Democracy Spraffa

ITEM 7 National Care Service Update

North Lanarkshire Council · 24 January 2024
Back to Health and Social Care Integration Joint Board — 24 January 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

1 
REPORT 
Item No: 7 
SUBJECT: National Care Service Bill Update
TO: Integration Joint Board Committee 
Lead
Officer for
Report:
Ross McGuffie, Chief Officer, North HSCP
Author(s) of
Report 
Morag Dendy, Head of Planning, Performance and Quality
Assurance
DATE: 24 January 2023 
1. PURPOSE OF REPORT
This paper is coming to the IJB for: 
For approval ☐ For endorsement ☐ To note ☒ 
2. ROUTE TO THE BOARD
This paper has been: 
Prepared By: ☐ Reviewed By: ☒ Endorsed By: ☐ 
By: The Senior Leadership Team.          
3. RECOMMENDATIONS
3.1 The IJB is asked to note the update on the NCS Bill.
3.2 The IJB is asked to receive further updates as they are available.

Page 2

2 
4.  VARIATIONS TO DIRECTIONS? 
5. BACKGROUND/SUMMARY OF KEY ISSUES
5.1 Background
5.1.1 An Independent Review of Adult Social Care (IRASC) was published in
February 202. The Review, chaired by Derek Feeley, a former Scottish
Government Director General for Health and Social Care and Chief Executive of
NHS Scotland made 53 recommendations including the creation of a national care
service (NCS)
5.1.2 In August 2021 consultation on a National Care Service for Scotland was
launched.
5.1.3 The National Care Service (NCS) Bill was published in June 2022 and provided
for the establishment of a NCS, under the responsibility of Scottish Ministers. The
Bill provided for the transfer of listed social care and social work local authority
functions, staff and assets to Scottish Minters or newly established local care
boards/
5.1.4 Call for Views on the Bill opened in July 2022 and closed in September 2022.
The North Lanarkshire Integration Joint Board considered the response on the 21
September 2022, the link below is to the approved NL IJB response. 
Response 189034250 to National Care Service (Scotland) Bill (Detailed) -
Scottish Parliament - Citizen Space
5.1.5 The Bill is currently at Stage 1 of the process, which aims to review the general
principles contained within the Bill. The Health, Social Care and Sport
Committee is the lead Committee, supported by seven others, in reviewing this
stage, which is due for completion by 31st January 2024. 
5.1.6 Stage 2 will then allow MSPs to propose amendments to the Bill, which will then
be debated and voted on at the Lead Committee. Any amendments agreed will
then be used to develop a new amended version of the Bill for publication and
consideration at Stage 3. 
5.1.7 Stage 3 allows MSPs to propose further amendments which will be debated
and decided on in the Debating Chamber, and at this stage all MSPs can vote
on them before final debate and vote on whether to pass the Bill in entirety. 
5.2 Summary of Key Issues
5.2.1 The NCS Bill is currently going through stage 1 scrutiny, led by the Health, Social
Care and Sport Committee. 
Yes  ☐ No ☒ N/A ☐

Page 3

3 
5.2.2 This paper provides information on two recent parliamentary updates provided as
part of this Stage 1 scrutiny:
 6 December Health, Social Care and Sport Committee.
 11 December Finance and Public Administration Committee.
5.2.3 It is still the intention of the Scottish Government to deliver the NCS programme in
line with the original commitment within the existing parliamentary session. The
original proposals, however, have been reassessed to take account of the very
challenging fiscal environment and as a result a phased approach to
implementation is to be adopted. The Programme Business Case, which is
attached at Appendix 1, sets out revised planning assumptions, based on re-
profiled funding and presents a realistic approach to the delivery of the NCS. Key
areas have been prioritised which are deemed to have greater impact on quality,
fairness and consistency and value for money within the financial envelope
available.
5.2.4 The updates to the parliamentary committees set out three main amendments
sought by Scottish Government at Stage 2:
 That Local Authorities will retain responsibility for all current functions and
the delivery of social work and social care services and there will be no
transfer of staff or assets, through a shared accountability agreement; 
 Reforming Integration Authorities (IAs) rather than creating new Care
Boards and; 
 The establishment of a National Care Service Board.
5.2.5 Scottish Government have also reaffirmed commitment to some priority areas
within the Bill, including:
 Ability for Scottish Ministers to be enabled to provide direct funding to
reformed Integration Authorities;
 Explore potential for independent appointment of chairs of integration
authorities;
 Carry forward existing powers within the Public Bodies Act not yet used in
practice, such as the ability to directly employ Chief Officers and other
members of staff; and
 Continued review of arrangements for delegation or otherwise of Children’s
and Justice Social Work.
5.3 Shared accountability agreement
5.3.1 Discussions with Scottish Government, local authorities and NHS Boards have
been ongoing since the summer on a variety of issues. Within the proposed new
national framework, local authorities and health boards will keep service delivery
functions, staff and assets.
5.3.2 On 12th July 2023, an initial consensus proposal was agreed between Scottish
Government and COSLA around a partnership approach that will provide for

Page 4

4 
shared legal accountability, supporting national oversight as well as the
maintenance of local delivery arrangements. 
5.3.3 The Scottish Government now believe they can achieve the aims of the proposed
Care Boards through reforming the current integration authorities. While the
updates recognise there is still significant change needed at local level to bring
consistently good quality services across the country, it’s important that this does
not bring about widespread change just for the sake of it. Instead, Ministers intend
to make amendments to the legislation which allow the Scottish Government to
keep the knowledge and good work already happening in this area, whilst
improving the areas in need of reform.
5.4 The National Care Service Board
5.4.1 One of the key amendments outlined the stage 2 process is the development of a
National Care Service Board, which would be established as the primary means
through which to secure, operationalise and manage the agreed shared
accountability. This would focus on:
 Setting national strategic direction.
 Developing standards, guidance and operating frameworks.
 Overseeing and seeking deliver assurance on local strategic plans and
ethical commissioning strategies.
 Monitoring system performance.
 Maintaining a support and improvement framework which will aim to provide
support to local areas when monitoring indicates that standards are not
being met with powers of intervention, when required, as a last resort.
 Ensuring visibility of data, information, and analysis about social care
support, social work and primary and community health services through
reporting on delivery.
 National commissioning and procurement by agreement for complex and
specialist social work services which will include prison social care.
 Seeking assurance on public protection arrangements; and 
 Providing support to local deliver partners.
5.4.2 Work is currently being undertaken to develop the delivery mechanism for the
National Board. While this may be in the form of a public body, the final shape of
the entity is still to be agreed. Following a final decision, amendment will be made
to the Bill at Stage 2 to ensure the Board has the necessary duties and powers to
fulfil its role effectively. The cost estimates in the Financial Implications paper have
assumed the set-up of a public body to ensure that costs are represented
appropriately.
5.4.3 It is expected that amendments would be introduced at Stage 2 which provides for
Ministers to set out the detail and composition of National Care Service Board
membership through regulations. Although it is not intended to outline the
membership of the National Care Service Board within primary legislation, it is
intended to include, at a minimum, an independent chair; representatives from

Page 5

5 
local government to preserve local democratic accountability; the NHS and people
with lived experience.
5.4.4 The National Care Service Board will be responsible for reviewing and overseeing
the performance of local strategic plans. To support this, the proposal is to transfer
Ministerial powers of intervention to the National Care Service Board. This will
allow the Board to invoke those powers as a last resort and give it the levers
needed to drive and support performance and take action if required.
5.4.5 The involvement of people with lived experience will remain at the heart of these
reforms, including at decision making level by extending who on the Board has
voting rights. The detail of this reform will be co-designed with people with lived
experience of accessing community health, social work and social care support
services, as well as unpaid carers, care providers, workforce and organisational
stakeholders.
5.5 Care Boards / Reformed IAs
5.5.1 In light of the shared accountability agreement between national and local
government one of the key proposed amendments to the Bill at Stage 2 is to revisit
the original intention to create Care Boards, replacing this provision with the reform
of current Integration Authorities (IA).
5.5.2 Scottish Government consider that amending the existing IAs would achieve the
integrated reforms in a manner appropriate to the aim.
5.5.3 There are a number of fundamental areas of financial impact or risk mitigation to
highlight:
• Reforming current IAs rather than creating new Care Boards as public
bodies will eliminate costs associated with the setup, operation and
governance. This means the set up of 31 new public bodies to support the
NCS is not proposed. There will be some new costs associated with the
reform of IAs as outlined in the financial implication paper, but significant
overall cost reductions are projected.
• Statutory delivery functions will remain with local government and health
boards respectively, along with assets, employment and relative funding.
Consequently, costs associated with the transfer of staff and assets
originally provided for will not be incurred. This significantly reduces the
risks associated with asset transfer and removes risks associated with staff
pensions and TUPE, previously highlighted by the Committee.
• Reforming IAs rather than creating new Care Boards is also expected to
significantly reduce costs associated with premises and IT. Therefore, as
funding will continue to flow as per current arrangements, unless specifically
agreed, this negates the concerns around VAT implications.
5.6 National Social Work Agency
5.6.1 The commitment remains to establish a National Social Work Agency (NSWA).
Scottish Government and COSLA leaders will work with the key stakeholders

Page 6

6 
regarding the structure and governance of the NSWA. Further information on the
NSWA’s establishment will be reported to the IJB in the coming months.
5.6.2 The original objectives of the NSWA were to provide national leadership/support
in:
 Education
 Improvement
 Workforce planning
 Training and development
 Social work terms and conditions 
5.7 Children’s and Justice Services
5.7.1 The NCS Bill outlined that the NCS would be responsible for social work and social
care for adults, mental health care and adult and child protection. Decisions about
including Children and Justice services were to be made following further research
and engagement with stakeholders.
5.7.2 A decision has not yet been taken on the possible inclusion of children’s and justice
services in the NCS. 
5.7.3 The Centre for Excellence for Children’s Care and Protection (CELCIS) published
its final report on 13th December, aiming to answer the question “what is needed
to ensure that children, young people and families get the help they need, when
they need it?”. The report findings were inconclusive on the impact of structural
integration. 
5.7.4 A second strand of independent research was commissioned to review the best
approach for Justice Social Work services, with a second strand of evidence
published in December. Again, report findings to date have been inconclusive on
the impact of structural integration. 
5.7.5 Scottish Government have noted their continued commitment to work with
children’s and justice teams and people with lived experience with the aim of
understanding how best to support children’s and justice services across Scotland.
5.8 The new timeline for NCS
5.8.1 The new timeline for the NCS is outlined below: 
September 2024: earliest Bill enactment.
Spring 2025: Shadow NCS National Board and Shadow National Social Work
Agency launch.
Spring 2026: NCS National Board and National Social Work Agency launch.
2028/29: NCS local reform of Integration Authorities.
2028/29 – 2030/31: Continued integration and delivery of local reform.

Page 7

7 
6. CONCLUSIONS
6.1 The attached NCS Business Case, December 2023, provides more detail and
information around the future intentions for the development of the National
Care Service.
6.2 There are a number of changes proposed for inclusion at Stage 2 of the Bill
process, which will impact on the IJB. This includes retaining and reforming
the existing Integration Authorities rather than forming Local Care Boards;
potential for independent chairs for IJBs; potential for direct funding for some
elements; retention of Public Bodies Act elements allowing IJBs to employ
staff; and importantly the shared accountability agreements supporting the
local partner bodies to retain current functions and employment of staff. 
6.3 Further detail will be required to fully understand the full impact of each of
these elements. It is vital that throughout this process, the very positive local
working arrangements between all the local partners are protected so we can
continue to deliver the best possible outcomes for the North Lanarkshire
population. 
6.4 Further updates will be brought to the IJB as they arise. 
7. IMPLICATIONS
7.1 NATIONAL OUTCOMES
Link(s) to National Health and Wellbeing Outcomes 
People are able to look after and improve their own health and wellbeing
and live in good health for longer 
☒
People, including those with disabilities or long-term conditions, or who are
frail, are able to live, as far as reasonable practicable, independently and at
home or in a homely setting in their community
☒
People who use Health and Social Care Services have positive
experiences of those services, and have dignity respected
☒
Health and Social Care Services are centred on helping to maintain or
improve the quality of life of people who use those services 
☒
Health and Social Care Services contribute to reducing health inequalities  ☒
People who use Health and Social Care Services are safe from harm ☒
People who work in Health and Social Care Services feel engaged with the
work they do and are supported to continuously improve the information,
support, care and treatment they provide
☒
Resources are used effectively and efficiently in the provision of Health and
Social Care Services 
☒
7.2 ASSOCIATED MEASURE(S) 
N/A

Page 8

8 
7.3 FINANCIAL 
This paper has been reviewed by Finance: 
7.4 RISK ASSESSMENT/RISK MANAGEMENT 
Relevant Risk Register
Details 
Current Risk Level  Risk Owner 
Noted below High Ross McGuffie 
National Care Service - IJB.16. 2022
There is a risk that the ongoing work around a National Care Service could
destabilise current service delivery due to significant change activity, time demands
around the co‐design process, staff uncertainty and partner organisations having to
focus inwardly due to the impact of change leading to an impact on the ability to
deliver the significant ongoing change programmes already approved by the IJB and
the Strategic Commissioning Plan for 2023‐26 
7.5  ENGAGEMENT & PARTICPATION
Please tick the engagement and participation objectives that link(s) with this piece of
work and provide further details regarding the engagement and participation that was
undertaken.
Objectives  Further Details 
☐ Involve stakeholders in the development
work aimed at achieving the national 
outcomes 
☐ Provide stakeholders with information on
how to get involved 
☐ Ensure a diverse range of engagement
and participation and opportunities are in 
place to suit different needs 
☐ Measure how well we involve community
stakeholders in the planning, design 
and delivery of our services 
☐ Provide regular feedback on how
stakeholder engagement and participation is 
Yes  ☐ No ☐ N/A ☒

Page 9

9 
shaping and influencing service
development and delivery
☐ Provide support to enable stakeholder
representatives to participate meaningfully
and confidently at meetings 
☐ Develop participation guidelines to
ensure a common understanding and set of 
expectations for both stakeholders and
partnership staff 
☐ Support engagement planning and
participation in localities, taking account of 
other engagement activity and local plans
across the Community Planning 
Partnership 
The National Care Service will have an impact on all Scottish residents. 
7.6 INEQUALITIES & FAIRER SCOTLAND DUTY 
EQIA Completed & Fairer Scotland Impact Assessment Form Completed and
attached to report: 
EQIA added to website: 
8. BACKGROUND PAPERS
8.1 Papers relating to the development and Consultation on the NCS were
previously circulated.
8.2 Scottish Government NCS web pages
https://www.gov.scot/collections/national-care-service/
8.3 Policy Memorandum
Yes  ☐ No ☐ N/A ☒
Yes /
Date
added 
☐ No ☐ N/A ☒

Page 10

10 
https://www.parliament.scot/bills-and-laws/bills/national-care-service-scotland-
bill/introduced
8.4 Financial Memorandum
https://www.parliament.scot/bills-and-laws/bills/national-care-service-scotland-
bill/introduced
8.5 Explanatory Notes
https://www.parliament.scot/bills-and-laws/bills/national-care-service-scotland-
bill/introduced  
9. APPENDICES
9.1 Appendix 1 National Care Service Programme Business Case. 
Morag Dendy
CHIEF ACCOUNTABLE OFFICER (or Depute)   
Members seeking further information about any aspect of this report, please contact
the following: Morag Dendy – dendym@northlan.gov.uk

Page 11

11 
Direction from North Lanarkshire Integration Joint Board (IJB) 
1 Reference Number  
2 Report Title  
3 Date direction issued by IJB 
4 Date from which direction
takes effect 
5 Direction to: 
6 Does this direction
supersede, revise or revoke a
previous direction – if yes,
include reference number(s) 
7 Functions covered by
direction 
8 Full text of direction 
9 Budget allocated by
Integration Joint Board to
carry out direction 
10 Performance Management /
Governance arrangements 
11 Date direction will be
reviewed

Page 12

12 
Appendix 1
December
2023 
NATIONAL
CARE
SERVICE 
Programme
Business Case

Page 13

13

Page 14

ii 
Contents
1. EXECUTIVE SUMMARY ....................................................................................................................................................... 4
1.1 INTRODUCTION.................................................................................................................................................................................................................... 4
1.2 SCOPE .................................................................................................................................................................................................................................... 5
1.3 STRATEGIC CASE .............................................................................................................................................................................................................. 6
1.4 ECONOMIC CASE ............................................................................................................................................................................................................... 8
1.5 FINANCE CASE (SEE SHARED ACCOUNTABILITY PAPER) ...................................................................................................... 8
1.6 MANAGEMENT CASE ........................................................................................................................................................................................................ 8
2. STRATEGIC CASE ................................................................................................................................................................ 9
2.1 INTRODUCTION.................................................................................................................................................................................................................... 9
2.2 THE STRATEGIC CONTEXT FOR A NCS PROGRAMME ........................................................................................................................................ 9
2.2.1 Scottish Government aims and strategies ................................................................................................................. 9
2.2.2 Relevant Strategies ....................................................................................................................................................... 9
2.3 THE CASE FOR CHANGE ................................................................................................................................................................................................ 10
2.3.1 The current system ..................................................................................................................................................... 10
2.3.2 Scale of demand on the current system ................................................................................................................... 11
2.3.3 Reform of Health and Social Care in Scotland up until this point ......................................................................... 14
2.3.4 Good Practice within the Current System ................................................................................................................ 17
2.3.5 Conclusions on Scale of Demand on the Current System ..................................................................................... 17
2.3.6 Problem Statements.................................................................................................................................................... 18
2.3.7 Summary of the current case for the NCS ............................................................................................................... 24
2.4 SCOPE OF THE PROGRAMME ......................................................................................................................................................................................... 24
2.5 DELIVERY APPROACH ......................................................................................................................................................................................................... 31
2.6 WIDER STRATEGIC RISKS ASSOCIATED WITH THE DELIVERY OF THE NCS .......................................................................... 32
2.7 KEY CONSTRAINTS AND DEPENDENCIES ................................................................................................................................................................... 34
2.8 KEY INTERDEPENDENCIES FOR THE NCS PROGRAMME .................................................................................................................................... 34
2 ECONOMIC CASE ............................................................................................................................................................... 35
INTRODUCTION .............................................................................................................................................................................................................................. 35
3.1 BACKGROUND ................................................................................................................................................................................................................... 35
3.2 CURRENT SITUATION ...................................................................................................................................................................................................... 35
3.3 INDEPENDENT REVIEW OF ADULT SOCIAL CARE ............................................................................................................................................... 36
3.4 OPTIONS .............................................................................................................................................................................................................................. 36
3.5 OPTION OF BUSINESS AS USUAL .............................................................................................................................................................................. 36
3.6 OPTION OF THE NATIONAL CARE SERVICE .......................................................................................................................................................... 37
3.7 COSTS .................................................................................................................................................................................................................................. 38
3.8 BENEFITS ............................................................................................................................................................................................................................ 38
Direct benefits of the NCS .................................................................................................................................................... 38
Benefits of the NCS maximising the benefits of wider reforms ....................................................................................... 40
Wider benefits ........................................................................................................................................................................ 42
3.9 RISKS .................................................................................................................................................................................................................................... 42
3.10 NEXT STEPS/CONCLUSION ........................................................................................................................................................................................... 43
4. COMMERCIAL CASE .......................................................................................................................................................... 44
4.1 OVERVIEW .......................................................................................................................................................................................................................... 44
4.2 COMMODITY LEVEL PROCUREMENT STRATEGIES ............................................................................................................................................. 45
4.3 WORK STREAMS, FORWARD PLANNING, AND REQUIRED OUTPUTS .......................................................................................................... 45
4.4 PROPERTY REQUIREMENTS ........................................................................................................................................................................................ 46
4.5 DIGITAL REQUIREMENTS ............................................................................................................................................................................................... 46
4.6 GOVERNANCE RELATING TO PROCUREMENT AND COMMERCIAL ACTIVITY ........................................................................................... 46
4.7 GOVERNANCE RELATING BUDGETARY APPROVAL ........................................................................................................................................... 47
5. FINANCE CASE ................................................................................................................................................................... 48
6. MANAGEMENT CASE ......................................................................................................................................................... 49
6.1 INTRODUCTION ...................................................................................................................................................................................................................... 49
6.2 PROGRAMME AND PROJECT FRAMEWORK ........................................................................................................................................................... 49
6.2.1 Programme high level structure................................................................................................................................. 49

Page 15

iii 
6.2.2 Appointed Personnel and vacancies ......................................................................................................................... 50
6.3 PMO GOVERNANCE AND REPORTING ARRANGEMENTS ................................................................................................................................ 51
6.3.1 Reporting Arrangements ............................................................................................................................................ 51
6.3.2 Scottish Government Internal Governance Arrangements .................................................................................... 52
6.3.3 Programme Management Office (PMO) .................................................................................................................. 53
6.4 PROGRAMME PLANNING ............................................................................................................................................................................................... 53
6.4.1 Programme Schedule ................................................................................................................................................. 53
6.4.2 Business Case approach ........................................................................................................................................... 54
6.5 CO-DESIGN ......................................................................................................................................................................................................................... 55
6.5.1 Themes ......................................................................................................................................................................... 56
6.6 BUILDING OUR COMMUNICATIONS CHANNELS AND MESSAGING ................................................................................................................ 57
6.7 MONITORING AND CONTROL ...................................................................................................................................................................................... 57
6.7.1 Risk Management ....................................................................................................................................................... 58
6.7.2 Change Control ............................................................................................................................................................ 58
6.8 PROGRAMME ASSURANCE .......................................................................................................................................................................................... 58

Page 16

1. Executive Summary 
1.1 Introduction 
The aim of this Programme Business Case (PBC) is to define the scope and purpose of the National
Care Service (NCS) programme, provide a clear understanding of what the programme is and what
it seeks to achieve, where its boundaries lie, as understood at December 2023 and to support
informed and robust decision making. 
This PBC is a live document and will continue to be developed as the Programme is further
defined and in line with the Business Case Strategy a high-level extract is shown in the
management case. 
Updates will be made to the PBC when there are significant changes to Programme scope, costs,
or timeline. Revisions to the case will ensure it remains current and that ongoing consideration is
given to the viability of the Programme at key decision and/or investment points. Key points will
include, but are not limited to, the development of underpinning project and workstream business
cases for projects that require significant funding as part of the NCS programme. 
Underpinning business cases as shown will provide additional detail and the opportunity for value
for money to be scrutinised further before any significant investment decision. All investment in the
NCS will require scrutiny as part of the Scottish Governments budget process. Programme
governance will ensure that the ongoing viability and value for money for the programme is
reviewed throughout the lifecycle of the programme. 
NCS Programme Business Case alignment to HMT Green Book Guidance
In accordance with HMT Green Book Guidance, the Programme Business Case provides
management with a tool for transparent and evidenced based decision making and a framework
for the co-ordination, delivery, monitoring and evaluation of the resultant outputs, outcomes, and
benefits. 1
The Green Book guidance is intended to be applied flexibly in line with the needs of a given
Programme. This is clearly set out in HMT Green Book.
• “The Green Book is not a mechanical or deterministic decision-making device. It provides
approved thinking models and methods to support the provision of advice to clarify the
social – or public – welfare costs, benefits, and trade-offs of alternative implementation
options for the delivery of policy objectives” 2.
• “The role of appraisal and evaluation is to provide objective analysis to support decision
making” 3. 
1 HM Treasury, Guide to developing the Programme Business Case - Introduction, page 4
2 HMT Green Book, para 1.2
3 HMT Green Book, para 1.5

Page 17

• “This guidance should be applied proportionately. The resources and effort employed
should be related to costs, benefits and risks involved to society and to the public sector as
a result of the proposals under consideration” 4.
• “The guide provides a framework for thinking and a process for developing and gaining
approval which is flexible and scalable as well as a range of tools that can be applied
proportionately to provide clarity in the decision support process. It also provides a clear
audit trail for purposes of public accountability” 5.
“The process is flexible, because the quality and quantity of supporting analysis can be tailored to
the size and complexity of the project under development.” 6A Programme Business Case should
• enable the organisation and its key stakeholders to understand and influence the direction
of the programme early on in the planning process.
• improve decision making through early consideration of the key issues and available
evidence base and assists decision makers to avoid committing resources to projects that
should not proceed.
• facilitate benefits realisation and risk management for the entire programme rather than a
single project.
• demonstrate the continuing viability of the programme to senior management and
stakeholders; and
• streamline the tasks and resources required for the preparation of supporting Business
Cases 7.
This Programme Business Case will add value to the NCS Programme through:
• ensuring that the overarching financial envelope (outlined at this stage in the shared
accountability document) envisaged for the lifecycle of the Programme is clear and justified,
providing a funding envelope against which future requests for investment approvals can be
made on a phased basis. Allowing scrutiny of proposed investment at the right time with the
available evidence.
• the iterative design process, which is being undertaken within the Programme, i.e. that as
the Programme undertakes design work, the evidence base which justifies the investment
in the Programme will grow more detailed, allowing time to co-design and test and learn.
• taking stock of the case for investment in the NCS as that evidence base grows; and
• having a series of ‘exit points,’ where decision makers can decide to make changes to the
Programme if the case for approval to proceed has not developed as expected. 
1.2 Scope 
This PBC reflects the progress of the NCS Programme has made to date on defining the
programme, the potential benefits that may be achieved from the NCS programme, under a shared
accountability model once the NCS is created and functioning. 
4 HMT Green Book, para 1.68
5 HMT Green Book, Programme Business Case Supplementary Guidance, page 7
6 HMT Green Book, Project Business Case Supplementary Guidance, page 11 
7 HM Treasury, Guide to developing the Programme Business Case - Introduction, page 4

Page 18

1.3 Strategic Case 
The reform of community health, social work and social care has been a high-profile public policy
agenda in Scotland, over the last two decades. The plans to introduce a National Care Service
(NCS) build upon principles and ambitions that are well established, but which have not been fully
realised to date. The required level of change cannot be achieved under existing legislation and
structures. The rationale for the NCS is that the scale of transformation needed to meet aspirations
for a rights-based, person-centred system that delivers a better experience and better outcomes for
the people of Scotland requires a fundamental, system wide change and a new approach to
community health, social work and social care. 
The case for reforming the delivery of integrated health and social care arose out of the Independent
Review of Adult Social Care (IRASC). Conducted in the latter half of 2020 and published in February
2021, the report concluded that whilst there were strengths in Scotland’s social care system, it
required revision and redesign to enable a step change in the outcomes for people in receipt of care,
accessing social care support. The critical role of social care, in supporting people to live well and
to have their rights respected, was further demonstrated starkly during the Covid-19 pandemic. 
The challenges identified by the IRASC included:
• Inconsistency of user experience ("postcode lottery").
• Complex and inconsistent governance arrangements.
• Lack of national oversight and collaboration.
• Lack of collaborative and strategic leadership.
• The need for a paradigm shift in care support to one underpinned by rights.
• Non-integrated budgetary and financial planning. 
The creation of a National Care Service (NCS) offers an opportunity to positively impact the national
economy and wellbeing across Scotland. Potential benefits will be achievable in outcomes for the
recipients of the services provided, improved terms and conditions for the workforce; and through a
greater focus on prevention, it will lessen the burden upon the wider health and social care system. 
While the delivery mechanisms for the NCS may now be different, the vision for the NCS as set
out in the policy memorandum at the time of introduction remains the same: 
 enable people of all ages to access timely, consistent, equitable and fair, high-quality health
and social care support across Scotland;
 provide services that are co-designed with people who access and deliver care and
support, respecting, protecting and fulfilling their human rights;
 provide support for unpaid carers, recognising the value of what they do and supporting
them to look after their health and wellbeing so they can continue to care, if they so wish,
and have a life beyond caring;
 support and value the workforce;
 ensure that health, social work and social care support are integrated with other services,
prioritising dignity and respect, and taking account of individual circumstances to improve
outcomes for individuals and communities;
 ensure there is an emphasis on continuous improvement at the centre of everything;
 provide opportunities for training and development, including the creation of a National
Social Work Agency providing national leadership, oversight and support;

Page 19

8 Independent Review of Adult Social Care (2021) (link) 
 recognise the value of the investment in social care support, contribute to the wellbeing
economy, make the best use of public funds, and remove unnecessary duplication. 
Table 1 sets out some of the wider strategic risks associated with the delivery of the NCS, bearing
in mind that further work around the identification of risk and assessment of the likelihood and
impact of these will be undertaken as part of delivering this business case. 
Table 1:
Affordability 
The NCS will require significant investment, which will need to be balanced against other
priorities. However, this investment is required to deliver the impactful long-term ambitions
and meet future demand for health and social care services. Programme funding, which
covers resourcing and additional costs, will require on-going management to ensure that
budgets are effectively and efficiently used. The need for investments must be balanced
against the cost to retaining the status quo. There are risks to continuing with business as
usual due to the current pressures on the health and social care systems, but these risks will
be compounded by the forecasted increase in demand. In addition improving the system and
creating efficiencies will be likely to save money. For example, while it is difficult to fully
assess the cost savings, it is estimated that delayed discharges cost the system £134 million
a year. Eliminating or reducing this cost to the acute health service is not necessarily a
reduction in cost to the public purse. Instead community health and social care costs may be
incurred, but we do expect to see efficiencies emerge.8
Relationships 
The Programme requires cross government and public sector wide collaboration to ensure
successful design, delivery and implementation of health and social care reform through the
National Care Service. The agreement on shared accountability between Scottish Ministers,
Local Authorities and the NHS will require the creation of new governance structures that
should not introduce risk to existing planning mechanisms or delivery responsibilities and
instead will enhance and clarify relationships.
Technology 
New technology will be required to deliver the integrated social care and health and social
care record. Our developing evidence base also indicates a mixed picture of digital maturity in
the social care sector and a resultant need to invest in the sector to improve digital capacity
and capability to successfully implement the required technology. This poses technology risks
in terms of successfully developing the technology; ensuring any technology is sufficiently
safe and secure for personal and special category data; and ensuring successful deployment
of said technologies into the sector. There is significant work already underway to ensure the
NHS has the capability and capacity to support the introduction of the record.

