources.  The internal audit
arrangements for the IJB are provided jointly by the internal audit teams of
North Lanarkshire Council and NHS Lanarkshire.   
The IJB approved the Internal Audit Plan 2025/2026 on 21 May 2025.  A total
of 60 days has been committed and the plan has been designed to target the
priority issues which have been aligned to strategic risks, and to reflect the
evolving and complex challenges to service delivery. 
The Internal Audit Plan 2025/26 will provide sufficient evidence to form an
Internal Audit Opinion on the overall adequacy and effectiveness of the IJB’s
framework of governance, risk management and control arrangements.
The Internal Audit Plan 2025/26 also takes account of assurances which will be
provided to the IJB based on the work performed under the Internal Audit Plans
of both North Lanarkshire Council and NHS Lanarkshire.  The audit of
operational activities is being undertaken under the auspices of the partner
bodies.  The IJB is asked to note that the outcomes of these operational audits
are reported to the partner body Audit Committees and discussed with the IJB
Yes ☐ No ☒ N/A ☐
Page 82 of 146

Page 83

3 
Chief Officer and IJB Chief Financial Officer.  The assurances gained will be
provided to the IJB as part of the overall assurances received from the partner
body Audit Committees.   
We include a summary of relevant completed NHS Lanarkshire and North
Lanarkshire Council reports at Appendix 2. 
7.  SUMMARY OF KEY ISSUES
Progress with the 2025/26 plan is set out at Appendix 1. The summary of
relevant partner body reports is at Appendix 2. 
Progress since the February 2026 Performance, Finance & Audit Committee:
 Internal Audit NL05-26 Financial Sustainability has been finalised and
is appended at Appendix 3. Management has agreed to take action to
address two findings in the following areas:
o Reducing reliance on reserves through a robust governed
savings framework
o Improving financial reporting arrangements 
 The scope for Internal Audit NL06-26 Governance & Committee
Effectiveness has been agreed and work is in progress. The Chief
Officer and Chief Finance Officer have agreed that the performance
element of the original scope of the audit will be risk assessed for
inclusion in future Internal Audit work and the 2025/26 audit will focus
on governance and committee effectiveness. This reflects the content
of the revised and updated risk register, within which risk NLIJBR05:
Inadequate Performance Management is scored as medium and risk
NLIJBR06: Governance Failure is scored as High. 
From 1 April 2025, Public Sector Internal Audit Standards were replaced by the
Global Internal Audit Standards (GIAS), supported by an ‘Application Note –
Global Internal Audit Standards in the UK Public Sector’. Within the Local
Government context application of GIAS is also supported by the CIPFA ‘Code
of Practice for the Governance of Internal Audit in Local Government’ (The
Code). 
Internal audit teams must work in accordance with the new standards from 1
April 2025 and the Chief Internal Auditors are progressing GIAS development
work to build up conformance to GIAS. 
8. CONCLUSIONS
The Internal Audit Plan 2025/26 is designed to target the priority issues and to
provide sufficient evidence to form an Internal Audit Opinion on the overall
adequacy and effectiveness of the IJB’s framework of governance, risk
management and control arrangements.
Page 83 of 146

Page 84

4 
9. IMPLICATIONS 
9.1 NATIONAL OUTCOMES
Link(s) to National Health and Wellbeing Outcomes 
People are able to look after and improve their own health and
wellbeing and live in good health for longer. 
☐
People, including those with disabilities or long-term conditions, or
who are frail, are able to live, as far as reasonably practicable,
independently and at home or in a homely setting in their
community.
☐
People who use Health and Social Care Services have positive
experiences of those services, and have dignity respected.
☐
Health and Social Care Services are centred on helping to maintain
or improve the quality of life of people who use those services. 
☐
Health and Social Care Services contribute to reducing health
inequalities. 
☐
People who use Health and Social Care Services are safe from
harm.
☐
People who work in Health and Social Care Services feel engaged
with the work they do and are supported to continuously improve the
information, support, care and treatment they provide.
☐
Resources are used effectively and efficiently in the provision of
Health and Social Care Services. 
☒
9.2 ASSOCIATED MEASURE(S)  
Page 84 of 146

Page 85

5 
9.3 FINANCIAL
There are no financial impacts arising directly from this report.  
This paper has been reviewed by Finance: 
Yes   No  N/A 
9.4 RISK ASSESSMENT/RISK MANAGEMENT 
The internal audit planning process which produced the Annual Internal Audit
Plan considers the strategic risk profile of the organisation. Individual internal
audit assignments identify the key risks at the planning stage and our work is
designed to evaluate whether appropriate systems are in place and operating
effectively to mitigate the risks identified. Legislative requirements are a core
consideration in planning all internal audit reviews. 
Relevant Risk Register
Details 
Current Risk Level  Risk Owner 
NLIJBR06: Governance
Failure
High Chief Finance Officer
NLIJB-R01: Financial
Sustainability – Short Term
High Chief Finance Officer
NLIJB-R02: Financial
Sustainability – Medium Term
Very High Chief Finance Officer
NLIJB-R03: Financial
Sustainability – Long Term
Very High Chief Finance Officer 
9.5  ENGAGEMENT & PARTICIPATION
The Chief Officer and the Chief Finance Officer have both been consulted in respect
of the preparation of the Internal Audit progress report. 
9.6 INEQUALITIES & FAIRER SCOTLAND DUTY 
An EQIA & Fairer Scotland Impact Assessment Form is not required as there
are no EQIA implications arising directly from this report. 
All internal audit reviews which involve review of policies and procedures will
examine the way in which equality and diversity is incorporated within
documentation.  
Page 85 of 146

Page 86

6 
EQIA Completed & Fairer Scotland Impact Assessment Form Completed and
attached to report: 
Yes  No  N/A 
EQIA added to website: 
Yes  No  N/A 
10. BACKGROUND PAPERS 
N/A 
11. APPENDICES
Appendix 1 
Internal Audit Progress Report 2025/26 
Appendix 2 
Summary of Relevant NHS Lanarkshire and North Lanarkshire Council Reports
issued. 
Appendix 3
IJB Financial Sustainability Report 
CHIEF ACCOUNTABLE OFFICER (or Depute)   
Members seeking further information about any aspect of this report, please contact
the following:
Chief Finance Officer
Page 86 of 146

Page 87

Appendix 1
7
Ref Audit Indicative Scope Target
Audit
Committee
Planning
Stage
Work in
Progress
Draft
Issued
Completed Grade
Internal Audit Plan 2025/26
NL01-26 Audit Planning Agreeing audit universe and
preparation of internal audit
annual plan.
May 2025     N/A
NL02-26 Audit
Management 
Liaison with management,
liaison with Chief Finance Officer
and attendance at Audit
Committee.
Ongoing N/A N/A N/A N/A N/A
NL03-26 Audit Follow
Up
Review of progress made by
management in implementing
those actions committed to in
response to previously agreed
Internal Audit recommendations. 
August
2026
    
NL04-26 Annual Report Preparation for Annual Report
including assistance with
completion of IJB governance
self-assessment checklist.
June 2026     
Page 87 of 146

Page 88

Appendix 1
8
NL05-26 Financial
Sustainability
Effective, efficient and economic
use of resources to ensure
financial sustainability, with a
focus on transformation.
May 2026     Reasonable
Assurance
NL06-26 Committee
Effectiveness
Accurate, relevant and reliable
reporting to the Board, staff, the
SGHSCD and the public.
March 2026
June 2026 
    
Page 88 of 146

Page 89

Appendix 2
9
The following relevant reports have been issued by NHS Lanarkshire:
Report Audit Opinion Key findings
L02/26 Internal
Control
Evaluation
(ICE)
Reasonable
Assurance
The 2025-2026 Internal Control Evaluation is a key piece of work within the Internal Audit Plan, and 
provides an interim position statement for NHS Lanarkshire, highlighting any concerns to allow 
remedial work to be undertaken by year end.
Actions points have been noted in relation to the following:- 
 Code of Corporate Governance Review (risk assessed as moderate)
 Monitoring and tracking of external reports (risk assessed as moderate)
 In-depth review of risk mitigating controls (risk assessed as merits attention)
 Updating of the Register of Interest (risk assessed as merits attention)
Management have agreed appropriate action to address the findings from this audit. A follow-up of
implementation of the agreed actions will be undertaken in accordance with the current audit reporting
protocol within the agreed timescales. 
L05/26 Review
of Risk
Management
Strategy,
Standards and
operations 
Reasonable
Assurance
Key findings:
 The Code of Corporate Governance (May 2024) and SFIs (April 2024) do not align with the Risk
Management Strategy (March 2025) and Policy (November 2025)
 Data reported in risk reports presented to Assurance Committees is not taken from InPhase, the
primary system for recording risks; risks are retrospectively approved after being created in
InPhase
 More than half of the corporate risks are out with risk appetite. Assurance Committee minutes do
not always provide a clear record of robust risk discussion and consideration of whether controls
are operating as expected, and whether additional controls are required.
 Risks are not always reviewed in a timely manner.
 Use of the optimal and tolerable zones demonstrating whether a risk is within or out with the zone
for risk appetite has not been reported consistently against the standard criteria
 The Audit and Assurance Committee Key Lines of Enquiry document (Annex F) has not been
presented to the Audit & Risk Committee (ARC) since March 2024
 Corporate Management Team (CMT) minutes and papers did not evidence horizon scanning
 There is no Standard Operating Procedure (SOP) for InPhase risk management processes. We
have been informed this is a planned development. Desktop Procedures have not been reviewed,
updated as appropriate and approved by the established Review Date, albeit no major changes
to the Procedures have been required and they remain fit for purpose.
Page 89 of 146

Page 90

Appendix 2
10 
Report Audit Opinion Key findings 
Agreed Action:
 Management has agreed that relevant content will be aligned to ensure core governance
documentation is consistent.
 Inphase process and reports will be revised to ensure that the reports presented are driven from
the most recent Inphase update.
 Relevant discussion will be included in the minutes and action taken to ensure that risk reports
are consistent.
 Annex F will be presented to the March 2026 ARC. A SOP will be developed which will cover the
process highlighted in the findings.
L06/26 Review
of Staff &
Patient
Environment –
Fire Safety
Reasonable
Assurance
The audit reviewed compliance with DL (2024) 28 - 'Fire Safety Policy for NHS Scotland' and assessment
of whether processes for fire risk assessment, fire safety control book audits and fire safety training comply
with NHS Assure fire safety requirements. 
Key findings:
 Internal Audit identified potential enhancements to the assurance provided on compliance with fire
safety duties, and assurances that there is no management contravention of the Fire (Scotland)
Act 2005 and the Fire Safety (Scotland) Regulations 2006.
 The Quarter 1 2025/26 Fire Safety report was not presented to the Corporate Management Team.
Quarter 2 2025/26 Fire Safety Report was presented to the 22 December 2025 CMT, following
issue of this draft report. 
Agreed Actions:
 A Short Life Working Group will review Key Performance Indicators. Site Directors will be
contacted to remind them of their statutory fire safety responsibilities and a system put in place
via the Fire Safety Group secretariat to escalate on a quarterly basis when no report or information
is submitted.
 Quarterly Fire Reports and ad hoc reports will be submitted to CMT and Finance & Resources
Sub-Committee for discussion and action
Page 90 of 146

