North Lanarkshire Council
Report
Policy and Strategy Committee 
Does this report require to be approved? ☒ Yes   ☐ No
Ref  DB / EK / GT Date 16/03/23 
PO12.1(1) – Strategic Capital Investment Programme 2023/24 to
2025/26 - Update 
From  Derek Brown, Depute Chief Executive  
E-mail telferg@northlan.gov.uk Telephone 07583 010692 
Executive Summary
This report provides an annual update on the Council’s Strategic Capital Investment
Programme including an update on available resources and the expected profile of
expenditure over the 2023/24 to 2025/26 period. 
The report highlights £709m of capital investment plans from 2021/22 to 2025/26 in support
of the Council’s long-term ambitions for place shaping transformation of North
Lanarkshire’s towns and communities. Alongside record level of investment in the Council’s
housing provision through the Housing Revenue Account, the total investment in North
Lanarkshire’s communities is planned to be £1.332 billion over the current five-year
planning period. 
The current Strategic Capital Investment Programme demonstrates £159.702m of external
funding, highlighting the Council’s continuing success in levering additional funding from
the Scottish Government, UK Government and public sector partners. 
Recommendations
It is recommended that Committee:  
(1) Approves the 2023/24 Strategic Capital Investment Programme as outlined in
Appendix 1; and
(2) Approves the updated profile of the Strategic Capital Investment Programme from
2024/25 to 2025/26 as outlined in Appendix 1;
(3) Approves the extension of the current Capital Strategy to 31 March 2024 as outlined
in paragraph 2.12; and
(4) Approves the updated Terms of Reference and Governance Framework for the
Council’s Strategic Capital Delivery Group outlined in Appendix 2.  
The Plan for North Lanarkshire
Priority  Improve North Lanarkshire's resource base
Ambition statement (25) Ensure intelligent use of data and information to support fully
evidence based decision making and future planning

Page 2

1. Background 
1.1 The Council’s capital investment plans are underpinned by the Capital Strategy that
was approved at Policy and Strategy Committee in June 2019. The Capital Strategy
aims to create an asset base that meets the shared ambition with the aspiration for
North Lanarkshire to be the place to Live, Learn, Work, Invest and Visit. 
1.2 The Council adopted the Strategy in preparing the Council’s Strategic Capital
Investment Programme approved at Policy and Strategy Committee on 17 March 2022.
This ambitious programme recognised General Services investment of £725.354m in
North Lanarkshire’s communities between 2021/22 and 2025/26. Excluding the impact
of City Deal this reflected a 260% increase in capital expenditure compared to the
previous five year programme and reflects the ambitions of the Council to deliver the
Plan for North Lanarkshire and to further support the recovery from the pandemic. 
1.3 The approved Capital Strategy highlights the role of the Council’s Strategic Capital
Delivery Group (SCDG) in ensuring the effective management, delivery and monitoring
of capital projects. The SCDG is an officer working group comprising of senior officer
representatives from key Council services. 
2. Report 
Updated Forecast Resources
2.1 The updated Strategic Capital Investment Programme has been developed based on
the latest estimates of available resources, including government grant, Community
Investment Fund and prudential borrowing. The following table provides an update on
the 5-year resource profile:   
Forecast Available Resources
2021/22 2022/23 2023/24 2024/25 2025/26 Total
£000 £000 £000 £000 £000 £000
Capital Grant 23,380 23,380 23,380 23,380 23,380 116,900
Community Investment Fund 2,606 24,299 80,444 97,972 33,751 239,072
Prudential Borrowing (Former
SC21) 15,504 55,639 49,063 0 0 120,206
Prudential Borrowing (NLC Match
for City Deal, Spend to Save etc) 15,406 6,659 6,005 9,466 30,545 68,081
External Funding (including City
Deal) 26,110 42,923 47,450 28,178 15,041 159,702
Capital Receipts 1,000 1,000 1,000 1,000 1,000 5,000
Total 84,006 153,900 207,341 159,996 103,717 708,960