Page 20

Maintaining existing services
The existing health and social care system is already stressed. Safely landing additional
change in that environment will be challenging. Careful planning and prioritisation of the
phases of change will be required in mitigation. Changes to the existing system must not
result in a reduction of service quality or introduce additional risk to the services experienced
by individuals. 
1.4 Economic Case 
The Economic Case outlines the expected benefits for people using care services, working in care
services and the way in which the NCS will enable the Scottish Government to implement broader
government objectives with maximum impact. Dependent on the final form that the NCS takes, there
is potential for substantial benefits to be realised from the NCS, and the associated wider social care
reform committed to by the Scottish Government. This Economic Case explores what these could
be and provides a framework for future detailed quantification of benefits as the programme
develops. 
1.5 Finance Case (See shared accountability paper) 
The costing of the Programme is included in the accompanying shared accountability paper. 
1.6 Management Case 
The management case sets out in Section 6 the Programme management approach to support
successful delivery as well as the Programmes management and control approach. 
Scottish Government, Director General of Health and Social Care (Accountable Owner) and
Senior Responsible Officer (SRO), the Director of the Social Care NCS Development Directorate
lead the Programme. The cross-cutting nature of the Programme requires collaborative working
across the Scottish Government and the wider social care sector to develop policy, design, and
implement an NCS that brings together community health and social care to deliver change and
benefits safely. 
A Programme structure has been developed, which sets out the Programme hierarchy, phasing,
and underpinning projects.

Page 21

9 National Performance Framework 
2. Strategic Case
2.1 Introduction 
The purpose of the strategic case is to make the case for change and demonstrate how the
programme provides strategic fit with Scottish Government’s national outcomes as outlined in the
National Performance Framework. The case also sets out the policy context, available evidence
and information that supports a compelling case for change and alignment with the broader
strategic direction including interdependencies, constraints and risks for the work proposed. 
2.2 The strategic context for a NCS Programme 
2.2.1 Scottish Government aims and strategies. 
The National Performance Framework (NPF9) defines the purpose of the wider public sector as “to
focus on creating a more successful country, with opportunities for all of Scotland to flourish,
through sustainable and inclusive growth.” This purpose is underpinned by the values that
Scotland is “a society which treats people with kindness, dignity and compassion; respects the
rules of law; and acts in an open and transparent way.”
The delivery of integrated community health, social work and social care services that best support
people has been at the heart of Scottish Government policy since devolution. The proposed
investment in and reform of integrated community health, social work and social care services will
touch all the key areas of the National Performance Framework by: 
2.2.2 Relevant Strategies 
The delivery of an NCS builds on the work of the Scottish Government to date including:
 The Public Bodies Act (2014) which established Integration Authorities.
 The work conducted under the Adult Social Care reform programme from 2019.
 The Adult Social Care Statement of Intent in March 2021 in which Scottish Government and
Convention of Scottish Local Authorities (COSLA) agreed to work together on the key
foundational aspects of the Independent Report on Adult Social Care.
 The actions underway as part of the Proactive and Preventative Care Programme, Fair
Work action plan, as well as rollout of Housing First Scotland.
 Wider strategic plans and approaches including The Promise, Digital Health, and Care
Strategy (2021) and A Changing Nation: How Scotland will thrive in a digital world (2021);
and
 Creating a more successful country.
 Giving opportunities to all people living in Scotland.
 Increasing the wellbeing of people living in Scotland.
 Creating sustainable and inclusive growth; and
 Reducing inequalities and gives equal importance to economic, environmental, and social
progress.

Page 22

11 Verity House Agreement 
 The 2019 Primary Care Outcomes Framework.
 The Scottish Approach to Service Design10 
These strategies provide the context for a shift in how health and care is delivered in Scotland, to
place people, human rights, and equality at the heart of decision-making, and build together a
future system that enables consistency, quality, and fairness at the core.
The Scottish Government is undertaking multiple large scale reform programmes:
 Keeping the Promise Implementation Plan
 Tackling Child Poverty Delivery Plan 2022 - 26
 The National Strategy for Economic Transformation
 The Climate Change Plan
 The Care and Wellbeing Portfolio
 Public Sector Reform
 Getting it Right for Everyone 
In addition to the above large-scale programmes the NCS will be delivering in line with the Verity
House Agreement signed in June 2023.11 The agreement is a partnership agreement between the
Convention of Scottish Local Authorities (COSLA) and the Scottish Government “setting out our
vision for a more collaborative approach to delivering our shared priorities for the people of
Scotland”.
In line with the Verity House Agreement the NCS Programme has reached agreement that the
NCS will operate with shared accountability between Scottish Ministers, Local Authorities, and the
NHS for the oversight and delivery of integrated health and social care. 
2.3 The case for change 
2.3.1 The current system 
This section sets out the current system in Scotland that delivers care and support to the people of
Scotland. It provides additional context for the case for change. 
Currently social care support across Scotland is delivered by a wide range of partners, including
organisations in the public, private and third sectors. Social care is provided in people's homes,
including through remote care and technology-enabled care, in residential accommodation and
care homes, or the wider community, including many advice and support services. 
Currently, local authorities are responsible for social work and social care support, and local health
boards are responsible for health services. They work together as integration authorities to assess
the needs of their area and plan and commission local community-based health and social care
services, using funding contributed by the local authority and health board. Health boards and
local authorities in each local area are responsible for delivering local community-based health
and social care services as directed by the integration authority, including adult social work and
adult social care support, community health services for adults. Some integration authorities also 
10 The Scottish Approach to Service Design (SAtSD)

Page 23

have responsibility for children's health, children and families social work and social care, justice
social work, and homelessness and housing support. To foster an integrated approach to delivery
of support services, the public bodies in each area bring their workforce together under what is
known as Health and Social Care Partnerships (HSCPs). 
Community health, social work and social care is there for people of any age who need assistance
with day-to-day living due to illness, physical disability, learning disabilities, mental health
conditions or issues relating to older age, frailty, or dementia.
There are three functional areas of social work and social care in Scotland: adult, justice and
children and families.
1. Adults – Adults’ social work and social care services provide assessment, support, and
interventions to people aged 18 or over who may need additional support due to physical
illnesses, physical or learning disabilities, mental health conditions or general frailty.
2. Children - Children’s social work and social care services provide assessment, support and
interventions for children and families, or where children are unable to live with their own
families.
3. Justice - Justice social work and social care services provides assessment, support, and
interventions for people in relation to offending or alleged offending, including though
diversion from prosecution, bail supervision, delivery of community orders, and supervision
and support for those serving prison sentences before and after release. 
2.3.2 Scale of demand on the current system 
The population receiving community health, social work and social care support is diverse, with
wide ranging needs and circumstances. In many cases, the needs and circumstances of
individuals mean they may interact with other services, including those relating to education,
housing, social security, and justice, provided by both the public sector and others including
voluntary and third sector bodies. Some of these needs are met by unpaid carers who support
their families and loved ones, with an estimated 700,000-800,000 people providing this kind of
support12.
The latest data (2019/20-2020/21) for the population receiving community health social care and
support is summarised below13:
Social Care: 
 17% of the adult population (over 16) provide care to one or more person.
 Around 1 in 25 people in Scotland were reported as receiving social care support and services
at some point in 2021/22
 Around 65,500 people in Scotland are receiving home care at any one point.
 The proportion of people receiving social care through any self-directed support option
increased from 18.4% (2020/21) to 18.9% (2021/22). The percentage measure is based on
the number per 1,000 population of those receiving self-directed support vs. the number of
people per 1,000 population receiving social care by any means. 
12  Scotland’s Carers: Update Release 12 April 2022 https://www.gov.scot/publications/scotlands-carers-update-release-2/
13 Insights in social care: statistics for Scotland - Support provided or funded by health and social care partnerships in Scotland 2021/22 - Insights in
social care: statistics for Scotland - Publications - Public Health Scotland#

Page 24

 Around 33,000 people received funding towards a long stay care home place in Scotland
during 2021/22.
 A high proportion (43%) of people accessing social care support are elderly and/or frail.
 Almost 1 in 3 (32%) have a physical or sensory disability.
 Around 6% are receiving social care support due to mental health issues.
 There were an estimated 32,800 long stay residents aged 18 years and over in Care homes
on 31 March 2023, 6% fewer than 31 March 2013. Care homes for older people (65 and over)
accounted for 92% of long stay residents in all care homes for adults, with around 63% of
older residents with dementia.14
 People can be receiving support for more than one reason, for example: problematic
substance use, neurological conditions, dementia, palliative care, autism, or other
vulnerabilities.
 Based on the Local Finance Return (LFR), the cost of social care in 2021-22 was £8.2
billion.15 
Primary Care16:
 As of 1 July 2023, there were around 5.9 million patients registered with General Practices in
Scotland, an increase of 2.1% over the past two years.17
 The number of patients aged 65+ has increased by 20% since 2012.18
 The total number of General Practices in Scotland is falling, and the average practice list size
is increasing. The average practice list size in Scotland for 2022 was 6,470 patients. 19 
Mental Health
 In 2021/2022, people living in the most deprived areas were around three times more likely
to experience inpatient mental health care than people living in the least deprived areas20. Of
the patients who experienced mental health inpatient care in 2021/2022, 53% were male21.
However, in the under-18 age category, 73% of patients were female22. 
14 Dashboard - Care home census for adults in Scotland - Statistics for 2013 – 2023 - Care home census for adults in Scotland - Publications -
Public Health Scotland
15 Scottish local government finance statistics (SLGFS) 2021-22: workbooks - gov.scot (www.gov.scot)
16 Definition: Primary care is the first point of contact with the NHS. This includes contact with community-based services provided by general practitioners
(GPs), community nurses, dentists, dental nurses, optometrists, dispensing opticians, community pharmacy and general practice-based pharmacists and
pharmacy technicians. It can also be with allied health professionals such as physiotherapists and occupational therapists, midwives, and pharmacists. Primary
Care also encompasses urgent community care including out of hours service provision.
17 General practice - demographics data visualisation - Up to 1 July 2023 - General practice - demographics data visualisation - Publications - Public
Health Scotland Note that the total number of patients registered is higher than the latest Scottish population estimate; PHS are working with NRS
to understand the reasons for this difference.
18 General Practice - GP Workforce and practice list sizes 2012 - 2022 - General Practice - GP workforce and practice list sizes - Publications -
Public Health Scotland
19 General Practice - GP Workforce and practice list sizes 2012 - 2022 - General Practice - GP workforce and practice list sizes - Publications -
Public Health Scotland
20 Data summary - Mental health inpatient activity - 28 March 2023 - Mental health inpatient activity - Publications - Public Health Scotland
21 Data summary - Mental health inpatient activity - 28 March 2023 - Mental health inpatient activity - Publications - Public Health Scotland
22 Data explorer - Mental health inpatient activity - 28 March 2023 - Mental health inpatient activity - Publications - Public Health Scotland

Page 25

Justice Social Work23:
 There were around 17,600 social work orders commenced in 2019-20, which was 15%
lower than the peak in 2016-17. In 2020-21 and 2021-22, this was 8,500 and 12,600,
respectively. These figures are lower than previously reported because of the COVID-19
pandemic.
 There were 16,800 community payback orders commenced in 2019-20, a rise of two per
cent on the year prior. These were lower than 2019-20 during the pandemic years: 8,200 in
2020-21 and 12,200 in 2021-22.
 There was 1,900 statutory custody and community based through care cases commenced
in 2019-20. These were lower than 2019-20 during the pandemic years: 1,500 in 2020-21
and 1,700 in 2021-22.
 The number of drug treatment and testing orders commenced was 520 in 2019-20. These
were lower than 2019-20 during the pandemic years: 230 in 2020-21 and 360 in 2021-22.
 Young people aged 16 to 20 represent 7% of the Scottish population aged 16 to 70 in 2020-
21 and accounted for 9% of criminal justice social work reports submitted and community
payback orders imposed and 20% of fiscal work orders imposed. 
Children’s Services24:
 On 31 July 2022, 12,596 children were being looked after in Scotland. This includes those
looked after at home, with kinship carers, with foster carers, in other community settings, or
in residential accommodation.
 On 31 July 2022, 2,031 children were on the Child Protection Register.
 On 31 July 2022, 382 children were both looked after and on the Child Protection Register.
 On 31 July 2022, the rate of children (0-15 years) on the Child Protection Register varied
considerably by local authority, ranging from 0.5 per 1,000 children in East Renfrewshire to
4.2 per 1,000 children in North Ayrshire.25
 During 2020/21, around 3,000 children and young people aged 0-17 received social care
services or support in Scotland, of which 22% had a learning disability and 16% a physical
and sensory disability. 515 children and young people had community alarms or received
telecare support, 195 home care and 70 children and young people were in a care home.26
 5,230 children and young people started treatment at Child and Adolescent Mental Health
Services (CAMHS) in Scotland during the quarter ending June 2022. Of these, 68.4% were
seen within 18 weeks, compared to the standard of at least 90% of children and young people
to receive treatment within 18 weeks of referral.27 
23 Justice Social work statistics 2021-22
24 Children’s services include children’s community health, social work, and social care services.
25 Children’s Social Work Statistics Scotland 2021-22
26 Insights in social care: Statistics for Scotland
27 Scottish Government Performance against LDP standards

Page 26

2.3.3 Reform of Health and Social Care in Scotland up until this point 
The figures above show that the demand and investment on Health and Social Care is
significant and far reaching. There have been initiatives to reform the system previously. Figure
1 sets out the published reports which preceded IRASC, and how reform was considered and
initiated.

Page 27

Figure 1: Published Reports on Health and Social Care Reform

Page 28

The introduction of the 2014 Public Bodies (Joint Working) Act was intended to address the
challenges present in the community health, social work, and social care system at the time. The
published documents set out in the above diagram provide a narrative on that implementation.
The key learning points and areas to consider based upon the experiences to date of
implementing health and social care integration are summarised below.
Table 2: 
Initial focus on entity rather than service or service user
The requirement to have the Integration Authorities (IA) in place by a set deadline meant much
of the focus was on leadership and structures. There was not enough focus on how services
would be delivered differently. There was little room for trial and error, building on what works or
for designing the service and wider features around the user. The start – and end – was to set
up the IA.
The IA has limited authority to change.
Other than NHS Highland, the structures of IAs mean that the IA is intended to be the strategic
commissioner and has statutory responsibility for decision-making, but the delivery bodies
retained statutory delivery responsibility. The IA therefore has limited ability to change the profile
of delivery, to innovate or redirect resources.
Funding made it hard to remove the ‘organisational’ lens.
IAs represented a limited change to the existing funding model - funds were ceded to IAs and
then largely given back to the hosts from which they came. There was little risk sharing or ability
to invest in one area to save in another. This impairs the policy intent to invest more in
prevention and pro-active care, as funds released from acute services that see reduced costs
are often reinvested to meet the growing demand for acute services (as investment is not
otherwise available to meet this demand). One review concluded that this means that funding
needs to be ‘new’ rather than abstracted from the acute services which would see reduced
costs.
Distinct entities behaving differently.
The culture, professions and system for Community Health, Social Work and Social Care
delivery are different. Where there is increased integration in the form of ‘lead agencies’ or
recently through the Enhanced Professional and Clinical Oversight, the view tends to be that the
clinical/medical approach becomes dominant rather than a true integration of approaches.
Over-reliance on leadership
The system for IAs placed high reliance on strategy, commissioning, and governance. To do this
the IAs only have to produce three documents – an annual performance statement, a strategic
plan (every three years) and an annual finance statement.
IJBs were required to have several representative groups on the Board. The high turnover of
Chief Officers, over-reliance on a few key leaders within the system and a limited number of
Board meetings for the significance of the work in hand did not provide the required drive for
change at a local level. For example, the ability to focus efforts on changing how third parties
are commissioned and engaging them differently on a relationship basis was highlighted as

Page 29

taking time, energy, and consistency of leadership, as well as needing changes to ways of
working beyond the leadership team layer itself. 
2.3.4 Good Practice within the Current System 
Although quality of provision across Scotland is not consistent, within the current system, there are
examples of social care being delivered to a high standard, despite the scale of the challenges
faced by the sector. Some examples are below.
The Independent Review of Adult Social Care (published in February 2021) heard many examples
of good practice in the current social care system, and noted “the dedication and responsiveness
of people in the workforce”, how “self-directed support [is] enabling people to ‘live a real life’”, that
integrated health and social care support services are “jointly focusing on the wellbeing of the
person using care”; and also recognised the support being given to carers in order that they can
carry on caring for their loved ones. 
The review found that Integration Joint Boards “have had benefits in terms of health and social
care support services working together better locally” and that the social care workforce is
'motivated', 'resilient', 'adaptable' and 'proud of their work'. Good examples were also noted about
engagement with the Care Inspectorate, including observations like “inspections being based on
dialogue and improvement.” 
2.3.5 Conclusions on Scale of Demand on the Current System 
Ensuring that the health and social care system is prepared to deal with the changing needs of the
people of Scotland is an important element for the general wellbeing of the country. The system
must have an increasing level of resilience that is able to deal with a variety of ongoing challenges
and pressures.
The Scottish Government is committed to supporting the delivery of Social Care services within
Scotland. Through dedicated funding to local bodies, provision should be made at a local level that
is responsive to the needs of local communities. The Scottish Government in collaboration with
partners has an important role in driving improvement and collaboration across the country as well
as coordinating response to emerging issues and pressures.
The Granite Care Consortium (GCC) was commissioned by Aberdeen City Health and
Social Care Partnership to deliver Care at Home services from 1st November 2020. GCC
consists of 10 care and support providers, all of whom are experienced in delivering care in
the city. The focus of the new model moves away from tradition time and task model to one
that is more responsive to delivering individual outcomes. There will be an increased focus
on local assets to connect people back into their communities. The model also aims to
improve market stability and provide greater stability for the workforce.
The model allows the packages of care to be stepped up and stepped down in response to
changing needs and in close collaboration with service users, their families and those
directly involved in providing the care.
An evaluation of first year of operations was carried out by Coalition of Care and Support
Providers Scotland (CCPS) and formed part of GCC’s Annual Report 2020-21.

Page 30

The health and social care system is still recovering from the Covid Pandemic as well as
responding to other emerging issues such as a changing demography and workforce pressures.
These issues present the system with challenges that require a holistic approach to ensuring that
it remains able to deliver for the people of Scotland.
The economic case provides additional detail, in summary the system is failing to meet current
demand and significant reform is required to enable it to meet future demand in terms of
Scotland’s future needs, including the projected burden of disease and the ageing population.
Moreover, IRASC identified that many current costs in Social Care are driven by crisis
management and late interventions, for example people who are delayed in hospital. It is
estimated that delayed discharges cost the system £134 million a year, plus the wellbeing loss
experienced by individuals.28 Eliminating or reducing this cost to the acute health service is not
necessarily a reduction in cost to the public purse. Instead community health and social care costs
may be incurred, but we do expect to see efficiencies emerge. 
2.3.6 Problem Statements 
The IRASC highlighted the challenges with the current system through a series of problem
statements, primarily focused on Adult Social Care. These have been built on further throughout
the business case process as follows:
• Reviewing other policies, research, reports, and analysis on the services in scope –
including The Promise.
• Holding working sessions with those with lived and living experience of the community
health and care sector and understanding their journey through the current system.
Through this wider work a longlist of over 200 problem statements were developed that cover
issues across the community health and social care system. These have been summarised and
grouped together into nine themes.
These problem statements highlight the need for a ‘whole system’ response. The issues identified
are not solvable through one off measures or by individual reforms. As the initial view of potential
enablers shows, they point to a scale of reform which is comprehensive, addresses the
fragmentation of the current system, and can overcome the barriers that have prevented the
current ways of working from making these changes. They also reflect messages that have been
repeated in previous years and which have not resulted in the level or pace of change needed to
address them. 
28 Independent Review of Adult Social Care (2021) (link)

Page 31

Figure 1: Problem Statements. 
Person-centered rights-based care
The current system is often not designed with the individual’s needs at the forefront, nor is it coordinated or flexible enough to reflect and address
the changing needs of individuals. It requires people to re-tell their story within and across different parts of the system creating frustration and
trauma for them, and inefficiencies for the system. As a result, many people and families feel support is hard to access and is system rather than
person-centred.
People who use care and their families often describe the social care system as over complicated. This is largely driven by the current processes
surrounding support planning which are not streamlined – making the system difficult to navigate and hindering people’s ability to access social
care support in a timely manner.
The aim of personalisation, for example through Self Directed Support (SDS)is not being met to a sufficiently high level. The HACE survey
previously referenced showed around 1 in 4 people who receive care did not feel they had a say in how it was delivered. The existing eligibility
criteria were cited within the IRASC as acting as barriers to accessing support, and often failing to acknowledge and support the whole needs for
a person. The creation of Integration Authorities and the Health and Social Care Partnerships which deliver services was intended to provide a
more co-ordinated and person-centred approach. While it is recognised integration authorities have made improvements in some areas – IRASC,
the Audit Scotland review of Health and Social Care Integration and the Ministerial Working group on Health and Social Care Integration progress
review have found they have not made sufficient progress. 
Prevention not Crisis
The current system often focuses on acute crisis support and there is a lack of access to the preventative care and early intervention needed by
people to support them to live an independent and fulfilling life and reduce the future need for high-cost crisis support. This cycle leads to people
feeling that the system is failing to meet their needs and leads to increased use of other health emergency/ acute services which results in further
inefficiencies in the system such as delayed discharges.
The difference in the operational style and context of NHS and Local Authority organisations reinforces different behaviours, with Social Care/Local
Authority services often seen as the ‘poor relation’ due to an inability to shift funding and attention from acute care to more preventative and pro-
active interventions.

Page 32

Stakeholders, representing people who access services, providers, and those within the current system, raised the issue of short-term funding
preventing long term planning and capacity to invest into preventative support services. Eligibility criteria create barriers to accessing services,
meaning people are unable to access the most appropriate support at the right time. 
Individuals and Unpaid Carers
Currently the complex bureaucracy within the system too often excludes the individuals in receipt of care and support, their families and unpaid
carers from assessment and support processes. This needs to be balanced with a stronger advocacy system that protects vulnerable people
while supporting families to be involved in a meaningful manner. For unpaid carers particularly there remains concern about the consistency of
access to information about the support available and the complex and lengthy processes required to get appropriate support for opportunities to
step away to undertake everyday tasks, recharge and take a break.
Evidence from Carers Scotland reveals almost three quarters (72%) said they had to continue providing care even though they felt they were at
breaking point.i Unpaid carers faced an extraordinarily challenging time providing many more hours of unpaid care during the pandemic, with
reduced support available from health and social care services and limited help from their support networks. Research shows that just over a third
of carers (35%) in State of Caring 2023 had not had any break from caring in the past year, often saying that it is just too difficult to get the breaks
they desperately need.ii IRASC findings and feedback from Current Operating Model (COM) workshop attendees showed that there is a need for
improved and more consistent support for unpaid carers to carry out their caring role and to take a break from caring, with regular access to a
range of options for respite. 
Workforce
The lack of parity between third, independent, NHS and local authority staff, with variation in remuneration, training and an unclear career
pathway all contribute to the perception that caring is not an attractive career, leading to recruitment and retention issues. Other cultural factors
and perceived hierarchies that exist within the workforce can result in individuals in receipt of care and support not placing equal value across all
professions involved with them.
For example, even before the current challenges with cost of living, carers were more likely to be in poverty than people without a caring role.
According to the Joseph Rowntree Foundation, 44% of working age adults who are providing unpaid care for more than 35 hours a week are in
poverty.iii Job market competition from other sectors with more attractive T&Cs (e.g. retail, hospitality) is also impacting recruitment and retention.
Currently there is not a unified approach to learning and development. Areas of development include the need to establish clear career pathways
and to identify the skills that workers need to develop, including leadership development and retention. There is no financial incentive for career

Page 33

progression due to the erosion of pay differentials with added responsibility. Training is the responsibility of employers, but funding options are
complex with little oversight on the quality of training.
At present, social work education, continuous professional development and improvement are supported and provided by several organisations
and agencies, including local authorities and the Scottish Social Services Council (SSSC). The Scottish Government sets the overall strategic
framework for the delivery of social work and has oversight of some of these bodies, namely the SSSC. There is no single national body tasked
with having oversight and leading social workers’ professional development, education, and improvement. Terms and conditions of social workers
employment are set by individual employers, resulting in local variations in social workers’ pay and grading. 
Consistency and Quality
There is a lack of consistency and a variation of quality of provision and services across Scotland. This can be attributed to a number of factors
including interpretation of eligibility criteria regulations; interpretation and/or implementation of the Self-Directed Support Act; the extent of choice
of provider or service available locally; and the variation of Integration Authority remits across the country and regulations and scrutiny that too
often focus on procedure and process rather than on individuals’ experiences of care. People have stated that these factors along with the lack of
a clear improvement framework for social care led to a feeling of a postcode lottery.
For example, looking at SDS, according to the National Report on ‘My Support My Choice: People’s Experiences of Self-directed Support and
Social Care in Scotland (Oct 2020)’, there has been difficulty in contacting social work departments, particularly when trying to obtain information
about how to access SDS (Self Directed Support) for the first time. Variable information was reportedly given to service users about the four SDS
options that links into people's needs assessment.
While it is generally clear how to make a complaint in relation to SDS and despite the positive outcomes that are achieved through a complaint, it
is noted that the actual process itself can be inconsistent, unpredictable, and dependent on various factors, such as geographic location, the
person receiving the complaint and levels of individual awareness.

Page 34

System Intelligence and Governance
The community health and social care system is seen as complex, with little transparency. Having multiple public sector bodies with different
governance and accountability structures makes creating the conditions for collaborative public sector and provider relationships challenging. This
impacts on the ability to fulfil tasks such as joint planning, risk sharing and providing oversight. The system is difficult for people to navigate with
multiple interfaces that leave them unclear about where responsibility and accountability for their care and support rests.
Integration Authorities were introduced to integrate Local Government and Health services, but it has proven hard to make this work in practice.
Some of the key issues include the following:
 There has been high leadership turnover due to many issues. For example, the challenge of working in a complex governance environment
and the need for IJB members to act in the interest of the IJB but also hold their substantive posts.
 The intention of integration was to pool resources and then direct them according to a shared plan, based on needs. In practice much of
the funding appears to be ‘circular,’ with funding allocated to the IJB from the local authority and health board, which then directs it back to
the local authorities and health boards (and Health and Social Care Partnerships) to deliver. The scale of funding of the IJB relies on the
financial position of its partners.
 The financial planning and budget cycles are not aligned; Local Authorities must agree budgets and set council tax by the end of March
while NHS Territorial Boards work to different timescales. Therefore, statutory bodies apply different budget setting timescales with IJB’s’
budgets being set last, making joined up planning for resources harder. 
Regulation and Standards
There is a disconnect between the considerable number of different standards in social care, the priority attached to these and awareness of them
by those who are delivering and receiving services on the ground, creating an implementation gap between policy and practice. The handling of
complaints and problems is also made more difficult as there is no single standard/measure. The current system regulates individual providers,
tackling underperformance highlighted through inspection with no embedded sectoral improvement strategy.
There is a view that social care roles are poorly defined across local authorities, third sector and independent providers and the NHS. A lack of
understanding on the range of roles and responsibilities including a clear distinction between social care and social work (whilst also recognising
its inherent partnership) has been raised with a need for the workforce to have its own “professional identity.”

