REPORT 
Item No: 11 
SUBJECT:  Investment in IT Infrastructure to support care delivery
TO:  Integrated Joint Board
Lead
Officer for
Report: 
Ross McGuffie
Chief Officer 
Author(s)
of Report 
Mark Russell
Associate Medical Director
DATE:  22nd June 2022 
1. PURPOSE OF REPORT 
This paper is coming to the IJB 
For approval  For endorsement  To note 
2. ROUTE TO THE BOARD 
This paper has been: 
Prepared By:
Associate Medical
Director, North
Lanarkshire HSCP 
Reviewed By:
Chief Officer 
Endorsed: 
3. RECOMMENDATIONS 
 Note the progress which has been made in procuring a reprovisioned IT system
for General Practice and the opportunity this provides for providing an
infrastructure for the work of integrated teams
 Note the opportunity to improve the quality and co-ordination of care by further
investment in broader IT infrastructure
 That a ring-fenced reserve is created of £1.5m, including 0.301m to fund shared
services linked to General Practice IT systems until 2029/30 
4.  VARIATIONS TO DIRECTIONS? 
Yes  No  N/A

Page 2

2 
5. BACKGROUND/SUMMARY OF KEY ISSUES 
5.1 Background to GP IT Reprovisioning
5.1.1. Contracts for the supply and support of GP Clinical Systems within Scotland
are currently held separately by each territorial NHS Board. These are coming
to end of life and in NHS Lanarkshire began to expire in May 2019.
5.1.2. In the meantime, a National procurement/re-provisioning exercise has been
undertaken with representatives from Scottish Health Boards. As a result,
NHS Scotland has put in place a National GP IT Managed Services contract,
signed and managed by NSS on behalf of the NHS Boards. This Multi-
Supplier Framework Contract, which will replace the existing individual NHS
Board contracts, was signed on 1st February 2019. Three suppliers, EMIS,
Cegedim (Vision) and Eva Health Technologies were appointed to this
framework. There have been significant delays and Eva have withdrawn from
the framework, with a system from Emis not being available for at least
another year.
5.1.3. The current system poses significant challenges for the development of
primary care services; in particular, the challenges of shared access to GP
clinical systems has acted as a rate limiter on the implementation of the
Primary Care Improvement Programme and remote access to GP clinical
systems requires the exclusive use of a physical desktop PC in the practice,
making efficient use of estate challenging. A process was therefore initiated in
Lanarkshire in June 2021 to examine the feasibility of a Direct Award to
Cegedim as soon as their system was available in Spring 2022 and a cohort
of GP practices formed. All except two practices have agreed to join this
cohort, which covers 99.5% of Lanarkshire’s population 
5.2. Current position
5.2.1. Significant work has been undertaken over the last 6 months:
 An accelerated rollout has been planned, with all cohort practices to be
completed by the end of the financial year and the rollout of key
features such as those to improve prescribing efficiency and safety by
the end of November
 Planning for the use of shared services infrastructure by vaccinations
and treatment rooms by the end of July 
 Implementation groups have been set up to cover technical, pharmacy
and primary care improvement plan issues. A further group is proposed
to deal with deployment in integrated services
 A Request for Proposal has been made to Cegedim, and groups have
scrutinised the financial, interfacing, and technical aspects of the
response. In addition, a group representing the cohort practices has
examined the response 
5.2.2. The Direct Award assessment process has identified a number of benefits of
moving forward immediately:

