REPORT 
Item No: 9 
SUBJECT: Winter Plan Business Case Progress Report
TO: Integration Joint Board 
Lead
Officer for
Report:
Morag Dendy, Head of Planning, Performance & Quality
Assurance 
Author(s)
of Report
Graeme Cowan, Senior Manager, Strategy & Performance 
DATE: 17 May 2023 
1. PURPOSE OF REPORT 
This paper is coming to the IJB for: 
For approval ☐ For endorsement ☒ To note ☐ 
2. ROUTE TO THE BOARD 
This paper has been: 
Prepared
By:
Senior
Manager,
Strategy &
Performance 
☐ Reviewed
By: 
Head of
Planning,
Performance
& Quality
Assurance 
☐ Endorsed By: ☐

Page 2

2 
3. RECOMMENDATIONS
It is recommended that the IJB Committee: 
(1) Endorse and support the progress reports of each of the workstreams which
comprise the Winter Planning & Enhance Supports Business Case 
4.  VARIATIONS TO DIRECTIONS? 
5. BACKGROUND/SUMMARY OF KEY ISSUES
5.1 The Scottish Government allocated additional funding in 2021/2022 and
2022/2023 to increase capacity across the health and social care system. In
February 2022, the Integration Joint Board approved a business case for the
commitment of the additional funding, while also taking the opportunity to
target nonrecurring reserves to implement a series of proposals, including the
development of a Home First model in North Lanarkshire, additional
community nursing capacity, enhanced care at home capacity, and additional
infrastructure supports. This report provides an update on the progress made
with implementing these proposals.
5.2 Within each phase of the implementation process, the business case
proposals have been re-evaluated both within workstreams and through the
Strategic Commissioning Plan Programme Board. Implementation plans are
revised and reconfigured regularly to reflect the reality of recruitment
challenges, the funding available and the outcomes achieved through the
preceding phases.
5.3 The original aims of the business case were to increase assessment and
planning capacity across the system and enhance direct provision of supports
and services across a range of organisations. Workstreams have been
established to implement plans and proposal against the following headings: 
 Home Assessment Team & Enhanced Integrated Rehabilitation
Provision
 Community Nursing
 Increased Capacity Across Home Support Service, Equipment and
Adaptations Service, Community Alarms Service & Assistive
Technology
 Hospital at Home
 Building Capacity of Independent Sector Providers  
 Investment in Communities   
Yes  ☐ No ☒ N/A ☐

Page 3

3 
5.4 Progress updates on each of the workstreams are attached to the report as Appendix
One, offering a summary of progress-to-date and planned future actions. 
6. CONCLUSIONS
6.1 Progress continues to be made to implement the business case and
undertake the recruitment as approved in order to progress the necessary
change activity in line with the Scottish Government funding allocations.
7. IMPLICATIONS 
7.1 NATIONAL OUTCOMES
Link(s) to National Health and Wellbeing Outcomes 
People are able to look after and improve their own health and
wellbeing and live in good health for longer 
☒
People, including those with disabilities or long-term conditions, or
who are frail, are able to live, as far as reasonable practicable,
independently and at home or in a homely setting in their community
☒
People who use Health and Social Care Services have positive
experiences of those services, and have dignity respected
☒
Health and Social Care Services are centred on helping to maintain or
improve the quality of life of people who use those services 
☒
Health and Social Care Services contribute to reducing health
inequalities 
☒
People who use Health and Social Care Services are safe from harm ☒
People who work in Health and Social Care Services feel engaged
with the work they do and are supported to continuously improve the
information, support, care and treatment they provide
☒
Resources are used effectively and efficiently in the provision of
Health and Social Care Services 
☒
7.2 ASSOCIATED MEASURE(S) 
7.3 FINANCIAL 
This paper has been reviewed by Finance: 
Yes  ☐ No ☐ N/A ☒