Page 35

Further issues have been highlighted with current commissioning and procurement practices which are seen to be characterised by mistrust,
conflict, and market forces, with procurement practices in social care increasingly driving and sometimes undermining strategic commissioning
and planning decisions. The lack of autonomy at different levels over-complicates the system and restricts decision-making. 
Continuous improvement
There are multiple organisations with the remit and role to support improvement. However, as set out throughout this analysis, a fragmented
system makes it harder to trace improvements through to either individual or national outcomes and therefore risks improving process and activity
rather than driving better results. There are also barriers in addressing known performance issues among some providers because of the limits of
the regulatory powers available.
It is recognised that a lack of collaborative leadership and lack of strategic capacity has affected the progress of integration in some areas.
Integration remains poorly understood and workforce pressures are a clear barrier to the implementation of integration plans.
1 State of Caring 2023: A health and social care crisis for unpaid carers in Scotland, November 2023. Carers Scotland
1 State of Caring 2023: A health and social care crisis for unpaid carers in Scotland, November 2023. Carers Scotland
1 Joseph Rowntree Foundation. Poverty in the UK 2022.

Page 36

2.3.7 Summary of the current case for the NCS 
There has been unprecedented demand on the Scottish health and social care system in a time of
global challenge and uncertainty. Meeting demand will only become more challenging in the future
with an ageing population with more complex needs. To deliver a system which meets Scottish
Government ambitions, in terms of outcomes and services for the people of Scotland, it is
essential to consider fundamental and systemic change, that optimises the system and makes real
change for people. The Public Bodies Act is not delivering the embedded approach to integration it
was intended to, meaning that many people are failing to have their social care needs met.
The Independent Review of Adult Social Care (IRASC) was instrumental in identifying how these
fundamental changes might be implemented. The Programme recognise that any solution
envisaged for social care must address the IRASC problem statements.
There are significant workforce issues within the current Social Care system (also identified by
IRASC). The NCS must seek to address these throughout the entirety of the Programme lifecycle
and beyond. Specific key issues include challenges around staff recruitment and retention.
Cultural paradigms and leadership issues are also suggested as key issues requiring
consideration.
In 2021/22, there were 236,000 people in Scotland reportedly receiving social care support or
services.29 If it is assumed that 10% of this group (23,600 people) experience a 0.1 point
improvement in wellbeing because of the establishment of the NCS for the reasons discussed
above, then this could lead to a potential annual benefit of around £34 million (2021 prices). 
In 2021, there were around 130,000 people employed in the Adult Social care sector.30 If it is
assumed 10% of this group (13,000 carers) experience a 0.1 point improvement in their wellbeing
on the life satisfaction scale because of the establishment of the NCS, then this could lead to a
potential annual benefit of around £19 million (2021 prices). 
2.4 Scope of the Programme 
The National Care Service (Scotland) Bill was published in June 2022; and has legislated for the
maximalist approach to scope for inclusion within the NCS, which includes Children and Families
services, Justice Social Work and Community Health Services along with Adult Social Work and
Social Care Services. At the time of Introduction this included the transfer of full accountability,
functions, staff, and assets to Scottish Ministers and included the set-up of local care boards to
replace Integration Authorities. This option has been refined further following ongoing definition
and evidence gathering as well as alignment with the recent Verity House agreement with Local
Government 
The Scottish Government has reached an initial agreement with local government and the NHS
about shared accountability arrangements for the National Care Service (NCS). Overall legal
accountability will be shared between Scottish Government, the NHS and local government. Staff
will continue to be employed by local authorities, which will also retain assets and delivery 
29 People supported - Insights in social care: statistics for Scotland - Support provided or funded by health and social care partnerships in Scotland
2021/22 - Insights in social care: statistics for Scotland - Publications - Public Health Scotland
30 This only includes those working in adult day care, adult placement services and housing support/care at home. It does not consider health
workers: Scottish Social Services Council, August 2023 (link)

Page 37

functions with similar arrangements for all NHS Health Boards assets, staff, functions, and
contracts. 
New governance arrangements will be introduced. These will be introduced to ensure consistently
high levels of service across the country, while building the flexibility to meet varying community
needs at a local level. Agreement has been reached that a National Board will be established to
oversee these new governance arrangements, with the detail and functions to be designed in
collaboration with key stakeholders and those who access and work in the sector. 
In addition, ongoing collaborative work will support the development of the preferred options for
local reform, rather than the creation of Care Boards. 
Figure 2: NCS Programme High level visual 
The figure below provides a visual representation of the scope of the NCS Programme that takes
account of these recent agreements.

Page 38

PBC
Children’s services
The IRASC concluded that "for Scotland to truly be the best place in the world for children to grow
up, a fundamental shift is required in how decisions are made about children and families.” For this
fundamental shift to happen, services must be designed in a truly collaborative way. The Scottish
Government is committed to delivering The Promise in partnership with the wider children’s
services sector.
Further consideration is required as to whether the integration of children’s social services with
adult and community health services in the NCS could provide a structure and system in which
The Promise can be delivered and maintained more effectively than out with the NCS. The NCS
model could improve these services for disabled children and children with health issues and
improve transitional arrangements as young people reach adulthood. 
Strategic aims for delivering The Promise and making improvements in children’s services have
been identified, which could be achieved by locating these services in the NCS. Including
children’s services in the scope of the NCS may be an opportunity to:
 address variation in access to and quality of services
 move to a more consistent national approach.
 set standards of care and strategic planning
 reduce variation in thresholds for services.
 improve accountability and shift focus to early intervention.
 improve alignment with community health services.
 improve transitions between children’s and adult services. 
Justice Social Work Services
Justice Social Work Services differ to other parts of the social care sector in that they tend to be
court imposed (and so are largely non-voluntary); have limited scope for the affected individual to
influence service delivery; can be partly aimed at the punishment of those who have committed an
offence in addition to rehabilitation and support; and have a focus on public protection and the
management of risk. These aspects will all be taken into account when considering how justice
social work services may be incorporated into the NCS (and what implications that may have for
the wider model of Community Justice), in close discussion with relevant stakeholders.
Community Health Services
We recognise that there are still a number of decisions to be made with regard to the scope of this
business case for community health, and that work to capture further detail and key issues in
Community Health more widely will continue for the next iteration. In relation to Community Health
services for children, further consideration is required regarding the inclusion of Children’s Services
within the NCS. Under the current Health and Social Care integration arrangements we have
services that must be delegated at a minimum and others such as Mental Health and Neurodiversity
services that are optional. This means there is currently much variation across Scotland. Delegation
of prescribed functions has not been consistent across the country, and this is leading to confusion
and a lack of clear accountability. Areas which have delegated a number of functions have
demonstrated the potential of integration and we therefore must now assess how best to advance
delegation of services under the NCS further.

Page 39

PBC 
2.4.1 NCS programme scope of delivery 
1. A National Board to oversee shared accountability.
The NCS National Board will ensure consistent, fair, human rights-based Social Care support and
Community Health services, underpinned by effective complaints and advocacy for people. At the
same time, it will support communities to maximise the benefits of reformed local delivery of
services.
The NCS National Board will drive forward improvements across the system by supporting
collaborative leadership and greater collaboration between partners. It will also seek to improve
the quality and consistency of services and ensure services are sustainable and person-led by
undertaking new functions at the national level that are not in place in the current system.
The Board will be accountable for standards, guidance, and performance metrics, with an agreed
support and improvement framework which will aim to help local areas when monitoring indicates
that standards are not being met.
The functions of the Board will be finalised through further work and co-design; however, at a high-
level agreement on the following functions has been reached:
o setting national strategic direction.
o developing standards, guidance, and operating frameworks.
o overseeing and seeking delivery assurance on local strategic plans and ethical
commissioning strategies.
o monitoring system performance.
o maintaining a support and improvement framework which will aim to provide support to
local areas when monitoring indicates that standards are not being met with powers of
intervention, when required, as a last resort.
o ensuring visibility of data, information, and analysis about social care support, social
work, and primary and community health services through reporting on delivery.
o national commissioning and procurement by agreement for complex and specialist
social care services which will include prison social care.
o seeking assurance on public protection arrangements; and
o providing support to local delivery partners. 
When it is established, the National Board will need to be supported to fulfil its functions. The
intention is for the National Board to enhance capacity in the system, and this needs to be
reflected in the way it is resourced. Further work is needed to determine the best way to support
the National Board and what its status should be. Our planning assumption is that, when the
Board is established, the Scottish Government’s work on policy, delivery and improvement activity
relating to the services in scope for the NCS will continue and will be aligned to the work of the
Board.
An assessment of the options for delivery, value and costs will be made through the development
of an outline business case on the development of the NCS National Board.
2. National Social Work Agency
The National Social Work Agency will provide a single national body with oversight of social work
education, training and professional development, and the improvement of social work services.
Its objectives will be to support and invest in the social work profession by providing national
leadership and overseeing social work education (pre/post-qualifying), improvement, workforce
planning, training, development, and implementation.

Page 40

PBC
It will work collectively with partners to address workforce pressures and factors impacting on
supply and the recruitment and retention of the social work workforce. The Agency will be located
within the Scottish Government but will be a partnership which works with key external
stakeholders and employers to support local solutions, develop regional approaches where
appropriate and where needed, national approaches. It will be an opportunity to address some of
the longstanding issues impacting on the sector and will seek to improve consistency in service
delivery and crucially, enable social workers to work more effectively to transform people’s lives
and implement rights-based practice.
3. Develop national functions.
There will be an ongoing need for Scottish Government to support Scottish Ministers. The
Programme will manage an organisational change project that will support integration by ensuring
policy development and improvement is delivered to support the aims and objectives of the NCS.
This will promote and foster more joined up person-led collaboration at local level between
different parts of the Health and Social Care system and other related services through effective
integration with the NHS at national level and effective joined up working across the public sector
at national level. 
Options for this will be determined through the Programme’s definition phase and will promote
integration and Getting it Right for Everyone (GIRFE) principles and embed Human Rights in
policy making and delivery across all areas of the NCS. Working to support the National Board in
policy development and improvement, ahead of the introduction of the National Board, the
National team will continue to support policy development and improvement, identifying and
delivering early improvements ahead of the introduction of the National Board. 
For the most part this will be a realignment of existing Scottish Government policy teams to
support joined up and integrated policy making in line with GIRFE principles. There will be a need
for some additional investment in some NCS National workstreams. These will include the
development of a complaints service and a consistent approach to independent advocacy, building
on services currently provided and filling gaps in provision where identified. Where that is the
case, the workstream will be supported by the development of specific business cases, that will
outline, costs, benefits, and value for money of proposed options for delivery. 
4. Transform local delivery through Reformed Integration Authorities
The shared accountability agreement between national and local government included agreement
that statutory delivery functions would remain with local government and health boards
respectively, along with assets, employment, and relevant funding. Consequentially, there are
provisions in the NCS Bill as introduced which would no longer be intended to be used as
originally envisaged. 
The Programme has therefore been examining whether the intended outcomes could be achieved
by putting forward amendments to the Public Bodies (Joint Working) (Scotland) Act 2014 under
which the integration authorities were created. We are now of the view that this is a reasonable
approach and would achieve the intended reforms in a manner proportionate to the aim. There
continues to be a need for reform, with significant changes needed at local level to realise the
intended quality and consistency.

Page 41

PBC
To ensure that there is a clear link between local and national shared accountability, the
programme will ensure through this project that processes are in place for reformed integration
authorities to be accountable to the National Care Service Board, with the National Care Service
Board responsible for reviewing, and securing assurance on the deliverability of local strategic
plans. 
Under this continuous improvement approach it is intended to carry over any existing powers
under the 2014 Act which have not yet been used in practice, such as the powers to allow
integration authorities to directly employ chief officers and other members of staff. 
We will also strengthen the opportunities for Integration Authorities to join together across current
geographical boundaries to achieve greater consistency, quality and economies of scale where
there is local agreement to do so. It is also the intention that the role of localities should be
strengthened, building on what works well and driving greater consistency in how these are set up
and used as part of community engagement, strategic planning, and other integrated functions. 
Finally, it remains the Scottish Government’s intention that the recommendation to give a greater
voice to lived experience within decision making structures should be actioned, including by
extending who on the board has voting rights. 
Local reform will be delivered in alignment with the Verity House agreement and the Programme’s
commitment to co-design. This will support the ambition to create a comprehensive Community
Health and Social Care service overseen by a National Board that supports individuals and
smooths transitions between different categories of care based upon local needs. Detailed scope,
benefits, value, and costs for the preferred approach to local reform will be presented as part of a
local reform business case.
5. Integrated Social Care and Health Record (IHSCR)
The Independent Review of Adult Social Care highlighted the frustration that many people felt of
being “asked to repeat the same information to several different professionals when better data
sharing arrangements would remove the need.” It highlighted how technology in general can “help
with people’s ownership of their care and support, particularly when people “own” their own data or
information that is about them and share it with the people who support.” To in part address this, the
Scottish Government consulted on the idea of ‘a nationally-consistent, integrated and accessible
electronic social care and health record’ in the Using Data to Support Care’ section in the formal
public consultation for NCS on. Notably, 85% of individuals and 89% of organisations taking part in
the consultation agreed to this proposal, supporting the idea that information about their health and
care needs should be shared across health and social care services. Moreover, there was a strong
view that care services should be more focused on individual needs and with individuals having
more access over their care and information.
The commitment to improving information sharing and access to information is long-standing: in
2018, the Scottish Government and COSLA committed to deliver “a Scottish health and care
'national digital platform' through which relevant real-time data and information from health and care
records, and the tools and services they use, is available to those who need it, when they need,
wherever they are, in a secure and safe way.” This followed a recommendation from an External
Expert Panel chaired by Harvard’s Professor David Bates and the conclusion from the Scottish
Parliament’s Health and Sport Committee report on technology and innovation in health and social
care that ‘the best way forward for data sharing is through a single platform, or spine, for data that
other systems connect into’.

Page 42

PBC
Work has progressed on this via NHS National Education for Scotland (NES) – the underlying
‘platform’ technology is a core part of the National Vaccine service, but it remains a long way from
realising the full ambition of the ‘national digital platform’ and providing citizen and professional
access to the right data at the right time. To address this, our 2021 ‘Care in the Digital Age’ Strategy
introduced in more detail our programme of work for accelerating citizen access – via a ‘Digital Front
Door’ (an existing PfG and Manifesto commitment) and, again joint with COSLA, our 2022 Data
Strategy for Health & Social Care extended this further to incorporate the recognised need to
develop an integrated social care & health record to enable professional access. 
Opening up citizen and professional access to relevant information has therefore long been a
strategic commitment of both the Scottish Government and COSLA, and is supported by all
stakeholders, international evidence and the Scottish Parliament.
Whilst work on a number of the underlying capabilities continues to progress, the core ‘routes in’
for citizens and professionals to access (and meaningfully use) health & social care information –
the digital front door and integrated record – don’t yet exist and as such will require major
investment in their own rights and will be subject to their own detailed business cases. Given the
significant dependencies between the NCS and these programmes of work (and the investment
required), the ISCHR business case will align closely with the NCS programme governance and
delivery arrangements.
By focusing our technology developments on the sharing of information across health and social
care, it is intended to establish an environment of collaboration across the public sector, positively
impacting the ability to provide joint planning, risk sharing and oversight. It is also intended that by
developing this in a national way, greater consistency and experiences of care will become more
possible across Scotland – currently, a small (but growing) highly localised examples exist but not
in a consistent, or equitable, manner. 
2.4.2 Statement of benefit
The NCS Programme. will build on the benefits contained in the statement of benefits as outlined
in the policy memorandum.
In tandem with the laying of the Bill in June 2022 a statement of benefit was published, this outlined
the overarching ambition and strategic outcomes the NCS would deliver for the people of Scotland.
Noting that “Care and support are an investment; they must work to remove barriers, tackle
inequalities and allow people to flourish and live their lives as they want to.”
The National Care Service will ensure consistency of provision and improvements in social care,
social work, and community health support, by working in partnership with people who access and
deliver services, trade unions, Local Government, and the third sector.
Working in partnership agreement has been reached that overall accountability will be shared
between Scottish Government, the NHS and local government. 
New governance arrangements in the form of a National Care Service Board will be introduced to
ensure consistently high levels of service across the country, while building the flexibility to meet
varying community needs at a local level.

Page 43

PBC
2.5 Delivery approach 
Co – design
The Programme has committed to deliver change through co-design. By collaborating with people
from all the different groups who will use and deliver services we can be more confident that the
changes will work for everyone. As the Scottish Approach to Service Design outlines in this way
we can design more responsive user-centred services by looking at the whole spectrum of needs
created by life events. This not only improves the quality and efficiency of the services but
improves outcomes for people who are trying to access services during stressful periods of
change.
We will design the services a NCS will deliver with the communities it will support in order to
ensure it represents best value for money, through building the right improvements that will impact
positively on the lives of the people of Scotland.
Phased approach
The Programme will build on current improvement work and ensure that opportunities to deliver
impactful change now ahead of the delivery of an NCS are maximised. Current improvement work
that the NCS is aligned to and will build on includes:
 “Getting it Right for Everyone” – new practice model that is person centred, human rights
based and secures a proactive single plan, actions and support from all agencies involved
in an individual’s life.
 Multi-disciplinary teams – originally set up to ensure health care is provided by the most
appropriate professional, centred around GPs and Allied Healthcare Professionals. Has
become a series of handoffs between professionals in most cases, rather than a team
around a person. Opportunity to focus this on the GIRFE model and broaden out to include
wider agencies.
 National Improvement Framework.
o The Framework will provide focus and structure for efforts to drive improvements
within the sector, giving flexibility for local areas to plan how to deliver and will be used
at a national level to track progress.
o This is being developed in partnership between the Scottish Government, COSLA and
SOLACE with representation from across the Social Care Support and Community
Health Sector to ensure the Improvement Framework captures the current and future
needs across the system. 
The NCS Programme will take a phased approach building on the work above. 
Phase 1: will further define the Programme and options for delivery; deliver the NCS Bill; establish
the National Board, National Social Work Agency (NSWA) and some national functions. 
Phase 2: will build on the work of the National Board and NSWA through embedding policy
development and improvements through collaborative working. Phase 2 will also set the
groundwork for local reform including development of the required secondary legislation. 
Phase 3: will see continued refinement of options for delivery of local reform. Options for delivery
will be considered in more detail as part of the local reform business case and will include
proposals for additional tests of change and phasing in Local Reform to support safe delivery and
mitigate risk.

Page 44

PBC 
In line with the above approach principles for test of change have been developed to support the
programme in successful delivery, these include:
 Continuity of Care and Public Protection must always be prioritised.
 Change should be gradual, and policy and delivery assurance through tests of change may
be required before full implementation.
 Evaluation and exit strategies will be agreed at the outset.
 Pathfinder activity should align with similar objectives and activity already underway to
avoid proliferation of national tests of change across the country. 
2.6 Wider Strategic Risks Associated with the Delivery of the NCS 
The Management Case section sets out how risk will be assessed and managed throughout the
lifetime of the Programme. Table 2 below sets out some of the wider strategic risks associated
with the delivery of the NCS, but these must be read in the context that further work around the
identification of risk will be undertaken as part of delivering this Business Case. Given the high
level and strategic nature of the risks set out in Table 2 it is difficult to assess the likelihood and
impact of these. Instead, they have been listed in order of how likely they are to crystallise,
Table 3: Wider Strategic Risks Associated with Delivery 
Risks
Affordability
The change will require investment, which will need to be balanced against other priorities if it is to
deliver the impactful long-term ambitions. Programme funding will require on-going management to
ensure that budgets are effectively and efficiently utilised and that Programme delivery plans are
regularly reviewed and adjusted, where necessary, to ensure that key programme milestones are
delivered in view of future budget agreements and changing scope – including cost and resource
requirements.

Page 45

PBC 
Risks
Relationships
The Programme requires cross government and public sector wide collaboration to ensure successful
design, delivery and implementation of Health and Social Care Reform through the National Care
Service. The agreement on shared accountability between Scottish Ministers, Local Authorities and the
NHS will require the creation of new governance structures that should not introduce risk to existing
governance, planning or delivery responsibilities.
Technology
Our current evidence base indicates that new technology will be required to deliver on the ambition of
the Integrated Health and Social Care Record. Whilst this is not part of the scope of the business case
the dependencies are such that the risk may impact on the NCS. This developing evidence base also
indicates a mixed picture of digital maturity in the Social Care Sector and a need therefore to invest in
the sector to improve digital capacity and capability to successfully implement the required technology.
This therefore poses technology risks in terms of successfully developing the technology; ensuring any
technology is sufficiently safe and secure for personal and special category data; and ensuring successful
implementation of said technologies into the sector.
Maintaining existing services
The existing Health and Social Care System is already stretched, safely landing additional change in that
environment will be a challenge. Careful planning and prioritisation of the phasing of change will be
required in mitigation. Changes to the existing system must not result in a reduction of service quality or
introduce additional risk to the services experienced by individuals.
Public sector Interfaces for people do not improve.
Implementing NCS delivers improvements in Health and Social Care but exacerbates the need for
effective interfaces between Health Services (e.g. primary and secondary) and other public services such
as housing and education.
People
There is a risk that the focus becomes system driven rather than focusing on the needs of people. The
consultation provided an evidence base for change, but we must continue to put the needs of users at
the heart of the change to deliver real and impactful change that meets their needs, supported by clear
communication of the Programme’s approach to co-design.
Localism
There is a balance to be struck between the development of national standards, consistency, and
transfer to new model of shared accountability to Ministers versus the flexibility needed to meet local
geographic and demographic differences.
Bureaucracy
Creation of a national board without consideration of local delivery and improvement may be seen as an
additional layer of bureaucracy, additional cost and layers of decision making as well as the risk of
creating new artificial boundaries between services.

Page 46

PBC
2.7 Key Constraints and Dependencies 
This section sets out the key constraints associated with both the NCS Programme, and also
considers the wider constraints associated with delivering the NCS alongside other Scottish
Government priorities.
Key Constraints associated with the NCS Programme
There are three key constraints associated with the NCS Programme, these are explored in more
detail at the headings below:
1. Resource
Undertaking the NCS Programme will require considerable resources, both from the Scottish
Government and from the Social Care Sector. Necessarily, the Programme will need to be
delivered within the available resources.
This Programme seeks to address complex issues within a complex system. Conducting the work
necessary to deliver a service which addresses these issues require investment. The
accompanying shared accountability paper sets out the anticipated financial resourcing
requirements in detail. There is a resource constraint on the social care sector, which may limit the
input available. There is heavy demand on a sector which is subject to its own resource
constraints. Given the user-centred design approach which the NCS Programme intends to take,
engagement from the social care sector is integral to the delivery of the Programme.
2. Stakeholders
As set out in the previous section, the NCS Programme is aware of the demand on that sector,
and the resulting resource constraints on the Scottish Social Care Sector. An additional constraint
is the willingness of stakeholders to engage with the Programme, especially as their engagement
is required to successfully deliver the change. So far, the NCS Programme has been able to
access the necessary level of stakeholder engagement. The Programme will also have to balance
the competing views of stakeholders e.g. balancing the views of system leaders, workforce, and
service users. 
2.8 Key Interdependencies for the NCS Programme 
The interaction between the Social Care Sector and the Third Sector will be a critical
interdependency for the NCS Programme. The Scottish Government recognises that the care and
support offered through the third sector community groups and third sector organisations of all
sizes are central to ensuring that people who need care support, and their families, have the
assistance with day to day living they need. This support also very often goes beyond regulated
care provision to ensure a better quality of life-based on wellbeing and human rights. It is critical
that this input is protected and promoted as part of future design. To deliver this, it is vital that the
breadth of input from the third sector to the social care system is understood and incorporated.
We must also consider the wider public sector reform landscape, and potential changes in the
future, for example the development of the Single Authority Model, changes to the operating
model of the NHS or wider reforms. The NCS legislation is being developed to enable such
flexibility and to support wider reforms and the programme will remain engaged with these
proposals as they emerge.

Page 47

PBC
2 Economic Case
Introduction 
The NCS Programme is being developed in partnership with COSLA and the NHS. As such, the
Programme continues to be defined through ongoing negotiations regarding respective
responsibilities and practicalities around service delivery. Dependent on the final form that the
NCS takes there is potential for substantial benefits to be realised from its introduction and the
associated wider social care reform, committed to by the Scottish Government. This Economic
Case quantifies what these could be and provides a framework for future detailed quantification of
benefits as the programme develops. 
Future iterations of the Programme Business Case (PBC), and subsequent underpinning Business
Cases, will outline the options for implementation of the NCS, following further decisions. At these
points in time, the evidence around the economic benefits, as well as costs, will continue to be
developed and refreshed and any gaps will be addressed. 
3.1 Background 
The reform of Community Health, Social Work and Social Care has been a high-profile item on the
public policy agenda in Scotland, over the last two decades. The intention to introduce a National
Care Service (NCS) builds upon principles and ambitions that are well established, but which have
not been fully realised to date. The rationale for the NCS is that the scale of transformation needed
to meet aspirations for a rights-based, person-centred system that delivers a better experience
and better outcomes for the people of Scotland, requires a fundamental, system wide change and
a new approach to Community Health, Social Work, and Social Care. This would aim to go beyond
both the individual and cumulative scale of reforms undertaken to date. 
3.2 Current situation 
Demand for Health and Social Care services has been unprecedented in recent years and is
expected to rise in the future. The current population structure includes a large concentration of
people in their early-50s to early-70s.31 Owing to higher life expectancy, compared to previous
generations, the latest projections suggest that the number of people aged 65 and over will grow
by nearly a third by mid-204532. In addition to this, estimates of Healthy Life Expectancy (HLE) –
the number of years an individual will live in ‘very good’ or ‘good’ general health – have been
falling in recent years. It is now estimated that children (both male and female) born in 2018-20
will, on average, spend a shorter proportion of their life in good health, relative to those born in
2009-11.33 Whilst predicting the future demand for Social Care is extremely challenging, factors
such as those highlighted here represent significant likely pressures on both Scotland’s current
and future social care systems. 
The concurrent fall in the working age population puts additional pressure on public finances,
making it even more challenging to achieve change and improvement. As such, it is critical that 
31 Mid-2020 population statistics.
32 National Records of Scotland (2023) (link).
33 National Records Scotland (2022) (link)

Page 48

34 Independent Review of Adult Social Care (2021) (link) 
PBC
the Scottish Government are able to respond in an efficient and cohesive way to deliver
consistent, high-quality Social Care Services, focused on the needs of the Scottish population.
At present, Local Authorities and Health Boards work together as Integration Authorities to assess,
plan and commission local Community Health and Social Care services in their local areas.
Integrated Health and Social Care is delivered through 31 Integration Authorities across Scotland.
Under these arrangements, Local Authorities remain statutorily responsible for the delivery of
Social Work and Social Care, and Health Boards for delivery of healthcare, on behalf of the
Integration Authorities. Scottish Ministers have limited statutory responsibilities for the delivery of
Social Care and Social Work Services locally. 
3.3 Independent Review of Adult Social Care 
The case for reforming the delivery of integrated health and social care arose out of an
Independent Review of Adult Social Care (IRASC)34. Conducted in the latter half of 2020, and
published in February 2021, the report concluded that whilst there were strengths in Scotland’s
Social Care system, it required revision and redesign to enable a step change in the outcomes for
people in receipt of care or accessing Social Care support. The critical role of Social Care, in
supporting people to live well and to have their rights respected, was further demonstrated starkly
during the Covid-19 pandemic.
The challenges identified by the IRASC included:
 Inconsistency of user experience ("postcode lottery")
 Complex and inconsistent governance arrangements
 Lack of national oversight and collaboration
 Lack of collaborative and strategic leadership
 The need for a paradigm shift in care support to one underpinned by rights.
 Non-integrated budgetary and financial planning 
The IRASC report found that the current arrangements for delivery of Integrated Health and Social
Care by Health Boards and Local Authorities, means that lines of accountability are not clear, and
this results in complexity in the system and poorer services for people. The IRASC concluded that
fundamental changes were needed regarding who is responsible for delivering Social Care in
Scotland and how that delivery is organised. This is because, although incremental reforms have
been ongoing for a number of years, people accessing Social Care support are still faced with
significant challenges in securing the services they need. 
3.4 Options 
This section presents the risks of continuing with business as usual and the additional benefits of
introducing the NCS. 
3.5 Option of Business as Usual 
IRASC identified that many current costs in Social Care are driven by crisis management and late
interventions. An example of these, and related poor outcomes, are those experienced by people
who are delayed in hospital. It is estimated that delayed discharges cost the system £134 million a

Page 49

35 Independent Review of Adult Social Care (2021) (link) 
PBC
year, plus the wellbeing loss experienced by individuals.35 This is an illustration of one of the costs
of the current system that could potentially be mitigated against by improving on business as
usual. 
If the IRASC recommendations are not implemented and we continue with piecemeal reforms to
the Social Care system, then there are risks that increasing inefficiencies could cost more than
investment in a new delivery system. 
A new system which enables strategic integration, national oversight, and accountability, would
provide opportunities to invest in preventative care, rather than crisis responses, avoiding
expenditure on poor outcomes such as those experienced by people who are delayed in hospital.
When instances such as this are considered across the whole social care, social work, and
community care landscape, there could be considerable costs that are avoidable if the current
system can be improved to better support the health care system and relieve pressures here.
Without a better developed social care system, pressure will continue to mount on the NHS and
there will be increased costs both of treatment and impacts on patients. 
Not only are there risks to continuing with business as usual due to the current pressures on the
health and social care systems, but these risks will be compounded by the forecasted increase in
demand, discussed above, as a result of the aging and worsening health of the population.
Continuing with business as usual becomes increasingly risky, as the system reaches breaking
point. As this increased demand for social care services starts to materialise, it is likely that service
quality will decrease under business as usual. 
3.6 Option of The National Care Service 
The Scottish Government is aiming to implement the recommendations from the IRASC through
ongoing social care reforms and the creation of the NCS. It is hoped that this will allow Scotland to
be better equipped to tackle both current and future issues in health and social care.
So far, agreement has been reached to establish an NCS Board as the primary means through
which to operationalise and manage shared accountability.
Discussions are still ongoing around the NCS Board including membership. The Board will,
amongst other things, determine the national strategic direction; set standards, guidance, and
operating frameworks; monitor system performance; and provide a framework for support,
improvement, and intervention. Further work and co-design is required to set out how the NCS
National Board’s monitoring and oversight functions will work in practice, and how those functions
will align to, and interact with, those community health, social work and social care support
services agreed to be within the scope of the NCS.
At the local level, it is expected that the existing IJBs will be reformed. These reformed IJBs will
have additional functions to deliver reforms, such as: a new independent chair who will be
accountable to the NCS Board; support for lived experience representatives to ensure unpaid
carers are able to attend board meetings; and improved consistency in the role of locality
managers.