Page 3

2.2 The analysis above reflects the updated estimate of Community Investment Fund
resources as reported to Policy and Strategy Committee on 29 September 2022,
reflects the capital programme reductions approved at Policy and Strategy Committee
on 1 December 2022, incorporates anticipated City Deal grant income and additional
income generated by the Council including grant support from organisations such as
Strathclyde Partnership for Transport; Scottish Government grants such as Vacant and
Derelict Land Fund; and partner / developer contributions. 
2.3 The total five-year programme presented to Policy and Strategy Committee in March
2022 highlighted total resources of £725.354m, representing a reduction of £16.394m.
This reflects the impact of a rephasing of City Deal expenditure and associated income
of £44.000m beyond the current planning period. Excluding the impact of this
programme reprofiling, overall resources have increased by £27.606m on a like for like
basis. This reflects the Council’s success in levering additional funding such as the
successful Levelling Up Fund application for Cumbernauld Town Centre. 
2.4 There have been no changes to the projections for the Council’s share of the General
Capital Grant, capital receipts allocated to support capital expenditure and ‘spend to
save’ funding linked to completion of the energy efficient LED programme delivery. 
Strategic Capital Investment Programme
2.5 The programme continues to face challenges caused by external market issues. These
include reduced capacity for external contractors to deliver projects within previously
assumed timelines linked to ongoing shortages of materials and labour, increasing
material costs, availability of vehicles and equipment and the requirement to adjust the
scope of programmes to reflect changes to service delivery. 
2.6 The Council’s Strategic Capital Delivery Group has continued to consider these issues
throughout the current financial year and agreed programme reprofiling in accordance
with its Terms of Reference at its meetings on 15 September 2022 and 2 February
2023.   
2.7 Following these reprofiling exercises, the table below outlines the updated programme
phasing over the current five-year capital planning period per service area. The work
to re-organise budgets to reflect updated service groupings is ongoing and will be
completed prior to presentation at Policy and Strategy Committee on 16 March 2023:

Page 4

Phasing By Service Area 2021/22 2022/23 2023/24 2024/25 2025/26 Total  
£000 £000 £000 £000 £000 £000
Place 24,126 46,507 55,390 32,791 67,682 226,496
Asset and Procurement  15,728 24,108 25,737 16,416 11,271 93,260
Asset and Procurement – Town
and Community Hubs 16,953 47,574 83,344 88,495 8,389 244,755
Community Operations 17,688 21,434 26,224 13,787 8,510 87,643
Housing Property Services (non-
HRA) 697 562 100 100 100 1,559
Adult Social Care 2,116 2,254 2,200 2,220 2,200 10,990
Business and Digital 5,741 10,264 10,589 3,227 1,988 31,809
Strategic Communications and
Engagement 957 1,197 3,757 2,960 3,577 12,448
Total 84,006 153,900 207,341 159,996 103,717 708,960 
2.8 This level of investment in North Lanarkshire’s communities supports the local
economy through the creation and maintenance of jobs and continues to demonstrate
to communities that the place making visions for towns remains a priority for the
Council. 
2.9 In line with the SCDG Terms of Reference, the programme outlined above and in
Appendix 1 will remain under continual review as the programme evolves and will
continue to be subject to an annual report to Policy and Strategy Committee outlining
amendments to the programme to reflect changes in priorities and / or changes in the
resources available. 
Housing Revenue Account Capital Programme
2.10 While this report focuses on the Council’s General Fund capital programme, Committee
should be aware of the record levels of investment in the Council’s current and future
housing stock. The updated planning assumptions linked to the approval of the
Council’s Housing Revenue Account budget for 2023/24 reflect investment of
£333.815m in the Council’s existing housing stock and a further £288.943m in new
supply over the current five-year planning period.   
Community Investment
2.11 Combining the updated General Fund Strategic Capital Investment Programme with
approved investment in the Housing Revenue Account Capital Programmes means
that the Council is planning for total Community Investment of £1.332 billion over the
current five-year planning period. 
Capital Strategy and Future Programme Development
2.12 In accordance with Prudential Code requirements, the Council carries out ongoing
reviews of the Capital Strategy. The current Strategy was due for review in 2022/23