Page 91

Appendix 2
11 
Report Audit Opinion Key findings
L12/26 Review
of
Whistleblowing
Reasonable
Assurance
This audit reviewed systems designed to ensure compliance with National Whistleblowing Standards. 
Key findings:
 The Whistleblowing SOP was not reviewed and updated by the scheduled date of February 2025.
The extant SOP does not contain sufficient information relating to the role of the Confidential
Contacts and there is no separate SOP for Confidential Contacts. 
Agreed Action:
 The Whistleblowing SOP will be reviewed and will include more detailed information on the role of
confidential contacts. 
The following relevant report has been issued by North Lanarkshire Council in this period.
Report Audit Opinion Key findings
0150.2026.001
Self-Directed
Support
Limited
Assurance
This audit reviewed the Council’s arrangements for ensuring that SDS budgets are calculated fairly and
consistently in line with guidance and are monitored to ensure that they are being used appropriately by
service users. 
While we found strong financial oversight arrangements and no evidence of incorrect budgets or misuse
of SDS funds, significant weaknesses were identified in the application of agreed procedures, the
retention of key documentation and the consistency of Direct Payment (DP) monitoring.  These
weaknesses could lead to DP funds being misused without detection or not being used in line with
assessed needs and agreed outcomes, potentially affecting the support being received by individual
service users and exposing the Council to potential financial loss and reputational damage. 
Further areas for improvement were noted relating to the consistent application of DP management and
monitoring procedures across all localities, updating the SDS Good Practice Guide, strengthening
procedures for retaining key documentation and consistently applying agreed SDS procedures and
establishing a formal training programme. 
Page 91 of 146

Page 92

Appendix 3 
12
INTERNAL AUDIT REPORT 
IJB FINANCIAL SUSTAINABILITY 
Headlines
The Integration Joint Board (IJB) continues to face a complex range of challenges and significant financial
pressures arising from increasing demand for health and social care services, rising costs and limited
options for generating additional income. The IJB is exposed to the financial pressures of NHS Lanarkshire
and North Lanarkshire Council, as its financial position is directly shaped by the level of resources
delegated by its partners and the cost pressures arising within delegated services. As a result, the IJB has
limited flexibility in mitigating these pressures. Collectively, these factors make setting a balanced budget,
while continuing to deliver statutory services, progressively more challenging.
In February 2025, the Accounts Commission highlighted the critical financial position facing Scotland’s
IJBs, noting that despite a real-terms increase in funding, rising cost pressures and diminishing reserves
require decisive action and difficult choices on service delivery.
The purpose of this audit was to provide assurance on the adequacy and robustness of the IJB’s approach
to long-term financial sustainability. Based on the results of our work, we have categorised this audit as
providing reasonable assurance.  We were pleased to note that the IJB has an established financial
planning framework in place, supported by a clear annual financial planning cycle. This includes the
development of an annual Medium-Term Financial Plan (MTFP), underpinned by a Long-Term Financial
Outlook that provides oversight of forecast financial pressures through to 2035.  
At the time of the audit for the 2025/26 financial year, the IJB was reliant on reserves and non-recurring
budget to manage in-year financial pressures, which is not a sustainable long-term financial position.
However, we recognise that significant progress has been made following approval of the MTFP in March
2026. In particular, the introduction of a formal Savings Programme, with robust savings identified to
address the forecast budget gap. This has strengthened the IJB’s financial sustainability position by
supporting a reduction in reliance on reserves to balance the budget. 
Despite these improvements, the IJB’s financial outlook remains uncertain, and it is essential that Board
members and partners remain fully sighted on emerging financial pressures and continue to support active
monitoring, regular review, and timely decision-making. This will be critical to ensuring that plans are
developed and implemented effectively, enabling the IJB to progress towards long-term financial
sustainability.
We have highlighted some areas for improvement, which are detailed in section 3 of this report and include:
 A need to strengthen the IJBs financial sustainability by reducing reliance on reserves through a robust
governed savings framework.
 Scope to improve financial reporting arrangements to enhance transparency and support informed
decision making. 
Internal Audit Opinion  Reasonable assurance 
Priority of Recommendations High Medium Low
0 1 1 
Report status FINAL Audit ref 0500/2026/004 Date issued 28/04/2026
Audit Team Kimberley Hall and Lesley Armstrong
Issued To Chief Finance Officer (NL HSCP)
Copied To Chief Officer (NL HSCP)   Page 92 of 146

Page 93

Appendix 3 
13
1.  Executive Summary 
Objectives
The audit sought to provide assurance on the following areas: 
 There are robust financial planning processes in place, aligning strategic objectives to a medium to long
term financial strategy. Key assumptions, risk and uncertainties are clearly stated and appear
reasonable.
 There are appropriate oversight and accountability for financial decisions, with board members, senior
officers and other stakeholders receiving timely and relevant financial information and being engaged
in financial planning processes decision making. 
 Progress against identified savings options is monitored, reported and followed up where required and
is there a strategy in place to manage the use of reserves.
Work undertaken by NLC Internal Audit included obtaining appropriate evidence, holding discussions with
relevant officers, and reviewing the IJB’s approach to long‑term financial sustainability to determine whether
it is adequate and robust.
This engagement has been conducted in accordance with the Global Internal Audit Standards. 
We would like to thank officers involved in this audit for their cooperation and assistance. 
2.  Findings and Recommendations 
Good practice identified
We noted the following areas of good practice during the audit:
 The IJB has an established financial planning cycle, with an annual Medium‑Term Financial Plan
(MTFP) supported by a Long‑Term Financial Outlook (LTFO) providing visibility of financial pressures
up to 2035.
 The introduction of updated Medium‑Term Financial Outlook (MTFO) reports in September and
December ensures emerging pressures are identified early and reflected in financial planning ahead of
the formal March budget‑setting cycle.
 The long-term financial planning aligns the MTFP and LTFO with the Strategic Commissioning Plan,
ensuring resources support key priorities. 
 The IJB has introduced a formal Savings Programme as part of the MTFP. This includes, for each
proposed saving, a risk rating, risks and impacts, forecast savings, and alignment to the Strategic
Commissioning Plan.
 Quarterly budget monitoring reports are presented the IJB providing timely updates on outturns,
variances, financial risks, savings delivery and reserves. 
 The Chief Finance Officer holds regular Senior Management Team meetings with finance colleagues
from both NLC and NHSL to discuss emerging financial risks, with any significant issues escalated
promptly. These discussions feed into the quarterly financial monitoring reports, ensuring senior officers
and Board members are kept informed.
 Budget liaison sessions are held with board members prior to setting the MTFP in March, ensuring
members receive timely and relevant financial information to make informed decisions and set a
balanced budget. 
Key areas requiring management action (High)
No key areas requiring urgent management action have been identified. 
Other areas for improvement (Medium)
One area for improvement was identified: 
 There is a need to strengthen the IJBs financial sustainability by reducing reliance on reserves
through a robust governed savings framework. 
Page 93 of 146

Page 94

Appendix 3 
14
3. Action Plan IJB FINANCIAL SUSTAINABILITY 0500/2026/004 
Ref Finding
1 There is a need to strengthen the IJB’s financial sustainability by reducing reliance on reserves through a robust governed savings framework.
Financial performance reported to the Performance, Finance and Audit (PF&A) Committee in 2025/26 shows a continued reliance on reserves and non-recurring budget measures to
support the IJBs financial position. The February 2026 report forecasts a £14.9m budget gap, with only £4.9m of approved savings expected to be delivered. Non‑recurring budget
measures are being used to offset most of this pressure, reducing the projected year‑end overspend to £1.9m. This demonstrates the IJBs reliance on one-off measures to bring the
financial position to a manageable level. 
The MTFO report, which was reported to the IJB in December 2025 provides an in-year update on the MTFP. The report projects a three-year cumulative gap of £80.905m, including a
gap of £38.177m for 2026/27. The IJB useable reserves balance at the time of the report was £36.560m lower than the projected deficit for 2026/27, demonstrating that the IJB does not
hold sufficient reserves to manage the level of financial pressures it faces. 
The 2026/27 MTFP presented to the IJB in March 2026 provided a more positive outlook, with the updated total three year forecasted budget gap of £67.464m, down £13.441 from the
December. The reduction was as a result of increased grant-aided expenditure from NLC, indicating that the IJB is reliant on partnership additional funding and/or reserves to balance the
budget. The MTFP sets out that any in-year shortfalls in savings delivery will be managed through the prudent use of contingency and risk‑based reserves and confirms that reserves will
be used to support project management capacity to deliver transformation and the approved savings programme. This demonstrates a strategic but increasing reliance on reserves, both
to address immediate financial pressures and to facilitate the redesign needed to achieve future savings. While this approach provides short-term stability, it also highlights that the IJB’s
ability to deliver longer-term financial sustainability and transformation is partly dependant on reserves, reinforcing the need for close monitoring and prudent reserve management. 
Review of the approved 2025/26 MTFP identified that information on savings and service redesign was limited and lacked transparency, providing only a brief description and overall high-
level totals with no detail on what makes up the savings proposal, risks, or what underpins the savings. It was confirmed that the IJB historically operated with no formal savings process,
contributing to the limited clarity. We recognise recent improvements in this area, including the introduction of a standardised savings template and monthly SMT and budget liaison
sessions, which provide IJB Board members with opportunities to discuss savings proposals. There has also been the integration of the new savings programme, which uses a risk-based
approach to develop recurring savings options. The new approach allows for each saving option to set out the risk rating, scope of saving, risks, alignment to the Strategic Commissioning
Plan, forecast savings amount and mitigations, this standardised approach which has been adopted allows for enhanced transparency. 
The MTFP for 2026/27 proposes the establishment of a dedicated Savings Board, chaired by the Chief Officer, to strengthen oversight through monthly monitoring and early identification
of undeliverable savings, with progress also reported quarterly to the PF&A Committee. However, these arrangements are still at an early stage, and do not yet provide a robust structure
for effective scrutiny or challenge. Given the IJB’s continued reliance on reserves and non-recurring budget, there is an increasing need for recurring savings that are realistic, deliverable
and clearly justified. At present, when approved savings become unachievable, the shortfall is met through drawdown of reserves or other one-off measures. This approach is not
sustainable, and it is important that the IJB identifies alternative recurring savings where proposals cannot be delivered, to reduce reliance on reserves to manage in-year pressures.
Implication Recommendation Priority Management response Implementation
Date
The IJB may be unable to
maintain financial sustainability
due to over-reliance on
reserves and non-recurring
measures and insufficient
recurring savings increases the
risk of future overspends and
limits the IJB’s ability to
manage significant financial
pressures.
The Chief Finance Officer (NL HSCP) should:
(1) Progress with the development of a sustainable
longer-term financial strategy underpinned by
recurring savings and reduced reliance on
non-recurring budget and reserves, including a
process to identify alternative recurring savings where
approved proposals become unachievable.
(2) Progress with establishing a dedicated Savings Board
to strengthen governance and transparency of
savings. 
Medium
Agree – Nicola Scott, Chief Finance Officer
The 2026/27 budget gap is fully met by a programme of savings
approved at the IJB in March 2026 without reliance on reserves.  
A Savings and Value Board has been established, with the first
meeting scheduled for 28th April to agree the documented Terms
of Reference. The meetings will take place monthly with the main
focus being to monitor progress against the approved savings. If
these cannot be achieved, Senior Managers will need to identify
and approve alternatives which will be reported to the IJB. 
April 2026
Page 94 of 146