Page 50

36 Measures of National Well-being Dashboard - Office for National Statistics (ons.gov.uk) 
PBC
3.7 Costs 
The Financial Memorandum and shared accountability paper provides information on the cost
estimates for the NCS Programme, as described in the Bill. 
3.8 Benefits 
This section outlines the potential benefits that may result from the NCS legislation and
Programme. These benefits cannot be quantified at this stage and there remains a high level of
uncertainty over the design of the remainder of the NCS. However, where possible, we have
provided illustrative figures to demonstrate the scale of benefits that could be in scope, depending
on the delivery of the NCS, to accompany the qualitative discussion. 
The three key pillars through which the NCS will deliver benefits, as outlined in Stage 1 of the Bill,
are: consistency, integration, and accountability. 
The NCS will enable people to access timely, consistent, equitable and high-quality health and
social care support across Scotland. 
The NCS is intended to continue the integration of health, social work, and social care support to
deliver benefits, both to those working within and those accessing social care, as well as to wider
healthcare services and society as a whole. 
There will be improved accountability in the system through the role the NCS Board itself will take
in monitoring system performance and driving a transparent framework of support, improvement,
and as a last resort, intervention, in cases of service failure or emergencies. 
The impact of these pillars are subsequently considered in two parts: the direct benefits of the
NCS; and the benefits of wider reform that the NCS enables to be maximised. It is expected that
these benefits would accumulate gradually over the next decade, rather than immediately after the
introduction of the NCS. 
Direct benefits of the NCS 
This section illustrates the direct benefits that the NCS could potentially deliver to those receiving
and providing care, through shared accountability; consistency; and integration. These benefits
come about through generating improved wellbeing outcomes of several groups. 
Wellbeing 
Wellbeing is defined by the Office for National Statistics (ONS) as “how we are doing” across ten
domains of wellbeing, as individuals, communities, and a nation, and how sustainable this is for
the future.36 Personal wellbeing, which is concerned with the experience of the individual, is the
most direct representation of how people are doing. Measures in this domain, as set out by ONS,
cover people’s views on their current life satisfaction, whether the things done in life are
worthwhile, and their happiness and anxiety levels. It is held that improvements to these ratings
represent a benefit to the individual in question.

Page 51

PBC 
It is important to understand this, as it is hoped that the NCS will help deliver wellbeing benefits to
those involved – both receiving and providing support – in the social care system. The current
context in the UK, is set out in ONS personal well-being statistics.37 
Focusing on Life Satisfaction, the latest estimates show that individuals in the UK, on average,
scored 7.45 out of 10 in the year ending March 2023, with scores of those living in Scotland
marginally higher at 7.49.38 Individual’s characteristics and circumstances can have a tangible
impact on their relative score. Across the UK, those that reported themselves as having Bad (Very
Bad) health, some of which may be recipients of social care, reported significantly lower levels of
life satisfaction of 5.86 out of 10 (4.65 out of 10). 
The section which follows looks to outline how it is anticipated that the NCS Principles will help to
deliver wellbeing related benefits. 
For individuals receiving care
The NCS Board will drive national strategic direction and provide standards and guidance to
address unwanted variation in the system, and drive improvements in the care delivered. 
The presumption in favour of further integration recognises that any transitions individuals
receiving care go through – be it in terms of geography, age, stage, or between health and social
care services – should be smoother. 
By strengthening the voice of lived experience in planning and decision making, health and social
care services that better meet the needs of users will be provided. 
For those working in care
Through mechanisms, such as the establishment of a National Social Worker Agency (NSWA), it
is expected that the policy will support the social work sector. This should drive improvements in
workplace standards, leading to overall improvements in job satisfaction levels. For those working
in social care, the expectation is that locality managers, engaging the community to a greater
extent, will improve the channels through which carers can raise concerns to the reformed IJBs. 
Alongside this, consistent training and career opportunities should be provided, enabling an
improvement in the experiences of the paid workforce, regardless of what part of Scotland they
are based in. 
Continued integration means that information flows and communication should improve between
health and social care services, making it easier for staff to manage transitions and improve
working relationships. 
37 Personal well-being in the UK - Office for National Statistics (ons.gov.uk)
38 People living in communal establishments (such as care homes), or other non-household situations are not represented in the APS and,
subsequently, are not captured within reported figures on personal wellbeing (link).

Page 52

PBC
Improvements to wellbeing 
Illustrative examples of improvements to wellbeing are provided below, for those who receive care
and for those who work in Adult Social care. In line with Green Book Supplementary Guidance, the
potential annual benefit from an improvement in wellbeing can be monetised.39 
This guidance proposes that a one-point change in life satisfaction, measured on a scale of 0 to
10, has a central value of £13,000 (low: £10,000, high £16,000) (2019 prices), per person per
year. This is referred to as a 'wellbeing adjusted life year’ or ‘WELLBY’. For illustrative purposes,
we look at the benefit that could be derived from a 0.1 improvement in wellbeing (equivalent to
10% of a central WELLBY), for 10% of each of the different groups. 
In 2021/22, there were 236,000 people in Scotland reportedly receiving social care support or
services.40 If it is assumed that 10% of this group (23,600 people) experience a 0.1 point
improvement in wellbeing because of the establishment of the NCS for the reasons discussed
above, then this could lead to a potential annual benefit of around £34 million (2021 prices). 
In 2021, there were around 130,000 people employed in the Adult Social care sector.41 If it is
assumed 10% of this group (13,000 carers) experience a 0.1 point improvement in their wellbeing
on the life satisfaction scale because of the establishment of the NCS, then this could lead to a
potential annual benefit of around £19 million (2021 prices). 
These are illustrative examples and are not intended to be used as true estimates, rather to
demonstrate that there is potential for substantial benefits depending on how the NCS is
implemented. The actual benefits which materialise could vary considerably depending upon the
number of people who benefit and the scale of benefits that accrue to individuals. 
Additionally, whilst these illustrative examples look to monetise the potential benefits to individuals'
wellbeing, it is important to recognise that they are non-cash releasing. This means that whilst
there are quantifiable benefits they do not lead to a direct reduction in spending or increases in
incomes. 
Benefits of the NCS maximising the benefits of wider reforms. 
The establishment of the National Care Service, and the potential direct benefits it may bring,
should also be considered alongside the wider social care investment that the Scottish
Government has committed to. This includes increasing adult social care pay to £12 an hour,
reopening the Independent Living Fund, removing charges for non-residential social care, and
overhauling eligibility.42 
By driving national improvements and bringing national oversight and accountability to the sector -
it is expected that the NCS will enable additional investments to go further and provide high quality
care for more people than otherwise would be the case. If the NCS enables wider social care 
39 Green Book Supplementary Guidance (link)
40 People supported - Insights in social care: statistics for Scotland - Support provided or funded by health and social care partnerships in Scotland
2021/22 - Insights in social care: statistics for Scotland - Publications - Public Health Scotland
41 This only includes those working in adult day care, adult placement services and housing support/care at home. It does not consider health
workers: Scottish Social Services Council, August 2023 (link)
42 Programme for Government 2023 to 2024 (link)

Page 53

PBC
reform to potentially reach those currently outside the formal care system, there are two main
groups who would benefit further, those with unmet need and unpaid carers. 
This section illustrates the potential marginal benefits that could be realised by the NCS, when
paired with wider policy reform which increases the provision of social care in Scotland. It is
important to note that provisions for such wider reform are not matched by costs set out in the
financial memorandum. Costs for increasing provision will instead be covered in individual policy
costings, for the wider reforms. 
Unmet need and unpaid carers
Currently, the social care system primarily provides support to those with critical or substantial
needs. Through wider social care reform, the Scottish Government has committed to overhauling
eligibility criteria, changing to a human rights approach that centres around need, rather than using
eligibility as a tool to control budget. It has also committed to removing the financial deterrents for
accessing such care. As such, it would be expected that social care within Scotland will reach
further and provide support to more people – including those with current “unmet needs”. 
For these reforms to be effective, and to reach the large sub-population of unmet need in
Scotland, the social care infrastructure and governance that the NCS will bring needs to be in
place. As such, it is plausible that the NCS will enable greater benefits to be achieved for those
currently with unmet need. 
IRASC estimated that, in 2018/19, there were 36,000 people in Scotland who “do not currently
have access to social care support to whom it would be beneficial”.43 and44As an illustrative
example, if it is assumed that 10% of this group (3,600 people) were to experience a 0.1 point
improvement in their wellbeing on the life satisfaction scale, the potential annual benefit could be
around £5 million (2021 prices).45 
People with unmet need are not the only group, within the informal care system, who could benefit
in such a way. There are estimated to be around 839,000 unpaid adult carers living in Scotland.46
Evidence shows that that these unpaid carers often experience lower earnings, and lower levels of
physical health than non-carers.47, 48 If the NCS where to enable a greater proportion of the people
that unpaid carers care for to access formal care (beyond that which a care system without an
NCS is able to) and reduce their unpaid caring needs, it is plausible that the NCS could lead to
improved health outcomes for unpaid carers. The benefits which materialise could vary
considerably depending on the number of people who benefit and the scale of benefits which
accrue to individuals. 
Young carers 
Another group that could benefit from the introduction of the NCS is young carers, who are a sub-
group of the unpaid carer group. As stated above, if the introduction of the NCS leads to a greater
proportion of the people that young carers care for, being able to access formal care and 
43 Independent Review of Adult Social Care (2021) (link)
44 The figures quoted are likely to under-estimate the scale of unmet need. However, work is ongoing to improve evidence around unmet need.
45 HMT Green Book, Supplementary Guidance (link)
46 Number of adult carers (aged 18 and over) living in Scotland 2020: Scottish Health Survey (link)
47 Brimblecombe N., Knapp, M., Stevens, M., & Cartagena Farias, J., (2020). The high cost of unpaid care by young people: health and economic
impacts of providing unpaid. BMC Public Health, 20:1115, https://doi.org/10.1186/s12889-020-09166-7
48 Thomas, G.P.A, Saunders C.L., Roland, M.O., & Paddison, C.A.M. (2015). Informal carers’ health-related quality of life and patient experience in
primary care: 195,364 carers in England responding to a national survey, BMC Family Practice, 16:62, DOI 10.1186/s12875-015-0277-y

Page 54

PBC
subsequently reduce their unpaid caring needs, then there are potential benefits specific to young
carers, regarding their educational participation and attainment. 
Over a quarter of young carers in the UK, aged 11 to 15, are reported to regularly miss school due
to their caring responsibilities and, when they do attend, that the burden of their caring
responsibilities can adversely affect their levels of tiredness and concentration.49 This can have a
lasting effect on their life chances.50 If the NCS enables young carers to reduce the number of
hours of care which they provide, beyond that achieved in a system without an NCS, not only
could this lead to health improvements (similar to those discussed for wider unpaid carer group),
but it could also lead to improvements in their educational attainment. This could then have a
knock-on effect on the quality of their future employment and earnings, labour force participation,
and ultimately the taxes they pay. This is an area that needs greater exploration, in order to
understand and quantify the potential benefits.
Wider benefits 
If formal care can replace care that is currently provided by unpaid carers, then this could
potentially lead to wider benefits too. Insights taken from Scotland’s Carers Census reported that
30% of unpaid carers reported that caring had affected their employment51. These proportions
were higher for those between the ages of 25 to 65 and how they were impacted, varied both in
scale and by gender. By reducing the barriers to individuals’ ability to work more hours or take up
new jobs, it can be assumed that there would be an associated increased participation within the
labour market. This is an area that needs greater exploration, in order to understand and quantify
the potential benefits. 
Any such increased participation in the labour market would be expected to have wider benefits for
society. For example, such individuals will receive an increased disposable income. This will then
lead to increased spending and saving of individuals, contributing positively towards economic
growth. Additionally, there may also be benefits to the state of increased revenue (through
additional tax receipts) and potential savings (through reduced provision of benefits, for example,
Carer’s Allowance). 
Another key area of benefits resulting from the NCS is the possibility of efficiency savings. This
need not be that overall costs fall, but that costs per unit of social care falls. If improved
management, integration of services or general logistics led to even relatively incremental time
savings for staff, then this could have substantial benefits across the system. Further analysis into
the scope and scale of these wider benefits will be carried out, to support the further development
of both the Programme and underlying businesses cases. 
3.9 Risks 
As options have not been evaluated at this stage, it has not been possible to quantitatively assess
risk. However, we have identified risks that would warrant further investigation in future Business
Case iterations. 
Risk categories are drawn largely from standard Government guidance and include risks in
funding and design from additional costs that may arise; reputational risks if standards are not 
49 Action for Children (link)
50 Action for Children (link)
51 Carers Census, Scotland, 2021-22 - gov.scot (www.gov.scot)

Page 55

PBC
met; operational and volume risks stemming from higher workforce costs or over utilisation of
services; commercial risks due to difficulties in transitioning of services; and environmental risks
from having to meet net zero targets. 
It could be argued that the introduction of the NCS offers greater mitigation against, for example,
the potential risk of reputational damage by actively implementing measures that prevent
standards from not being met. There is therefore less chance of that reputational damage and a
lower overall risk score. Conversely, it can be argued that continuing with business as usual will
become increasingly risky, as the system reaches breaking point. Establishing an NCS could
enable the system to deliver care in a more efficient way, which in turn would result in a lower risk
of the system reaching crisis point. 
3.10 Next steps/conclusion 
There is potential for substantial benefits to be realised from the NCS, and the associated wider
social care reform, committed to by the Scottish Government. This Economic Case illustrates the
potential scale of these benefits and provides a framework to enable future detailed quantification
of benefits as the programme develops. 
Discussions between the Scottish Government, COSLA, the unions and the NHS have been still
ongoing. Once these have concluded, the implications of these discussions are understood, and
subsequent options for how the NCS will be implemented are known and developed, we will refine
this Economic Case and those in future underpinning business cases. This will provide more
detailed analysis on the scale of benefits that each option provides compared to its costs to
provide a value for money assessment. We will continue the development of the evidence base for
the NCS, to ensure informed decisions are made that offer best public value to society.

Page 56

PBC
4. Commercial case
4.1 Overview 
This Commercial Case section recognises that to support the NCS Programme two main strands
of procurement activity are likely to be required. Firstly, there will be a requirement to engage
procurement colleagues in activity related to the processes and timescales that will inform the
purchase of goods or securing of services as required to establish the National Care Service
National Board including any support services. Secondly, procurement professionals will also be
engaged in the purchase of services such as user research, professional advice, and stakeholder
engagement related services as need is identified, to support the NCS programme. This will
include supporting the ongoing co-design and policy development, meeting the commitment to
design the detail of the NCS with people with lived experience, the workforce and key
stakeholders including delivery partners.
As individual requirements for key procurements become clear, market engagement and
Statement of Requirement activity will be described in Commodity Lead Procurement Strategies
that relate to those workstreams (rather than in the Programme-level Business Cases). That work,
and those Commodity Lead Procurement Strategies will ensure that procurement activity is
compliant with procurement legislation and standards, including Digital Scotland Service Standard
(DSSS), sustainable procurement standards, fair work first, and data security considerations - from
both the programme and the supplier’s perspectives.
It is recognised that Procurement colleagues are key stakeholders not only in the delivery of the
Programme policy and outcomes but also as prospective supportive stakeholders of the future
delivery boards in live running. Procurement colleagues are also leading projects within the
programme including the reform of procurement guidance and tools to embed an ethical
procurement approach, working with colleagues on how procurement will be delivered within the
national care service, and the development of a market shaping approach. As the National Care
Service Programme continues to develop, its requirements for key procurements and commercial
relationships will change and develop to meet the Programme’s evolving needs. The nature of this
Programme, close working with policy teams across it, and comparisons with similar recent
programmes in the Scottish Government (particularly the Social Security Programme) has
informed this Commercial Case and reasonable predictions of the types of services that will be
required to be made. Commentary on sourcing those services is provided below.
Scottish Government Procurement Strategy
The Scottish Procurement and Property Directorate (SPPD) has published its Procurement
Strategy for 2022-24. As part of the core Scottish Government, the NCS Programme is bound by
that Procurement Strategy. The Programme will be supported by The More Powers
Implementation Procurement (MPIP) team which acts in accordance with this strategy when acting
for the Programme. The Scottish Government Procurement Strategy notes that the Scottish
Government’s key priorities are centred on contributing to Scotland’s purpose of creating a more
successful country, with opportunities for all to flourish, through increasing sustainable and
inclusive economic growth. This is underpinned by the National Performance Framework,
Scotland’s National Strategy for Economic Transformation (NSET) and the annual Programme for
Government which sets out the plan for policy delivery, public procurement priorities and
legislation over the next year. It ensures compliance to, and delivery of the priorities through the
sustainable procurement duty as outlined in Procurement Reform (Scotland) Act 2014. Our
strategy continues to support the Scottish Government’s work on addressing climate change,
supporting, and embedding a fair work first approach, tackling child poverty, delivering COVID-19

Page 57

PBC
recovery, and building our constitution. The sustainable procurement duty helps public sector
organisations identify opportunities to include economic, social, and environmental considerations
in contracts and show how our procurement activity contributes to the National Outcomes and
Indicators and, in turn, to Scotland’s NSET. We develop sourcing strategies for each procurement
project worth £50,000 or more. This work is supported by the Sustainability Test and, where
appropriate, the Sustainable Public Procurement Prioritisation Tool (SPPPT). We track our
contribution to the Scottish Government’s purpose and priorities through our compliance with the
sustainable procurement duty.
In doing so the Programme ensures our activity furthers our Procurement Strategic Aims and
Objectives such as.
 Tackling Child Poverty through Fair Work First. Our vision is that by 2025, people in
Scotland will have a world-leading working life where Fair Work drives success, wellbeing
and prosperity for individuals, businesses, organisations, and society. We use public
procurement to tackle in-work poverty and, by extension, child poverty by ensuring job
security and fair pay in our contracts.
 Climate change. Our sustainable procurement tools include indicators and guidance to
support Scottish public sector buyers to consider and act on several climate change and
circular economy considerations. We are committed to acting on climate change and to
develop the circular economy by buying goods and services which reduce emissions,
minimise waste and allow for repair, re-use, refurbishment, or recycling wherever
appropriate.
 Covid recovery. The strategy covers commitments described in Scotland’s National
Strategy for Economic Transformation and Scotland’s Programme for Government. This
includes using the £13.3 billion annual procurement spend across the Scottish public
sector to boost inclusive economic recovery, support longer term economic wellbeing,
and a just transition to net zero. Our tools and guidance will influence and empower
buyer, supplier, and key stakeholder communities to use public procurement to support
an inclusive and green economic recovery.
The strategy is underpinned by detailed guidance on each stage of the Procurement Journey
(phases of activity). 
4.2 Commodity level Procurement Strategies 
Commodity level Procurement Strategies set-out the approach to buying the goods, services and
works in a series of procurements. These strategies are bespoke on a procurement-by-
procurement basis and include sections on the choices of procurement procedure or potential
payment mechanism as these will be defined in each commodity level procurement strategy to suit
the needs of the individual contract. These Procurement Strategies are aligned with the Scottish
Governments overarching procurement strategy. 
4.3 Work Streams, Forward planning, and Required Outputs 
The Programme level picture of procurement requirements will constantly evolve as projects mature.

Page 58

PBC
The Programme has so far identified requirements such as research, consultation analysis,
professional advisors, contingency labour, and digital expertise. Commodity-level Procurement
Strategies will be developed for each of these when the value is greater than £50,000. As the
Programme is already in operation, contracts for these types of services have already been secured
for the Programme. For each of these service types, the work to date has demonstrated sufficient
market capacity and multiple routes to market, including existing frameworks, Dynamic Purchasing
Agreements, and open competition. There are no current issues regarding the interdependency
between pace and scope of the Programme and MPIP’s ability to secure the required services
through these routes to market. 
MPIP in conjunction with the Programme will develop a procurement Forward Plan and contracts
register of detailing priority contracts. The Programme procurement ‘Forward Plan’ is a live
document and will assist the Programme to plan for future procurements, manage contract relets,
manage resources, and understand which projects should be considered prioritised. 
4.4 Property requirements 
No property is intended to transfer from Local Authorities to establish the National Care Service, but
the National Care Service may have property requirements (for example, occupying space in
existing Scottish Government offices). Scottish Procurement Property Division continue to advise
on property requirements for the Programme. Property Division will support the Programme in
appointing appropriately experienced external advisors and are managing the delivery of
professional services for property matters for the Programme. The Chief Surveyor leads commercial
advice in relation to the acquisition of Property for Scottish Government Core Directorates and
Agencies. 
4.5 Digital requirements 
The Digital Strategy for Scotland, “A Changing Nation: How Scotland Will Thrive In A Digital World”
sets out the role digital will play and this, together with other relevant digital strategies such as Cyber
Resilience underpin our approach to digital procurement activity. 
When appropriate, the MPIP team undertake pre-market supplier engagement to ensure that the
market is aware of future procurement activity prior to the publication of tender documents. This is
designed to increase supplier participation in the procurement process and provide increased
opportunities for the delivery of innovative digital solutions and de-risk delivery outcomes. In
delivering the procurement of projects including digital platforms and software, the agile approach
is used predominately. 
4.6 Governance Relating to Procurement and Commercial Activity 
Delegated Purchasing Authority (DPA) is the authority to enter into a contract for goods, services
and works and applies to all contracts placed by the Scottish Government. Purchasing Authority is
separate from budgetary authority and the two cannot sit with one individual. This is common across
both public and private sectors and is standard fraud prevention measure. A Budget Owner can
decide to allocate funding to a particular initiative, but they cannot award a procurement contract.
Delegated Purchasing Procedures must be followed for all procurement exercises:

Page 59

PBC
 Delegated purchasing authority for low level spend (i.e., contracts valued under
£50,000) typically sits with trained (Delegated Purchasing Officers) Programme
officers and is supported by the MPIP team where required.
 Regulated procurement activity (contracts worth £50,000 or more) is managed
by the MPIP Team. The Head of MPIP has a commercial delegation of
£75,000,000 ex VAT and is ultimately responsible for the commercial due
diligence of contract awards up to this value. DPA of higher values sits with
other officers in the Scottish Procurement and Property Directorate and they
will be drawn-into the governance of high-value projects as required. 
4.7 Governance Relating Budgetary Approval 
The National Care Service Programme Budgetary Governance is described in the Management
case section.

Page 60

PBC 
5. Finance Case 
For the purposes of this version of the case the accompanying shared accountability paper should
be referred to.

Page 61

PBC
6. Management Case
6.1 Introduction 
The approach to management of the Programme is set out below.
Scottish Government, Director General of Health, and Social Care (Accountable Owner) are
delivering the Programme. A Senior Responsible Officer (SRO) leads the Programme, the Director
of the Social Care NCS Development Directorate. The cross-cutting nature of the Programme
requires collaborative working across the Scottish Government, Local Authorities, NHS, and the
wider social care sector to develop policy, design and implement an NCS that brings together
community health and social care to improve the service for the people of Scotland.
The preferred programme management methodology is a hybrid model supported by Managing
Successful Programme (MSP®), using both agile and waterfall methodologies. Agile
methodologies will be used where an iterative approach is required, with waterfall methodologies
adopted where a linear and more traditional approach is preferable.
The sections below set out how this methodology is applied. 
6.2 Programme and Project framework 
6.2.1 Programme high level structure 
A Programme structure has been developed, which sets out the Programme, scope, underpinning
projects, which will include detailed workstreams and programme functions. This sets out what the
programme will deliver.
Figure 2: 
Scope
For the purposes of this PBC, the management case section applies to all projects and
workstreams which will contribute to the delivery of the NCS. Further evidence will be considered
on the inclusion of Children and Families and Justice Social Work as well as final decisions on the
community health services that will form part of the NCS. The programme planning assumption is
that all areas are in scope until such time as a final decision is made, this is essential to ensure

Page 62

PBC
their needs and any impacts are fully considered. Each of these areas will be represented in the
teams delivering the Programme, projects and workstreams.
Level 1 Programme
The Programme refers to all projects, work streams and functions required to deliver the NCS, the
Programme SRO is accountable for the successful delivery of the Programme and its expected
benefits and outcomes, they have delegated responsibility for underpinning projects to Project
Responsible Owners as outlined below.
Level 2 Projects
The Programme will deliver a fully integrated NCS, for the purposes of delivery and good
governance five overarching projects have been identified that underpin the successful delivery of
the Programme. These are NCS National Board, National Social Work Agency, National functions,
Local reform. The Integrated Social Care and Health Record is also listed here given the
significant dependencies between the projects. As a major project, it will have its own governance
arrangements that will be embedded with the NCS Programme. Each project has a project
responsible owner who is accountable for the successful delivery of the project, underpinning
workstreams and expected benefits and outcomes. In line with the Programme’s business case
strategy, where appropriate, each project will be supported by a business case.
Level 3 Workstreams
Sitting below the projects are a number of interdependent workstreams. Each workstream will
have an identified owner that aligns with the Programme governance and accountability structure.
Programme functions
In addition to the workstream delivery, the Programme requires functional teams who will ensure
common programme management processes are applied consistently across the programme, the
expectation is that these will cease at programme closure. Some examples of functional teams in
the current Programme are:
 Communications and Engagement
 Analytical Services
 Co-design
 Finance
 Change management.
 Programme Management Office
6.2.2 Appointed Personnel and vacancies 
The Programme has appointed an Accountable Owner, Senior Responsible Owner, Project
Responsible Owners and workstream leads.