Page 4

4 
7.4 RISK ASSESSMENT/RISK MANAGEMENT 
Relevant Risk Register
Details 
Current Risk Level  Risk Owner 
Choose an item. 
7.5  PEOPLE 
7.6 INEQUALITIES & FAIRER SCOTLAND DUTY 
EQIA Completed & Fairer Scotland Impact Assessment Form Completed and
attached to report: 
EQIA added to website: 
8. BACKGROUND PAPERS   
9. APPENDICES
Appendix one – Business Case Workstream Updates 
Appendix two – Summary of Winter Planning Funding & FTE 
CHIEF ACCOUNTABLE OFFICER (or Depute)   
Members seeking further information about any aspect of this report, please
contact Graeme Cowan CowanG@northlan.gov.uk 
Yes  ☐ No ☒ N/A ☐
Yes  ☐ No ☐ N/A ☒

Page 5

5 
Direction from North Lanarkshire Integration Joint Board
(IJB) 
1 Reference Number  
2 Report Title  
3 Date direction issued by
IJB 
4 Date from which direction
takes effect 
5 Direction to: 
6 Does this direction
supersede, revise or revoke
a previous direction – if
yes, include reference
number(s) 
7 Functions covered by
direction 
8 Full text of direction 
9 Budget allocated by
Integration Joint Board to
carry out direction 
10 Performance Management /
Governance arrangements 
11 Date direction will be
reviewed

Page 6

Appendix One 
Winter Planning & Enhanced Supports Business Case – Workstream Updates 
Workstream Home Assessment Team & Enhanced
Integrated Rehabilitation Provision
Overall
RAG
Status
AMBER (some
concerns that need to
be monitored closely) 
Workstream Ambition 
Ring-fenced teams to enable:
• A designated workforce with focus on facilitating discharge without delay and enabling
admission avoidance 
• A robust discharge pathway for those who require home assessment and rehabilitation
following discharge from both front door and downstream wards
• A robust admission avoidance pathway for those not requiring hospital admission but
requiring the benefit of a person centred approach to assessment in their own home setting
• Flexibility to deploy the workforce across the sectors
• Home first conversation to become the norm at every stage of the person’s journey (Why not
home? Why not now?)
• Clear leadership within discharge services
• An approach to avoiding admission to be developed with the IRT and locality teams- Systems
in place to ensure that Home Support, Community IRT and Locality Social Work Teams will be
aware of patients likely to transition to them from HAT at the end of the agreed assessment
period. Agreement in place to ensure HAT transition outwards is not jeapardised.
• Wide-ranging strong links with discharge facilitators within the hospital discharge hub- HAT is
embedded in the Hospital Discharge Hubs and communication, liaison and multi-agency
working in inherent.
• Utilisation of the embedded Planned Date of Discharge (PDD) approach to identify suitable
patients pathways 
• Close working relationship with associated teams: hospital Multi-Disciplinary Teams (MDTs),
District Nursing, Integrated Rehabilitation Teams, Third sector colleagues with access to
satellite equipment stores.
Highlights 
Progress and Achievements:
• Home Assessment Team soft launched in Wishaw in late April 2022 taking referrals from
University Hospital Wishaw and University Hospital Monklands.
• Cumbernauld soft launch in August 2022
• Cumbernauld and Wishaw Home Assessment Teams operating and almost fully staffed.
• As of 3rd April 2023, 561 patients had been referred and discharge supported by the Home
Assessment Team. The growth in the referral rate to the Home Assessment Team has shown a
sustained growth, particularly since the beginning of November 2022. The Hospitals involved
in the referral were UHM 42%, UHW 55%, other 1% and 1% offsite bed.
• During the month of March 2023 HAT had a total of 118 (up 26 referrals from February 2023)
referrals across both sites. Patients were discharged into localities including Wishaw 31 (up 3
from February 2023), Motherwell 38 (up 22 from February 2023, Cumbernauld 26 (up 4 from
February 2023), Airdrie 19 (down 3 from February 2023)
• Workshops held in October to map pathways and review and agree pan-Lanarkshire referral
criteria with all key stakeholders in the MDT including transfers of care into mainstream home
support and rehabilitation services.
• Interface with other teams/staff eg IRT, Locality Social Work, Home Support Teams, GPs