Page 95

Appendix 3 
15
3. Action Plan IJB FINANCIAL SUSTAINABILITY 0500/2026/004 
Ref Finding
2 There is scope to improve financial reporting arrangements to enhance transparency and support informed decision making. 
The MTFP workings are based on a range of risk-based scenarios, envisaged, pessimistic and optimistic over a three-year planning period. While the envisaged scenario includes a full
breakdown of pressures, recurring and non-recurring funding and the resulting funding gap, the pessimistic and optimistic scenarios are presented only as headline budget-gap figures
with no supporting detail. The lack of transparency over the underpinning assumptions and components of these scenarios limits Board members’ ability to understand the scale and
drivers of the projected budget gaps, reduces insight into the financial implications of alternative scenarios, and restricts informed decision‑making by weakening scrutiny of the underlying
assumptions and risks.
We also noted that the MTFP that is reported and approved annually, and the MTFO reported in September and December, do not present the overall financial position in a single
consolidated view. Instead, information on pressures, savings, reserves and outturn position are reported across different sections of the reports, making it more difficult for Board members
and stakeholders to clearly understand the full finance forecast and drivers influencing the projected outturn position.
Implication Recommendation Priority Management response Implementation
Date
The IJB may not have a complete or
fully informed understanding of the
IJB’s financial position due to the lack
of scenario detail, increasing the
likelihood of ineffective decision
making.
The Chief Officer (NL HSCP) should consider:
(1) Providing full supporting detail for all three risk-based
scenarios to enable effective scrutiny. 
(2) Improving the clarity and transparency of financial reporting,
with consideration being given to a single consolidated
financial overview. 
Low
Agree – Nicola Scott, Chief Finance Officer
The financial outlook which will be prepared for
IJB in September will incorporate these
recommendations. 
September 2026 
Page 95 of 146

Page 96

Appendix 3 
16
APPENDIX 1 – Audit Grading
Audit reports are graded with an overall assurance opinion, and any issues and associated
recommendations are classified individually to denote their relative importance, in accordance with
the definitions in the tables below. 
Definition of audit assurance and recommendation categories
Assurance Confidence based on sufficient evidence that internal controls are in place,
operating effectively and objectives are being achieved. 
Assurance opinion definitions
Substantial
Assurance
A sound system of governance, risk management and control exists, with internal
controls operating effectively and being consistently applied to support the
achievement of objectives in the area audited.
Reasonable
Assurance
There is a generally sound system of governance, risk management and control
in place. Some issues, non-compliance or scope for improvement were identified
which may put at risk the achievement of objectives in the area audited.
Limited
Assurance
Significant gaps, weaknesses or non-compliance were identified. Improvement is
required to the system of governance, risk management and control to effectively
manage risks to the achievement of objectives in the area audited.
No
Assurance
Immediate action is required to address fundamental gaps, weaknesses or non-
compliance identified. The system of governance, risk management and control
is inadequate to effectively manage risks to the achievement of objectives in the
area audited. 
Recommendation priority definitions
High
Significant control failure or weakness that, if not addressed, may lead to a major
financial, operational or reputational risk to the organisation and/or significantly
impact the successful delivery and achievement of the objectives of the area under
review.  Urgent/Immediate action is required.
Medium
Control failure or weakness that, if not addressed, may lead to a moderate financial,
operational or reputational risk to the organisation.  Weakness may be individually
significant but is unlikely to affect the successful delivery and achievement of the
overall objectives of the area under review.  The risk of error would, however, be
significantly reduced if corrective action was taken.  Prompt action is required.  
Low
Control failure or weakness that may lead to a minor financial, operational or
reputational risk to the organisation.  Weakness does not appear to significantly
affect the ability to meet objectives.  Minor issue raised to improve the efficiency
and effectiveness of controls. 
Page 96 of 146

Page 97

1 
REPORT   
Item No: 10 
SUBJECT: Draft Internal Audit Plan 2026/27
TO: Integration Joint Board Performance, Finance & Audit Committee.
Lead
Officer for
Report:
Claire Ray, Chief Officer
Author(s) of
Report
Francis Scott, Chief Officer (Audit and Risk), North Lanarkshire
Council
Jocelyn Lyall, Chief Internal Auditor, NHS Lanarkshire
DATE: 20 May 2026 
1. PURPOSE OF REPORT
This paper is coming to the IJB PFA for: 
For Approval: ☒ For Endorsement: ☐ To Note: ☐ 
Item 10
Page 97 of 146

Page 98

2 
2. ROUTE TO THE BOARD
This paper has been:
Prepared By:
Chief Officer
(Audit and
Risk), North
Lanarkshire
Council and
Chief Internal
Auditor, NHS
Lanarkshire)
☒ Reviewed By:
Chief Finance
Officer
☒ Endorsed By:
Chief Officer
☒
3.  EXECUTIVE SUMMARY
The Internal Audit Plan 2026/27 is designed to provide sufficient evidence to
form an assessment of the overall adequacy and effectiveness of the IJB’s
framework of governance, risk management and control arrangements.
The planning process for 2026/2027 has taken cognisance of the Global
Internal Audit Standards, which  require an internal audit plan that supports
achievement of the organisation’s objectives.
The proposed Internal Audit Plan for 2026/2027 has been designed to target
the priority issues.  It seeks to align to strategic risks and takes account of
assurances which will be provided to the IJB based on the work performed
under the Internal Audit Plans of both North Lanarkshire Council and NHS
Lanarkshire for 2026/2027.         
4. RECOMMENDATIONS
4.1 It is recommended that the IJB Performance, Finance & Audit Committee: 
(1) Approve the proposed Internal Audit Plan for 2026/2027 (Appendix 1);
(2) Approve the recommendation by the Chief Financial Officer that the joint
working arrangements between the North Lanarkshire Council (NLC) and
NHS Lanarkshire (NHSL) Internal Audit teams continue in order to deliver the
IJB Internal Audit Service; and 
(3) Approve the delegation of authority to the Chief Finance Officer to agree
with the Chief Officer (Audit and Risk) (NLC) and the Chief Internal Auditor
(NHSL) the scope of the audit assignments in the Internal Audit Plan for
2026/2027 including the allocation of responsibilities for completion of
assignments. 
Page 98 of 146

Page 99

3 
5.  VARIATIONS TO DIRECTIONS?
This section outlines if the report requires a direction to be issued to the Local
Authority, the Health Board, to both, or that no direction is required      
6.  BACKGROUND
Standard 9.4 of the Global Internal Audit Standards (GIAS) set out the need to
create an internal audit plan that supports achievement of the organisation’s
objectives.
GIAS Standard 9.4 states that ‘the Chief Audit Executive must base the internal audit
plan on a documented assessment of the organisation’s strategies, objectives and
risks. This assessment must be informed by input from the board and senior
management, as well as the chief audit executive’s understanding of the organisation’s
governance, risk management and control processes’. 
The internal audit plan must:
 Consider the internal audit mandate and the full range of agreed to internal audit
services
 Specify internal audit services that support the evaluation and improvement of
the organisation’s governance, risk management and control processes
 Consider coverage of information technology governance, fraud risk, the
effectiveness of the organisation’s compliance and ethics programmes, and
other high risk areas
 Identify the necessary human, financial and technological resources necessary
to complete the plan
 Be dynamic and updated timely in response to changes in the organisation’s
business, risks, operations, programmes, systems, controls and organisational
culture.
 The Chief Audit Executive must review and revise the internal audit plan as
necessary and communicate timely to the board and senior management:
 The impact of any resource limitations no internal audit coverage
 The rationale for not including an assurance engagement in a high risk area or
activity in the plan 
7.  SUMMARY OF KEY ISSUES
The Internal Audit Plan is designed to provide the Chief Officer (Audit and Risk) of
North Lanarkshire Council (NLC) and the Chief Internal Auditor of NHS Lanarkshire
(NHSL) with sufficient evidence to form an overall independent and objective annual
conclusion on the organisation’s governance, risk management, and control.
It therefore includes the delivery of standard products required each year and is
based on professional judgement of audit need based on the IJB’s risk environment. 
Yes ☐ No ☒ N/A ☐
Page 99 of 146

Page 100

4 
In addition, account is taken of assurance which can be provided to the IJB based on
work performed under the Internal Audit Plans of both parties.  The Internal Audit
Plan describes how the available resources will be utilised during the year. 
Integrated Resource Advisory Group (IRAG) Finance Guidance states that it is the
responsibility of the IJB to establish adequate and proportionate internal audit
arrangements. This will include a review of the adequacy of the arrangements for
risk management, governance, and control of the delegated resources.
A joint internal audit arrangement is in place for the North Lanarkshire IJB with input
from Internal Audit teams at both NLC and NHSL. The internal audit programme of
work and the annual Internal Audit opinion are therefore delivered jointly by the Chief
Officer (Audit and Risk) of NLC and the Chief Internal Auditor of NHSL. 
8. CONCLUSIONS
The proposed Internal Audit Plan for 2026/2027 is attached at Appendix 1 for
consideration and approval.  
The Committee is asked to delegate authority to the Chief Financial Officer to agree
with the Chief Officer (Audit and Risk) of NLC and the Chief Internal Auditor of NHSL
the scope of the audit assignments in the Internal Audit Plan for 2026/2027 including
the allocation of responsibilities for the completion of assignments. The Chief Officer
and the Chief Financial Officer will consult with both partners.
Internal Audit Plan 2026/2027 
The proposed Internal Audit Plan for 2026/2027 totals 60 days and is attached as an
appendix for approval. We have reviewed the extant risk register of the organisation
and we have consulted the Chief Officer and Chief Finance Officer to ensure the
substantive audit assignment in 2026/27 adds maximum value.  The IJB’s Internal
Auditors will flexibly adjust the plan as required if risks change throughout the year. 
Of the 60 days available, 27 days relate to standard audit deliverables of audit
planning, audit management, the provision of the annual internal audit report and the
follow-up of previously agreed actions. Progress reports will be presented to the
Performance, Finance & Audit Committee during the year. 
40 days have been allocated to assess workforce planning arrangements including:
workforce planning to ensure alignment to service delivery; adequacy of workforce
resilience; and review of arrangements to ensure compliance with the Health and
Care (Staffing) (Scotland) Act 2019. This work will be undertaken jointly by the North
Lanarkshire Council and NHS Lanarkshire Internal Audit teams. 
Page 100 of 146

Page 101

5 
9. IMPLICATIONS
9.1 NATIONAL OUTCOMES
Link(s) to National Health and Wellbeing Outcomes 
People are able to look after and improve their own health and wellbeing
and live in good health for longer 
☒
People, including those with disabilities or long-term conditions, or who are
frail, are able to live, as far as reasonable practicable, independently and at
home or in a homely setting in their community
☒
People who use Health and Social Care Services have positive
experiences of those services, and have dignity respected
☒
Health and Social Care Services are centred on helping to maintain or
improve the quality of life of people who use those services 
☒
Health and Social Care Services contribute to reducing health inequalities  ☒
People who use Health and Social Care Services are safe from harm ☒
People who work in Health and Social Care Services feel engaged with the
work they do and are supported to continuously improve the information,
support, care and treatment they provide
☒
Resources are used effectively and efficiently in the provision of Health and
Social Care Services 
☒
9.2 ASSOCIATED MEASURE(S) 
9.3 FINANCIAL  
This paper has been reviewed by Finance: 
Yes  X No  N/A 
9.4 RISK ASSESSMENT/RISK MANAGEMENT 
Relevant Risk Register
Details 
Current Risk Level  Risk Owner 
NLIJ-R06: Governance
Failure
High (12) Chief Finance Officer
NLIJB-R08: Workforce
Availability and Capacity 
Medium (8) Head of Health / Head
of Adult Social Work /
Nursing Director 
Page 101 of 146