Page 63

PBC
Figure 4 – Senior Team 
The figure above shows the senior team responsible for delivery of the NCS and the critical
dependency of the Integrated Health and Social Care Record. The senior team are supported by
workstream and functional leads.
As outlined above, the programme is led by the Senior Responsible Officer (SRO) who, in line with
the Scottish Public Finance Manual (SPFM), has delegated responsibility from the Accountable
Officer for the successful implementation of the Programme, with Scottish Ministers remaining
accountable for policy.
The SRO is supported in successful delivery by senior civil servants with considerable experience
in all areas in scope of the NCS as well as specialism in digital, design, user research, analysis,
legal and project management.
In recognition of the wide scope and complex governance of the National Care Service
Programme the Programme Management Office are putting in place a bespoke Senior
Responsible Officer delegated authority which will be supported by Director level Programme
Responsible Officers from across Scottish Government. 
In addition, the Programme leadership is supported by the advice and guidance of a range or
professional advisors who provide expert input and advice on the role of the professions within the
current sector. An embedded Programme Management office ensures robust governance and
reporting processes are in place to support the successful delivery of this Programme. 
6.3 PMO Governance and Reporting Arrangements 
6.3.1 Reporting Arrangements 
The NCS Programme has in place robust reporting arrangements, in line with the programme
structure and hierarchy outlined above, proportionate reporting arrangements are in place at
workstream, project and programme level. Workstreams report into regular project working
groups, covering progress against plans, and risks and issues. In turn projects report into the
Programme Delivery Board (PDB) on a fortnightly cycle. The PDB tracks and monitors progress
against plan, risks and issues and programme costs. In addition, the Programme provides a report
to the dedicated programme assurance board and to Minsters via the Cabinet Sub Committee. All
Programme reporting arrangements support SG corporate reporting.

Page 64

PBC 
6.3.2 Scottish Government Internal Governance Arrangements 
The programme has established an internal governance structure to support programme delivery
and enable timely decision-making at an appropriate level of authority, providing assurance to
senior stakeholders and Ministers. The internal governance arrangements and Ministerial
oversight support the cross-cutting nature of the Programme through having representation from
all areas in scope or impacted by the NCS.
The Programme Delivery Board is the Programme’s main decision-making board for
implementation decisions. It is here where the SRO is given assurance that project deliverables
and milestones are being delivered. Above the Programme Delivery Board, sits the NCS
Assurance Board, acts as an escalation point for the PDB. This provides senior cross-Government
assurance to the Scottish Government Executive team that the Programme is managed
effectively.
Additionally, the Programme has established governance forums subordinate to the PDB, these
include project working groups, the risk review panel and co-design assurance group which work
with designated authority from the PDB.
Project Working Groups provide detailed oversight and governance at a project level, reporting
into Programme level governance via the PDB. The Risk Review Panel provides management and
oversight of the Programme risk profile to ensure threats to Programme objectives are minimised
and opportunities maximised.
The Co- Design Assurance Group’s role is to ensure that a consistent and co-ordinated approach
to co-design is being taken across the programme. The Group also manages the administration
for the Lived Experience Panel and the NCS Stakeholder Register.
Parallel to the internal governance structures within the NCS programme, there are several forums
for engagement with external stakeholders, those who access and work in care and organisations.
There will be a need enhance governance arrangements as the Programme progresses to support
the development of shared accountability through the national board, this will be likely to include
representation of key delivery partners.
Figure 5: NCS Programme Governance Landscape

Page 65

PBC 
6.3.3 Programme Management Office (PMO) 
The Programme is supported by programme functions including a Programme Management Office
(PMO) that provides support, coordination, and control across the Programme.
The PMO consists of a central team led by the Programme Manager and overseen by the SRO. It
delivers consistency across the programme by developing and maintaining a set of PMO
strategies which set the standards for all programme management functions.
All PMO owned strategies, processes, artefacts, and templates are living documents and are
maintained and updated regularly. In the initial phases of the Programme, the team oversee
standards and processes including in the following areas:
 Programme Governance, Reporting and Secretariat
 Planning and dependency management
 Programme Assurance
 Resource management
 Risk and Issues
 Change Control
 Benefits Realisation
6.4 Programme Planning 
This section will outline the programme approach to planning and dependency management,
including the high-level programme schedule of delivery, the programme phases and change
management approach, and how it will be monitored and controlled. In addition, the section will
provide an overview of the Programme’s approach to underpinning business cases to support
future investment decisions and the Programme costs. 
6.4.1 Programme Schedule 
The National Care Service is a significant transformation programme and will be delivered over
several years. The programme is structured to deliver in phases, supporting the need for early
improvement balanced with the need to maintain continuity of safe care.
The current priority for the NCS programme is to support the passage of the Bill and secondary
legislation during this Parliament to create a strong framework for the future delivery of social care
across Scotland and putting in place the enabling functions that will allow the programme to
implement the programme deliverables on a phased basis.
The programme phases are supported by the agreed co-design process. Through co-design and
phasing the Programme is working to ensure that we close the ‘implementation gap’ between
legislation and delivery as highlighted in the Independent Review of Adult Social Care.
Figure 6: High level route map & programme phasing

Page 66

PBC 
Programme planning strategy.
The programme high level route map for delivery will be supported by the Programme planning
strategy which outlines the three-level approach to planning, programme, project and workstream,
that supports successful delivery through consistent application of planning controls.
Programme phasing
As outlined in the figure below the Programme will be delivered in phases. This supports the
Programme to prioritise continuity of safe care. This ensures that much needed improvements can
be rolled out ahead of full reform whilst mitigating the risk of landing significant change on an
already stretched sector. The phased approach allows for co design, test of change, and
evaluation of change to support decision making on future change activity.
The starting point is not the same across Scotland, with some Integration Joint Boards already
operating with full delegated powers for both children’s health services, children’s social care
services and criminal justice social work services. The Programme’s phased approach will protect
these existing partnerships and ensure we do not inadvertently roll back on the commitment to
integration that supports people. The Programme approach to phased transition will reduce the
risk of transfer and support co-design and inclusion of local areas. It may be that for some
localities, change can be implemented in advance of the timelines set out in the current planning
assumptions. 
6.4.2 Business Case approach 
The NCS business case approach will follow HM Treasury Green Book methodology in developing
proposals for the scope, planning and delivery of the NCS programme.

Page 67

PBC
The PBC seeks to outline the key decisions made to date, the scope, case for change,
overarching strategic benefits and funding envelope required over the lifecycle of the Programme.
The case also outlines how the Programme will be managed and the phases of delivery. The case
will be an iterative document and updated at key phases of the Programme as options for delivery
develop. 
The PBC will be underpinned by project business cases that will provide additional detail to
support investment decisions in line with the phases of the Programme. 
Figure 8: Business Case approach 
NCS B  SINESS CASE APPROACH 
6.5 Co-design 
Co-Design Approach
The Programme has committed to deliver change through co-design. This approach will involve
engaging with three key groups through its co-design activity.
People with experience:
This includes people who need health and social care support and their friends and family, people
who deliver health and social care support and people who might need support in the future.
People with experience matter because people’s experiences of how the current system works
help us to think together about what a future system of care might look like. What is happening in
people’s lives can affect their health and social care, or their work in health and social care, so it’s
important we think about that too. 
By collaborating with people from all the different groups who will use and deliver services we can
be more confident that the changes will work for everyone. Participating in things like this is also
an important human right. 
Integrated
Social Care
& Health
Record
Business
Case  Underpinning
Business Cases
OBC/FBC
Local reform
National Social
W
ork Agency
National Board
Purpose
Set out the:
Scope
Funding envelope
Phases of the Programme
that align with the annual
budget setting process
Programme Business Case
Phase 1 Phase 2 Phase 3

Page 68

PBC
Delivery partners:
This includes the organisations which deliver social care services and organisations that support
social care services. Delivery organisations matter because organisations that provide health and
social care services locally, or support other organisations to do that, understand the opportunities
for change in the current system, they also understand where there are barriers to change, and
what works well. They are vital to helping us be sure that proposed changes can be put in place. 
Stakeholder organisations:
This includes organisations that represent different communities (organisations that represent
communities that might find it harder to connect directly with publicly promoted co-design
activities) and organisations that have a key connection to social care. 
Stakeholder organisations mater because they have a great deal of knowledge about groups of
people who access health and social care support, or deliver health and social care support, and
about particular issues that affect the delivery of care. They are also in a unique position to
promote or conduct co-design activities with communities with whom they have trusted
relationships, increasing access to communities that might find it hard to otherwise engage in the
process. 
Combining the views of all three groups, creates a rich set of ideas and insights from many
different points of views to inform decision making. 
To deliver this approach the Programme will structure the co-design activity in phases. These are
as follows:
 Understanding: Thinking about what needs to change and why. Looking at the data and
evidence that exists and agreeing what it tells us and where more is needed. Considering
the things that will impact what change can happen.
 Making sense of information and coming up with ideas (sometimes now as ‘Sensemaking’):
Generating ideas about what could change, how change might work, look, and feel. Testing
out ideas for changes and making sure they will work in practice.
 Agreeing: Helping to check that proposed decisions that result from the work of
understanding and imagining are the right ones. This would also include ensuring that
proposals are affordable, legal, deliverable, and proportionate.
 Drafting of regulations / service design: Co-design conclusions will be developed into
regulations where appropriate or taken forward into service design.
 Review: It will be important to share the draft regulations or service design plans back with
people for review of the alignment with co-design process. 
6.5.1 Themes 
As outlined in the Programme structure design themes have been identified, whilst not exclusively
the case for all co-design engagement, the Programme will often choose to align a number of
policy areas to larger themes, known as ‘design themes.’ This allows for co-design activities to be
conducted within the scope of a larger thematic area, with the insights gained then being aligned
with the more granular policy areas of scope through analysis sessions.

Page 69

PBC
Co-design is central to successful delivery and is therefore embedded in the governance
structures, as outlined above there is a dedicated co-design assurance group that supports
decisions making on co-design on behalf of the PDB.
Successful delivery will require effective stakeholder engagement and communication. The
Programme will prioritise meaningful, inclusive, and accessible stakeholder communications and
engagement. The priority will be to disseminate timely and accurate information and to ensure that
the voices of the diverse range of partners and stakeholders with an interest in the NCS are heard,
with an emphasis on the centring of the voices of people with lived and living experience of
accessing and delivering social care support. The key objective underpinning all NCS programme
communications and engagement activity is that; 
The Programme Strategic Communications and Engagement unit aims to ensure that we
communicate and engage with these groups in meaningful and inclusive ways and will support
colleagues to do so, ensuring that the voices of our diverse range of partners and stakeholders are
heard.
Co-design activity will continue and grow over the lifecycle with participants drawn from the Lived
Experience Experts Panel and the Stakeholder Register, as well as partnership work with
stakeholder partners. 
6.6 Building our Communications Channels and Messaging 
The NCS Programme has developed a communications strategy to support different elements of
the Programme. This followed audience insights research in early 2023. The communications
strategy and plans are based on evidence and developed in conjunction with stakeholders.
The audience for this strategic messaging is internally across the Programme, Scottish
Government and externally with stakeholders, people with lived experience and the wider public.
This is supported by the Key Stakeholder Reference Group and focused Key Stakeholder Steering
Group, both of which include a wide range of stakeholder representatives from across all sectors.
Channels in place, include internal newsletter, presentations, online content including blogs and
social media, stakeholder newsletter and stakeholder toolkit.
Our ‘Voices’ of community health and social care video campaign has been another key channel
for shining a light on the diverse living and lived experiences of those accessing and delivering
care and their hopes for a future NCS.
The Programme will continue to build a strategic and joined up approach to stakeholder
engagement. 
6.7 Monitoring and Control 
The Programme has in place monitoring and control processes to support successful delivery, the
includes the governance arrangements outlined above and proportionate risk and change control
arrangements.
People with lived and living experience of community healthcare, social work, and social care
services, those delivering services, and the wider public are at the centre of our work in
creating a National Care Service for everyone, with equality, dignity, and human rights at its
heart.

Page 70

PBC 
6.7.1 Risk Management 
The Programme has in place proportionate risk management processes. This includes programme
level risk log and supporting processes to ensure its regular and robust management.
The Programme’s Risk and Issue Management Strategy sets out the purpose and goals of the risk
and issue management framework required within the NCS Programme. This strategy provides
risk management guidance to the Programme to ensure the application of a consistent,
standardised approach which is in line with the wider risk protocols of the Scottish Government
and for the management of issues that arise from them.
The approach uses assessments from subject matter experts within the Programme to identify
programme risks and to identify and implement the appropriate mitigations. The process also
enables scrutiny and discussion of risks, as well as mitigations at the Risk Review Panel (RRP)
and facilitates the regular update and consideration of these risks. The RRP is subordinate to the
Programme Delivery Board, which is provided with regular reporting of programme level risks and
acts as an escalation point for RRP where risks are deemed to require greater intervention by the
panel. 
6.7.2 Change Control 
Change Control Strategy is designed to ensure that changes are made at the appropriate level, by
the people with the authority to make them. Change Control introduces a robust process for
scrutinising changes that are made to key elements of the Programme, such as scope, planning or
budget. 
6.8 Programme Assurance 
The Programme is establishing an Assurance process linked to the Governance arrangements.
This will include both independent and internal assurance activity.
This will include Gateway reviews, Gateway 0 at Programme level with Gateway 2-5 at project
level, mandatory digital assurance, and internal audit. In addition, the Programme will engage
regularly with Audit Scotland.

Page 71

1 
NATIONAL CARE SERVICE (SCOTLAND) BILL – UPDATED FINANCIAL MEMORANDUM
DECEMBER 2023 
1. In line with the request from the Finance and Public Administration Committee in their report published 1 December 2022,
this paper provides an update to the Financial Memorandum for the National Care Service (Scotland) Bill, as an annex to the
Scottish Government’s response to that report. 
2. This version reflects the Bill as Introduced, and the costs that would arise should the Parliament decide not to make any
significant changes to the Bill at Stage 2. New text and tracked changes to the text are shown in red to be clear where and what
the updates are. Where no changes are shown, the text of this document remains that of the Financial Memorandum submitted
with the National Care Service (Scotland) Bill as Introduced on 20 June 2022. Separate papers set out the key changes that the
Scottish Government proposes to bring forward, following the agreement made with COSLA on shared accountability, and the
anticipated impact of those changes on the costs arising from the Bill. 
3. Original tables are shown which can be directly read back to the Financial Memorandum at 20 June 2022. Updated tables
are presented below the original tables and now show a ten year period compared to the original five years, due to the longer
phasing of Care Boards being established. 
4. The Scottish Ministers originally gave a commitment to deliver a National Care Service (NCS) by the end of this Parliament.
This assumed that there would be wider agreement on the progression of local structures and that there would be sufficient funding
and resources available. In consideration of the current financial position nationally and within the Scottish Government, what is
achievable within the current anticipated funding envelope has been reviewed, alongside the effect of the longer time taken for
scrutiny of the Bill by Parliament. It is expected that the national level part of the NCS will be established during 2025-26 (as
described below, the NCS at national level under the Bill as introduced would be part of the core SG), and again, under the Bill as
introduced, NCS local care boards were assumed to go live during 2028-
29. As such, the costs outlined in the tables below have been re-phased across a ten year period from 2022-23 to 2031-32 to account for this and
so there are some significant financial moves between this update and the original Financial Memorandum.

Page 72

2 
INTRODUCTION 
5. This Financial Memorandum is structured as follows: 
From paragraph
Background 8
Summary of total costs of the Bill After 23 (Table 1)
Establishment of a National Care Service and Care Boards 26
Care boards 47
Health and Social Care Information 66
Right to Breaks from Caring 69
“Anne’s Law” – Visits to or by care home residents 85
Changes to powers and functions of the Care Inspectorate 100 
6. Each part will examine the estimated costs for the different sectors involved, including, as appropriate, the Scottish
Administration, Local Authorities, Health Boards, other public bodies, businesses and third sector organisations, and individuals.
Each part will set out:
 the best estimates of the administrative, compliance and other costs to which the provisions of the Bill will give rise;
 the best estimates of the timescales over which the costs and savings are expected to arise, and
 an indication of the margins of uncertainty in these estimates.
7. The figures set out in this Financial Memorandum represent the Scottish Government’s best estimates of the costs of the
activities affected by the provisions of the Bill. These figures are not spending commitments and should not be used as a tool for
future budgeting, as costs may be affected by other factors in addition to the changes made by the Bill. Funding for the organisations
involved will be negotiated in the usual way taking into account the projected costs of their functions at the time. 
BACKGROUND 
8. The purpose of the National Care Service (Scotland) Bill is to improve the quality and consistency of social services in
Scotland. Part 1 gives the Scottish Ministers a duty to promote a comprehensive and integrated care service, and gives them the
powers they need to achieve that, including making provision for the establishment of care boards to carry out Ministers’ functions
in relation to social care and community

Page 73

3 
health. Part 1, Chapter 6 gives the Scottish Ministers powers to transfer relevant functions from local authorities or from health boards. “The
National Care Service” (NCS) means the Scottish Ministers and care boards working together to deliver those functions. 
9. Part 2 of the Bill allows for information sharing and information standards and is intended to underpin the creation of the
nationally- consistent, integrated and accessible electronic social care and health record. This will help professionals to support
individuals in a more co- ordinated way, and support national and local planning and commissioning. 
10. Part 3 makes additional reforms to the delivery and regulation of care. It introduces a right to breaks from unpaid caring, and
Anne’s Law, to support people living in care homes to maintain contact with family and friends even in outbreak situations. It makes
changes to the powers of the Care Inspectorate, and Health Improvement Scotland. These are all changes that can be implemented
to improve the lives of people who access social care support and their carers before the NCS is established. Some of them take
the framework approach to allow for further engagement and flexibility; others are more detailed where they address specific points
in existing legislation. 
Framework and Co-design approach 
11. It is essential that reforms to social care support must be developed with the people who access that support, including
unpaid carers, and with those who provide it. The Scottish Government is committed to engaging with people with experience to
co-design the detail of the new system, to finalise new structures and approaches to minimise the historic gap between legislative
intent and delivery. For that reason the bill creates a framework for the NCS, but leaves space for more decisions to be made at
later stages through co-design with those who have lived experience of the social care system, and flexibility for the service to
develop and evolve over time. Some of those future decisions will be implemented through secondary legislation, others will be for
policy and practice. 
12. As a result of this framework and co-design approach, there are increased uncertainties surrounding the cost estimates, and
the timing of those costs. Estimates for a range of possible options have been included in this Financial Memorandum where possible
and the costs have been timed to deliver an operational NCS and begin the reform of local delivery by the end of this Parliament.
Future decisions about the implementation and phasing of the NCS will take into account rigorous, evidence-based options
appraisals, value for money, where benefits and quality are paramount, and the resources available to ensure affordability. Where
those decisions are implemented through secondary legislation (under this Bill or through pre-existing powers), financial and
regulatory impact assessments will be provided. The Parliament will, therefore, have further opportunities to examine the cost
implications of the Scottish Government’s proposed reforms to the social care system.

Page 74

4 
Other planned reforms 
13. The costs set out in this Financial Memorandum reflect community health and social care services as they are currently
delivered, and estimates the changes to those costs that will result from the provisions of this Bill. However, the creation of the
NCS and other changes made by the Bill are only part of a wider programme of social care reform. Other elements of those reforms,
that do not require primary legislation and could go forward irrespective of the Bill, are likely to have an impact on the overall cost
and expenditure on community health and social care support during the time period covered by this Financial Memorandum. In
order to focus only on the impact of the Bill, the estimates provided here do not include the effect on the NCS of the following
Scottish Government commitments:
 To increase pay and improve terms and conditions for adult social care staff in the third and private sectors, including
establishing appropriate channels for workforce and trade union representation
 To bring Free Personal Nursing Care rates in line with National Care Home Contract rates
 To remove charging for non-residential care
 To increase investment in social work services
 To increase provision of services focusing on early intervention and prevention
 To invest in data and digital solutions to improve social care support.
14. Overall the Government has committed to increase public investment in social care by 25% over this Parliamentary session (2021-
26). 
15. Creation of the NCS will support many of these reforms; for example, it is intended that it will support greater consistency in the
provision of services focusing on early intervention and prevention, and in ethical commissioning which will promote Fair Work
standards for staff. However, these are policy decisions to be made or sustained under the new framework, not necessary
consequences of the Bill provisions. 
Economic benefits of establishing the NCS 
16. The purpose of creating the NCS is to improve the delivery of community health and social services. Social services have a
significant economic impact, and therefore investments in improving their quality and consistency can have a positive effect on the
economy.

Page 75

4 
17. Making Scottish Ministers responsible for social care with local care boards commissioning community health and social
care together enables:

Page 76

5 
 the development of a system based on and driven by shared principles which enshrine human rights and person-centred
care with opportunities for the voice of lived experience to be embedded in all levels of decision making;
 opportunities to build on health and social care integration and to bring together different services to with a focus on
outcomes and to help smooth transitions for people - noting that there needs to be further evidence gathering to see if
children’s services and justice social work should be brought in scope of the NCS;
 strengthening of ethical commissioning of care;
 the development of clear and consistent standards and to support the delivery of high quality and improve consistency; and
 market oversight to promote the financial sustainability of social care providers and, where necessary inform service
design and market shaping to help ensure the market for social care as a whole remains vibrant and stable which will
ensure continuity of quality social care provision.
18. This in turn, is expected to lead to the benefits for people and for Scotland’s wider society and economy through improved
community health and social care support for people those who need it and their families, with people being able to access services
when they are needed. It is also expected to lead to improved experiences for those who work in social services through
strengthening fair work in the sector and improved support and recognition for social work and social care. This will help with
workforce retention and recruitment. 
19. In 2020 social services directly employed 209,690 people, approximately 8% of the Scottish workforce, with a whole time
equivalent (WTE) of 159,2601. A 2018 report commissioned by the Scottish Social Services Council (SSSC)2 quantified the direct,
indirect and induced contributions that the adult social care sector makes to the Scottish economy:
 The direct economic value of social care activity is estimated at £2.3 billion - £2.6 billion (dependent on measurement method
used).
 The indirect economic value of goods and services in the sector’s supply chain is estimated at £0.5 billion - £0.6 billion.
 The induced impact associated with goods and services bought by those directly or indirectly employed by the sector
are estimated at £0.7 billion.
 The indirect and induced impacts resulted in an additional 50,800 jobs.
1 Scottish Social Service Sector: Report on 2020 Workforce Data | Scottish Social Services Workforce Data (sssc.uk.com)

Page 77

5 
2 The Economic Value of Adult Social Care (https://data.sssc.uk.com/data-news/15-announcements/175-the-economic-value-of-adult-social-
care#:~:text=The%20adult%20social%20care%20sector,and%20Wales%20published%20similar%20reports.)

Page 78

6 
 The total estimated economic value of the sector is therefore in the range £3.5 billion - £3.9 billion (excluding harder to
quantify catalytic effects). 
20. A report by the Women’s Budget Group (WBG) of the International Trade Union Congress (ITUC) identified that for every £1
spent on social care, more than £2 is generated in other sectors3. The same group4 estimates that the majority of new jobs created
by investment in social care will be taken by women. Investment in social care can therefore help to reduce the gender pay gap.
The large reach of the sector also has an important contribution to make to tackling inequalities, including child poverty, and meeting
Scotland’s climate change and sustainability goals through more efficient use of estates, travel, and waste. 
21. The social care sector has an important role in supporting local economies across the country. Social care employment and
investment is present in every area of Scotland; in areas of economic disadvantage the sector can be a critical employer, particularly
in areas with high youth unemployment. The sector is also an important procurer and purchaser of goods and services and this
can have important local benefits. The sector can direct spending towards local small businesses, voluntary, and community
organisations rather than national corporations, and can also lead through setting importance on quality non-financial standards in
procurement processes. 
22. Investment in social care support generates social value in terms of people’s emotional wellbeing and better health. A study
of the Independent Living Fund in Northern Ireland estimates that every £1 spent generates £11 of social value5. Both for people
who use social care support, and equally importantly for unpaid carers, the availability of high quality adult social care support can
help people to engage in and remain in education and also to enter and remain in work. 
23. Improving social care support, particularly increasing early intervention and prevention and supporting unpaid carers to
protect their health and wellbeing, also reduces costs which would otherwise fall on other parts of the public sector. This can include
unplanned hospital admissions, additional residential care needs, and family breakdown. It is difficult to estimate the size of these
wider savings and benefits in total but the Scottish Government expects these to be considerable. Some estimates relating to the
benefits of improving support for unpaid carers are provided in paragraphs 72-75. 
3 Investing in the Care Economy - Womens Budget Group (wbg.org.uk)

Page 79

6 
4 Investing in the Care Economy - Womens Budget Group (wbg.org.uk)
5 44188-ILF-NI-Impact-Evaluation-Report.pdf

Page 80

7 
SUMMARY OF ESTIMATED COSTS OF THE BILL 
Table 1: Total estimated costs of Bill provisions 
Note: in all tables, there may be small discrepancies in totals due to rounding
As per published Financial Memorandum on 20 June 2022 
Sector 2022-23 2023-24 2024-25 2025-26 2026-27 
£ millions £ millions £ millions £ millions £ millions
Total
estimated
costs of Bill
provisions 
24-36  63-95  84-126  232-477  241-527
Establishment and running of NCS national organisation – table 6
Scottish
Administration 24-36 60 - 90 72 - 108 92 - 138 83 - 124
Establishment and running of care boards – table 7
Scottish
Administration 0 4 - 6 12 - 18  
Care boards    132 -326 142 - 376
Total NCS
costs 24-36 63 - 95 84 - 126 216 – 452
224 - 464
216 - 488
225 - 500
Right to breaks from caring* - table 11
Care Boards - - - 8 – 13 16 – 27
Anne’s Law – table 14
Care
Inspectorate 0.186 0.09 0 0 0

Page 81

8 
*Note that tables 10-14 show costs to 2034-35
Note the Finance and Public Administration Committee were previously notified6 that there is a mathematical error for 2025/26 and 2026/27 in
the above table 7 extract. Total NCS costs for these years should be £224m - £464m, and £225m to £500m respectively and so have been
updated. 
Updated as per December 2023 
Sector
2022-23 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
£m £m £m £m £m £m £m £m £m £m
Total estimated
costs of Bill
provisions 
13  11 - 13  13 - 17  32 - 46  45 - 64  64 - 115  105 - 353  158 - 438  210 - 524  229 - 609           
Establishment and running of NCS at national level – table 6
Scottish
Administration * 13 11 - 13 13 - 17 19 - 27 18 - 26 17 - 26 17 - 26 18 - 27 18 - 28 18 - 28
Establishment and running of care boards – table 7
Scottish
Administration 0 0 0 0 0 7 - 30 0 0 0 0
Care boards 0 0 0 0 0 0 33 - 247 70 - 309 106 - 371 109 - 433
Total 0 0 0 0 0 7 - 30 33 - 247 70 - 309 106 - 371 109 - 433
Total NCS costs 13 11 - 13 13 - 17 19 - 27 18 - 26 24 - 56 50 - 273 88 – 336 124 – 399 127 - 461           
6 Minister for Mental Wellbeing and Social Care (parliament.scot)

Page 82

9 
Right to breaks from caring - table 11
Social Care /
Care Boards 0 - 0 0 13 - 19 27 - 38 40 - 59 55 - 80 70 - 102 86 - 125 102 - 148
Anne’s Law – table 14
Care
Inspectorate  0.19  0.09  0.05  0  0  0  0  0  0  0
Total right to
breaks & Anne's
law 
0 0  0  13 - 19  27 - 38  40 - 59  55 - 80  70 - 102  86 - 125  102 - 148
*Note that costs in 2022-23 are based on actuals, 2023-24 are forecast outturn. 
Variance 2022-23 23-24 24-25 25-26 26-27 
£m £m £m £m £m
Scottish Administration -11 – -23 -49 – -77 -59 – -91 -73 – -111 -65 - -98
Care Boards 0 -4 – -6 -12 – -18 -132 - -326 -142 - -376
Right to Breaks & Anne’s law 0 0 0 5 – 6 11 
Reasons for Variances:
 The most significant change is driven by the movement as to when NCS local care boards will go live. The go live date
has been moved to 2028-29 from the original estimate of 2025-26. See table 7 for a further breakdown and explanation.
 Due to a clearer understanding of the requirements in the set-up of the NCS at National level, obtained through the co-
design workshops and engagement with people with lived experience, the NHS and COSLA, the NCS programme has
reprioritised and rephased various workstreams to reflect the new understanding. Ensuring value for money has been a
focus of these considerations. This has led to a significantly reduced financial outlay for the Scottish Administration in
the assumed set up phase under the Bill as introduced compared with the original FM. Tables 3-6 provide further detail
on the changes that have driven this reduction. In summary, they relate to a far more streamlined staffing complement
with reduced agency involvement alongside the reduction in external procurement of services and the utilisation of
existing Scottish Government systems, where previously there had been provision for new systems.

