Contract Variation – Carnbroe and Sikeside Community Hub 
From  James McKinstry, Chief Officer (Assets and Procurement) 
E-mail  McBrideMark@northlan.gov.uk Telephone 07583094928 
1. Background 
1.1 The council’s Financial Regulations detail the threshold variances where reporting of
contract variations is required. 
1.2 A Design and Build Development Agreement (DBDA) was signed on 13 December
2021 for the construction of Carnbroe and Sikeside Community Hub (now known as
Riverbank Community Hub). This award was approved at the Policy and Strategy
Committee on 2 December 2021. The total contract sum was £24,821,452. 
Executive Summary 
In accordance with the council’s Financial Regulations, any variation where the
outturn/expected costs exceed the tendered contract price by the higher of £25,000 or 5%,
should be reported by the appropriate budget holder to the relevant spending committee. 
The purpose of this report is to inform committee of a variation in costs against the tender
contract price incurred on contract for the construction of Carnbroe and Sikeside
Community Hub. 
Recommendations
It is recommended that the Policy and Strategy Committee: 
(1) Acknowledges the contents of this report and the accompanying appendix. 
The Plan for North Lanarkshire
Priority  All priorities
Ambition statement
(2) Refocus our town centres and communities to be multi-functional
connected places which maximise social, economic, and
environmental opportunities

Page 2

1.3 The overall cost for delivering this project has exceeded the original contract sum for
various reasons. 
2. Report 
Footbridge Construction 
2.1 When the project was granted planning approval, a condition of that approval was to
provide safe pedestrian access from the south of the site prior to the hub opening
(Planning Application No. 21/00436/FUL, Condition 24). The planning process was
managed by Hub South West Scotland Limited and the appointed Tier 1 contractor,
Morgan Sindall. The team reviewed various options and concluded that the
construction of a footbridge was the most efficient way to satisfy this condition. 
2.2 As design and tendering process was well underway when the planning decision was
made to allow for continued project momentum, there was not sufficient time to include
this requirement within the initial DBDA. If the process had been stopped at this time to
include this requirement within the contract, the construction of the community hub
would have been delayed by 6-12 months and due to volatility in the construction
market this would have significantly increased the cost of the community hub by at least
2% for every three months delay.   
2.3 As this requirement was a condition of the planning application for the community hub
and there was insufficient time to independently procure this requirement, internal
approval from the Chief Officers within Legal and Democratic Services and Assets and
Procurement was sought to vary the existing construction contract to include for the
construction of the footbridge. 
2.4 By doing so, this allowed for efficiencies in construction timescales (which are important
as the hub cannot open without access from the south or other contingency measures
being in place); value for money through sharing of site accommodation and an already
established supply chain; and reduction in risk of health and safety complexities due to
more than one main contractor working in close proximity. By selecting this
procurement route, the council ensures that the bridge will be in place when the
community hub opens. 
2.5 The original budget estimate was in the region of £1.8m. The cost of the footbridge is
anticipated to be no greater than £1,500,000 including design and survey costs and
15% client contingency. This will be funded from the Town and Community Hub Capital
Programme budget. 
2.6 The Town and Community Hub Board has approved the procurement route and funding
being contained within the overall programme budget. 
Other Variations to Date 
2.7 Any construction contract can experience variations due to a number of factors outwith
the council’s control. In addition to the variation for the footbridge construction, there
have been 10 other variations instructed into this contract. 
2.8 These are for a number of reasons including:
 installation of EV charging bays and future ducting provision;
 adjustments to external works including increasing the height of the pitch fence;
 replacement goals and painting of adjacent fencing;
 specification change to internal classroom doors to glazed doors; and

Page 3

 finalising the fixed furniture and equipment required for the new hub. 
The variations noted above total circa £258k. 
2.9 All of the above variations will be accommodated within the Town and Community Hub 
Capital Programme budget. 
3. Measures of success 
3.1  Successful delivery of the Carnbroe & Sikeside Community Hub project and installation
of the pedestrian footbridge to satisfy planning conditions.     
4. Supporting documentation 
Appendix 1 – Detail of Project Costs   
James McKinstry
Chief Officer (Assets and Procurement)

Page 4

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Additional £1,753,055 of expenditure through existing contract. Additional cost can
be incorporated within overall Town and Community Hub capital programme
budget. 
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☒ No ☐ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
Advice has been sought from Legal and Democratic Services in advance of
instructing Hub South West Scotland Limited regarding potential amendments to
existing contractual agreements and compliance with the relevant procurement
regulations. 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐

Page 5

If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐
5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☒
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact?
Installation of EV chargers at community hub to support council’s environmental
policies. 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.

Page 6

Appendix 1 – Detail of Project Costs 
Project Contractor Contract
Sum
Estimated
Final
Account
Difference Main Reasons for Additional Costs
Carnbroe & Sikeside
Community Hub
(also known as
Riverbank
Community Hub)
Hub South
West
Scotland
Limited
£24,821,452 £26,574,507 £1,753,055
Inclusion of footbridge construction within construction contract
to satisfy planning conditions and incorporation of additional
works which could not be finalised when construction contract
signed