REPORT
Item No: 12
SUBJECT: Our Health Together 
TO: IJB
Lead
Officer for
Report:
Ross McGuffie, Chief Officer North HSCP
Author(s)
of Report 
Stacey Anderson, Support Services, Project Manager 
DATE: 17 May 2023
1. PURPOSE OF REPORT
This paper is coming to the IJB for:
For approval ☐ For endorsement ☐ To note ☒
2. ROUTE TO THE BOARD
This paper has been:
Prepared By: ☐ Reviewed By:
The Planning,
Performance
and
Resource
Committee 
☒ Endorsed By: ☐

Page 2

2 
3. RECOMMENDATIONS
It is recommended that the IJB note the content of the report. 
4.  VARIATIONS TO DIRECTIONS? 
5. BACKGROUND/SUMMARY OF KEY ISSUES
5.1  Our Health Together - Living Our Best Lives in Lanarkshire 
5.1.1 The engagement to inform NHS Lanarkshire’s new healthcare strategy ‘Our
Health Together’ launched on 21st April and gives our communities and those
who work in the service the chance to shape how we deliver healthcare for
future generations. 
5.1.2 The aim is to deliver a wide-ranging stakeholder engagement programme
involving patients, unpaid carers, our staff and local communities (including
children and young people), working together to inform the development of our
new strategy ‘Our Health Together – Living Our Best Lives in Lanarkshire’.    
5.1.3 Now is the time for everyone in Lanarkshire, residents and staff, to play a major
role in shaping services for the future and to be involved in discussions about:
 Factors that affect people’s health and wellbeing;
 Ways in which NHS Lanarkshire can support local people to stay well;
 Access to NHS Lanarkshire services 
 The role of digital developments in healthcare. 
5.1.4 Advances in medicines, technology and science provide opportunities to change
and modernise the way we deliver care.  There are also challenges that we
need to plan for now. To help treat and support those who need healthcare the
most we need to maximise what we can provide within our resource.  Local
residents and staff need to play a vital role in shaping services that deliver
modern healthcare.   
5.1.5 In February the NHS Lanarkshire Planning, Performance and Resource
Committee signed off the Our Health Together (OHT) Public Engagement Pack,
with approval to finalise and move to engagement thereafter.  Since February
a number of actions have been completed by the Our Health Together team as
Yes  ☐ No ☒ N/A ☐

Page 3

3 
detailed below which has resulted in the formal of Stakeholder Engagement
Programme which took place on Friday 21st April 2023. 
5.2 Our Health Together Development Actions Feb- April 2023. 
5.2.1 Communications
 Communication plan finalised (Appendix 1 OHT Engagement Plan)
 OHT web page developed 
 Animation Video and BSL video produced detailing the purpose of the
engagement
 Social media and media campaign agreed 
5.2.2 Documentation and Resources
 Review and update of the engagement briefing concluded ensuring
compliance with plain English guidelines
 Graphics incorporated to make the document more engaging and
accessible
 Development of an “in-brief” version 
 Development of an “easy-read” version of the briefing 
 Demographic questions incorporated
 Presentation developed
 Facilitators pack developed 
 Staff engagement questions consulted on and finalised based on agreed
themes and the community engagement plan  
 Questionnaire (staff and community) build completed on Smart Survey
platform 
5.2.3 Pre Engagement Testing
 Consultation and testing of the briefing pack and community engagement
questions
 Successful pre-engagement event with the NL Community Board
undertaken to test the approach 
5.2.4 Review and Evaluation
 Engagement with Healthcare Improvement Scotland – Community
Engagement Directorate who have reviewed and fed back positively on
the approach we are adopting 
 Development of an Evaluation process which will allow us to review and
adjust our approach as we progress
 Mid engagement review process agreed to review reach and feedback to
date based on collated demographics
 Evaluation timeline agreed (quantitative evaluation to be concluded early
July)

Page 4

4
5.3 The next steps.
5.3.1 Work will continue to: 
 review feedback to further refine the Engagement Programme Plan
(Appendix 1); and
 review staff and community responses to determine if additional
targeted communications are required.
6. CONCLUSIONS
6.1  The IJB is asked to note the ongoing development and refinement of the
Stakeholder Engagement programme to inform the development of our new
Our Health Together strategy. 
The OHT Development Timeline is detailed below for information. 
7. IMPLICATIONS
7.1 NATIONAL OUTCOMES
Link(s) to National Health and Wellbeing Outcomes 
People are able to look after and improve their own health and wellbeing
and live in good health for longer 
☒
People, including those with disabilities or long-term conditions, or who are
frail, are able to live, as far as reasonable practicable, independently and at
home or in a homely setting in their community
☐
People who use Health and Social Care Services have positive
experiences of those services, and have dignity respected
☒
Health and Social Care Services are centred on helping to maintain or
improve the quality of life of people who use those services 
☐