Page 83

10 
 Inflationary assumptions have been revised in light of more recent data, see table 1A for full details on the changes
made to the inflationary assumptions. To summarise, the changes are variable but from 2023-24 onwards the picture is
one of reduced inflationary impact. 
INFLATION 
24. Following the significant volatility in the rate of inflation throughout the course of 2022-23 and 2023-24 the inflation estimates
used in the original Financial Memorandum have been revised. This is part of ongoing financial modelling work to track changes to
inflation and a range of other assumptions. 
25. The Office for Budget Responsibility (OBR) and Scottish Fiscal Commission (SFC) forecasts have been assessed, and will
be used as the basis for inflation going forward. Source documents can be found here: Where can I find your latest forecasts? -
Office for Budget Responsibility (obr.uk) – link to document under 1.7 supplementary economy tables / Scotland’s Economic and
Fiscal Forecasts – Scottish Fiscal Commission – May 2023 Report
 The projected figures extend to 2027/28. Given the extended timeframe due to the assumed rephasing of Care Boards
going live, the Bank of England target inflationary figure of 2% has been applied from 2028-29 onwards.
 The below rates have been used for all future year non pay cost calculations. This impacts costs throughout the Financial
Memorandum.
Table 1A: Inflation (was not numbered in finance memo before) 
As per published Financial Memorandum on 20 June 2022 
2020-21 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27
2.3% 2.5% 6.2% 6.2% 2.0% 2.0% 2.0% 
Updated as per December 2023 
2020-21 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
0.6% 4.0% 10.0% 4.1% 0.6% 0% 0.8% 1.7% 2.0% 2.0% 2.0% 2.0%

Page 84

11 
Pay Uplifts
 In line with revising non pay inflation as set out above, assumptions on pay uplifts have also been revised.
 Scottish Government pay awards were analysed between 2015-2016 and 2024-2025, 2024-25 was included following
the agreement on the multi year pay deal between SG and its employees, but no direct correlation was found between
the average pay award and the CPI inflationary figures across this period. The average pay increase over this period was
2.8%, with 2023-24 excluded from the average as this was an outlier due to the unprecedented impact of inflation. The
2.8% average figure has therefore been applied to all staffs future forecasts from 2025-26 onwards, the exception being
direct care workers as set out below, to ensure consistency.
 Care workers pay is based on the National Living Wage commitments from 2021-22 to 2023-24 while Auxiliary staff are
based on the Real Living Wage. The staff in scope for transfer (under the Bill as introduced) are Local Government
employed staff. We are aware their pay will not track directly to the National Living Wage / Real Living Wage but this
provides a standard minimum assumption to work from. Pay inflation of 5% has been applied to this group to conform
with historical averages and based on the ongoing Fair Work commitments.
ESTABLISHMENT OF A NATIONAL CARE SERVICE AND CARE BOARDS 
Current costs of social care support and community health 
26. Part 1, Chapter 6 of the Bill provides powers to allow for the transfer of social services functions from local authorities to the
Scottish Ministers or to care boards. The functions covered by these powers include adult social care and social work, children’s
social work and social care, and justice social work. In relation to services for children and justice, further work will be undertaken
with stakeholders to consider the risks and opportunities, and to rigorously assess the costs and benefits, before decisions are
made about implementing the transfer and how it might be phased. Section 30 makes provision requiring the Scottish Ministers to
consult publicly about any proposed transfer relating to children’s or justice services before regulations are brought forward. A
summary of the process and responses received to the consultation must be laid before Parliament at the same time as the draft
regulations. Ministers will also have powers to transfer functions from health boards to the new care boards, and to delegate their
own health functions as NCS functions, in order to maintain the integration of community health and social care functions. 
27. The figures for the costs of delivering services which may transfer, set out in table 2, provide a range of estimates in which
the lower figure would cover only the transfer of adult social care, and the upper figure would include the transfer of all the services
mentioned in paragraph 24 above. These are not additional costs to the system therefore have not been included in table 1.

Page 85

12 
28. Care boards will have the statutory duty to carry out the transferred functions in their local area, and will hold the funding for
them. Care boards will plan and commission local services. Social work and social care support will continue to be delivered by a
range of public, private and third sector partners. For services currently provided in-house by local authorities, that may continue
under a procurement arrangement with the care board, or the care board may take over direct delivery, with staff transferring to the
care board. These will be decisions to be taken locally as the care boards are established, following careful options appraisals. It
is expected that health services will continue to be delivered by the NHS, as commissioned by the care board. 
29. It is anticipated that the Scottish Ministers may transfer some functions, at least in part, to themselves, and the NCS at national
level may plan, commission and procure social care services for people with complex and specialist needs across Scotland. Further
decisions will need to be taken, in discussion with those accessing and providing such services, about which services may be
treated in this way, before any estimate can be made of what proportion of costs they will represent. 
30. Table 2 sets out the approximate current and projected costs of the services that could be transferred to care boards and to
the Scottish Ministers. In terms of the total costs to the public purse, it is assumed the transfer of services itself has no effect: the
costs of providing these services will simply transfer from local authorities and health boards to the NCS. Any policy decisions
between now and the date of transfer would be taken into account in rebasing the transfer value. Subsequent sections of this
Financial Memorandum set out the additional costs relating to setting up the new bodies, and to issues such as aligning terms and
conditions for staff transferring from different organisations. 
31. The transfer of functions may take place immediately on establishment of care boards in 2025-26 2028-29, or may be phased
with different functions transferring gradually over a number of years. A phased approach may result in a period of double running
costs or transfer costs in addition to the costs set out below, these would be anticipated to be applicable to back office functions
only. Decisions on the timing of transfers will be subject to rigorous readiness and financial assessment to ensure value for money
and affordability, as well as ensuring there is no disruption to the provision of support to people. 
32. The costs set out in table 2 are based on a range of caveats and assumptions as follows:
 Figures are presented in real terms, based on the most recently available full data collection. The Local Finance Return
(LFR) data for Local Authorities is from 2021-22 while the NHS cost book data is taken from 2019-20. This is due to
removing the outlier COVID year data and many NHS Boards not completing full returns in the subsequent years as a
result of ongoing COVID pressures. Public Health Scotland (PHS) note that a full data collection is expected for the 2022-
23 data but this is currently still under development (source: Scottish health service costs - High-level costs summary
2021 to 2022 - Scottish health service costs - Publications - Public Health Scotland)

Page 86

13 
 Local government finance statistics - gov.scot (www.gov.scot) based on Local Financial Return on Social Work (LFR03)
 Scottish health service costs - CostsBook 2020 (April 2019 to March 2020) - Public Health Scotland.
 They do not account for any impact of Covid on services, to avoid extrapolating forward any non-recurring expenditure.
 Figures given here are illustrative to show a scale of the services in scope. Figures represent the Scotland-wide costs
of functions which are expected to be transferred to care boards. Currently, the range of functions delegated to Integration
Authorities is different in each area, therefore the costs of future NCS functions cannot be extracted from integration
budgets.
 The LFR03 captures actual total expenditure by local authorities on Social Work services as reported in their published
annual accounts and is therefore the most accurate data on costs available at this time. This will not necessarily agree
with specific funding allocations, such as for justice social work services, as local authorities will utilise additional
resources to meet expenditure commitments (Block grant, Council Tax and Non-Domestic Rates).
 The exact list of health functions that may be transferred to care boards is yet to be determined, therefore the costs of
health functions are indicative at this stage.
 These figures have been projected forward using inflation (see table 1A above) plus a standard 3% increase on all years
and services to show growth in activity and any pressures above inflation e.g. pay, prescribing and energy prices. This is
net of any savings made.
33. Work will continue through the period of developing the NCS to understand demand and activity trends, as well as the exact
services to be transferred, to provide robust cost forecasts for the NCS and inform future budget and funding negotiations. Figures
given here are illustrative to show a scale of the services in scope.

Page 87

14 
Table 2: Costs of providing services that could be transferred to care boards 
As per published Financial Memorandum on 20 June 2022 
Cost Category 2019-
20
2020-
20
2021-
22
2022-
23
2023-
24
2024-
25
2025-
26
2026-
27 
£m £m £m £m £m £m £m £m
Social Care services
Adult social
care 3,517 3,659 3,844 4,205 4,600 4,833 5,077 5,334
Children’s and
families 992 1032 1084 1186 1298 1363 1432 1505
Justice social
work 137 143 150 164 180 189 198 208
Service
Strategy 52 54 57 63 68 72 76 79
Total 4,699 4,889 5,136 5,618 6,146 6,457 6,783 7,127
Community Health services
Primary care 2,690 2,799 2,941 3,217 3,518 3,696 3,884 4,080
Community
Health 3,135 3,261 3,427 3,748 4,100 4,307 4,525 4,754
Mental health
services (apart
from inpatient
and state
hospital) 
70  73  76  84  92  96  101  106
Total 5,895 6,133 6,444 7,048 7,710 8,100 8,510 8,940

Page 88

15 
Updated as per December 2023: 
Cost Category 2019-
20
2020-
21
2021-
22
2022-
23
2023-
24
2024-
25
2025-
26
2026-
27
2027-
28
2028-
29
2029-
30
2030-
31
2031-
32 
£m £m £m £m £m £m £m £m £m £m £m £m £m
Social Care services             
Adult social care £3,517 £3,644 £3,987 £4,513 £4,842 £5,018 £5,168 £5,367 £5,624 £5,909 £6,208 £6,522 £6,852
Children’s and families £992 £1,028 £1,038 £1,175 £1,261 £1,307 £1,346 £1,398 £1,465 £1,539 £1,617 £1,698 £1,784
Justice social work £137 £142 £149 £169 £181 £188 £194 £201 £211 £221 £233 £244 £257
Service Strategy £52 £54 £84 £95 £102 £105 £109 £113 £118 £124 £130 £137 £144
Total £4,699 £4,869 £5,258 £5,952 £6,387 £6,619 £6,816 £7,079 £7,418 £7,793 £8,188 £8,602 £9,037
Community Health
services             
Primary care £2,690 £2,787 £2,986 £3,380 £3,626 £3,758 £3,870 £4,019 £4,212 £4,425 £4,649 £4,884 £5,131
Community Health £3,135 £3,248 £3,479 £3,938 £4,226 £4,379 £4,509 £4,684 £4,908 £5,156 £5,417 £5,691 £5,979
Mental health services
(apart from inpatient
and
state hospital) 
£70  £73  £78  £88  £94  £98  £101  £105  £110  £115  £121  £127  £133
Total £5,895 £6,108 £6,542 £7,406 £7,947 £8,235 £8,480 £8,808 £9,230 £9,697 £10,187 £10,703 £11,244 
Reasons for Variances:
 Changes to costs of service provision that could be transferred to care boards is due to inflationary adjustments and the
inclusion of 2021/22 Local Finance Return data, previously 2019/20 (see table 1A for full details on the changes made
to the inflationary assumptions).
 We are aware much of the costs above will be driven by the costs of staff who deliver care services, however there is
no available data to disaggregate pay and non-pay cost drivers.
 As noted in the original Financial Memorandum an additional 3% growth rate has also been applied to these in addition
to inflation to cover any additional pay or demographic increases.

Page 89

16 
 The source for table 2 remains published information from the NHS Cost book and Local Government Finance Returns
with all other assumptions set out in the original Financial Memorandum remaining in place. Inflation has been applied
as per table 1A with an additional 3% growth rate in our assumption. 
Establishment of the National Care Service 
34. Section 35 of the Bill sets out that “the National Care Service” means local care boards and the Scottish Ministers exercising
their functions in relation to social services. Under the Bill as introduced a At national level there would will not be a new public
body; the Scottish Ministers’ new responsibilities for social work and social care support would will be managed and overseen by civil
servants directly accountable to Scottish Ministers, in the same way that the National Health Service is managed by the Health
Directorates of the Scottish Government. This would will include the proposed National Social Work Agency, which would will be
established as a unit within the NCS to provide national leadership and support for the social work profession. 
35. Staff currently engaged in policy development and oversight of public bodies relating to social services would will transition
to become part of the NCS structure. However the increased responsibilities will require additional staff to be recruited, with
associated costs such as premises, equipment and IT. Those increased responsibilities would include:
  providing leadership, oversight, and accountability for community health, social work and social care support,
including by providing strategic direction and planning at the national and regional levels
 creating, managing and promoting national community health and social services policies, setting national standards
and developing practice standards, models and guidance to improve access to care
 creating and overseeing a framework for ethical commissioning, including Fair Work requirements, and carry out
workforce planning
 developing and maintaining a national complaints system
 design and delivery of the integrated social care and health record and NCS digital services.
National costs – establishment phase
36. The Scottish Government is committed to establishing the NCS by the end of this Parliamentary term, i.e., in financial year
2025-26. Costs for an additional year have been provided to allow for the transition to steady operating costs. Work is ongoing to
ensure the NCS can go live in 2025-26. This includes policy development and co-design, Programme and Project Management
(PPM), recruitment costs, financial

Page 90

17 
forecasting, data and digital discovery work and workforce planning. Costs include staff and non-staff costs with a transition into running costs
once the a NCS is fully established in 2025-26. These costs cannot therefore be thought of as ‘one off’ set up costs, they are the foundation of
an NCS, with the staff and skills transferring into the running of the organisation. This allows investment into public sector staff, to upskill on
data and digital capabilities, PPM methodologies and financial qualifications. 
37. The staff set up costs shown in table 3 are based on a headcount profile currently assumed for the length of the establishment
phase, as above these staff would then in the main move to the running cost of the NCS, hence this drops to 0 in 2026-27. It is
expected a portion of the staff costs will be in the data and digital space, some of which will be shorter term contractors with specific
skills for set periods of time. This causes a spike in the latter part of 2023-24 based on current phasing of programmes. 
38. Current assumptions of staff headcount and costs have been based on actual staff numbers in 2022-23 and 2023-24 with
management and policy estimates of resource need for the various elements of the programme in the longer term. As the scope,
scale and timeline for the NCS is still to be fully developed through co-design and evidence-based options appraisal, this headcount
profile is likely to change, potentially significantly, as more detail is known. 
Table 3: NCS National establishment phase headcount and staff costs 
As per published Financial Memorandum on 20 June 2022: 
2022-23 2023-24 2024-25 2025-26 2026-27
Headcount 200 - 300 440 - 660 440 - 660 60 - 90 0
Staff costs (£m) 18 - 27 47 - 71 48 - 72 5 - 7 0 
Updated as per December 2023: 
2022-23 2023-24 2024-25 2025-26 2026-27
Headcount 183 204 - 249 222 – 271 240 – 293 0
Staff costs (£m) 10 10 - 12 11 – 14 7 – 8 0
Variance (£m) -8 - -17 -37 – -59 -37 - -58 2 - 1 0
* The staff costs in 2025-26 represents 6 months of costs as during 2025-26 it is anticipated the NCS will go live. As such staff will migrate to
the running phase as set out in table 6

Page 91

18 
Underlying Calculation Assumptions:
The estimate of staffing is taken from current staffing figures and costs, alongside expected requirements for new posts, tied to delivery timelines.
The updated figures anticipate a gradual increase in staff as the Programme approaches the launch date in 2025-26, but this is smaller than
previously estimated.
The costs in 2025-26 represent partial year costs as staff migrate across to working in the running of NCS National. The running phase 2025-26
costs of those staff that move are reflected in table 6 below. 
Reasons for Variances:
 Reductions in headcount numbers and therefore staff costs are due to a more fully developed understanding of the
requirements since the Bill was introduced, as well as the rephasing and reprioritisation of workstreams to ensure the
most effective use of resources. It is anticipated that the programme will continue to run with a more streamlined staffing
base compared with the original Financial Memorandum through the development and subsequent operation of the NCS
as a result of this. The programme will increase the skills of existing staff and limit the number of external contractors
further reducing the incurred and anticipated staffing cost.
 Headcount drops to 0 in 2026-27 as staff are assumed to transfer to the NCS National running costs.
 The ratio of staff costs to headcount has also reduced. This is partly as there is a lower ratio of contractor staff, who
carry a higher wage, compared to previously forecast costs, coupled with a more robust ongoing staffing forecast based
on actual staff numbers in 2022-23 and 2023-24. For future years there remains an element of contingency for areas that
are still to be developed as part of the codesign phase and where additional staff have been included.
39. Non-staff costs relate to areas such as IT systems, consultancy costs, co-design and engagement work, external grants to
partner organisations and operational expenses and training and premises costs. This is estimated in table 4. 
Table 4: NCS National establishment phase non-staff costs 
As per published Financial Memorandum on 20 June 2022: 
2022-23 2023-24 2024-25 2025-26 2026-27
£m £m £m £m £m      
Systems and IT 0 0 - 1 9 - 13 2 - 4 0
Training and other staff costs 0 2 2 0 0

Page 92

19 
Premises costs 0 1 2 - 4 2 0
Third party advice (legal -
consulting) 6 - 9 10 - 14 10 - 14 2 0
Total 6 - 9 13 - 19 22 - 34 6 - 8 0 
Updated as per December 2023: 
2022-23 2023-24 2024-25 2025-26 2026-27
£m £m £m £m £m
Systems & IT 0 0 0 0 - 1 0 - 1
Staff Related 0 0 0 0 0
Engagement 1 0 0 0 - 1 0
Grants 0 0 0 0 0
Co-Design 0 0 - 1 0 - 1 1 0
Research & External Advice 2 0 1 1 0
Total 3 1 2 - 3 2 - 4 1      
Variance -3 - -6 -12 - -18 -20 - -31 -4 - -4 1 – 1 
Note – The costs above show a significant number of £0s. While we expect some costs, these fall below the £500k threshold to be rounded up.
The average costs for the individual lines are between £300k - £600k per annum with the exception of staff related which is on average £120k. 
Underlying Calculation Assumptions:
 The costs within the setup phase have been based on the current breakdown of expenditure incurred within the NCS
programme as well as a programme wide assessment of the anticipated requirements aligned to planned delivery
timescales.
 Costs have been inflated forward using the revised inflationary rates, see table 1A for full details.
 Cost range – The lower limit is based on reducing costs from 2023-24 onwards to 80% to reflect any underspend against
budget / anticipated spend values. The upper limit is based on increasing the costs to 120% to reflect any unforeseen
expenditure or cost over runs in the project work

Page 93

20 
Reasons for Variances:
 Inflation assumptions have changed, see table 1A for full details.
 2022-23 costs are based on actuals as per the end of financial year. These are lower than the original Financial
Memorandum as a result of government wide savings exercises following the Emergency Budget Review in November
2022.
 2023-24 through to 2025-26 costs are significantly lower than previously estimated due to a change in nature of the
programme and a more developed understanding of programme requirements. The internal staff skillset will be utilised
in favour of externally contracted services. NCS National is assumed to share IT and back office services with SG and
therefore Systems and IT costs have been reduced along with premises as NCS National will utilise existing Scottish
Government sites.
 The spend categories have been amended to be more reflective of the programme reporting framework and better
highlight how money has been and is planned to be spent. 
National ongoing running costs
40. The Bill as introduced provides for the Scottish Ministers to become responsible for social work and social care support for
adults, for children, and relating to the justice system. As set out in the policy memorandum, further work is required to consider the
risks and opportunities, costs and benefits of the transfer of services for children and justice, and the transfer may be phased over
a longer period. However, since no decisions have yet been taken on such phasing, the figures in tables 5 and 6 assume that the
NCS would will take on the full range of services from the start. As the Scottish Ministers already have responsibility for primary
care and community health, and teams in the Scottish Government managing those areas, it is assumed there will be no change
in costs relating to that work 
41. Running costs for the NCS have been estimated based on this full range of functions. This includes staff costs across various
different teams, the majority being the existing staff from the establishment phase. Total headcount is expected to grow to the region
of 500 – 700 people, though not to the previous estimate of 500 – 700 people, which is in line with other large areas within
government, such as Social Security as the programme resource requirement has been reviewed and streamlined. These are not
all additional posts compared to current headcount profile, and as per the headcount profile for the establishment phase, the staff
base for the NCS will be built over the next 3-4 2-3 years. 
42. The estimated set up and running costs have been established by assessment of current programme progress and

Page 94

20 
requirements alongside the anticipated expansion as the programme moves from set up to running and what that will involve and
the NCS National requirements. comparison to the existing costs of national management of the National Health Service and other
large scale transformation programmes in the public sector, such as the creation of Social Security Scotland.

Page 95

21 
43. The range of functions has been considered that would need to be developed to support the NCS – quality improvement,
performance and delivery, workforce planning, policy development, finance (for example) and how these might be delivered most
efficiently. The costs of national management of the NHS have been referenced while considering the drive for public sector reform
and increased efficiency. 
44. Non staff costs are set out in table 5 below. As above, these are high level ranges based on current estimates, and further
work is required to refine these estimates. 
Table 5: NCS National running costs - non-staff costs 
As per published Financial Memorandum on 20 June 2022 
2022/23 2023/24 2024/25 2025/26 2026/27
£m £m £m £m £m      
Systems and IT 0 0 2 11-16 10-16
Training and other staff costs 0 0 0 3-5 3-5
Premises costs 0 0 0 5-7 5-7
Third part advice (legal / consulting) 0 0 0 4-6 4-6
Total 0 0 2 23-34 22-34
Updated as per December 2023: 
2022-23 2023-24 2024-25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
£m £m £m £m £m £m £m £m £m £m
Systems & IT 0 0 0 0 - 1 0 - 1 0 - 1 0 - 1 0 - 1 0 - 1 0 - 1
Staff Related 0 0 0 0 0 0 0 0 0 0
Engagement 0 0 0 1 1 1 1 1 1 1
Grants 0 0 0 1 - 2 1 - 2 1 – 2 1 – 2 1 – 2 1 – 2 1 - 2
Co-Design 0 0 0 0 - 1 0 - 1 0 - 1 1 1 1 1
Research & External
Advice 0 0 0 0 0 0 0 0 0 0
Total 0 0 0 3 - 5 3 - 5 3 – 5 3 – 5 3 – 5 3 – 5 3 - 5

Page 96

21 
Variance 0 0 2 -20 - -29 -19 - -29 No figures for comparison

Page 97

22 
Note – As above the £0 notation has been used to signify costs below the £500k threshold but above £0. There are no costs incurred prior to
2025-26 as these all sit in the set up phase. Staff related costs average £120k while Research & External Advice average £320k per annum 
Underlying calculation assumptions:
The costs identified within the running phase of the NCS have been reassessed. It is assumed that the NCS National, under the Bill as introduced
would exist within Core Scottish Government and as such will be able to utilise existing premises, IT systems and legal services. The costs of
running a complaints system have been evaluated based on the desired approach of a web hosted service. There is an expectation that the grant
funding to partner organisations will increase to enable them to deliver key services while co-design will become an ingrained part of the ongoing
improvement of the NCS. 
Cost ranges – As with the set up phase the costs are reduced to a lower limit of 80% to reflect the inherent uncertainty in requirements with an
upper limit of 120% 
Reasons for Variances:
 Inflation assumptions have changed, see table 1A for full details.
 Certain non-staff elements have been substantially reduced due to a clearer understanding of how the NCS will function
within core Scottish Government. The assumed costs around systems, e.g new payroll and HR systems have been
removed and these contributed a large cost to the overall position. The digital costs associated with running a complaints
system, based on current design analysis, are significantly reduced as well.
 It is anticipated existing premises will be used thereby removing the need for another large additional cost.
 The figure set aside for consulting and legal is significantly reduced as existing Scottish Government legal services will
be utilised while external procurement of services has been reassessed with a focus on more in house provision to better
manage the use of available resources on a recurrent basis and deliver value for money.
 Non-Staff costs have been re-categorised to better align with programme developments and to provide more clarity and
relevance in the relation to non-staff spend against the revised forecasting categories.
45. All the costs of the national management of the NCS will fall to the Scottish Administration.

Page 98

23 
National Social Work Agency
46. The Scottish Government is committed to establishing a National Social Work Agency, to support and provide national
leadership to the social work profession. This would be part of the NCS national management. It is currently estimated that this will
contribute costs of £8-121- 2 million in additional staffing annually, which are included in the figures in table 6. The NSWA will
support and invest in the social work profession, enabling social workers to work with people to transform their lives and implement
rights-based practice as part of the overall objectives on the NCS. 
Table 6: Costs for NCS National (Costs on the Scottish Administration) 
As per published Financial Memorandum on 20 June 2022 
Cost Category 2022-23 2023-24 2024-25 2025-26 2026-27 
£m £m £m £m £m
Establishment phase
Staff costs 18-27 47-71 48-72 5-7 0
Non-staff costs 6-9 13-19 22-34 6-8 0
Totals 24-36 60-90 70-106 10-16 0
Ongoing running costs
Staff costs 0 0 0 59-88 60-91
Non staff costs 0 0 2 23-34 22-34
Totals 0 0 2 82 - 122 83 - 124      
Overall Total 24-36 60-90 72-108 92-138 83-124

Page 99

24 
Updated as per December 2023 
Cost
Category 2022-23 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 
£m £m £m £m £m £m £m £m £m £m
Establishment          
Staff 10 10 - 12 11 – 14 7 – 8 0 0 0 0 0 0
Non-Staff 3 1 2 - 3 2 - 4 1 0 0 0 0 0
Total
Establishment 13 11 - 13 13 – 17 9 – 12 1 0 0 0 0 0
Running          
Staff 0 0 0 7 – 10 14 – 20 14 – 21 14 – 21 15 – 22 15 – 23 15 – 23
Non-Staff 0 0 0 3 - 5 3 - 5 3 – 5 3 – 5 3 – 5 3 – 5 3 - 5
Total
Running
0 0 0 10 – 15 17 – 25 17 – 26 17 – 26 18 – 27 18 – 28 18 -28           
Total NCS
National 13 11 - 13 13 – 17 19 – 27 18 – 26 17 – 26 17 – 26 18 – 27 18 – 28 18 – 28 
Variance -11 – -23 -49 - -77 -59 – -91 -73 - -111 -65 – -98 No figures for comparison 
Underlying calculation assumptions:
The assumptions outlined below tables 4 and 5 apply to this summary table. The one additional item is the basis for calculating the costs of the
running phase staffing. Currently it is anticipated that the majority of staff will migrate from current Scottish Government functions into NCS
National. There will of course be those posts that are no longer required and they have been removed, as well as the creation of specific functions
that will be expected to go live with the National launch, such as the running of a complaints system. The staff associated with these functions
have therefore been included. 
Reasons for Variances:
 Inflation assumptions have changed, see table 1A for full details

Page 100

25 
 The most significant reduction evidenced above is in relation to the ongoing staffing requirement and cost. Previously
the estimate had been based on assessing the current health directorate spend and attributing a similar cost profile.
However, following development in the understanding of the needs of the NCS and assessing opportunities to utilise
existing staff and the changing of existing roles, the staff numbers have been streamlined to ensure the NCS delivers
value for money yet is flexible enough to meet the challenges faced. The reduction in assumed premium contractor costs
in favour of upskilling current staff to provide in house provision is also a contributing factor.
 The previous assessment of reductions in tables 3,4 and 5 apply to this summary as well.
 See Table 3 for further breakdown of variances for establishment phase staff costs, and Table 4 for establishment phase
non-staff costs.
 For breakdown of ongoing running non-staff costs variances please see Table 5. 
Care Boards 
47. The Bill gives the Scottish Ministers powers to establish care boards, which are expected to carry out the delivery functions
of the NCS and replace the current Integrated Joint Boards (creating an additional body in Highland). Care boards will be
accountable to the Scottish Ministers and directly funded by them, and they will employ their own staff. Summary costs for these
boards are set out in table 7. 
Table 7: Summary costs of establishment and running costs of care boards 
As per published Financial Memorandum 20 June 2022 
Sector 2022-23 2023-24 2024-25 2025-26 2026-27 
£m £m £m £m £m
Scottish
Administration 0 4 - 6 12 - 18 0 0
Care Boards 0 0 0 132 - 326 142-376

Page 101

26 
Updated as per December 2023: 
Sector 2022-23 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 
£m £m £m £m £m £m £m £m £m £m
Scottish
Administration 0 0 0 0 0 7 - 30 0 0 0 0
Care Boards 0 0 0 0 0 0 - 0 33 - 247 70 - 309 106 - 371 109 - 433
Due to the significant change in phasing the variance table has been excluded. 
Underlying Assumptions:
These will be set out under the detail tables 8A and 8B as will the basis for the ranges. 
It is assumed Care Boards will go live in 2028-29. The costs shown in 2027-28 are the preparatory costs to enable launch. The range is based
on either a full roll out of Care Boards at the upper end or a phased introduction at the lower end. 
Reasons for Variances:
 Inflation assumptions have changed, see table 1A for full details
 Rephasing of the Care Board inception date to 2028/29
 Revision of estimates for running costs and premises/IT (further detail beneath tables 8A and 8B). 
48. Section 4 gives the Scottish Ministers power to determine the number of local care boards and the areas they will cover.
Decisions on the number of care boards will require rigorous assessment to ensure value for money, while also considering the
best approach to ensure services are designed to meet local needs and circumstances. While the number of local care boards has
yet to be decided, the figures in table 7 assume at the top end of the range there will be 3231, one for each Integration Joint Board. 
49. The Scottish Ministers will also have powers to create special care boards, which could provide central functions in a similar
way to the Special Health Boards. Any decisions to create such special care boards would take account of the costs of setting up
a new board balanced against the benefits and any savings to be gained from providing central services. The cost of creating any
special boards, should they be formed, will be calculated based on the function and size of the board. Of the current eight Special
Health Boards, in 2019/202022-23 their resource allocation share budgets ranged from £18 30 million - £425 492 million.