Page 3

3 
 Primary Care – delivery of the GP contract through allowing access to
GP records which will facilitate collaboration, and more broadly, enable
closer working between GPs and other professionals
 Clinical Infrastructure – currently community services lack a booking
and communication platform, which the Vision Anywhere application
would provide.
 Infrastructure for Integrated Services –Vision Tasks is a standalone
application which could be used for communication between (for
example) social work and district nursing teams
 Population Level Planning – Cegedim have asked Lanarkshire to
consider forming a strategic partnership with them, to further develop
their Outcomes Manager product to integrate both primary and
secondary care data. Subject to extension of existing Data Sharing
Agreements with practices, this would significantly enhance the
population health and planning abilities of the Health and Social Care
Partnership 
5.2.3. The group representing the cohort practices is content that the product is fit
for purpose but was clear that the rationale for moving forward immediately is
dependent on the Shared Services and Outcomes Manager features, which
are prerequisites for delivering the benefits above, and require investment
from NHS Lanarkshire and North and South Lanarkshire HSCPs in addition to
the core funding provided by Scottish Government. 
5.3. Future investment in other care critical IT services 
5.3.1. A number of other partnership programmes will require further investment to
maximise their capabilities for assisting with the delivery of safe and high
quality care: 
 Replacement of SWIS in Social Work and development of dynamic
scheduling
 Extension of deployment of Morse to CAMHS and purchased and
deployment of scheduling component
 Further development of TrakCare within managed services to enable
Electronic Medical Record capabilities
 Deployment of Hepma to Paediatrics and Hospital at Home 
5.3.2. These developments are expected to take place over the next 5-8 years and it
is proposed that reserves are set aside to fund this. 
6. CONCLUSIONS 
6.1. The IJB is asked to note the work that has been undertaken to improve the IT
infrastructure available to ensure the availability of information to staff to
promote the delivery of high quality care and facilitate inter-professional
working.

Page 4

4 
6.2. It is asked to approve the creation of a reserve to fund the above and other key
IT developments over the next 8 years 
7. IMPLICATIONS 
7.1 NATIONAL OUTCOMES
Improving the IT infrastructure and connectivity will impact on all nine health
and wellbeing outcomes by improving service efficiency and multi-disciplinary
working. 
7.2 ASSOCIATED MEASURE(S) 
7.3 FINANCIAL
The Scottish Government has agreed to fund the gap between the current
annual costs for GP IT and the higher costs that will be incurred under new
arrangements. It will also fund central costs over the implementation period
and the ongoing contract and service management costs of GP IT. However,
these ‘Core’ costs do not include local deployment, training or interface costs,
or the costs for shared services. 
£3.03m is required to implement the system and cover costs beyond those
covered by Scottish Government until the anticipated end of this procurement
in 2029/30. £0.935m can be met by redirecting existing NHS Lanarkshire
eHealth funding streams, and South Lanarkshire IJB has previously set aside
reserves of £1.5m to cover initial deployment and training.
Negotiations with Cegedim has delivered significant reduction in costs,
however a funding gap of £0.602m remains. Given the potential for this
investment facilitating transformative change in community health and broader
integrated services across both North and South Lanarkshire HSCPs, it is
suggested that this gap should be funded by both IJBs setting aside a reserve
of £0.301m.
It should be noted that this is a maximum cost; in negotiations, Cegedim have
committed to remove all costs for Shared Services share (which would
eliminate this funding gap) should they reach a 55% national population
share. Their current share is 48%. In addition, negotiations are ongoing with
regard to the terms of a potential strategic partnership for Population Health
features and this may yield further savings. 
This paper has been reviewed by Finance: 
Yes   No  N/A 
7.4 RISK ASSESSMENT/RISK MANAGEMENT 
Risk 2086 – GP sustainability sits as a Very High risk on the NHSL Corporate
Risk Register. 
7.5  PEOPLE

Page 5

5 
The potential for improved information sharing between services could
positively impact the integration and seamless delivery of services for NL
residents.   
7.6  STAKEHOLDER ENGAGEMENT (Detail below any stakeholder engagement
that has taken place).
Key stakeholders in the development of the Health and Wellbeing work are
staff across health and social care employed through NHSL, NLC as well as
all third and independent sector providers. Wide engagement has been
maintained to ensure wide benefit and uptake of the approach described in
the report. 
7.7 INEQUALITIES & FAIRER SCOTLAND DUTY 
EQIA Completed & Fairer Scotland Impact Assessment Form Completed: 
Yes  No  N/A 
7.8  CARBON MANAGEMENT IMPLICATIONS 
No negative impacts identified. 
8. BACKGROUND PAPERS  
9. APPENDICES 
.............................................................................
CHIEF ACCOUNTABLE OFFICER (or Depute)   
Members seeking further information about any aspect of this report, please contact
Ross McGuffie on telephone number 01698 752 591.