Page 5

5 
Health and Social Care Services contribute to reducing health inequalities  ☐
People who use Health and Social Care Services are safe from harm ☐
People who work in Health and Social Care Services feel engaged with the
work they do and are supported to continuously improve the information,
support, care and treatment they provide
☐
Resources are used effectively and efficiently in the provision of Health and
Social Care Services 
☒
7.2 ASSOCIATED MEASURE(S)
Progress against implementation of the final strategy will be monitored via NHS
Lanarkshire’s Planning, Performance and Resources Committee. 
7.3 FINANCIAL 
This paper has been reviewed by Finance: 
7.4 RISK ASSESSMENT/RISK MANAGEMENT 
Relevant Risk Register
Details 
Current Risk Level  Risk Owner 
Corporate Risk 2062 Choose an item. Strategy Delivery Team 
7.5  ENGAGEMENT & PARTICPATION
Please tick the engagement and participation objectives that link(s) with this piece of
work and provide further details regarding the engagement and participation that was
undertaken.
Objectives  Further Details 
☒ Involve stakeholders in the development
work aimed at achieving the national 
outcomes 
☒ Provide stakeholders with information on
how to get involved 
☒ Ensure a diverse range of engagement
and participation and opportunities are in 
place to suit different needs 
☒ Measure how well we involve community
stakeholders in the planning, design 
Yes  ☐ No ☐ N/A ☒

Page 6

6 
and delivery of our services 
☒ Provide regular feedback on how
stakeholder engagement and participation is
shaping and influencing service
development and delivery 
☒ Provide support to enable stakeholder
representatives to participate meaningfully
and confidently at meetings 
☒ Develop participation guidelines to
ensure a common understanding and set of 
expectations for both stakeholders and
partnership staff 
☒ Support engagement planning and
participation in localities, taking account of 
other engagement activity and local plans
across the Community Planning 
Partnership 
7.6 INEQUALITIES & FAIRER SCOTLAND DUTY 
EQIA Completed & Fairer Scotland Impact Assessment Form Completed and
attached to report: 
An EQIA on the communications and engagement process has been completed, with
EQIAs developed/being developed for individual work stream engagement. 
EQIA added to website: 
8. BACKGROUND PAPERS   
Yes  ☒ No ☐ N/A ☐
Yes /
Date
added 
☐ No ☐ N/A ☐

Page 7

7
9. APPENDICES
Appendix 1 – Engagement Programme Plan 
CHIEF ACCOUNTABLE OFFICER (or Depute)  
Members seeking further information about any aspect of this report, please contact
Ross McGuffie on telephone number 01698 752 591.

Page 8

8
Direction from North Lanarkshire Integration Joint Board (IJB)
1 Reference Number
2 Report Title
3 Date direction issued by IJB
4 Date from which direction
takes effect
5 Direction to:
6 Does this direction
supersede, revise or revoke a
previous direction – if yes,
include reference number(s)
7 Functions covered by
direction
8 Full text of direction
9 Budget allocated by
Integration Joint Board to
carry out direction
10 Performance Management /
Governance arrangements
11 Date direction will be
reviewed