Page 5

with a revised Strategy intended to be in place for 1 April 2023. However, given the
intention to commence work on the development of a new five-year programme to
commence from 1 April 2024, the wider review of the Capital Strategy has been delayed
to ensure appropriate alignment with the Council’s updated Programme of Work and
driven by the updated Corporate Asset Management Plan. The main principles outlined
and adopted within the current Strategy remain unchanged. 
Updated SCDG Terms of Reference and Governance Framework
2.13 The current SCDG Terms of Reference and Governance Framework was approved at
Policy and Strategy Committee in September 2021. With the revised management
team and organisational structure approved at Policy and Strategy Committee in
December 2022, SCDG has reviewed its Terms of Reference to ensure it properly
reflects the Council’s current organisational structure. The proposed revision to the
Terms of Reference and Governance Framework is presented in Appendix 2. 
3. Measures of success 
3.1  The SCDG will continue to monitor the performance of the capital programme and liaise
with officers, Corporate Management team and Elected Members to ensure completion
of the programme in line with available resources.   
4. Supporting documentation 
Appendix 1 – Strategic Capital Investment Programme – Updated 2021/22 to 2025/26
Programme Profile 
Appendix 2 – Strategic Capital Delivery Group – Updated Terms of Reference and
Governance Framework 
Derek Brown
Depute Chief Executive

Page 6

5. Impacts 
5.1 Public Sector Equality Duty and Fairer Scotland Duty 
Does the report contain information that has an impact as a result of the Public
Sector Equality Duty and/or Fairer Scotland Duty? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact?   
If Yes, has an assessment been carried out and published on the council’s
website? https://www.northlanarkshire.gov.uk/your-community/equalities/equality-
and-fairer-scotland-duty-impact-assessments 
Yes ☐ No ☐
5.2 Financial impact 
Does the report contain any financial impacts? 
Yes ☒ No ☐ 
If Yes, have all relevant financial impacts have been discussed and agreed with
Finance? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the impact? 
The financial impacts are outlined throughout the report. The Council’s SCDG has
responsibility for ongoing management of the strategic capital investment
programme and the monitoring of the overall programme will continue to be
presented to Finance and Resources Committee at each committee cycle.
5.3 HR policy impact 
Does the report contain any HR policy or procedure impacts? 
Yes ☐ No ☒ 
If Yes, have all relevant HR impacts have been discussed and agreed with People
Resources? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.4 Legal impact 
Does the report contain any legal impacts (such as general legal matters, statutory
considerations (including employment law considerations), or new legislation)? 
Yes ☐ No ☒ 
If Yes, have all relevant legal impacts have been discussed and agreed with Legal
and Democratic? 
Yes ☐ No ☐ 
If Yes, please provide a brief summary of the impact? 
5.5 Data protection impact 
Does the report / project / practice contain or involve the processing of personal
data?   
Yes ☐ No ☒ 
If Yes, is the processing of this personal data likely to result in a high risk to the
data subject? 
Yes ☐ No ☐ 
If Yes, has a Data Protection Impact Assessment (DPIA) been carried out and e-
mailed to dataprotection@northlan.gov.uk 
Yes ☐ No ☐