Page 102

6 
The management of risk is an integral part of the development of the Internal Audit
Plan. The Internal Audit Plan 2026/2027 has also been informed by the draft Internal
Audit Opinion 2025/2026 and an assessment of current and ongoing risks. 
9.5  ENGAGEMENT & PARTICIPATION
The Chief Officer and the Chief Financial Officer have both been consulted in
respect of the preparation of the Internal Audit Plan 2026/2027.
Objectives  Further details 
☐ Involve stakeholders in the development
work aimed at achieving the national 
outcomes
N/A
☐ Provide stakeholders with information on
how to get involved
N/A
☐ Ensure a diverse range of engagement
and participation and opportunities are in 
place to suit different needs 
N/A
☐ Measure how well we involve community
stakeholders in the planning, design 
and delivery of our services 
N/A
☐ Provide regular feedback on how
stakeholder engagement and participation is 
shaping and influencing service
development and delivery
N/A
☐ Provide support to enable stakeholder
representatives to participate meaningfully
and confidently at meetings
N/A
☐ Develop participation guidelines to ensure
a common understanding and set of 
expectations for both stakeholders and
partnership staff
N/A
☐ Support engagement planning and
participation in localities, taking account of 
other engagement activity and local plans
across the Community Planning 
Partnership
N/A 
Page 102 of 146

Page 103

7 
9.6 INEQUALITIES & FAIRER SCOTLAND DUTY 
EQIA Completed & Fairer Scotland Impact Assessment Form Completed and
attached to report: 
Yes  No  N/A X 
EQIA added to website: 
Yes  No  N/A X 
10. BACKGROUND PAPERS
N/A   
11. APPENDICES
Appendix 1 – Draft internal audit plan 2026/27 
CHIEF ACCOUNTABLE OFFICER (or Depute)   
Members seeking further information about any aspect of this report, please contact
the following:
Francis Scott, Chief Officer (Audit and Risk), North Lanarkshire Council) – Scott
Fr@northlan.gov.uk
Jocelyn Lyall, Chief Internal Auditor (NHS Lanarkshire) – Jocelyn.lyall2@nhs.scot 
Page 103 of 146

Page 104

Appendix 1 
Internal Audit Plan 2026/27 
8
Ref Audit Indicative Scope Strategic
risk
Days
NL01-27 Audit
Planning
Preparation of internal audit
annual plan 2026/27.
Full IJB risk
register
considered
1
NL02-27 Audit
Management 
Liaison with management and
external audit, liaison with Chief
Finance Officer and attendance
at Audit Committee.
N/A 7
NL03-27 Audit Follow
Up
Review of progress made by
management in implementing
those actions committed to in
response to previously agreed
Internal Audit recommendations. 
N/A 5
NL04-27 Annual
Report
Prepare and present an annual
report containing the Annual
Internal Audit Opinion for
2026/2027.
Full IJB risk
register
considered
7
NL05-27 Workforce Assessment of the design and
effectiveness of workforce
planning
arrangements including:
ensuring alignment to service
delivery; adequacy of workforce
resilience; and review of
arrangements to ensure
compliance with the Health and
Care (Staffing) (Scotland) Act
2019.
NLIJB-R08:
Workforce
Availability
and Capacity 
40 
Page 104 of 146

Page 105

REPORT 
Item No: 11 
1. PURPOSE OF REPORT
1.1 This paper is coming to the Performance, Finance and Audit (PFA) Committee:   
For approval  For endorsement  For noting 
1.2 The purpose of this report is to seek approval of proposed changes to the Chief
Finance Officer (CFO) role, which are intended to strengthen financial governance,
resilience and workforce planning arrangements for the Integration Joint Board.
2. ROUTE TO THE PERFORMANCE, FINANCE AND AUDIT COMMITTEE
2.1 This paper has been: 
Prepared By:
Chief Officer
☒ Reviewed By:
Chief Officer
☒ Endorsed By: ☐ 
3.       RECOMMENDATIONS
3.1  It is recommended that the PFA Committee: 
(1) Acknowledge the contents of this report and the rationale for the proposed
changes to the CFO role.
(2) Approve the proposed changes to the CFO role, as set out in this report,
recognising the additional support being provided by North Lanarkshire
Council.
(3) Note that the proposed arrangements are designed to strengthen governance,
reduce single‑point‑of‑failure risk, and improve workforce and succession
planning, with no reduction in service to the Integration Joint Board (IJB). 
4. VARIATIONS TO DIRECTIONS 
5. Background
5.1 The IJB continues to operate in a highly challenging financial environment, with
increasing demand pressures and significant financial risk concentrated largely
within adult social care. The scale and complexity of these pressures require strong,
resilient and well-integrated financial leadership.
SUBJECT: Chief Finance Officer Role
TO: Performance, Finance and Audit Committee
Lead Officer for Report: Chief Officer
Author(s) of Report Chief Officer 
DATE: 20 May 2026
Yes  No  N/A 
Item 11
Page 105 of 146

Page 106

5.2 The CFO role is a statutory post under section 95 of the Local Government
(Scotland) Act 1973 and is central to good governance, financial stewardship and
strategic planning. Recent national audit findings have highlighted the increased
vulnerability of IJBs where there is insufficient resilience around statutory financial
roles, particularly in the context of workforce shortages and recruitment challenges
at senior levels.
5.3 In parallel, North Lanarkshire Council is reviewing its wider finance arrangements,
providing an opportunity to strengthen integration, improve resilience and align
financial leadership across the system while protecting the independence of
statutory advice provided to the IJB.
6 PROPOSAL
6.1 It is proposed that the IJB CFO role be adapted to operate as a dual role, combining
the statutory CFO responsibilities for the IJB with a substantive role within the
Finance Management Team of North Lanarkshire Council.
6.2 Under this arrangement:
 The CFO will remain the statutory section 95 officer to the IJB and a full member
of the Partnership Senior Management Team.
 The CFO will also be embedded within the Council’s senior finance leadership
structure, improving alignment with council-wide budget setting, medium-term
financial planning and risk management.
 Responsibility for the Adult Social Care finance team within the Council will
transfer into the remit of the dual role.
 Certain operational duties will be delegated to appropriately qualified finance
managers and accountants, supported by a clear governance and delegation
framework.
6.3 North Lanarkshire Council will provide additional capacity and support to ensure that
the IJB continues to receive a full and effective finance service, with no detriment to
service delivery.
7. RATIONALE
7.1 The proposed changes are intended to deliver clear and measurable benefits: 
Avoidance of single point of failure 
The current model places significant reliance on a single individual for statutory,
strategic and operational finance responsibilities. The dual-role approach increases
resilience by embedding the CFO within a broader finance leadership team and
enabling effective delegation and cover arrangements. 
Improved workforce and succession planning 
The changes support more sustainable workforce planning by widening access to
finance expertise, reducing over-reliance on one postholder and creating clearer
succession and contingency arrangements. 
Stronger integration and governance 
Closer alignment with council financial leadership strengthens whole-system
planning, enhances governance and provides earlier visibility of risks and pressures. 
Page 106 of 146

Page 107

Enhanced strategic capacity 
Delegating routine operational tasks allows the CFO to focus on strategic
leadership, financial sustainability, transformation and assurance areas of
increasing importance given the financial outlook.
8. IMPACT
8.1 The proposed changes to the CFO role are designed to strengthen resilience and
governance arrangements while maintaining, and in some areas enhancing, the
level of financial support provided to the IJB.
8.2 Impact on the IJB 
There will be no reduction in the capacity or quality of financial support provided to
the IJB. The CFO will continue to operate independently in their statutory role,
providing objective advice and assurance to the Board.
8.3 Impact on partnership working 
Relationships with NHS Lanarkshire Finance and Management Teams will remain
unchanged and will continue to be supported through regular senior-level
engagement. The proposals are expected to further strengthen partnership working
across finance teams.
8.4 Financial impact 
The dual-role arrangement will result in a partial sharing of salary costs with North
Lanarkshire Council. While the precise value is still to be finalised, an indicative
saving to the IJB of approximately 25% of salary costs has been identified, with no
associated service reduction.
9. LEARNING FROM THE ACCOUNTS COMMISSION REPORT
9.1 The Accounts Commission’s report on Clackmannanshire and Stirling Integration
Joint Board (March 2026) provides an important national case study on the risks
associated with insufficient resilience around the statutory CFO (section 95 officer)
role.
9.2 In that case, the IJB’s substantive CFO resigned in August 2025 and left post in
October 2025. Despite collaborative and well‑intentioned support from partner
organisations’ finance leads, the IJB operated for approximately nine weeks without
a formally appointed section 95 officer. During this period, financial management
functions continued and partnership working remained strong; however, no
individual was formally designated to discharge the statutory responsibilities of the
role.
9.3 The Accounts Commission concluded that, while day-to-day financial administration
was maintained, the legal requirement to appoint a section 95 officer was not met.
The Commission described this as a serious governance failure by the IJB and its
partners, particularly given explicit warnings raised at an IJB meeting during the
period of vacancy. Of specific concern was the absence of formal contingency
arrangements and the provision of assurance to Board members that statutory
requirements were being met when this was not the case.  As a result, the Controller
of Audit exercised statutory reporting powers to draw the matter to the Accounts
Commission’s attention. 
Page 107 of 146

Page 108

9.4 Therefore the proposed changes to the CFO role directly reflect these national
findings and expectations. By strengthening resilience, reducing reliance on a single
postholder, embedding clearer delegation and governance arrangements, and
aligning the CFO role more closely with a wider finance leadership structure, the IJB
is proactively addressing the risks highlighted by the Accounts Commission. These
changes are intended to ensure statutory compliance is maintained at all times,
even during periods of staff turnover or absence, while improving workforce planning
and long-term sustainability.
10. ASSURANCE
10.1 The Committee can be assured that the proposed changes to the CFO role have
been explicitly designed to address the risks and lessons identified by the Accounts
Commission. The arrangements strengthen compliance with statutory
requirements, improve resilience and continuity for the section 95 officer role, and
provide clear, formal governance, delegation and contingency arrangements.
10.2 The proposals have been reviewed and approved by the Chief Executive of North
Lanarkshire Council and are supported by the Chair and Vice Chair of the IJB,
providing further assurance of their robustness and alignment with best practice. In
addition, the enhanced support being provided by North Lanarkshire Council
ensures that there will be no reduction in the level or quality of financial support to
the IJB, while improving workforce planning and reducing reliance on a single
postholder.
10.3 Taken together, these measures position the IJB strongly to meet current and future
financial challenges and to avoid the governance risks experienced elsewhere in
the sector.
11. NEXT STEPS
11.1 Subject to Committee approval:
i. Revised role descriptions, delegation arrangements and governance
documentation will be developed in conjunction with HR.
ii. Clear reporting lines and accountability arrangements will be formally
documented to ensure transparency and independence of the CFO’s statutory
role.
iii. North Lanarkshire Council will complete a capacity review of the relevant finance
teams.
12.  IMPLICATIONS
12.1 NATIONAL OUTCOMES  
People are able to look after and improve their own health and wellbeing
and live in good health for longer 
☐
People, including those with disabilities or long-term conditions, or who are
frail, are able to live, as far as reasonably practicable, independently and at
home or in a homely setting in their community
☐
People who use Health and Social Care Services have positive
experiences of those services, and have dignity respected
☐
Health and Social Care Services are centred on helping to maintain or
improve the quality of life of people who use those services 
☐
Page 108 of 146