Page 9

NHS LANARKSHIRE OUR HEALTH TOGETHER
Engagement Plan
Updated 18.4.23
DATE ACTIVITY DETAILS WORKSTREAMS/THEMES STAKEHOLDERS STATUS
Jul-Sep '23 Development of Equality Impact Assessment
on the engagement process
EQIA developed to inform final engagement plan and support an
inclusive approach to the process
Our Health Together Public, staff Complete
Aug-Sep '22 Staff briefing, The Pulse Sustainability and Climate Change Strategy survey Sustainability Staff Complete
6.9.22 NHS Lanarkshire Public Reference Forum Update on Our Health Together and discussion to inform engagement
plan
Our Health Together Public Complete
Sep '22 Online survey Public and staff survey to inform development of digital strategy Digital Public, staff Complete
Sep '22 Online survey Public and staff survey to inform development of quality strategy Quality Public, staff Complete
26.19.22 Cluster Quality Leads Update with GPs in Lanarkshire Our Health Together Staff Complete
28.9.22 Planning, Policy and Resources Committee
Meeting
Our Health Together framework and draft engagement plan Our Health Together NHS Lanarkshire Board Complete
30.11.22 Planning, Policy and Resources Committee
Meeting
Update report Our Health Together NHS Lanarkshire Board Complete
25.1.23 NHSL Board Meeting Update report Our Health Together NHS Lanarkshire Board Planned
7.2.23 NHS Lanarkshire Public Reference Forum Update on Our Health Together and discussion to inform engagement
plan
Our Health Together Public Complete
22.2.23 Planning, Policy and Resources Committee
Meeting / NHSL Board Meeting
Board sign-off of framework and engagement document Our Health Together NHS Lanarkshire Board Complete
23.3.23 Our Health Together - Future Engagement
with Community Boards
MS Teams engagement meeting including presentation and breakout
group discussion
Our Health Together Members of North Lanarkshire Community Boards Complete
29.3.23 Lanarkshire Rehabilitation Strategy Steering
Group
MS Teams meeting including presentation and questions. Calvin
attending.
Our Health Together Staff, public, third sector and partners Complete
14.4.23 Area Medical Advisory Committee MS Teams meeting including presentation and questions. Calvin
attending. Meeting postponed as not quorate.
Our Health Together Staff Complete
21.4.23 Launch of Our Health Together community
and staff engagement programme
Engagement period runs from 17 April to 23 June 2023. Details of
specific communications and engagement activity below.
Our Health Together All Planned
21.4.23 Our Health Together public webpages New Our Health Together web section on NHSL public website
https://www.nhslanarkshire.scot.nhs.uk/our-health-together/ including:
engagement document; in brief engagement document; video; BSL
video; EQIAs - comms/engagement; survey links;
details of engagement events; email inbox:
ourhealthtogether@lanarkshire.scot.nhs.uk
Our Health Together All In progress
21.4.23 Full engagement document Distributed electronically to stakeholders and available on the website.
Printed copies available on request.
Our Health Together All In progress
21.4.23 In brief engagement document Distributed electronically to stakeholders and available on the website.
Printed copies available on request.
Our Health Together All In progress
Appendix 1

Page 10

DATE ACTIVITY DETAILS WORKSTREAMS/THEMES STAKEHOLDERS STATUS
21.4.23 Easy read (assessible) engagement
document
Easy read version of document for people with learning disabilities Our Health Together All In progress
21.4.23 Online surveys Online stakeholder surveys developed and delivered with support from
Snook. Separate surveys for public and staff stakeholders.
Our Health Together All In progress
21.4.23 Paper survey Paper alterative for those unable to access online survey Our Health Together All In progress
21.4.23 Engagement feedback email address Our Health Together email address for stakeholder feedback and
questions: ourhealthtogether@lanarkshire.scot.nhs.uk
Our Health Together All In progress
21.4.23 Stakeholder electronic newsletters Reguar newsletters issued to stakeholders during the engagement
process up to launch of the final strategy including: link to video; link to
survey; link to documents
Our Health Together All In progress
21.4.23 Media release on launch of engagement Engagement launch media release followed by reguar media releases
issued to stakeholders during the engagement process up to launch of
the final strategy
Our Health Together All In progress
21.4.23 Engagement video Overview engagement video for use on website social media Our Health Together All In progress
21.4.23 Engagement BSL video British Sign Language engagement video for use on website and social
media
Our Health Together All In progress
21.4.23 Social media posts Regular social media posts to inform, update and encourage
stakeholder participation
Our Health Together All In progress
21.4.23 Flyers A5 flyer for use at in person engagement opportunities to encourage
update of engagement survey
Our Health Together All In progress
21.4.23 Posters Our Health Together All In progress
21.4.23 Pulse article on launch of engagement Engagement launch media release followed by reguar articles during
the engagement process
Our Health Together Staff and GPs In progress
21.4.23 All in Lanarkshire staff email on launch of
engagement
Engagement launch email to all NHS Lanarkshire staff and GPs Our Health Together Staff and GPs In progress
TBC NHS Lanarkshire Ethnic Minority Employee
Network Newsletter
Article in newsletter on Our Health Together Our Health Together Staff In progress
21.4.23 Weekly email staff briefing Item on engagement launch followed by regular reminders during the
engagement process
Our Health Together Staff and GPs In progress
24.4.23 Disabillity Network MS Teams meeting including presentation and questions. Calvin
attending.
Our Health Together Staff Planned
24.4.23 GP Sub Committee MS Teams meeting including presentation and questions Our Health Together GPs Planned
26.4.23 Planning, Policy and Resources Committee
Meeting
Update report Our Health Together NHS Lanarkshire Board Planned
27.4.23 Area Clinical Forum 2pm - Presentation and feedback discussion with ACF Our Health Together Area Clinical Forum, staff and GPs Planned
4.5.23 Acute Site Medical Staff Association - UHM MS Teams meeting including presentation and questions Our Health Together Staff Planned
2.5.23 Public Reference Forum MS Teams meeting including presentation and questions. Single item
agenda to focus on OHT discussion. Calvin attending.
Our Health Together Staff and Public Planned