Page 7

5.6 Technology / Digital impact 
Does the report contain information that has an impact on either technology, digital
transformation, service redesign / business change processes, data management,
or connectivity / broadband / Wi-Fi? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
Where the impact identifies a requirement for significant technology change, has
an assessment been carried out (or is scheduled to be carried out) by the
Enterprise Architecture Governance Group (EAGG)? 
Yes ☐ No ☐
5.7 Environmental / Carbon impact 
Does the report / project / practice contain information that has an impact on any
environmental or carbon matters? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.8 Communications impact 
Does the report contain any information that has an impact on the council’s
communications activities? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the impact? 
5.9 Risk impact 
Is there a risk impact? 
Yes ☒ No ☐ 
If Yes, please provide a brief summary of the key risks and potential impacts,
highlighting where the risk(s) are assessed and recorded (e.g. Corporate or
Service or Project Risk Registers), and how they are managed? 
Through SCDG the Council will be managing ongoing risk associated with the
strategic capital investment programme, including but not limited to: 
• Failure to spend in-year capital grant which may result in any unspent portion
being returned to the Scottish Government. However, given the significant
level of Community Investment Fund investment this risk is deemed to be low
at this stage. 
• Project delays and programme issues that impact on the delivery of the
programme and result in increases costs or reduced outcomes.
5.10 Armed Forces Covenant Duty 
Does the report require to take due regard of the Armed Forces Covenant Duty (i.e.
does it relate to healthcare, housing, or education services for in-Service or ex-
Service personnel, or their families, or widow(er)s)? 
Yes ☐ No ☒ 
If Yes, please provide a brief summary of the provision which has been made to
ensure there has been appropriate consideration of the particular needs of the
Armed Forces community to make sure that they do not face disadvantage
compared to other citizens in the provision of public services.

Page 8

Appendix 1
Strategic Capital Investment Programme 2021/22 to 2025/26 – Updated 
Project / Theme 2021/22 2022/23 2023/24 2024/25 2025/26 Total
£000 £000 £000 £000 £000 £000  
Asset and Procurement 
Maintaining Existing Assets - windows, re-roofing, re-wiring and
condition survey works for the Council's building assets
4,887 9,025 8,201 7,103 5,917 35,133
Carbon Management 387 517 2,110 2,686 2,686 8,386
Office Rationalisation 151 438 3,303 2,000 0 5,892
Shared Campus 0 0 0 0 0 0
Leisure Development 377 1,411 668 500 84 3,039
Health & wellbeing and digital classrooms 318 412 351 0 0 1,081
Rationalisation including ASN & Social Work 1,136 1,590 4,942 0 0 7,669
Curriculum Development -342 864 400 296 0 1,219
Sustainable Estate 939 1,199 1,786 1,205 600 5,728
Outdoor Education and Outdoor Spaces 509 3,928 1,390 135 0 5,962
Future Capital Receipts Investment 216 774 581 320 220 2,112
Design Fees  1,501 1,469 1,563 1,594 1,625 7,753
1140 Early Learning and Childcare Expansion 5,525 1,971 260 39 39 7,834
Demolitions 125 510 180 538 100 1,454
Sub-Total Asset and Procurement 15,728 24,108 25,737 16,416 11,271 93,260  
Town and Community Hubs
Town and Community Hubs - development of campus sites across
North Lanarkshire in consultation with local communities
16,953 47,574 83,344 88,495 8,389 244,754
Sub-Total Town and Community Hubs 16,953 47,574 83,344 88,495 8,389 244,754