Page 109

Health and Social Care Services contribute to reducing health inequalities  ☐
People who use Health and Social Care Services are safe from harm ☐
People who work in Health and Social Care Services feel engaged with the
work they do and are supported to continuously improve the information,
support, care, and treatment they provide
☐
Resources are used effectively and efficiently in the provision of Health and
Social Care Services 
☒
12.2 ASSOCIATED MEASURE(S) 
The implementation of agreed actions will strengthen financial governance,
resilience and workforce planning arrangements 
12.3 FINANCIAL 
This paper has been reviewed by Finance: 
Yes  No  N/A 
12.4 RISK ASSESSMENT/RISK MANAGEMENT 
The strategic financial risks detailed in the IJB Risk Register has been updated
where necessary and are included in a separate report to the IJB. 
Relevant Risk Register Details  Current Risk Level  Risk Owner 
Financial Sustainability – Short Term High Nicola Scott
Financial Sustainability – Medium Term Very High Nicola Scott
Financial Sustainability – LongTerm Very High Nicola Scott
Governance Failure High Nicola Scott
Failure to meet Legislative
Requirements
High Pauline Izat /
Morag Dendy /
Joanne Jenkins 
12.5 ENGAGEMENT & PARTICIPATION 
Please tick the engagement and participation objectives that link(s) with this piece
of work and provide further details on the engagement and participation that was
undertaken. 
Objectives  Further details 
☐ Involve stakeholders in the development work aimed at   
achieving the national outcomes 
☒ Provide stakeholders with information on how to get
involved
☐ Ensure a diverse range of engagement and participation
and opportunities are in place to suit different needs 
☐ Measure how well we involve community stakeholders in
the planning, design, and delivery of our services 
☒ Provide regular feedback on how stakeholder engagement
and participation is shaping and influencing service
development and delivery
Page 109 of 146

Page 110

☒ Provide support to enable stakeholder representatives to
participate meaningfully and confidently at meetings
☐ Develop participation guidelines to ensure a common
understanding and set of 
expectations for both stakeholders and partnership staff
☐ Support engagement planning and participation in
localities, taking account of 
other engagement activity and local plans across the
Community Planning 
Partnership 
12.6  INEQUALITIES & FAIRER SCOTLAND DUTY
Equality and Diversity Impact Assessment Completed & Fairer Scotland Impact
Assessment Form Completed and EQIA added to website: 
Yes  No  N/A 
13. BACKGROUND PAPERS 
None. 
14. APPENDICES 
None         
Chief Officer   
Members seeking further information about any aspect of this report, please contact
Claire Rae
Page 110 of 146

Page 111

Page 111 of 146

Page 112

Page 112 of 146

Page 113

REPORT 
Item No: 12 
1. PURPOSE OF REPORT
1.1 This paper is coming to the Performance, Finance and Audit (PFA) Committee:   
For approval  For endorsement  For noting 
1.2 This report provides an outline of the actions agreed with the External Auditor,
Internal Auditor, and the Senior Management Team to further develop the IJB
governance framework. 
2. ROUTE TO THE PERFORMANCE, FINANCE AND AUDIT COMMITTEE
2.1 This paper has been: 
Prepared By:
Chief Finance
Officer
☒ Reviewed By:
Chief Officer
☒ Endorsed By: ☐ 
3.       RECOMMENDATIONS
3.1  It is recommended that the PFA Committee: 
(1) Acknowledge the contents of the report; and
(2) Agree that further progress reports will be presented to future meetings of the
PFA Committee in respect of the ongoing actions. 
4. VARIATIONS TO DIRECTIONS 
5. ANNUAL GOVERNANCE STATEMENT ACTION PLAN
5.1 As part of the statutory annual accounts, an Annual Governance Statement is
included which reports on the effectiveness of the IJB’s governance arrangements
and system of internal control and explains how the IJB complies with the Code of
Corporate Governance and meets the requirements of ‘Delivering Good
Governance in Local Government’ framework developed by CIPFA and SOLACE in
2016. 
5.2 To ensure continual improvement of the IJB’s governance arrangements, an action
plan is included within the Annual Governance Statement which was approved at
the IJB in June 2025.  Included within this are improvement areas identified by Audit
Scotland within their Annual Audit report, Internal Audit as part of their annual audit
SUBJECT: Annual Governance Statement – Action Plan Progress
TO: Performance, Finance and Audit Committee
Lead Officer for Report: Chief Officer
Author(s) of Report Chief Financial Officer 
DATE: 20 May 2026
Yes  No  N/A 
Item 12
Page 113 of 146

Page 114

work as well as improvements highlighted as part of the IJB self-assessment
process. 
5.3 Following conclusion of the 2024/25 External Audit, the Annual Audit Report
identified 1 recommendation with regards to financial sustainability therefore this
has been added to the action plan. 
6 ACTION PLAN PROGRESS
6.1 Appendix 1 details the actions as well as progress against these actions.  For audit
purposes, all actions will remain on the plan for a full financial year however those
completed during the year will be removed for the first report after April 1st each
year.  Table 1 provides a summary of the status of the actions. 
Table 1 
Year the
action was
identified
Total
Actions
Completed
Actions
Ongoing
Actions
2022/23 2 2 0
2023/24 5 4 1
2024/25 3 1 2
2025/26 1 1 0
TOTAL 11 8 3 
7.  IMPLICATIONS
7.1 NATIONAL OUTCOMES  
People are able to look after and improve their own health and wellbeing
and live in good health for longer 
☒
People, including those with disabilities or long-term conditions, or who are
frail, are able to live, as far as reasonably practicable, independently and at
home or in a homely setting in their community
☒
People who use Health and Social Care Services have positive
experiences of those services, and have dignity respected
☒
Health and Social Care Services are centred on helping to maintain or
improve the quality of life of people who use those services 
☒
Health and Social Care Services contribute to reducing health inequalities  ☒
People who use Health and Social Care Services are safe from harm ☒
People who work in Health and Social Care Services feel engaged with the
work they do and are supported to continuously improve the information,
support, care, and treatment they provide
☒
Resources are used effectively and efficiently in the provision of Health and
Social Care Services 
☒
7.2 ASSOCIATED MEASURE(S) 
The implementation of agreed actions will contribute to the ongoing development of
the internal control framework and will also inform the Annual Governance
Statement for 2025/26. 
Page 114 of 146

Page 115

7.3 FINANCIAL 
This paper has been reviewed by Finance:
Yes  No  N/A 
7.4 RISK ASSESSMENT/RISK MANAGEMENT 
The strategic financial risks detailed in the IJB Risk Register has been updated
where necessary and are included in a separate report to the IJB. 
Relevant Risk Register Details  Current Risk Level  Risk Owner 
Governance Failure Low Pauline Izat/Morag
Dendy/Joanne
Jenkins 
7.5 ENGAGEMENT & PARTICIPATION 
Please tick the engagement and participation objectives that link(s) with this piece
of work and provide further details on the engagement and participation that was
undertaken. 
Objectives  Further details 
☒ Involve stakeholders in the development work aimed at   
achieving the national 
outcomes
This report
includes all
engagement and
participation
objectives as
effective
governance
arrangements
ensure the IJB
can fulfil its
statutory duties. 
Good governance
enables the IJB to
pursue its vision
effectively as well
as underpinning
that vision with
mechanisms for
control and
management of
risk.
☒ Provide stakeholders with information on how to get
involved
☒ Ensure a diverse range of engagement and participation
and opportunities are in 
place to suit different needs 
☒ Measure how well we involve community stakeholders in
the planning, design, and delivery of our services 
☒ Provide regular feedback on how stakeholder engagement
and participation is shaping and influencing service
development and delivery
☒ Provide support to enable stakeholder representatives to
participate meaningfully and confidently at meetings
☒ Develop participation guidelines to ensure a common
understanding and set of 
expectations for both stakeholders and partnership staff
☒ Support engagement planning and participation in
localities, taking account of 
other engagement activity and local plans across the
Community Planning 
Partnership 
7.6  INEQUALITIES & FAIRER SCOTLAND DUTY
Equality and Diversity Impact Assessment Completed & Fairer Scotland Impact
Assessment Form Completed and EQIA added to website: 
Yes  No  N/A  Page 115 of 146

Page 116

8. BACKGROUND PAPERS 
None. 
9. APPENDICES 
Appendix 1   Annual Governance Statement – Action Plan Progress   
Appendix 2   Briefing Note – Outstanding Audit Action – Hosted Services 
Chief Finance Officer   
Members seeking further information about any aspect of this report, please
contact Nicola Scott on telephone number 07581 007187.
Page 116 of 146

Page 117

Appendix 1 
Annual Government Statement - Action Plan Progress                        
Reference Improvement Area Agreed Action Responsible
Person
Projected
Completion
Date
Current Status Ongoing /
Complete
2022/23: 1 Service Level
Agreement (SLA)
To agree an SLA with Children, Families and
Justice for future hosting arrangements
following the budget disaggregation exercise. 
Work is currently underway to agree, approve
and implement the new SLA in partnership with
Children, Families and Justice Services. 
Chief Officer
Claire Rae
September
2025
Following a full review with Senior Managers within Finance,
Adults Social Care and Education and Families a robust
framework for financial governance of hosted services has
been agreed.  This will see the development of a combined
Revenue Budget Monitoring Report specifically for hosted
services as well as the introduction of budget governance
meetings.   A briefing note outlining the proposal which has
been agreed by Chief Officers is included at Appendix 2 for
information. 
Complete
2022/23: 2 National Care Service To develop a sound understanding of the
impact for the Partnership of the National Care
Service legislation.   Paper presented to the
IJB in January 24 giving an update on
timescales for implementation.  Further
updates will be presented to the board as
details are released.
Chief Officer
Claire Rae
September
2025
This action is no longer relevant given the changes from the
proposed NCS to the Care Reform Bill.  The Senior
Management Team will keep abreast of ongoing
developments and report to the IJB as necessary.
Complete.       
2023/24: 1 2023/24 Self-
Assessment Agreed
actions
1. Development of a revised framework for
North Lanarkshire which will ensure
engagement and participation in the
development of the Strategic Commissioning
Plan across the entire health and social care
system. 
Chief Officer
Claire Rae
December
2025
The development of a new Strategic Commissioning Plan is
underway with a view to the new plan coming into effect from
April 2026, upon expiry of the current Strategic
Commissioning Plan 2023-2026.
An engagement and consultation process has been initiated
to ensure a wide range of staff, people who use services,
carers and partner organisations have an opportunity to
participate in shaping the next commissioning plan.
This was reported to the IJB on 17th September 2025
Strategic Commissioning Plan 2026 and Beyond
Complete  
2.  Undertake an exercise to review
performance output and associated data from
other Health Boards and Local Authorities. 
Chief Officer
Claire Rae
December
2025
Benchmarking is undertaken within our family group of local
authorities against all national performance indicators and
reported within the Annual performance report.
Annual Performance Report 2024/25 - DRAFT
Complete  
3.  Recognition that there is a formalised risk
sharing agreement in place with NHSL, NLC
and SL IJB within the risk management
strategy but no reference to similar in relation
to performance and finance.
Chief Officer
Claire Rae
December
2025  This remains under review to consider whether a formalised
agreement is required and what this would consist of.  A
decision will be taken by the end of this financial year.
Ongoing
2023/24: 2 Presentation of
financial and non-
financial information
in the annual
accounts
In the production of future accounts, the IJB
should review the presentation of both financial
and non-financial information to ensure this
reflects the organisation’s role as a strategic
commissioning body.
Chief Finance
Officer
Nicola Scott
September
2025
A review of other IJB’s accounts was undertaken to ascertain
the style and content of their Annual Reports.  Using this, the
format of the 2024/25 Annual Report was updated which has
been accepted by Audit Scotland.
Complete
2023/24: 3 Presentation of
financial and non-
financial information
in the financial
performance reports
The financial reports will be further defined to
give an overview in the delivery of services
against the overall funding aligned to the
Strategic Commissioning Plan and Medium-
Term Financial Plan/Long Term Financial Plan
including earmarked reserves. 
Chief Finance
Officer
Nicola Scott
September
2025
An updated report, taking into account Audit Scotland’s
recommendations, has been prepared for the first quarter. 
This was presented to PFA in August 2025 and has been
accepted by Audit Scotland as part of their 2024/25 External
Audit.  
Complete
Page 117 of 146