Page 11

DATE ACTIVITY DETAILS WORKSTREAMS/THEMES STAKEHOLDERS STATUS
10.5.23 In person - staff engagement roadshows Staff engagement roadshow at University Hospital Hairmyres Lecture
Theatre (10-11am) All staff from NHS Lanarkshire and health and
social care partnerships invited.
Our Health Together Staff Planned
12.5.23 Mid-engagement review meeting Meeting of NHS Lanarkshire Communications and Engagement
Strategy Delivery Goup (with stakeholder involvement) to review
progress with engagement process
Our Health Together All Planned
16.5.23 In person - staff engagement roadshows Staff engagement roadshow at University Hospital Wishaw Ronald
Miller Lecture Theatre (10-11am) All staff from NHS Lanarkshire and
health and social care partnerships invited.
Our Health Together Staff Planned
22.5.23 snook
23.5.23 Area Partnership Forum 9.30am - Presentation and feedback discussion with APF Our Health Together Area Partnership Forum Planned
24.5.23 In person - staff engagement roadshows Staff engagement roadshow at University Hospital Monklands Lecture
Theatre (10-11am) All staff from NHS Lanarkshire and health and
social care partnerships invited.
Our Health Together Staff Planned
9.6.23 Elected represenative briefing session MS Teams elected representative engagement session open to
Lanarkshire MSPs, MPs and councillors. Presentation by Colin and
Chris
Our Health Together MSPs, MPs, councillors Planned
21.6.22 AHP Area Advisory Committee MS Teams meeting including presentation and questions Our Health Together Staff Planned
Apr-Jun  '23 Online community engagement events MS Teams meetings including presentation, questions and group
discussion. Invite to be open to all stakeholders. One daytime and one
evening session planned. Details to be confirmed
Our Health Together All Planned
Apr-Jun  '23 Engagement outreach Face-to-face engagement opportunities to raise awareness of
engagement, encourage completion of survey and answer questions.
Locations to include hospitals, health centres, vaccination clinics
Our Health Together All Planned
Apr-Jun  '23 Health Improvement engagement
opportunities
Health Improvement Team to undertake engagement with relevant
groups and make use of exisiting interactions with services users to
raise awareness of the engagement process and encourage completion
of the survey
Our Health Together All Planned
Apr-Jun  '23 Engagement presentation to community
groups
Opportunity for local groups to request engagement presentation at
their meeting
Our Health Together Community stakeholders Planned
Apr-Jun  '23 Online staff engagement event Two online staff engagement events - one aimed at North Lanarkshire
and one at South Lanarkshire health and social care partnerships staff.
Our Health Together Staff Planned
Apr-Jun  '23 Voluntary Action South Lanarkshire
(VASLAN) locality network engagement
events
Two engagement sessions (one rural, one urban)  with the VASLAN
localtiy networks. Details to be confirmed.
Our Health Together Voluntary Action South Lanarkshire Planned
Apr-Jun  '23 Voluntary Action North Lanarkshire (VANL)
locality engagement events
Engagement sessions with VANL localities. Details to be confirmed. Our Health Together Voluntary Action South Lanarkshire Planned
23.6.23 Close of Our Health Together community and
staff engagement programme
Closing date for official engagement period and survey. Our Health Together All Planned
Sep '23 Stakeholder review of draft strategy Post engagement stakeholder meeting to review how feedback has
informed the draft strategy document
Our Health Together All Planned
Nov '23 Launch of Our Health Together strategy Launch of final document following sign off and Board approval Our Health Together All Planned