Page 9

Project / Theme 2021/22 2022/23 2023/24 2024/25 2025/26 Total
£000 £000 £000 £000 £000 £000  
Community Operations
Contaminated land and pollution control 312 368 360 372 384 1,797
Vehicle replacement programme 1,909 49 3,804 5,861 1,774 13,397
Depot rationalisation and investment 612 1,691 6,655 0 0 8,958
HWRC equipment 498 465 25 25 25 1,038
Landfill Provision 0 0 0 0 0 0
Cemeteries Infrastructure 314 1,608 3,711 955 205 6,793
Road Asset Management including street lighting, road improvements
and gateway signage
9,145 11,941 9,124 4,059 4,059 38,328
Drumbreak Marsh River Restoration Project (SEPA Funding) 3,195 1,276 48 0 0 4,519
Play area equipment and surface renewal 87 213 150 150 150 750
Bin rationalisation project and replacement 815 138 25 25 25 1,028
Environmental Assets replacement of plant and machinery 619 773 659 467 442 2,960
Parks Masterplan 182 2,912 1,663 1,873 1,445 8,075
Sub-Total Community Operations 17,688 21,434 26,224 13,787 8,510 87,643  
Place
Economic Regeneration 5,833 17,625 25,018 3,966 1,000 53,441
City Deal Programme  10,984 19,507 21,248 26,399 47,591 125,728
City Deal - East Airdrie Link Road (NLC-funded increase) 0 412 0 0 0 412
City Deal - Ravenscraig Infrastructure Access (NLC-funded increase) 0 0 1,000 0 16,600 17,600
Infrastructure and Transportation improvements, major maintenance
and development including traffic signals, pedestrian crossings, active
travel, bridge, drainage and flood risk management
7,309 8,748 8,125 2,427 2,491 29,101
Antonine Wall Project 0 215 0 0 0 215
Sub-Total Place 24,126 46,507 55,390 32,791 67,682 226,497  
Housing Property Services (Non-HRA)
Water Quality Management 697 562 100 100 100 1,559
Sub-Total Housing Property Services 697 562 100 100 100 1,559  
Total Enterprise and Communities 75,192 140,185 190,795 151,590 95,952 653,713

Page 10

Project / Theme 2021/22 2022/23 2023/24 2024/25 2025/26 Total
£000 £000 £000 £000 £000 £000  
Adult Social Care
Equipment and Adaptations 2,116 2,254 2,200 2,220 2,200 10,990
Total Adult Social Care 2,116 2,254 2,200 2,220 2,200 10,990  
Business and Digital
Line of Business (LOB) System Portfolio 294 1,504 1,678 808 610 4,893
End User Device (EUD) Refresh 198 1,498 1,760 1,180 600 5,237
Digitisation & Innovation 5,250 7,262 7,151 1,239 778 21,679
Sub-Total Business and Digital 5,741 10,264 10,589 3,227 1,988 31,809  
Strategic Communications and Engagement
Community Board Project Investment Fund 957 1,198 3,756 2,960 3,577 12,448
Sub-Total Strategic Communications and Engagement 957 1,198 3,756 2,960 3,577 12,448              
Total Chief Executives 6,698 11,462 14,346 6,187 5,565 44,257              
TOTAL GENERAL SERVICES CAPITAL PROGRAMME 84,006 153,900 207,341 159,996 103,716 708,960              
HRA Mainstream Investment Programme  53,285 57,950 54,682 76,821 91,077 333,815
HRA New Supply  35,205 44,721 76,308 70,027 62,682 288,943
TOTAL COMMUNITY INVESTMENT 172,496 256,571 338,331 306,844 257,475 1,331,718

Page 11

Appendix 2
STRATEGIC CAPITAL DELIVERY GROUP                    
TERMS OF REFERENCE & GOVERNANCE FRAMEWORK 
1. ROLE
The Strategic Capital Delivery Group (the Group) is a working group convened of senior
officers.  The Group advises elected members in terms of capital allocation and project
approval and has responsibility for the day to day management of the capital
programmes, including the realignment of resources to facilitate the effective delivery
of the Council’s Strategic Capital Investment Programme, including: 
• General Services Core Investment Programme (including Town and
Community Hubs and Enterprise Projects)
• HRA Mainstream Investment Programme
• HRA New Supply Programme
The Group makes recommendations on and amendments to the approved capital
programmes, as required, with any amendments reported to Committees in line with
the financial regulations and the agreed limits, as outlined in the Terms of Reference &
Strategic Framework Section 4 – Authority. 
1.1  Chair
The Depute Chief Executive will act as Chair of the Group, with the Chief Officer of
Finance as Depute. 
1.2 Group objectives
• Monitor the Council’s Strategic Capital Investment Programme, including
performance against delivery aims and objectives; 
• Advise Elected Members on capital allocations and project approval,
making recommendations on and amendments to the approved capital
programme;
• Ensure the proper alignment of capital resources to allow for effective
delivery of the programmes;
• Monitor expenditure projections against budgets and available resources,
revising these where necessary, subject to the limits set out in Section 4
– Authority;
• Ensure robust governance arrangements around the delivery, monitoring
and reporting of capital programmes;
• Consider the quarterly capital monitoring report to Finance and Resources
Committee to ensure appropriate actions are agreed for review by Elected
Members;
• Ensure Participatory Budgeting principles are embedded in key capital
investment decisions of the Council;
• Arrange and undertake training/awareness sessions as required to
reinforce skills/knowledge across the Council in respect of capital
monitoring and capital financing;
• Ensure all decisions made by the Group are Intra Vires and in line with
The Plan for North Lanarkshire.