Page 118

Appendix 1 
Reference Improvement Area Agreed Action Responsible
Person
Projected
Completion
Date
Current Status Ongoing /
Complete
2024/25: 1 2024/25 Self-
Assessment   
Agreed actions
1. Holding to Account - effective scrutiny,
challenge and support of services by the
Management Team and IJB members when
reviewing presented papers. 
Chief Officer
Claire Rae
December
2025 
Work on this will be undertaken as part of updating the
standing orders in Q2 2026.
Ongoing  
2.  Vision for IJB should be clear and ambitious
with membership being diverse and engaged. 
Management team to review induction process
and liaison sessions. 
Chief Officer
Claire Rae
December
2025
Work on this is underway and will be finalised along with the
renewal of the Strategic Commissioning Plan in June 2026.
Ongoing  
3. Review what goes to IJB and PFA and
ensure there are appropriate development
sessions to support the financial picture. 
Chief Officer
Claire Rae
December
2025
A workplan has been prepared for 12months for both PFA
and IJB and presented to both for approval.  This is a live
document that can be added to as necessary.
There has also been a series of IJB Development Sessions
scheduled for the remainder of 2025 and Q1 2026 with
specific topics allocated including Finance and Risk.
Complete 
2025/26 Financial
Sustainability
The IJB should continue to:
 Develop and refine the arrangements it has
in place for securing financial sustainability,
including its medium and long term financial
plans and savings plans. 
 Work effectively in partnership with the local
council and the health board on service
transformation. 
 Apply its reserves strategy to effectively
manage the use of reserves to supplement
savings and efficiencies when required.
Chief Finance
Officer 
Nicola Scott
Ongoing It was agreed with the Audit Director that this action will
remain ongoing as there is no end date to this.  The
management response provided and included in the Final
Audit Report was as follows: 
A financial outlook for the 3 year period has been prepared
and is being presented to Board Members on 17th September
2025.  This outlines the forecast budget gaps for the next 3
years and will lead into Board Development sessions where
savings will be discussed for approval at a later Board.   
The outlook clearly identifies the current reserves position
and the impact non achievement on savings will have on
reserves. 
Discussions have taken place with both NLC & NHSL on the
forecast position and an Elected Members briefing session
within NLC was undertaken in June this year with another
scheduled in the Autumn to ensure all relevant parties are
aware of the forecast. 
The medium term and long term outlooks will continue to be
reviewed throughout the year with budget setting for 2026/27
set for March 2026. 
Complete 
There will be
ongoing
review as part
of the annual
financial
planning
arrangements.
Key 
Complete 
Ongoing – within projected completion timescale 
Ongoing – has exceeded projected completion date 
Page 118 of 146

Page 119

Appendix 2 
Page 1 of 6 
Briefing Note
Subject: Outstanding audit action - Hosted Services 
Prepared By: Paula Hendry and Scott McCrossan (Business Finance Managers)
For:
E&F - Alison Gordon (Chief Social Work Officer – Children, Families, Justice, and
Integrated Practice)
ASC - Claire Rae (Chief Officer – North Lanarkshire HSCP), Morag Dendy (Chief Officer
– Planning, Performance, and Quality Assurance), Diane Fraser (Chief Officer – Adult
Social Work Services)
Date: 9 March 2026
Background
At its meeting on 27 September 2018, the Policy and Resources Committee approved a
revised organisational structure, as set out in the Chief Executive’s report “We ASPIRE – A
Shared Ambition for North Lanarkshire.”  This restructure introduced substantial changes to
the Council’s management arrangements at that time. 
A key implication for the Health and Social Care service related to the realignment of ‘Children,
Families and Justice Services’. The associated budgets were to be transferred from ‘Health
and Social Care’ and incorporated within the newly established ‘Education and Families’
Service.  Consequently, the ‘Health and Social Care’ Service was redesignated as ‘Adult
Health and Social Care’. 
Following approval of the restructure, Finance prepared a series of discussion papers for the
relevant Chief Officers.  These papers supported the detailed consideration and agreement of
the budget lines to be transferred to Education and Families and those to be retained within
Adult Health and Social Care.  The budget transfers completed during 2019/20 and 2020/21. 
During these deliberations, it was recognised that a complete and distinct separation of all
budget areas was operationally impracticable.  As a result, certain budgets transferred to
Education and Families to continue to support both Services and were therefore “hosted”
within Education and Families.  Likewise, some budgets retained within Adult Health and
Social Care also supported both Services and continued to be “hosted” within that Service. 
Outstanding Audit Action
Following the disaggregation, recommendations were raised by Internal Audit (Financial Due
Diligence Report, May 2020) and External Audit (Annual Audit Report 2019/20,
September 2020) requiring the finalisation and implementation of hosting arrangements for
budgets relating to cross-cutting services associated with this disaggregation. This
requirement has also been captured as an improvement action within the IJB’s Annual
Governance Statement (AGS). 
Internal Audit has monitored progress on this action since 2020 through formal follow-up
processes.  In parallel, the IJB Chief Finance Officer has provided periodic progress updates
to the IJB Performance, Finance and Audit Committee as part of routine AGS action plan
reporting.  Management previously advised that progression of this audit action had been
paused pending further clarity on the Scottish Government’s proposals for a National Care
Service.   
Appendix 1 sets out extracts from the relevant audit reports alongside a summary of the
position as reported in the Internal Audit follow-up reports since the recommendation was
made along with the most recent progress update for the AGS action plan. 
Page 119 of 146

Page 120

Appendix 2 
Page 2 of 6 
Budget Composition 2025/26
For the 2025/26 financial year, the overall budget associated with North Lanarkshire’s Social
Work hosted services equates to c. £115.290m which has c. £6.143m and £109.147m hosted
within the Council’s Education and Families Service (General Fund) and Adult Social Care
Service (Integrated Joint Boad) respectively.  Appendix 2 provides a high-level, functional
breakdown of this budget for reference. 
There is a long-established practice within the respective Finance Teams and across the
relevant Services to ensure that associated budget areas are clearly identified and well
understood.  However, it is acknowledged that, in light of the outstanding audit action, overall
governance relating to how these budgets are utilised requires greater visibility and improved
oversight.   
Financial Governance and Reporting
To enhance financial governance and strengthen oversight across Social Work Hosted
Services, it is proposed that the Finance Team develop a combined Revenue Budget
Monitoring Report specifically for these hosted services. This report will present a clear and
comprehensive financial position, drawing together all relevant budget information into a single
monitoring framework.  It is intended that the report be issued to the designated Chief Officers
on a bi-annual basis, aligned with Period 6 and the Final Outturn. 
From a wider financial governance perspective, it is proposed that budget governance
meetings be convened on an as-required basis to provide a formal mechanism for
cross-service consideration of financial matters relating to the hosted budgets. These
meetings would support scrutiny and agreement on issues such as:
 requests for, and approval of, the utilisation of specific budgets outlined in Appendix 2 (e.g.
training allocations);
 project-related funding requirements;
 emerging cost pressures; and
 savings reviews and associated financial planning implications. 
Any decisions relating to these matters will require discussion and endorsement by the
relevant Chief Officers. To ensure robust oversight, attendance should ideally include the
aligned Business Finance Managers together with all associated Chief Officers.  However,
where timely decision-making is required, a minimum quorum of one Chief Officer from each
service area and one Business Finance Manager would be sufficient to ensure governance
standards are maintained while enabling prompt and co-ordinated action. 
Conclusion
The proposal outlined above establishes a proportionate and robust framework for the
financial governance of hosted services supporting North Lanarkshire’s social work functions.
Finance is of the view that implementing these arrangements will address, and enable closure
of, the outstanding audit action. 
The introduction of a bi-annual Revenue Budget Monitoring Report, providing a consolidated
financial position for Social Work Hosted Services, together with the proposed budget
governance meetings, will ensure that Chief Officers receive tailored, timely and
comprehensive financial and management information.  This enhanced reporting and
oversight structure will support cohesive, well-informed decision-making and strengthen
assurance over the effective use of hosted service budgets. 
Page 120 of 146

Page 121

Page 3 of 6 
Appendix 1: Social Work Hosted Services – Audit Recommendation and Management Response Extracts 
Internal Audit: Financial Due Diligence, May 2020 
Page 121 of 146

Page 122

Page 4 of 6 
Appendix 1: Social Work Hosted Services – Audit Recommendation and Management Response Extracts 
External Audit: Annual Report 2019/20, September 2020 
Page 122 of 146

Page 123

Page 5 of 6 
Appendix 1 (cont): Social Work Hosted Services – Audit Recommendation and Management Response Extracts 
Update Position on status of Audit recommendations as reported to IJB via Internal Audit Follow-Up Reports 
Position as at Apr 2021 Position as at Feb 2022 Position as at Apr 2023 Position as at June 2024 Position as at June 2025
The SLA for future
hosting arrangements
and associated budgets
had not yet been
presented to the IJB,
Adult Health and Social
Care Committee, or
Education and Families
Committee. 
Work was underway and
expected to conclude by
the end of April 2021.
Complete – the budget
disaggregation exercise
was concluded. The
revised IJB direction to
NLC (23 March 2021)
excluded the total budget
transfer for Children,
Families & Justice
Services. 
Ongoing – SLA
finalisation overdue.   
Revised Timeline: June
2022.
Complete – The budget
disaggregation exercise
remained concluded. 
Ongoing – SLA overdue
and paused pending
clarity around what
services will be part of the
new National Care
Service (NCS). 
Revised Timeline: TBC.
Complete – Budget
disaggregation
concluded. 
Ongoing – SLA overdue.
NCS timeframe delayed
further than intended by
Scottish Government. 
IJB will now consider
creating its own SLA with
Children Families and
Justice. 
Revised Timeline: TBC.
Budget disaggregation
complete. 
SLA still overdue with
limited progress due to a
change in the SMT. 
Action included in
Governance Statement
with new timescale to
review and finalise. 
Revised Timeline:
September 2025. 
Latest update position as reported to IJB at Performance, Finance and Audit Committee on 18 February 2026
Page 123 of 146

Page 124

Page 6 of 6 
Appendix 2: Social Work Hosted Services Budget Composition (2025/26) 
Hosted by Education and Families (General Fund)
Category No. of Cost Centres 2025/26 Budget
Admin 7 £5.287m
Locality running costs 6 £0.513m
Specific (Training – SW
Secondment Scheme)
2 £0.342m
TOTAL 16 £6.143m 
Hosted by Adult Social Care (IJB)
Category No. of Cost Centres 2025/26 Budget
SDS 83 £106.801m
Planning & Quality
Assurance (P&QA)
12 £1.597m
Business Process Change
& Improvement (BPC&I)
1 £0.636m
Equipment & Adaptation
Service (EAS)
3 £5.886m
Specific (includes MIST –
Emergency Planning &
Grounds)
2 £0.112m
TOTAL 101 £109.148m 
Following the conclusion of the Council’s 2026/27 Budget Master Process (c. June 2026), updated
budgetary information will be provided to the respective Chief Officers. 
Page 124 of 146

Page 125

1 
REPORT   
Item No: 13 
SUBJECT: IJB Risk Register
TO: North Lanarkshire Integration Joint Board
Lead
Officer for
Report:
Claire Rae, Chief Officer
Author(s) of
Report
Kerry Taylor, Business Support Manager
DATE: 20 May 2026 
1. PURPOSE OF REPORT 
This paper is coming to the IJB PFA for: 
For Approval: ☐ For Endorsement: ☐ To Note: ☒ 
2. ROUTE TO THE BOARD
This paper has been: 
Prepared By:
Kerry Taylor,
Business
Support
Manager
☒ Reviewed By:
Claire Rae,
Chief Officer
☒ Endorsed By: ☐ 
Item 13
Page 125 of 146