Page 7

7 
• Of the 35.75 FTE Integrated Rehabilitation Team (IRT) posts supported within the Business
Case, 29.5FTE have been recruited to.
Ongoing Actions
• HAT service model in development phase, this will be finalised by end of April 2023. 
• Additional accommodation restructuring ongoing at UHW to ensure teams are co-located
appropriately for next steps. Review by planning team at UHW due to complete end of April
2023 - possibility of new options following same - previous review on hold.
• Recruitment to HAT ongoing to build capacity and roll out across other NL localities (see
appendix 1 for update). The pressures within the system regarding workforce are widely
acknowledged. These pressures have been impacted by the competitive employment market
with staff leaving for better pay and conditions, training and career opportunities. The social
care sector is facing significant challenges, as a regulated workforce, the number of people
leaving to seek alternative careers is at its highest. Additionally, the cost of living and fuel costs
are impacting directly on the workforce
• Virtual Board to be discussed to communicate and act as an early warning system/ barometer
to downstream statutory support services re expected transition from HAT- discussion with
IRT T/Ls, Advanced Practitioners reached agreement re early warning practices and agree no
requirement for virtual board as highlighted in gap analysis
• Discussions re CCA/ increase requests etc and implications for HAT
• Further review of HAT/ Home First pan-Lan criteria to encompass admission avoidance and
plan to develop pan-Lan poster for staff when complete
Future Actions 
• A number of recruitment campaigns have been progressed across health and social care to
recruit across the team including Home Support, Physiotherapy and Occupational Therapy
staff. This is with the intention that the Wishaw and Cumbernauld Team will be fully
operational by end February. Work ongoing to stabilise Airdrie and Cumbernauld localities for
HAT with cross cover
• Moving on to implement HAT in remaining localities, with Coatbridge and Bellshill 
• Communication and engagement activities are progressing including staff briefing sessions,
reaching out to comms department re other comms including animation video
• Review, analysis and recommendations to be undertaken to ensure HAT and home first
approach is intrinsic within the wider HSCP teams and not a stand-alone service
• Establish key links within the Health & Social Care Whole System Dashboard and track wider
impacts of the service on Delayed Discharge performance, and capacity of the home support
service.

Page 8

8 
Workstream Community Nursing Overall
RAG
Status
AMBER (some
concerns that need to
be monitored closely) 
Workstream Ambition
As part of the SCP/ Winter planning work supported by Scottish Government, funding was agreed
to support increased capacity in community nursing teams and to support delivery of the
Community Nursing Review. 
Funding agreed and recruitment progress is highlighted below 
Posts Funded In post
Band 3 HCSW 40 WTE 32.63 WTE
Band 3 admin 8WTE 5WTE
Band 5 RGN 15 WTE 11 WTE
Band 7 ANP 2 WTE 1WTE
Band 7 Practice assessor 2 WTE 2 WTE
Band 8a Senior Nurse 1WTE 1WTE 
There has been turnover in the Band 3 HCSW staff group which has made growth challenging. 
Band 5 recruitment growth has also been challenging due to vacancies within current funded
establishment which is prioritised. 
Progress and Achievements:
• Community Nursing Review Programme Board established with two Short Life Working
Groups set up and running
o Care Management
o Vision and modelling
• Roadshows held
• District Nursing Pathway Evaluation now ready for final comments
• A rolling program for recruitment is being considered and evaluated
• Delays to some actions due to work being carried out on Operation Flow
• Work with Scottish Government in relation to retention, development of workplace and
improving culture 
Future
• Caseload complexity review
• Define the criteria for core and additional caseloads in conjunction with the views of staff.
Consideration will need to be given as to how this fits in with the MORSE system. Although
changes are unlikely to be made before the end of the year/beginning of next year, simple
changes of benefit to staff may be adopted. A couple of roadshows will be scheduled for
further down the line.
• The District Nursing service is aiming for a transformation surrounding how it delivers its
services. There is a shift in the balance of care from acute to primary care and will need to
consider what that will look like and how it can be made ‘fit for purpose’. There is further
emphasis on health promotion and educating families.