Page 102

27 
50. Set up costs such as recruiting board members and acquiring premises prior to establishment of the boards will fall to the
Scottish Administration, while ongoing running costs will be allocated to the boards themselves as public bodies. The figures in table
7 include assumed efficiencies from incorporating support services that already exist across the health boards and local authorities,
and from the abolition of Integration Joint Boards, which is set against the additional costs of the new boards. The range of costs
which have been offset as assumed to already exist are between £25 27 - £40 45 million per year, inflated to 2028-29 costs when
Care Boards are due to go live. 
51. The timing and phasing of establishing care boards and transferring functions to them will be subject to further discussion
through the co-design process and the production of business cases. These will need to consider local tests of change,
implementation plans tailored to individual areas and a delivery readiness assessment to ensure no detriment to services while
change takes place. The top end of the range of costs in table 7 is based on all care boards having their first year of operation in
2025-262028-29, and assuming that all social workers and care workers will transfer in a phased approach to the NCS. The lower
end reflects the possibility that decisions may be taken to start the transfer in a small number of areas, building up over time, to
allow appropriate planning, consultation and impact assessment with no staff transferring across. 
52. The core management costs of care boards social care staff cost is shown in table 8A while the management costs of care
boards are shown in table 8B and will include the following. As noted above, these are all high-level estimates which will be refined
as proposals are further developed through the co-design and options appraisal process.
 Governance and Executive Team – the Bill gives the Scottish Ministers powers to determine in secondary legislation
how many members each care board must have and how they provide representation for people with experience of
accessing support, workforce and service providers, carers, and partner organisations.
 Premises and digital set up – high level assumptions are included on costs for digital and premises set up, assuming staff
would need digital devices, software licences and access to systems, existing and potentially new. As Integration Joint
Boards currently use premises from either the local authority or the health board, it is assumed there will be some need for
additional office space, although the current premises will then be freed up for alternative use. Further work will be
required to refine this, as the number and size of care boards becomes clearer.
 Support functions (renamed to Back Office Care Board Staff) – it is assumed that a number of support functions will be
required to assist care boards, such as finance, HR, analytics, business support etc. The Scottish Government is
considering the opportunity for shared services and what functions the National NCS structure could provide and which
need to be held by care boards at the local level.
 Communications and administration costs (renamed to Running Costs). These are the general running costs of the board.

Page 103

27 
This covers aspects such as, audit fees, legal advice, general administration and communications, supplies and services
and staff related costs.

Page 104

28 
Provision has also been made in 2027-28 for the inception costs in preparing the board to launch, such as setting up the IT
infrastructure and the recruitment of new board members.
 Pay and terms and conditions – this currently assumes a phased approach to the movement of local authority staff into
care boards. As this will depend on future discussions between the Scottish Government and local authorities, costs are
estimated here to show the quantum of the potential impact. Costs rise from 2025/26 to 2026/27 2028-29 to 2031-32 at
the top end of the estimate as it is assumed a varying percentage of staff would transfer each year. The lower end of the
estimate assumes that no staff would transfer. These costs have been baselined against current pay and terms and
conditions costs as far as is possible with existing data, compared to the future direction of travel of public sector terms
and conditions. Much of the overall costs of care boards reported here are therefore for front line delivery services. 
Staff transfer
53. The Scottish Government has agreed that local government continue in its role as a direct provider of social care services.
This includes continuing to hold and invest in assets and employ staff directly. Under the Bill as introduced, decisions on the role
each local authority wants to play, and associated staffing decisions, will be taken locally once the structure and governance of
care boards and their localities have been decided. However, an ability to transfer staff, and assets, is necessary to support the
transfer of accountability that may at some point require care boards to take on the ability to deliver services in-house. 
54. Table 8A currently assumes a phased approach in which all local authority staff would eventually transfer into care boards.
However, it is not a foregone conclusion that this will be the case, and it will depend on future, and ongoing, discussions between
care boards and local authorities. The recently adopted Shared Accountability Agreement sets out that staff and assets will remain
with the local Authority however, as noted the intention of this document is to establish the potential cost were staff to move as per
the provisions in the Bill. Costs are estimated here to show the maximum potential impact. 
55. Approximately 75,000 staff are currently employed by local authorities in social work and social care support services,
including children’s services and justice social work. If staff were to transfer to the NCS, pay rates and terms and conditions would
need to be rationalised within the single service. While it has never been expected that all 75,000 staff will transfer, even in the long
term, this represents the maximum limit for estimating costs. Estimating the cost of staff transfers is difficult as all local authorities
may have different pay rates and terms and conditions for their staff, The figures for pay and terms and conditions set out in table
8A have been baselined against current assumptions on Fair Work. “Pay” represents the additional cost of increased basic pay
rates, while “terms and conditions” represents the cost of other issues, for example increased sick pay or covering increased holiday
entitlements and pension contributions. Further assessment and engagement with

Page 105

29 
local authorities and with the workforce would be required, if the Bill were to be passed as introduced, to determine how many staff were likely
to transfer and on what conditions. 
56. Costs in table 8A rise from 2028-29 to 2031-32 at the top end of the estimate as it is assumed a varying percentage of staff
would transfer each year. The lower end of the estimate assumes that no staff would transfer. Much of the overall costs of care boards
reported here are therefore for front line delivery services. 
57. It is expected professional expert support will be required to identify costs further in a number of areas including VAT as well
as assets and pensions were the transfer of staff and assets to occur.
 For pensions, a number of options for the provision and ongoing management of pensions have been initially considered
for staff who may be affected by any changes. More work and engagement will be required to determine the most
suitable and affordable design, as decisions are made on the scope of the NCS. A standard pension contribution rate of
20.9% is currently assumed in the care board costs, based on expected future direction of travel of public sector terms
and conditions.
 Assets directly linked to care delivery will also have to be considered, as to whether ownership or leases will be
transferred to new care boards. Data does not currently exist in one place on market value of social care properties,
backlog maintenance or other associated costs. This will be further investigated. No capital costs of any asset transfer,
or revenue costs of any asset maintenance, are assumed in table 7 or 8 .
VAT
58. Currently Integration Joint Boards are established in a similar way to a local authority body, and can therefore reclaim VAT
on services. The Scottish Government are committed to securing a VAT neutral status for Care Boards to ensure maximal funding
is directed to support front line services. As such, work is underway to understand and mitigate any VAT implications including
engagement with HMT and HMRC to discuss options for obtaining this neutral status. 
59. Prior to the agreement of a broadly neutral VAT accounting arrangement with HMRC in 2014, the VAT cost impact associated
with the establishment of Integrated Authorities under the Public Bodies (Joint Working) (Scotland) Act 2014 was estimated to be
around £32 million. After taking account of inflation and making provision for an increase for a larger volume of contracts of between
2% and 3% per annum, the equivalent VAT cost for providing the same services in 2025/26 is estimated to be between £54 million
to £60 million. Without this increase in contract volume the cost would be £42 million.

Page 106

30 
60. Note VAT costs are not assumed in table 7 or 8 at present as we are working towards the assumption that a VAT neutral
status will be agreed. 
61. After taking into account the re-phasing of the NCS, the NCS Local Go Live date is expected to be 2028/29. The VAT cost
estimate for this year, if a VAT neutral status is not achieved and after including further inflation and an assumed annual increase
in contract volumes of 2- 3% (lower & upper limits), is £59 million to £69 million. This would be an annual recurring cost. 
Transfer of functions
Where local authorities deliver social care services directly, that delivery may in future transfer to care boards, together with the staff who
provide those services. This could involve up to 75,000 employees across social work and social care. Costing of this is difficult as all local
authorities may have different pay rates and terms and conditions for their staff, which will need to be rationalised within a single service. The
figures for pay and terms and conditions set out in table 8 have been baselined against current assumptions on Fair Work. Decisions will require
further assessment and engagement with local authorities and with the workforce, to determine how many staff are likely to transfer and on what
conditions. “Pay” represents the additional cost of increased basic pay rates, while “terms and conditions” represents the cost of other issues, for
example increased sick pay or covering increased holiday entitlements.

Page 107

31 
Table 8: Additional costs for Care Boards 
As per published Financial Memorandum 20 June 2022: 
Costs to Scottish Administration Costs to care boards
Cost Category 2022-23 2023-24 2024-25 2025-26 2026-27 
£m £m £m £m £m
Governance and
Board costs 0 0 0 22-33 23-34
Premises and
digital 0 2 - 4 10 - 15 63 - 94 69-103
Support services 0 0 0 45 - 67 46 - 69
Administration and
communications 0 1-2 2 2-4 4-6
Pay 0 0 0 0 - 43 0 - 43
Terms and
Conditions 0 0 0 0-84 0-120
Totals 0 4-6 12-18 132- 326 142-376 
Updated as per December 2023: 
Table 8A: Staff Transfer Costs 
Scottish Administration Care Boards
2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
Pay Parity 0 - 0 0 - 0 0 - 0 0 - 0 0 - 0 0 - 0 0 - 15 0 - 23 0 - 25 0 - 32
Terms and
conditions 0 - 0 0 - 0 0 - 0 0 - 0 0 - 0 0 - 0 0 - 81 0 - 131 0 - 187 0 - 238
Total 0 - 0 0 - 0 0 - 0 0 - 0 0 - 0 0 - 0 0 - 96 0 - 154 0 - 212 0 - 270

Page 108

32 
Table 8B: Care Board Running Costs 
Scottish Administration Care Boards
2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
Back Office (Care
Board Staff) 0 0 0 0 0 2 - 7 19 - 90 42 - 92 63 - 95 65 - 98
Premises and IT 0 0 0 0 0 0 - 1 1 - 6 3 - 6 4 - 6 4 - 6
Running Costs 0 0 0 0 0 5 - 22 11 - 53 24 - 54 36 - 55 37 - 56
Governance and
Board costs 0 0 0 0 0 0 1 - 3 2 - 3 2 - 3 2 - 4
Total 0 0 0 0 0 7 - 30 32 - 152 71 - 155 105 - 159 108 - 164
*Note – slight variance between Table 7 and the sum of tables 8A and 8B is due to rounding 
Underlying Calculation Assumptions:
The Scottish Social Services Council provided a public sector specific breakdown of their workforce data. This formed the basis of the
calculations as it allowed the splitting up of care staff, auxiliaries and managers. The cost of each group was calculated by taking their Whole
Time Equivalent against their hourly rate. Hourly rates were based on National Living Wage commitments for care staff, Real Living Wage for
auxiliaries and Agenda for Change manager bands for management staff. Varying levels of on costs were applied to determine the potential
additional cost. 
For Care Boards it is assumed that they will now go live in 2028/29 and that there would be 31 to match up with the current Integration Joint
Boards (IJBs). Each board is assumed to require staff to run the various functions allowing it to operate effectively such as admin, finance,
procurement etc. There is also the requirement to have an executive board. 
The approach to Care Board costing has changed from the Financial Memorandum in June 2022. The specific elements are detailed below but
broadly, given the anticipated size and nature of the Care Boards it was felt that an assessment of Non Departmental Public Body (NDPB) costs
would provide a reasonable barometer for the likely costs attributable to running a Care Board. 
Cost Range – The lower range is based on all staff remaining within the Local Authority and also a phased approach to the establishment of
Care Boards, building up from 2028-29 to full running by 2030-31. The upper range is based on a full staff transfer with all Care Boards going

Page 109

32 
live in 2028-29.

Page 110

33 
Reasons for Variances:
 Inflation assumptions have changed, see table 1A for full details
 Categories have been re-named to better reflect our understanding of how future costs are expected to be incurred.
 Staff transfer costs have been split out in table 8A with table 8B showing all other running costs.
 Premises cost estimates have been revised with the approach now being the use of current commercial rental rates and
the approximate space size requirements of the anticipated staffing numbers. Edinburgh prices were used as a proxy
given they are generally higher than elsewhere in the country, so as not to underestimate the potential liability. The prior
estimate had built in a more significant contingency factor given the uncertainty. The reduction of this contingency due
to the new costing approach has reduced the premises cost. The new estimate for Care Board rental is in more closely
aligned with some of the (NDPB) costs which has given assurance that these are more robust.
 The approach to IT costs has also changed from the previous iteration. The basis now is the evaluation of annual account
data for multiple NDPB with a mid-range figure becoming the estimate applicable, scaled up by the number of Care
Boards. Previously, the approach had also factored in large contingency costs for the potential transition and corporate
costs given the uncertainty, though this made the cost vastly higher than the comparable figures assessed and so the
revised approach felt more closely aligned to the likely outcome
 Running costs have also been established from assessment of NDPB annual accounts figures. The common elements
for the various accounts were taken and then the associated costs were adjusted to reflect the anticipated size and
operation of Care Boards. This again brought the overall cost more in line with similar bodies. 
Costs to local authorities and health boards 
62. The If functions were to be transferred transfer of functions from local authorities to the NCS, in line with the Bill as introduced,
in particular may this could have additional financial implications These may include including, for example, costs for the transition
process, but
t. There may also be potential savings on central services such as finance, digital systems and premises, if a significant number of staff move
to the NCS, but alternatively local authorities could experience a loss of economies of scale. These costs and savings will depend on what
services are to be included in the NCS, when the transfer is to take place and how the transition process will be staged. If this approach were to
be taken, the Scottish Government would carry out thorough options appraisal, working with COSLA, to identify these financial implications at
the appropriate time and inform the approach taken. Further information would be provided to the Scottish Parliament when the relevant
secondary legislation is brought forward.

Page 111

34 
63. The financial implications for health boards are expected to be less significant, because of the expectation that they will
continue to deliver services commissioned by the NCS. As with local authorities, those implications will be considered when more
detail of the arrangements is known. 
Costs on other bodies, businesses or individuals 
64. It is not anticipated that the establishment of the NCS and care boards, and the transfer of functions to those bodies, would
have any financial implications for any other public bodies, businesses or third sector organisations, or for individuals. 
65. If social care functions are transferred from local authorities to care boards, it is assumed that in the first instance, all
contracts and arrangements with external organisations for the provision of social care support services will also transfer. Over
time, changes to policies on ethical procurement and Fair Work may lead to changes in the requirements on potential providers.
While the Bill will enable the Scottish Ministers to promote such policies more effectively, the detail is not set out in the Bill and will
be subject to separate financial and regulatory impact assessment. 
HEALTH AND SOCIAL CARE INFORMATION 
66. Part 2 of the Bill gives the Scottish Ministers the power to set up a statutory scheme through Regulations to permit data
sharing for the efficient and effective provision of services by, or on behalf of, the NCS and NHS, and to produce information
standards to ensure information is processed in a consistent way. This will enable better sharing of information across the health
and social care sector, to the benefit of people and professionals. Crucially, it will also support the creation of the nationally-
consistent, integrated and accessible electronic social care and health record. The creation of these provisions will have no
immediate financial implications for the NCS, NHS or Scottish Government. The NCS consultation noted that improvements to data
and digital would require additional investment in data and digital systems locally and nationally. This is expected to cover
infrastructure, staffing, training and development costs. The Scottish Government will work closely with people who access support,
carers, providers and front line staff to develop the social care and health record. 
67. The development of the electronic social care and health record does not arise from the NCS Bill, and is therefore not
covered in this financial memorandum. The integrated record requires a full process of discovery and design, which includes co-
design with all stakeholders. Work has been initiated on discovery and alpha phases of the integrated record to develop detailed
requirements which will inform the development work ahead. At this early stage it is not possible to provide an exact position on
the total cost of investment or how the costs will be phased. As part of this work The Scottish Government has begun the drafting
of the Strategic Outline Case for the integrated record, which includes an options appraisal and outline of indicative costs for the

Page 112

34 
integrated record. Through this co-design process and wider work to develop

Page 113

35 
the evidence base it will be possible to robustly estimate costs. Supporting business cases and appropriate assurance will be created while the
process of seeking funding and scope decisions continue.here significant investment will be required. The final costs will depend on user
engagement to finalise the ultimate scope and specification, and the outcomes of any future competitive tender processes to deliver those
requirements to ensure optimal public value. Scope and specification will be informed by the co-design approach being taken to the NCS. 
68. There will also be work to develop digital services to underpin and enable the NCS as well as investment in people to make
sure they have the right skills to use digital platforms and analyse data. Again, more investigation and co-design is required to define
this. All options will be subject to rigorous assessment to ensure value for money and affordability. 
REFORMS CONNECTED TO DELIVERY AND REGULATION OF CARE 
Right to Breaks from Caring NOTE – this section to be updated once new carers population figures are published on 5 December 
69. Section 38 of the Bill makes changes to the Carers (Scotland) Act 2016 (“the Carers Act”) to establish a right to personalised
short breaks support for carers who have an identified need for that support, through an adult carer support plan (ACSP) or young
carer statement (YCS). These changes will adjust and extend the duties of Local Authorities and Integration Authorities, which are
expected to pass to care boards when the NCS is established. These duties will lead to additional costs in providing breaks from
caring. 
70. The Scottish Government also intends to maintain a national short breaks fund, using existing powers7, to enable easy-access
support for people in less intensive caring roles. This will build on existing non-statutory voluntary sector short breaks funding.
These schemes provide micro grants schemes for unpaid carers to help them take short breaks that meet their needs. Individual
grants can be used flexibly, e.g. for a weekend away, entertainment subscription or sporting or hobby equipment. Time To Live
grants are delivered locally, usually by local carer centres. Take a Break Scotland grants for carers of disabled children and young
people and their families are delivered nationally by the Family Fund. The Scottish Government is committed to increasing this
funding to provide easy access to breaks for carers without the need for a support plan or statement. While this fund does not require
new legislation, it will have an impact on the costs of providing the personalised support required by the provisions of the Bill,
depending on the balance of whether carers access personalised support or easy access breaks. 
71. The cost of these measures has been estimated using data on the following:
 Number of carers by intensity of caring8

Page 114

35 
7 Social Work (Scotland) Act 1968, section 10
8 Intensity of caring based on the bands of number of hours per week, as per table 9.

Page 115

36 
 Balance of replacement care between residential and home based
 Unit costs for replacement care, carer breaks and easy access support
 Cost and Whole Time Equivalent for young carer support workers. 
72. There are number of areas of uncertainty, for which information is incomplete or missing, where assumptions have had to
be made, in particular:
 the number of carers who will seek to exercise their right to breaks
 the average amount of replacement care required for personalised support
 the balance of breaks between personalised support and easy access support
 current levels of local authority and Integration Authority expenditure on breaks and replacement care, for which local
authority systems do not generally differentiate short breaks support from other services, and
 the rate at which demand and available provision will build over time.
73. The full set of assumptions for all groups is extensive, the following example is provided for illustration: For adult carers
providing over 50 hours of care per week, it is assumed that 50% of those with an ACSP will take up replacement care, and that
this will average 4 weeks per carer per year, of which 65% is assumed to be residential care and the remainder intensive homecare
at 22 hours per week. Additionally, it is assumed that 60% of this group will take up a carer break (additional support to help them
recharge during their time away from caring), averaging 3 breaks per year. These figures can then be combined with the numbers
of carers set out in table 10 and the costs of breaks9 identified above and netted against estimates of existing expenditure to estimate
the total net cost of implementing breaks for carers. 
74. Table 9 shows how a selection of the assumptions vary for different intensity groups.

Page 116

36 
9 Care home respite at weighted average of cost of £981 per week and homecare at £21 per hour. Carer breaks costed at £300 per break. All at 2022/23
prices.

Page 117

37 
Table 9: Assumptions used in calculating costs of breaks from caring 
<20
hours a
week
20 - 34
hours a
week
35 - 49
hours a
week
50 or
more
hours
Proportion of adult carers with ACSP that receive
replacement care (%) 5% 10% 20% 50%
Number of weeks replacement care per carer (Adult
carers) 1 2 3 4
Proportion of adult carers with ACSP that receive carer
break (%) 10% 20% 40% 60%
Number of carer breaks per adult carer 1.0 2.0 2.0 3.0
Proportion of young carers with YCS with activity
enabling break 100% 100% 100% 100%
Proportion of young carers with YCS receiving
replacement care 0% 100% 100% 100%
Easy access payment (per carer)10 £300.0 £330
Uptake of easy access support by adult carers who do
not receive personalised support 10% 40% 40% 40%
Uptake of easy access support by young carers 10% 40% 40% 40%
* The only variances since the original Finance Memo are an update to the easy access payment (per carer) from £300 to £330 and to include
replacement care for young carers caring for 20 + hours per week. 
75. The calculations produce estimates for a future steady state of support in which the proportion of carers with an ACSP and
or a YCS has reached the same proportions as those assumed in the Financial Memorandum for the Carers (Scotland) Bill11,
specifically 34% of adult carers and 64% of young carers (see table 10, rows 2 and 5 for steady state number of carers with ACSP
and YCS respectively). The estimates for personalised support are based on the number of carers with plans and statements, and
those for easy access support are based on the balance of carers who do not have plans/statements. 
10 Estimate based on feedback from providers of Time to Live and Take a Break Scotland grants

Page 118

37 
11  https://archive2021.parliament.scot/S4_Bills/Carers%20(Scotland)%20Bill/b61s4-introd-en.pdf

Page 119

38 
76. Table 10 shows the number of carers (updated using the latest published carer population data12) by intensity of caring and
our estimate for how many will have ACSP/YCS in the steady state. The distributions assume that 80% of carers in the 50+ hours
per week band will have plans/statements, with reducing proportions for less intensive bands and with the balance in the <20 hours
per week band to give total proportions of 34% and 64%. 
As per December 2023: 
12 Scotland’s Carers update release Scotland's Carers - gov.scot (www.gov.scot)

Page 120

39 
Table 10: Number of carers and proportion expected to have ACSP / YCS in steady state 
As per published Financial Memorandum 20 June 2022: 
<20
hours
per week
20  -  34
hours
per week
35  -  49
hours
per week
50+
hours
per week
Total
Number of adult carers 624,864 59,280 29,640 125,215 839,000
Number of carers with ACSP 143,592 23,712 17,784 100,172 285,260
Proportion of carers with ASCP 23% 40% 60% 80% 34%
Number of young carers 27,900 900 300 900 30,000
Number of carers with YCS 17,670 585 225 720 19,200
Proportion of carers with YCS 63% 65% 75% 80% 64%

Page 121

40 
Updated as per December 2023: 
<20
hours
per
week
20 - 34
hours
per
week 
35 - 49
hours
per week
50+
hours
per
week  Total
Number of adult carers 487,507 58,210 36,381 123,696 705,793
Number of carers with ACSP 95,901 23,284 21,829 98,957 239,970
Proportion of carers with ASCP 20% 40% 60% 80% 34%
Number of young carers 22,676 1,043 0 1,043 24,761
Number of carers with YCS 14,335 678 0 834 15,847
Proportion of carers with YCS 63% 65% N/A 80% 64% 
77. Based on Carers Census13 data on the numbers of such plans and statements, the Scottish Government estimates that it
will take approximately ten years to reach the steady state number of carers with plans and statements, increasing on average by
approximately 27,000 22,000 plans and 1,600 1,300 statements per year from 2025/26 to 2034/35. This assumes the right to
personalised short breaks support under the Carers Act, established by the Bill, is implemented from April 2025, although the
implementation date is yet to be decided. Table 11 shows estimated additional costs of the Carers Act personalised breaks element
of the proposed right to breaks established by the Bill. (Note that the summary table (Table 1) only shows costs to 2026-27 2031-
32). 
13 Carers Census, Scotland, 2019-20 and 2020-21 - gov.scot (www.gov.scot) and Carers Census, Scotland, 2021-22 - gov.scot (www.gov.scot)

Page 122

41 
Table 11: Costs of Carers Act breaks (£m) – costs to local authorities / Integration Authorities, transferring to Care Boards 
As per published Financial Memorandum on 20 June 2022: 
2023-24 24-25 25-26 26-27 27-28 28-29 29-30 30-31 31-32 32-33 33-34 34-35 
£m £m £m £m £m £m £m £m £m £m £m £m
Upper
Estimate 0 0 13 27 40 53 66 80 93 106 120 133
Lower
Estimate 0 0 8 16 25 33 41 49 58 66 74 82 
Updated as per December 2023: 
2023-24 24-25 25-26 26-27 27-28 28-29 29-30 30-31 31-32 32-33 33-34 34-35 
£m £m £m £m £m £m £m £m £m £m £m £m
Upper
Estimate
0 0 19 38 59 80 102 125 148 173 198 225
Lower
Estimate
0 0 13 27 40 55 70 86 102 119 137 155
Central
Estimate
0 0 16 32 50 67 86 105 125 146 167 190 
Reasons for Variances:
 Updating estimates using the latest available data on carer population and intensity of caring (as Table 10);
 Uprating the unit costs from 2022/23 to 2023/24 prices;
 Including an estimate for replacement care for young carers caring for 20+ hours per week as part of Carers Act short break
support;
 Increasing the number of carers to reflect the projected increase due to demographic change over the growth period;
 Inflating the estimated costs from 2023/24 prices to nominal prices (in line with the approach in the rest of the
Financial Memorandum);
 Central estimates have been added to the updated table as a new row.

Page 123

42 
78. Table 12 on the costs of easy access breaks is included to show the balance of funding, although this is not a consequence
of the Bill (and is not included in the total costs of the Bill in Table 1). Table 12 includes estimated costs from 2023-24 as this
support does not require new legislation and can therefore be implemented immediately is already building on existing support.
The model assumes this support builds over time allowing the sector to expand its staffing and provision while growing the numbers
of unpaid carers being supported. These figures are predicted to reach a steady state towards the middle of the period as higher
numbers of carers are expected to be receiving personalised breaks under the Carers Act. 
Table 12: Costs of easy access breaks (£m) – costs to the Scottish Administration: 
As per published Financial Memorandum on 20 June 2022: 
2023-24 24-25 25-26 26-27 27-28 28-29 29-30 30-31 31-32 32-33 33-34 34-35 
£m £m £m £m £m £m £m £m £m £m £m £m
Upper Estimate 10 15 20 25 30 35 37 37 37 37 37 37
Lower Estimate 10 15 20 25 30 34 34 34 34 34 34 34 
Updated as per December 2023: 
Easy access breaks
(Scottish Ministers)  2023-24  24-25  25-26  26-27  27-28  28-29  29-30  30-31  31-32  32-33  33-34  34-35 
£m £m £m £m £m £m £m £m £m £m £m £m
Upper Estimate 0 5 10 15 21 26 32 34 35 35 36 37
Lower Estimate 0 5 10 15 21 26 30 31 31 32 33 33
Central Estimate 0 5 10 15 21 26 32 33 33 34 35 36 
Reasons for Variances:
 Updating estimates using the latest available data on carer population data and intensity of caring (as Table 10);
 Uprating the unit costs from 2022/23 to 2023/24 prices;
 Bringing the estimate for existing funding in line with Scottish Government easy-access breaks budgets for 2023/24;

Page 124

43 
 Increasing the number of carers to reflect the projected increase due to demographic change over the growth period;
 Inflating the estimated costs from 2023/24 prices to nominal prices (in line with the approach in the rest of the
Financial Memorandum).
79. Combining the estimates for personalised breaks under the Carers Act (as a consequence of the Bill) and easy access
breaks, the cost of the steady state is estimated to be between £116m and £170m £188m and £261m by 2034/35, with the
central estimate being a cost of £143m
£225m. at 2034/35 prices (£158, £221m and £190m respectively at 2023/24 prices). 
Table 13: Total additional cost of rights to breaks (£m) 
As per published Financial Memorandum on 20 June 2022: 
2023-
24
24-25 25-26 26-27 27-28 28-29 29-30 30-31 31-32 32-33 33-34 34-35 
£m £m £m £m £m £m £m £m £m £m £m £m
Upper Estimate 10 15 33 52 70 88 103 117 130 143 157 170
Lower Estimate 10 15 28 41 55 67 75 83 92 100 108 116
Central Estimate 10 15 31 47 62 78 90 101 111 122 133 143

Page 125

44 
Updated as per December 2023: 
Total Carers Act
& Easy Access
Breaks  2023-24  24-25  25-26  26-27  27-28  28-29  29-30  30-31  31-32  32-33  33-34  34-35 
£m £m £m £m £m £m £m £m £m £m £m £m
Upper Estimate 0 5 29 54 79 106 134 158 183 208 234 261
Lower Estimate 0 5 23 42 61 81 100 117 133 151 169 188
Central Estimate 0 5 26 48 70 94 118 138 159 180 202 225 
Reasons for Variances:
 See reasons at Tables 11 and 12 above.
80. Recognising the considerable uncertainty inherent in these estimates, it will be important to continue to monitor the rate of
growth in provision of breaks from caring as implementation progresses and refine estimates accordingly. Decisions on funding will
also be dependent on future government spending reviews. The Carers Census already aims to collect information about breaks
provided under the existing Carers Act. However, this information has proven challenging for organisations to return and so the
data available is largely incomplete. The Carers Census is currently being has been reviewed and work is ongoing to support local
areas to improve the collection. 
Savings due to rights to breaks
81. The Scottish Government estimates unpaid care is currently saving Scotland £12.8 billion per year in social care costs, plus
£320 million in health care costs – a total saving of £13.1 billion per year14. 
82. The measures in the Bill are designed to protect carers’ health and wellbeing, helping sustain caring relationships. This will
reduce costs which would otherwise arise for the NHS, Local Authorities and Integration Authorities, and subsequently the NCS,
through unplanned hospital admissions, failed hospital discharge and additional residential care when caring relationships break
down. There are around 156,000 people in Scotland providing 35 hours of unpaid care or more per week15. If the right to breaks
helps prevent 1% of these intensive caring relationships 
14 Scottish government calculation of replacement care and hospital days avoided (April 2022) using results in Weaver et al: Does availability of informal care within the
household impact hospitalisation? Health Econ Policy Law. 2014 Jan; 9(1):71-93.