Page 12

2. MEMBERSHIP 
2.1  Membership
Membership to include:
Depute Chief Executive (Chair)
Chief Officer (Finance) 
Chief Officer (Assets and Procurement)
Chief Officer (Place)
Chief Officer (Housing Property Services) 
Chief Officer (Education – North)
Chief Officer (Legal and Democratic)
Chief Officer (Business and Digital)
Chief Officer (Community Operations)
Chief Office (Strategic Communication and Engagement) 
Head of Planning, Performance and Quality Assurance
Business Finance Manager (Resources Solutions)
Membership of the Group reflects the composition of the capital programmes and
ensures the fair representation of Council services responsible for investment in all
Council assets.
The Group must make decisions on a corporate basis, in line with The Plan for North
Lanarkshire, Financial Strategy, Financial Regulations and other relevant plans and
policies. 
In the event that the Council structure changes the membership will be aligned to the
new structure, unless membership is formally changed by the Policy and Strategy
Committee.   
2.2  Attendance
Where group members are unable to attend meetings, nominated deputies should
attend. Group membership should be representative of the Council services, with
members acting in an independent manner.
Quorum is achieved with 70% attendance (including substitutes). In the event that a
meeting is not quorate, the Group is required to reconvene.
Officers and external parties may be invited to attend meetings of the Group to provide
information/ support and to answer questions in respect of the Council’s capital
programmes. 
3. PROCEDURES
3.1  Meeting Frequency
The Group will meet, as a minimum, quarterly, prior to each cycle of Policy and Strategy
Committee.  
3.2  Administration
Administrative support will be arranged by the Chair to coordinate and distribute
agendas, minutes and meeting papers.  Records of all minutes, decisions and actions
will be maintained.

Page 13

3.3  Submissions and Reports
Group members may make submissions to the Group. Submissions and progress
reports should reach the nominated administrative support no later than five working
days before each meeting.
Urgent matters may be submitted later than this deadline, but only with the approval of
the Chair.
3.4  Agendas and Papers
Agendas will be prepared and distributed to Group members with supporting papers at
least three working days before each meeting. 
3.5  Minutes
Minutes will be taken of meetings and will be distributed in draft via email within five
working days of the Group meeting. Minutes will be approved by the Group at the
following meeting.
3.6  Responsibility for Actions and Communication
Group members shall ensure that any decisions relevant to their Service are actioned
by relevant officers. Responsibility for actions within minutes will be recorded in an
updated work plan as per the outcome of the meeting.
The Depute Chief Executive and Chief Officers shall refer Group decisions to individual
Service Committees for approval or noting, in accordance with agreed limits outlined in
Section 4 – Approvals below, and will advise the Group of outcomes and decisions
made by Committee.
The Chair will refer Group minutes to Corporate Management Team.
3.7  Special Meetings
Special meetings of the Group may be called at the discretion of the Chair.  As far as
possible, normal procedures will be followed. 
4. AUTHORITY
4.1 Resources
The Capital Programmes are based on estimates of future investment targets funded
by a combination of Scottish Government Grants, capital receipts, CFCR and
prudential borrowing. When confirmation of investment targets are reviewed or
amendments to resources are known, the Group will give consideration to adjusting the
Programme accordingly. Recommendations for a revised programme, based on the
actual level of resources will subsequently be referred to Policy and Strategy
Committee for approval annually.
4.2 Virement & Re-profiling
4.2.1 General Fund Capital Programme
In the event the Group agrees a virement between approved Project / Thematic
Categories, this will be up to a maximum of £500,000.  Virements above this value
require the approval of the Individual Service Committee (if they remain within Service-
headings), or the Finance and Resources Committee if the virement is across Services.  
4.2.2 Housing Capital Programmes 
The Group has the authority to redirect resources across the following Thematic
Categories. These virements should be reported to the Housing Committee:

Page 14

• Estate Regeneration
• Energy Efficiency
• Major Repairs
• Internal Upgrading
• Tower Strategy
• Community Care
• Fees/Miscellaneous
• New Build
• Council Buy Back Schemes 
The Group has the authority to agree virements up to £1,000,000, virements in excess
of this amount will be reported to the Finance and Resources Committee for noting. 
Virements above this value require the approval of the Housing Committee.
4.3  Re-profiling of Capital Allocations
The Group has authority to re-profile capital allocations within Project / Thematic
Categories up to a maximum of £10,000,000 to and from future years of the Programme
to ensure effective delivery over the 5 year timeframe, provided this can be managed
within the overall annual budgeted resources (i.e. does not create additional
unbudgeted borrowing costs). This will be reported to appropriate Service Committees,
and Finance and Resources Committee for noting.
4.4 Over - programming Allowance
The Group is required to review and monitor the over-programming allowance within
programmes to ensure levels of funding remain sufficient to meet programme
commitments. 
4.5 Additional Project Approval
Approval must be sought from the Chief Officer of Finance and Policy and Strategy
Committee for new projects/ additional investment which cannot be contained within
the currently approved Council Programmes.
Emergency works outwith the approved Programme should be referred to the Chair
who will consult with the Chief Officer of Finance in seeking approval to proceed from
the Council Leader. 
4.6 Monitoring
4.6.1 All Capital Programmes
Individual Service Committee reports will provide monitoring information showing the
appropriate level of detail, predominately in line with the project / theme groupings as
laid out within the Strategic Capital Investment Programme 2021/22 to 2025/26 or
alternatively in accordance with the appropriate project groupings within the Housing
Capital Programme.
Whilst individual budget holders have responsibility for reporting variances and
ensuring compliance with Financial Regulations and General Contract Standing
Orders, overall responsibility for financial management lies with the Chief Officer of
Finance. Therefore, Financial Solutions staff must be provided with information for
individual projects to allow for effective financial monitoring.
4.7 Sub Groups
To ensure specific management of resources to advance the Plan for North
Lanarkshire and Programme of Work objectives, the Group will establish and delegate
authority to either sub-groups or other governance groups (i.e. Projects Boards), as
considered necessary.  The sub-groups will have Terms of Reference and Governance

Page 15

Framework established which shall include the requirement to report back to the
SCDG. 
The following is an example of the governance groups created with delegated authority
from the Group to manage project delivery, including allocating resources:
• Economic Regeneration Delivery Programme (ERDP) Project Board
Delegated responsibility for managing the ERDP capital programme including
town centre regeneration and external funding streams such as Vacant and
Derelict Land Fund, Town Centre Fund, Place Based Investment Programme
and other capital funds supporting economic regeneration. 
• Town and Community Hub Board
Delegated responsibility for managing Town and Community Hub programme
delivery including assessment of external funding opportunities from the
Scottish Government’s Learning Estate Investment Programme. 
• City Deal Board
Delegated responsibility for managing the Council’s City Deal programme
including supporting wider City Region objectives. 
• DigitalNL Board
Delegated responsibility for managing the Council’s digital transformation
programme. 
5. POST PROJECT REVIEWS
The Group has oversight of the performance of the Council’s Capital Programmes and
may carry out post implementation reviews, in line with the Council’s Project
Management guidelines.
6. RISK MANAGEMENT
All risks relating to the Programme and to individual projects will be managed in line
with the Council’s Risk Management Strategy and in accordance with Project
Management guidelines.