Page 9

9 
Workstream Increased Capacity Across Home Support
Service, Equipment and Adaptations
Service, Community Alarms Service &
Assistive Technology
Overall
RAG
Status
AMBER (some
concerns that need to
be monitored closely) 
Workstream Ambition 
The expansion of current direct provision of support will include: 
• Home support expansion, making permanent some temporary measures which are required
longer term to facilitate improved capacity and quality of service. Both frontline practitioners
as well as logistics and operational management posts are included in the immediate
requirements. 
• Increased capacity within the Equipment and Adaptation Service 
• Development of a dedicated Technology Team to support the use of technology within the
HSCP to support individuals within their homes and communities. This team will focus on
embedding technology into assessment and planning processes; providing training to all staff
groups on technology and its use in care and support; supporting with risk assessments;
ensuring technology support advice is embedded in SDS; and providing high level data on the
technology being used within our communities.
Highlights 
Home Support 
 71.89 WTE permanent posts funded by the Business case allocated across localities; process
commencing to match existing temporary staff into these posts within each team.
 New Home Support Delivery Project Board established to progress high level Project Plan, with
Risk Register, Benefits Realisation Plan and Workstreams agreed and being progressed. 
Technology Team and Equipment & Adaptation Service 
 Recruitment to posts complete for the Technology Team and in progress for the Integrated
Equipment & Adaption Service
 Technology team now embedded and links with locality teams being developed.   
Workstream Hospital at Home  Overall
RAG
Status
AMBER (some
concerns that need to
be monitored closely) 
Workstream Ambition 
Extension of Working Hours
 Introduction of Advanced Nurse Practitioners (Band 7) to allow service hours and patient
admission to service to continue until 10pm.
 To allow 2 Band 7 ANPs to be rostered on 7 days a week (one from 8am-6pm, and one from
2pm-10pm) would require 4.58 WTE (including 22.5% planned leave allowance).
 There is a current national shortfall in the availability of qualified Advanced Practitioners,
therefore a training programme would need to be offered and supported, this requires up to
2 years to complete (although some potential internal Hospital @ Home candidates have
already been supported through the advanced clinical care and Non-Medical Prescribing
programmes, so may require less support before becoming fully qualified).
Permanent Funding of Step-Down Pathway
 During the Covid pandemic to assist with anticipated hospital flow and to increase our ability
to serve GPs with hospital admission a “step down” hub was created to ring fence staff and

Page 10

10 
create a designated flow for Acute inpatients to be discharged into the Hospital @ Home
service.
 This service improvement contributed to the increased referral activity and has admitted an
average of 38 patients per month in 2021. Due to the clinical presentation of the patients at
admission to Hospital @ Home the model could be slightly adapted to allow the patients to be
managed by a Junior doctor (with Consultant in-reach when necessary) and band 5 nurses.
Junior doctors have been difficult to recruit on a continuing basis, however an ANP band 7
nurse could provide clinical management to these patients.
Highlights 
• Step down pathway has been operational since May 2020. The permanent funding of this
allowed us to continue this service provision. Since the initial programme we have had some
Band 5 RGNs leave the service for various reasons, some gaining promotion within the service.
This has allowed them to be successful at gaining Band 6 Nurse Practitioner posts within the
service. 
• The Band 5s and Band 4 have been in temporary posts, the permanent funding has allowed us
to appoint on a permanent basis. We have 3 of the 4 Band 5 posts filled permanently with the
third at the recruitment stage, after the previous successful candidate withdrew. The Band 4
is appointed permanently.
• The Band 7 ANP who was appointed withdrew due to personal reasons, the new COR is with
finance for approval to re-advertise.
• The stepdown pathway has supported 390 patients from NHSL Acute wards from April 2022
to Feb 2023 
Workstream Building Capacity of Independent Sector
Providers  
Overall
RAG
Status
AMBER (some
concerns that need to
be monitored closely) 
Workstream Ambition 
It was agreed that a local provider sustainability fund is established to facilitate an individualised
approach to: 
• Supporting recruitment and retention 
• Supporting staff wellbeing 
• Supporting cross sector support to SVQ2 
• Increase to Scottish Care support to the sector 
Highlights 
 Two phases of funding bids have been completed 
 Successful implementation of Interim care home beds programme 
 Successful uptake of financial support in place to support Carers