Page 126

44 
15 The number of adult carers is based on the Scottish Health Survey (SHeS) 2020 (published at: Scotland’s carers: update release - gov.scot
(www.gov.scot), Scottish Government 2021) and the profile is based on Scottish Surveys Core Questions (SSQC) data (2016-19).

Page 127

45 
breaking down, that will save £68 million per year in health and social care costs. If the right protects 5% of these intensive caring relationships,
the saving will be £318 million per year16. 
83. Research suggests that unpaid carers have on average 1117 fewer days of full heath per year compared with non-carers.
For Scotland’s unpaid carers this is 9.6 million days per year. If these measures reduce carer ill health by 1%, that will avoid 96,000
days of ill health valued
£8 million per year. If they reduce days of carer ill health by 5%, that will result in 478,000 fewer days of ill health, valued at £39 million per
year18. 
84. There are around 268,000 people in Scotland balancing paid work with an unpaid caring role19. Women make up 61% of
unpaid carers of working age20. Protecting carer health and wellbeing should also lead to wider benefits to the Scottish economy
by enabling more carers to remain economically active, reducing the gender pay gap and social security costs. It is not possible to
precisely estimate the size of these wider savings and benefits but they are expected to be considerable. Additional breaks can
make the difference to help people remain in work or return to work. If the right to breaks helps 1% more carers to remain in work,
the benefit to them and to Scotland’s economy would be worth £71 million21. If it means an extra 5% are working, the benefit would
be £353 million per year. This would also reduce the current £340 million per year expenditure on Carer's Allowance (DWP) and
on Carer's Allowance Supplement (Social Security Scotland). 
“Anne’s Law” – Visits to or by care home residents 
85. Section 39 makes provision for “Anne’s Law”, which ensure that people living in adult care homes to see the people important
to them even during outbreaks of infectious disease. The financial cost of these measures should be viewed in the context of the
progress made since 2021 in maximising meaningful social connections and visiting in adult care homes, effectively readying the
care home sector for the implementation of the statutory requirements provided for in the Bill. 
86. In September 2021, the Scottish Government in collaboration with Public Health Scotland, the Adult Social Care Clinical and
Professional Advisory Group and groups representing families and care home provider published updated “Open with Care” visiting
guidance. 
16 Scottish government analysis of replacement care and hospitalisation (April 2022) 
17 Informal carers’ health-related quality of life and patient experience in primary care: evidence from 195,364 carers in England responding to a national survey. Thomas et
al. BMC Family Practice (2015) 16:62

Page 128

45 
18 Scottish government calculation of unpaid carer days of ill health (April 2022)
19 Scotland's Carers report, Scottish Government, 2015: www.gov.scot/publications/scotlands-carers based on Scotland's Census 2011.
20 Scotland's Carers report, Scottish Government, 2015: www.gov.scot/publications/scotlands-carers
21 Scottish government calculation using data from Annual Analysis of Hours and Earnings (ASHE) 2021, ONS

Page 129

46 
This allowed recommended that for people living in care homes are supported to being able to nominate “named visitors” to see them - even in
a COVID-19 outbreak situation. The guidance promotes and encourages care homes to maximise opportunities for meaningful contact both in
and away from the home. It has been adopted in the most part and serves to practicably and financially prepare the sector for Anne’s Law. 
87. On 31 March 2022, the Scottish Government utilised powers conferred by Section 50 of the Public Services Reform (Scotland)
Act 2010 and introduced two new statutory Health and Social Care Standards relating to visiting. The Health and Social Care
Standards set out what people should expect when experiencing health, social care or social work services in Scotland. As with the
current “Open with Care” guidance. They are taken into account by the Care Inspectorate in relation to inspections, and registration,
of social care services.the Care Inspectorate is required, by law to consider how care service providers are upholding the Standards
both in relation to registering and inspecting care services. 
88. The Bill will enable the Scottish Ministers to exercise a new power under subsection 2 of the Public Services Reform
(Scotland) Act 2010 to require care home service providers to comply with any direction issued by the Ministers about visits to
residents, and visits by residents, of accommodation provided by a care home service (“a visiting direction”). The use of Directions
will allow the Scottish Ministers to set expectations around supporting meaningful connection and visiting and potentially respond
quickly to what may be a rapidly developing situation. and impose requirements on care homes to remove any barriers to full and
normalised visits that may have emerged. This will build further on the principles established through the guidance and Health and
Social Care Standards and ensure that Anne’s Law is enshrined in legislation. 
89. As a result of this incremental approach, the costs of supporting implementing visiting rights and meaningful contact in care
homes fall to both the introduction of the new Standards and to the Bill, and it is not possible to precisely separate them. 
Costs to other bodies and businesses
90. Representatives from care home service providers, local care home oversight teams (now known as Collborative Care Home
Support Teams) , Care Inspectorate and Public Health form part of the Scottish Government’s expert reference group on Anne’s
Law , along with families of care home residents, and help shape and promote the guidance. It is expected that there will be some
costs to these groups for example care home providers and those supporting care homes, to promote and champion Anne’s Law
through in their staff and provider awareness sessions, formal training, updating visiting policies and for printing leaflets and other
administration. However, there has already been work to support the adoption of the new Health and Social Care standards around
visiting and no specific costs have been highlighted by care home providers, and . Accordingly it is anticipated that the new
requirements will be absorbed within the usual costs of updating training and other materials. There are is potentially a time burden
associated with any proposed local oversight and assurance arrangements for Anne’s Law involving professional leads from Local

Page 130

46 
Authorities and NHS Boards. However this could be facilitated through existing local mechanisms for care home support and is not
expected to result in additional staff costs.

Page 131

47 
91. The Scottish Government will continue to consult widely on the anticipated practical application of Anne’s Law within the
expected provisions of the legislation and make note in any divergence from current guidance and potential costs. While this
process is ongoing, it has not highlighted additional costs to the sector. 
Costs to the Care Inspectorate
92. Currently, complaints regarding visiting can be made to registered services, or directly to the Care Inspectorate and for
individual staff via the Scottish Social Services Council (SSSC). Less commonly cComplaints can also go via the local authority,
the Health and Social Care Partnership (HSCP), or the individual NHS health board. If individuals are not happy with the decision
relating to their complaint, from any of these bodies, they can approach the Scottish Public Services Ombudsman 
93. The Scottish Government estimates that there will be heightened public interest in the new legislation, and this which may
result in adults living in care homes, or their friends and families, people exercising their right to complain. Therefore Ccomplaints
to the Care Inspectorate are may expected to increase in the short term, although current arrangements for adopting the new Health
and Social Care Standards and supporting visiting during outbreaks are already well adopted within the sector. while improvements
to visiting become embedded in the sector, but to fall away within 32 years. This is reflected in part in the additional costs below.
Any increase in complaints via other routes is not expected to be significant. 
Additional Costs
94. The Care Inspectorate will also incur costs in the lead up to and following the introduction of Anne’s Law, as there is a need
to promote the guidance, the new Standards and prepare the sector for Anne’s Law with the aim of building capacity and capability
within the sector for improvement. 
95. We have worked with the Care Inspectorate to determine the work over and above their core responsibilities. We have agreed
a package of additional measures, materials and resources to support preparation for Anne’s Law “Open with Care” guidance
including support for care homes to develop new policies reflecting the Health and Social Care Standards; staff induction and internal
and external training; self-evaluation improvement support for services; and developing capacity to enable the immediate resolution
of complaints through direct engagement with providers and services. 
96. In the year 2022/23, total Care Inspectorate costs to support the introduction of Anne’s Law are was estimated to be £186,000,
and
£90,000 in 2023-24 and £50,000 in 2024-25 as shown in table 14. Thereafter, improvements to visiting will become embedded in the sector and

Page 132

47 
we estimate that costs will fall away from year 20245/256 onwards.

Page 133

48 
Table 14: Costs to the Care Inspectorate of implementing Anne’s Law 
Cost Category 2022-23 2023-24 2024-25 2025-26 2026-27 
£m £m £m £m £m
Other public bodies
(Care Inspectorate)
£0.186 £0.090 £0.050 0 0 
Benefits
97. The financial cost of Anne’s Law should also be viewed in the context of the benefits to the health and wellbeing of adult
care home residents and their friends and families, with a case to be made that that there will be savings realised in other aspects
of the Health and Social Care system. 
98. A consultation was launched on 24 September 2021 to seek views on the Scottish Government’s proposals for delivering
Anne’s Law in primary legislation. Analysis of the consultation showed that there is considerable support for the approach of
introducing Anne’s Law. Many respondents commented on their own experiences of family members being isolated in care homes
over the course of the pandemic and the lasting harm this has caused. 
99. Reference to the potential individual and wider system benefits because of improved health and wellbeing was
highlighted by NHS Greater Glasgow and Clyde: 
"There is a wide range of evidence internationally that social connectedness is required for good health. Anne's Law would reduce social
isolation, poor mental health and associated effects on physical health. This creates a more efficient and effective service as there are
less care needs for staff to manage and residents, carers and staff are happier" 
Changes to powers and functions of the Care Inspectorate 
100. A number of proposals have been made in recent years to enhance and strengthen the powers currently available to the Care
Inspectorate, as the independent regulator and scrutiny body for social care services under the Public Services Reform (Scotland)
Act 2010 (“the 2010 Act”). These proposals would enable the regulator to speedily take action with poor performing services, better
protect social care users, and drive up the consistency and quality of care expected across all social care services in Scotland. The
Bill makes provision for two changes which require primary legislation.

Page 134

49 
Enhanced enforcement powers
101. Section 42 of the Bill amends the 2010 Act to give the Scottish Ministers power to set out circumstances in which the Care
Inspectorate can move directly to proposing to cancel a care service’s registration without first issuing an improvement notice,
including on the basis of previous enforcement action. 
102. It is not anticipated that the enhanced criteria to propose to cancel a service’s registration would impose any additional costs
or resource requirements on the Care Inspectorate, care providers or any other organisation. The change is not expected to lead to
any increase in enforcement cases, but it will enable the Care Inspectorate to cancel a service’s registration more quickly, therefore
better protecting social care users. 
Additional joint inspection powers
103. Section 43 enables the Healthcare Improvement Scotland (HIS) to assist the Care Inspectorate to carry out inspections and
the option to charge the Care Inspectorate a reasonable fee determined by HIS for any assistance provided by it. HIS could be
asked to provide additional expertise to contribute to an inspection led by the Care Inspectorate, for example, advice on infection
prevention and control in care homes. Any request for assistance from HIS is expected to be in exceptional circumstances only,
such as during a pandemic. Should the request be for short- term assistance with a small number of inspections then this may be
delivered within HIS’ existing resources. In the unlikely scenario that HIS assistance is requested for a larger number of inspections
or over a longer time period HIS may request payment to cover additional staff costs they incur. Experience during the Covid
pandemic suggests that costs might be between £1000 and £1500 per inspection, if required. No costs for this provision have been
included in table 1 because it is not possible to predict when, or whether, such exceptional circumstances might arise.

Page 135

1 
National Care Service (Scotland) Bill – Financial Implications of Proposed Changes 
Introduction: 
1. In support of the National Care Service (Scotland) Bill, the Scottish Government have provided an update to accompany the
Financial Memorandum (FM) that outlines the costs associated with the Bill as introduced. 
2. Following the agreement between COSLA and the Scottish Government on shared accountability for the NCS, the Scottish
Government proposes to bring forward changes to the Bill at Stage 2 which, if agreed by Parliament, will result in a significant
change to the underlying assumptions associated with the FM. Accordingly, this paper provides a further revision of the updated
costings to reflect the proposed changes, in so far as these can be estimated at this stage. The main differentiating factors between
the updated FM and the Shared Accountability agreement focus on reforming the current Integration Joint Boards (IJB) as opposed
to creating new public bodies (Care Boards), to remove the potential for any staff transfer from Local Authorities as well as adding
the costs associated with the establishment of a National Board. For the purposes of this paper the reformed IJBs will be referred
to as Integration Authorities (IA).

Page 136

2 
Updated Financial Memorandum – Bill as introduced 
3. Table 1 sets out the costs from the updated FM detailing the range of costs associated with the Bill as Introduced. 
Table 1 – Updated Financial Memorandum – Total Costs of Bill Provision 
Sector
2022-23 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
£ millions £ millions £ millions £ millions £ millions £ millions £ millions £ millions £ millions £ millions
Total estimated
costs of Bill
provisions 
13  11 - 13  13 - 17  32 - 46  45 - 64  64 – 115  105 – 353  158 – 438  210 – 524  229 – 609           
Establishment and running of NCS at national level – table 6
Scottish
Administration 13 11 - 13 13 - 17 19 - 27 18 - 26 17 – 26 17 – 26 18 – 27 18 – 28 18 – 28
Establishment and running of care boards – table 7
Scottish
Administration  0  0  0  0  0  7 - 30  0  0  0  0
Care Boards 0 0 0 0 0 0 33 - 247 70 - 309 106 - 371 109 - 433
Total
Establishment and
running of care
board 
0 0  0  0  0  7 - 30  33 - 247  70 - 309  106 - 371  109 - 433
Total NCS costs 13 11 - 13 13 - 17 19 - 27 18 - 26 24 – 56 50 – 273 88 – 336 124 – 399 127 - 461           
Right to breaks from caring* - table 11
Social Care / Care
Boards 0 0 0 13 - 19 27 - 38 40 - 59 55 - 80 70 - 102 86 - 125 102 - 148
Anne’s Law – table 14
Care
Inspectorate* 0 0 0 0 0 0 0 0 0 0

Page 137

3 
Total right to
breaks & Anne's
law 
0 0  0  13 - 19  27 - 38  40 - 59  55 - 80  70 - 102  86 - 125  102 - 148
(Table numbers refer to the corresponding table in the update to the FM)
(*The costs relating to the Care Inspectorate for Anne’s Law are not £0 throughout but instead £186k in 2022/23, £90k in 2023/24 and £50k in 2024/25) 
Table 2 sets out revised costs for the NCS, taking account of the Scottish Government’s proposed changes, where these can be
estimated at this time. 
Table 2 – Revised cost reflecting proposed changes 
Sector 2022-23 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
£ millions £ millions £ millions £ millions £ millions £ millions £ millions £ millions £ millions £ millions
Total estimated costs of Bill
provisions – subject to Shared
Accountability agreement 
13  11 - 13  13 - 18  33 - 48  50 - 72  70 – 104  86 – 126  102 – 149  118 – 175  135 – 198           
Establishment and running of NCS at national level
Scottish Administration 13 11 - 13 13 - 18 20 - 29 21 - 31 20 – 31 21 – 31 22 – 32 22 – 34 22 – 34
Total Establishment and running of Reformed IAs
Reformed IAs 0 0 0 0 2 - 3 10 - 14 10 - 15 10 - 15 10 - 16 11 - 16
Total NCS costs 13 11 - 13 13 - 18 20 - 29 23 - 34 30 – 45 31 – 46 32 – 47 32 – 50 33 – 50           
Right to breaks from caring*
Social Care 0 0 0 13 - 19 27 - 38 40 - 59 55 - 80 70 - 102 86 - 125 102 - 148
Anne’s Law
Care Inspectorate * 0 0 0 0 0 0 0 0 0 0
Total right to breaks & Anne's law 0 0 0 13 - 19 27 - 38 40 - 59 55 - 80 70 - 102 86 - 125 102 - 148
(*The costs relating to the Care Inspectorate for Anne’s Law are not £0 throughout but instead £186k in 2022/23, £90k in 2023/24 and £50k in 2024/25) 
For the purposes of consistency and to provide a direct comparison to the update to the FM the costs from ‘Rights to break from

Page 138

4 
caring’ have been included. However, the shared accountability agreement has no impact upon these cost estimates and so in

Page 139

5 
Table 3 below, the variance assessed is those costs directly attributable to the NCS development. These are the ‘Total NCS Costs’
line in the above tables. 
Variances & Assumptions: 
4. Table 3 sets out the overall variance between the updated FM and the costs reflecting the proposed changes. 
Table 3 – Variance analysis between the updated FM and the Costs reflecting the proposed changes 
2022-23 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
£ millions £ millions £ millions £ millions £ millions £ millions £ millions £ millions £ millions £ millions
Total estimated costs of
Bill provisions (FM) 13 11 - 13 13 - 17 19 - 27 18 - 26 24 – 56 50 – 273 88 – 336 124 – 399 127 - 461
Total estimated costs of
Shared Accountability 13 11 - 13 13 - 18 20 - 29 23 - 34 30 – 45 31 – 46 32 – 47 32 – 50 33 – 50
Variance 0 0 to 0 0 to 1 1 to 2 5 to 8 6 to -11 -19 to -227 -56 to -289 -92 to -349 -94 to -411 
5. There are three significant changes from the updated FM to the shared accountability costings that drive the difference in
estimates. Under the shared accountability agreement, Local Authorities will retain responsibility for delivering social work and
social care services and there will be no transfer of staff and assets. This means that business as usual expenditure will remain and
there will be no additional costs associated with the movement of staff. The basis of the cost was transferring circa 75,000 social
care staff over to terms and conditions baselined against current assumptions on Fair Work and a change in employer pension
contribution rates. At the start of the phased implementation in 2028-29, this was estimated to be £96m rising to £270m per annum
in 2031-32 at full implementation. This is reflected in Table 8A of the updated FM. 
6. The second substantial change is that the FM assumed there would be 31 Care Boards created along with the associated
functions required to run these, Table 8B of the FM sets out the detail of these costs. However, alternative mechanisms to
delivering policy mandates through reforming current local structures are being explored. Reforming Integration Authorities (IA)
rather than creating new Care Board public bodies would result in a significant cost associated with the setup, operation and
governance of these new Boards being removed, with some new, but smaller, costs being incurred in place. The detail of the
proposals is currently being worked through as part of the ongoing Co-Design with service users and discussions with COSLA,
NHS and partners to find the optimal operating model but associated costs will likely include:

Page 140

6 
 Increased support for lived experience representatives on IA boards, including support provided for those who
undertake caring responsibilities to facilitate their involvement.
 Greater training and development and induction support for all board and committee members.
 Strengthening of localities through increased community engagement. This will entail the creation of additional posts
to engage more fully within the localities, addressing and supporting members of the community to ensure their
voices are heard.
 There may be the provision made for the IA to directly employ staff such as the Chief Officer and so provision has
also been made for a centrally hosted team who will manage the operational requirements of the transfer such as HR
and payroll. Table 4 below is a comparator to Table 8B of the updated FM. 
Table 4 – Estimated Care Board / Reformed IA Costs with proposed changes, and variance 
2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
£ millions £ millions £ millions £ millions £ millions £ millions
Staffing 1 – 2 6 - 9 6 - 9 6 - 9 6 - 9 6 - 9
Premises and IT 0 0 0 0 0 0
Running Costs 1 2 2 2 2 - 3 2 - 3
Governance and Board costs 0 2 - 3 2 - 3 2 - 3 2 - 4 2 - 4
Total 2 - 3 10 - 14 10 - 15 10 - 15 10 - 16 11 - 16
FM Table 8B 0 7 - 30 32 - 152 71 - 155 105 - 159 108 - 164
Variance 2 to 3 3 to -16 -22 to -137 -61 to -140 -95 to -143 -97 to -148
* costs in 2026-27 represent the transition costs as the move from IJBs to IAs take place. 
Breakdown of Costs: 
7. The majority of the staffing costs cover the expansion of community engagement teams to support the work with local
communities and lived experience groups. There is also provision made for the creation of a small hosted team who will deliver the
HR, payroll and associated functions should reformed IAs directly employ the Chief Officer and Chief Finance Officers. These posts
are currently employed by Local Authorities or NHS Boards and seconded to the IA. The Premises and IT costs are reduced as the
assumption is that existing premises will continue to be used, so there is no additional cost, while a small provision has been made
for the expansion in IT requirements related to the additional staff. The running costs provide funding in the form of grant support to

Page 141

7 
the new lived experience board members to ensure their full participation is not limited by their caring responsibilities, there is also
further funding to support the engagement and co-design work of the new locality staff, additional training and development for
board members as well as funding to ensure all documents are available in easy read format. Finally, the Governance and Board
costs reflect the remuneration of additional lived experience members who will sit on the reformed IA boards. The transitional costs
in 2026-27 are those related to the early adoption of the new staff and their associated recruitment, training and equipment in order
to ensure a smooth transition into the new operating model. 
8. The third significant change is that within the Bill as introduced, there was no provision for the establishment of a National
Care Service Board. However, as set out in the letter from the Minister for Social Care, Mental Wellbeing and Sport to the Health,
Social Care and Sport Committee on 6 December 2023, COSLA and the Scottish Government have agreed that the NCS should
have a National Board to be the main route through which shared accountability is operationalised and managed. As stated in that
letter, we are currently developing the delivery mechanism for the National Board. While this may be in the form of a public body,
the final shape of the entity is still to be agreed. There is a rigorous approval process within Scottish Government for any new public
body and the proposals for this Board will be subject to that in due course. However, for the purposes of this paper, the revised
costs presented here have assumed that it will be established as a body with its own legal identity, such as a Non Departmental
Public Body (NDPB), as means of identifying the upper range costs for the Board. We are acutely aware however, of the financial
pressures faced across Government and so while the costing of a new public body provides assurance over the upper levels of
liability, the design approach has also endeavoured to maximise value for money and make the body as streamlined as possible. 
9. To determine estimated costs for the National Board, numerous sets of annual accounts of current NDPBs have been
assessed to determine consistent cost elements that can be included, based on the anticipated size and function of the National
Care Service Board. Community Justice Scotland specifically was identified as being a relevant baseline for subsequent
comparison. Table 5 below sets out high level cost estimates for the National Board. It is estimated that Board will go live on the 1
April 2026. Costs associated with the setting up of the National Board are expected in 2024-25 and 2025-26 to enable this go live
date.

Page 142

8 
Table 5 – National Board Cost 
Cost Area 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 
£ millions £ millions £ millions £ millions £ millions £ millions £ millions £ millions
Staff 0 1 2 - 3 2 - 3 2 - 3 2 - 4 2 - 4 2 - 4
Premises & IT 0 0 0 0 0 0 0 0
Running Costs 0 - 1 1 1 1 1 1 1 1
Governance & Board
Costs 0 0 0 0 0 0 0 0
Total 0 - 1 1 - 2 3 - 5 3 - 5 4 - 5 4 - 5 4 - 6 4 - 6 
Breakdown of Costs: 
10. The staffing cost covers the running of the body, complete with its own operational staffing complement. We have assessed
the options for shared services for areas like payroll and HR, such as those found in other public organisations, and have built in
provision for other specific activities, for example, to ensure the Board can carry out the functions set out below as well as
administration, communications and engagement. The premises and IT costs cover provision for rental costs and the set up and
ongoing costs associated with IT capabilities, these are noted as £0 above but that is due to them being below the £0.5m threshold
for rounding up, the average annual cost is estimated as £0.2m. The running costs cover the operational costs of the Board with
provision for, but not limited to, external legal advice, audit fees, administration and communications, supplies and staff related
expenditure. The governance and board costs cover the executive management function and the associated costs attributable to
the decision making board, such as member remuneration. 
Scope & Function 
11. The NCS National Board will drive forward improvements across the system by supporting collaborative leadership and
greater collaboration between partners. It will also seek to improve quality and consistency of services and ensure services are
sustainable and person-centred by undertaking new functions at the national level.. 
12. The high level functions of the National Care Service Board are expected to include:
 setting national strategic direction;
 developing standards, guidance and operating frameworks;

Page 143

9 
 overseeing and seeking delivery assurance on local strategic plans and ethical commissioning strategies;
 monitoring system performance;
 maintaining a support and improvement framework which will aim to provide support to local areas when monitoring
indicates that standards are not being met with powers of intervention, when required, as a last resort;
 ensuring visibility of data, information, and analysis about social care support, social work and primary and community health
services through reporting on delivery;
 national commissioning and procurement by agreement for complex and specialist social care services which will include
prison social care;
 seeking assurance on public protection arrangements; and
 providing support to local delivery partners. 
13. Members of the Board will include Scottish Government, local government, NHS Boards and, importantly, people who
access these services, workforce representatives and unpaid carers. The wider membership of the board will be co-designed. We
recognise the importance of embedding the voice of the third sector and unions, for example, in the governance structures for the
NCS nationally and locally. 
14. There are a number of elements that have remained consistent in the cost estimates presented within the updated FM and
this revised costing. An internal Scottish Government function would be required either to implement the Bill as introduced or to
implement the proposed shared accountability arrangements, to organise and deliver the setup of the NCS and reformed IA / Care
Boards. When established, the National Board will need to be supported to fulfil its functions. The intention is for the National Care
Board to enhance capacity in the system, therefore staffing arrangements must reflect this approach and remain flexible. Options
are still being considered for supporting the National Board. The cost estimates presented in this paper assume that the Board, if
established as a separate body with its own legal identity, will require a core staff team of its own with broader support for the work
of the Board coming from existing Scottish Government teams. 
Affordability 
15. Throughout the work undertaken on shared accountability and more widely in the ongoing design of the NCS, affordability
and achieving value for money is a primary concern. We are acutely aware of the challenging financial position and as highlighted

Page 144

10 
in Table 3 above, the recurrent operating cost has been substantially reduced
with this shared accountability approach. In terms of the additional
investment required, Table 2 above sets out the anticipated cost of the NCS
development (excluding carer’s breaks) which over the 10 year time frame, at
the upper level, sits at £345 million. However, it should be noted that
currently we are incurring in excess of £10 million per annum by way of
Scottish Government staff, costs which even were the NCS to cease would
continue to be incurred. Table 6 below therefore, sets out the NCS
development costs compared to the current staff cost. For the purpose of
comparison the staff numbers have been kept constant but adjusted for
inflation. This table therefore highlights what additional investment would be
required excluding those currently employed staff in order to give the truer
reflection of the additional liability. 
Table 6 – Additional Investment 
2022/23 202
3/24
2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
£m £m £m £m £m £m £m £m £m £m
Total NCS costs 13 - 13 11 -
13
13 - 18 20 - 29 23 - 34 30 - 45 31 - 46 32 - 47 32 - 50 33 - 50
Current Staff
Cost
10 10 11 11 11 12 12 12 13 13
New Costs 3 1 - 3 2 - 7 9 - 18 12 - 23 18 - 33 19 - 34 20 - 35 19 - 37 20 - 37 
Based on this comparison the additional investment over and above
employed civil servants sits between £120 million and £227 million across this
10 year time period. Work will continue to Co-Design the NCS in the most
financially sustainable way.