Item 17 - Chryston Community Health Clinic Update

North Lanarkshire Council · 22 March 2023
Back to Health and Social Care Integration Joint Board — 22 March 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

1 
REPORT 
Item No: 17
SUBJECT: Progress Update: Development and Delivery of Chryston
Community Health Clinic
TO: IJB
Lead Officer for
Report:
Ross McGuffie, Chief Officer 
Author(s) of
Report 
Maggs Thomson, Head of Health
DATE: 22nd February 2023 
1. PURPOSE OF REPORT
This paper is coming to the IJB to provide an update on the development and
delivery of Chryston Community Health Clinic 
For approval  For endorsement  To note 
2. ROUTE TO THE BOARD
This paper has been:
Prepared   Reviewed   Endorsed   
Prepared by Maggs Thomson, Head of Health in consultation with both Chryston
Community Health Clinic Mobilisation Group and the Northern Corridor Service
Repatriation Group.         
3. RECOMMENDATIONS
The IJB is asked to:
1) Note the active and ongoing progress with the delivery of this capital
programme.
2) Note the progress with the repatriation of the clinical services from NHS Greater
Glasgow & Clyde (NHSGG&C) and their associated Health and Social Care
Partnerships (HSCP’s)

Page 2

2 
3) Note the previously identified financial gap reported Feb 2022 and reflect on
work to date to progress towards final conclusion.  
4.  VARIATIONS TO DIRECTIONS?                  
5. BACKGROUND/SUMMARY OF KEY ISSUES
5.1 Background
5.1.1 From 1st April 2014, Health Board boundaries were realigned with those of
the Local Authorities across Scotland, with the aim of reducing administrative
barriers and ensuring full alignment with the integration of health and social
care services as set out in the Public Bodies (Joint Working) (Scotland) Act.
5.1.2 This boundary change aimed to facilitate the development of integrated
services across all areas of Scotland. The change resulted in the Northern
Corridor (covering the areas of Moodiesburn, Muirhead, Chryston, Stepps,
Gartcosh and Auchinloch) being transferred into the NHS Lanarkshire (NHSL)
boundary.
5.1.3 This geographical area has one health facility located within Muirhead
(Muirhead Clinic), which is small and at the time of transfer, dilapidated and
not fit for function. The facility required backlog maintenance and asbestos
work to be undertaken which was completed.
5.1.4 Despite the upgrade and refurbishment which improved compliance with
healthcare standards, the facility could still not support the provision of all
services for the local population.
5.1.5 Consideration was given to providing a new build facility on the existing site,
however the footprint and parking limitations would not allow for the size of
centre required to meet the clinical ask.
5.1.6 Due to the limited capacity of this facility, NHSL was unable to fully repatriate
services from NHSGG&C, resulting in northern corridor residents having to
travel significant distances across Glasgow to access some health services,
with teams and clinics based in a range of areas including Shettleston,
Kirkintilloch, Easterhouse and Bridgeton. 
5.1.7 The services identified below continue to be delivered via a Service Level
Agreement (SLA) with NHSGG&C and the associated HSCP’s.  
• Community Diabetic Service
• Community Mental Health Teams
• Dietetics
• Physiotherapy
Yes  No  N/A

Page 3

3 
• Sexual and Reproductive Health Services
• Substance Misuse  
5.1.8 An opportunity emerged with the development of North Lanarkshire Council’s
(NLC) ‘The Plan for North Lanarkshire’ which set out an ambitious estates
strategy that looked to develop Community Hubs / Campuses.  Further to
consideration of this approach, NHSL working in partnership with NLC, invited
hub South West Scotland to deliver a single campus for the replacement of
Muirhead Community Health Clinic and Chryston Primary School.
5.1.9 There was extensive engagement with all stakeholders including NLC and
NHSL project teams which resulted in the optimum design being developed to
the satisfaction of all the stakeholders. The agreed design went through wide-
ranging routes of engagement with key stakeholders including NHSL staff,
H&SCP staff, teachers, support staff and pupils at Chryston Primary School.
This process also included joint engagement with representatives of the
Parent Council and elected members, culminating in an online public
consultation to inform residents of the design outcome.
5.1.10 The business case for the Development of Chryston Community Health Clinic
was considered by the NHSL Board on December 2021 at a cost of £3.65M
and signed off with all legal agreements completed in January 2022.
5.1.11 The build programme began on Monday 14th February 2022 with a completion
date of early August 2023 identified.
5.1.12 In tandem with the facility development, a process was initiated with NHSGG&C
(and associated H&SCP’s) to begin the process of repatriation of the identified
clinical services.
5.1.13 A Service Level Agreement (SLA) continues to be in place and as of February
2022 this exposed H&SCNL to a £392k financial gap if services where to be
delivered with the known funded establishment and skill mix of the NHS
Lanarkshire service model.
5.1.14  It was also recognised in February 2022 that to support the smooth transition,
clinical safety and continuity of care there would be an expectation of double
running costs for a period of 3 months, equating to an increased cost of £212k
for that quarter.
5.1.15 All work has progressed on the basis of the funding being agreed in February
2022 calculation.  
5.2 Chryston Community Health Clinic
5.2.1 The build programme is currently on schedule for completion August 2023 (see
Appendix 1 for visual update).