Page 11

11 
Workstream Investment in Communities    Overall
RAG
Status
AMBER (some
concerns that need to
be monitored closely) 
Workstream Ambition 
To make prevention and early intervention a reality, additional investment is required to add to
the community capacity building work already well embedded in the Community Solutions
Programme through VANL. Further investment through the new Improving Lives workstream will
see development across a number of key priorities for the Partnership, in line with the Strategic
Commissioning Plan, and to ensure there is sufficient capacity within the community and
voluntary sector to respond to demand. 
The range of achievements via the Community Solutions Programme Approach has seen
significant development through anchor organisations of; Support in the Right Direction,
Community Connectors, Improving Cancer Journey and Social Prescribing. Early findings from the
innovation test site introducing 3 conversations to improve First Point of Contact, has indicated
that there is a need to invest more significantly in a robust response through the sector which
would facilitate a further focus on prevention and wellbeing. This will be achieved through
connectedness and valued activity with a combination of paid roles and community investment
funding. 
Funding proposals are based on the appointment of Community Connector posts across key
anchor organisations to support 3 Conversations with Older Adults, Younger Adults and Carers. An
umbrella approach through Community Solutions will ensure a co-ordinated approach throughout
North Lanarkshire and link clearly to the Community Consortia in promoting local opportunities
for and with people, avoiding the need for more formal services for longer. The Community
Connectors will also play an important role in the transitional arrangements for people at the
point they may need more formal responses from the HSCP. 
A core, recurring investment of £1.1m pa supports the Community Solutions programme but an
additional £1.2m over a two-year period would see the considerable expansion of the offer.
Achievements:
• Project to be embedded in the Community Solutions programme and named Improving Lives.
• Project plan finalise and agreed by Chief Officer and Head of Planning, Performance and
Quality Assurance.
• Model for recruitment and deployment of Community Connectors agreed. 
• The current Support in the Right Direction link workers (2wte) have received a 12 month
extension to their funding from SG (to 31 March 2024). This will be of benefit to the new
Community Connectors as these existing staff have established good relationships across NL
and can share learning thought their previous involvement in the 3 Conversation test of
change.
• Opportunity to extend the reach of the Community Connector posts by building in the
Improving Cancer Journey funding. This investment means there will be a total of 10wte posts
(NB this is an increase from the original proposal of 9.5wte).
• Commissioning of locality hosts complete which allows us to recruit to the Community
Connector posts once the ICJ application agreed by Macmillan. 
Activities:
Complete

Page 12

12 
• Project plan agreed.
• Funding for physical activity programmes confirmed for 22/23.
• New part time senior manager recruited to provide capacity to oversee implementation of
Improving Lives programme.
• Six Locality hosts agreed. 
Outstanding
• Finance to be transferred to VANL
• Governance arrangements for test of Individual Support Fund
• Relationship to GP Community Link Workers to be strengthened with the aim of developing
future joint proposals to make best use of available resources where possible. 
• Community Solutions thematic priorities review (first meeting took place 09 Feb) 
Future
• Recruitment of 10 Community Connectors will be progressed once Macmillan agree the ICJ
application (expect approval imminently).

Page 13

13 
Appendix 2
Funding
2022/2023
Projected Costs
2022/2023
Variance
2022/2023
£m £m £m
Recurring Budget 15.750 7.104 8.646
Non-Recurring Budget 1.162 0.448 0.714
Earmarked Reserves 7.712 2.447 5.265
TOTAL FUNDING 24.624 9.999 14.625
APPROVED IN POST VARIANCE
Integrated Rehabilitation Team 49.33 22.02 27.31
Home Assessment Team 138.68 58.08 80.6
Home Support 165.78 125.2 40.58
Infrastructure 18 9 9
Social Work Management 4 3 1
Community Alarms/Stores/Tech 20.2 13 7.2
Community Nursing 69.35 39.71 29.64
Hospital at Home 8.58 3 5.58
TOTAL FTE AS AT PERIOD 12 473.92 273.01 200.91
SUMMARY OF WINTER PLANNING FUNDING AND POSTS
FUNDING DESCRIPTION
OPERATIONAL CATEGORY FTE