Page 126

2 
3. RECOMMENDATIONS
3.1 It is recommended that the IJB PFA: 
(1) considers the risks identified, the control measures in place, and the risk actions
in progress to mitigate their impact;
(2) makes recommendations it thinks appropriate to the Chief Officer in relation to
those risks, controls and actions 
4.  VARIATIONS TO DIRECTIONS?
This section outlines if the report requires a direction to be issued to the Local
Authority, the Health Board, to both, or that no direction is required         
5.  BACKGROUND
From a good practice and sound governance perspective, all public bodies
are required to identify and take account of the impact of any potential risks
in delivering their business. 
The IJB PFA Committee has delegated oversight and responsibility for
financial and performance risks associated with the remit of the Integration
Joint Board.
A new risk register was presented and approved at North Lanarkshire
Integration Joint Board in March 2026.   
NORTH LANARKSHIRE INTEGRATION JOINT BOARD RISK OVERVIEW 
Risks scoring between 16-25 are considered Very High, with two risks within
this category:
 NLIJB-R02: Financial Sustainability - Medium Term – Risk Score 20
 NLIJB-R03: Financial Sustainability - Long Term – Risk Score 16 
Risks scoring between 10-15 are considered High, with three proposed risks
within this category:
 NLIJB-R01: Financial Sustainability - Short Term – Risk Score 12
 NLIJB-R06: Governance Failure – Risk Score 12
 NLIJB-R09: Delayed Discharge – Risk Score 12 
Yes ☐ No ☐ N/A ☒
Page 126 of 146

Page 127

3 
Risks scoring between 5-9 are considered Medium, with four proposed risks
within this category: 
 NLIJB-R04: Performance Delivery – Risk Score 8
 NLIJB-R05: Inadequate Performance Management – Risk Score 6
 NLIJB-R07: Failure to Meet Legislative Requirements – Risk Score 7
 NLIJB-R08: Workforce Availability and Capacity – Risk Score 9 
NEXT STEPS
Members of North Lanarkshire Integration Joint Board are invited to discuss the
proposed risks, and if deemed appropriate to approve the new risk register.
Work is ongoing to develop a new risk management strategy in partnership with
NHS Lanarkshire and North Lanarkshire Council. This strategy has now been
drafted, with final amendments being made. This will be presented to the IJB
PFA in August 2026.  
It has been agreed for the North IJB risks to be recorded on the NHS
Lanarkshire risk recording system InPhase. The risks are currently in progress
of being added to InPhase. 
9.3 FINANCIAL  
This paper has been reviewed by Finance: 
Yes   No  N/A 
9.4 RISK ASSESSMENT/RISK MANAGEMENT 
Relevant Risk Register
Details 
Current Risk Level  Risk Owner 
New IJB Risk Register
Proposed
Choose an item. 
10. BACKGROUND PAPERS   
Page 127 of 146

Page 128

4 
11. APPENDICES
Appendix 1 – IJB Risk Dashboard (May) 
CHIEF ACCOUNTABLE OFFICER (or Depute)   
Members seeking further information about any aspect of this report, please contact
the following; Kerry Taylor  kerry.taylor@lanarkshire.scot.nhs.uk  
Page 128 of 146

Page 129

5 
Direction from North Lanarkshire Integration Joint Board (IJB) 
1 Reference Number  
2 Report Title  
3 Date direction issued by IJB 
4 Date from which direction
takes effect 
5 Direction to: 
6 Does this direction
supersede, revise or revoke a
previous direction – if yes,
include reference number(s) 
7 Functions covered by
direction 
8 Full text of direction 
9 Budget allocated by
Integration Joint Board to
carry out direction 
Page 129 of 146

Page 130

6 
10 Performance Management /
Governance arrangements 
11 Date direction will be
reviewed 
Page 130 of 146

Page 131

Executive Summary
• New risk register presented and approved at North Lanarkshire Integration Joint Board on 18 March 2026
• Work is ongoing in partnership with NHSL and NLC to develop new Risk Management Strategy
North Lanarkshire IJB Risks Dashboard – May 2026
Number of RisksRisk Register
9
North Lanarkshire Integration Joint
Board
Risk Movement Since Last Report
EscalatedNewDe-escalatedClosedDecreaseIncreaseNo Change
------9
NL IJB Risk Heat Map
0
1
2
3
4
5
6
Within Optimal
Zone
Within Tolerable
Zone
Out with Tolerable
Zone
IJB Risks
IJB Risk Appetite
0
111
2 21
4
5
Number of RisksRisk Register
Overview
2Very High (16-25)
3High (10-15)
4Medium (5-9)
0 Low (1-4)
1
Page 131 of 146

Page 132

Accountable
Officer
Risk OwnerCurrent Risk
Score
Tolerable
Zone
Optimal
Zone
Date
Opened
RiskRisk Ref
Chief OfficerChief Finance Officer125-91-418 March
2026
Financial Sustainability – Short
Term
NLIJB-
R01
Chief OfficerChief Finance Officer2010-155-918 March
2026
Financial Sustainability –
Medium Term
NLIJB-
R02
Chief OfficerChief Finance Officer1610-155-918 March
2026
Financial Sustainability – Long
Term
NLIJB-
R03
Chief OfficerHead of Planning,
Performance and
Quality Assurance
85-91-418 March
2026
Performance DeliveryNLIJB-
R04
Chief OfficerHead of Planning,
Performance and
Quality Assurance
65-91-418 March
2026
Inadequate Performance
Management
NLIJB-
R05
Chief OfficerChief Finance Officer125-91-418 March
2026
Governance FailureNLIJB-
R06
Chief OfficerHead of Health / Head
of Adult Social Work /
Nursing Director
65-91-418 March
2026
Failure to Meet Legislative
Requirements
NLIJB-
R07
Chief OfficerHead of Health / Head
of Adult Social Work /
Nursing Director
95-91-418 March
2026
Workforce Availability and
Capacity
NLIJB-
R08
Chief OfficerHead of Health / Head
of Adult Social Work
125-91-418 March
2026
Delayed DischargeNLIJB-
R09
North Lanarkshire IJB Risks Overview – March 2026
Page 132 of 146

Page 133

NLIJB-R01: Financial Sustainability - Short Term
Accountable
Officer Risk OwnerRisk Description
Chief OfficerChief Finance
Officer
The Public Bodies (Joint Working) (Scotland) Act 2014 requires IJB’s to set a balanced budget as
part of their strategic planning. This is essential for delivering integrated functions and budgets
under IJB’s control, as outlined in the Act’s statutory guidance.
There is a risk of North Lanarkshire Integration Joint Board not achieving a balanced budget within
the current year as approved by the IJB annually in March. 
Current Controls
• Chief Finance Officer (S95 officer)
• Due diligence by S95 officer on budget contributions from partner bodies each year as part of annual budget process
• Financial position monitored on ongoing basis by SMT, IJB Performance, Finance and Audit Committee and full IJB, underpinned by a
strong system of internal financial control and governance
• Financial position reported to NHSL Board and NLC Adult Care & Social Work Committee quarterly
• Monthly savings Board being introduced in 2026 to monitor progress against annual savings targets
• Financial Regulations in place
• NL Integration Scheme – agreed financial and budgetary responsibilities including for overspends against delegated IJB functions
• Ongoing monitoring of in year budget and key risk areas regularly reported to the Board
• Reserves strategy & policy in place
Actions
• Agree 2026/2027 budget and Medium-Term Financial Plan on 18 March 2026 - complete
• Continue to report financial position via SMT, IJB Performance, Finance and Audit Committee and full IJB
• Continue monthly meetings between Partner finance teams and budget managers to ensure variances are reported timeously
Risk Update
May 2026 – Risk approved on 18 March 2026 at
the North IJB.
Risk reviewed, one action to be closed.
New risk created on North HSCP L2 risk register
(NHSL) – ‘North HSCP Financial Sustainability’
Is current assessment within Risk Appetite?
No1-4Risk Appetite: Optimal Zone
No5-9Risk Appetite: Tolerable Zone
12
Page 133 of 146

Page 134

NLIJB-R02: Financial Sustainability - Medium Term
Accountable
Officer Risk OwnerRisk Description
Chief OfficerChief Finance
Officer
The Public Bodies (Joint Working) (Scotland) Act 2014 requires IJB’s to set a balanced budget as
part of their strategic planning. This is essential for delivering integrated functions and budgets
under IJB’s control, as outlined in the Act’s statutory guidance.
There is a risk of North Lanarkshire Integration Joint Board failing meet this statutory duty by not
delivering  financial balance over the medium three year financial planning cycle due to income
levels not keeping pace with increasing demand and costs pressures.
Current Controls
• Chief Finance Officer (S95 officer)
• Due diligence by S95 officer on budget contributions from partner bodies each year as part of annual budget process
• Medium Term Financial Outlook prepared and reported to IJB and Partners annually in September and December
• Medium term financial plan prepared annually as part of the annual budget setting process and approved by IJB each March
• Financial position monitored on ongoing basis by SMT, IJB Performance, Finance and Audit Committee and full IJB, underpinned by a
strong system of internal financial control and governance
• Monthly savings Board being introduced in 2026 to monitor progress against annual savings targets
• Financial Regulations in place
• NL Integration Scheme – agreed financial and budgetary responsibilities including for overspends against delegated IJB functions
• Reserves strategy and policy in place
Actions
• Agree 2026/2027 budget and Medium-Term Financial Plan on 18 March 2026 - complete
• Continue to report financial position via SMT, IJB Performance, Finance and Audit Committee and full IJB
• Savings proposals to be presented to IJB members early to allow full consideration before the budget is set in March
• Regular review of reserves to maximise funds that can be held in contingency to meet budget gaps
Risk Update
May 2026 – Risk approved on 18 March 2026 at
the North IJB.
Risk reviewed, one action to be closed.
New risk created on North HSCP L2 risk register
(NHSL) – ‘North HSCP Financial Sustainability’
Is current assessment within Risk Appetite?
No5-9Risk Appetite: Optimal Zone
No10-15Risk Appetite: Tolerable Zone
20
Page 134 of 146

Page 135

NLIJB-R03: Financial Sustainability - Long Term
Accountable
Officer Risk OwnerRisk Description
Chief OfficerChief Finance
Officer
Forecasting over an extended period remains inherently uncertain, particularly given the potential
for policy change, economic volatility and wider system pressures. Despite this uncertainty, it is
essential that the IJB adopts a long-term perspective to ensure it can identify emerging risks early
and take proactive steps to safeguard financial sustainability. 
There is a risk of North Lanarkshire Integration Joint Board not forecasting the long-term factors
appropriately resulting in being unable to achieve a balanced budget over the 10-year forecasting
timeline.
Current Controls
• Chief Finance Officer (S95 officer)
• Due diligence by S95 officer on budget contributions from partner bodies each year as part of annual budget process
• Long term financial outlook is presented alongside the Medium term financial plan annually
• Financial position monitored on ongoing basis by SMT, IJB Performance, Finance and Audit Committee and full IJB, underpinned by a
strong system of internal financial control and governance.
• Financial Regulations in place
• NL Integration Scheme – agreed financial and budgetary responsibilities including for overspends against delegated IJB functions
• Key risk areas regularly reported to the Board
• Reserves strategy and policy in place
Actions
• Continue to report financial position via SMT, IJB Performance, Finance and Audit Committee and full IJB
• Savings proposals to be presented to IJB members early to allow full consideration before the budget is set in March
• Regular review of reserves to maximise funds that can be held in contingency to meet budget gaps
• Long Term Financial Forecast to be presented to IJB in March each year along with the Medum Term Financial Plan
• Assumptions are updated annually using census date, OBR forecasts and demand forecasts from Partners
Risk Update
May 2026 – Risk approved on 18 March 2026 at
the North IJB.
Risk reviewed, no proposed changes.
New risk created on North HSCP L2 risk register
(NHSL) – ‘North HSCP Financial Sustainability’
Is current assessment within Risk Appetite?
No5-9Risk Appetite: Optimal Zone
No10-15Risk Appetite: Tolerable Zone
16
Page 135 of 146