Page 4

4 
5.2.2 H&SCNL mobilisation group is progressing well with all work streams and is
currently on track to have all systems in place for operational delivery in August
2023.  At the point of writing, all planned milestones have been met.
5.2.3 The next three months will require development around the operational plan for
the clinic, communication plan for all stakeholders, procurement, staff
engagement, system education and mobilisation plan.  All milestones have
been identified and the new work plan for the next 3 months will be in place by
the end of February 2023.
5.2.4 The work plan is now being progressed in tandem with the repatriation
programme and the next iteration will show a confluence of milestones as
recruitment will be a key work stream and this is in development.  
5.3  Repatriation of Services 
5.3.1 The timeline for repatriation and local delivery of services continues to move
toward completion that will coincide with the operational delivery of the new
health clinic in August 2023. There is the comfort of double running agreed for
3 months to support smooth and safe transition of care. 
5.3.2 Discussion between H&SCNL and NHSGG&C (and associated H&SCP’s) is
ongoing and progressing to achieve a smooth and clinically safe transfer of
services.  This is being managed via two discrete working groups focussing
on mental health services and physical health services. 
5.3.3 There is currently work ongoing with finance colleagues from both NHSL and
NHSGG&C to conclude financial agreements to provide certainty to allow
recruitment to progress. 
6. CONCLUSIONS
6.1 In conclusion, this paper confirms that Chryston Community Health Centre
has been commissioned by NHSL in partnership with NLC and is on track to
be operationally available for service delivery from August 2023.  
6.2 In tandem with the build programme, work is ongoing to repatriate the
identified services, with work ongoing with both finance and operational
teams.
6.3 The IJB has already approved additional fundng to support double running
costs for one quarter, as well as additional recurring funding to support the roll
out of the NHS Lanarkshire service models in the area. Work continues
between the two finance departments around the financial transfers and
further updates will come to the IJB once finalised.

Page 5

5 
7. IMPLICATIONS 
Noted within the content of the paper
7.1 NATIONAL OUTCOMES
The repatriation of services will support improvements in a range of service
performance measures, particularly around mental health and substance
misuse. 
7.2 ASSOCIATED MEASURE(S) 
None.
7.3 FINANCIAL 
Yes   No  N/A 
At this time (2022 calculation), it is known that there is a revenue gap of
£392k per annum and a non-recurring cost of £212k to support double
running of service for a 3-month period, as previously approved by the IJB
and built into the IJB’s Medium Term Financial Plan.  Finance teams are
reviewing our known position and will provide contemporary costs by the end
of March 2023. 
7.4 RISK ASSESSMENT/RISK MANAGEMENT 
Risks around the repatriation of services, including the transfer of complex
treatment packages, ongoing recruitment challenges and the funding gap
already identified and will be built into the operational risk register. 
7.5  PEOPLE
A significant programme of engagement has taken place as part of the
development of the business case. 
7.6 INEQUALITIES & FAIRER SCOTLAND DUTY 
Yes  No  N/A 
Developed as part of the business case.    
8. BACKGROUND PAPERS 
NHS Lanarkshire Chryston Community Health Clinic Business Case

Page 6

6 
https://www.nhslanarkshire.scot.nhs.uk/download/2021-december-20-board-
papers/ 
9. APPENDICES
Appx 1 Artistic representation of Health Clinic and progress photograph
date 22nd February 2023.   
.
CHIEF ACCOUNTABLE OFFICER (or Depute)   
Members seeking further information about any aspect of this report, please contact
the following; Maggs Thomson, maggs.thomson@lanarkshire.scot.nhs.uk

Page 7

7 
Appendix 1 
1: Artists Impression of main entrance with health clinic to the left of the picture 
1: Work to date (22nd February) of health clinic