Page 136

NLIJB-R04: Performance Delivery
Accountable
Officer Risk OwnerRisk Description
Chief Officer
Head of
Planning,
Performance
and Quality
Assurance
There is a risk of deterioration in performance delivery of the priorities and outcomes of the
Strategic Commissioning Plan due to required expenditure reduction, workforce supply challenges
and service demands resulting in North Lanarkshire Integration Joint Board not meeting its
statutory duty.
Current Controls
• Quarterly Performance reviews
• Benchmarking against national comparators
• Medium term and long-term financial forecasting in place
• Service redesign and innovation to progress implementation of the Strategic Commissioning Plan
• Regular reporting to IJB Performance, Finance and Audit Committee
Actions
• Draft Strategic Commissioning Plan for 2026-2029 to be presented to IJB in March 2026 - complete
• Final SCP to be presented in June 2026
Risk Update
May 2026 – Risk approved on 18 March 2026 at
the North IJB.
Risk reviewed, one action to be closed.
New risk created on North HSCP L2 risk register
(NHSL) – ‘Performance Delivery’
Is current assessment within Risk Appetite?
No1-4Risk Appetite: Optimal Zone
Yes5-9Risk Appetite: Tolerable Zone
8
Page 136 of 146

Page 137

NLIJB-R05: Inadequate Performance Management
Accountable
Officer Risk OwnerRisk Description
Chief Officer
Head of
Planning,
Performance
and Quality
Assurance
There is a risk that achieve key objectives will not be achieved due to processes for the review and
scrutiny of health and council performance either not being in place or are ineffective, resulting in
less than robust scrutiny arrangements, and failure to identify, challenge, or rectify poor
performance.
Current Controls
• Regular reporting to IJB Performance, Finance and Audit Committee
• Agreed outcomes / performance measures
• Robust performance management within NLC / NHSL
• Regular monitoring by IJB and SMT
• Annual performance report
Actions
• Draft Strategic Commissioning Plan for 2026-2029 to be presented to IJB in March 2026 - complete
• Final SCP to be presented in June 2026
Risk Update
May 2026 – Risk approved on 18 March 2026 at
the North IJB.
Risk reviewed, one action to be closed.
New risk created on North HSCP L2 risk register
(NHSL) – ‘Performance Delivery’
Is current assessment within Risk Appetite?
No1-4Risk Appetite: Optimal Zone
Yes5-9Risk Appetite: Tolerable Zone
6
Page 137 of 146

Page 138

NLIJB-R06: Governance Failure
Accountable
Officer Risk OwnerRisk Description
Chief OfficerChief Finance
Officer
There is a risk that less than robust scrutiny arrangements and appropriate internal processes and
procedures are either not in place or are ineffective, leading to a lack of leadership, accountability
or scrutiny, resulting in a failure to meet key objectives, financial overspends or reputational
damage.
Current Controls
• Chief Officer
• Chief Finance Officer (S95 officer)
• Standing Orders
• Financial Regulations
• Code of Conduct
• Local Code of Corporate Governance, Annual Governance Statement and Governance Issues Log
• Performance, Finance and Audit Committee
• Internal auditor, annual audit plan and internal audit annual report
• IJB Development sessions
Actions
• Appoint Standards Officer
• New Risk Management Strategy in progress – strategy has been drafted
• Review of IJB constitutional documents
• Timetable of future development sessions / training for IJB members
• New induction pack for IJB members
Risk Update
May 2026 – Risk approved on 18 March 2026 at
the North IJB.
Risk reviewed, no proposed changes.
Is current assessment within Risk Appetite?
No1-4Risk Appetite: Optimal Zone
No5-9Risk Appetite: Tolerable Zone
12
Page 138 of 146

Page 139

NLIJB-R07: Failure to Meet Legislative Requirements
Accountable
Officer Risk OwnerRisk Description
Chief Officer
Head of Health /
Head of Adult
Social Work /
Nursing Director
There is a risk that the IJB has limited ability to commission services efficiently due to financial and
workforce instability alongside demand pressures sufficiently resulting in failure to meet legislative
requirements (including safe staffing).
Current Controls
• Financial and performance monitoring reports to the IJB and IJB PFA
• Further information to be added
Actions
• Ongoing collaborative working with partners to deliver requirements under Health & Care Staffing Act, and escalation of arising
Risk Update
May 2026 – Risk approved on 18 March 2026 at
the North IJB.
Risk reviewed, no proposed changes at present.
Further review from SMT required.
Is current assessment within Risk Appetite?
No1-4Risk Appetite: Optimal Zone
Yes5-9Risk Appetite: Tolerable Zone
6
Page 139 of 146

Page 140

NLIJB-R08: Workforce Availability and Capacity
Accountable
Officer Risk OwnerRisk Description
Chief Officer
Head of Health /
Head of Adult
Social Work /
Nursing Director
There is a risk that full implementation of workforce plans can not be achieved due to financial and
demand pressures which could lead to longer term workforce difficulties, shortages in some skill
sets, negatively impacting on service delivery and the IJB’s ability to deliver the strategic plan.
Current Controls
• Lanarkshire Health and Social Care Workforce Plan 2025 – 2028 in progress
• NLC Workforce Plan
• Service transformation, including redesign/review of services
• Regular workforce monitoring
• Partnership working between NHSL and NLC HR Services with workforce reports presented to the HSCP SMT
Actions
• Ongoing collaborative working with partners to deliver requirements under Health & Care Staffing Act, and escalation of arising
Risk Update
May 2026 – Risk approved on 18 March 2026 at
the North IJB.
Risk reviewed, no proposed changes at present.
Further review from SMT required.
Is current assessment within Risk Appetite?
No1-4Risk Appetite: Optimal Zone
Yes5-9Risk Appetite: Tolerable Zone
9
Page 140 of 146

Page 141

NLIJB-R09: Delayed Discharge
Accountable
Officer Risk OwnerRisk Description
Chief Officer
Head of Health /
Head of Adult
Social Work
There is a risk that patients are not being discharged in a timely manner resulting in suboptimal
patient flow, impacting on poor patient and staff experience and poorer outcomes of care.
Current Controls
• Daily enabling hubs
• Senior decision makers within team to oversee
• Daily reporting of delays
• Home Assessment Model
• Home Care Redesign
• Escalation process in place
• weekly scrutiny meeting with HSCP senior managers present
• Weekly oversight meetings with whole system representation
• Agreed Target Operating Model implementation
• Close working with Acute Colleagues
• Criteria to Reside Audits
• Daily Dynamic Scheduling tool implemented within home care
Actions
• Deep Dive into current performance inclusive of daily meetings with Senior staff
• Home care redesign roll out/completion
Risk Update
May 2026 – Risk approved on 18 March 2026 at
the North IJB.
Risk reviewed, no proposed changes at present.
Further review from SMT required.
Is current assessment within Risk Appetite?
No1-4Risk Appetite: Optimal Zone
No5-9Risk Appetite: Tolerable Zone
12
Page 141 of 146

Page 142

Page 142 of 146

Page 143

NORTH LANARKSHIRE INTEGRATION JOINT BOARD PERFORMANCE, FINANCE AND AUDIT WORK PLAN 
Item  Lead Oicer  Meeting Date  Recurrence  Reason / Notes 
Wednesday 20 May 2026
Financial Monitoring - Final Outturn Chief Finance Oicer 20 May 2026 Quarterly 
Reserves Update Chief Finance Oicer 20 May 2026  
Annual Governance Statement
Actions - Progress Update
Chief Finance Oicer 20 May 2026  
IJB Performance Report (Q3) Head of Planning,
Performance & Quality
Assurance
20 May 2026 Quarterly 
Internal Audit Plan 2026/2027 Chief Oicer – Audit
and Risk (NLC) / Chief
Internal Auditor (NHS)
20 May 2026 Annual  
Internal Audit Progress Report
2025/2026
Chief Oicer – Audit
and Risk (NLC) / Chief
Internal Auditor (NHS)
20 May 2026 Quarterly  
IJB Risk Report Chief Oicer 20 May 2026 Quarterly   
Wednesday 19 August 2026
Financial Monitoring - Month 4 &
Period 4 (July)
Chief Finance Oicer 19 August 2026 Quarterly  
IJB Performance Report (Q4) Head of Planning,
Performance & Quality
Assurance
19 August 2026 Quarterly  
Internal Audit Progress Report
2025/2026
Chief Oicer – Audit
and Risk (NLC) / Chief
Internal Auditor (NHS)
19 August 2026 Quarterly  
IJB Risk Management Strategy Business Support
Manager
19 August 2026 Annual New Strategy for approval 
Item 14
Page 143 of 146

Page 144

NORTH LANARKSHIRE INTEGRATION JOINT BOARD PERFORMANCE, FINANCE AND AUDIT WORK PLAN 
Item  Lead Oicer  Meeting Date  Recurrence  Reason / Notes
IJB Risk Report Chief Oicer 19 August 2026 Quarterly   
Wednesday 21 October 2026
Financial Monitoring - Month 6 &
Period 6 (September)
Chief Finance Oicer 21 October 2026 Quarterly  
IJB Performance Report (Q1) Head of Planning,
Performance & Quality
Assurance
21 October 2026 Quarterly  
Internal Audit Progress Report
2025/2026
Chief Oicer – Audit
and Risk (NLC) / Chief
Internal Auditor (NHS)
21 October 2026 Quarterly  
IJB Risk Report Chief Oicer 21 October 2026 Quarterly   
Feb 2027
Financial Monitoring - Month 8 &
Period 9 (December)
Chief Finance Oicer 18 February 2026 Quarterly 
Reserves Strategy 2026/27 Chief Finance Oicer 18 February 2026 Annual 
Annual Governance Statement
Actions - Progress Update
Chief Finance Oicer 18 February 2026 Biannual  
IJB Performance Report (Q2) Head of Planning,
Performance & Quality
Assurance
18 February 2026 Quarterly 
Internal Audit Progress Report
2025/2026
Chief Oicer – Audit
and Risk (NLC) / Chief
Internal Auditor (NHS)
18 February 2026 Quarterly  
External Audit Report Chief Finance Oicer 18 February 2026 Annual 
Governance Log Chief Oicer 18 February 2026 Biannual 
Financial Regulations Chief Finance Oicer 18 February 2026 Annual 
Page 144 of 146

Page 145

NORTH LANARKSHIRE INTEGRATION JOINT BOARD PERFORMANCE, FINANCE AND AUDIT WORK PLAN 
Item  Lead Oicer  Meeting Date  Recurrence  Reason / Notes     
Future Reports
Integration Joint Boards: Finance and
Performance 2025
Chief Finance Oicer TBC Annual Meeting date dependant on
publishing from Audit
Scotland
Best Value Framework Chief Finance Oicer TBC Triennial 
Best Value – Annual Statement of
Compliance
Chief Finance Oicer TBC Annual 
Accounts Commission Reporting TBC TBC As and when publications
released from Accounts
Commission 
Local Code of Corporate Governance TBC TBC Annual 
Risk Management Strategy  Business Support
Manager
TBC Triennial  
Risk Management Annual Report Business Support
Manager
TBC Annual 
Pharmacy Savings Approach TBC TBC  Added to work plan from PFA
rolling action log 
Page 145 of 146